Beruflich Dokumente
Kultur Dokumente
Bachelors of Technology
in
ACKNOWLEDGEMENT
With profound respect and gratitude, I take the opportunity to convey my thanks to complete the training here. I do extend my heartfelt thanks for providing me this opportunity to be a part of this esteemed organization. I would also like to thank the training in charge of KIIT COLLEGE OF ENGINEERING, GURGAON and all the faculty members of Electrical Engineering Department for their effort of constant co- operation, which have been a significant factor in the accomplishment of my report.
Introduction
A transformer i a stati devi e t at t ansfers electrical energy from one circuit to anot er t rough inductively coupled conductorsthe transformer's coils. A varying current in the first or primary winding creates a varying magnetic flux in the transformer's core and thus a varying magnetic field through the secondary winding. This varying magnetic field induces a varying electromotive force (EM called mutual induction. If a load is connect ed to the secondary, an electric current will flow in the secondary winding and electrical energy will be transferred from the primary circuit through the transformer to the load. In an ideal transformer, the induced voltage in the secondary winding ( Vs) is in proportion to the primary voltage (Vp), and is given by the ratio of the number of turns in the secondary (Ns) to the number of turns in the pr imary (Np) as follows: or "voltage" in the secondary winding. This effect is
By appropr iate selection of the ratio of turns, a transformer thus allows an alternating current (AC) voltage to be "stepped up" by making Ns greater than Np, or "stepped down" by making Ns less than Np. In the vast major ity of transformers, the windings are coils wound around a ferromagnetic core, air-core transformers being a notable exception. Transformers range in si e from a thumbnail-si ed coupling transformer hidden inside a stage microphone to huge units weighing hundreds of tons used to interconnect portions ofpower grids. All operate with the same basic pr inciples, although the range of designs is wide. While new technologies have eliminated the need for transformers in some electronic circuits, transformers are still found in near ly all electronic devices designed for household ("mains") voltage. Transformers are essential for high-voltage electric power transmission, which makes long-distance transmission economically practical.
magnetic flux, which occurs within the coil, doesn't leak out, the coil efficiency is good, and the magnetic flux has little influence on other components. Laminated transformers contain laminated-steel cores; they are also called E-I transformers. These steel laminations are insulated with a nonconducting material, such as varnish, and then formed into a core that reduce electrical losses. Power transformers can be one of many types. These include autotransformer, control transformer, current transformer, distribution transformer, generalpurpose transformer, instrument transformer, isolation transformer, potential (voltage) transformer, power transformer, step-up transformer, and step-down transformer. Mountings available for high voltage transformers include chassis mount, dish or disk mount, enclosure or free standing, h frame, and PCB mount
Testing Of Transformer
As regards complex electrical equipment such as high voltage power transformers, internal insulation is subject to defects due to several reasons associated to bad material, design, manufacturing processesor resulting from shipment. On-site electrical tests are for the test voltage to simulate on the transformer under testing the equivalent stresses which may be established during service condition. Basically, electrical tests on power transformers are grouped in type and routine tests. The goal of a routine test is to check correct manufacture of HV insulation while the goal of a type test is to confirm correct design of HV insulation. In addition, the application of on-site tests may be able to be separated in: commissioning tests: as part of the on-site equipment commissioning procedure in order to demonstrate that shipment and erection have not caused any new defects to HV insulation; on-site repair or refurbishment: as part of the repair or refurbishment procedure in order to demonstrate that repair or refurbishment have been successfully completed and HV insulation is free of dangerous defect; and diagnosis: as part of a diagnostic procedure in order to provide reference values to further tests or to confirm results obtained from other types of test. Up to date, on-site high voltage withstand tests including partial discharge monitoring and measurements are the most significant tests in order to quantify HV insulation quality. The use of a separate HV source is more informative than measurement at normal operation voltage, as it allows investigation of the HV insulation performance with voltage.
Alternating voltages are most important for on-site tests . Other voltage shapes for simulation of overvoltages have been used; however, they are strongly dependent on availability of onsite testing systems. The application of HV on-site tests has been a good practice in South America. Since 1992, on-site HV tests have been performed in more than 110 power transformers ranging from 30MVA to 550MVA, 115kV to 765kV (AC) and 600kV (DC). Large electric power utilities and industrial plants are the main customers to this technology.
During the test, partial discharge activities were measured (up to 7500pC at 130%Un) and located in the HV winding exit areas. Figure 5 shows the results of PD location through the application of 3 acoustic sensors.
The transformer has been visually inspected internally and partial discharges evidences have been located in the area indicated by the previous test induced test. After that, the transformer has been shipped back to factory and disassembled for complete repair.
In most of the cases power transformers cannot be assumed as a purely capacitive load for the LI testing. Usually the LI test voltage is applied to one winding terminal of the transformer to be tested, whereas all other terminals are connected with the earth. Hereby, not only the input capacitance of the transformer winding acts as the load for the impulse voltage test generator but also its impedance to all other short circuited windings. The principal circuit (fig. 1) must be extended by the transformer inductance Lt that is connected in parallel to the test capacitance Ct
Thereby the inductance Lt of the load becomes smaller with decreasing impedance voltage vimp%, with decreasing rated phase -to-phase voltage VP-P and with increasing power Ptot of the transformer winding to be tested. Therefore the lowest values of the inductance Lt have to be considered by testing the low-voltage side windings for power transformers. For a three -phase winding in a star connection the following equation can be applied: Lt Inductance (stray inductance) of the winding to be tested Impedance voltage of the winding to be Tested VP-P Rated phase-tophase voltage of the three-phase winding to be tested Ptot Rated total power of the three-phase winding to be tested f Rated frequency
With decreasing inductance Lt the impulse capacitance Ci of the impulse voltage test generator is not only discharged via the tail resistor Rp, but also via the low inductance Lt of the winding to be tested. Thereby the time to half -value T2 of the LI is reduced and the aperiodic discharge of the impulse capacitance turns to a damped oscillating cosine shape. This is permitted in principle acc. to IEC 60076-3 [2]. However, the lower tolerance limit for the time to half-value of T2 min may not remain under 40 s (= 50 s - 20 %). At the other side the amplitude of opposite polarity of the LI voltage dmax should not exceed 50 %. To fulfil these both requirements the impulse voltage impulse voltage test generator must have a minimum required impulse capacitance
Projection of an impulse voltage test generator for the LI test of power transformers
The main technical data of the transformers to be tested, like the circuitry and the arrangement of the windings, their rated voltage, rated power, impedance voltage and not at least the rated frequency determine essentially the total charging voltage and the stage energy of an impulse voltage test generator for the LI test. The total charging voltage of the impulse voltag e test generator should lie for LI testing 30 % 60 % above the highest required LI test voltage. In many cases the value of 30 % is sufficient for routine tests. If development tests are to be carried out, a total charging voltage, which lies 60 % above the highest rated LI test voltage, is recommended. If the exception earthing via termination resistors is not considered, the required impulse capacitance Ci req can be calculated for each winding voltage level acc. to equation (5). Taking into consideration the different circuitry options of the impulse voltage test generator (parallel connection of stages, partial operation) and the above aspects regarding the total charging voltage the stage charging energy can be calculated in principle for each possi ble test case. Normally a stage energy of 5 10 kJ per 100 - kV-stage and a stage energy of 10 20 kJ per 200-kV-stage will be sufficient. Whereas the lower values apply to transformers with lower power, the higher values apply to transformers with higher power (fig. 4). Often, impulse voltage test generators for power transformer testing have an energy of 15 kJ per 200-kV-stage,
a) Running the impulse voltage test generator in partial operation, i.e. with the minimum number of stages, being necessary to reach the required test voltage level.
b) Switching a certain number of generator stages r espectively in parallel and connect this parallel stages in series to reach the required test voltage.
Fig. 5: Impulse Voltage Test System IP 150/2000 G (150 kJ, 2000 kV) with impulse voltage divider and chopping multiple spark gap, with a stage energy of 15 kJ being used for the LI test of power transformers up to 245 kV
Fig. 7: LI test of power transformers by using the Glaninger-circuit, adjustment of the voltage shape at the voltage crest by means of an additional resistor Rt (optimal adjustment Rt = 300 Ohm for this example)
Fig. 8: LI test of power transformers by using the Glaninger-circuit, adjustment of the time to half-value T2 and the amplitude of opposite polarity d by means of the tail resistor Rp (optimal adjustment Rp = 60 Ohm for this example, T2 > 40 s, d < 50 %) With a Glaninger-circuit the front time T1, the time to half-value T2 and the amplitude of opposite polarity d of the LI test voltage can be set almost independently, i.e. T1 with the tail resistor Rs, T 2 and d with the resistors Rp und Rt (fig. 7 and 8). A variation of the Glaninger-coil inductance is as a rule not necessary. The Glaningercircuit enables for LI testing the most effective adaptation of the impulse voltage test generator and the transformer to be tested. An existing impulse voltage test generator can be utilised optimally.
6. Conclusion
The testing of power transformers with LI test voltage acc. to the IEC standards presupposes special knowledge of the interaction between the impulse voltage test generator and the inductive load. For example, there exists a close connection between the main data of the transformer to be tested and the required impulse capacitance of the impulse voltage test generator. There are also requirements related to the damping characteristic of the test circuit to utilise an existing impulse voltage test generator optimally. Some basic aspects and circuitries were described in this paper.
Oxidation of oil: Oxidation usually results in the formation of acids and sludge in the transformer liquid. It is mainly due to exposure to air and high operating temperatures.
Pressure-relief diaphragm broken: This is due to an internal fault causing excessive internal pressures or the transformer liquid level being too high or excessive internal pressure due to loading of transformer. Discoloration of transformer liquid: Discoloration is mainly caused by carbonization of the liquid due to switching, core failure, or contaminati ons.
Leakage of transformer liquid: Leakage can occur through screw joints, around gaskets, welds, casting, pressure-relief device, and so on. The main causes are improper assembly of mechanical parts, improper fi lters, poor joints, improper fi nishing of surfaces, defects in the material used, or insuffi cient tightness of mechanical parts. Moisture condensation: The main causes for moisture condensation are improper ventilation in open -type transformers and a cracked diaphragm or leaking gaskets in sealed-type transformer. Gas-sealed transformer troubles: In gas-sealed transformers, additional problems can be the loss of gas, oxygen content above 5%, or gas regulator malfunctions. These problems are caused by gas leaks above the oil, leaky valve seats, insuffi cient gas space, and/or insuffi cient fl ushing of gas space with nitrogen. Transformer switching equipment troubles: Many transformers are equipped with tap chargers and other switching equipment. The problems associated with these transformers may be excessive wearing of contacts, mechanism overtravel, moisture condensation in mechanism liquid, and others.
Excessive contact wear is due to loss of contact pressure from weakened springs or a contact-making voltmeter set at too narrow a bandwidth or insuffi cient time delay. Mechanism overtravel usually is due to defective or improper adjustment of controller
contacts. Moisture condensation is due to improper ventilation, and carbonization is due to excessive operation and lack of fi ltering. Othe r problems such as control fuse blowing and mechanism motor stalling are due to short circuits in the control circuit, mechanical binding, or low -voltage conditions in the control circuitry
AC Hi-Pot Test
The AC hi-pot test is applied to evaluate the condition of transformer windings. This test is recommended for all voltages, especially those above 34.5 kV. For routine maintenance testing of transformers, the test voltage should not exceed 65% of factory test voltage. However, the hi-pot test for routine maintenance is generally not employed on transformers because of the possibility of damage to the winding insulation. This test is commonly used for acceptance testing or after repair testing of transformers. The AC HV test value should not exceed 75% of the factory test value. When AC hi-pot testing is to be used for routine maintenance, the transformer can be tested at rated voltage for 3 min instead of testing at 65% of factory test voltage. The AC hi-pot test values for voltage systems up to 69 kV a re shown in Table 5.9. Testing procedures and test connections are similar to the DC hi-pot tests
TTR Test
The TTR test applies voltage to one winding of a transformer and detects the voltage being generated on another winding on the same core. In the case of a low voltage hand-crank powered TTR, 8 V AC is applied to the low-voltage winding of the transformer under test and a reference transformer in the TTR set. The HV windings of the transformer under test and the TTR reference transformer are connected through a null detecting instrument. After polarity has been established at 8 V, when the null reading is zero, the dial readings indicate the ratio of the transformer under test.
In the case of an electronic TTR test set, a voltage (typically 80 V AC) i s applied to the HV winding of the transformer under test. The voltage generated on the lowvoltage winding is measured and the voltage ratio between high and low windings is calculated. Voltage ratio is proportionally equal to turns ratio. The hand -crank
powered TTR, the handheld electronic TTR, and the three-phase electronic TTR are through c, respectively. The TTR test provides the following information: It determines the turns ratio and polarity o f single - and three-phase transformers, one phase at a time. It confi rms nameplate ratio, polarity, and vectors. It determines the ratio and polarity (but not voltage rating) of transformers without markings. Tests include all no-load tap positions on a transformer. Tests include all load taps on load, tap changer (LTC) transformers if connected for voltage ratio control. On LTC transformers connected for phase angle control, ratio and polarity are performed in neutral positions only. If tested on load taps, readings may be taken for reference for future comparison, but will deviate from nameplate ratings. LTC taps may be confi rmed by application of low three-phase voltage and reading volts and the phase angle for each. Identify trouble in transformer windings, such as open -circuit and short-circuits of turn-to-turn sensitivity. The standard deviation as defi ned by ANSI/IEEE C57.12.00 -2006, Section 9.1 states that results should be within 0.5% of nameplate markings, with rated voltage applied to one winding. The TTR with accuracy of 0.1% is accepted as a referee.