Beruflich Dokumente
Kultur Dokumente
oller compacted concrete (RCC) has had a lot of attention in the past several years because of its growing acceptance for use as mass concrete in dam construction. Howe ve r, a recent d e velopment is the increasing use of RCC as a comp a ra t i vely low cost, durable paving material to carry heavy loads. The U.S. Army Corps of Engineers has accepted it for aircraft parking aprons, taxiways and other pavements at military installations, and thus stimulated interest among all those concerned with pavement construction. Roller compacted concrete as used for pavements is a dry portland cement concrete material which is consolidated by external vibration using heavy vibratory rollers or similar equipment. It is normally dryer than a noslump consistency and must be stiff enough to support the compaction equipment. RCC for pavement construction is generally placed with an asphalt paver or similar equipment, modified to accommodate the stiff consistency of RCC and the thicker lifts used. The most obvious advantage of using RCC pavement is lower cost, achieved primarily by the use of lower cost equipment and fewer workers than with conventional concrete pavements. In some cases, lower cost aggregates can also contribute to the saving. The term RCC pavement is normally considered to refer to installations where the RCC is the wearing course, without any other applied surfacing.
Fort Lewis RCC test road surface. Close-up of the 34 -inch aggregate pavement at about 1 year, showing a nonraveled transverse crack. These cracks formed at 40- to 80-foot spacing throughout the road project.
roller compacted concrete used for pavements at the Yakima, Washington airport in 1941. Although the equipment was primitive by todays standards, and the mix design and control were likely less than perfect, that pavement has served well. It is still in use, with only a thin asphalt overlay added during 45 years of service.
How RCC pavement compares with treated bases and RCC for dams
Use of RCC for pavements evolved from the use of soil cement and cement treated base (CTB) courses. Although equipment for batching or feeding and mixing has developed from that used for the base courses, RCC for pavements requires better controls on proportioning. Also, a true paver or laydown machine is normally
BACKGROUND OF DEVELOPMENT
Construction technology similar to that of the RCC pavement has been available for many years in pavement base construction. There is even a record of true
Ends of a broken test beam from the Fort Hood, Texas tank stand (1984) show internal structure of the RCC pavement.
piggyback trailer parks, and it was decided to try RCC as a combined base and surfacing or total pavement. The attitude was: The RCC is performing so well. Why do we need the asphalt surfacing? This line of thinking led to construction in 1976 of a full RCC pavement for a log sort yard at Caycuse in the central part of Vancouver Island, British Columbia. The forest products industry was then facing stiff environmental regulations which made it impractical to continue the common practice of sorting and yarding logs in the waters throughout the timberland. But dry-sort yards in that climate would immediately become huge mud holes unless surfaced. Since asphalt was impractical at many isolated sites, the decision was made to try RCC.
Since the conventional asphalt pavers available could handle only about 10 inches in an RCC lift, anything thicker had to be two-course construction. The specified sequence of two-course construction re q u i re d placing the second course within an hour of the first, but with no treatment of the surface of the first lift. Each lane of pavement was placed immediately adjacent to the previous lane, with the longitudinal construction joint formed by leaving a 12- to 18-inch unrolled strip at the edge of the preceding lane and rolling it after the succeeding lane had been placed in contact with it. If the operation was shut down overnight, the edge of the last lane was cut back to a vertical face with a motor grader or similar equipment and then the new lane butted up against this face the next day. No transverse joints were formed; the pavement was simply allowed to crack as shrinkage occurred. The transverse cracks did form, reasonably straight across the pavement, from 40 to 70 feet apart.
Dawson Creek, beginning point of the Alcan Highway in northeast British Columbia. Along with the road there was also a 6-acre load-out at the railhead, built in the late fall of 1983 over extremely poor subgrade. The load-out area has 7 inches of RCC with no other surfacing. The road612 inches of RCC plus 112 inches asphalt surfacingwas designed with no base course, but in many areas of poorest subgrade the contractor put down a granular base as a working platform. The RCC mix had 12 percent cementitious material by weight, half portland cement and half natural pozzolan from a local source. It was designed for a flexural strength of 450 psi at 56 days. Two pavers operated in echelon, one about 150 feet behind the other in the adjoining lane. Curing was by water truck for the first few hours, followed by an application of asphalt emulsion. Much of the RCC froze hard the night after it was placed. We inspected this work in the summer of 1985 because of great interest in the durability of RCC pavement in extremely severe climate. The asphalt surfacing on the road has deteriorated considerably, but the RCC has performed very well, with the only distress spots showing where subgrade support was extremely poor. In the load-out area where the RCC is exposed without other surfacing, it seemed to be in perfect condition, showing no sign of freeze-thaw deterioration. The road is used by 7-axle coal trucks with a gross weight of 80 tons, operating 24 hours per day year round.
RCC MIXES FOR FORT LEWIS TEST ROAD, PER CUBIC YARD
Material/property Portland cement Fly ash Mix A 350 pounds 180 pounds (Class F) 1935 pounds, 3 4-inch gravel 1560 pounds 168 pounds (20.3 gallons) 600 psi Mix B 520 pounds
Coarse aggregate
3500 pounds, 8-inch, crushed 203 pounds (24.5 gallons) 800 psi
Sand Water
Vibratory roller was the only compaction equipment needed following the paver at Portland Airport. Specifications required rolling to begin within 10 minutes of placement and to be completed within 60 minutes from start of mixing at the plant. Weather was also a problem at Fort Hood. A temperature of 100 degrees F with the wind blowing made it difficult to prevent excessive drying of the surface. Originally it was planned to saw joints similar to those in conventional concrete pavements; this proved impractical and the pavement was left unjointed. In spite of difficulties, beams sawed from the pavement tested at 800 to 900 psi, well above the specified flexural strength of 650 psi.
690 psi
960 psi
gatean asphaltic concrete aggregate used by the Washington Department of Transportation, with 7 to 10 percent passing the No. 200 sieve. The proportioning (feeding) and mixing equipment were essentially the same as that used in British Columbia (described on page 291), but two aggre g a t e feeds were needed for Mix A because it had both coarse and fine aggregate. Transporting, paving and rolling practices were also like those used in British Columbia. The number of passes with the rubber-tired roller was varied to study the effect. The general opinion was that two passes helped tighten up the surface, but more passes tended to degrade it. The 34-inch gravel mix (Mix A) placed and finished well, although the 58- i n c h crushed asphalt aggregate mix was even easier to handle and finish. Both mixes consistently produced RCC surfaces to an a ve rage 316-inch tolerance when measured transversely with a 10-foot straightedge. Transverse cracks developed at 50- to 80-foot spacings. Early strength tests on beams sawed from the pavement showed Mix B (no fly ash) 30 to 40 percent stronger than Mix A (see table).
land cement, 100 pounds of fly ash and the same 58-inch crushed aggregate used in the Fort Lewis test section. On the first area, the low bidders price was $1,764,000 for RCC, compared with $2,275,000 for a conventional portland cement concrete option. The first two RCC projects at the Tacoma docks were built with equipment similar to that previously described, but on the third project a German paver new to this country was used. The machine is similar to American asphalt pavers, but heavier duty, capable of laying an RCC lift of 12-inch compacted thickness. It was equipped with two tamping screeds which can compact the material to 94 to 95 percent of modified Proctor density as it comes out of the paver. Thus the single roller following did little additional compaction, causing almost no settlement of the pavement surfacea great advantage in maintaining finish tolerances.
PUBLICATION #C860287
Copyright 1986, The Aberdeen Group All rights reserved