Beruflich Dokumente
Kultur Dokumente
Document Type
Procedure
Security
Unrestricted
Discipline
Owner
Issue Date
May 2012
Revision
6.0
This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any part of this document may be disclosed to others or reproduced, stored in a retrieval system, or transmitted in any form by any means (electronic, mechanical, reprographic recording or otherwise) without prior written consent of the owner.
Page 2
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Document Authorisation
Page 3
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
ii Revision History
The following is a brief summary of the 4 most recent revisions to this document. Details of all revisions prior to these are held on file by the issuing department. Revision No. 6.0 Date May-12 Author Robin Norman UOP6 Scope / Remarks Interim Amendments incorporated and procedure aligned with Sour Isolation Philosophy. See Addendum 10 for details Extensive changes. Refer to Addendum 7 for changes Re-issued. Refer to Addendum 6 for changes SI-26 rewritten to new format with minor comments incorporated.
Page 4
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
TABLE OF CONTENTS
1 Introduction ............................................................................................................................ 7 1.1 1.2 1.3 1.4 1.5 1.6 2 3 Background ...................................................................................................................... 7 Purpose ............................................................................................................................ 7 Distribution / Target Audience .......................................................................................... 7 Changes to the Document................................................................................................ 7 Step-out Approval ............................................................................................................. 7 ALARP .............................................................................................................................. 7
Roles and Responsibilities ..................................................................................................... 8 Isolation of Process Equipment ........................................................................................... 10 3.1 3.2 Scope ............................................................................................................................. 10 Terminology.................................................................................................................... 10 Major Work .............................................................................................................. 10
3.2.1
Table 1 Minimum Isolation Requirements ........................................................................... 11 3.2.2 3.2.3 3.2.4 3.2.5 3.2.6 3.2.7 3.2.8 3.2.9 3.3 Minor Work .............................................................................................................. 12 Battery Limits ........................................................................................................... 12 Baseline Isolation Standard ..................................................................................... 12 Boundary Isolation ................................................................................................... 12 Hydrocarbon Services.............................................................................................. 12 Hazardous Substance / Service............................................................................... 12 Non-Hazardous Service ........................................................................................... 12 H2S / Toxic System .................................................................................................. 13 Issue of PTW to Permit Holder ................................................................................ 13 Positive Isolation of Equipment for Maintenance ..................................................... 13 Removal and Replacement of Relief Valves on Live Systems .............................. 13 Isolation of Moving Machinery ................................................................................. 14 Isolation of Vessels .................................................................................................. 14 Isolation of Tanks..................................................................................................... 14 Isolation of Equipment Containing H2S .................................................................... 14 Use of Breathing Apparatus ..................................................................................... 15 Immobilising Devices ............................................................................................... 15
3.3.1 3.3.2 3.3.3 3.3.4 3.3.5 3.3.6 3.3.7 3.3.8 3.3.9 3.4 3.5 3.6
General Exceptions ........................................................................................................ 15 Precautionary Considerations for Isolation ..................................................................... 15 Typical Isolation and De-isolation Process ..................................................................... 17
Figure 1 Process Equipment Isolation Process .................................................................. 17 Appendix 1 Positive Isolation Arrangements ............................................................................ 20 Appendix 2 Abbreviations ......................................................................................................... 25
Page 5
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Appendix 3 Tank Pressure / Vacuum Valve Changeout .......................................................... 26 Appendix 4 Reference Material ................................................................................................ 30 Appendix 5 - User Feedback Page .............................................................................................. 31 Addendum 1 Changes at Revision 2.1 ..................................................................................... 32 Addendum 2 Changes at Revision 3 ........................................................................................ 33 Addendum 3 Changes at Revision 3.1 ..................................................................................... 34 Addendum 4 Changes at Revision 3.2 ..................................................................................... 35 Addendum 5 Changes at Revision 3.3 ..................................................................................... 36 Addendum 6 Changes at Revision 4.0 ..................................................................................... 37 Addendum 7 Changes at Revision 5.0 ..................................................................................... 38 Addendum 8 Interim Amendment May 2011 ............................................................................ 39 Addendum 9 Interim Amendment September 2011 ................................................................. 40 Addendum 10 Changes at Revision 6.0 ................................................................................... 41
Page 6
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
1
1.1
Introduction
Background
Whenever process plant, equipment or systems require to be taken out of service for major maintenance, repair or modification, then positive mechanical isolations shall be provided between the process plant, equipment or system and any potential hazardous energy source. Positive Mechanical Isolations requires the insertion of a spade / blind in the line, or the removal of a spool (if required), downstream of the last tight isolation valve to physically isolate the potential energy source. IMPORTANT: A double block and bleed arrangement on its own is not considered positive mechanical isolation without the insertion of a spade / blind.
1.2
Purpose
The purpose of this procedure is to provide a safe and consistent method for the isolation of process equipment prior to and during maintenance / modification / repair.
1.3
1.4
1.5
Step-out Approval
This procedure is mandatory and shall be complied with at all times. Should compliance with the procedure be considered inappropriate or the intended activity cannot be effectively completed or safely performed, then step out authorisation and approval must be obtained in accordance with PR-1001e Operations Procedure Temporary Variance prior to any changes or activities associated with the procedure being carried out.
1.6
ALARP
ALARP is the acronym for As Low As Reasonably Practicable which simplified means, reducing the risk to a level at which the cost and effort (time and trouble) of further risk reduction are grossly disproportionate to the risk reduction achieved. Full Compliance to PDO Standards and Procedures is a key element in achieving ALARP. For more details refer to ALARP Definition
Page 7
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Maintenance Personnel
Page 8
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Conducting TRIC discussions and completing TRIC with personnel carrying out the work Ensure that any changes to work scope or conditions are captured and implemented before work is allowed to continue Maintain safe working conditions and practices Witness and / or apply isolations / overrides with attendance of the Area Authority Witness and / or remove isolations / overrides with attendance of the Area Authority
Page 9
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
3
3.1
Positive isolation shall be applied once the above have been completed between any adjacent systems that may, or may not, remain live during the work.
3.2
3.2.1
Terminology
Major Work Positive isolation shall be required for all Major Work. For the purpose of this procedure major work will be considered as any intervention that results in spools or equipment being removed from a process line (including non-hydrocarbons), Confined Space entry, or Hot Work (including cold cutting) being carried out. Examples: Valve removal / replacement (including RV changeout); Spool removal / replacement; Equipment i.e. pump, changeout; Vessels / tank inspections: IMPORTANT NOTE: There may be exceptions to the above e.g. relief valves changeout, and these shall be addressed on an individual basis after risk assessment.
Page 10
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Positive isolation by a single proven valve (Note1) and a swung spectacle blind/spade or removable spool (Note 2).
II
System in service, of ANSI class 600# and above. All systems containing toxic fluids (Note 3). Systems containing flashing liquids above ANSI 300, (Note 4) i.e. ANSI 600 and above.
and
bleed
plus
NOTE 1 Provided the line upstream of the required isolation is depressurised, drained, flushed and hydrocarbon free then a single proven valve will provide sufficient isolation for Major Work. NOTE 2 A bleed connection should be installed between the valve and the spade/blind for line sizes 6" and above. The purpose of the bleed is to establish that positive isolation is achieved and to provide a means of draining or depressurising the volume between the isolation valve and the spade/blind. NOTE 3 For the purposes of this requirement, toxic in the case of H2S is defined as more than 500 ppm H2S in the process stream. NOTE 4 The definition of flashing liquids for the purposes of this Table is that given for Cat. A fluids in Appendix B of the IP Code Part 15, section 1.6.7, table 1.2.
Page 11
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Valved isolation shall be required for all Minor Work. For the purpose of this procedure minor work will be considered as any intervention that does not require spools or equipment being removed from a process line (including non-hydrocarbons), or where there is no Hot Work. Examples: As a pre-cursor for major work; Breaking flanges for draining of depressurised systems; Insertion of blinds between flanges on depressurised systems; Working on instrumentation lines.
NOTE: For Minor work the valve isolation will require to be appropriate to address the risk i.e. double block and bleed for H2S or pressurised lines, and demonstrated tight. 3.2.3 Battery Limits This term is often used loosely with the industry. The word battery is used to represent a set of units. For the purpose of this procedure a battery limit is an agreed boundary surrounding a processing unit or battery of units, along with related utilities and services. Therefore the perimeter of a Battery Limit can form a single boundary isolation or a number of boundary isolations within the defined limit. 3.2.4 Baseline Isolation Standard The Baseline Isolation Standard is the minimum acceptable standard of final isolation for intrusive and non intrusive maintenance against live plant under normal circumstances as per the HSE guidelines, (UK HSE Publication Issue 2006 ISBN 0-7176-6171-7 The Safe Isolation of Plant and Equipment) This standard is based upon risk assessment. The Baseline Isolation Standard shall be one of the following two isolation methods: Positive Isolation: is the removal of a spool and fitting of blinds, or fitting of a spade or spectacle blind to allow complete separation of the plant/ equipment to be worked on from other parts of the system Proved Isolation: is a valved isolation where effectiveness of the isolation can be confirmed via vent/bleed points before breaking into the system, and for the duration of the isolation 3.2.5 Boundary Isolation An isolation at any location where the defined Baseline Isolation Standard is met. 3.2.6 Hydrocarbon Services All systems containing hydrocarbons. 3.2.7 Hazardous Substance / Service A substance or containing a substance which is able to cause harm or damage if loss of containment occurs. 3.2.8 Non-Hazardous Service Any service not classified as hazardous.
Page 12
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
High concentrations of H2S in the process fluid, requiring a high degree of protection against leakage. For the purpose of this procedure an H2S / Toxic System is defined as having >500ppm in the process stream.
3.3
3.3.1
3.3.2
Positive Isolation of Equipment for Maintenance A spade and blind check list, marked up copies of the As-Built drawings etc, shall be made by the Permit Applicant and submitted with the PTW to ensure the correct spades or blinds are closed during isolation and removed upon completion of the work. NOTE: This spade list will be signed off by the Operator / Area Authority after isolation and prior to equipment reinstatement after de-isolation. The positive isolation shall be reviewed and approved by the Responsible Supervisor. The Area Authority shall apply or oversee the positive isolation for every piece of equipment identifying the connections that will be isolated, disconnected and tagged before starting to open the equipment. The Area Authority shall verify spade and blind positions with the list before the work is commenced and after the work is completed. He will also supervise gas testing and gas freeing / purging as required. Locked Open / Locked Closed valves that are operated during isolation shall be recorded on the Lock Open / Locked Closed Register. Valves used as part of isolation shall be tight when shut off. Where this cannot be demonstrated the Production Coordinator shall be informed and a variance raised in accordance with PR-1001e Operations Procedures Temporary Variance. NOTE: Butterfly valves shall not to be considered as tight shut-off valves.
3.3.3
Removal and Replacement of Relief Valves on Live Systems The permit applicant shall write a site specific procedure for the removal and replacement of Relief Valve(s) and attach a Risk Assessment signed by the appropriate authority. The procedure shall be reviewed and approved by the Responsible Supervisor and shall be attached to the PTW. PTW shall be in accordance with PR-1172 Permit to Work Section 15.6 No authorisation for the work shall be given if: The system that the relief valve is protecting does not have 100% redundancy; The relief valve does not have as a minimum a double block and bleed arrangement upstream. This includes interlock systems; The relief valve is connected to a live vent and flare system that cannot be isolated by one demonstrated tight valve
Page 13
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Moving machinery is defined here as any equipment using external motive force such as electricity, air, steam or hydraulic fluid. The electrical, air, steam, hydraulic or other source of energy to the moving machinery, both flow and return circuits, shall be isolated from the drive unit and the drive unit secured immobile before work commences. Isolation of moving machinery from process fluids shall be accomplished by tight valves and spades or blinds on the equipment side of inlet and outlet lines in order that maintenance may be carried out while the surrounding facilities remain live. Where H2S is present in the process stream double block and bleed and swung blind is the minimum mandatory requirement. Machinery brakes and brake locks are to be applied and the clutch (if applicable) is to be disengaged. 3.3.5 Isolation of Vessels Spades / blinds shall be installed on the downstream side of the inlet block valve and the upstream side of the outlet block valve. Where practical these spades / blinds should be mounted directly on the flange. Where H2S is present in the process stream double block and bleed and swung blind is the minimum mandatory requirement. Non-compliance shall be in accordance with PR-1001e Operations Procedure Temporary Variance. NOTE: Refer to Table 1 for recommendations regarding isolation requirements. 3.3.6 Isolation of Tanks Blinds / spades shall be inserted on the tank side of all inlet and outlet block valves. These shall be placed as close to the tank as possible. This also applies to blanket / purge gas lines, tank-balancing lines, and vent lines to flare headers and water draw-off lines. The cathodic protection electrical connections should be isolated to prevent any possibility of a spark occurring. Drain sumps should be routed to a closed drain header, collection tank or suitable open pit (refer to PR-1073 Section. 3.3.7 Isolation of Equipment Containing H2S Reference PR-1078 - Hydrogen Sulphide Management Procedure for classifications of H2S risk. For isolations on equipment containing H2S a double block and bleed system and swung blind is the minimum mandatory requirement. Variance to this requirement shall be in accordance with PR-1001e Operations Procedure Temporary Variance. For double block and bleed systems used on H2S service the bleed shall be hard-piped to a safe disposal location to ensure that it does not create a hazard. Acceptable disposal routes are to a remote vent or to a plant closed drain system. When using closed drains systems checks shall be made to ensure that reverse flow does not occur in the system.
Page 14
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
It is mandatory to wear positive pressure breathing apparatus when breaking flanges and opening equipment containing toxics. This shall be clearly stated under Work Description on the W ork Permit. Adequate isolation and purging shall be proven by a direct measurement (using gas detector) for both hydrocarbons and the toxic component concerned (usually H2S). Further work such as opening the equipment for inspection will be carried out wearing a personal H2S monitor and escape set. Refer to PR-1148 Entry into a Confined Space for conditions allowing entry into a confined space. 3.3.9 Immobilising Devices There are a number of proprietary devices used in the industry for immobilisation, however PDO has standardised with pro-lock securing device.
3.4
General Exceptions
Any proprietary insertion or extraction device e.g. Welker/ COSASCO retrievable probes, Daniel Orifice Carriers etc, used on sweet systems up to, and inclusive of, 900# rating shall be allowed by exception to the isolation requirements of this procedure. NOTE: This exception shall be allowed provided the design of the fittings is not modified or changed and that regular maintenance and inspection is carried out.
3.5
2)
3)
ALL isolation work shall be carried out under the Permit to Work system. Hazards shall be identified, detailed and controlled by proper use of the Permit to Work system. All work shall be authorised by the Production Supervisor or his delegated representative. The method of positive isolation shall be in accordance with this procedure and SP-1125 Specification for the Isolation of Process Equipment. The use of home made spades require the explicit approval of the TA for Static equipment. All approved blinds that are fitted shall have all of their bolts set to correct torque in accordance with SP-2020 Flange Connections Bolt Torquing and Tensioning.
Page 15
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Actuated valves shall only be used as part of the positive isolation if the fail safe condition is closed and all motive power to the valve has been physically disconnected from the actuator. WARNING: Reliance on switches shall not be acceptable under any circumstances.
11)
Double block and bleed arrangements provide positive isolation when used in conjunction with spades or blinds. Where the insertion of spades and blinds in conjunction with double block and bleed is considered impractical i.e. not possible to break containment or suitable spading and blinding locations not available, the use of the double block and bleed may be authorised by the Production Coordinator provided a variance is raised in accordance PR-1001e Operations Procedures Temporary Variance. For minor work, such as replacing a faulty instrument on a vessel a single demonstrated tight valve may be allowed if authorised by the Production Coordinator. For toxic and high pressure applications double block and bleed shall be considered a minimum requirement. Where the piping and valve arrangement of process equipment does not allow this to be met a variance shall be raised in accordance with PR-1001e Operations Procedures Temporary Variance. In addition the work shall be completed during a working shift, all valves employed for isolation shall be demonstrated tight and the work site shall not be left unattended while the work is in progress. For work of longer duration or where fittings and accessories remain removed for an appreciable period, e.g. overnight or longer, spades or blinds shall be employed to provide positive isolation.
12)
For long term isolations where a piece of equipment, or a system, is taken out of service for a considerable period, e.g. months, yet the adjacent plant remains live, it is essential that proper records are kept. (e.g. spade / blind / valve checklist) and a record kept of the status of the isolation and its continuing integrity. This should be carried out on an Extended Period Isolation and verified regularly. Such isolations shall be audited and checked for integrity at a frequency defined by the Production Coordinator.
13) 14)
All process isolations shall be recorded on the Process Isolation Wall. All electrical isolations must be done in accordance with SP-1108 - Electrical Safety Operational Procedures.
The most important rule for isolation of equipment is Stick to the Procedures. For guidance, the schematic diagrams in Appendix 1 should be used for reference to typical isolation arrangements.
Depending on the type of long term isolation moth balling may be considered.
Page 16
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC 3.6 Typical Isolation and De-isolation Process
Responsible Supervisor
Area Authority
Permit Holder
Production Coordinator
YES
DO ISOLATIONS COMPLY TO
PR-1076? NO
VARIANCE
AUTHORISED?
NO
YES AUTHORISE THE PTW RECEIVE PERMIT FROM PA / RESP. SUPRV. SUBMIT FOR
VALIDATION
PERFORM / OVERSEE
POSITIVE ISOLATION AS DEFINED ON MECHANICAL ISOLATION CERTIFICATE AND SIGN
UNDERTAKE WORK IN
ACCORDANCE WITH
PTW
CARRYOUT PERIODIC
SITE INSPECTIONS TO ENSURE POSITVE ISOLATION AS DEFINED BY
CARRYOUT PERIODIC
SITE INSPECTIONS TO ENSURE POSITVE ISOLATION AS DEFINED BY
PTW
PTW
ON COMPLETION OF WORK DE-ISOLATE. CHECK THAT DEISOLATION AGAINST MECHANICAL ISOLATION CERTIFICATE / MARKED UP
PEFS
CLOSE-OUT PTW
Figure 1 Process Equipment Isolation Process The following process shall be followed to isolate and de-isolate process equipment prior to and on completion of maintenance / repair / modification work.
Page 17
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
The Permit Applicant Shall complete the relevant sections of the PTW certificate and define the isolation requirements on an As Built drawing (PEFS). The marked up As Built drawing and the PTW shall be submitted to the Responsible Supervisor.
2.
The Responsible Supervisor shall review and discuss the PTW and isolation requirements with the Permit Applicant. The positive isolation proposed on the marked up As-Built drawing shall comply to this procedure and SP-1125 Specification for the Isolation of Process Equipment. Where compliance has been demonstrated the PTW shall be authorised by the Responsible Supervisor. Isolations that do not comply with this procedure shall require to have a variance raised against them in accordance with PR-1001e Operations Procedures Temporary Variance. The Production Supervisor and the Permit Applicant shall agree the minimum isolation that can be used to address the risks. The Risk Assessment and the variance shall be reviewed, endorsed and authorised by the DTL and Operations Manager before further work can be planned. The authorised PTW with the marked up As Built drawing shall be handed to the Permit Holder who shall give them to the Area Authority. The Area Authority shall complete the Mechanical Isolation Certificate from the 2 approved positive isolation on the As Built drawing. isolation as detailed on the Mechanical / Electrical Isolation Certificate authorised by the responsible Supervisor. IMPORTANT NOTE: No PTW shall be validated by Area Authority until the required isolation process is completed. Mechanical isolations that are to be put in place shall be listed on the Mechanical Isolation Certificate or Mechanical Isolation Continuation Sheet and attached to the PTW. These certificates shall be used to verify that all mechanical isolations have been removed. NOTE: Electrical and Safeguarding Instrumentation isolations are recorded on separate Certificates and Forms and are attached to the PTW accordingly.. Positive isolation shall require having spades or blinds / spectacle blinds placed into the lines. This shall involve breaking pipework at flanges and shall be recorded in a specific procedure / method study for the work. All precautions and safety points shall be recorded in the Safety Plan before any breaks are made to the system / equipment integrity
3.
4.
5.
The Area Authority shall witness all gas freeing and gas testing operations. The work required to be undertaken can be progressed as soon as the isolation has been established, checked and the PTW is issued. The Area Authority shall validate the PTW and hand it to the Permit Holder to undertake the work.
6.
If the equipment is required to be test run this should be carried out under a De Isolation for Test (DFT) procedure using the reverse side of the Mechanical and / or Electrical Isolation Certificates
All isolated valves, spades, blinds etc, shall be tagged with the 3 Part Tag. The 2 part of the rd tag shall be attached to the PTW and the 3 part of the tag shall be placed on the PTW board. The valve spade etc, should be secured with pro-lock fittings.
Page 18
nd
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Depending on the length that the isolations will be applied, integrity checks shall be defined. The integrity checks shall be carried out by the Area Authority and Production Supervisor who will ensure that the isolations are correct and intact. The positive isolation shall be checked before the PTW is revalidated. Any violations shall be reported to Production Coordinator and a fountain Incident raised. The work will be stopped until an investigation has been carried out.
8.
On completion of all works, commissioning and testing the process equipment can 3 be de-isolated . The de-isolation should be checked off against the Mechanical Isolation Certificate and the marked up As-Built drawings. When the de-isolation is completed by the Area Authority the PTW can be closed out by the Permit Holder.
9.
This includes de-spading and re-instating blinds / spectacle blinds into their operating positions.
Page 19
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
BLANKET GAS
LO LO
OIL INLET
Breakout Spool
WATER OUTLET
NC
NC
NC
Normal Operation
TO FLARE HEADER
BLANKET GAS
LC LC
WARNING. The Blind on the tank vent line to Flare can only be swung if the station / facility is Shutdown or an isolation valve is provided on the line upstream of the spade location.
LC Flange Blinded LC
OIL INLET
LC
LC
WATER OUTLET
LO
NOTE. The Bleed Valve will be locked open to relieve any pressure build up to the closed drains. Provision should be made to provide a means of monitoring the bleed line from the double block and bleed
LO
SPADE
Isolated
Page 20
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
LO
LO
Vessel 2
Vessel 1
Vessel 3
WARNING: In this case blinds can only be swung if the Vessel connected to the flare line is shutdown, isolated and depressurised. Where relief lines combine then all associated vessels and equipment shall require to be shutdown, isolated and depressurised.
LC
LC
Vessel 2
Vessel 1
Vessel 3
Isolated
Page 21
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
PIG LAUNCHER
Vent & Flare System or Atmosphere at Safe Location Vent & Flare System or Atmosphere at Safe Location
PG
NC NC
Pig Indicator
NC
PG
PG
NC NC NC NC NC NO
DRAINS SYSTEM
(Balance Line)
NC
NC
Normal Operation
Vent & Flare System or Atmosphere at Safe Location Vent & Flare System or Atmosphere at Safe Location Vent & Flare System or Atmosphere at Safe Location
LC NC
Pig Indicator
LC LC LC NC
WARNING. Where a Pressure Safety Relief valve is provided on the Launcher that is tied into a Vent and Flare System then a full Shutdown is required unless isolation is provided upstream of the Relief Valve
NC
LC
LC
LC
NO
DRAINS SYSTEM
(Balance Line)
LC
LC
LC
FROM / TO MAIN LINE
Isolation
Page 22
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Normal Operation
To Vent / Flare WARNING. The Blinds on the Pressure Safety Relief and Blowdown lines can only be swung if the vent and flare systems are shutdown or isolation valves are provided upstream of the Relief and Blowdown valves.
LC Inlet
LC
H LO LG LG LA L LO Closed Drains NOTE. The Bleed Valve will be locked open to relieve any pressure build up to the closed drains. Provision should be made to provide a means of monitoring the bleed line from the double block and bleed SPADE NC NC NC NC Liquid Outlet NC
Isolation
Page 23
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
CENTRIFUGAL PUMP
Pump Discharge
Pump Suction
NC
Motor
NC
Normal Operation
CENTRIFUGAL PUMP
Pump Discharge LC NO
Pump Suction LC
PG PG
Motor
Isolation
Page 24
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Appendix 2 Abbreviations
The following abbreviations are used in this Procedure. ANSI CDFP CFDH DFT EPI ESOP LC LO NC NO PEFS PDO PR PTW PVV RAM TRIC American National Standards Institute Corporate Discipline Focal Point Corporate Functional Discipline Head De-isolated for Test Extended Period Isolation Electrical Safety Operational Procedures Locked Closed Locked Open Normally Closed Normally Open Process Engineering Flow Schematic Petroleum Development Oman LLC Procedure Permit to Work Pressure Vacuum Valve Risk Assessment Matrix Toolbox Talk Risk Identification Card
Page 25
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
WARNING: In single tank operation if production cannot be diverted from the tank then the activity shall not be allowed to proceed. Similarly, if a spare valve is not available, the activity shall not proceed. Tank must be isolated on the inlet Process Equipment in accordance with PR-1076 Isolation of
Pressure in the tank shall be vented to atmospheric via the flare / vent line or via an atmospheric vent to a safe area Operations or work in the vicinity of the tank shall be suspended for the duration of the changeout Work shall be undertaken in accordance with PR-1172 Permit to Work System The minimum number of personnel required to undertake the work safely shall be employed on or around the tank A TRIC discussion shall be conducted prior to any work being commenced and the TRIC completed and attached to the PTW If an unsafe operation is observed or monitored then work must be stopped immediately and the area made safe
2.
Precautions to be Observed
Gas Testing Gas testing shall be carried out in accordance with PR-1154 Gas Testing Procedure. All gas tests shall be undertaken by authorised gas testers as required by PR-1172 Permit to Work System.
Breathing Apparatus Breathing apparatus supplied from an external air source shall be required. Breathing apparatus may be Self Contained Breathing Apparatus (SCBA), a positive pressure hood supplied from an external air source or a combination of the two. Prior to use the charges in the air cylinders must be checked and it shall be ensured that sufficient supplies, including reserves, are available to complete the work.
Fire Fighting Equipment Fire services shall be requested to be on station for the duration of the work. If this is not feasible then a competent fire fighting team shall be employed to man fixed firefighting equipment for the duration of the work. Fixed and portable fire equipment shall be provided both on the tank roof and at the work site to enable a fire to be contained.
Safety harnesses and safety ropes shall be provided and issued to the working party prior to deployment on the tank roof. Secure anchor points for the harnesses shall be identified and marked prior to personnel moving to the tank roof. PR-1076 - Isolation of Process Equipment
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
A man basket (intrinsically safe) shall be provided with rated lifting strops to evacuate causalities from the tank top in emergency.
3.
Tools and Spares A new gasket, bolts, nuts and washers shall be procured for the PVV and bagged ready for use. Spanners and a suitable torque wrench for removing and replacing bolting. Scrappers and brass wire brushes for cleaning and preparing the flange joint. Solvents for cleaning (WD40) may be used provided they are suitable for the application. Absorbent cloths for cleaning the area and mopping small spills. All tools for the work shall be bagged and a check list provided to enable accounting to be carried out on completion of work. The replacement PVV shall be checked to ensure it is correct for the application and has been tested accordingly. The flanges of the replacement PVV shall be protected prior to lifting to the tank top.
Safety Equipment The SCBAs and air lines for the positive pressure hoods will require to be carried or lifted to the tank top. Personnel working on the tank top shall be issued with Emergency Escape Hoods for evacuation.
Lifting Equipment A suitably rated (25ton) with sufficient jib extension will be located, preferably up wind of the operation, on site. Suitably rated slings shall be provided to lift the old and replacement PVV during changeout. NOTE: Gas monitoring shall be carried out before starting the crane and continuously throughout the operation when the crane engine is running. Permitry If the tank is in H2S sour service all personnel involved in the operation shall have an in date H2S certificate. Personnel using breathing apparatus (SCBA) must be certificated. SCBA or positive pressure hoods shall require to be worn by all personnel working on the tank top while the operation of changing out the PVV is being carried out.
Preliminary Work Prior to Removal / Replacement a) Close inlet isolation valve and inlet ESD valve (if provided) to the tank that is to be worked on. b) Divert the flow to second tank (if available) by opening inlet isolation valve on the receiving tank.
Page 27
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
c) Reduce the level in the tank to be worked on to low low level. Overriding of safety critical alarms and trips shall be in accordance with PR-1001c temporary Overriding of Safeguarding Systems d) Complete manual isolation of oil and drain outlet by closing the isolation valves on the tank to be worked on. Record the valves and positions on the PEFS. Update Locked Open / Lock Closed register for any normally Locked Open / Locked Closed valves that are used. Refer to PR-1086 - Locked Valve Control Requirements. e) Isolate the blanket gas line (if provided) on the tank to be worked on. f) Blow down / vent the residual gas inside the tank to be worked on to via the flare / vent line or atmospheric vent line, to atmospheric.
NOTE: Use suitable sited pressure gauge on the tank to confirm condition. g) PTW validated by the Area Authority h) Hand-over the isolated tank to maintenance team.
4.
g) The Area Authority wearing a SCBA shall carry out gas testing. NOTE: The results of the gas testing shall dictate whether personnel will require to wear SCBA or positive pressure hoods to perform preparatory work. Continuous gas testing shall be carried out while preparatory work is being undertaken. Clean the threads on the bolts securing the PVV. Apply solvent cleaner if required. h) Unbolt using the appropriate spanners. WARNING: As the tank will still contain hydrocarbons this operation and the operation of re-bolting on completion will constitute hot-bolting and will require the Approval of the Production Coordinator in accordance with SP2020 - Flange Connections Bolt Torquing and Tensioning Section 10. i) Attach lifting strop to the PVV. Attach to crane hook in readiness of lift.
At this point a further gas test should be carried out and positive pressure hoods worn by all personnel in the direct vicinity of the work. All other personnel should be moved away from the PVV. A rescuer in a SCBA shall be made ready while the PVV is not in place. For added safety all work should be undertaken if possible up wind of the opening. j) Un-bolt the PVV flange and carefully lift from the tank skin. Move to a suitable laydown on the tank top. PR-1076 - Isolation of Process Equipment
Printed 25/02/14
Page 28
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Clean and prepare the flange for fitting of the new gasket. Fit new gasket.
m) Lift the replacement PVV into position, ensuring that the gasket is not damaged. NOTE: If the replacement of the PVV is halted due to damage of misalignment that shall cause delay, a flange can be fitted providing it is fitted with a low range pressure gauge to monitor a pressure build up. In conjunction with the pressure gauge, a tee piece with a valved vent facility should be fitted, with the vent to a safe area or flare system so that any pressure build up due to temperature change can be vented safely (See Illustration below). A documented risk assessment shall be carried out if this method is employed. The risk assessment shall ensure that regular monitoring of the pressure gauge and venting is carried out by operations for the duration that this flange is in place.
n) Replace the bolting and torque down to specified torque. See Warning following Step i). o) Carryout a gas test around the completed job to ensure tightness. Repeat the gas test at intervals as working pressure is established and when the tank is at normal operating pressure. p) Check and confirm all tools are accounted for. Lift and remove old PVV from the tank top to the Canter. q) Carefully lift all remaining equipment from the tank top and secure the site. r) Hand the tank back to Operations personnel to de-isolate and commission.
Page 29
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Page 30
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Page Ref:
To:
Page 31
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
9 10
10
11 12
12 13 15
Page 32
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Page 33
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Page 34
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Page 35
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Page 36
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
13
Page 37
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Page 38
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Page 39
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Valved isolation shall be required for all Minor Work. For the purpose of this procedure minor work will be considered as any intervention that does not require spools or equipment being removed from a process line (including non-hydrocarbons), or where there no Hot Work. Examples: As a re-cusor for major work; Breaking flanges for draining of depressurised systems; Insertion of blinds between flanges on depressurised systems; Working on instrumentation lines.
NOTE: For Minor work the valve isolation will require to be appropriate to address the risk i.e. double block and bleed for H2S or pressurised lines, and demonstrated tight.
Page 40
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Page 41
Printed 25/02/14
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.