Beruflich Dokumente
Kultur Dokumente
Overview
Testing Equipment History of VLF Testing & Procedures Project Overview Test Results Failed Splice Analysis
Testing Equipment
Test Equipment
Second Generation Sinusoidal Waveform 0.1 Hz maximum 60 kV DC / 43kV AC Bluetooth communication for Tan Delta Partial Discharge Add On
Only 1 PD set
Management became reluctant to test any in service cable Explained that the test was finding existing weak spots Management was not convinced
10
When the entire circuit is new VLF (sinusoidal) with Tan Delta analysis 0.1 Hz standard Test voltages from IEEE 400.2 Test duration = 60 minutes
11
Project Overview
Project Overview
New 23kV Sub-transmission Cable 1000kcMil copper, 260 mils EPR, JCN (18#14 round wire), LLDPE jacket 2 cables per phase due to loading Spliced to existing cable after river crossing 1000kcMil copper, 260 mils XLPE, Jacketed, drain wire shield, LLDPE jacket New cable from supply sub across river ~ 2200 Old Cable from far side of river to next substation ~ 2500
16
River Crossing
New Manholes
TD 6.5
20
TD 6.5
TD 11
22
Circuit 2339
The test crew did not report the problem with B phase of the 2339X cable to the cable crew or project management In fact, they reported the cable as being ready for service Accustomed to DC testing if the set doesnt trip out, cable is OK However, they did report the set as tripping out at least one time Heat shrink end seals removed and splices to old cable installed in MH 597 Old cable length to substation ~ 2500 Total cable length now ~ 4700
23
24
25
Tan Delta
Tan Delta Ratio of IR to IC IR (leakage current) should be <<< than IC IC (capacitive current) varies according to cable
Length Test Voltage Remains stable at a given test voltage
11 46 11 12 24 12
28
31
32
33
Splice in this manhole (592) was removed and replaced B phase acceptance test repeated
34
TD 11.5
Failure Analysis
The failed splice was analyzed to determine the root cause Cold Shrink, 23kV, Separate Outer Jacket Tinned copper, water stopped connector Bonding of Concentric Neutral per company standards 2 - #4 solid, tinned copper ground leads brought out of splice Contractor removed outer jacket and splice body from cable
37
Failure Analysis
Splice Body removed from cable Left side cable Manufacturer A, Right side Manufacturer B
38
Failure Analysis
Unable to determine the exact splice body alignment on the cable Since splice body was removed prior to receiving the splice Alignment is critical insulation interface must be fully engaged with cable insulation However, marks remained where the splice body was positioned Alignment was OK There was visible tracking on the interface of side A There were matching tracks on that side of the splice body
39
Failure Analysis
40
Failure Analysis
Cable and splice body interior prior to cleaning Leakage tracks are visible Insulation was sanded
41
Failure Analysis
Failure believed to be due to contamination on interface Dirt from cable jacket where splice body was parked? Improper cleaning? Other source?
42
Questions?