Sie sind auf Seite 1von 8

Managing Civil Engineering Projects Dr. Z. A.

Vattai, BUTE DCT&M


Assignment
As an extension of an industrial plant a new production hall is to be constructed. The building has
more bays with one or two floors. Main elements ( foundation blocks, piers, beams, panels ) of the
reinforced concrete frame structure are manufactured at a company referred as "V N
o
31".
Your job is to elaborate estimates for accomplishment ( schedule, bill of quantities, cost estimate )
and to describe your ideas in a written form detailed as listed below:
- Bill of quantities, Bill of works ( See: technical specifications )
- Periodic layout of site
( preparatory works, foundation works, erecting structure, internal and external finishes )
- Master schedule of performance ( PERT + Bar chart ) indicating tasks of great importance
- Detailed schedule of erecting the structure ( with sequencing elements for positioning )
- Technical Report
- Suggested changes of original plan - if considerable
For to elaborate Detailed- and Master schedules you may accept traditional principles of building
structures of this kind ( See: Phases of construction ).
Documents to be elaborated Responsible Assessed
Bill of quantities, bill of works
Site layout
Master schedule
Detailed schedules
Technical Report
Introduction / Performance
Phases of construction :
If soil conditions necessiated foundation works are started with piling or with soil improvement under each foundation block. For piling they drive
0.30 x 0.30 x 6.00 m sized reinforced concrete piles, more pieces at each block. It is followed by topsoil excavation ( 10 cm thick a layer ), and by
excavating ditches ( including extra excavations due to pile-cap construction or soil improvement ) or trenches. Before positioning sleeve foundation
blocks ( after piling or soil improvement - if needed ) concrete blinding of 10 cm is needed. When sleeve foundation blocks positioned trenches of
strip foundations can be concreted. After refilling ditches overburden earth should be spread under the building for to provide correct floor level.
Before erecting prefabricated frame structure ( applying wheel- or truck-mounted cranes for moving and fixing elements ) main sewers and hardcore
layer should be constructed. Roof panels are to be positioned directly from haulers, while other elemenst may be stored on site until erected according
to delivery system contracted. Frame posts needed for horizontal panels must be erected together with main piers of the structure. Vertical panels are
to be joint to footings and to roof panels directly. When structural frame erected damaged hardcore layer must be reconditioned.
For to protect internal working place against rainfall, next step is constructing breeze concrete layer, heat insulation and water proofing on the roof,
together with assembling downpipes and joining them into main sewers. Edging strips are to be constructed together with roof insulation. That time
fill-in brickworks, masonry of partition walls and works of monolitic stair-case could be started.
Gates, external windows ( together with tie-beams and glass planks - if needed ) are built-in after completion of assembling prefabricated structural
frame. During that floor structures, partition walls and plumbing systems are constructed inside the building. Internal doors and windows are built-in
when partition walls and fill-in brick walls are constructed. ( One half of them into partition walls and the other half into fill-in walls. ) Internal
masonry will get plaster on it, after which lime-wash is needed throughout the whole internal surface ( walls and ceilings ). Finally pave-ways around
the building are to be constructed.
Budapest Supervisor
15 15 a
b
l
15 a
b
l
2
0
2
0
20 a
b
l
2
0
20
2
9
P1 P2 P3 - P7
2
5
2
5
N
o
P1
P2
P3
P4
P5
P6
P7
a [cm] b [cm] l [cm] W [Ton]
50 40 822 4.24
50 40 822 4.24
50 40 822 4.11
50 40 908 4.54
40 40 908 3.63
40 40 488 1.95
35 35 828 2.54
c
20 20
5 5
5 5
a
d
e
f
b
2
0
2
0
5
5
5
5
P i e r s
N
o
K1
K2
K3
K4
K5
a [cm] b [cm] c [cm] d [cm]
50 40 240 180
50 40 220 240
35 35 200 160
40 40 220 160
40 40 200 220
e [cm] f [cm] W [Ton]
42 83 6.08
42 83 7.08
22 63 2.79
32 68 4.00
32 68 4.78
S l e e v e F o u n d a t i o n B l o c k s
K1 - K4
14 14 1.20
3
0
8
.
2
0
8
.
6
0
8
,
6
0
AP2
1
0
22
h
l
N
o
FP1
FP2
FP3
FP4
h [cm] l [cm] W [Ton]
120 598 3.59
120 718 4.31
140 598 4.19
140 718 5.03
FP1 - FP4
AP1
AP3
1
5
14 14 1.20
3
0
1
5
29 29 1.20
3
0
1
5
- 0.20
1
0
1
.
5
0
1
0
6
0
F2
F3
F1
H o r i z o n t a l P a n e l s
V e r t i c a l P.
- 0.20
- 0.20
W = 2.96 Ton W = 3.70 Ton W = 4.45 Ton
Soil
Improvement
Piles, Drived, 6 m
( 4 pcs 30x30 cm )
F l a t
F o u n d a t i o n
20
a
2
5
b
G1 - G3
l
20 20
2
5
b
a
G4
l
G5
l
20 15
a
2
5
b
l
20 20
a
b
/
2
b
G6 - G11
b
a l
G12 - G15
B e a m s
4.77 60
N
o
G1
G2
G3
G4
G5
G6
G7
a [cm] b [cm] l [cm] W [Ton]
50 80 598 4.34
50 80 556 4.03
50 80 536 3.89
80 80 598 6.28
65 80 598 4.90
50 60 676 4.92
50 656
G8
G9
G10
G11
G12
G13
G14
40 60 676 3.94
40 60 656 3.82
40 60 556 3.22
40 60 536 3.10
35 50 598 2.62
35 50 576 2.52
20 60 718 2.15
G15 20 60 598 1.79
Roof Panel,
Cement Screed, 5 cm
Estrich, 2 cm
PVC, Foil, Glued, 0.5 cm
F l o o r
S t r u c t u r e s
FS
mezzanine
Hardcore, 15 cm
Floor Slab, 5 cm
Bituminous sheet, 2 layers
Cement Screed, 5 cm
Basalt Concrete, 3 cm
FS1
Hardcore, 15 cm
Floor Slab, 5 cm
Bituminous sheet, 2 layers
Reinforced Concrete, 5 cm
Basalt Concrete, 3 cm
Protect., Concrete, 15 cm
FS2
Roof Panel
Breeze Concrete, 2-8 cm
Moisture Barrier, 1 layer
Insulation, Nikecel, 4 cm
Bituminous Sheet, Reinfd
NEOACID, Foil, 1 layer
RS2
Roof Panel
Pearlite Concrete, 4-10 cm
Bitumious Sheet, 2 layers
RS1
R o o f
S t r u c t u r e s
2.30
4
1
R o o f P a n e l s
1.20
5 5
W = 3.54 Ton
5.97
41/5 Reinforced
W = 8.70 Ton
2.30
1.20
5 5
6
1
11.56
61/5 Reinforced
2.38
5
4
0
1.20
W = 10.30 Ton
2
2
5
17.97
18 Pre-Stressed
W = 10.22 Ton
1.48
6
5
3
5
T24 Pre-Stressed
23.76
4
6
4
6
4
6
4
6
2 3 2 3 2 3 2 3 2 3 2 3 2 3 2 3 2 3 2 3 2 3 2 3
MNO P QR S T UVWX AB CDE F GH I J KL
1
2
3
4
5
6
7
8
n
k
Perimeter Wall
AP FP AP FP AP FP AP FP AP FP AP FP
Foundation
F1 F2 F3 F1 F2 F3
Building
A B
R
o
o
f


S
t
r
u
c
t
u
r
e
F
l
o
o
r

S
t
r
u
c
t
u
r
e
F
S
1
F
S
2
R
S
1
R
S
2
R
S
1
R
S
2
AP2
AP3
FP3
FP
1
FP1
FP1
FP
4
FP
2
FP2
FP2
G
14
G
14
G
15
G
8
G
6
G
8
G
15

18

18

41/ 5

41/ 5

41/ 5

41/ 5

41/ 5

41/ 5
+ 00
+ 0.40
+ 4.52
+ 9.02
In Inner Bay
M
e
z
z
a
n
i
n
e
R
o
o
f
3 x 6.00 m
18.00 m
n x 18.00 m
k

x

7
.
2
0

m
7
.
2
0

m
K4
K4
K4 K4 K4 K4 K4
K4 K4 K4 K4 K4
P
5
P
5
P
5
P
4
G
11
G
10
G
11
G9
P
5
P
5
P
4
P
5
P
5
P
5
P
5
P
4
P
5
P
5
P
5
K5
K5
G9
(G
8
)
G9
(G
8
)
G9
(G
8
)
G7
G7
(G
6
)
P6 P6 P6 P6
In Outer Bay G9
In Inner Bay G
8
G9
(G
8
)
G9
(G
8
)
G9
(G
8
)
B u i l d i n g " B "
With Horizontal Panels With Vertical Panels
Expectations declared by the Client
The earliest handover of the first bay has great importance, while extensions ( construction of other bays ) can be
scheduled later.
Though whole foundation works and basic supplies can be constructed in the first phase, handover of at least one
bay as soon as possible is favoured. Structural works of extensions ( other bays ) can be scheduled later.
After completing structural works, the earliset handover of the first bay is desired, while finishes of other sections
can be scheduled later.
E
x
p
e
c
t
a
t
i
o
n
s

d
e
c
l
a
r
e
d

b
y

t
h
e

C
l
i
e
n
t
T
h
e

e
a
r
l
i
e
s
t

h
a
n
d
o
v
e
r

o
f

p
r
o
d
u
c
t
i
o
n

h
a
l
l

(

s
i
n
g
l
e
-
s
t
o
r
e
y

s
e
c
t
i
o
n
s

)

h
a
s

g
r
e
a
t

i
m
p
o
r
t
a
n
c
e
.

C
o
n
s
t
r
u
c
t
i
o
n

o
f

o
f
f
i
c
e
b
l
o
c
k

c
a
n

b
e

s
c
h
e
d
u
l
e
d

l
a
t
e
r
.
O
f
f
i
c
e

b
l
o
c
k

a
n
d

o
n
e

b
a
y

o
f

p
r
o
d
u
c
t
i
o
n

h
a
l
l

m
u
s
t

b
e

c
o
n
s
t
r
u
c
t
e
d

f
i
r
s
t
,

w
h
i
l
e

e
x
t
e
n
s
i
o
n

(

o
t
h
e
r

b
a
y
s

)

o
f

p
r
o
d
u
c
t
i
o
n
h
a
l
l

c
a
n

b
e

c
o
n
s
t
r
u
c
t
e
d

l
a
t
e
r
.
A
f
t
e
r

c
o
m
p
l
e
t
i
n
g

s
t
r
u
c
t
u
r
a
l

w
o
r
k
s
,

t
h
e

e
a
r
l
i
e
s
t

h
a
n
d
o
v
e
r

o
f

o
f
f
i
c
e

b
l
o
c
k

i
s

f
a
v
o
u
r
e
d
,

w
h
i
l
e

f
i
n
i
s
h
i
n
g

o
t
h
e
r

s
e
c
t
i
o
n
s
c
a
n

b
e

s
c
h
e
d
u
l
e
d

l
a
t
e
r
.

B u i l d i n g " A "
K2
K1
AP1 AP1
FP3
FP1
FP1
FP3
FP3
FP1
FP1
FP3
+ 00
+ 0.40
+ 4.25
+ 8.62
G15
G15
G3
G1
G3
G5
61/ 5
61/ 5
24 24 G4
G15
G15
G1
P3
P3
P3
G1
G1
P1
P1
P1
P1
G4
G4
K2 K3 K3 K3
P7 P7 P7
K2 K3
K1
P7 P7 P7 G13 G13 G12 G12
P3
P3
P3
K1
P7
P2
P3
P7 G13 G13 P2
P2
K2
G1 Roof
G3 Mezzanine
G1 Roof
G2 Mezzanine
G5 Roof
G3 Mezzanine
G5 Roof
G2 Mezzanine
G3 Mezzanine
G3 Mezzanine
P2
With Horizontal Panels With Vertical Panels Office Block
12.00 m
6.00 m
n x 24.00 m
4 x 6.00 m 24.00 m
k

x

6
.
0
0

m
6
.
0
0

m
M
e
z
z
a
n
i
n
e
R
o
o
f
P3
K1
Glass Planks
12.00 m + n x 24.00 m 25.00 m 22.00 m
1
5
.
0
0

m
k

x

6
.
0
0

m
3
8
.
0
0

m
A
S
R
n x 18.00 m 20.00 m 25.00 m
2
8
.
0
0

m
k

x

7
.
2
0

m
3
5
.
0
0

m
B
S
1
T O
S
2
R
ID Unit
4 6 4 6 4 6 4 6
K
1
K
3
1 Excavation, Topsoil, 10 cm m
2
1612 2356 2236 3268 1170 1718 1725 2531
2 Piling, Driven, ( per foundation block ) m 24,0 24,0
3 Excavation, Ditch, ( per foundation block ) m
3
23,5 11,5
4 Excavation, Trench m
3
38,6 44,2 49,7 55,2 29,8 38,4 38,1 44,7
5 Soil Improvement, ( per foundation block ) m
3
7,8 5,9
6 Excavation, Pile-Cap, ( per foundation block ) m
3
3,1 2,4
7 Chisel-off, Pile-Cap, ( per foundation block ) m
3
0,18 0,18
8 Excavation, Refinery, ( per foundation block ) m
2
5,2 4,0
9 Blinding, ( per foundation block ) m
3
0,52 0,40
10 Strip Foundations, Footings, Cast-In Concrete m
3
33,6 38,4 43,2 48,0 25,9 31,7 33,1 38,9
11 Refill + Spread m
3
12 Grading m
2
1612 2356 2236 3268 1170 1718 1725 2531
13 Hardcore m
3
241,8 353,4 335,4 490,2 175,6 257,6 258,7 379,7
14 Erecting Structure, Pre-Fabricated pcs
15 Roof Insulation, Concrete, Pearlite m
3
100,8 151,2 141,1 211,7 72,6 108,8 108,8 163,3
16 Roof Sealing, Bitumious Sheet, 2 layers m
2
1440 2160 2020 3020 1040 1560 1560 2340
17 Breeze Concrete m
3
72,0 108,0 100,8 151,2 51,8 77,8 77,8 116,6
18 Roof Sealing, Neoacid, Insulated m
2
1440 2160 2020 3020 1040 1560 1560 2340
19 Flashing, Edging Strips m 168,0 192,0 216,0 240,0 129,6 158,4 165,6 194,4
20 In-Fill Brick Works m
3
79,8 91,2 102,6 114,0 64,8 79,2 82,8 97,2
21 Stormwater Drainage, Downpipes, Internal m 65,6 98,4 82,0 123,0 51,6 77,4 68,8 103,2
22 Hardcore, Reconditioning m
3
48,4 70,7 67,1 98,0 35,1 51,5 51,7 75,9
23 Drainage, Water Supply, Main Pipes
24 Floor Slab / Screeding m
3
72,0 108,0 100,8 151,2 51,8 77,8 77,8 116,6
25 Damp Proofing, Bituminous Sheet, 2 layers m
2
1440 2160 2020 3020 1040 1560 1560 2340
26 Protective Layer, Concrete m
3
72,0 108,0 100,8 151,2 51,8 77,8 77,8 116,6
27 Reinforcement, Floor Slab Ton 8,6 13,8 12,1 18,1 6,2 9,3 9,3 14,0
28 Concreting, Floor Slab m
3
216,0 324,0 302,4 453,6 155,5 233,3 233,3 349,9
29 Floor Topping, Basalt Concrete m
2
1440 2160 2020 3020 1040 1560 1560 2340
30 Expansion Joints, Cutting + In-Fill, Bitumin m 600 300 840 1260 432 648 648 972
31 Cement Screed, Mezzanine m
3
14,4 21,6 14,4 21,6 51,8 77,8 77,8 116,6
32 Formwork, Stair-Case m
2
33 Reinforcement, Stair-Case Ton
34 Concreting, Stair-Case m
3
35 Masonry, Partition Walls m
2
319,2 364,8 410,4 456,0 259,2 316,8 331,2 388,8
36 Plumbing & HVAC System
37 Plasterwork, Internal m
2
1277 1459 1642 1824 1037 1267 1325 1555
38 Lime Wash m
2
3780 4930 4940 6380 3680 5070 5160 7070
39 Doors & Windows, Internal, Build-In pcs 24 32 28 36 24 32 28 36
40 Windows, External, Build-In Horizontal Panel pcs 162 186 210 234 130 162 166 198
Vertical Panel 216 248 280 312 152 184 200 232
41 Flashing, Sills Horizontal Panel m 324,0 372,0 420,0 468,0 247,2 304,8 319,2 376,8
Vertical Panel 216,0 248,0 280,0 312,0 152,0 184,0 200,0 232,0
42 Tie Beams, under glass planks Ton
43 Glass Planks m
2
44 Gates, External, Built-In pcs
45 Paving, External, Around m
2
172,0 196,0 220,0 244,0 133,6 162,4 169,6 198,4
46 Scaffolding
m
2
10248 11712 13176 14640 8035 9821 10267 12053
Volumes & quantities at items 2, 3, 5, 6, 7, 8, 9, 11, 14 are to be identified according to specifications.
K
2
K
4
K
5
Building
n
k
Sleeve Foundation
"A" "B"
2 3 2 3 Name
24,0 24,0 24,0
25,9 15,3 16,9
9,4 6,5 7,9
3,7 2,6 3,2
0,18 0,18 0,18
6,2 4,3 5,3
0,62 0,43 0,53
Total volume assigned to items 3 and 4
As in specifications
34,6
0,55
6,92
69,2
1,11
13,84
2,30 3,45
2 2
230,4 245,6

Das könnte Ihnen auch gefallen