Ref Avg/Bwk Length Inner Outer Fwk to side 300mm 230mm thk 345mm thk Strut Weephole Plastering
No Depth Width Width of drain base H/R brickwall brickwall at 3m c/c
(m) (m) (m) (m) (m2) (m) (m2) (m2) (nr) (nr) (m2)
b x 0.318 x 2 b 2xbxa b/3 x 2 b(a+0.23)2
2 1.39 178.058 0.60 1.06 113.24 178.06 * 320.50 * 172.72 * 60 118.71 576.91
14 1.14 112.673 0.60 1.06 71.66 112.67 * 202.81 * 54.08 * 38 75.12 308.72
1.22 19.514 0.60 1.06 12.41 19.51 * 35.13 * 12.29 * 7 13.01 56.59
1.28 13.863 0.60 1.06 8.82 13.86 * 24.95 * 10.54 * 5 9.24 41.87
0.55 106.729 0.60 1.06 67.88 106.73 117.40 71.15 166.50
16 1.23 6.096 0.60 1.06 3.88 6.10 * 10.97 * 3.96 * 3 4.06 17.80
a b c
Length width Qty 125mm thk Steel bar 2 layer of Fwk to soffit Fwk to side
Concrete R12 BRC B6 of slab of cover slab
(m2) (kg) (m2) (m2) (m)
axbxc 8.88 x c axbxcx2 0.6 x a x c (2a + b)c
a b c
Length width Qty BRC B6 Fwk to side Extra fwk to side Lean conc.
slab base of slab base
(m2) (m) (m) (m2)
axbxc 2a x c 0.15 x 2 x c axbxc
(m)
3 34.75
4 60.04
5 96.01
7 59.3
9 31.71
11 64.01
13 65.53
14 106.73
15 96.01
614.09
a b
Length Qty Entrance slab Top plastering
cover length for entrance slab
(m) (nr) (m) (m2)
axb a x 0.23 x b x 2
Rebated Concrete Coping , Plastering, Side Formwork To Drain Base, Concrete To Drain Base & Concrete Benching - 2E1
∴ Rebated concrete coping = 2 (Total drain length - Backlane - Entrance slab ) + P.C.slab at backlane
= 2 (2359.22 - 614.09 - 707.19) + 123.30
= 2075.88 + 123.30
= 2199.18 m
∴ Formwork to side of drain base = Side formwork of total drain base - Side formwork of entrance slab base
= 1500.49 - (1106.14 x 0.15)
= 1500.49 - 165.92
= 1334.57 m2
∴ Concrete to drain base = Drain base concrete + Extra arising from entrance + Additional concrete from 345mm thk bwk
= 375.13 + 137(2 x 0.15 x 0.15 x 4.037) + 19.84
= 375.13 + 24.89 + 19.84
= 419.86 m3
∴ Concrete to benching = Concrete benching -Volume affected by entrance base detail +Additional conc.from 345mm thk bwk
= 315.49 - 137 x 2 ( 0.23 x 0.168 x 4.037) + 22.22
= 315.49 - 42.74 + 22.22
= 294.97 m3
∴ 230mm brickwork = 230mm thk bwk + Additional bwk affected by entrance base detail
= 3281.58 + 137 ( 2 x 0.168 x 4.037)
= 3281.58 + 185.83
= 3467.41 m2
∴ 450 x 600mm p.c slab = Qty for rebated concrete coping ÷2 ÷ 0.45
= 2199.18
2 x 0.45
= 2444 pcs
∴ Excavation n.e 1.5m deep = Excavation n.e 1.5 m + Additional excavation from 345mm thk bwk
= 2705.13 + 201.15
= 2906.28 m3