TRANSITION OF V4 PASOLINK TO i PASOLINK

V4 PASOLINK ODU iPASOLINK ODU IF CABLE i PASOLINK IDU

IF CABLE V4 PASOLINK IDU

N CONNECTOR POWER CONNECTOR

TNC CONNECTOR

MDR D SUB CONVERSION CABLE D SUB CONNECTOR POWER CONNECTOR

De-installation of V4 Pasolink: 1. Identification of V4 IDU & V4 ODU to be replaced 2. Give a CALL from V4 IDU NEAR End & confirm Beep sound at FAR End 3. Switch OFF IDU at NEAR End & confirm traffick is down/ NO RSL at FAR End 4. Identify DCDB & switch off Power to IDU from DCDB 5. After confirmation of traffic down remove V4 IDU by removing Ground Cable & Power Cable/Molex Connector 6. Cut Molex Connector check Voltage & identify -48V & 0 7. Remove N - type IF Connector at IDU end. 8. Remove Grounding cable & IF Cable at V4 ODU 9. Remove V4 ODU

Reinstallation of iPasolink: 1. iPASO Power Connector is available in IDU Box in plastic pack & same is to be used for iPASO Power after connctorisation V cables label same 2. Recheck Voltage at iPASO Power Connector & confirm -48V & 0 V. Insert Power Connector in iPASO IDU as per Voltage Marking 3. Replace IF Connector at IDU end from N-type to TNC Connector 4. Replace V4 ODU to I-Paso IHG ODU 5. Connect Grounding cable & IF Cable for iPASO ODU 6. Install MDR ( Y Cable) to iPASO IDU & connect D-Sub end to D-Sub 37 PIN Connector of PCM E1 cable 7. Interconnect E1 Cable from I-Paso IDU & from Existing DDF Port 8. Any blank MDR Cable end / D-Sub Cable end to be tied to Rack after wrapping with (Bubble) Plastic Sheet 9. Installation & Termination of Grounding cable for IDU. Confirm the Installation Done & "Switch ON" the IDU

Das könnte Ihnen auch gefallen