Substation Automation and Protection Training

PCM 600 Parameter Setting Tool PST

ABB Power Technologies AB, 2007 2007-09-07 1

Substation Automation and Protection Training

Parameter Setting Tool PST

ABB Power Technologies AB, 2007 2007-09-07 3

Substation Automation and Protection Training

PST Parameter Settings

ABB Power Technologies AB, 2007

Settings for different IEDs

2007-09-07 4

Substation Automation and Protection Training

PST Parameter Layer

ABB Power Technologies AB, 2007 2007-09-07 5

Substation Automation and Protection Training

PST Parameter Filter

ABB Power Technologies AB, 2007 2007-09-07 6

Substation Automation and Protection Training

PST Write Parameters to IED

ABB Power Technologies AB, 2007 2007-09-07 7

Substation Automation and Protection Training

PST Read All Parameters from the IED

From the highest level (Settings) on the IED structure click on button (Read).
ABB Power Technologies AB, 2007

2007-09-07 8

Substation Automation and Protection Training

PST Read Settings from the IED

ABB Power Technologies AB, 2007

Choose this:
2007-09-07 9 Substation Automation and Protection Training

PST Read Settings from the IED

ABB Power Technologies AB, 2007 2007-09-07 10

Substation Automation and Protection Training

PST Read Settings from the IED

ABB Power Technologies AB, 2007

Save and Exit from Parameter Setting.

2007-09-07 11

Substation Automation and Protection Training

PST Hide Information

Hide Column

ABB Power Technologies AB, 2007 2007-09-07 12

Substation Automation and Protection Training

PST Hide Information

Hide Row
ABB Power Technologies AB, 2007

2007-09-07 13

Substation Automation and Protection Training

PST Find Hidden Information