Beruflich Dokumente
Kultur Dokumente
omet
Community Method
for the
Self-management
of Development
Projects
-1-
COMET
Contents
Page
1.0 - Introduction 4
Diagrams
-2-
COMET
Page
-3-
COMET
1.0 - Introduction
There are many methods available for the participatory formulation, planning
and evaluation of development projects. In addition, logical methodologies such
as the “Logical Framework Approach” are often used by NGOs in conjunction
with or in place of participatory methods. COMET is not designed to replace or
supersede these methods, but rather to compliment and enhance them.
This manual explains how communities and institutions can utilize the processes
and tools provided by COMET to achieve the self-management of development
projects.
-4-
COMET
Diagnostics,
Problem
Identification &
Project formulation
Confirm the
Objectives of the
Project
Approve the
Project Plan
Implement the
Project
Monitor and
Evaluate the
Project
Take Corrective
Action and
Implement
Changes
Produce the Final
Project Report
and perform the
Participatory
Evaluation Close the Project
-5-
COMET
In the project planning phase, COMET is used to confirm the objectives of the
project, create the Project Organization, and to produce a Project Plan. Once
the Project Plan is approved, the Project Team can start to implement the
project.
Once all of the project’s activities have been performed, the COMET project is
closed and the Final Project Report is written.
-6-
COMET
-7-
COMET
The Project Board is ultimately responsible for the tactical management of the
project, because it is required to make decisions concerning the administration
of the project’s activities. To create the Project Board it is recommended that
the community chooses 3 representatives, who will become members of the
Project Board. According to the circumstances, the Project Board can contain
more or less members; this is left to the discretion of the community.
The Project Board will meet with the Project Manager on a weekly, fortnightly
or monthly basis, to discuss the project’s progress. Exactly how often it is
necessary for the board to meet will vary from project to project; the
community will therefore make the final decision. Throughout the duration of
the project lifecycle, full participation in the community project is achieved as
the Project Board reports progress to the community as and when this is
required.
-8-
COMET
The Project Team works under the supervision of the Project Manager,
performing the project’s activities in order to realize the objectives and goals of
the project. The size of the Project Team will vary according to the size, type
and nature of the project.
-9-
COMET
Planning a Project
- 10 -
COMET
Sequence of Activities
Plan of Work
Project Plan
- 11 -
COMET
Initially, participatory diagnostic tools and/or logical planning methods are used
for problem analysis, the identification of solutions and to define the project to
be implemented. With the information collected by these methods it is possible
to complete the first document in the COMET project planning process, the
Project Mission Statement.
The Project Mission Statement and the Plan of Work constitute parts of the final
document to be produced in the planning phase, the Project Plan. The
Project Plan is essential to a projects success, as it contains all the information
needed before project implementation can begin. Information concerning
objectives, planned activities, project finances and monitoring and evaluation, is
recorded in the Project Plan.
The final activity in the project planning phase is for the Project Board to
Authorize the Project Plan. This authorization signifies that the Project
Board considers the proposed project to be suitable to proceed, and that
project implementation can begin.
- 12 -
COMET
The menu of participatory methods includes the following techniques and tools:
- 13 -
COMET
- 14 -
COMET
Logical planning methods are tools that are often used by NGOs to diagnose
problems, find solutions and create the basis for local development projects.
The most widely used logical planning tool is called the “Logical Framework
Approach”. Some NGOs use either participatory methods or logical planning
methods to formulate development projects and some use a combination of
both.
When both participatory and logical methods are employed, the participatory
problem diagnosis is often performed first, and then the results from this
analysis are used to complete the logical framework.
LFA uses its logical approach to determine the causes and effects of a central
problem and create a hierarchy of problems called a problem tree. The problem
tree is then converted into an objectives tree, which shows the objectives that
need to be achieved if the problems are to be solved. Finally, the hierarchy of
objectives from the objectives tree is transferred to a logframe matrix, and
additional information relating to indicators, means of verification, and
assumptions is added.
Like the results of participatory diagnostics, the logframe can also serve as the
starting point for the COMET project. The information in the logframe matrix
contains many similarities to the information required to complete the Project
Mission Statement.
The COMET method therefore works in conjunction with both logical and
participatory planning methods, depending on which of these two diagnostics
tools the NGO or local community prefers to use.
- 15 -
COMET
A Project Mission Statement defines and clarifies information and details about
the project. The Project Mission Statement is split into the following two
sections:
• Project Purpose
• Project Objectives
The project purpose is used to outline the reasons for performing the project,
and the expected benefits of performing the project’s activities. The project
purpose could also be considered as a justification for undertaking the project,
which is important when one considers that the physical and financial resources
invested into the project could be spent on another project. It is therefore
necessary to clearly show what the benefits of the project to be implemented
will be. Details to be included in the project purpose are as follows:
The reasons for performing the project should demonstrate how the project will
help to remedy or rectify the current problems or situation. When discussing
the expected benefits, it is important to identify the beneficiaries, i.e. the
people or sections of the community who will receive the benefits.
Once the project purpose has been clarified, the Project Mission Statement then
defines the project’s objectives, which are as follows:
Many of the details contained within the project purpose will be restated in the
project objectives section, however, they will be reaffirmed as short statements
of the project’s products, changes and impacts.
- 16 -
COMET
- 17 -
COMET
PROJECT PURPOSE
Indirect benefits of this project will include the reduction in travelling time for
Community A children who currently go to school in another town. These
children will have more time to spend with their families and assist with
household chores.
Also, parents will have the ability to participate in the education of their
children. A primary school in community A will enable parents to have an
increased influence over the education that their children receive, which they
can monitor by creating a parents association.
- 18 -
COMET
PROJECT OBJECTIVES
- 19 -
COMET
Through the creation of the Project Mission Statement, the objectives of the
proposed project have been defined and agreed. The next stage is to create a
Sequence of Activities, which is a sequential list of the tasks that need to be
completed in order to achieve the objectives of the project.
What is an activity?
Example 2 shows a Sequence of Activities for the primary school project defined
by the Project Mission Statement in Example 1. Three groupings of activities
can be seen in Example 2, each grouping has a number of activities listed
underneath the title of the grouping. For example, there are 5 activities that
need to be performed so that a building is modified and is ready to be used as
a classroom (Sequence of Activities section 1.0 – 1.5).
- 20 -
COMET
The Sequence of Activities divides the list of activities into a hierarchy based
or logical groups of activities. Each grouping has a title activity that describes
the overall purpose of the activities in the grouping.
In the primary school project example, the title activity ‘Hire a teacher to work
in the school’ groups together the four activities that need to be performed in
order to achieve this, ‘Advertise the position’, ‘Interview the candidates’, ‘Hire
the successful candidate’ and ‘Complete an orientation process’.
TIP: When creating an activity sequence, think of the main or title activities
first and then begin to list the sub-activities that should belong to the
grouping.
- 21 -
COMET
- 22 -
COMET
Unique identifiers
• Planned Cost of the Activity = The planned cost of the activity before
work begins.
- 23 -
COMET
- 24 -
COMET
The first task to be performed is to insert the Activity Sequence into the
columns for Activity Number and Activity Name, as depicted in Example 3.
June July
- 25 -
COMET
- 26 -
COMET
2) Insert information for activity durations and start and finish dates
The planned durations of activities (calculated in working days) are the next
information to be added to the Plan of Work. In conjunction with the activity
predecessors, the planned activity durations provide us with the information
needed in order to plan when activities can start and finish.
In Example 4, the planned durations for the primary school project have been
added to the table. The project itself has an implementation start date of
Monday the 1st of June 2009. All those activities that do not have predecessors
can therefore start on the 1st of June, these activities are ‘Select an appropriate
site’, ‘Advertise the position’, ‘Buy furniture’, ‘Buy course textbooks’ and ‘Buy
stationery and teaching materials’.
Those activities that do have predecessors must wait for those predecessors to
finish before they can begin to be performed. For example, ‘Decorate the
classroom’ must wait for its predecessor ‘Select an appropriate site’ to be
completed. ‘Select an appropriate site’ requires 10 working days to be
performed, so the first working day on which work can begin on activity
‘Decorate the classroom’ is the 15th of June. Activity 1.5, ‘Furnish the
classroom’, has 2 predecessors and must therefore wait for them both to be
completed before its work can begin.
The planned duration of the title activity shows the amount of time required to
complete all the activities in its grouping. For example ‘Modify a building in the
community so that it can be used as a classroom’ has a planned duration of 36
days because this is the total duration required to complete all the activities in
its grouping. Although the total number of days for the grouping is 45, some of
activities can be performed at the same time, therefore 36 days is the minimum
amount of time required to complete this group of activities.
- 27 -
COMET
Having entered durations and dates as explained above, the Plan of Work now
contains the earliest start and finish dates for each of the activities. It can be
seen that the earliest completion date for the example project as a whole is the
29th of July, when the final activity is completed. Of course, the dates can be
altered so that activities start later than the earliest opportunity. Activities can
be started whenever is desirable or possible, and the project doesn’t have to be
completed in the shortest time possible.
However, the implementation process will endeavor to follow the Plan of Work
as closely as possible, so the completed Plan of Work should be a realistic plan
of how it is intended to implement the project. For example, if it is known that
an activity cannot begin before a specific date, do not insert an earlier date into
the Plan of Work. Due to the fact that delays to the planned schedule might be
seen as a failure to meet expectations by project beneficiaries during project
evaluation, it is important that the Plan of Work is an accurate reflection of the
intended project. Activity durations and start and finish dates should therefore
be planned as realistically as possible.
- 28 -
COMET
- 29 -
COMET
The final two columns in the Plan of Work to be completed during project
planning are ‘Planned Cost’ and ‘Persons Responsible’. The planned cost of each
activity should be recorded. The title activities show the sum of all the costs for
the activities in that grouping. For example, Example 5 shows that ‘Hire a
teacher to work in the school’ has a total cost of $740, which is the sum of
‘Advertise the Position’ ($40), ‘Interview the Candidates’ ($200), ‘Hire the
Successful Candidate’ ($400), and ‘Complete an Orientation Process’ ($100).
The names of the people who will perform or supervise the activities should be
recorded in the ‘Persons Responsible’ column. This finalizes the Plan of Work,
although the ‘Actual Activity Duration’, ‘Actual Activity Start Date’, ‘Actual
Activity Finish Date’, and ‘Actual Activity Cost’ columns will be completed during
project implementation.
Activity Costs
- 30 -
COMET
- 31 -
COMET
The Project Plan is the end product of the COMET planning process. It brings
together the other documents produced during the planning phase, the Project
Mission Statement and the Plan of Work, and supplies additional information to
create a comprehensive project proposal.
In its totality, the Project Plan explains exactly what the project aims to
achieve, what will be the project’s activities and how they will be implemented.
Once the Project Plan has received authorization from the Project Board,
implementation processes can begin. The Project Plan contains the following
sections:
• Project Information
• Project Mission Statement
• Project Organization
• Plan of Work
• Financial Plan or Financial Information
• Monitoring and Evaluation Plan
• Project Board Authorization
1) Project Information
The Project Information section provides the following basic details concerning
the project and the Project Plan:
• Project Name
• Community Name (or NGO Name, Parish Name etc)
• Project Plan Version
• Date of Project Plan
• Author of Project Plan
The Project Mission Statement was written earlier in the COMET planning
process and outlines the reasons for performing the project. It describes the
current development situation, the problems to be resolved by the project, the
- 32 -
COMET
expected benefits of performing the project, and the impacts and changes that
will be achieved by performing the project’s activities.
The Project Organization section should also describe the plan for
communication between the Project Board, the Project Manager and the Project
Team. The communication plan should contain details of how and how often
members of the Project Organization will communicate with each other.
Example 7 shows that the Project Board of the primary education project will
meet with the Project Manager on a weekly basis, and make further
communication by telephone in case of a situation arising that requires
immediate attention. The Project Manager will also meet with the Project Team
once a week to discuss the project’s progress, with further communication
occurring via email and the telephone. In order to incorporate and encourage
community participation, the Project Board will hold a community meeting
every month to discuss the project’s progress.
- 33 -
COMET
Similar to the Project Mission Statement, the Plan of Work has already been
produced earlier in the COMET planning process. The Plan of Work shows the
sequence in which the project’s activities will be performed, along with
information concerning activity durations, planned activity start and finish
dates, planned activity costs, and the people who will be responsible for each
activity.
PROJECT ORGANIZATION
D Responsible
E Responsible
F Responsible
G Responsible
A Responsible
B Responsible
C Responsible
COMMUNICATION PLAN
• The Project Manager will meet with the Project Board on a weekly basis
to discuss the progress made by the project. In the case of a situation
requiring immediate attention, communication will be made by
telephone.
• The Project Manager will meet with the Project Team on a weekly basis
to discuss the progress made by the project. Any additional
communication that is required will be made either by telephone or by
email.
• The Project Board will hold a community meeting every month to discuss
the progress made by the project. The entire community will be invited
to attend the monthly meetings to receive updates and contribute their
opinions concerning the progress made by the project.
- 34 -
COMET
The Plan of Work contains information relating to planned and actual costs for
each of the project’s activities. In some projects this will be sufficient Financial
Information for the needs and purposes of the community and the Project
Organization, as displayed in Example 8.
- 35 -
COMET
- 36 -
COMET
• Total Planned Cost = The total planned cost required by the resource
should be entered in this column. If the resource has a unit cost this
should be multiplied by the number of units required to give the total
cost.
• Actual Units Required, Actual Unit Cost and Total Actual Cost =
These columns will be used during the project implementation phase to
record the actual costs of the resources.
Financial Information OR
Financial Plan
- 37 -
COMET
Resource Resource Activity Units Cost Total Date Date Actual Actual Actual
Number Required per Planned Resource Payment Units Cost Total
Unit Cost ($) Required Required Required per Cost ($)
($) Unit
($)
RBE001 Paint and decorating EB1.2 400 15-JUN-09 15-JUN-09
materials
RBE002 Cleaning materials EB1.3 100 13-JUL-09 13-JUL-09
RBE003 Desks EB1.4 20 20 400 20-JUL-09 13-JUL-09
RBE004 Chairs EB1.4 20 20 400 20-JUL-09 13-JUL-09
RBE005 Advertising EB2.1 40 01-JUN-09 08-JUN-09
RBE006 Room Hire EB2.2 200 29-JUN-09 22-JUN-09
RBE007 Legal costs EB2.3 400 20-JUL-09 27-JUL-09
RBE008 Training costs EB2.4 100 27-JUL-09 27-JUL-09
RBE009 Textbooks EB3.1 50 7 350 01-JUN-09 01-JUN-09
RBE010 Stationery EB3.2 200 01-JUN-09 01-JUN-09
TOTAL 2590
- 38 -
COMET
The Monitoring and Evaluation Plan describes how it is intended to monitor and
evaluate the changes and impacts created by the project. “Monitoring and
Evaluation” is an activity that relates to the following two areas of development
projects:
Both logical and participatory planning methods contain tools for the monitoring
and evaluation of project impacts and changes. Both of these methods use
indicator based systems, the difference being that while logical methods use
largely quantitative and objective indicators, participatory methods focus on the
collection of qualitative data by project participants.
- 39 -
COMET
Participatory M&E
Indicators
- 41 -
COMET
Sources of Verification
• Timings of Verification = This column shows how often and when the
verification data is to be collected. The regularity and timings of data
collection will vary according to the indicator. Example 10 shows that
data for component ‘Cost of primary school education’ will be collected
by B Responsible on 30/08/09.
7) Project Authorization
The final section of the Project Plan is reserved for the signatures of
authorization of all the members of the Project Board.
It is the responsibility of the Project Board to assess the accuracy and viability
of the Project Plan, and to authorize the advancement of the project from the
planning phase to the implementation phase. The Project Board should ensure
that all the sections of the Project Plan have been completed correctly, and they
- 42 -
COMET
should also be satisfied that the activities of the project will achieve the
objectives described in the Project Mission Statement. The Project Board should
also decide whether the Plan of Work is realistic and will be achievable through
good management of the project during the implementation phase.
Authorization of the project by all members of the Project Board signifies the
end of the project planning phase, and that the COMET project is now ready to
be implemented.
Project Authorization
- 43 -
COMET
- 44 -
COMET
5
Implementing a
Project
- 45 -
COMET
- 46 -
COMET
In the project implementation phase, the COMET method assists the community
or NGO to manage the implementation of their projects by providing processes
for monitoring, decision making and the taking of corrective actions.
During project implementation the Plan of Work and Financial Plan sections of
the Project Plan are updated to reflect actual timings of project activities and
the actual costs associated with the project’s activities and resources.
To record other details of the project’s progression the Project Diary is used.
The Project Diary enables members of the Project Team to record information
concerning problems, risks, actions and changes. The Project Diary is used by
the Project Manager and the Project Board to analyse the progress of the
project and make decisions concerning corrective actions and changes that
need to be made for the benefit of the project.
When all of the project’s activities have been executed the implementation
phase finishes and the project can move into the final phase of the project
management cycle, project evaluation and close-out.
- 47 -
COMET
There are four columns of the Plan of Work that are updated during the project
implementation phase, these are:
When an activity starts it is possible to add the ‘Activity start date’. However,
only when the activity is completed can the ‘Actual activity duration’, ‘Actual
activity finish date’ and ‘Actual cost’ be recorded. It is the responsibility of the
Project Manager to record the information related to project implementation in
the Plan of Work.
The updating and revision of the Plan of Work during the implementation phase
is important because its details enable the Project Organization to understand
how the project is progressing. Many of the activities performed are sequential,
meaning that a delay in the completion of one activity will affect other activities
performed later in the project. The records of real durations, start and finish
dates and costs will also help the Project Manager to evaluate the performance
of the project when all of its activities have been completed.
When the final activity in the Plan of Work has been completed, this signifies
the end of project implementation and the project moves into the final project
phase of evaluation and close-out.
- 48 -
COMET
In addition to the ‘Total actual cost’ of all the project’s resources, there are
three columns of the Financial Plan that are updated during the project
implementation phase, these are:
When the actual figures or costs for each resource are known they should be
recorded in the Financial Plan. It is the responsibility of the Project Manager to
record the actual resource information in the Financial Plan.
Similar to the Plan of Work, it is important to update and monitor the Financial
Plan during project implementation so as to be aware of potential problems as
soon as they become apparent. When a project has a limited budget, an
overspend on one resource may lead to spending cuts for other resources. As
with the Plan of Work, the Financial Plan will assist the Project Manager during
the evaluation of project performance.
- 49 -
COMET
The Project Diary is used to record the progress made by the project during the
implementation phase. As the Project Manager and the Project Team start to
perform the activities in the Plan of Work, issues will arise concerning the
activities and costs, as well as risks and changes. These issues should be
recorded in the Project Diary.
When decisions have been taken to adjust the project in some way, these
actions are also to be recorded in the Project Diary. In addition, the Project
Diary enables lessons that have been learned during the course of the project
to be recorded.
The Project Board and the Project Manager will use the Project Diary to review
the progress that is made by the project and also as the basis for taking
decisions concerning the future direction of the project’s activities. The columns
of the Project Diary are as follows:
- 50 -
COMET
Risks
DBE5 & DBE6 in Example 11 show how the M&E code can be used to
record updates of successful M&E data collection. However, DBE9 shows
how the M&E code can also be used to record a problem with the
execution of the M&E Plan.
- 51 -
COMET
M&E Updates
- 52 -
COMET
Change is Inevitable!
Logical planning methods for development projects have often been criticized
due to their apparent lack of flexibility. NGOs have found it difficult to make
changes to the objectives and activities of a logical planning project once the
implementation process has begun.
With the procedures described in this section COMET provides the capacity to
alter the scope of development projects, through an effective change
management process.
Nonetheless, major changes will affect all aspects of the original Project Plan,
including finances, activities and objectives. Think carefully before applying
changes to the project and its objectives!
Details of all the changes made to the project should be recorded in the
Project Diary. When the change is recorded, details of any alterations to
the Project Plan, such as to the Plan of Work or the Financial Plan,
should be added to the description column.
- 53 -
COMET
Learning Lessons
Recording details of mistakes and problems will help to avoid making the
same mistakes, or creating the same problems in future.
• Author = The ‘Author’ is the person who added the diary entry to the
Project Diary. This could be the Project Manager or a member of the
Project Team. An entry could also be made by a member of the
- 54 -
COMET
• Date Recorded = The ‘Date recorded’ is the date on which the entry
was added to the Project Diary.
• Status = Each diary entry can have one of two possible statuses, ‘OPEN’
or ‘CLOSED’. A diary entry has a status of ‘Open’ if it has not yet been
reviewed by the Project Board, if an appropriate action has yet to be
decided upon, or if an action for the entry has yet to be implemented. A
diary entry has a status of ‘Closed’ if it has been reviewed by the Project
Board, and an appropriate action has been decided upon and taken. A
status of ‘Closed’ means that no further work is to be performed or
decisions are to be taken by the Project Board in relation to the entry.
Some entries will not require actions, such as general questions or M&E
updates, in which case the entries can be closed. DBE9 in Example 11
shows an entry that is yet to be reviewed by the Project Board, DBE4
shows an entry for which an action has been decided upon but not yet
taken, and DBE5 and DBE8 are examples of closed entries.
• Action Date = The ‘Action date’ is the date on which the decision for
action has been taken by the Project Board, and the Project Plan has
been updated to reflect the changes. Since the taking of the decision
resolves many diary entries, this date will often but not always be the
date on which the entry becomes closed.
Actions
- 55 -
COMET
Entry Type of Related Description Author Date Status Action Action date
number entry activities recorded
DBE1 PROBLEM ABE1.1 There is only one suitable G Responsible 16-JUN-09 Open
site in the community, and
negotiations are still
continuing with the building’s
owner. This activity should
have been completed on 12-
06-09, but is now late
DBE2 RISK ABE3.1 The suppliers of the C Responsible 16-JUN-09 Open It has been decided to
textbooks say that they will find another supplier
not be able to deliver them who can deliver the
in the next 4 weeks books more quickly
DBE3 PROBLEM RBE003, The budget for furniture G Responsible 17-JUN-09 Open
RBE004 appears to be too low. It is
now apparent that the
furniture is going to cost
$1000
DBE4 GENERAL Some of the community G Responsible 18-JUN-09 Open It has been decided
members would prefer to that one of the duties
have someone from the of the new teacher will
community as the primary be to provide training
schoolteacher. They want to to selected local
know if this is possible community members
so that they can help
out with the school as
volunteers
DBE5 M&E M&EBE3 The information concerning B Responsible 18-JUL-09 Closed
prices of primary school
education for community A
children at the neighboring
school have been collected
- 56 -
COMET
DBE6 M&E M&EBE1 The exam results for the A Responsible 01-JUL-09 Closed
school in the neighboring
community have been
collected as per the M&E
plan
DBE7 LESSON DBE4 When creating the project G Responsible 02-JUL-09 Closed
we did not consider asking
local people if they were
interested in teaching or
helping in the school. This
was a failure in participatory
communication which should
be corrected for future
projects
DBE8 CHANGE ABE1.2 It has been decided that F G Responsible 02-JUL-09 Closed The plan of work has 03-JUL-09
Responsible is to be been changed to show
responsible for decorating that F Responsible is
the new school classroom as now in charge of
F Responsible has more time decorating the school
than A Responsible classroom
DBE9 M&E M&EBE2 There is a problem with A Responsible 02-JUL-09 Open
collecting the information
concerning attendances rates
for community A children at
the neighboring community
school. The school is refusing
permission for access to
these records
DBE10 GENERAL ABE1.1 Members of the community G Responsible 03-JUL-09 Open
feel that the building which
has been chosen to be the
school classroom is not
appropriate, They feel that it
will be too cold in the winter
- 57 -
COMET
The Project Board and the Project Manager will meet on a regular basis,
according to the timetable in the Project Plan, to review the progress made by
the project and to decide upon future courses of action. The Project Diary
should form the agenda for these meetings, and all the open entries in the
Project Diary should be reviewed.
The Project Board can decide that the problems and risks in the Project Diary
do not require action, and they can therefore close the diary entries. However,
as the project progresses it is inevitable that some of the Project Diary entries
will require the Project Board to take corrective or pre-emptive actions.
When presented with a problem, the Project Board should consider all the
possible courses of action before selecting the most appropriate action for the
problem situation. This process requires the Project Board to use their
judgement and experience to take the correct decisions for the benefit of the
project.
The Project Board can decide that a problem is insignificant and will not have a
serious affect on the success of the project. In such cases the problem can be
closed without action.
When project activities encounter delays and problems, the project completion
date will often be affected.
However, in some development projects the overall completion date may not be
critical, meaning that activities can be delayed without problems or ramifications.
In such cases the Project Board may choose to accept individual activity delays
without taking corrective action.
When the project completion date is critical, the Project Board will have to take
corrective action to reduce the effects of the delay. This is done by thinking of
possible solutions to the problem and then by making a decision about which
alternative is the most suitable.
- 58 -
COMET
An alternative course of action is to accept the cost to the project caused by the
overspend on the resource, and to increase the financial resources available to
the project. DBE3 in Example 12 shows the type of decision that can be taken
to deal with the effects of an overspend on a project resource.
When a risk to the success of the project has been identified, the Project Board
can take actions to limit the effects caused by a risk, should it occur. It is not
possible to control risks because they occur external to the Project
Organization; however, contingency measures can be taken to counteract the
risks or to lessen their effects. DBE2 in Example 12 shows the type of
contingency action that can be taken to counteract a risk and its effects.
Actions to avoid or reduce the effects of risks are taken in the same manner
as actions for activity delays and resource overspends.
The Project Board thinks of possible actions to negate the effects of the risk
and implements the best solution.
- 59 -
COMET
- 60 -
COMET
6
Evaluating a Project
- 61 -
COMET
End of Project
Implementation
- 62 -
COMET
When the final activity of the project has been performed, the implementation
phase of the project comes to a close. The remaining project phase is that of
evaluation. For development projects evaluation has a dual purpose, namely to
evaluate the performance of the project, and the changes and impacts created
by the project’s activities.
The COMET process for the evaluation of project performance begins at the
start of the implementation phase, when details of the project’s progression
against the Project Plan are recorded in the Plan of Work, the Financial Plan
and the Project Diary. In the evaluation phase these details are used to
examine the progress of the project, which is recorded in the Final Project
Report.
Whereas the Final Project Report represents a factual account of how the
project performed against its plan, participatory project evaluations attempt to
assess the impacts and changes created by the project. Participatory
Evaluations often use qualitative information, such as the views and opinions of
the people affected by the project, to analyse how the lives of people have
been changed by the project and its activities. The COMET process for
Participatory Evaluation begins with the completion of the M&E Plan in the
planning phase, continues with the collection of M&E data in the
implementation phase, and culminates with the Participatory Evaluation itself.
The COMET project closes once the Final Project Report and the Participatory
Evaluation have been completed.
Why Evaluate?
Evaluation also enables us to learn lessons about the project and its
activities, for the benefit of future development projects. As such, the
Project Organization will be able to implement future projects with
increased efficiency and effectiveness.
- 63 -
COMET
The Final Project Report uses the documents created during the planning and
implementation phases to analyse the important aspects of how the project was
performed in comparison to the Project Plan. The following documents are used
to assist the evaluation of project performance:
These documents are used to describe the history of the project so that the
lessons learned can be recorded for the benefit of future projects. The following
areas are analysed by the Final Project Report:
• Planning
• Implementation
• The performance of the Project Organization
• Project results and outputs compared with project objectives
For each of these areas there are a number of issues that need to be addressed
by the Final Project Report. These are:
PLANNING
• How well did the planning process define the project to be implemented?
Were the objectives set by the project an effective representation of the
needs of the community? How well were the activities identified by
project planning able to meet the objectives of the project?
• How efficiently did the Plan of Work and the Financial Plan provide the
foundation for project implementation? How well did the design of these
documents facilitate project implementation?
• How well did the M&E Plan provide the basis for the evaluation of project
changes and impacts?
• Overall, what were the strengths and weaknesses of the project planning
process? How could the project have been planned better?
IMPLEMENTATION
- 64 -
COMET
• What risks were identified during project implementation? How did the
Project Organization deal with those risks?
• Were any changes to the original project objectives made during project
implementation? Why were these changes made? How did these
changes affect project implementation?
• What happened with the implementation of the M&E Plan? Which data
was unsuccessfully collected? Why?
• How well did the Project Board direct the implementation of the project?
How well did the board work with the Project Manager to rectify the
problems and address the risks that arose during project
implementation?
• How well did the Project Manager and the Project Team perform during
the implementation of the project? What did the Project Manager and
Project Team do well? In what areas could the Project Manager and
Project Team improve their performance?
• How well did the communication plan outlined in the Project Plan meet
the needs of the project and the Project Organization?
- 65 -
COMET
It is suggested that the entire Project Organization (the Project Board, the
Project Manager and the Project Team) participates in the production of the
Final Project Report, as their different perspectives on the development of the
project are all important to the evaluation process. However, the responsibility
for writing the Final Project Report lies with the Project Manager.
- 66 -
COMET
INTRODUCTION
1) Planning
The planning process highlighted the need for a primary school that is local to
the community. As such the objectives of the project were to perform the
activities necessary for the opening of a new school. The three principal
activities of finding and adapting a schoolroom, hiring a teacher and purchasing
the necessary equipment and books were the minimum requirements of the
project. Any further activities such as recreational and cooking facilities can be
addressed by later projects.
The Project Plan provided an effective basis for project implementation. The
Plan of Work effectively outlined all the activities that needed to be performed
in order to successfully complete the project and open the school. The Financial
Plan effectively allocated the funds available to the project’s activities, although
as will be described later, these funds proved to be insufficient for the
resources required. The M&E Plan successfully set out the indicators, sources,
timings of verification, and responsibilities for data collection, although some
problems were experienced with the execution of the plan, as will be described
later.
- 67 -
COMET
2) Implementation
The majority of the projects activities were performed successfully and were
completed on time. However, finding a suitable site for the school proved to be
very problematic. This activity was delayed by two weeks. The delay was
caused by protracted negotiations with the building’s owner. Swift action was
taken by the Project Organization to reduce the affects of the delay, and to
alter the remaining activities of the project so that the delay caused to the
overall project completion date was minimised.
One of the main problems to occur during project implementation was the lack
of funds available to the project, which became apparent when the furniture
required for the schoolroom exceeded the budget by $200. Although the Project
Board redirected funds from other activities so that the furniture could be
bought, eventually the project overspent by $150 in comparison with its
planned budget.
No major changes were made to the project’s objectives, only some minor
changes which affected the responsibilities assumed by Project Team members.
These changes caused no adverse consequences to project implementation.
The M&E Plan was largely successful in its implementation. However, there was
a problem with the collection of verification data from the primary school in the
neighboring community. This meant that the indicator for attendances at the
school in the neighboring community could not be used. In future, access to
verification data should be considered more carefully when the M&E Plan is
being designed.
A major flaw in the project design was uncovered when members of the
community started to voice the opinion that the teacher should be a person
from the community, and not someone contracted from outside. The
community members were not consulted on this issue during project planning,
which was a significant mistake. However, changes were subsequently made to
the project so that the new teacher can train local people as volunteers to help
with the education of local children.
- 68 -
COMET
The performance of the Project Organization was very efficient. The Project
Board met with the Project Manager on a frequent basis to review the progress
made by the project, and decisions for action made by the Project Board helped
to avert delays to the completion of the project. The communication plan set a
weekly schedule for meetings between the Project Board and the Project
Manager, and this schedule effectively met the needs of the project.
The Project Team, under the guidance of the Project Manager, performed most
of the activities efficiently. The Project Team does feel that they could have
anticipated the problem concerning the negotiations for the building, and
therefore made contingency plans to avoid the delay that subsequently
occurred.
Overall, the Project Manager and the Project Team have gained vital experience
of the project implementation process, which should benefit the future projects
with which they are involved.
The project has made a significant contribution to the overall development goal
of improving the education of Community A children. However, additional
projects have been identified. The community would like to provide future
teachers for the school, which requires a teacher training programme, and also
they would like to provide the children with recreational facilities and hot meals
at lunchtime.
The project to open a primary school in community A has been planned and
implemented successfully. The Project Organization has learnt a lot about the
process of project implementation, which will help to benefit future projects.
- 69 -
COMET
The Project Manager, the Project Board and the Project Team are now
confident that they can participate successfully in future development projects
for the benefit of the community.
The Project Organization now awaits the results of the participatory evaluation
of the changes and impacts created by the project.
- 70 -
COMET
The Monitoring and Evaluation Plan, completed as part of the Project Plan,
specifies indicators that are to be used to measure the impacts and changes
that are attributable to the project. In addition, the M&E Plan specifies the
sources from which data will be sought to verify the achievement of the
indicators, as well as when the data will be collected and by whom.
The data that will be used to evaluate the impacts and changes created by the
project’s activities can be either quantitative or qualitative. Quantitative data is
often sourced from statistics and provides an objective measurement of the
success of the project in achieving its desired impacts and changes. However,
qualitative data often comprises of the views and opinions of members of the
community, collected using Participatory Evaluation tools and techniques.
Subsequent to the collection of M&E data, as specified in the Project Plan and
performed during project implementation, the Project Organization assumes the
responsibility of organising a Participatory Evaluation of project impacts and
changes. Participatory Evaluations are often performed in workshops, which
take place after project implementation has finished.
- 71 -
COMET
should also analyse the sustainability of the impacts and changes created by
the project, and consider any unexpected changes and impacts that have
occurred as a result of the project’s activities.
Once the Final Project Report and Participatory Evaluation Report have been
written, the project’s activities have been completed and the COMET project is
closed.
Participants may also consider who will benefit from the changes, and
the sustainability of project impacts.
- 72 -
COMET
Sequence of Activities
PLANNING
Plan of Work
EVALUATION
Participatory Final Project
Evaluation Report Report
- 73 -
COMET
During project implementation the Project Plan is updated with details of actual
project performance, and the Project Diary is used to record problems and
progress. In the evaluation phase the Final Project Report is completed by the
Project Organization, and the Participatory Evaluation of impacts and changes is
performed and reported on.
Once the project evaluation has been completed and the project has
been closed, this project document serves as an important record of
the project’s life, of the outputs, results, impacts and changes
achieved by the project, and of the experiences gained and lessons
learned by the Project Organization.
- 74 -
COMET
- 75 -
COMET
Project Document
Project: ___________________
Community: _________________
- 76 -
COMET
Project Plan
1) Project Information
PROJECT PURPOSE
PROJECT OBJECTIVES
- 77 -
COMET
COMMUNICATION PLAN
- 78 -
COMET
Activity Activity Predecessors Planned Planned Planned Planned Persons Actual Actual Actual Actual
Number Name Duration Start Finish Cost Responsible Activity Activity Activity Cost of
Date Date Duration Start Finish Activity
Date Date
- 79 -
COMET
Resource Resource Activity Units Cost per Total Date Date Actual Units Actual Cost Actual
Number Required Unit ($) Planned Resource Payment Required per Unit ($) Total
Cost ($) Required Required Cost ($)
TOTAL
- 80 -
COMET
- 81 -
COMET
The Project Plan has been approved by the Project Board and can
now start to be implemented by the Project Manager and the
Project Team
Signature: _______________________
Date: _______________________
Signature: _______________________
Date: _______________________
Signature: _______________________
Date: _______________________
- 82 -
COMET
- 83 -
COMET
Community Name:
INTRODUCTION
1) Planning
2) Implementation
CONCLUSIONS Y RECOMMENDATIONS
- 84 -
COMET
Project Name:
Community Name:
INTRODUCTION
CONCLUSIONS Y RECOMMENDATIONS
- 85 -