Beruflich Dokumente
Kultur Dokumente
PROJECT TOPIC:
Author:
Mathias B. Michael
Master’s Thesis
Renewable Energy Engineering
School of Engineering and Physical Sciences
Heriot-Watt University, Edinburgh
JUNE, 2008
Project Supervisor:
Dr. Wolf G. Fruh
School of Engineering and Physical Sciences
1
PROJECT BACKGROUND
2
the Energy Commission. The contingent valuation method would be used in
the environmental cost analysis survey.
Ghana is suffering from serious energy shortage for the decade as a result of
serious draught in South Saharan Africa and the dramatic increase in
population which leads to increase in annual growth of electricity demand.
The conventional hydro-power plant which is the main reliable power
generating plant is now generating only about 65% of the country’s electricity
demand which is about 70% of its generation capacity. Although, there are
number of thermal electricity generation plants which produce a total of
550MW representing 32 percent of the current electricity supply and the
106MW Mini Hydro supporting the national grid, but their capacity do not meet
the national demand due the following constraints; poor availability, high fuel
price and the environmental constraint. This power shortage has resulted a
serious power rational for the period of decade and consequently led to the
closure of some heavy industries in Tema which has significantly affected the
economy of Ghana. However, Tema has a considerably amount of wind
energy potential. Therefore, the main aims and objectives of this project is to
utilised the potential wind energy at Tema to generate a 40 MW electricity
power to support the medium voltage side of the electricity network at Tema.
The project aims at supplying power to the residential and light commercial
network in the Tema Municipality, in order to divert more of the power supply
by the conventional hydro power plant to the heavy industrial network which
has the highest demand.
3
METHODOLOGY
1. Preparatory work
• Operating requirement
• General Requirement
• Material, Equipment
• Qualified wind Turbines
• Wind resource and turbine siting
• Output meter
• Storage system
3. Design methodology
This consists of the design analysis thus the feasibility of the following:
Available wind energy potential on the candidate sites
Site assessment, which include visual inspection, Topographic survey,
a study of the local road network and land investigation for potential
litigation
• Design analysis of the wind farm model for overall system performance
verifications.
• Design model for network integration
4
• Design the computer model of overall distributed generation, for
simulation and optimization with software tool (PSCAD 4.2)
5
SCOPE
6
Work Breakdown Structure
project
Initial
Site Planning
Site selection Environmental
Assessment consultation
Analysis
Preparation of
Continue statutory Continue
Assessment environment consultation
Assessment
assessment
Tasks definition
1. Site Assessment covering wind resource, electrical connection,
access requirements, site capacity and ownership
2. Initial environmental analysis covering planning framework,
landscape classification, visual effects, ecology, recreation and
telecommunications
3. Preliminary consultation; local planning authority and major
consultees
4. On-site surveys covering wind resource, existing land uses, site
access, ground conditions, electrical connection and draft design
7
Logic Diagram
4A 5A
1 4B 5B 6 7 9 10 11
4C 5C 8
Tasks definition
Code Task
1 Research
2 Functional specification
3 Design specification
4 Preliminary data collection
5 Project Feasibility
6 Preliminary design
7 Design evaluation
8 Data collection
9 Data analysis and simulation
10 Alternative design
11 Final design
12 Preparation of statutory environment and socio-economic assessment
13 planning application
Work schedule
The thesis start date is 2nd June 2008 and expected to complete on 29th
August 2008. The Gant chart attached explains the detail of schedule.
8
Activity duration start date finish date
1 Research 14d Mon 02/06/08 Thu 19/06/08
2 Functional Specification 2d Mon 16/06/08 Tue 17/06/08
3 Design Specifications 2d Thu 19/06/08 Fri 20/06/08
4 Preliminary data collection 30d Mon 02/06/08 Fri 11/07/08
5 Design analysis 14d Fri 04/07/08 Wed 23/07/08
6 Preliminary design 7d Wed 23/07/08 Thu 31/07/08
7 Data acquisition 30d Mon 16/06/08 Fri 25/07/08
8 Design Testing 2d Mon 04/08/08 Tue 05/08/08
9 Simulation & Analysis 2d Wed 06/08/08 Thu 07/08/08
10 Final design 1d? Fri 08/08/08 Fri 08/08/08
11 Environ. & Socio-economic analysis 3d Mon 11/08/08 Wed 13/08/08
12 Thesis writing 40d Tue 01/07/08 Mon 25/08/08
13 Thesis submission 1d Fri 29/08/08 Fri 29/08/08
Gant Chart
ID T a s k N a m e D u r a tiSo tna r t
0 2 J u n ' 0 80 9 J u n ' 0 81 6 J u n ' 0 82 3 J u n ' 0 83 0 J u n ' 0 80 7 J u l ' 0 8 1 4 J u l ' 0 8 2 1 J u l ' 0 8 2 8 J u l ' 0 8 0 4 A u g '0 18 1 A u g ' 0 18 8 A u g ' 0 8
TFSSMTWTFSSMTWT FSSMTWT FSSMTWTFS SMTWTFSSMTWTFSSMTWT FSSMTWT FS SMTWTFSSMTWTFSSMTWTF
1 R e s e a r c h 1 4 d Ma yo s n 0 2 / 0 6 / 0 8
2 F u n c t i o n a l S p2 e d c aMi fyi sco an ti 1o 6n / 0 6 / 0 8
3 D e s i g n S p e c 2 if id c a aT yt hsi ou n 1s 9 / 0 6 / 0 8
4 P r e l i m i n a r y d3 a0 t ad Mac yo sl nl e 0c 2t i/ o0 n6 / 0 8
5 D e s i g n a n a l 1y s4 i sd aF y r s i 0 4 /0 7 / 0 8
6 P r e l i m i n a r y d 7 e sd iaWg y nse d 2 3 / 0 7 / 0 8
7 D a t a a c q u i s 3it 0i o dn Ma yo s n 1 6 / 0 6 / 0 8
8 D e s i g n T e s t i2 n gd aM y so n 0 4 / 0 8 / 0 8
9 S im u l a ti o n & 2 A dn aWa yl yse s d i s 0 6 / 0 8 / 0 8
10 F in a l d e s i g n 1 d a Fy ?r i 0 8 /0 8 / 0 8
11 E n v i r o n . & S o3 c di oaM- yeso c no n1 o1 m/ 0 i8 c / 0 a 8n a ly s i s
12 T h e s i s w r i t i n4 g 0 d Ta yu se 0 1 / 0 7 / 0 8
13 T h e s i s s u b m i 1s sd iaoF y nr i 2 9 /0 8 / 0 8
RISK ASSESSMENT
9
late
Preliminary Data Acquisition on; wind resource ,
Data electrical load, distribution network
collection plan, topographical, environmental 15 6 High
legal information of proposed site,
(Ghana)
Data Computer modelling; not expect in
analysis the use of WAsP programme 5 0 Low
Design Complete computer modelling of
modelling distribution generation network;
availability of software. Only 5 users 20 4 Low
available on PC Cal.
Supervision Consultation; 10 15 High
Risk Reduction
EXPECTED OUTCOMES
10
• Economic viability; costs of electricity cheaper than the conventional
Hydro and Thermal electricity
REFERENCES
11
http://www.eia.doe.gov/kids/energyfacts/sources/renewable/wind.html#
history
INFORMATION NEEDED
The following data is needed from the Tema branch of Electricity company of Ghana.
12
Electricity Consumption
Hour Total (KWh)
Domestic Industrial
(KWh) (KWh)
13
0000
0100
0200
0300
0400
0500
0600
0700
0800
0900
1000
1100
1200
1300
1400
1500
1600
1700
1800
1900
2000
2100
2200
2300
0000
Total
14
Sep
Oct
Nov
Dec
The following information can be obtained from the Energy Commission, Ghana, or
the Meteorological Services Department, Ghana:
THE SITES
15