Project : 2E1 & 2E2, Bkt Rimau

Subject : Summary Of Surface Drain - 2E1 Date prepared : 29/8/01

a b c d
Ref Avg/Bwk Length Inner Outer Fwk to side 300mm 230mm thk 345mm thk Strut Weephole Plastering
No Depth Width Width of drain base H/R brickwall brickwall at 3m c/c
(m) (m) (m) (m) (m2) (m) (m2) (m2) (nr) (nr) (m2)
b x 0.318 x 2 b 2xbxa b/3 x 2 b(a+0.23)2

1 0.59 109.783 0.60 1.06 69.82 109.78 129.54 - - 73.19 180.04

2 1.39 178.058 0.60 1.06 113.24 178.06 * 320.50 * 172.72 * 60 118.71 576.91

3 0.45 59.133 0.60 1.06 37.61 59.13 53.22 - - 39.42 80.42

4 0.56 60.040 0.60 1.06 38.19 60.04 67.24 - - 40.03 94.86


1.08 60.040 0.60 1.06 38.19 60.04 * 109.67 * 15.01 * 17 40.03 157.30

5 0.69 96.012 0.60 1.06 61.06 96.01 132.50 - - 64.01 176.66


0.83 24.384 0.60 1.06 15.51 24.38 40.48 - - 16.26 51.69
0.57 96.012 0.60 1.06 61.06 96.01 109.45 - - 64.01 153.62

6 0.63 54.196 0.60 1.06 34.47 54.20 68.29 - - 36.13 93.22


0.65 25.230 0.60 1.06 16.05 25.23 32.80 - - 16.82 44.40

7 0.55 59.301 0.60 1.06 37.72 59.30 65.23 - - 39.53 92.51


0.78 23.230 0.60 1.06 14.77 23.23 36.24 - - 15.49 46.92
0.83 38.100 0.60 1.06 24.23 38.10 * 60.78 * 1.39 * 3 25.40 80.77
0.95 55.604 0.60 1.06 35.36 55.60 * 92.26 * 10.95 * 9 37.07 131.23
0.93 25.584 0.60 1.06 16.27 25.58 * 41.53 * 4.74 * 4 17.06 59.35

8 0.65 48.758 0.60 1.06 31.01 48.76 63.39 - - 32.51 85.81


0.98 85.111 0.60 1.06 54.13 85.11 * 153.20 * 9.12 * 13 56.74 205.97
1.16 52.528 0.60 1.06 33.41 52.53 * 94.55 * 27.31 * 18 35.02 146.03

9 0.40 71.968 0.60 1.06 45.77 71.97 57.57 - - 47.98 90.68

10 0.60 64.008 0.60 1.06 40.71 64.01 76.81 - - 42.67 106.25


0.60 45.672 0.60 1.06 29.05 45.67 54.81 - - 30.45 75.82
1.11 64.008 0.60 1.06 40.71 64.01 * 115.21 * 26.24 * 22 42.67 171.54

11 0.50 64.008 0.60 1.06 40.71 64.01 64.01 - - 42.67 93.45

12 0.71 97.906 0.60 1.06 62.27 97.91 139.03 - - 65.27 184.06


0.87 45.672 0.60 1.06 29.05 45.67 79.47 - - 30.45 100.48
0.61 43.042 0.60 1.06 27.37 43.04 52.51 - - 28.69 72.31
0.74 25.906 0.60 1.06 16.48 25.91 38.34 - - 17.27 50.26
0.78 65.534 0.60 1.06 41.68 65.53 102.23 - - 43.69 132.38

13 0.57 45.672 0.60 1.06 29.05 45.67 52.07 - - 30.45 73.08


0.54 65.532 0.60 1.06 41.68 65.53 70.77 - - 43.69 100.92

14 1.14 112.673 0.60 1.06 71.66 112.67 * 202.81 * 54.08 * 38 75.12 308.72
1.22 19.514 0.60 1.06 12.41 19.51 * 35.13 * 12.29 * 7 13.01 56.59
1.28 13.863 0.60 1.06 8.82 13.86 * 24.95 * 10.54 * 5 9.24 41.87
0.55 106.729 0.60 1.06 67.88 106.73 117.40 71.15 166.50

15 0.60 29.334 0.60 1.06 18.66 29.33 35.20 - - 19.56 48.69


0.55 96.012 0.60 1.06 61.06 96.01 105.61 - - 64.01 149.78
0.68 27.432 0.60 1.06 17.45 27.43 37.31 - - 18.29 49.93
0.72 91.440 0.60 1.06 58.16 91.44 131.67 - - 60.96 173.74

16 1.23 6.096 0.60 1.06 3.88 6.10 * 10.97 * 3.96 * 3 4.06 17.80

17 0.56 6.096 0.60 1.06 3.88 6.10 6.83 - - 4.06 9.63

1,500.49 2,359.22 3,281.58 348.35 199 1,572.84 4,732.19

Note : * Refer attachment


Summary Of Entrance Slab - 2E1 Date prepared : 29/8/01

Entrance Slab Cover

a b c
Length width Qty 125mm thk Steel bar 2 layer of Fwk to soffit Fwk to side
Concrete R12 BRC B6 of slab of cover slab
(m2) (kg) (m2) (m2) (m)
axbxc 8.88 x c axbxcx2 0.6 x a x c (2a + b)c

5.162 1.06 137 749.63 1,216.56 1,499.25 424.32 1,559.61

Entrance Slab Base

a b c
Length width Qty BRC B6 Fwk to side Extra fwk to side Lean conc.
slab base of slab base
(m2) (m) (m) (m2)
axbxc 2a x c 0.15 x 2 x c axbxc

4.037 1.36 137 752.17 1,106.14 41.10 752.17

Steel bar - R12


L = 4 x 1.5 + 4(1.060 - 2(0.03))
=6+4
= 10 m

R12 = 10m x 0.888m/kg


= 8.88 kg per grating cover
Omission And Addition For Rebated Concrete Coping & Plastering - 2E1 Date prepared : 29/8/01

Deduction For Rebated Concrete Coping At Backlane


Ref No. Backlane

(m)
3 34.75
4 60.04
5 96.01
7 59.3
9 31.71
11 64.01
13 65.53
14 106.73
15 96.01
614.09

Deduction For Rebated Concrete Coping & Plastering At Entrance Slab

a b
Length Qty Entrance slab Top plastering
cover length for entrance slab
(m) (nr) (m) (m2)
axb a x 0.23 x b x 2

5.162 137 707.19 325.31

Addition For Rebated Concrete Coping At Backlane

Rebated concrete coping at backlane = 137 x 0.45 x 2


= 123.3 m
Date prepared : 19/7/01

Rebated Concrete Coping , Plastering, Side Formwork To Drain Base, Concrete To Drain Base & Concrete Benching - 2E1

∴ Rebated concrete coping = 2 (Total drain length - Backlane - Entrance slab ) + P.C.slab at backlane
= 2 (2359.22 - 614.09 - 707.19) + 123.30
= 2075.88 + 123.30
= 2199.18 m

∴ Plastering = Total plastering - Entrance slab area top plastering


= 4732.19 - 325.31
= 4406.88 m2

∴ Formwork to side of drain base = Side formwork of total drain base - Side formwork of entrance slab base
= 1500.49 - (1106.14 x 0.15)
= 1500.49 - 165.92
= 1334.57 m2

∴ Concrete to drain base = Drain base concrete + Extra arising from entrance + Additional concrete from 345mm thk bwk
= 375.13 + 137(2 x 0.15 x 0.15 x 4.037) + 19.84
= 375.13 + 24.89 + 19.84
= 419.86 m3

∴ Concrete to benching = Concrete benching -Volume affected by entrance base detail +Additional conc.from 345mm thk bwk
= 315.49 - 137 x 2 ( 0.23 x 0.168 x 4.037) + 22.22
= 315.49 - 42.74 + 22.22
= 294.97 m3

∴ 230mm brickwork = 230mm thk bwk + Additional bwk affected by entrance base detail
= 3281.58 + 137 ( 2 x 0.168 x 4.037)
= 3281.58 + 185.83
= 3467.41 m2

∴ 450 x 600mm p.c slab = Qty for rebated concrete coping ÷2 ÷ 0.45
= 2199.18
2 x 0.45
= 2444 pcs

∴ Excavation n.e 1.5m deep = Excavation n.e 1.5 m + Additional excavation from 345mm thk bwk
= 2705.13 + 201.15
= 2906.28 m3