Material Cost
Labour Cost
Base screed 3.23 per m2 ( 0.30 per ft2 )
Labour Cost 2.20 per m2 ( 0.20 per ft2 )
Screeding Cost / m2
20mm thk 25mm thk
Material cost 2.84 3.55
Wastage @ 5% 0.14 0.18
Total material cost / m2 2.98 3.72
Labour Cost 2.20 2.20
Plant Cost ( Inclusived ) - -
Tender Cost / m2 5.18 5.92