Beruflich Dokumente
Kultur Dokumente
Table of Contents
Table of Contents...........................................................................1 List of Figures ................................................................................5 List of Tables..................................................................................9 Chapter 1: Installation ................................................................. 11
1.1 OMS1664 Installation Sequence .............................................. 11
1.1.1 1.1.2 1.1.3 1.1.4 1.1.5 1.1.6 1.1.7 1.1.8 1.1.9 1.1.10 1.1.11 1.1.12 Marconi
Copyright- Refer to title page
Install Rack - Raised Modular Floor ................................................... 11 Fitting Double Channel, Drop Rods and U Brackets ........................ 15 Installation Under Overhead Ironwork ................................................ 18 Fit EF80 .............................................................................................. 20 Cable and Fibre Management Devices .............................................. 21 Cable Bracket ..................................................................................... 21 Fibre Spools ....................................................................................... 23 Cable Brake-out Bracket .................................................................... 24 Cable Management Bars.................................................................... 24 Installing OMS 1664 Subrack............................................................. 26 Installing OMS 1654 Subrack............................................................. 28 Fan Tray Installation ........................................................................... 30 Topic 4 Page 1 1PHA60131AAV Issue 04
Slide in Unit Insertion/Removal .......................................................... 31 Slide in Unit Handling ......................................................................... 31 Installation Procedure......................................................................... 32 SIU Extraction/Insertion...................................................................... 33
1.2
1.3
General Cabling Rules Fibre Optic Cables ..................................... 70 Inspection And Cleaning Of Optical Fibres ........................................ 70 Managing Fibres Within The Rack ..................................................... 71 Managing Optical Fibres OMS 1664 Subrack................................. 73 Managing Optical Fibres OMS 1654 Subrack................................. 75 Topic 4 Page 2 1PHA60131AAV Issue 04
1.5
Chapter 2: Commissioning.......................................................... 81
2.1 Introduction ............................................................................... 81
2.1.1 2.1.2 2.1.3 2.1.4 2.1.5 2.1.6 Introduction and Scope....................................................................... 81 EMC Protection .................................................................................. 81 Static Sensitive Warning..................................................................... 81 Cleaning Procedures for Optical Connectors ..................................... 81 Test Equipment .................................................................................. 82 Information Required For Commissioning.......................................... 84
2.2
1:1 MSP STM-1 Trib Protection......................................................................... 95 2.2.2 OMS1634 Shelf Configuration.......................................................... 100
2.3 2.4
OMS1654 (Compact) Typical Shelf Configurations .............. 106 OMS1644 Typical Shelf Configuration................................... 110
2.4.1 OMS1644 STM-16 ADMUX: Up to 126 x 2Mbit/s Ports................... 110
2.5
Marconi
Copyright- Refer to title page
STM-4 Traffic Card Link Settings ..................................................... 124 STM-16 Traffic Card Link Settings ................................................... 127 STM-16 Core Card Link Settings .................................................... 127 Flexible STM-1/4 Traffic Card (SFP Based) 8 Port and 16 Port Version .......................................................................................................... 128 Flexible STM-1/4 Traffic LTU ........................................................... 129 Management and Sync LTU Link Settings ....................................... 131 Power LTU Link Settings .................................................................. 132 Alarms and Aux LTU ........................................................................ 132 Ethernet 100M LTU SFP Link Settings ............................................ 134 Card Installation................................................................................ 135 Power Supply & Rack Alarm Checks ............................................... 135
2.6
Marconi
Copyright- Refer to title page
Topic 4 Page 4
1PHA60131AAV Issue 04
List of Figures
Figure 1-1: End View Of Suite ..................................................................................................... 12 Figure 1-2: ETSI Rack with Cable Duct Cut Out Template (900x300)........................................ 13 Figure 1-3: Fitting Trim (Typical Only) ......................................................................................... 13 Figure 1-4: RMF Support Where Floor Void Is Less Than 350mm............................................. 15 Figure 1-5: RMF Support Where Floor Void Is Greater Than 350mm ........................................ 18 Figure 1-6: Additional and Modified Brackets (2.6m Ironwork). .................................................. 20 Figure 1-7: Aligning EF80............................................................................................................ 21 Figure 1-8: Mounting Plate .......................................................................................................... 22 Figure 1-9: Cable Bracket............................................................................................................ 22 Figure 1-10: Bracket Finger Orientation ...................................................................................... 22 Figure 1-11: Side Mounting Plate................................................................................................ 23 Figure 1-12: Fibre Management Spool and Bracket ................................................................... 24 Figure 1-13: Cable Brake-out Bracket......................................................................................... 24 Figure 1-14: Cable Management Bar (Standard Subrack).......................................................... 25 Figure 1-15: Cable Management Bar (Compact subrack) .......................................................... 25 Figure 1-16: Shelf Mounting Bracket........................................................................................... 27 Figure 1-17: Mounting Bracketsa ................................................................................................ 27 Figure 1-18: OMS1654 Subrack.................................................................................................. 28 Figure 1-19: Fan Tray Installation ............................................................................................... 30 Figure 1-20: SIU .......................................................................................................................... 32 Figure 1-21: Sketch of the OMS1664 Infrastructure ................................................................... 36 Figure 1-22: Typical termination of the Rack Top Fuse Rail ....................................................... 40 Figure 1-23: ETSI DC Power Rail (Typical Only) ........................................................................ 41 Figure 1-24: 0 Volt Earth Rail ...................................................................................................... 41 Figure 1-25: Factory Assembled Power Looms .......................................................................... 43 Figure 1-26: Factory Assembled Power Looms .......................................................................... 43 Figure 1-27: Power LTUs DC cables........................................................................................... 44 Figure 1-28: Rack Protective Earth Terminal .............................................................................. 44
Marconi
Copyright- Refer to title page
Topic 4 Page 5
1PHA60131AAV Issue 04
Figure 1-29: Subrack Safety Protective Earth Terminal.............................................................. 45 Figure 1-30: Fan Tray.................................................................................................................. 46 Figure 1-31: Fan Tray Earthing ................................................................................................... 46 Figure 1-32: Filter Cleaning ......................................................................................................... 47 Figure 1-33: Cable Routing ......................................................................................................... 48 Figure 1-34: LTU Area. 32 Ports Per Card.................................................................................. 51 Figure 1-35: Typical Cabling Layout in a 900 x 3000mm Rack .................................................. 52 Figure 1-36: Cables formed to front of LTU 1 to 6....................................................................... 53 Figure 1-37: Running Stitch......................................................................................................... 54 Figure 1-38: Cable Forming Diagrams ........................................................................................ 54 Figure 1-39: Securing Form to CMB with Cable Tie ................................................................... 56 Figure 1-40: Tribs 1-4 Cabled with ST 212 Coaxial Cable.......................................................... 56 Figure 1-41: Tribs 1-4 Cabled with ST 212 Coaxial Cable.......................................................... 57 Figure 1-42: Tribs 5-8 Cabled with ST 212 Coaxial Cable.......................................................... 57 Figure 1-43: Plugging and Dressing of Cables (1) ...................................................................... 59 Figure 1-44: Plugging and Dressing of Cables (2) ...................................................................... 59 Figure 1-45: Plugging and Dressing of Cables (3) ...................................................................... 60 Figure 1-46: STM 1E High Band Trib Cards ............................................................................... 61 Figure 1-47: STM-1 Electrical Lower Shelf Cable Management ................................................. 62 Figure 1-48: STM-1 Electrical Upper Shelf Cable Management ................................................. 62 Figure 1-49: Cabling of an STM-1 Electrical and Optical Mix ..................................................... 63 Figure 1-50: LTU Area Interface.................................................................................................. 64 Figure 1-51: 75 ohm interface/ 120 ohm interface ...................................................................... 65 Figure 1-52: Permitted Cable Forms ........................................................................................... 66 Figure 1-53: Cable Management Bar .......................................................................................... 67 Figure 1-54: Fan Tray Alarm Cabling .......................................................................................... 67 Figure 1-55: Alarm Cable Assembly............................................................................................ 68 Figure 1-56: Lower and Upper LTU Areas .................................................................................. 69 Figure 1-57: Kopex Flexible Conduit ........................................................................................... 71 Figure 1-58: Typical Installation................................................................................................... 71 Figure 1-59: Fibre Spool.............................................................................................................. 73 Marconi
Copyright- Refer to title page
Topic 4 Page 6
1PHA60131AAV Issue 04
Figure 1-60: Mid Shelf Fiber Guides ........................................................................................... 74 Figure 1-61: View Showing Card Cage with STM-1 Optical Tribs .............................................. 74 Figure 1-62: Wrist Strap Tester ................................................................................................... 78 Figure 2-1: EPL-100 Fast Ethernet LTU Interface:- .................................................................... 84 Figure 2-2: Two pair Cross-over UTP Fast Ethernet Test Cable ................................................ 84 Figure 2-3: OMS1664 Standard Shelf ......................................................................................... 86 Figure 2-4: STM-16 Cross Connect: Up to 8 x STM-16 Ports..................................................... 93 Figure 2-5: STM-16 Cross Connect: Up to 128 x STM-1 Ports................................................... 94 Figure 2-6: STM-16 Cross Connect: Up to 504 x 2Mbit/s Ports.................................................. 95 Figure 2-7: STM-16 Add-Drop Multiplexer: Up to 128 x STM-1 Ports......................................... 97 Figure 2-8: STM-16 Add-Drop Multiplexer: Up to 504 x 2Mbit/s Ports........................................ 98 Figure 2-9: OMS1634 (Compact) 2Mb/s Admux Shelf.............................................................. 106 Figure 2-10: OMS1654 (Compact) STM-1 Admux shelf ........................................................... 107 Figure 2-11: Subset of ALS Configurability Currently Supported By OMS1664 ....................... 118 Figure 2-12: ALS Shelf Commissioning Process Flowchart...................................................... 120 Figure 2-13: ALS Card Insertion Process Flowchart................................................................. 121 Figure 2-14: ALS link settings for an STM-1 Trib/Traffic card (Sketch) .................................... 122 Figure 2-15: ALS Link Settings for an STM-1 Trib/Traffic card (Photo) .................................... 123 Figure 2-16: Blow-up of Link Area for STM-1 Trib/Traffic Card................................................. 123 Figure 2-17: ALS link settings for an STM-4 Trib/Traffic card (Photograph)............................. 126 Figure 2-18: Blow-up of Link Area for STM-4 Trib/Traffic Card................................................. 126 Figure 2-19:STM-16 Core Card Link Settings ........................................................................... 127 Figure 2-20: Link Settings for Flexible STM-1/4 Traffic Card .................................................... 129 Figure 2-21: Link Settings for Flexible STM-1/4 LTU ................................................................ 130 Figure 2-22: Management and Sync LTU ................................................................................. 131 Figure 2-23: Link settings for the Alarms & Aux LTU ................................................................ 133 Figure 2-24:Schematic and Picture of Ethernet 100M LTU Link Settings................................. 134 Figure 2-25: Power Connectors ................................................................................................ 136
Marconi
Copyright- Refer to title page
Topic 4 Page 7
1PHA60131AAV Issue 04
Blank Page
Marconi
Copyright- Refer to title page
Topic 4 Page 8
1PHA60131AAV Issue 04
List of Tables
Table 1-1: Item Codes for figures Figure 1-4 and Figure 1-5...................................................... 15 Table 1-2: Marconi Part Numbers ............................................................................................... 36 Table 1-3: OMS1664 Full Shelf Typical Power Consumption ..................................................... 37 Table 1-4: DC Rail Part Codes .................................................................................................... 42 Table 2-1: LCT to OMS1664 Interface Cable.............................................................................. 83 Table 2-2: Standard Shelf Line/Trib Units Slot Allocation ........................................................... 87 Table 2-3: Standard Shelf LTU Units Slot Allocation .................................................................. 92 Table 2-4: LTU Port Numbers ..................................................................................................... 96 Table 2-5: STM-1 Ports with Different Line Functionality............................................................ 97 Table 2-6: LTU Port Numbers ..................................................................................................... 98 Table 2-7: OMS1654 Shelf Slot Allocation ................................................................................ 108 Table 2-8: ALS configurability per card ..................................................................................... 119 Table 2-9: Switch settings for Management & Sync LTU.......................................................... 132
Marconi
Copyright- Refer to title page
Topic 4 Page 9
1PHA60131AAV Issue 04
Blank Page
Marconi
Copyright- Refer to title page
Topic 4 Page 10
1PHA60131AAV Issue 04
Chapter 1: Installation
1.1 OMS1664 Installation Sequence
Note: Prior to the start of ANY activity (Installation or Commissioning) on an InService exchange, or on ANY equipment within a live/ in-service environment, the Engineer must contact the relevant overall installation authority. Note: It must be remembered that after installing and commissioning on an in service exchange all doors, end panels, ducting covers and screws should be refitted. This will ensure that the integrity of the faraday cage (EMC) is not compromised. The ETSI rack is a 900mm x 300mm rack and will accommodate a fully cabled subrack, Fibre splice shelf and a DC Distribution Panel.
1.1.1
Note: Front access ETSI racks positioned on a raised modular floor, require fixing through the tiles to the sub-floor. If a single 300mm deep rack is to be installed without an adjacent rack to the rear, both front & rear holes must be used with fixings to the sub-floor. Back to back racks require only the front holes of each rack to secure. Refer to Figure 1-1: End View Of Suite
Marconi
Copyright- Refer to title page
Topic 4 Page 11
1PHA60131AAV Issue 04
SINGLE ROW
F
BACK TO BACK
600x600 TILE
1.1.1.1
WARNING!
Ensure the area is cornered off prior to the removal of the floor tile. Note: Modification to floor tiles should only be undertaken by operators fully trained in woodworking techniques or under authorised supervision. Note: It is a mandatory requirement to wear ear defenders, eye shields and gloves during the drilling and cutting operations. Note: Any drilling operation on site should be carried out in such a manner as to keep dust and debris from contaminating adjacent equipment. Secure the tile to the workmate using G clamps protecting the vinyl / carpet surface from possible damage. Spot drill the four previously marked holes using a 6 mm bit drilling from the top surface of the tile only. Enlarge each hole to the required size using the appropriate drill bits. Spot drill each corner of the marked area for the cable access hole using a 6 mm bit. Enlarge the holes sufficiently to accept the jigsaw blade.
Marconi
Copyright- Refer to title page
Topic 4 Page 12
1PHA60131AAV Issue 04
Starting from the pilot holes, cut cable slot along marked lines, exercising care to keep the jigsaw blade perpendicular to the tile during the cutting operation. It may be advisable to do the top cut from the top surface and trim from the bottom surface of the tile later to obtain smooth and straight edges. Using a file, smooth all sharp edges from the drill holes and slots. Inspect the tiles to ensure they have straight and smooth edges.
Figure 1-2: ETSI Rack with Cable Duct Cut Out Template (900x300)
180mm
60mm 70mm
120mm
Note: Where racks are positioned back to back on a cut tile, the tile will require extra support. This is to be achieved with the use of additional pedestals positioned strategically along the tile centre line. Measure the circumference of the slot, and allowing for an overlap at the joint, cut PVC (1MAA 12174 AES) and trim to the required length. The trim is to be fitted from the underside of the slot. Fix PVC to the tile using 25mm wire nails. If necessary use hot airgun at the corners to obtain a good fit.
V in y l o r C a rp e t C o v e rin g
F lo o r T ile
H .D . C h ip b o a rd M e ta l C a b le A c c e s s
A p p ly H e a t
C u t to O b ta in a B u tt F it
Marconi
Copyright- Refer to title page
Topic 4 Page 13
1PHA60131AAV Issue 04
Take the floor tile to the equipment area and replace in position ensuring correct orientation. When drilling and cutting are completed the area should be swept clean of any accumulated dust or debris. Note: The installers should be supplied with a site installation folder from the appropriate overall installation authority giving information concerning earthing and cable size for an individual site.
1.1.1.2
WARNING!
Prior to lifting any floor tiles ensure the area to be worked in is cordoned off using cones and barrier tape. Warning signs must be placed at all entrance points to the room being worked in. Using a correctly orientated floor spotting aid, mark the sub floor for correct positioning of the brackets, under the 600 x 600 tile. Mark the positions of the holes to be drilled on the floor and drill out the two holes to a maximum depth of 32mm using an 8mm masonry bit for concrete floors. Insert rawlplugs 1MAB 00129 AAJ into each drilled hole. Note: Installer to use drill stops to ensure that the maximum depth of 32mm is not exceeded.
WARNING!
Before drilling into walls or floors, a check must be carried out using a cable/conduit detector to ensure that there are no buried services. Secure the four U Brackets to the floor using screws 1MAB 00132 ACT and associated fixings, refer to Figure 1-4. Clear away any dust and debris from the drilling area.
Marconi
Copyright- Refer to title page
Topic 4 Page 14
1PHA60131AAV Issue 04
1.1.2
18 1 13 11 14 15 4 5 7 16 17 8 9 10 2 3
19
Using a length of double channel (cut on site to suit), refer to Figure 1-4 for a typical under-floor support KOP.
Table 1-1: Item Codes for figures Figure 1-4 and Figure 1-5
ITEM NO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 1MAB00534AEJ 1MAB00047AAD 1MAB00277AAM 1MAB00010AAS 1MAB00273AAD 1MAB00279AAR 1MAB00274AAF 1MAB00132ACT 1MAB00268AAY 1MAA01896ABF 1MAA11841AAV 1MAB00006AAQ 1MAB00534ABG 1MAB00059AAX 1WAA10050ADL 1MAB00338AJY 1MAC10133AAS 1MAA00588ABE 1MAA00589AAP 1MAA00587AAK M6x50mm HEX. Screw M6 Washer M6 Special Nut M12 HEX.Nut S M12 Special Nut M12x22mm HEX. Screw SQ, Plate Washer M8 Coach Screw M8 Flat Washer Nylon Plug M6 x 6 Lug M6 Nut M6 x 20mm HEX. Screw M6 Shakeproof Washer 4mm G/Y Earth Cable M12 Threaded Rod 229mm 16 O/D Plastic Sleeving 41x 41 Channel 600Long Bracket U Bracket 90 CODE DESCRIPTION QTY Fig 4.4 2 2 2 6 2 2 4 4 4 1 1 4 1 1 2 1 1 2 QTY. Fig.4.5 2 2 2 6 6 2 2 2 1 1 1 1 1 1 4
Marconi
Copyright- Refer to title page
Topic 4 Page 15
1PHA60131AAV Issue 04
The length of double channel should be positioned directly below the rack fixing holes, previously drilled in the floor tiles. Do not fully tighten saddle brackets screws until the racks and drop rods are fitted. Repeat the above for each additional channel length identified on the site drawing. Fit end caps to all exposed ends of the channel. Replace the suite of tiles, ready prepared with cable and fixing holes. Ensure the correct orientation of the tiles. Locate the rear of the racks along the suite line
WARNING!
The stability of the rack must be maintained at all times. Once the racks are in position, remove the floor tile from the front of the rack to gain access for securing. Note: If two racks are to be fitted back to back, only two drop rods are required under each rack. If a single rack or suite of single racks is to be sited, the racks should be secured using the four rack fixing holes.
Cut the drop rods to suit and fit the nuts/washers as shown in Figure 1-4. Note: 16mm conduit must be fitted over the rods also cut to suit, to protect cables. Fit the nut near the top of the rod and feed up through the fixing holes in the base of the tile and rack, refer to. Figure 1-4. Fit a further nut below the conduit, these nuts and washers are for bracing between the underside of the tile and the channel. Site the bottom of the rod into the saddle bracket or straight onto the channel, see . Figure 1-4. Fit special nuts within the channel to capture top of drop rods. Check the drop rods are vertical before tightening any nuts. Fit a nut and washer at the top of rod within the base of the rack and tighten. Secure the nuts and washers between the tile and channel and ensure the screws are now fully tightened on the saddle bracket. Continue fitting drop rods until all the racks are secured.
1.1.2.1
1.1.2.2
Marconi
Copyright- Refer to title page
Topic 4 Page 16
1PHA60131AAV Issue 04
Insert rawlplugs 1MAB 00129 AAJ into each drilled hole. Note: Installer to use drill stops to ensure that the maximum depth of 32mm is not exceeded.
WARNING!
Before drilling into walls or floors, a check should be carried out using a cable/conduit detector to ensure that there are no buried services. Secure the four right-angled brackets to the floor using screws 1MAB 00132 ACT and associated fixings, refer to Figure 1-4. Clear away any dust and debris from the drilling area. Repeat the above for each additional channel length identified on the site drawing. Fit end caps to all exposed ends of the channel. Fit Horizontal and Vertical Double Channel and Right Angled Brackets Using length of double channel for the horizontal (cut on site to suit) this should be positioned directly below the rack fixing holes, previously drilled in the floor tiles. For the vertical double channel height measure the floor void and minus the depth of the horizontal double channel (cut to suit) x 2. Present the vertical channels to the right angled brackets previously secured to the sub floor, secure with M12 x 22 screw (1MAB 00279 AAR) and M12 nut special (1MAB 00273 AAD), repeat for remaining vertical channels, see. Figure 1-5. Fit a second right angled bracket to the top of the vertical, secure with fixings as above. Fit horizontal channel and secure with above fixings. Note: Ensure two M10 nut specials (1MAB 00273 AAD) are fitted to the upper of the horizontal channel and positioned to correspond with the rack fixing holes previously drilled in the floor tiles. Replace the suite of tiles, ready prepared with cable and fixing holes.Ensure the correct orientation of the tiles. Locate the rear of the racks along the suite line.
WARNING!
The stability of the rack must be maintained at all times.
Marconi
Copyright- Refer to title page
Topic 4 Page 17
1PHA60131AAV Issue 04
Figure 1-5: RMF Support Where Floor Void Is Greater Than 350mm
18 11 13 14 15 18 8 9 10 1 2 3
6 20
1.1.2.3
1.1.2.4
1.1.3
Marconi
Copyright- Refer to title page
Topic 4 Page 18
1PHA60131AAV Issue 04
1 2
The floor is clearly marked, if not remark as necessary. The location of Equipment racks, DDFs, etc are known.
Note: Site supervisors should be aware that the 900x300 ETSI racks weighs approx. 85Kg unequipped. Mechanical handling aids should be used wherever possible to move racks within an exchange. Anti static precautions must be observed when erecting racks. The rack should be transported as near as possible to its final location still in its packing. Remove the rack from its packing. Care should be exercised to avoid the spring action of the polyprop retaining bands. Gloves and eye protection must be worn. Consultation with the Customers Representative to agree on a suitable area for unpacking of racks materials should be made prior to commencing this activity. Lower the rack to the floor. Ensure the stability of the rack is maintained. When all packing has been removed, carry out a visual check to ensure that no obvious damage has occurred to the metalwork or internal cabling during transportation. Refer to the floor plan for the position the rack is to be installed. Align the front of the rack base to the tile edge or fixing holes and lower to the floor. Note: The last stages of moving and erecting a rack will normally be done manually. Site Supervisors are to ensure sufficient staff is available for this activity. Align the rear of the rack to the suite datum line. Using a plumb line, align the rack vertically. Use the screw feet at the base of the rack as necessary. A tolerance of +/- 3mm is allowed on the vertical alignment of the equipment. Note: All four, rack feet must be in full contact with the floor.
1.1.3.1
Marconi
Copyright- Refer to title page
Topic 4 Page 19
1PHA60131AAV Issue 04
For 2.6m ironwork fit a bracket DT 40214/1 to the rack fixing point with a C bracket fixed above that.
Modified Bracket
1.1.3.2
1.1.4
Fit EF80
Refer to Contract Engineering site drawings to identify the required position(s) for the EF80 fuse distribution panel. Position the foot of the EF80 to the datum line. Using a plumb line ensures the vertical alignment of the EF80, and mark the two fixing holes in the base. Note: A fixing hole will need drilling in the side of the cable duct if the EF80 is to be fitted adjacent, mark the top fixing hoe in the EF80, see Figure 1-7.
Topic 4 Page 20
1PHA60131AAV Issue 04
Drill two holes (opposite corners) using an 8mm drill bit to a depth not exceeding 30mm and insert rawplugs 1MAB 20477 AAP into the holes. Ensure plug is flush with the floor level. Clear away dust and debris from the drilling area. Note: Installer to use drill stops to ensure that the maximum depth of 32mm is not exceeded.
Align hole at the top of the EF80 to the side panel of the cable duct, and fasten together using a M8 screw, washer and nut. Secure finger tight only. Align the EF80 to the floor markings, insert screws NSR-1248/f625 (2 off) into the previously drilled holes. Do not fully tighten at this stage. Using a plumb line, align the EF80 vertically using packing as necessary and fully tighten all floor and rack fixings. Repeat the above for each EF80.
Fixing Hole
1.1.5 1.1.6
Marconi
Copyright- Refer to title page
Topic 4 Page 21
1PHA60131AAV Issue 04
The cable bracket is secured to mounting uprights provided in the cable duct. This offers a number of fixing positions to attach a partition bracket.
Partition Bracket
Partition brackets are to be mounted onto the rear plate using bolts provided. Bracket fingers are to be orientated towards the subrack as shown below.
Marconi
Copyright- Refer to title page
Topic 4 Page 22
1PHA60131AAV Issue 04
Refer to the cabinet face rack layout diagram to establish bracket locations within the cable ducts. Note: The partition brackets for the OMS 1664 installation are to manage the STM-1 cables within the duct. Note: The LTU cables will be managed on the breakout cable brackets.
1.1.7
Fibre Spools
Fibre spools are fixed to a support plate which is mounted to the duct side uprights. The front of the plate is provided with tapped holes for fixing the spool bracket to and with the rear of the plate enabling COF type fibre cable to be supported using cable ties. The spool and bracket have a number of fixing positions on the plate for small adjustments in the height.
Front
Rear
Note: At least one spool should be mounted adjacent to the fibre management device provided on the subrack. This enables fibres to be correctly routed away from the subrack. Note: Remaining spools can be used to manage excess length in patch cords. Side plates are to be secured to the rack, using the fixings provided.
Marconi
Copyright- Refer to title page
Topic 4 Page 23
1PHA60131AAV Issue 04
In turn secure the right-angle brackets to the side plates and attach the spool with the bolts supplied.
1.1.8
The bracket is secured to the uprights in the cable ducts using the bolts provided.
1.1.9
1.1.9.1
Standard Subrack
Two management bars will be required in Standard subrack installations (e.g. OMS 1664) as shown below.
Marconi
Copyright- Refer to title page
Topic 4 Page 24
1PHA60131AAV Issue 04
Cables are to be dressed onto management bars in to ensure that air flow through the unit is not restricted and access to SIU s is not impaired. The procedure for dressing cables is accordance with details outlined in Section 7 of this document. Cable management bars are to be fitted using M6 screws, black plastic cup washers and cage nuts. Insert cage nuts in desired positions in the rack front mounting rails. Note: The upper cable management bar is to be fitted protruding IN towards the rear of the rack. The lower bar is to be fitted protruding OUT towards the front of the rack.
1.1.9.2
Compact Subrack
A single management bar will be required in compact subrack installations (e.g. OMS 1654) as shown below.
Marconi
Copyright- Refer to title page
Topic 4 Page 25
1PHA60131AAV Issue 04
Cables are to be dressed onto the management bar to ensure that air flow through the unit is not restricted and access to subrack SIU s is not impaired. The procedure for dressing cables is accordance with details outlined in Section 7 of this document. The Cable management bar is to be fitted using M6 screws, black plastic cup washers and cage nuts. Insert cage nuts in desired positions in the rack front mounting rails. Note: The cable management bar is to be fitted protruding IN towards the rear of the rack.
1.1.10
CAUTION!
The subrack weighs approximately 10 kg when empty. Refer to Section 2 Lifting and Handling of this document for details of handling procedure. WARNING: The standard subrack weighs approximately 10 kg when empty. It is necessary to obtain assistance from a colleague during installation activities.
1.1.10.1
Rack Preparation
The following activities ensure that the rack is prepared to accept the subrack. Note: Refer to the information provided by Contract Engineering establish the location of the subrack within the cabinet. The subrack is secured in to the rack via the front mounting brackets using M6 screws and cage nuts. Fit 8 off M6 it cage nuts 1MAB 20026AAK into positions in cabinet mounting rails corresponding with the subrack fixing holes.
Shelf support brackets 1MBB 61103 AAM are provided to ease installation of the subrack. The shelf support brackets provide a pivot point for the subrack during installation. Fit 2 off M6 it cage nuts 1MAB 20026AAK into positions in cabinet mounting rails for shelf support brackets. These are fitted 1 SU below the subrack bottom fixing screw. Secure the shelf mounting brackets to the rack using M6 screws as shown.
Marconi
Copyright- Refer to title page
Topic 4 Page 26
1PHA60131AAV Issue 04
1.1.10.2
Installation Procedure
CAUTION!
Ensure cable assemblies and internal brackets will not impede subrack insertion into the rack. Prior to installing the subrack connectors are to be terminated to the unit DC power cables Refer to Section 5 of this manual for method of fitting connectors. The subrack is to be moved to a position adjacent to the rack using mechanical transportation devices suited to the working environment. Note: It is preferable that the equipment remains in its packaging during transportation. Remove packaging and inspect the subrack for any signs of damage. Using the procedure outlined in section 2 of this document present the subrack upto the support brackets attached to the rack front rails. Pivot the subrack into place until the unit is vertical and the mounting brackets are in contact with the rack front rails.
Marconi
Copyright- Refer to title page
Topic 4 Page 27
1PHA60131AAV Issue 04
Stabilise the subrack and secure to the rack framework using 8 off M6 x 16 mm long screws (1MAB 20025 AAH) and black plastic cup washers (1MAB 20027 AAM) in the positions fitted with cage nuts. The stability of the subrack must be maintained at all times, until all the fixing screws are fitted. Remove the shelf support mounting brackets from the rack once the subrack is secure for reuse.
Note: Ensure that the black plastic covers, are fitted to the bracket mounting studs, once the subrack installation is completed. Remove all packing materials from the area and dispose of in accordance with procedure agreed with the customer.
Note: A supplementary earthing strap must be connected to the stud provided on the subrack chassis prior to application of DC power. Refer to Section 5 of this document for subrack earthing requirements.
1.1.11
CAUTION!
The compact subrack weighs approximately 5 kg when empty. Whilst a single operator may be capable of lifting the unit into place it is advisable to obtain assistance from a colleague during installation activities. Note: Prior to installing the subrack connectors are to be terminated to the unit DC power cables. Marconi
Copyright- Refer to title page
Topic 4 Page 28
1PHA60131AAV Issue 04
1.1.11.1
Rack Preparation
The following activities ensure that the rack is prepared to accept the subrack. The subrack is secured in to the rack via the front mounting brackets using M6 screws and cage nuts. Fit 6 off M6 it cage nuts 1MAB 20026AAK into positions in cabinet mounting rails corresponding with the subrack fixing holes.
Shelf support brackets 1MBB 61103 AAM are provided to ease installation of the subrack. The shelf support brackets provide a pivot point for the subrack during installation. Fit 2 off M6 it cage nuts 1MAB 20026AAK into positions in cabinet mounting rails for shelf support brackets. These are fitted 1 SU below the subrack bottom fixing screw. Secure the shelf mounting brackets to the rack using M6 screws as shown previously.
1.1.11.2
Installation Procedure
Ensure cable assemblies and internal brackets will not impede subrack insertion into the rack. The subrack is to be moved to a position adjacent to the rack using mechanical transportation devices suited to the working environment. Note: It is preferable that the equipment remains in its packaging during transportation. Remove packaging and inspect the subrack for any signs of damage. Carefully lift the subrack and present it upto the required location in the rack. Rest the chassis on the attached support brackets. Pivot the subrack into place until the unit is vertical and the mounting brackets are in contact with the rack front rails. Whilst stabilising the unit request the assistance of a colleague to secure it to the rack framework using 6 off M6 x 16 mm long screws (1MAB 20025 AAH) and black plastic cup washers (1MAB 20027 AAM).
CAUTION!
The stability of the subrack must be maintained at all times, until all the fixing screws are fitted. Remove the shelf support mounting brackets from the rack once the subrack is secure for reuse. Note: Ensure that the black plastic covers, are fitted to the bracket mounting studs, once the subrack installation is completed.
Marconi
Copyright- Refer to title page
Topic 4 Page 29
1PHA60131AAV Issue 04
Remove all packing materials from the area and dispose of in accordance with procedure agreed with the customer.
Note: A supplementary earthing strap must be connected to the stud provided on the subrack chassis prior to application of DC power.
1.1.12
Fan Filter
Power Connector
The fan tray requires a protected independent DC power supply. A three pin D-type power connector is located on the front of the unit. A D-type alarm cable input connector is also provided on the front of the unit. Note: Refer to the power and earthing and alarm cable requirements in this document. Attach a supplementary earth strap to the stud on the front face of the fan unit prior to connecting a DC power supply.
Marconi
Copyright- Refer to title page
Topic 4 Page 30
1PHA60131AAV Issue 04
Securing Screws
The fan tray is provided with a replaceable fan filter element. If this is not already fitted slide this into place in the slot at the bottom of the unit.
1.1.13
1.1.14
Note: Units are provided typically in see-through anti-static bags. Wherever possible checking and inspection of a unit should occur without removing it from the bag. Note: If a unit is to be removed from its protective bag, for inspection or insertion into the rack, the following precautions must be adhered to: Fix an ESP grounding wrist strap and cord to the ESD stud on the rack. Handle unit by its face plate or card ejectors.
Marconi
Copyright- Refer to title page
Topic 4 Page 31
1PHA60131AAV Issue 04
Note: The ESP wrist strap must have a 2 M Ohm resistor fitted at either end. All straps and cords MUST be tested prior to use. Wrist straps should be worn in direct contact with bare skin and not over clothing. Note: If a fault or damage is found on a SIU, then it is the engineers responsibility to arrange for a replacement to be dispatched and the faulty unit to be returned to the factory.
1.1.15
Installation Procedure
Subrack SIU installation process is as follows: Refer to the site documentation to obtain the correct card location within the subrack. Hold the SIU by the card ejectors and align with the guides in the subrack. Slide the unit into the subrack ensuring the two ejectors are in the horizontal (open) position.
Push the unit home by pressing the two card ejectors inwards towards the centre of the unit. Ensure that the unit is correctly located by operating the card ejectors.
Marconi
Copyright- Refer to title page
Topic 4 Page 32
1PHA60131AAV Issue 04
Repeat the above procedure for all slide in units which are to be installed in the subrack. Note: Blanking covers must be fitted to empty card slots to maintain ideal EMC and ESP conditions.
CAUTION!
Do not attempt to temporarily park SIU s in the subrack as incorrect placement or forced insertion of the unit could cause damage to the backplane.
1.1.16
SIU Extraction/Insertion
Removal and re-insertion of units during upgrade or maintenance activities can be summarised as follows: Note: Consult with a customer representative to ensure that the SIU is not in service prior to removal. Disconnect coax or fibre connections to the card taking care not to disturb adjacent terminations.
Note: Use appropriate connector removal tools where necessary. Great care must be taken to ensure that cables are not pulled during disconnection. Carefully operate card ejector devices to disconnect the unit from the subrack backplane. Hold the unit by the ejectors and withdraw it from the subrack. Place the unit in a static protective bag. Remove the replacement unit from packaging. Insert the unit into the empty sot in the subrack.
CAUTION!
Great care must be taken not to damage the EMC fingers on the unit to be installed or any adjacent units in the subrack.
Marconi
Copyright- Refer to title page
Topic 4 Page 33
1PHA60131AAV Issue 04
Slide the unit along the runners until the face panel makes contact with the EMC fingers and face panels of the adjacent units. Push the unit home by pressing the two card ejectors inwards towards the centre of the unit. Ensure that the unit is correctly located by operating the card ejectors.
Marconi
Copyright- Refer to title page
Topic 4 Page 34
1PHA60131AAV Issue 04
1.2
1.2.1
General
The OMS1664 subrack has two power supply unit cards. A sketch of the DC power infrastructure for the OMS1664 is shown in Figure 1-21. The requirements below are based on a OMS1664 with a typical power consumption of 963W. Design Current: The load for the OMS1664 is taken as 963W which gives a load current of 20A at 48V. Cable Protection: The protection of cables C, D, E and F shown in Figure 1-21 is provided by a 40A BS88 fuse or 40A Type B MCB at the E.O.S. distribution board. This device must only be used in an ambient temperature equal to or less than 35C. A 25A Type B MCB must be used to protect the cables within assemblies J and K. This MCB must only be used in an ambient temperature (at the rack-top) of no more than 45C. Cable Size: The size of cables C, D, E and F shown must be 16mm to accommodate the load current of 25A, grouping factor for 4 circuits and ambient temperature of 45C. Cables C, D, E and F are serving one subrack. It is dual fed with 2 x 50v and 2 x +50v.
The size of cables within the assemblies J and K must be 4mm with 85C insulation and must be screened for EMC purposes. This is to accommodate the full load current and an ambient temperature of 45C. Volt-drop & Maximum Route Length: The volt-drop from the power plant to the equipment must be no more than 2V. Therefore assuming no more than a 1V drop from the power plant to the Distribution Board (DB). the length of cables C, D, E and F must be no longer 10m. The length of cables within the cable assemblies J & K must be no longer than 2m. Earthing Conductors: The earth cable marked G in Figure 1-21 must be 16mm. The bonding conductor marked L in Figure 1-21 must be 16mm. The protective earth conductor marked M in Figure 1-21 must be 6mm.
Marconi
Copyright- Refer to title page
Topic 4 Page 35
1PHA60131AAV Issue 04
A list of the components used above and their part numbers are shown below.
Summary Infrastructure based on a maximum load of 20A at 48V. Infrastructure based on an ambient temperature of 35C at D.B. and 45C at rack-top. Cable protection, 40A BS88 protects the 16mm cables and 25A Type B MCB protects the 4mm cables. Cables C, D, E and F from D.B. to rack-top must be 16mm and may be grouped with up to three identical circuits. Topic 4 Page 36 1PHA60131AAV Issue 04
Marconi
Copyright- Refer to title page
Cables within assemblies J and K must be 4mm and EMC Braided. Cable installation for the 16mm is BS7671 Method 11 (Installed on perforated cable tray). Cable installation for the assemblies J and K is BS7671 Method 12 (Installed in free air). Maximum length allowed for cables C, D, E and F is 10m. Maximum length allowed for cables within assemblies J and K is 2m. Volt-drop based on 1v from the D.B. to the PLTU. The earth cable from the rack earth terminal to the distribution earth bar must be 16mm. The bonding conductor from the rack-top earth bar to the rack must be 16mm. The sub-rack to cabinet bonding conductor must be 4mm.
1.2.2
Install DC Cables
Note: All cables should be fully proven using a continuity tester before any connections are made to validate both source and destination address of each cable. Isolate the power feeds into the top of the fuse or breakers to be terminated. This could mean the removal of end of suite fuses or placing a main switch in the OFF position. Note: Having isolated fuses or switches ready to work on the equipment, ensure a label is attached to the empty fuse carrier or switch to ensure the supply is not restored while work is still being carried out.
Marconi
Copyright- Refer to title page
Topic 4 Page 37
1PHA60131AAV Issue 04
1.2.2.1
1.2.2.2
Marconi
Copyright- Refer to title page
Topic 4 Page 38
1PHA60131AAV Issue 04
1.2.2.3
Marconi
Copyright- Refer to title page
Topic 4 Page 39
1PHA60131AAV Issue 04
Marconi
Copyright- Refer to title page
Topic 4 Page 40
1PHA60131AAV Issue 04
1.2.3
At the top of the rack, secure the cable to the debris tray with plastic ties. Ensure sufficient length is left on the cable for terminating the earth wire to the rack framework. Note: Breakout is 400mm for all seven wires. Remove the inner/outer sheathing from the cable. Cut back the braiding to 25mm. Open out the braiding and select approx. 20 wire strands and twist together. Cut off the remaining wires from the braiding level with the cable sheathing. Remove approx. 12mm of insulation from the 2.5mm cream cable and solder to the twisted braiding ensuring a good connection is made. Fit heatshrink over the joint. Note: Prior to terminating any cables carry out a continuity check to ensure correct polarity. Dress wires 1,3,5 (0 Volt) to the 0 Volt termination rail, fit spade connectors 1CXB 21161 AAW, using crimp tool BMR6U3 (1PAC 10336 AMA) to each wire and terminate on the rail. See Figure 1-24.
Wire Number
Marconi
Copyright- Refer to title page
Topic 4 Page 41
1PHA60131AAV Issue 04
1.2.3.1
DC Rail 332-0293/05.01
Fit rack top DC rail 332-0293/05.01 to the top most position in the rack. Fix using four 2 M5 screws provided. Ensure supplementary earth bonding conductor 6mm grn yel, 336-1674/02.01 is fitted from DC rail to rack earth bonding point. M6 ring terminal is provided to fit to rack 92 top earth stud. Fit MCBs, earth terminal blocks and supplementary earth blocks (grn/yel) to DIN rail. Ensure they are equally spaced about the rack centre line. See Figure 1-22. Fit jumper bars to earth terminal blocks and screw in position. Link earth terminal blocks to supplementary blocks using 6mm grn/yel cable provided. Fit end stops to secure components to the rail. See table below for additional codes. Fit common rail and connectors to MCBs. This will allow the application of larger cables.
2
Common Code 55210-44/235 6100331-0028 6100394-0063 67372-27/012 67372-51/112 67372-51/113 1CFB 20019 AER 1CXB 21237 AAV 67372-51/114 1MAB 20025 AAH 1MAB 20026 AAK
1.2.3.2
Factory Assembled Power Looms fitted with 3 Way D Type Connectors (1HAU 62488 AAL) OMS1664
The cable consists of 3 individual 4.0mm insulated wires, blue (-ve), black (+ve) and Gn/Y (Eth). The power supply cables from the subrack to the DC distribution rail are factory assembled and ready for fitting. The D type end is connected to the upper part of the subrack in slots 19 (pwr A) and 20 (pwr B). The free end is connected to the appropriate circuit breaker and earth connection strip on the DC distribution rail.
Marconi
Copyright- Refer to title page
Topic 4 Page 42
1PHA60131AAV Issue 04
1.2.3.3
Factory Assembled Power Looms fitted with 3 Way D Type Connectors (1HAU 62489 AAN) OMS1634
The cable consists of 3 individual 4.0mm insulated wires, blue (-ve), black (+ve) and Gn/Y (Eth). The power supply cables from the subrack to the DC distribution rail are factory assembled and ready for fitting. The D type end is connected to the upper part of the subrack in slots 19 (pwr A) and 20 (pwr B). The free end is connected to the appropriate circuit breaker and earth connection strip on the DC distribution rail.
1.2.4
Marconi
Copyright- Refer to title page
Topic 4 Page 43
1PHA60131AAV Issue 04
1.2.5
Earthing
Rack Earth Bonding
Run a length of 16mm G/Y cable from the customers main earth bar to the rack via the central power tray. Strip approx. 10mm of insulation from the cable and crimp an Elpress M6x16 ring lug to both ends using the appropriate Elpress crimping tooling and die. Fasten the cable to the terminating stud on the customers main earth bar using the washer and nut supplied. Fully tighten the fixings. Route the cable to the rack Earth stud (4 are provided 2 x top and 2 x bottom of rack) and fasten to the stud using the fixings already in place. Refer to Figure 1-28 below. Note: The earth cables supplied are flexible cables and the correct lug and crimp tool should be used. Ensure the lug has the suffix F marked on it i.e. 16mm x 6f. The BMR 16U3 or the Elpress T2600 crimp tool fitted with dies marked with the number 9.
2
1.2.5.1
1.2.5.2
Marconi
Copyright- Refer to title page
Topic 4 Page 44
1PHA60131AAV Issue 04
on the front right hand side of the subrack to the nearest rack Safety Protective Earth Terminal positioned on the top or bottom of the rack marked:
Connect one end of the Safety Protective Earth conductor to the connection point on the subrack (no leg required). Crimp an Elpress M6x6mm lug to the free end and secure using existing fixings at the top or bottom of the rack. See Figure 1-29 below. Ensure black plastic cover is replaced on earth stud after termination of earth bonding lead.
1.2.6
Marconi
Copyright- Refer to title page
Topic 4 Page 45
1PHA60131AAV Issue 04
The fan tray is designed such that in the event of a single fan failure the remaining fans are driven at full speed to help compensate for the fan failure. This applies in all fan tray operation modes and under this condition, the fan tray generates a major alarm condition both visually, front panel LED and via the 9 way connector.
1.2.6.1
The safety protective earth cable must be connected prior to connecting any power to the unit. See Figure 1-31 below.
1.2.6.2
Filter Cleaning
An air filter is housed inside the fan tray and can be pulled out without removing the fan unit for cleaning or replacement The life time of the filters is dependent on the specific environmental conditions the equipment is installed into and the distance from floor level i.e. the position of the subrack in the rack. There is a filter block alarm which will be raised when the filter becomes blocked or dirty and the filter must be replaced/cleaned as soon as possible to ensure maximum airflow to the subrack.
Marconi
Copyright- Refer to title page
Topic 4 Page 46
1PHA60131AAV Issue 04
The front panel LED will flash amber when this occurs.
1.2.6.3
1.2.7
Marconi
Copyright- Refer to title page
Topic 4 Page 47
1PHA60131AAV Issue 04
1.2.7.1
1.2.8
Cable Routing
Feed fan cable assembly up the right hand side of the cabinet to rack top fuse and earth rails. Connect 50v wire to auxiliary fuse and 0v wire to the rack top earth rail. Ensure cables are routed to avoid catching on brackets. The fan tray power and alarm cables should be installed in such a manner to avoid stress on the cables and connectors when closing the rack door.
DC Power Cable Note: Fan Unit must have the Safety Protective Earth conductor connected prior to powering up
1.2.9
Fan Fusing
The rack top Cct breaker is to be rated at 6A, with a 20A fuse at end of suite. Feed a 2 16mm cable from end of suite to auxiliary fuse.
Marconi
Copyright- Refer to title page
Topic 4 Page 48
1PHA60131AAV Issue 04
1.3
Cable routes will have been planned at the engineering stage of the contract. Consultation with the Customers Representative for a variation in the routing of the cables to suit site conditions may be agreed, so long as the length of the cable run does not exceed the length of the cables engineered for that site. All drawings must be red lined to identify new routes and sent to Contract Engineering who must agree to any proposed changes in cable routes. The routing of the cables from the OMS1664 to frame will be dependent on rack design, equipment configuration, OHI and frame, however, the following cabling rules always apply: Cabling on transmission cable trays should be kept as flat as possible. Sharp bends of cables across trays should be avoided and no slack should be left in any cabling within the rack area. Cabling from the equipment racks to Digital Distribution Frames (DDF) should be routed via the longitudinal suite transmission tray and appropriate transverse cable tray leading to the vertical of the DDF on which the cable terminates (i.e. same side cabling). Cabling should only be tied when leaving a transverse tray and dropping to a longitudinal tray (or frame), or to the central conduit bearer when entering a rack. At the top of a vertical cable run, bends in the cable form should be sufficiently large enough to ensure that the weight of the cables is supported by the ties throughout the vertical run and not by the horizontal section. Cables should be routed in a manner to ensure a minimum separation of 200mm is maintained at all times between signal and AC cables. It is permissible to allow such cables to cross at 90 to each other. Cabling should enter ETSI rack from the longitudinal suite transmission trays on the opposite side of the suite centre line via the central conduit cable bearer (i.e. opposite side cabling). Cables should be secured to the support brackets in the cable void/duct with plastic cable ties. Cables of less than 20 pair should be mixed in bundles not exceeding 50mm in diameter. Sharp bends must be avoided at all times. Always make provision for future growth and expansion. Allowances in cable forms should be made for the removal of existing equipment for maintenance, etc.
Marconi
Copyright- Refer to title page
Topic 4 Page 49
1PHA60131AAV Issue 04
Installers are advised that where Marconi have to pass cables through any cable hole that has not been previously fire stopped and does not have an instruction label adjacent to the hole they MUST contact the customers Cable Hole Management Team if applicable Additionally where cables are to be passed through previously fire stopped cable holes; installers MUST follow the Mandatory Instruction Label adjacent to the hole. Terminations should not be stressed. Installers are advised that where cables pass through cable holes that have not been previously fire stopped they MUST contact the customers Cable Hole Management Team if applicable. Where cables are to be passed through previously fire stopped cable holes; installers MUST follow the Mandatory Instruction Label adjacent to the hole.
Note:
1.3.1.1
1.3.2
Cabling to OMS1664
Cabling to the OMS1664 subrack is summarised as follows.
1.3.3
Marconi
Copyright- Refer to title page
Topic 4 Page 50
1PHA60131AAV Issue 04
Note: Interface area will be either 120 Ohm or 75 Ohm. Above picture shown only to identify both types of interface available A fully cabled 2Mbit/s LTU interface area accommodates up to 1008 coaxial cables (504 ports) or 64 x 37 way D type connectors (504 ports). Note: The 2Mbit/s LTU interface area of the OMS1664 sub-rack, when fully populated, will hold up to 4 tribs (max per shelf).. Four LTUs equate to one trib Each LTU has 32 ports. On even numbered 2Mbit/s LTUs there is a requirement of one (1) free port to be left which can be used for monitoring purposes. For allocation of external cables to the LTU interface area refer to the information supplied by the overall installation authority. Cables must be run in accordance with the General Cabling Rules. It is imperative that these rules are adhered to at all times. The forming and terminating of cables will be accordance with the exchange cable running out list (CROL). Due to the heavy volume of cables in a restricted area it is essential that careful consideration is paid to the approach and marshalling of cables at drop off areas to maintain the best possible feed pattern down the rack. During cabling it is advisable that crossovers/twists should be kept to a minimum down the rack to prevent congestion, and thought must be given to keep ultimate cable spaces clear. Starting at the first position to be cabled, attach cable labels, refer to 1.3.1.1, or mark the cables with a marker pen to identify the to/from routing of the cables and run the cables in manageable bundles (32 cables) to or from the first required position in the rack. Arrange cables on the cable trays to ensure a direct approach to the rack, taking a side sweep as necessary to leave space for the ultimate growth within the rack. Marconi
Copyright- Refer to title page
Topic 4 Page 51
1PHA60131AAV Issue 04
Temporarily tie cables back at bends or employ cabling aids to maintain direct approach and to allow cables to be disciplined in formation. Bring down cables in manageable quantities; marshal them into formation on the roll bar. Note: Bundles of cables must be secured in formation on the roll bar with plastic cable ties. Where cables are fed from the base of the rack the procedure is the reverse of the above. Requirements for future cabling should again be taken into consideration. Cables will require to be supported at regular intervals within the cable void. To avoid congestion within the racks cabling void, the LTU interface area must be cabled from both sides. Note: Cable management bars are required to manage the cables. Refer to Contract Engineering Face Layout information for correct placement of cable management bars in rack.
1.3.3.1
2Mbit/s Coaxial Cable to LTU/Trib Area Routed Via Cable Duct and Secured to Cable Management Bars Above Subrack
Cables to the subrack should be fed, as per normal transmission practice, from the overhead baskets situated at the rear of the suite, cabling over the centre roll bar into the top of the cable ducts right or left. Note: The cables to LTU positions 1 to 8 should be formed in the left-hand cable duct. Cables to LTU positions 9 to 16 should be formed from the right-hand cable duct. Note: The subrack should be cabled LTUs 1 to 4 (trib 1) firstly and working inwards to the middle of the shelf. Marconi
Copyright- Refer to title page
Topic 4 Page 52
1PHA60131AAV Issue 04
Feed the cables for LTUs 1 to 4 inclusive to the outside of the ducts brackets, cables for LTUs 5 and 8 to be fed to the inside of the previous 4 LTU cables, see Figure 1-36 All cables to the subrack should be formed in the cable duct, dressed across the cable management bar and secured using plastic ties. Run the cables in bundles of 32 to each half of the LTU through the cable duct and fit temporary ties to support the cable bundles wherever possible. Bring cables from the side of the rack to secure to the front of the CMB mounted above the subrack interface area to drop vertically over the LTU. Drop the cables down the front of the CMB to the top half of the LTU interface card and secure temporarily to the bar, see Figure 1-36. Note: Check the cables are long enough to reach their terminating position on the LTU interface card. Do not terminate the cables at the LTU interface card at this stage.
Marconi
Copyright- Refer to title page
Topic 4 Page 53
1PHA60131AAV Issue 04
When the bundle of 32 cables have been installed to the front of the LTU, termination of the cables at the LTU interface card can commence. Note: Extreme care must be taken when routing cables to the front of the LTU interface area. Cabling should not encroach on adjacent LTU interface cards; there must be sufficient room to remove, for maintenance purposes, the LTUs & AIUs behind the cable forms. To achieve maximum cable management efficiency apply a running stitch to the cable form. see Figure 1-38 Avoid any crossover of cables and allow a space between each row of 64 cables (1 LTU interface card), for easy insertion of connector extraction tool. Starting with cables to the top half of the LTU, terminate each cable to its designated port. When terminating is complete, apply running stitch up to the cable management bar and secure with cable tie. Note: Ensure that there is no pressure exerted on the connections therefore the cables must allow for some movement. Remove temporary cable tie from the CMB holding cable bundle Terminate each cable to designated port. When the termination is complete apply running stitch up to CMB and secure using a cable tie.
Marconi
Copyright- Refer to title page
Topic 4 Page 54
1PHA60131AAV Issue 04
Dress the two bundles back to the front of the upper CMB, ensuring that there is no further pressure exerted on the connections therefore the cables must allow for some movement. The cables should sweep up to the CMB and outwards to the cable duct, before exiting, ensuring they are not stressed and moving any excess cable back through ducting to source (overhead ironwork /basket). Note: Ensuring the minimum bend radius is maintained at all times on all cables and the weight of the bundle is equally shared. Note: Ensure that the cable forms do not impede the air flow/circulation of the ventilation area at the top of the sub-rack.
The cables to the subsequent LTU interfaces should follow the same route and method, being secured in the duct to the side of the first 64 cables.
Marconi
Copyright- Refer to title page
Topic 4 Page 55
1PHA60131AAV Issue 04
Running stitch
Marconi
Copyright- Refer to title page
Topic 4 Page 56
1PHA60131AAV Issue 04
Tribs 1-4 pass behind upper management bar and brought to the front of the lower bar and secured. See Figure 1-40 for pictorial view of Tribs 1-4
1.3.3.2
External Cabling 120 Ohm LTU I/F Area (D Type Twisted Pair)
Cables must be run in accordance with the General Cabling Rules. It is imperative that these rules are adhered to at all times. The forming and terminating of cables will be accordance the exchange Cable Running Out List (CROL). A fully cabled 2Mbit/s LTU interface area accommodates 64 x 37 way D type connectors (504 ports). Note: The 2Mbit/s LTU interface area of the OMS1664 sub-rack, when fully populated, will hold up to 4 tribs (max per shelf).. Four LTUs equate to one trib Each LTU has 32 ports. On even numbered 2Mbit/s LTUs there is a requirement of one (1) free port to be left which can be used for monitoring purposes.
Marconi
Copyright- Refer to title page
Topic 4 Page 57
1PHA60131AAV Issue 04
For allocation of external cables to the LTU interface area refer to Contract Engineering information supplied. During cabling it is advisable that crossovers/twists should be kept to a minimum down the rack to prevent congestion, and thought must be given to keep ultimate cable spaces clear. Starting at the first position to be cabled, attach cable labels, refer to 1.3.1.1 or mark the cables with a marker pen to identify the to/from routing of the cables and run the cables in manageable bundles (32 cables) to or from the first required position in the rack. Arrange cables on the cable trays to ensure a direct approach to the rack, taking a side sweep as necessary to leave space for the ultimate growth within the rack. Temporarily tie cables back at bends or employ cabling aids to maintain direct approach and to allow cables to be disciplined in formation. Bring down cables in manageable quantities; marshal them into formation on the roll bar. Note: The cables to LTU positions 1 to 8 should be formed in the left-hand cable channel. Cables to LTU positions 9 to 16 should be formed from the right-hand cable channel. Note: The subrack should be cabled LTUs 1 to 4 (trib 1) firstly and working inwards to the middle of the shelf. All cables to the subrack should be formed in the cable channel, dressed across the cable management bar and secured using plastic ties. Run the cables to each half of the LTU through the cable channel and fit temporary ties to support the cable bundles wherever possible. Bring cables from the side of the rack to secure to the front of the CMB mounted above the subrack interface area to drop vertically over the LTU. Plug up each cable as it is installed and secure using the retaining screws on the connector. Dress any excess slack away from the subrack into the cable channel. Refer to Figure 1-43 to Figure 1-45. Note: Extreme care must be taken when routing cables to the front of the LTU interface area. Cabling should not encroach on adjacent LTU interface cards; there must be sufficient room to remove, for maintenance purposes, the LTUs & AIUs behind the cable forms.
Marconi
Copyright- Refer to title page
Topic 4 Page 58
1PHA60131AAV Issue 04
Marconi
Copyright- Refer to title page
Topic 4 Page 59
1PHA60131AAV Issue 04
1.3.4
1.3.4.1
Marconi
Copyright- Refer to title page
Topic 4 Page 60
1PHA60131AAV Issue 04
The preferred cable for the high band electrical tribs is BR 7000 fitted with right-angles connectors. Route the cables down the cable ducts, separate if possible from the 2Mbit/s coax. Securing them to the Segregation Brackets. Run the cables in card allocation sequence, across the fibre/cable channel Form the cables in a group of six to drop vertically above their designated card, see Figure 1-47. Place a cable tie around the 8 cables and the front of the right-angled bracket, this action will allow for segregation/identification purposes and also to give the cable form the lowest profile as possible at the front of the trib card. The 8 coax with a 1.0/2.3 right-angle connector fitted to each should be dressed to the correct port on the card. Marshall cables to the port terminations, alternating the pairs of cables to be dressed down the cards from right then left. Note: When removing a trib card for replacement/maintenance, due to the angle of the connector, care should be taken to limit knocking cables formed to the adjacent cards.
Marconi
Copyright- Refer to title page
Topic 4 Page 61
1PHA60131AAV Issue 04
Note: Left hand side of shelf shown. Cable to the right hand side are a mirror image.
Note: When cable management bracket 1MBD60712AAS is supplied this must be used. The cables must follow the same forming and management as shown in Figure 1-47.
Marconi
Copyright- Refer to title page
Topic 4 Page 62
1PHA60131AAV Issue 04
1.3.4.2
Optical cables pass underneath the electrical cable and pass through the guides
Marconi
Copyright- Refer to title page
Topic 4 Page 63
1PHA60131AAV Issue 04
1.3.5
Cabling to OMS1654
Cabling of the OMS 1654 subrack is summarised as follows:
1.3.6
LTU Area
Marconi
Copyright- Refer to title page
Topic 4 Page 64
1PHA60131AAV Issue 04
Note: When cabling to a 75 ohm LTU 3002 coax cable or equivalent is to be used. A fully cabled 2 Mbit/s LTU interface area accommodates up to 256 coaxial cables (128 ports) or 16 x 37 way D type connectors.
Note: On even numbered 2 Mbit/s LTU's there is a requirement of one (1) free port to be left which can be used for monitoring purposes. Note: For allocation of external cables to the LTU interface area refer to Contract Engineering information supplied. Cables must be run in accordance with the General Cabling Rules It is imperative that these rules are adhered to at all times. The forming and terminating of cables will be accordance the exchange Cable Running Out List (CROL). If not already present secure a cable a management bar above the subrack using M6 screws plastic cup washers and cage nuts.
Note: Cable management bar is to be secured with formed section installed towards the rear of the cabinet. Commence cabling on the left hand side of the LTU card area. Connections to the ports on the LTU must be made starting at the top of the card. Subsequent connections to the lower ports on the card are to be laid on top of those previously installed. Topic 4 Page 65 1PHA60131AAV Issue 04
Marconi
Copyright- Refer to title page
Form cables vertically up to the cable management bar and temporarily secure the bundle using a nylon cable tie. On completion of card connections remove temporary cable ties. Dress cable bundles serving the first two LTUs to the left hand rack cable space. Dress cable bundles serving the remaining LTUs to the right hand rack cable space. Secure cables to the management bar with cable ties.
Note: It is essential that the cable bundle is formed to ensure that removal of adjacent cards is not impeded. Note: Ensure that a minimum bend radius is maintained on cable forms. Note: Cable bundles must not protrude beyond the front face of the subrack chassis.
Marconi
Copyright- Refer to title page
Topic 4 Page 66
1PHA60131AAV Issue 04
Note: A 3 SU gap (75 MM) is required between adjacent subracks. This provides room for cable management and allows free air-flow from the top of the unit. Cable bundles from subracks mounted in the lower section of the rack are to be installed towards the rear of the cable space. Subsequent cable bundles are to be installed forwards of these.
1.3.7
Marconi
Copyright- Refer to title page
Topic 4 Page 67
1PHA60131AAV Issue 04
Fit alarm cable 1HAU62481AAV to the connector on the fan tray. Route cable across to right hand side of rack and into the cable duct. Run the cable neatly and secure using cable ties. Route the cable above the subrack along the cable management bar and secure using nylon cable ties. Drop the cable vertically down to Management and Sync LTU and connect to the Fan Management port on the card.
Note: Ensure that routing of cable does not impede removal of subrack traffic or power LTUs.
1.3.8
Marconi
Copyright- Refer to title page
Topic 4 Page 68
1PHA60131AAV Issue 04
1.3.9
Power Cable
A power cable 1HAU62488AAL is to be connected between the rack fuserail and both subrack power LTUs. Attach cable to the power LTU and secure using both retaining screws provided on the connector. Run the cable up the right hand side of the rack (as viewed from the front) to the required MCB position on the fuserail. See section 5 of this document for cable termination method and subrack power requirements. Secure the cable in the cable duct using plastic cable ties.
CAUTION!
Ensure that the circuit breaker is de-energised to isolate the circuit from the power supply prior to connecting to the subrack.
Marconi
Copyright- Refer to title page
Topic 4 Page 69
1PHA60131AAV Issue 04
1.4
1.4.1
1.4.2
Marconi
Copyright- Refer to title page
Topic 4 Page 70
1PHA60131AAV Issue 04
1.4.3
Marconi
Copyright- Refer to title page
Topic 4 Page 71
1PHA60131AAV Issue 04
Fibre spools are provided within the ETSI rack cable ducts for management of fibre patch cords. Spools are to be utilised to lose excessive cable slack, maintain minimum bend radii and prevent fibre damage. See below.
Marconi
Copyright- Refer to title page
Topic 4 Page 72
1PHA60131AAV Issue 04
Note: Velcro straps must be utilised where securing fibres. Care must be taken to ensure that straps are not over tightened thus avoiding fibre damage. The fibre tails should be fed across to the adjacent cable duct in the rack and onto the first fibre spool. Note: The lengths of the fibre tails used may require the use of additional spools to manage any excess length. Fibres are to be loaded in a figure-eight formation around adjacent spools in order to lose the excess length. The optical cables are to be fed from the spools and onto fibre management device provided with the subrack. Depending upon whether the rack is installed in an overhead or raised floor application fibre tails are to be managed to the rack exit at the top or bottom of the cable duct. Cables are to be run along the suite length (in Kopex flexible conduit if non-ruggedised) to an interface shelf. Note: Excessive slack should be avoided in fibres by correctly using fibre spools provided. Note: There may be a requirement for removal of fibres for maintenance or system upgrade. This should be considered during fibre installation.
1.4.4
Marconi
Copyright- Refer to title page
Topic 4 Page 73
1PHA60131AAV Issue 04
Cable management devices are provided in the mid shelf section of the subrack. Features are provided to correctly manage and route fibres feeding cards fitted in the subrack. Note: The fibre management device must be utilised to ensure the minimum bend radius and correct management of the fibre optic cables is maintained. Cables feeding common cards are to be bundled together and secured using a velcro strap. Dress bundles vertically upto the cable management area and locate inside the retaining rings provided as shown below.
Depending on the card location in the shelf, route bundles left and right as required. Feed the fibre bundles around the guides provided and along the main channel of the management shelf. Run fibres into the cable ducts on either side of the rack. Note: It may be necessary to protect fibre cables in the cable ducts using flexible conduit e.g. Kopex.
Figure 1-61: View Showing Card Cage with STM-1 Optical Tribs
Marconi
Copyright- Refer to title page
Topic 4 Page 74
1PHA60131AAV Issue 04
1.4.5
WARNING!
Great care must be taken to avoid crossing of fibres, sharp bends or coiling too tightly on management devices. Fibres must not be positioned where they could be trapped in rack doors closing door, Fibre are to be kept neat, observe min bend radius. Do not stress fibres.
1.4.6
WARNING!
Nylon cable ties must not be used to secure optical fibre patch cords.
Marconi
Copyright- Refer to title page
Topic 4 Page 75
1PHA60131AAV Issue 04
Marconi
Copyright- Refer to title page
Topic 4 Page 76
1PHA60131AAV Issue 04
1.5 1.5.1
1.5.2
Note: The wrist strap cords must have a 2Meg Ohm resistor fitted at either end. All straps and cords should be tested using a Wrist Strap Tester prior to use. Wrist straps should be worn in direct contact with bare skin and not over clothing.
Marconi
Copyright- Refer to title page
Topic 4 Page 77
1PHA60131AAV Issue 04
WARNING
Under no circumstances is it permissible for units to be handled by unprotected operators.
1.5.2.1
1.5.3
Portable Field Service Kit (PFSK) And Safe Handling Areas (SHAs)
Currently the philosophy for unit repairs is that all SIUs are to be returned to headquarters for modification and repair. Under no circumstances attempt to modify or repair a unit on site. Consequently, PFSKs and SHA equipment have been withdrawn from circulation and must not be used. If for any reason in the future PFSKs or SHAs are necessary on site, Installation Methods and Standards must verify their specification before use.
1.5.4
Test Button
Marconi
Copyright- Refer to title page
Topic 4 Page 78
1PHA60131AAV Issue 04
At the start of each days activity all wrist straps and cords are to be checked using a wrist strap tester, see Figure 1-62 for typical tester. To check: Fit the wrist strap to wrist. Fit cord from wrist strap to the appropriate stud on the top of the tester. Press the test button. Any result other than a "pass" LED illuminating, reject the cord and strap and obtain replacements. A pass result will emit a continuous bleep.
1.5.5
Test Records
Results of the test detailed in 1.5.4 are to be recorded on the appropriate inspection record card supplied to site or a note to the same effect can be made in the site diary. It is important that all straps and cords are tested and that any operator who arrives on site with a personal strap identifies this fact in order that it will be included on the inspection record.
Marconi
Copyright- Refer to title page
Topic 4 Page 79
1PHA60131AAV Issue 04
Blank Page
Marconi
Copyright- Refer to title page
Topic 4 Page 80
1PHA60131AAV Issue 04
Chapter 2: Commissioning
2.1 2.1.1 Introduction Introduction and Scope
This procedure details the initial tasks that need to be performed when carrying out the commissioning of the OMS1664, OMS1654, OMS1644, and OMS1634 Multiplexer at Release 1.3 prior to the use of the Local Craft Terminal (LCT) and LCT Subsystem (LCTS) software for the commissioning and configuration process proper. For all information concerning the use of the LCT in this commissioning and configuring process, refer to TOPIC 5.
2.1.2
EMC Protection
An OMS 1664 sub-rack must have all card slot positions and all LTU positions fitted to maintain the EMC performance of the equipment. If any shelf slots do not have cards fitted then slot blanking plates should be fitted to maintain the equipment EMC protection.
2.1.3
2.1.4
Marconi
Copyright- Refer to title page
Topic 4 Page 81
1PHA60131AAV Issue 04
2.1.5
Test Equipment
1
For PDH Tributaries a Pattern Generator/Error Detector, with bit by bit comparison, capable of operating at 1.5, 2, 34, 45 and 140 Mbit/s. Suitable instruments are the Wandel & Goltermann PF4, the Hewlett Packard 3764A, the Hewlett Packard 37117B/C (with PDH Tx/Rx modules) or equivalent. For STM-1/4/16 Tributaries a SDH Analyser capable of simulating/analysing electrical or optical STM-1, STM-4, or STM-16 signals. Suitable instruments are the Anritsu MP1560A, the Hewlett Packard 37717B/C (with electrical and optical STM-1/4 modules) or equivalent.
The instruments in (1) and (2) should be capable of monitoring errors over a 24 hour period, with an associated printout of the result.
Anritsu MD1231A IP Network Analyser Or Or Or Or Agilent J2127A Transmission Test Set EXFO-8510 Packet Blazer DLI NIC GigE with 10/100 module Smartbits 200 with 10/100 SmartMetrics Card. 1G Ethernet Tributaries: Compatible Test equipment
Anritsu MD1231A IP Network Analyser Or Or Or Or Agilent J2127A Transmission Test Set EXFO-8510 Packet Blazer Smartbits 200 with Gigabit Ethernet Smart Card. DLI NIC GigE A digital voltmeter capable of operating in the range 0-60v with an accuracy of + 0.5%. A single mode optical power meter with a wide area sensor capable of operating in the range +10 to -50 dBm at 1300nm-1550nm, such as the Photodyne 2250XF. It should also have a suitable optical patch cord.
5 6
Marconi
Copyright- Refer to title page
Topic 4 Page 82
1PHA60131AAV Issue 04
The LCT should be a laptop PC with a Pentium/Celeron processor with a min. speed of 300 MHz, running the LCT application software. The PCs operating system should be either Win 2000 or Win XP. Communications to the shelf is via the serial port, using the LCT cable. The PCs serial port parameters will be automatically configured when the LCT is loaded. Software application releases are:Release 1.1 LCT & NE Software on CD-ROM code 03PHS00010AAG. Release 1.1 Rev 2A LCT & NE Software on CD-ROM code 03PHS00024AAF. Release 1.2 LCT & NE Software on CD-ROM code 03PHS00010ACR. Release 1.3 LCT & NE Software on CD-ROM code 03PHS00010ADJ.
8 9
Suitable quantity of optical test leads with LC connectors. A quantity of 5dB and 10dB Diamond attenuators terminated with LC optical connectors. The Site Engineer will select the actual value, 10dB being the preferred value. Suitable quantity of coaxial test leads, with type 1.0/2.3 coax connectors. For 10/100M Fast Ethernet Trib/LTU test: lead terminated at the electrical LTU with 16 x RJ45 Ports:- 17 off CAT5 Standard LAN UTP two pair cross-over cable, any length For Gigabit Ethernet Test: Analyser to Gig-E test cables ie 4 off optical leads, SC to LC optical connector conversion.
10 11
12
WARNING!
All instruments must conform to the appropriate safety regulations, bear a valid calibration label and a valid electrical safety label if 250 volts mains driven.
2.1.5.1
Marconi
Copyright- Refer to title page
Topic 4 Page 83
1PHA60131AAV Issue 04
2.1.5.2
Eth Data In (A) Eth Data In (B) Eth Data Out (A) a.c. to 0v a.c. to 0v Eth Data Out (B) a.c. to 0v a.c. to 0v
Figure 2-2: Two pair Cross-over UTP Fast Ethernet Test Cable
RJ45 End A 1 2 3 4 5 6 7 8
RJ45 End B 1 2 3 4 5 6 7 8
87654321
nc nc nc nc
nc nc nc nc
2.1.6
Marconi
Copyright- Refer to title page
Topic 4 Page 84
1PHA60131AAV Issue 04
Comms configuration details including LAPD settings. If available, fibre loss figures for the sub-network under test. Alarm configurations if different from defaults. Link Settings (if different from default) ALS Policy
Marconi
Copyright- Refer to title page
Topic 4 Page 85
1PHA60131AAV Issue 04
2.2 2.2.1
LTU
Pow er LTU A
PSU A n-19
Pow er LTU B
PSU B n-20
LT U n-1
LT U n-2
LT U n-3
LT U n-4
LT U n-5
LT U n-6
LT U n-7
LT U n-8
LT U n-9
LT U n-10
LT U LT U n-11 n-12
LT U LT U n-13 n-14
LT U LT U n-15 n-16
LT U n-17
LT U n-18
Switch A
Switch B
Line 1/
8 Trib 7 Trib
9 Trib
Card n-21
Card n-25
Card n-26
Trib
Card n-27
Card n-28
Card n-29
Card n-30
Card n-31
Card n-32
Card n-33
Card n-34
Card n-35
Card n-38
The above layout drawing shows the principle structure of the OMS1664 standard shelf. Although slots have been labelled as Line or Trib these are just highlighting a typical application. All slots are fully flexible and can be either Lines or Tribs. (up to STM-16). The Shelfs Core cards are those shaded. The bottom row offers 21 slots for Line Cards, Tributary (Trib) Cards, TDM Switch, Auxiliary Unit (Aux), and Communications Control Unit (CCU). The top row contains the Line Terminating Units (LTUs) of the corresponding Trib Cards and the system LTUs (Power Supply, Clock, TMN access) corresponding to Aux and CCU units.
Marconi
Copyright- Refer to title page
Topic 4 Page 86
1PHA60131AAV Issue 04
10 (2M#3)
Trib
Trib 11 (2M#4)
Trib 3 (2M#2)
Trib
Line 2/Trib
Line 3/
Line 4/
Trib
CCU A
Trib 6
Trib
Trib
Trib
Aux
2.2.1.1
Marconi
Copyright- Refer to title page
Topic 4 Page 87
1PHA60131AAV Issue 04
SLOT
DESCRIPTION Generic Card Type Variant Card Type 2 x STM-1/4 1 x STM-16 DATA Card 16 x 10/100M Fast Ethernet 2 x 1000M Gigabit Ethernet
LTU Slot For Card Type N/A N/A 4 N/A 5,6,7,8 5 5 5 5 5 N/A N/A 5 N/A 6 6 6 6 N/A N/A 6 N/A 7 7 7 7 N/A N/A 7 N/A N/A 8 8 8
25
PDH Card
SDH Card
DATA Card
26
Trib 4
6 x 34/45M 16 x STM-1/4 Flex SFP 8 x STM-1/4 Flex SFP 8 x STM-1 2 x STM-1/4 1 x STM-16
DATA Card
27
Trib 5
6 x 34/45M 16 x STM-1/4 Flex SFP 8 x STM-1/4 Flex SFP 8 x STM-1 2 x STM-1/4 1 x STM-16
DATA Card
28 29
Switch A Trib 6
Marconi
Copyright- Refer to title page
Topic 4 Page 88
1PHA60131AAV Issue 04
SLOT
DESCRIPTION Generic Card Type Variant Card Type 8 x STM-1 2 x STM-1/4 1 x STM-16 DATA Card 16 x 10/100M Fast Ethernet 2 x 1000M Gigabit Ethernet 8 N/A N/A 8 N/A N/A 9 9 9 9 N/A N/A 9 N/A 10 10 10 10 N/A N/A 10 N/A 11 11 11 11 N/A N/A 11 N/A
30 31
Switch B Trib 7
128 x 128 6 x 34/45M 16 x STM-1/4 Flex SFP 8 x STM-1/4 Flex SFP 8 x STM-1 2 x STM-1/4 1 x STM-16
DATA Card
32
Trib 8
6 x 34/45M 16 x STM-1/4 Flex SFP 8 x STM-1/4 Flex SFP 8 x STM-1 2 x STM-1/4 1 x STM-16
DATA Card
33
Trib 9
6 x 34/45M 16 x STM-1/4 Flex SFP 8 x STM-1/4 Flex SFP 8 x STM-1 2 x STM-1/4 1 x STM-16
DATA Card
34
PDH Card
9,10,11,12 12 12 12
SDH Card
Marconi
Copyright- Refer to title page
Topic 4 Page 89
1PHA60131AAV Issue 04
SLOT
DESCRIPTION Generic Card Type Variant Card Type 8 x STM-1/4 Flex SFP 8 x STM-1 2 x STM-1/4 1 x STM-16 DATA Card 16 x 10/100M Fast Ethernet 2 x 1000M Gigabit Ethernet
LTU Slot For Card Type 12 12 N/A N/A 12 N/A 13,14,15,16 13 13 13 13 13 N/A N/A 13 N/A N/A 14 14 14 14 N/A N/A 14 N/A 15 15 15 15 N/A N/A 15 N/A 16
35
PDH Card
SDH Card
DATA Card
36
PDH Card
SDH Card
DATA Card
37
Line 3 / Trib
6 x 34/45M 8 x STM-1 16 x STM-1/4 Flex SFP 8 x STM-1/4 Flex SFP 2 x STM-1/4 1 x STM-16
DATA Card
38
Line 4 / Trib
PDH Card
6 x 34/45M
Marconi
Copyright- Refer to title page
Topic 4 Page 90
1PHA60131AAV Issue 04
SLOT
DESCRIPTION Generic Card Type SDH Card Variant Card Type 8 x STM-1 16 x STM-1/4 Flex SFP 8 x STM-1/4 Flex SFP 2 x STM-1/4 1 x STM-16 DATA Card 16 x 10/100M Fast Ethernet 2 x 1000M Gigabit Ethernet
39 40
AUX CCUA
All All
CCU Comms 41 Reserved for future use Reserved for future use Reserved for future use N/A
Marconi
Copyright- Refer to title page
Topic 4 Page 91
1PHA60131AAV Issue 04
LTU UNITS:-
Marconi
Copyright- Refer to title page
Topic 4 Page 92
1PHA60131AAV Issue 04
2.2.1.2
LTU
Power LTU A
PSU A n-19
Alarms &
Au x
Power LTU B
PSU B n-20
LTU n-1
LTU n-10
LTU n-11
LTU n-17
LTU n-18
Switch B
Tri b
Card n-21
Card Card Card Card Card Card n-22 n-23 n-24 n-25 n-26 n-27
Card n-30
Card n-31
Trib
Card Card Card Aux CCUA CCUB n-36 n-37 n-38 n-39 n-40 n-41
The STM-16 Line/Trib Cards can be inserted into any of the 16 slots at the bottom row of the standard shelf. More than eight slots are available. But only 8 off (max) cards can be inserted in any of the 16 slots. The above drawing shows one example where Trib positions 21-24 & 35-38 are used, the limiting factor being the port number. i.e. The capacity of 128 x 128 STM-1 TDM Switch.
Marconi
Copyright- Refer to title page
Topic 4 Page 93
Aux
1PHA60131AAV Issue 04
CCU A
Switch A
Card # 11 1 Port
Card # 13 1 Port
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
Power LTU A
PSU A n-19
LTU # 9
Alarms &
LTU # 12
LTU # 15
LTU # 10
LTU # 11
LTU # 13
LTU # 14
LTU # 1
LTU # 2
LTU # 3
LTU # 4
LTU # 5
LTU # 6
LTU # 7
LTU # 8
LTU # 16
Au x
LTU
Power LTU B
PSU B n-20
LTU n-1
LTU n-10
LTU n-11
Switch A
Switch B
Ca rd #3 Trib
Card n-21
Card n-31
Card Card Card Aux CCUA CCUB n-36 n-37 n-38 n-39 n-40 n-41
The STM-1 Trib and LTU Cards contain hot plug-in modules or SFPs with two optical (LC/PC connectors) or electrical interfaces each. Mixed versions with any optical and electrical interfaces are possible. One LTU Card is available for each Trib Card using hot plug-in modules to extend the port capacity from 4 ports to 8 ports and for protection purposes. Ie Trib#1 + LTU#1 = 8 Ports. Or, an 8 port LTU Card is available for each Flexible STM-1 Trib Card using SFP modules to extend the port capacity from 8 ports to 16 ports and for protection purposes. Ie Trib#1 + LTU#1 = 16 Ports. The above drawing shows the corresponding LTUs in the top row of the standard shelf. The STM-1 Trib Cards can be inserted in any of the 16 slots at the bottom row of the standard shelf. There exists only one type of BASIC Trib. and BASIC LTU Cards (cards without modules). The different hot plug-in modules (different optical STM-1 modules and one electrical module) can be inserted in both cards. The limiting factor for the number of STM-1 ports in the standard shelf, is both the number of available slots and the capacity of the TDM Switch. (ie OMS1664 STM-16: 16 slots with 8 STM-1 ports each = 128 STM-1 ports.)
Marconi
Copyright- Refer to title page
Topic 4 Page 94
1PHA60131AAV Issue 04
CCU A
Aux
4 Ports
31 Ports
32 Ports
31 Ports
32 Ports
32 Ports
31 Ports
32 Ports
31 Ports
31 Ports
32 Ports
31 Ports
32 Ports
32 Ports
31 Ports
32 Ports
31 Ports
Power LTU A
PSU A n-19
LTU # 1 - 4
LTU # 1 - 3
LTU # 1 - 2
LTU # 1 - 1
LTU # 2 - 1
LTU # 2 - 2
LTU # 2 - 3
LTU # 2 - 4
LTU # 3 - 4
LTU # 3 - 3
LTU # 3 - 2
LTU # 3 - 1
LTU # 4 - 1
LTU # 4 - 2
LTU # 4 - 4
LTU # 4 - 3
Alarms &
Au x
LTU
Power LTU B
PSU B n-20
LTU n-1
LTU n-6
LTU n-7
LTU n-11
LTU n-15
Card n-21
Card n-28
Card n-29
Card n-30
Card Card Card Card Card Card Card Card Aux CCUA CCUB n-31 n-32 n-33 n-34 n-35 n-36 n-37 n-38 n-39 n-40 n-41
The 2Mbit/s Trib Cards can only be inserted in slots 24, 25, 34, or 35 of the bottom row. Whilst the Trib Protection card is inserted in slot 36. Up to 4 LTUs can be allocated to each Trib Card. The above drawing shows the Trib. Card vs. LTU positions. The 126 x 2Mbit/s signals are distributed to the four LTUs according to the following rule, (refer to the notation of the LTUs in above drawing):-
Marconi
Copyright- Refer to title page
Topic 4 Page 95
1PHA60131AAV Issue 04
CCU A
Aux
Switch A
Switch B
Marconi
Copyright- Refer to title page
Topic 4 Page 96
1PHA60131AAV Issue 04
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
4 Ports
Power LTU A
PSU A n-19
Alarms &
LTU # 12
LTU # 13
LTU # 10
LTU # 11
LTU # 14
LTU # 3
LTU # 4
LTU # 5
LTU # 6
LTU # 7
LTU # 8
LTU # 9
Au x
LTU
Power LTU B
PSU B n-20
LTU n-1
LTU n-11
LTU n-12
LTU n-17
LTU n-18
Line Card # 1
Line Card # 2
Line Card # 1
Line Card # 1
Card n-23
Card Card Card Card Card n-24 n-25 n-26 n-27 n-28
Card n-29
Card n-30
Card Card Card Card Card n-34 n-35 n-36 n-37 n-38
The above shelf drawing shows a configuration with STM-1 Trib/LTU cards & four Line cards. Useable STM-1 Ports with Different Line Functionality:-
STM-16
2) 2) 2)
1)
Available slots for Trib and LTU cards Capacity of 128 x 128 STM-1 TDM Switch
2)
Note: In case of STM-16 the number of usable STM-1 ports is higher, because STM16 protection doesnt allocate any switch capacity.
Marconi
Copyright- Refer to title page
Topic 4 Page 97
Aux
Tri b
1PHA60131AAV Issue 04
CCU A
Switch A
Switch B
Card # 14 4 Ports
31 Ports
32 Ports
31 Ports
32 Ports
32 Ports
31 Ports
32 Ports
31 Ports
31 Ports
32 Ports
31 Ports
32 Ports
32 Ports
31 Ports
32 Ports
31 Ports
Power LTU A
PSU A n-19
LTU # 1 - 4
LTU # 1 - 3
LTU # 1 - 2
LTU # 1 - 1
LTU # 2 - 1
LTU # 2 - 2
LTU # 2 - 3
LTU # 2 - 4
LTU # 3 - 4
LTU # 3 - 3
LTU # 3 - 2
LTU # 3 - 1
LTU # 4 - 1
LTU # 4 - 2
LTU # 4 - 4
LTU # 4 - 3
Alarms &
Au x
LTU
Power LTU B
PSU B n-20
LTU n-1
LTU n-6
LTU n-7
LTU n-11
LTU n-15
Line Card # 1
Line Card # 2
Line Card # 3
Line Card # 4
Card n-21
Card n-28
Card n-29
Card n-30
Card Card Card Card Card Card Card Card Aux CCUA CCUB n-31 n-32 n-33 n-34 n-35 n-36 n-37 n-38 n-39 n-40 n-41
With line functionality, the number of available 2Mbits Trib Ports of OMS1664 is not reduced. The above configuration shows the example of an OMS1664 standard shelf with 4 x Line Cards, 4 x Tribs. and 16 x LTU Cards. The 2Mbit/s Trib. Cards can only be inserted in slots ,24,25, 34,35 of the bottom row. Whilst the Trib Protection card is inserted in slot 16. Up to 4 LTUs can be allocated to each Trib. Card. The above drawing shows the Trib. Card vs. LTU positions. The 126 x 2Mbit/s signals are distributed to the four LTUs according to the following rule, (refer to the notation of the LTUs in above drawing):-
Marconi
Copyright- Refer to title page
Topic 4 Page 98
1PHA60131AAV Issue 04
CCU A
Aux
Switch A
Switch B
Marconi
Copyright- Refer to title page
Topic 4 Page 99
1PHA60131AAV Issue 04
2.2.2
Power LTU A
PSU A n-19
Au Alarms &
LTU
Power LTU B
PSU B n-20
LTU n-1
LTU n-4
LTU n-5
LTU n-6
LTU n-7
LTU n-10
Trib 3 (2M#2)
Line 1/Trib
Line 2/Trib
Trib 1
Card n-21
Card Card Card Card Card Card Card n-22 n-23 n-24 n-25 n-26 n-27 n-28
Trib
Card n-29
Card Card Card Card Card Card Card Aux CCUA CCUB n-32 n-33 n-34 n-35 n-36 n-37 n-38 n-39 n-40 n-41
The Shelfs core cards are those shaded. The bottom row offers slots for Tributary (Trib) Cards, Core/TDM Switch, Auxiliary Unit (Aux), and Communications Control Unit (CCU). The top row contains the Line Terminating Units (LTUs) of the corresponding Trib Cards and the system LTUs (Power Supply, Clock, TMN access) corresponding to Aux and CCU units. The TDM bandwidth supported on the Core card is limited by its switch functionality. In the case of STM 4/16 Core card, the limitation is 48 x STM-1. This is distributed as 8 x STM-1 to 4 slots and 4 x STM-1 to 4 slots. Lines 1,2,3,4 and Tribs 4,6,7,9 have no TDM bandwidth allocation, & are NOT supported.
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
Aux
SWITCH/CORE B
SWITCH/CORE A
Trib 11 (2M#4)
Trib 10 (2M#3)
Line 3/Trib
Line 4/Trib
CCU A
Trib 5
Trib 6
Trib 7
Trib 8
Trib 9
2.2.2.1
31 Ports
32 Ports
31 Ports
32 Ports
32 Ports
31 Ports
32 Ports
31 Ports
31 Ports
32 Ports
31 Ports
32 Ports
32 Ports
31 Ports
32 Ports
31 Ports
Power LTU A
PSU A n-19
LTU # 1 - 4
LTU # 1 - 3
LTU # 1 - 2
LTU # 1 - 1
LTU # 2 - 1
LTU # 2 - 2
LTU # 2 - 3
LTU # 2 - 4
LTU # 3 - 4
LTU # 3 - 3
LTU # 3 - 2
LTU # 3 - 1
LTU # 4 - 1
LTU # 4 - 2
LTU # 4 - 4
LTU # 4 - 3
Alarms &
Au x
LTU
Power LTU B
PSU B n-20
LTU n-1
LTU n-6
LTU n-7
LTU n-11
LTU n-15
Card n-21
Card n-28
Card n-29
Card n-30
Card Card Card Card Card Card Card Card Aux CCUA CCUB n-31 n-32 n-33 n-34 n-35 n-36 n-37 n-38 n-39 n-40 n-41
The above configuration shows the example of an OMS1634 shelf with 2 x Core Cards which include Line functionality, & 4 x 2Mbit/s Tribs. with 16 x LTU Cards. The 2 Mbit/s Trib. Cards can only be inserted in slots 4, 5, 14, or 15, of the bottom row. Whilst the Trib. Protection card is inserted in slot 16. Up to 4 LTUs can be allocated to each Trib. Card. The above drawing shows the Trib. Card vs. LTU positions. The 504 x 2 Mbit/s signals are distributed to the LTUs according to the following table:-
LTU 1 2
Trib 2 3 4 5 6 Trib 3 7 8 64-95 96-126 + monitor 33-63 + monitor 1-32 1-32 33-63 + monitor
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
SWITCH/CORE A
SWITCH/CORE B
CCU A
Aux
2.2.2.2
LINE/TRIB UNITS:ALLOWABLE CARD TYPES SLOT DESCRIPTION Generic Card Type 21 22 23 Line 1 / Trib Line 2 / Trib Trib 1 Not Supported Not Supported PDH Card SDH Card 6 x 34/45M 8 x STM-1/4 Flex SFP 8 x STM-1 2 x STM-1/4 DATA Card 16 x 10/100M Fast Ethernet 2 x 1000M Gigabit Ethernet 24 Trib 2 (or 2M#1) PDH Card 126 x 1.5/2M 32 x 1.5/2M 6 x 34/45M SDH Card 8 x STM-1/4 Flex SFP 8 x STM-1 2 x STM-1/4 DATA Card 16 x 10/100M Fast Ethernet 2 x 1000M Gigabit Ethernet 25 Trib 3 (or 2M#2) PDH Card 126 x 1.5/2M 32 x 1.5/2M 6 x 34/45M SDH Card 8 x STM-1/4 Flex SFP 8 x STM-1 2 x STM-1/4 Variant Card Type LTU Slot For Card Type N/A N/A 3 3 3 N/A 3 N/A 1,2,3,4 4 4 4 4 N/A 4 N/A 5,6,7,8 5 5 5 5 N/A
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
SLOT
DESCRIPTION Generic Card Type DATA Card Variant Card Type 16 x 10/100M Fast Ethernet 2 x 1000M Gigabit Ethernet 5 N/A N/A 6 x 34/45M 8 x STM-1/4 Flex SFP 8 x STM-1 2 x STM-1/4 DATA Card 16 x 10/100M Fast Ethernet 2 x 1000M Gigabit Ethernet 7 7 7 N/A 7 N/A N/A N/A 64 x 64 N/A N/A 6 x 34/45M 8 x STM-1/4 Flex SFP 8 x STM-1 2 x STM-1/4 DATA Card 16 x 10/100M Fast Ethernet 2 x 1000M Gigabit Ethernet 10 10 10 N/A 10 N/A N/A 126 x 1.5/2M 32 x 1.5/2M 6 x 34/45M SDH Card 8 x STM-1/4 Flex SFP 8 x STM-1 2 x STM-1/4 DATA Card 16 x 10/100M Fast Ethernet 2 x 1000M Gigabit Ethernet
26 27
Trib 4 Trib 5
28 29 30 31 32
CORE Card Not Supported CORE Card Not Supported PDH Card SDH Card
64 x 64
33 34
35
PDH Card
SDH Card
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
SLOT
DESCRIPTION Generic Card Type DATA Card Variant Card Type 16 x 10/100M Fast Ethernet 2 x 1000M Gigabit Ethernet
LTU Slot For Card Type 13 N/A N/A 14 14 14 N/A 14 N/A N/A N/A
36
PDH Card
SDH Card
DATA Card
37 38 39 40
Not Supported Not Supported AUX/EOW Card CCU MC All CCU Comms All
17 N/A
41
N/A
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
LTU UNITS:ALLOWABLE CARD TYPES SLOT 1-16 1-16 LTU DESCRIPTION Generic Card Type 1.5M LTU 32 x Bal 2M LTU 32 x Bal 2M LTU 32 x Unbal 1-16 1-16 1-16 1-16 34/45M LTU 6 x UnBal STM-1 LTU 8 x SFP STM-1 LTU 2 x Opt Module Protection LTU (Type) 1 34/45M 8 x STM-1/4 Flex SFP 8 x STM-1 6 x 34/45M 8 x STM-1 8 x STM-1/4 Flex SFP 1-16 16 x 10/100M Fast Ethernet LTU 10/100M Electrical (RJ45) 10/100M Optical (SFP, LC) 17 18 19 20 Alarms & Aux LTU Management & Sync LTU Power LTU Power LTU AUX/EOW Mgt/Sync LTU Power A Power B All All All All All All All All All All All All 1.5M 2M All All Variant Card Type
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
2.3
2.3.1.1
Trib 3 - 2M Protection
LTU
n-19
n-1
n-2
n-3
n-4
n-5
n-6
n-7
n-8
n-9
n-10
n-11
n-12 n-13
n-14
n-15
n-16
n-17
n-18
n-20
Fan Tray
Up to 4 LTUs can be allocated to the 2M Tributary Card, see above drawing for LTU positions. The 126 x 2 Mbit/s signals are distributed to the four LTUs according to the following table:-
LTU 1 2
2M Card Protection:A maximum of 126 x 2M can be supported on the OMS1654, using Trib 4 (slot 12). 2M card protection is supported by using 2M trib in Trib 3 (slot 11).
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
Power LTU B
Aux Card
Alarms &
Au
Switch B
Switch A
Line 1
Line 2
Line 3
Line 4
Trib 1
Trib 2
CCU
Power LTU A
2.3.1.2
LTU
n-19
Trib 1 LTU
Trib 2 LTU
Trib 3 LTU
Trib 4 LTU
n-1
n-2
n-3
n-4
n-5
n-6
n-7
n-8
n-9
n-10
n-11
n-12 n-13
n-14
n-15
n-16
n-17
n-18
n-20
Fan Tray
The STM-1 Trib and LTU Cards contain hot plug-in modules or SFPs with two optical (LC/PC connectors) or electrical interfaces each. Mixed versions with any optical and electrical interfaces are possible. One LTU Card is available for each Trib Card using hot plug-in modules to extend the port capacity from 4 ports to 8 ports and for protection purposes. Ie Trib#1 + LTU#1 = 8 Ports. Or, an 8 port LTU Card is available for each Flexible STM-1 Trib Card using SFP modules to extend the port capacity from 8 ports to 16 ports and for protection purposes. Ie Trib#1 + LTU#1 = 16 Ports. There is one type of BASIC Trib. and BASIC LTU Cards (cards without modules). The different hot plug-in modules (different optical STM-1 modules and one electrical module) can be inserted in either cards. Non-PDH Trib Protection:All 4 Tribs have an associated LTU. Flexible 1:N can be supported. Protection options are: One group of 1:3 or 1:2, Two groups of 1:1. Data Card Protection:Unit protection for the 2x1000M (EPL-1000) Gigabit Ethernet & 16x10/100M (EPL100) Fast Ethernet card is NOT supported.
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
Power LTU B
Aux Card
Alarms &
Au
Switch A
Switch B
Line 1
Line 2
Line 3
CCU
Line 4
Power LTU A
2.3.1.3
DESCRIPTION Generic Card Type AUX/EOW Card CCU MC CCU Comms All All All 16 x STM-1/4 Flex SFP 8 x STM-1/4 Flex SFP 8 x STM-1 Variant Card Type
Line 1
SDH Card
Line 2
2 x STM-1/4 1 x STM-16 DATA Card 2 x 1000M Gigabit Ethernet 128 x 128 16 x STM-1/4 Flex SFP 8 x STM-1/4 Flex SFP 8 x STM-1
5 6 7
Line 4
2 x STM-1/4 1 x STM-16 DATA Card 2 x 1000M Gigabit Ethernet 6 x 34/45M 16 x STM-1/4 Flex SFP 8 x STM-1/4 Flex SFP 8 x STM-1
Trib 1
10
Trib 2
2 x STM-1/4 1 x STM-16 DATA Card 16 x 10/100M Fast Ethernet 2 x 1000M Gigabit Ethernet
11
PDH Card
SDH Card
DATA Card
12
Trib 4
PDH Card
126 x 1.5/2M
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
SLOT
DESCRIPTION Generic Card Type Variant Card Type 32 x 1.5/2M 6 x 34/45M SDH Card 16 x STM-1/4 Flex SFP 8 x STM-1/4 Flex SFP 8 x STM-1 2 x STM-1/4 1 x STM-16 DATA Card 16 x 10/100M Fast Ethernet 2 x 1000M Gigabit Ethernet
ALLOWABLE CARD TYPES LTU DESCRIPTION Generic Card Type 1.5M LTU 32 x Bal 2M LTU 32 x Bal 2M LTU 32 x Unbal 1.5M 2M All All Variant Card Type
13-16 13-16
All All
13-16 14-16
All All All All All All All All All All All
13-16
17 18 19 20
Alarms & Aux LTU Management & Sync LTU Power LTU Power LTU
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
2.4
2.4.1
n-1
n-2
n-3
n-4
n-5
n-6
n-7
n-8
n-9
n-10
n-11
n-12 n-13
n-14
n-15
n-16
n-17
n-18
Fan Tray
Up to 4 LTUs can be allocated to the 2M Tributary Card, see above drawing for LTU positions. The 126 x 2 Mbit/s signals are distributed to the four LTUs according to the following table:LTU 1 2 Trib 4 3 4 33-63 + monitor 1-32 Associated 2Mbit/s Card Port Numbers 96-126 + monitor 64-95
2M Card Protection:A maximum of 126 x 2M can be supported on the OMS1644, using Trib 4 (slot 12). 2M card protection is supported by using 2M trib in Trib 3 (slot 11).
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
Power LTU B
Aux Card
Alarms &
Au
Trib 1
Trib 2
Trib 3 - 2M Protection
Switch/Core A
Line 1
Line 2
Switch/Core B
Line 3
Line 4
CCU
LTU
2.4.1.1
SLOT 1 2 AUX CCU
All All All N/A N/A Switch 64 x 64 8 x STM-1/4 Flex SFP 8 x STM-1 2 x STM-1/4
3 4 5 6 7 8
DATA Card
9 10
Trib 1 Trib 2
DATA Card
11
PDH Card
SDH Card
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
SLOT
DESCRIPTION
12
Trib 4
PDH Card
SDH Card
DATA Card
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
ALLOWABLE CARD TYPES LTU DESCRIPTION Generic Card Type 1.5M LTU 32 x Bal 2M LTU 32 x Bal 2M LTU 32 x Unbal 1.5M 2M All All Variant Card Type
34/45M LTU 6 x UnBal STM-1 LTU 8 x SFP STM-1 LTU 4 x Opt Protection LTU (Type) 1
34/45M 8 x STM-1/4 Flex SFP 8 x STM-1 6 x 34/45M 8 x STM-1 16 x STM-1/4 Flex SFP 8 x STM-1/4 Flex SFP
All All All All All All All All All All All All All
13-16
17 18 19 20
Alarms & Aux LTU Management & Sync LTU Power LTU Power LTU
2.5
Preliminary Checks
WARNING!
If specific authority is required power is not to be applied until instructed
2.5.1
2.5.1.1
Inspection
Visual Inspection
Visually inspect all units, both working and spare, for obvious evidence of mishandling during transportation or installation. Do not remove unit lids or covers. Visually inspect the backplane connector pins, to ensure none are bent or broken.
2.5.1.2
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
2.5.2 2.5.3
ALS Link Settings Summary of all Card/Port ALS Links (inc. Default Settings)
Below is a summary of all the ALS card and port control link options including the default settings that shall be adopted on the Slide in Units. These shall however be tailored to suit each customer during the installation and commissioning phase. In order to reduce implementation times the default settings shall be achieved by not requiring a link to be fitted.
2.5.3.1
2.5.3.2
2.5.3.3
2.5.3.4
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
working, the operator MUST configure different transmitted section trace identifier values at both ends of the section. Failure to do so will result in permanent shutdown and consequent loss of traffic. There is one ALS Single-Fibre Working Control Link per port, any change to the setting necessitates removing the card from the subrack. The two possible link settings are:Not Fitted Fitted Dual-Fibre working (uni-directional) Single-Fibre working (bi-directional)
2.5.4
2.5.4.1
No default is offered on the commissioning screen (the field is blank), forcing the operator to select an option from the drop-down list before commissioning can be completed.
2.5.4.2
2.5.4.3
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
The purpose of having an NE ALS Operation Default is to allow the operator to define the default. All cards in the NE will then behave consistently. This is configured by the operator via LCT when the NE is commissioned. It cannot be changed thereafter without de-commissioning the NE. The user configurable options are:ALS Enabled ALS Disabled ALS used ALS not used
No default is offered on the commissioning screen (the field is blank), forcing the operator to select an option from the drop-down list before commissioning can be completed.
2.5.4.4
ALS Operation
If enabled by the Card ALS Control Link, the operator is able to configure via NM/LCT whether ALS should operate or not. When a card is added to the subrack logical configuration, its default NM/LCT Control will be the same as the NE ALS Operation Default which was configured when the NE was commissioned. For equipment which does not yet support NE ALS Operation Default configuration at commissioning, when a card is added to the subrack logical configuration, its default NM/LCT Control will be ALS inactive. The ALS operation can be configured by the operator via NM/LCT at any time. The user configurable options are:ALS Enabled ALS Disabled ALS used ALS not used
2.5.4.5
2.5.4.6
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
broken fibre end to exceed safety limits. This feature provides a means to stagger the restart pulses. Configuration is possible for each individual optical port. The same delay value is used for the delay between Manual (pushbutton), Remote and Automatic restart pulses. The ALS Restart Pulse Interval can be configured by the operator via NM/LCT at any time. The user configurable options are:100 to 300 seconds (default 100) In increments of 1 second
2.5.4.7
If the configuration is set to Used, then ALS will shut-down the laser if this Constantly Changing Trace Identifier condition is detected. The reasoning behind this is that the signal could be a heavily attenuated reflection from a broken fibre-end.
2.5.4.8
2.5.4.9
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
CARD ALS POLICY (NM/LCT CONFIGURATION) (PER CARD) HARDWARE ENABLED NM/LCT CONTROL
AS SHIPPED
DEFAULT
ALS ACTIVE AUTO RESTARTS ENABLED DISABLED REMOTE MANUAL RESTARTS (R1.3 onwards) ENABLED DISABLED RESTART PULSE LENGTH RESTART PULSE INTERVAL DUALFIBRE WORKING SINGLEFIBRE WORKING ALS INACTIVE
AS SHIPPED
NOT FITTED
FITTED
DEFAULT = 2 SECS
AS SHIPPED
NOT FITTED
AS SHIPPED
FITTED
FITTED
NOT FITTED
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
Per Card (S/w per port) S/W only, per port S/W only, per card H/W only, per port. H/W only, per card H/W only, per card
No link fitted 2 sec Disabled No link fitted No link fitted No link fitted
ALS ON (no S/W control) Restart pulse 2 sec Enhanced SFW not used SFW disabled No Micro Restarts allowed Automatic Restarts enabled
RESTARDIS
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
Yes
No
No
Yes
No
If the "NE ALS Preference Default" is "H/W Enabled", then the "NM/LCT ALS Operation Default" can be set to either "Enabled" or "Disabled" (it doesn't matter which), but a default must be set before the commissioning screen can be closed.
Yes Set "NM/LCT ALS Operation Default" to "Disabled" Set "NM/LCT ALS Operation Default" to "Enabled"
End
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
Yes
No Might you ever want to choose which ports have ALS enabled ? Yes
No
Yes
No
End
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
2.5.5
Figure 2-14: ALS link settings for an STM-1 Trib/Traffic card (Sketch)
PIN A1
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
Figure 2-15: ALS Link Settings for an STM-1 Trib/Traffic card (Photo)
ALS Links
1 3 5 7 9
2 4 6 8
Pin 1-2
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
2.5.6
Front fascia
Cards with ENU 007 000 000 have X2 link near bottom edge of card. Cards with ENU 007 000 000 or greater have X2 link near
Bot tom
2.5.7
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
- BIDIEN2
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
Figure 2-17: ALS link settings for an STM-4 Trib/Traffic card (Photograph)
ALS
Pin 1-2
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
2.5.8
2.5.9
ENALSDIS: RESTARDIS:
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
2.5.10
Flexible STM-1/4 Traffic Card (SFP Based) 8 Port and 16 Port Version
Note: The Card and LTU also has BIDIENA links for use when working in Single Fibre Working mode. Link Header ALS_LNK
- STM-1 Port 1 - STM-1 Port 2 - STM-1 Port 3 - STM-1 Port 4 - STM-1 Port 5 - STM-1 Port 6 - STM-1 Port 7 - STM-1 Port 8
Pin 1-2 (also STM-4 port on 8P and 16P versions ) Pin 3-4 Pin 5-6 (also STM-4 port on 16P version ) Pin 7-8 Pin 9-10 (also STM-4 port on 8P and 16P versions) Pin 11-12 Pin 13-14 (also STM-4 port on 16P version ) Pin 15-16
Note: Pin 1 of each link header is marked as indicated by the lines below.
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
2.5.11
- STM-1 Port 1 - STM-1 Port 2 - STM-1 Port 3 - STM-1 Port 4 - STM-1 Port 5 - STM-1 Port 6 - STM-1 Port 7 - STM-1 Port 8
Pin 1-2 Pin 3-4 Pin 5-6 Pin 7-8 Pin 9-10 Pin 11-12 Pin 13-14 Pin 15-16
Note: Pin 1 of the link header is marked as indicated by the line below.
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
B I D
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
2.5.12
S W 10
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
2.5.13
2.5.14
Bw7R
-S -S -S b unused Za(B) Za(LE) +S +S +S a el unused Za(A) GND
Telecom Italia
-V Service -V Service -V Service unused INT NURG EXT NURG WARNING (IND) +V Service +V Service +V Service SUM REM INT URG EXT URG GND
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
Figure 2-23: Link settings for the Alarms & Aux LTU
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
2.5.15
SETTINGS CONNECTOR
JTAG CONNECTOR
SETTINGS CONNECTOR
JTAG CONNECTOR
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
2.5.16
Card Installation
Cards should be inserted into correct shelf positions. Card complement will vary with each contract. Refer to Section 2 for examples of the Shelf layouts.
2.5.17
2.5.17.1
DC Powered Rack
WARNING!
This equipment is supplied with more than one DC power feed. To isolate, both feeds must be disconnected. Given the wide tolerance of the possible primary supply voltage. Which can vary i.e. (40.5V to 75V operating range). The total supply current for any rack will depend on the input voltage:
Check that the End Of Suite fuses at the Distribution Board, the fuses/circuit breakers of the OMS1664 shelfs Power Supplies, & Fan Tray fuse/circuit breaker, are removed or switched OFF (as appropriate). Ensure that the shelf Power LTU connectors are disconnected from the shelf, & confirm that the alarm ribbon connectors to the external alarm scheme (if provided) are inserted into the correct shelf connector. Confirm that the End Of Suite fuses at the Distribution Board, the fuses/circuit breakers of the OMS1664 shelfs Power Supplies, & the Fan Tray fuse/circuit breaker, are correctly rated. If in any doubt the Engineer should contact Marconi support. Confirm that fuses/circuit breakers labelling is correct. Check that the two shelf power connectors are wired correctly, refer to the Power LTU connector drawing below:At the Distribution Board, insert the End of Suite fuse for the SMA power Supply 1 and measure the voltage present at the racktop. This should lie in the range -40.5 75V dc, nominal 48V dc.
4 5 6
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
A1
A2
A3
Fit the subrack power connector to Power LTU PSA, insert the Racktop fuse or turn ON the Circuit Breaker for Power Supply 1 and confirm that, on the Power LTU PSA in slot 19, the Green LED is lit.
Note: The Comms/Controller card has a dedicated PSU powered directly from the subrack power supply. At this point the card will begin its initial power up, indicated by the AMBER led flashing.
8 9
Repeat (5) & (7) for Power Supply 2/Power LTU PSB in slot 20. If an external alarm scheme is connected, confirm that the appropriate Power Fail alarms are generated. It should not be possible to acknowledge these alarms
2.5.17.2
Application of Power
Note: The shelf is powered from duplicated power connectors from a nominal 48v dc feed. Note: The supplies must NOT be switched OFF while the AMBER LED on the CCU card is flashing, as this may corrupt the Controllers EEPROM data. Note: The two supplies MUST NOT be switched between the On/Off states in rapid succession as such action can cause a Laser Trip condition on the Optical Cards 1 Whilst the CCU Card is executing its start up sequence, the AMBER LED will flash. This will take up to 4 minutes, when completed it will then remain lit, this will indicate that the Comms/Controller has finished its start up sequence. Any shelf alarms present at this stage should be disregarded. Immediately after power-up, the sub-rack cards will undergo an initialisation period controlled by the CCU (Comms/Controller) card. During this period, it is normal for a number of the card LEDs to flash on and off. This process stops when the CCU (Comms/Controller) card has completed its initialisation cycle. Topic 4 Page 136 1PHA60131AAV Issue 04
2 3
Marconi
Copyright- Refer to title page
Turn ON the Fan Tray circuit breaker or fit its rack top fuse (as appropriate). Check that the fan tray is operating correctly.
2.6
To install the LCT, first insert the CD-ROM into the CD drive. The set-up instructions are given below: Invoke Windows Select Windows Explorer and view the CD drive. Select the Local Craft Terminal (LCT) directory, and execute setup.exe. The user is then guided through the installation process.
The LCT is launchable by one of the following methods: Double-clicking the icon on the Windows desktop. Selecting Programs > Marconi Local Craft Terminal from the Start Menu
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04
Blank Page
Marconi
Copyright- Refer to title page
1PHA60131AAV Issue 04