Beruflich Dokumente
Kultur Dokumente
A critical aspect of project failure due to poor logistic & SCM is construction delay,
which often results in construction claims. Another survey in UK shows that 52% of UK
construction projects end up with claims of some type [2]. Statistical figures show that
main contractors are purchasing more labour and material than previously. As a
consequence, main contractors become more and more reliant on other actors in the
construction supply chain (e.g., suppliers and subcontractors). Lim’s study on
construction productivity in Singapore shows that the industry is perceived as a low-
productivity sector [3]. Personally, my own investigation on time waste reveals that
site work-force spends a considerable amount of time waiting for approval or for
materials to arrive on site. The amount of work of non-value adding activities was
found to be as high as 40% of the overall project duration from inception to
completion.
• In construction & commissioning, skilled craftsmen are often using their skills
for less than 50% of their time on site. Amongst the non-skilled tasks they are
involved in are moving tools/equipments around and finding/sourcing items
around yard. Other sectors use special equipments and designated trained
teams to deal with material handling activities.
• Construction materials are often stored on site for long periods of time and
have to be moved to other parts of the site when they are eventually needed.
Higher man-hours and cost spent in preservation of these materials. Retailers
and those under other industries are continually trying to reduce inventories
and at least ensure they are held in the most appropriate location. Effort goes
into delivering the right quantities at the right time.
• There is little formal training in logistics and yet there are a large number of
tasks that fall within a logistics umbrella.
An oil & gas EPC project can be a complex one-of-a-kind product development,
made up of a large number of interconnected sub-systems and components, requiring
considerable human efforts and financial commitment. The EPC activities are time
phased according to specified precedence and resource requirements and constraints.
Engineering/Design (E) is the process by which the needs, wishes, and desires of
an owner or Oil & Gas operator defined, quantified, qualified into clear requirements
which will be communicated to the builders/contractors. This phase has the highest
level influence to make key decision which will be made for planning. These decisions
will lead to the commitment of a large sum of the funds and other resources necessary
for the successful implementation and completion of the project which will be
accomplished through a series of steps to include conceptual design, preliminary
design and detail design [4]. Most of the work involved in an O&G projects is carried
out by specialists in the design process, usually employed as engineering contractor to
a main contractor. It is at this design stage that the involvement of specialist can be
most beneficial.
2
traditional processes and attitudes will have to be abandoned with a new culture
focused on primary objectives and ‘worth’ of the project to client. Strategies that may
be adopted to facilitate supply management throughout design and construction
phases of a project include the strategies where the client can participate or strategies
facilitating collaboration.
I propose the suitable procurement strategy, which will enable client participation
in managing the supply chain; where the client or his project manager employs trade
contractors direct. This approach will, however require constant participation by the
client who may not wish or be technically competent enough to have that level of
involvement. In such a case that employment of a client’s project manager is vital.
Experienced clients or operators who can lever advantage through repeat business so
as to offset the extra fees incurred therefore mainly adopt this strategy.
The engineering and design phase is closely followed by the procurement (P)
phase. A contractor begins to procure project equipment and
construction/commissioning materials upon receipts of engineering drawings,
specifications and other relevant documents. The main procurement/logistics activities
include sourcing, purchasing, contracting, and on-site materials management.
Since the mid 1990, EPC contractors have adopted different strategies to procure
sub-contractors. Whilst regular, experience and informed EPC contractor have begun
to adopt different strategies, there is a little evidence to show that the numerically
dominant inexperienced irregular purchaser have done so. By far the dominant
strategy adopted is bid-build with the lowest bidder winning the work.
Adopting ‘low bid win’ strategies results in a number of well documented and
inevitable outcomes, particularly where the design is already established. They are;
• Construction & Commissioning process that are geared to lowest cost rather
than to ‘right first time’ or to ‘best value’.
Many of the weakness associated with such an approach include late completion,
budgets overspend and mechanical completion punches/defects which can usually be
attributed to the rigid adoption of the ‘low bid’ strategy. There is a tendency for
construction professionals and in particular contractors to focus on cost and it is this
focus which underpins and dominates the strategies adopted in managing the existing
supply chain.
Whilst cost is not irrelevant, most clients usually focus upon the value of their
project in terms of the business case for it. This value or ‘worth’ which will form the
key success factor for the project. Alternatives do exist but require cultural change
3
within the oil & gas project sectors and its professions and critically in relation to the
advice offered, particularly to inexperienced clients.
In the oil & gas projects, larger firms usually use matrix organization for the
management of projects. Matrix organization remains a complex structure. Authority
and responsibility for project task accomplishment are shared between the project
manager and the functional manager. There is a mutual commitment in fulfilling
project requirements. But, the balance of power between the project and the
functional organization must be clear defined initially and closely monitored
afterwards. Depending on the strength and weakness of the individual managers, the
power and influence can shift to detriment of the overall company organization. From
the perspective of individual worker, there is often a split in the chain of command for
reporting purposes. The individual is sometimes “pulled” between project boss and the
functional boss.
There is no integrated team between end-user/operators, client, EPC contractor,
and sub-contractor/suppliers. Logistics within these kinds of projects will not be
adequately addressed until the teams’ works in more integrated way, with all parts of
the supply chain, including specialist contractors and key manufacturers / suppliers,
involved at the outset of projects. In terms of improving logistics, a more integrated
approach will help break down the barriers that the current contractual relationships
impose and help encourage greater cost transparency on projects.
It brings together the design and construction activities, with maintenance
considered as well, whether or not to integrated project team will be responsible for
the ongoing maintenance of the facility; it involves valued input from all parties in the
supply team. The process and the team are integrated around the construction
project. Team working is characterized by mutual trust and openness, where problems
and risks are shared and resolved collectively by the integrated project team-easy in
principle, more difficult to achieve in practice, especially where one or more of the
parties have not worked in that way before. But, team working is simply common
sense.
4
Model of Integrated Project Team
Project activities are highly inter-dependent as they are intricately connected and
have a complex process relationship. For example, it is not only upstream activities,
which affect the downstream activities, but the reverse is also true. Austin [6] gives an
example on the interdependence of the design activities, as illustrated below.
Interdependence of activities
5
The duration of some activities in unpredictable, especially in negotiation,
obtaining approval from authorities, and in international suppliers usually has longer
lead-time, and hence, higher uncertainty in timely arrival on site. The need to
exchange information and drawings between suppliers may further delay the
procurement time. The technical specifications of capital equipment may interrelate
with other equipment and subsystems from different suppliers.
Surveys by Chan [8] demonstrate that the project changes and variations are
critical factors that cause project delay and failure. It is generally perceived that the
engineering construction industry has become inflexible and unresponsive to the
needs of its customers, which caused project changes and rework. It has been
estimated by the US’s Construction Industry Institute that rework constitutes 12.4% of
the total installed-project cost in O&G projects.
These project challenges always act together, and further complicate the project
execution. The management of interdependence of project activities will become
increasingly critical as the phases are extensively overlapped in order to compress
schedule.
6
i. Material costs represent a major portion of total costs in projects
ii. Procurement needs more communication and negotiation with these external
companies whom are suppliers and subcontractors;
iii. The control is not as strong as in the case of engineering and construction,
especially in outsourcing and purchasing long lead-time equipment;
iv. Unlike other industry, neither the major equipment supplier nor the client keeps
the buffer inventory for the project;
v. The major equipments such as power generator, diesel generator, pumps is very
costly and requires long lead time to manufacture
vi. Suppliers and prime contractors separately use time buffers to protect
themselves from uncertainty due to unforeseen circumstances
Everyone shall understand that each O&G project is unique even if similar design
is involved. Procurement planning is unique for each project. As all the experienced
team members always assume a lot of things from their previous projects and
applying the same to the new one. These usually destroy the project as this
assumption always doesn’t meet the particular project requirements. A new site
condition, a new client in a different country or new suppliers can lead to new project
requirements. The considerable overlaps of engineering/design phase with the
procurement phase increase uncertainties. The procurement decisions on long lead-
time items are usually made soon after the preliminary designs are finished and
before the construction designs and drawings are completed. The uncertainty of
procurement may affect the entire project process and overall project schedule.
7
requirement and etc. No involvement from client as well as supplier’s wrong
assumption had created long delay and additional cost.
8
The broad proposals have three streams of approach; cultural, process, and
technology (IT). Culturally, the proposal hinges on the management of partnering and
trusting relationships with project stakeholders, particularly vendor and sub-
contractors in supplies and supports of equipments/materials and services. The trust
among internal team members also shall be high and spirited. The emphasis is to
create an outward-looking and extended value system that leverages on the resources
and strengths of external partner. It requires major change in corporate mindset.
9
10
References
[] Bechtel, C., and Yavaram, J. (1997). “Supply Chain Management: a Strategic Perspective.” Intl. J. of Logistics Mgmt., 8(1) 15-34.
[2] Conlin J. The application of project management software and advanced IT techniques in construction delays investigation. International Journal
of Project Management 1997;15(2):107-20.
[3] Lim X. Construction productivity issues encountered by Contractors in Singapore. International Journal of Project Management 1995;13(1):51-8
[4] Blanchard BS, Logistic Engineering & Management, Prentice Hall, Upper Saddle River, NJ, 2004.
[5] Nethery SK, Model planning and controlling system for engineering, procurement and construction of industrial projects, 1989.
[6] Austin S. Manipulating the flow of design information to improve the programming of building design. Construction Management and Economics
1994;12:445-55
[7] Nethery SK, Model planning and controlling system for engineering, procurement and construction of industrial projects, 1989.
[8] Chan DWM, Kumaraswamy MM. A comparative study of causes of time overruns in
projects. International Journal of Project Management 1998;15(1):55-63
Readings:
KT Yeo and J.H. Ning, Integrating Critical Chain Concepts in EPC projects. International Journal of
Project Management
2002; 253-262
11