Sie sind auf Seite 1von 28

(

SETTING OUT
5.1 INTRODUCTION

In surveying, existing features and levels are located on the ground and then plotted at a reduced scale on plan. Setting-out is the reverse process, where the position and levels of new works already recorded on a working plan are transferred to the ground. The accuracy of measurement required in setting out depends on the type of building work that is to take place. Where prefabricated frames and components are to be used, the setting out must be sufficiently precise for such components to fit within the tolerances laid down. Measurements must therefore be made with great care. s in surveying, the setting out must be arranged so that the work is checked. !very peg placed must be proved to be in its correct position within allowable limits. 5.2 PURPOSE AND FIELD WORK

The controlled process of setting out covers three aspects of positioning new works. a" Horizontal Control, in which the true relative positions of points are fixed on the hori#ontal plane and marked by pegs in the ground. b" Vertical Control, in which pegs defining different levels of construction are suitably placed. c" Works Control, in which the construction processes are controlled, e.g. the vertical alignment of buildings during construction and the control of embankment slopes and excavations. Most site operatives have little concept of the time, effort and expertise involved in establishing setting out pegs. $or this reason the pegs are frequently treated with disdain and casually destroyed in the construction process. typical example of this is the centre%line pegs for route location which are the first to be destroyed when earth%moving commences. It is important, therefore, that control stations and &M should be protected in some way 'usually as shown in figure

2 ).(" and site operatives, particularly earthwork personnel, impressed with the importance of maintaining this protection.

$igure ).( * +ontrol ,tation - &M ,et In +oncrete Ra say!

(Source : Land Surveying,

Where the destruction of the pegs is inevitable, then referencing procedures should be adopted to relocate their positions with the original accuracy of fixation. .arious configurations of reference pegs are used and the one thing that they have in common is that they must be set well outside the area of construction and have some form of protection, as in $igure /.(. commonly%used method of referencing is from four pegs ' , &, + 0 1 " established such that two strings stretched between them intersect to locate the required position 'figure ).2". 1istances &, &+, +1, 1, + and &1 should all be measured as check on the possible movement of the reference pegs, whilst distances from the reference pegs to the setting%out peg will afford a check on positioning. Intersecting lines of sight from theodolites at say and & may be used where ground conditions make string lining difficult. Where ground conditions preclude taping, the setting%out peg may be referenced by trisection from three reference pegs. The peg should be established to form well%conditioned triangles of intersection ' $igure ).3 ", the angles being measured and set out on both faces of a (4 theodolite. ll information relating to the referencing of a point should be recorded on a diagram of the layout involved.

$igure ).2 * 5ocate The 6equired 7osition (Source : Land Surveying, Ra say!

$igure ).3 * Triangles 8f Intersection (Source : Land Surveying, Ra say! 5.3 BASIC SETTING-OUT PROCEDURES USING CO-ORDINATES

7lans are generally produced on a plane rectangular co%ordinate system, hence salient points of the design may also be defined in terms of rectangular co% ordinates on the same system. $or instance, the centre%line of a proposed road may be defined in terms of co%ordinates at, say, 39m intervals, or alternatively, only the tangent and intersection points may be so defined. The basic methods of locating position when using co%ordinates is by either polar co%ordinates, or intersection.

: 5.3.1 By Polar Co-ord !a"#$ In $igure ).:, , & and + are control station whose co%ordinates are known. It is required to locate point I7 whose design co%ordinates are also known. The computation involved is as follows* i. ii. iii. iv. $rom the co%ordinates compute the bearing & 'this bearing may already be known from the initial control survey computations". $rom the co%ordinates compute the hori#ontal length and bearing of &%I7. $rom the two bearings compute the setting%out angle &'I7", i.e. ;. &efore proceeding into the field, draw a neat sketch of the situation showing all the setting%out data. +heck the data from the plan or by independent computation.

$igure ).: * +ontrol ,tation &y +o%ordinates (Sources : Land Surveying, Ra say! The field work involved is as follows * i. ,et up theodolite at & and backsight to and note the hori#ontal circle reading. ii. dd the angle ; to the circle reading & to obtain the circle reading & < I7. ,et this reading on the theodolite to establish direction & < I7 and measure out the hori#ontal distance 5. If this distance is set out by steel tape, careful considerations must be given to all the error sources such as standardi#ation, slope, tension and possibly temperature if the setting%out tolerances are very small. It should also be carefully noted that the sign of the correction is reversed from that applied when measuring a distance. $or example, if a 39m tape was in fact 39.9(m long, when

) measuring a distance the recorded length would be 39m for a single tape length, although the actual distance is 39.9(m= hence a 78,ITI.! correction of (9mm is applied to the recorded measurement. >owever, if it is required to set out 39m, the actual distance set out would be 39.9(m= thus this length would need to be reduced by (9mm= i.e., a ?!@ TI.! correction. The best field technique when using a steel tape is to align pegs carefully at A and B each side of the expected position of I7 ' $igure ).) ". ?ow, carefully, measure the distance &A and subtract it from the known distance to obtain distance A < I7, which will be very small, possibly less than one metre. ,tretch a fine cord between A and B and measure A < I7 along this direction to fix point I7.

$igure ).) * 7osition 8f I7 (Source : Land Surveying, Ra say! Modern !1M, such as the ga @eodimeter (22, displays hori#ontal distance, so the length & < I7 may be ranged direct to a reflector fixed to a setting%out pole. The use of short range !1M equipment has made this method of setting out very popular. 5.3.2 By I!"#r$#%" o! This technique, illustrated in $igure ).C, does not require linear measurements= hence, adverse ground conditions are immaterial and one does not have to consider tape corrections. The computation involved is as follows * i. $rom the co%ordinates of , & and I7 compute the bearings &, & < I7 ii. $rom the bearing compute the angles D and ;

< I7 and

The relevant field work, assuming two theodolites are available, is as follows* i. ,et up a theodolite at , backsight to & and turn off the angle D ii. ,et up a theodolite at &, backsight to and turn off the angle ;

$igure ).C * The Intersection (Source : Land Surveying, Ra say! The intersection of sight lines < I7 and & < I7 locates the position of I7. The angle E is measured as a check on the setting out. If only one theodolite is available, then two pegs locate position I7, as in $igure ).2. 5.& TEC'NI(UE FOR SETTING OUT A DIRECTION

It can be seen that both the basic techniques of position fixing require the turning%off of a given angle. To do this efficiently the following approach is recommended. In $igure ).C, consider turning off the angle ; equal to 29F 3CG 29H using a Watts ?o. ( '29H" theodolite '$igure ).I'a"". i. With theodolite set at &, backsight to 92F ))G29H. and read the hori#ontal circle % say,

ii.

s the angle ; is clockwise of & the required reading on the theodolite will be equal to ,92F ))G 29H J 29F 3CG 29H", i.e. 23F 3(G :9G.

s the minimum main scale division is equal to 29G anything less than this will appear on the micrometer '$igure ).I'a"". Thus, set the micrometer to read ((G :94, then release the upper plate clamp and rotate theodolite until it reads approximately 23F 29G on the main scale= using the upper plate slow%motion

I screw, set the main scale to exactly 23F 29G. This process will not alter the micrometer scale and so the total reading is 23F 3(G :9H, and the instrument has been swung through the angle ; K 29F 3CG 29H.

$igure ).I * 'a" Watts ?o. ( < 294 theodolite. 'b" Wild T2 < (4 theodolite (Source : Land Surveying, Ra say! If the Wild T.2 '$igure ).I'b"" had been used, an examination of the main scale shows its minimum division is equal to (9G. Thus, to set the reading to 23L 3(G :9H one would set only 9(G :9H on the micrometer first before rotating the instrument to read 23F 39G on the main scale. Therefore, when setting out directions with any make of theodolite, the observer should examine the reading system to find out its minimum main scale value, anything less than which is put on the micrometer first. &asically the micrometer works as shown in $igure )./, and, if applied to the Watts theodolite, is explained as follows* . ssuming the observerGs line of sight passes at M9F through the parallel plate glass, the reading is 23F 29G J ,. The parallel plate is rotated using the micrometer screw until an exact reading '23F 29G" is obtained on the main scale, as a result of the line of sight being refracted towards the normal and emerging on a parallel path. The distance ,, through which the viewerGs image was displaced, is recorded on the micrometer scale '((G :9H" and is a function of the rotation of the plate. Thus it can be seen that rotating the micrometer screw in no way affects the pointing of the theodolite, but back%sets the reading so that rotation of the theodolite is through the total angle of 29F 3CG 29H.

$igure )./ * Micrometer (Source : Land Surveying, Ra say! s practically all setting%out work involves the use of the theodolite and or level, the user should be fully conversant with the various error sources and their effects, as well as the methods of adNustment. The use of co%ordinates is now universally applied to the setting out of pipelines, motorways, general road works, power stations, offshore piling and Netty works, housing and high%rise buildings, etc. Thus it can be seen that although the proNect may vary enormously from site to site the actual setting out is completed using the basic measurements of angle and distance. There are many advantages to the use of co%ordinates, the main one being that the engineer can set out any part of the works as an individual item, rather than wait for the overall establishment of a setting%out grid. 5.5 USE OF GRIDS

Many structures in civil engineering consist of steel or reinforced concrete columns supporting floor slabs. s the disposition of these columns is inevitably that they are at right%angles to each other, the use of a grid, where the grid intersections define the position of the columns, greatly facilitates setting out. It is possible to define several grids as follows, '(" Survey grid* the rectangular co%ordinate system on which the original topographic survey is carried out and plotted '$igure ).M". '2" Site grid: defines the position and direction of the main building lines of the proNect, as shown in $igure /.M. The best position for such a grid can be

M determined by simply moving a tracing of the site grid over the original plan so that its best position can be located in relation to the orientation of the maNor units designed thereon. '3" Structural grid: used to locate the position of the structural element9 within the structure and is physically established usually on the concrete floor slab '$igure ).M". In order to set out the site grid, it may be convenient to translate the co%ordinates of the site grid to those of the survey grid using the well%known transformation formula. ! K O! J !( cos P < ?( sin P ? K O? J ?( cos P J !( sin P where O!, O? K difference in easting and northing of the respective grid origins !(, ?( K the co%ordinates of the point on the site grid P K relative rotation of the two grids !, ? K the co%ordinates of the point transformed to the survey grid Thus, selected points, say A and B '$igure ).M" may have their site%grid coordinate values transformed to that of the survey grid and so set%out by polars or intersection from the survey control. ?ow, using AB as a base%line, the site grid may be set out using theodolite and steel tape, all angles being turned off on both faces and grid intervals carefully fixed using the steel tape under standard tension. When the site grid has been established, each line of the grid should be carefully referenced with marks fixed clear of the area of work. s an added precaution, these marks could be further referenced to existing control or permanent, stable, on%site detail.

(9

$igure ).M * 7lan With @rid 5ines (Source : Land Surveying, Ra say!

Activity 5a
).( What is the meaning of setting% outQ ).2 What are the three forms of control provided by setting%out processesQ ).3 What are the two procedures of setting%out by using coordinatesQ ).: What are the forms of using grid proceduresQ

Feedback 5a
".# Setting-out is the reverse process, where the position and levels of new works already recorded on a working plan are transferred to the ground. ).2 The three forms of control provided by setting%out processes is

(( a. Horizontal Control, in which the true relative positions of points are fixed on the hori#ontal plane and marked by pegs in the ground. b. Vertical Control, in which pegs defining different levels of construction are suitably placed. c. Works Control, in which the construction processes are controlled, e.g. the vertical alignment of buildings during construction and the control of embankment slopes and excavations. ).3 The two procedures of setting%out by using a co%ordinates is 7olar coordinates Intersection

).: The forms of using grid procedures is ,urvey grid 5.) ,ite grid ,tructural grid

SETTING OUT BUILDINGS

$or buildings with normal strip foundations the corners of the external walls are established by pegs located direct from the survey control or by measurement from the site grid. s these pegs would be disturbed in the initial excavations their positions are transferred by theodolite on to profile boards set well clear of the area of disturbance R$igure ).(9". 7rior to this, their positions must be checked by measuring the diagonals as shown in $igure ).((. The profile boards must be set hori#ontal with their top edge at some pre% determined level such as da $ $roo% course '17+" or %inished %loor level '$$5". Wall widths, foundation widths, etc. can be set out along the board with the aid of a steel tape and their positions defined by saw%cuts. They are arranged around the building as shown in $igure ).((. ,trings stretched between the appropriate marks clearly define the line of construction. In the case of buildings constructed with steel or concrete columns, a structural grid must be established to an accuracy of about S2 to 3 mm, otherwise the prefabricated beams and steelwork will not fit together without some distortion.

(2 The position of the concrete floor slab may be established in a manner already described. Thereafter the structural grid is physically established by hi(ty nails or small steel plates set into the concrete. 1ue to the accuracy required, a (H theodolite and standardi#ed steel tape corrected for temperature and tension should be used. 8nce the bases for the steel columns have been established, the axes defining the centre of each column should be marked on and, using a template oriented to these axes, the positions of the hooding%down bolts defined '$igure ).(2". height mark should be established, using a level, at a set distance 'say, I) mm" below the underside of the base%plate, and this should be constant throughout the structure. It is important that the base%plate starts from a hori#ontal base to ensure verticality of the column.

$igure ).(9 * 7rofile &oard (Source : Land Surveying, Ra say!

(3

5.*

$igure ).((* 1iagonal +hecks (Source : Land Surveying, Ra say! CONTROLLING +ERTICALIT,

5.*.1 U$ !- a .l/01 1o1 In low%rise construction a heavy plumb bob ') to (9 kg" may be used as shown in $igure ).(3. If the external wall was perfectly vertical, then when the plumb bob coincides with the centre of the peg, distance d at the top level would equal the offset distance of the peg at the base. This concept can be used internally as well as externally provided that holes and openings are available.

$igure ).(2 * >ooding%down &olts (Source : Land Surveying, Ra say!

$igure ).(3 * >eavy 7lumb &ob ') to (9 kg" (Source : Land Surveying, Ra say!

(:

5.*.2 U$ !- a "2#odol "# If two centre%lines at right%angles to each other are carried vertically up a structure as it is being built, accurate measurement can be taken off these lines and the structure as a whole will remain vertical. Where site conditions permit, the stations defining the Hbase figure4 'four per line" are placed in concrete well clear of construction '$igure ).(:'a"". 5ines stretched between marks fixed from the pegs will allow offset measurements to locate the base of the structure. s the structure rises, the marks can be transferred upon to the walls by theodolite, as shown in $igure ).(:'b", and lines stretched between them. It is important that the transfer is carried out on both faces of the instrument. Where the structure is circular in plan the centre may be established as in $igure ).(:'a" and the radius swung out from a pipe fixed vertically at the centre. s the structure rises, the central pipe is extended by adding more lengths. Its verticality is checked by two theodolites 'as in $igure ).(:'b"" and its rigidity ensured by supports fixed to scaffolding. The vertical pipe may be replaced by laser beam or autoplumb, but the laser would still need to be checked for verticality by theodolites. ,teel and concrete columns may also be checked for verticality using the theodolite. &y string lining through the columns, positions % and &%& may be established for the theodolite '$igure ).()"= alternatively, appropriate offsets from the structural grid lines may be used.

()

$igure ).(: * 'a" 7lan 'b" ,ection (Source : Land Surveying, Ra say!

$igure ).() * ,tring 5ining (Source : Land Surveying, Ra say! With the instruments set up at , the outside face of all the uprights should be visible. ?ow cut the outside edge of the upright at ground level with the vertical hair of the theodolite. 6epeat at the top of the column. ?ow depress the telescope back to ground level and make a fine mark= the difference between the mark and the outside edge of the column is the amount by which the column is out of plumb. 6epeat on the opposite face of the theodolite. The whole procedure is now carried out at &. If the difference exceeds the specified tolerances, the column will need to be corrected. 5.*.3 U$ !- o." %al .l/01 !$or high%rise buildings the instrument most commonly used is an autoplumb '$igure).(C". This instrument provides a vertical line of sight to an accuracy of S ( second of arc '( mm in 299 m". ny deviation from the vertical can be quantified and corrected by rotating the instrument through M9 L and observing in all four quadrants= the four marks obtained would give a square, the diagonals of which would intersect at the correct centre point. base figure is established at ground level from which fixing measurements may be taken. If this figure is carried vertically up the structure as work proceeds, then identical fixing measurements from the figure at all levels will ensure verticality of the structure '$igure ).(I".

(C

$igure /.(C * The optical system of the autoplumb (Source : Land Surveying, Ra say! base figure is established at ground level from which fixing measurements may be taken. If this figure is carried vertically up the structure as work proceeds, then identical fixing measurements from the figure at all levels will ensure verticality of the structure '$igure ).(I". To fix any point of the base figure on an upper floor, a 7erspex target is set over the opening and the centre point fixed as above. ,ometimes these targets have a grid etched on them to facilitate positioning of the marks. The base figure can be proNected as high as the eighth floor, at which stage the finishing trades enter and the openings are closed. In this case the uppermost figure is carefully referenced, the openings filled, then the base figure re%established and proNected upwards as before. The shape of the base figure will depend upon the plan shape of the building. In the case of a long rectangular structure, a simple base line may suffice, but T shapes and B shapes are also used.

(I

$igure ).(I * 'a" !levation 'b" 7lan (Source : Land Surveying, Ra say! 5.3 CONTROLLING GRADING E4CA+ATION

This type of setting out generally occurs in drainage schemes where the trench, bedding material and pipes have to be laid to a specified design gradient. Manholes 'M>" will need to be set out at every change of direction or at least every (99 m on straight runs. The M> 'or inspection chambers" are generally set out first and the drainage courses set out to connect into them. The centre peg of the M> is established in the usual way and referenced to four pegs, as in $igure ).2. lternatively, profile boards may be set around the M> and its dimensions marked on them. If the boards are set out at a known height above formation level the depth of excavation can be controlled, as in $igure ).(/.

$igure ).(/ * +ontrol !xcavation (Source : Land Surveying, Ra say! 5.3.1 U$# o5 $ -2" ra l$

(/

,ight rails ',6" are basically hori#ontal rails set a specific distance apart and to a specific level such that a line of sight between them is at the required gradient. Thus they are used to control trench excavation and pipe gradient without the need for constant professional supervision. $igure ).(M illustrates ,6 being used in conNunction with a boning rod 'or traveller" to control trench excavation to a design gradient of ( in 299 'rising". 7egs and & are offset a known distance from the centre%line of the trench and levelled from a nearby T&M. ssume peg has a level of :9m and the formation level of the trench at this point is to be 3/ m. It is decided that a reasonable height for the ,6 above ground would be (.) m. i.e. at a level of :(.)= thus the boning rod must be made ':(.) T 3/" KK 3.) m long, as its cross%head must be on level with the ,6 when its toe is at formation level.

$igure /.(M * Illustrates ,6 (Source : Land Surveying, Ra say! U +onsider now peg &, with a level of :9./ m at a hori#ontal distance of )9 m from . The proposed gradient is ( in 299, which is 9.2) m in )9 m, thus the formation level at & is 3/.2) m. If the boning rod is 3.)m, the ,6 level at & is '3/.2) J 3.)"K :(.I)m and is set f:(.I) T :9./" K 9.M) m above peg &. The remaining ,6s are established in this way and a line of sight or string stretched between them will

(M establish the trench gradient 3.) m above the required level. Thus, holding the boning rod vertically in the trench will indicate, relative to the sight rails, whether the trench is too high or too low. Where machine excavation is used, the ,6 are as in $igure ).29, and offset to the side of the trench opposite to where the excavated soil is deposited. Vnowing the bedding thickness, the invert pipe level may be calculated and a second cross%head added to the boning rod to control the pipe laying, as shown in $igure ).2(. 1ue to excessive ground slopes, it may be necessary to use double sight rails with various lengths of boning rods as shown in $igure ).22. ?ote* (. ,6 offset far enough to allow the machine to pass. 2. 8ffset distance marked on pegs which support ,6 boards. 3. 5ength of traveller marked on both ,6 and traveler. :. ll crossheads should be leveled with a spirit leveled. ). +olouring ,6 and traveller to match can overcome problems of using wrong traveler. C. ,6 must be offset square to the points to which they refer.

29

$igure ).29 * Wse of offset sight rails ',6" (Source : Land Surveying, Ra say!

$igur e ).2( * &oning rod to control the pipe laying (Source : Land Surveying, Ra say!

2(

$igure ).22 * 1ouble sight rails (Source : Land Surveying, Ra say! 5.6 RESPONSIBILIT, ON SITE

6esponsibility with regard to setting out is defined in +lause (I of the I+! +onditions of +ontract* The contractor shall be responsible for the true and proper setting%out of the works, and for the correctness of the position, levels, dimensions, and alignment of all parts of the works, and for the provision of all necessary instruments, appliances, and labour in connection therewith. If at any time during the progress of the works, any error shall appear or arise in the position, levels, dimensions, or alignment of any part of the works, the contractor, on being required so to do by the engineer, shall, at his own cost, rectify such errors to the satisfaction of the engineer, unless such errors are based on incorrect data supplied in writing by the engineer or the engineerGs representative, in which case the cost of rectifying the same shall be borne by the employer. The checking of any setting out, or of any line or level by the engineer or the engineerGs representative, shall not, in any way, relieve the contractor of his responsibility for the correctness thereof, and the contractor shall carefully protect and preserve all bench%marks% sight rails. pegs, and other things used in setting%out the works. The clause specifies three persons involved in the process, namely, the employer, the engineer and the agent, whose roles are as follows* The employer who may be a government department, local authority or private individual, is required to carry out and finance a particular proNect. To this end, he commissions an engineer to investigate and design the proNect, and to take responsibility for the initial site investigation, surveys, plans, designs, working drawings, and setting%out data. 8n satisfactory completion of his work he lets the

22 contract to a contractor whose duty it is to carry out the work. 8n site the employer is represented by the engineer or his representative, referred to as the resident engineer '6!", and the contractorGs representative is called the agent. The engineer has overall responsibility for the proNect and must protect the employerGs interest without bias to the contractor. The agent is responsible for the actual construction of the proNect. 5.17 RESPONSIBILIT, OF T'E SETTING-OUT ENGINEER

The setting%out engineer should establish such a system of work on site that will ensure the accurate setting out of the works well in advance of the commencement of construction. To achieve this, the following factors should be considered= '(" complete and thorough understanding of the plans, working drawings, setting%out data, tolerances involved and the time scale of operations. +hecks on the setting%out data supplied should be immediately implemented. '2" complete and thorough knowledge of the site, plant and relevant personnel. +ommunications between all individuals is vitally important. $ield checks on the survey control already established on site, possibly by contract surveyors, should be carried out at the first opportunity. '3" complete and thorough knowledge of the survey instrumentation available on site, including the effect of instrumental errors on setting%out observations. t the first opportunity, a base should be established for the calibration of tapes, !1M equipment, levels and theodolites. ':" complete and thorough knowledge of the stores available, to ensure an adequate and continuing supply of pegs, pins, chalk, string, paint, timber, etc. ')" 8ffice procedure should be so organi#ed as to ensure easy access to all necessary information. 7lans should be stored flat in plan drawers, and those amended or superseded should be withdrawn from use and stored elsewhere. $ield and level books should be carefully referenced and properly filed. ll setting%out computations and procedures used should be clearly presented, referenced and filed.

23 'C" Wherever possible, independent checks of the computation, abstraction, and extrapolation of setting%out data and of the actual setting%out procedures should be made. It can be seen from this brief itinerary of the requirements of a setting%out engineer that such work should never be allocated, without complete supervision, to Nunior, inexperienced members of the site team.

Activity 5b

).)" ).C"

What are the three forms of control verticalityQ 1escribe how some forms of earthwork of setting%out may be controlled by means of sight rails.

Feedback 5b

).)"

The three forms of control verticality is Wsing a 7lum &op Wsing a Theodolite Wsing optical%plumbing

).C" ,ight rails ',6" are basically hori#ontal rails set a specific distance apart and to a specific level such that a line of sight between them is at the required gradient. Thus they are used to control trench excavation and pipe gradient without the need for constant professional supervision. $igure A illustrates ,6 being used in conNunction with a boning rod 'or traveller" to control trench excavation to a design gradient of ( in 299 'rising". 7egs and & are offset at a known distance from the centre%line of the trench and levelled from a nearby T&M.

2:

F -/r# 4 8 Ill/$"ra"#$ SR ssume peg has a level of :9m and the formation level of the trench at this point is to be 3/ m. It is decided that a reasonable height for the ,6 above ground would be (.) m. i.e. at a level of :(.)= thus the boning rod must be made ':(.) T 3/" K 3.) m long, as its cross%head must be on level with the ,6 when its toe is at formation level. +onsider now peg &, with a level of :9./ m at a hori#ontal distance of )9 m from . The proposed gradient is ( in 299, which is 9.2) m in )9 m, thus the formation level at & is 3/.2) m. If the boning rod is 3.)m, the ,6 level at & is '3/.2) J 3.)"K :(.I)m and is set f:(.I) T :9./" K 9.M) m above peg &. The remaining ,6s are established in this way and a line of sight or string stretched between them will establish the trench gradient 3.) m above the required level. Thus, holding the boning rod vertically in the trench will indicate, relative to the sigh rails, whether the trench is too high or too low. Where machine excavation is used the ,6 are as in $igure B, and offset to the side of the trench opposite to where the excavated soil is deposited. Vnowing the bedding thickness, the invert pipe level may be calculated and a second cross%head added to the boning rod to control the pipe laying, as shown in $igure X. 1ue to excessive ground slopes it may be necessary to use double sight rails with various lengths of boning rods as shown in $igure V.

2) ?ote* (. ,6 offset far enough to allow the machine to pass. 2. 8ffset distance marked on pegs which support ,6 boards. 3. 5ength of traveller marked on both ,6 and traveler. :. ll crossheads should be leveled with a spirit leveled. ). +olouring ,6 and traveller to match can overcome problems of using wrong traveler. C. ,6 must be offset square to the points to which they refer. F -/r# , 8 U$# o5 o55$#" $ -2" ra l$ 9SR:

F -/r# ; 8 Bo!! !- rod "o %o!"rol "2# . .# lay !-

F -/r# ; 8 Do/1l# $ -2" ra l$

2C

S#l5 A$$#$$0#!"

(" 1escribe the employerYs responsibility on the work site. 2" 1escribe the engineerYs responsibility of setting out.

Feedback of Self Assessment


(. !mployerYs responsibility on the work site The employer who may be a government department, local authority or private individual is required to carry out and finance a particular proNect. To this end, he commissions an engineer to investigate and design the proNect, and to take responsibility for the * initial site investigation surveys plans designs working drawings settling out data 8n satisfactory completion of his work, he lets the contract to a contractor whose duly it is to carry out the work. 8n site the employer is represented by the engineer or his representative, referred to as the resident engineer '6!", and the contractorGs representative is called the agent. The engineer has overall responsibility for the proNect and must protect the employerGs interest without bias to the contractor. The agent is responsible for the actual construction of the proNect.

2I

2. !ngineers responsibility of setting out. complete and thorough understanding of the plans, working drawings, setting%out data, tolerances involved and the lime scale of operations. +hecks on the setting%out data supplied should be immediately implemented. complete and thorough knowledge of the site. plant and relevant personnel. +ommunications between all individuals is vitally important. $ield checks on the survey control already established on site, possibly by contract surveyors, should be carried out at the first opportunity. complete and thorough knowledge of the survey instrumentation available on site, including the effect of instrumental errors on setting%out observations. t the first opportunity, a base should be established for the calibration of tapes. !1M equipment, levels and theodolites. complete and thorough knowledge of the stores available, to ensure an adequate and continuing supply of pegs, pins, chalk, string, paint, timber, etc.

8ffice procedure should be so organi#ed as to ensure easy access to all necessary information. 7lans should be stored flat in plan drawers, and those amended or superseded should be withdrawn from use and stored elsewhere. $ield and level books should be carefully referenced and properly filed. ll setting%out computations and procedures used should be clearly presented, referenced and filed. Wherever possible, independent checks of the computation, abstraction, and extrapolation of setting%out data and of the actual setting%out procedures should be made.

2/

Das könnte Ihnen auch gefallen