Beruflich Dokumente
Kultur Dokumente
Case 3
By: GROUP 5
Ariefka Sari Dewi
12/341231/PEK/17320
12/341246/PEK/17335
Hartatiek
12/341257/PEK/17346
Niken Andry
12/341279/PEK/17368
Rifqa
12/341295/PEK/17384
A. FACTS
Cementos Mexicanos (Cemex) is a multinational company that produces cement in
Mexico. Cemex is the largest cement manufacturer in the Americas, and third largest in
the world. Cemex began its international expansion in an effort to reduce its reliance on
the Mexican market to capitalize on demand in many countries. Cemex competes in the
global marketplace for both market share and capital. The international cement market,
like markets in other commodities such as oil, is a dollar-based market. For this reason
and for comparisons against its major competitors in both Germany and Switzerland, so
Cemex considers the U.S. dollar its functional currency. Cemex wants to increase its
market capitalization through global expansion and entering in Asia market. In the year
1998, Cemex was considering the construction a cement manufacturing facility on the
Indonesian island of Sumatra. The project, Semen Indonesia, would be a wholly owned
greenfield investment with a total installed capacity of 20 million metric tons per year
(mmt/y). There were three driving reasons for this project:
1. Initiate a productive presence in Southeast Asia.
2. Favorable long-term prospects for Asian infrastructure development and growth.
3. Positive prospects for producing and exporting from Indonesia due to the depreciation
of the Indonesian rupiah (Rp) in 1997.
In analyzing feasibility of this project, Cemex make a road map of the complete
multinational capital budgeting to enter in Indonesia market.
B. SITUATION ANALYSIS
1. Financial Assumption
This project would be held in Indonesia so the calculation was in Indonesian
Rupiah. Before the capital budgets (NPV and IRR) were calculated, financial assumptions
must be made. Based on the case, the financial assumption will be explained below.
a. Capital Investment
Cemex had production capacity of 20 million metric ton per year (mmt/y) with cost of
installed capacity $110/tonne. Cemex assumed exchange rate of Rp 10,000/US$ in the
year 1 and would be change consistent with inflation rate. Therefore, cost of initial
investment can be calculated by 20 million mmt/y*$110/tonne = $2.2 billion or Rp 22
trillion. The amount cost of plant and equipment were Rp 17,6 trillion and Cemex
assumed an annual depreciation charge of Rp 1.76 million (10 years straight-line
depreciation schedule).
b. Foreign Exchange Rate
This project was assuming that PPP holds for the Rp/US$ exchange rate. The spot rate
in year 0 was Rp 10.000/US$. The projected inflation rates for Indonesia were 30%
per annum and 3% per annum for United States. This table below shows that
calculation of spot rate Indonesian Rupiah against U.S. Dollar
Table 1: Spot Rate (Rp/US$)
Project year
1
(1.3/1.03)*
10,000
2
((1.3/1.03)^2)*
10,000
10,000
12,621
15,930
Calculation
Spot rate
(Rp/US$)
3
4
((1.3/1.03)^3)* ((1.3/1.03)^4)*
10,000
10,000
20,106
5
((1.3/1.03)^5)*
10,000
25,376
32,028
c. Financing
Capital structure was used by project viewpoint consists of 50% equity and 50% debt.
All equity form Cemex, 75% debt from Cemex, and 25% from a bank consortium
arranged by the Indonesian government. When, capital structure was used by parent
viewpoint consist of 60% equity and 40% debt. The loan is denominated in U.S.
dollars and Indonesian Rupiah. In U.S. dollars, the loan has 10% of annual interest
with maturity 5 years. In Indonesia Rupiah, the loan has 35% of annual interest with
maturity 8 years. This capital structure makes the difference of weighted average cost
of capital (WACC) between project viewpoint (used in Indonesian Rupiah) and parent
viewpoint (used in U.S. Dollar). This is calculation of WACC from project and parent
viewpoint:
Table 2: Calculation of WACC from Parent Viewpoint
Information
Risk-free rate
Credit spread
Cost of debt
Cost of debt, after-tax
Debt proportion
Cemex Beta
Equity premium
Cost of equity
Equity proportion
Calculation
8%*(1 0.35)
(13% - 6%)
(6% + 7%)*1.5
Result
6%
2%
8%
5.2%
40%
1.5
7%
16.5%
60%
Result
33%
2%
35%
24.5%
6.125%
38.835%
27.184%
20.388%
26.513%
50%
1
7%
40%
50%
d. Revenues
Cemex assumes that the 20 mmt/y facility is expected to operate at only 40% capacity
(producing, 8 million metric tonnes). Sales price of cement was $58/tonne and would
remain constant over the life project. Capacity is expected to be 50% in year 2 and
60% from year 3 on.
e. Costs
Costs of this project consist of manufacturing cost, production costs, and loading
costs. Manufacturing costs (labor, materials, power, etc.) were estimated at Rp
115,000 per tonne for 1999 and increasing in accordance with inflation rate of 30%
per year. Production costs are estimated Rp 20,000 per tonne for 1999 and increasing
in accordance with inflation rate of 30% per year.
2. Project Viewpoint Capital Budget
Evaluation of a project from local viewpoint serves some useful purposes, but it
should be subordinated to be evaluated from the parents viewpoint. In evaluating a
foreign projects performance relative to the potential of a competing project in the same
host country, we must pay attention to the projects local return. Almost any project
should at least be able to earn cash return equal to the yield available on host government
bonds (with the same maturity as projects economic life).
For project viewpoint, net cash flow or free cash flow is calculated by summing
EBITDA, recalculated taxes, and changes in net working capital. Capital budgeting is
estimated by using EBITDA, not EBT, which contains both depreciation and interest
expense. Furthermore, taxes are recalculated on the basis of EBITDA. The firms cost of
capital used in discounting also includes the deductibility of debt interest in its
calculation.
The initial investment of Rp 22 trillion is the total capital invested to support these
earnings. Although receivables average 50 to 55 days sales outstanding (DSO) and
inventories 65 to 70 DSO, payable and trade credit are also relative long at 114 DSO in
the Indonesian cement industry. Semen Indonesia expects to add approximately 15 net
DSO to its investment with sales growth.
The terminal value (TV) of project represents the continuing value of the cement
manufacturing facility in the years 5, last year of detailed pro forma financial analysis.
3
TV calculated as perpetual net operating cash flow after year 5. TV from Semen
Indonesia can be estimated by using form below.
Terminal Value
NOCF5 (1 g) 6,547,059 (1 0)
RP19,686,258
k WACC g
0.33257 0
The result of the capital budget from the project viewpoint indicate a negative
present value (NPV) of Rp 9,443,460 million or about Rp 9,4 trillion and internal rate of
return (IRR) of only 15.4% less than cost of capital about 33.257%. According to this
calculation, the project is not acceptable.
Tabel 4: Capital Budget: Cemex Indonesia (millions RP)
Project Year
Spot Rate (Rp/$)
EBITDA
Recalculated taxes
(@30%)
Net Operating
cash flow
Year 0
10,000
Additions to NWC
Initial Investment
Terminal Value
(22,000,000)
(22,000,000)
NPV @ 33.257%
IRR
($9,443,460)
15.4%
Year 1
12,621
2,979,029
Year 2
15,930
4,499,067
Year 3
20,106
6,504,982
Year 4
25,376
7,813,589
Year 5
32,028
9,352,941
(893,709)
(1,349,720)
(1,951,495)
(2,344,077)
(2,805,882)
2,085,320
3,149,347
4,553,487
5,469,512
6,547,059
(240,670)
(139,028)
(436,049)
(289,776)
(625,314)
19,686,258
1,844,650
3,010,319
4,117,438
5,179,736
25,608,003
Year 0
10,000
Dividend Remittance
Dividends paid (RP)
Withholding tax @ 15%
Net dividend remitted (RP)
Net dividend remitted ($)
License Fees Remittance
Fees remitted
Withholding tax @ 5%
Net dividend remitted (RP)
Net license fees remitted ($)
Debt Service Remittance
Promised interest paid ($)
Withholding tax @ 10%
Net interest remitted ($)
Principal payments remitted
($)
Year 1
12,621
Year 2
15,930
Year 3
20,106
Year 4
25,376
Year 5
32,028
0
0
0
0
0
0
0
0
560,423
(84,063)
476,360
24
555,757
(83,364)
472,393
19
651,450
(97,717)
553,732
17
117,126
(5,856)
111,270
8.8
184,787
(9,239)
175,547
11.0
279,871
(13,994)
265,877
13.2
353,235
(17,662)
335,573
13.2
445,831
(22,292)
423,539
13.2
82.5
(8.25)
74.3
69.0
(6.90)
62.1
54.1
(5.41)
48.7
37.8
(3.78)
34.0
19.8
(1.98)
17.8
135.1
148.6
163.5
179.9
197.8
0.0
8.8
209.4
218.2
0.0
11.0
210.7
221.8
23.7
13.2
212.2
249.1
18.6
13.2
213.9
245.7
17.3
13.2
215.7
246.2
(1,925)
614.66
(1,925)
(925.62)
-1.84%
218.2
221.8
249.1
245.7
860.8
In order to evaluate the projects cash flows that are returned to the parent
company, Cemex must discount these at the corporate cost of capital. If Cemex were
undertaking an investment of the same relative degree of risk of the firm itself, a simple
discount rate of 11.98% might me adequate. Cemex, however, requires new investment to
yield an additional 6% over the cost of capital for international projects. The discount rate
for Semen Indonesias cash flows repatriated to Cemex will therefore be discounted at
11.98% + 6%, or 17.98%. From the parent viewpoint capital budgeting, it is indicated a
negative NPV of US$925.6 million with IRR -1.84%. Based on this result yhis
investment is unacceptable from the parents viewpoint.
Multinational firm should invest only if they can earn a risk-adjusted return greater
than locally based competitors can earn on the same project. If they are unable to earn
superior returns on foreign projects, their stockholders would be better off buying shares
in local firms, where possible, and letting those companies carry out the local projects.
5
Most firms appear to evaluate foreign projects from both parent and project NPV and the
overall effect on consolidated earning of the firm. For foreign projects, must adjust for
agency cost and foreign exchange rate risks and costs.
B. KEY ISSUES
Cemex was using traditional capital budgeting for considering expansion in
Indonesia. From traditional capital budgeting, Cemex got negative NPV and IRR that is
less than WACC, not only from project viewpoint but also from parent viewpoint. These
calculations meant the investment should be rejected. Is there any wrong assumption that
Cemex use?
Cemex was considering expansion to Indonesia yet Cemex did not consider the
additional risk or sensitivity analysis from both project viewpoint and parent viewpoint.
From project viewpoint, sensitivity analysis could be measured from foreign exchange
risk and other sensitivity variable such as the capacity utilization rate. Furthermore, from
parent viewpoint, the additional risk can be measured in at least two ways, adjusting the
discount rates or adjusting the cash flows. What will happen if Cemex considers these
additional risks?
C. ALTERNATIVE SOLUTIONS
1. Changing in Foreign Exchange Rate
Cemex should consider additional risks for both project viewpoint and parent
viewpoint. Cemex should consider whether if the rate of rupiah was depreciated or
appreciated. We try to make some estimation based on this consideration, rupiah
depreciate and appreciate.
a. Rupiah depreciate
When the rate of rupiah depreciation were greater than US dollar at the PPP it
would make the assumed cash flows to Cemex worth less in dollars and the cheaper
rupiah made Semen Indonesia more competitive. It will happen caused by cash flow of
Semen Indonesia both cash inflows (export to Taiwan) and outflows (imported
components from parent company) are denominated in foreign currencies. Rupiah
depreciation would make higher inflation, so we would like to forecast the capital budget
with Indonesia inflation rate 40% (>30%). And the result is capital budget have the
negative NPV of Rp -6,435,034 and IRR of 24.5%, compared to 36.06%. This result
shows that the project should be rejected.
b. Rupiah appreciate
Rupiah appreciates because of the decreasing of inflation rate. For this estimation,
we assume that inflation Indonesia decrease 10% or become 20%, inflation America stays
the same or 3%, WACC for project is 30.45% and 17.98% for parent. Based on these
assumptions, we try to estimate NPV and IRR for both project viewpoint and parent view
point. For project viewpoint, we got a negative NPV of Rp 12,126,108 million and IRR
6.1% that is less than WACC. And for parent viewpoint, we got a negative NPV of
$921.83 million with a negative IRR 1.65%. Based on this estimation, we can assume that
this investment should be rejected.
c. Real Option
We can find the NPV and IRR based on the financial assumptions. When the NPV
value is negative, for example $-614.710 it mean that the project must be rejected. In this
6
NPV= Rp -6,435,034
p=33,3%
NPV= Rp -9,443,460
p=33,3%
Pesimist
NPV= Rp -9,443,460
p=50%
Project
Optimist
NPV= Rp -4,677,058
p=50%
Total NPV = (0.5 x Rp -9,443,460) +(0.5 x Rp -4,677,058)
= Rp -7,060,259
Therefore, using the real inflation rate and cost of capital data, this project is not
acceptable. Cemex should not build plant and equipment in Indonesia.
D. RECOMMENDATION
From all of our estimate with sensitivity analysis, this project should be rejected.
We adjusts increase and decrease in inflation rate, the project should not acceptable. We
also adjusts the sales volume into 50%-90%, but still the NPV is negative and IRR still
less than WACC. And we adjust the NPV and IRR by using real market condition, the
result stays the same, NPV still negative and IRR still less than WACC. This investment
could not applied in Indonesia and also the timing of investment was not in good
condition because Indonesia was suffering crisis during 1997-1998.
If Cemex really want to make a greenfield investment in Indonesia, there are
several recommendations that we can give for Cemex:
1. Cemex should use optimist assumption for calculating capital budgeting, both project
viewpoint and parent viewpoint.
2. Cemex should use Rupiah for the all debt. Cemex use US dollar as functional
currency, so the all revenue will be in US Dollar. At that time Rupiah was
depreciated, Cemex will get more Rupiahs if Cemex converted US Dollar to Rupiah.
3. In 1998, Indonesia faced economic crisis, but the crisis will not last forever. Cemex
should make assumption that crisis and hyperinflations are expected to normalize.
E. BIBLIOGRAPHY
Saphiro, Alan C. (2010). Multinational Financial Management 9th Edition. John Wiley
& Sons, Inc.
http://www.bps.go.id/aboutus.php?inflasi=1
http://www.usinflationcalculator.com/inflation/historical-inflation-rates/
http://www.imf.org/external/pubs/ft/weo/2013/02/weodata/weorept.aspx?sy=1997&ey=2
003&scsm=1&ssd=1&sort=country&ds=.&br=1&pr1.x=85&pr1.y=8&c=536%2C111&
s=PPPEX%2CPCPI%2CPCPIPCH%2CPCPIE%2CPCPIEPCH&grp=0&a=
http://data.worldbank.org/indicator/FR.INR.RINR?page=3
Appendix
Exhibit 1: Semen Indonesia Debt Service Schedule
Project Year
Spot Rate (Rp/$)
Year 0
10,000
Year 1
12,621
Year 2
15,930
Year 3
20,106
Year 4
25,376
Year 5
32,028
2,654,061
(962,500)
(95,939)
(1,058,439)
2,524,543
(928,921)
(129,518)
(1,058,439)
2,349,694
(883,590)
(174,849)
(1,058,439)
2,113,648
(822,393)
(236,046)
(1,058,439)
1,794,985
(739,777)
(318,662)
(1,058,439)
689.9
(82.5)
(135.1)
(217.6)
541.2
(69.0)
(148.6)
(217.6)
377.7
(54.1)
(163.5)
(217.6)
197.8
(37.8)
(179.9)
(217.6)
0.0
(19.8)
(197.8)
(217.6)
(825,000)
(1,351,329)
(2,176,329)
(689,867)
(1,486,462)
(2,176,329)
(541,221)
(1,635,108)
(2,176,329)
(377,710)
(1,798,619)
(2,176,329)
(197,848)
(1,978,481)
(2,176,329)
Actual (@ current
spot rate)
Interest Payment
Principal Payment
Total Payment
(1,041,262)
(1,705,561)
(2,746,823)
(1,098,949)
(2,367,915)
(3,466,864)
(1,088,160)
(3,287,494)
(4,375,654)
(958,480)
(4,564,190)
(5,522,670)
(633,669)
(6,336,691)
(6,970,360)
(2,746,823)
(3,466,864)
(4,375,654)
(5,522,670)
(6,970,360)
(409,082)
(546,940)
(580,770)
(435,821)
(881,453)
(1,652,385)
(2,765,571)
(4,358,210)
(1,290,535)
(2,199,325)
(3,346,341)
(4,794,031)
Year 4
25,376
16,000
58
1,471,813
Year 5
32,028
18,000
58
1,857,627
Year 0
10,000
Year 1
12,621
10,000
58
732,039
Year 2
15,930
12,000
58
923,933
Year 3
20,106
14,000
58
1,166,128
10
7,320,388
11,087,190
16,325,798
23,549,001
33,437,295
(1,150,000)
(200,000)
(252,427)
(1,262,136)
(2,864,563)
(1,794,000)
(312,000)
(393,786)
(1,968,932)
(4,468,718)
(2,720,900)
(473,200)
(597,243)
(2,986,214)
(6,777,556)
(4,042,480)
(703,040)
(887,332)
(4,436,660)
(10,069,512)
(5,912,127)
(1,028,196)
(1,297,723)
(6,488,616)
(14,726,662)
Gross Profit
4,455,825
6,618,472
9,548,241
13,479,489
18,710,633
License Fees
General & Admin
Expenses
EBITDA
(146,408)
(221,744)
(326,516)
(470,980)
(668,746)
(585,631)
3,723,786
(997,847)
5,398,881
(1,632,580)
7,589,146
(2,590,390)
10,418,119
(4,012,475)
14,029,412
(1,760,000)
1,963,786
(1,760,000)
3,638,881
(1,760,000)
5,829,146
(1,760,000)
8,658,119
(1,760,000)
12,269,412
(825,000)
(570,494)
(962,500)
(394,208)
(689,867)
(1,290,535)
(928,921)
729,557
(541,221)
(2,199,325)
(883,590)
2,205,010
(377,710)
(3,346,341)
(822,393)
4,111,675
(197,848)
(4,794,031)
(739,777)
6,537,756
0
(394,208)
(31)
0
729,557
46
0
2,205,010
110
1,995,610
2,116,064
83
1,961,327
4,576,429
143
Depreciation &
Amortization
EBIT
Year 1
13.592
8.000
58
788.350
6.306.796
Year 2
18.475
10.000
58
1.071.543
10.715.430
Year 3
25.111
12.000
58
1.456.466
17.477.595
Year 4
34.132
12.000
58
1.979.663
23.755.954
Year 5
46.393
12.000
58
2.690.804
32.289.647
(920.000)
(1.610.000)
(2.704.800)
(3.786.720)
(5.301.408)
(160.000)
(217.476)
(1.087.379)
(2.384.854)
(280.000)
(380.583)
(1.902.913)
(4.173.495)
(470.400)
(639.379)
(3.196.893)
(7.011.472)
(658.560)
(895.130)
(4.475.650)
(9.816.061)
(921.984)
(1.253.182)
(6.265.911)
(13.742.485)
Gross Profit
3.921.942
6.541.935
10.466.123
13.939.894
18.547.162
License Fees
General & Admin
Expenses
EBITDA
(126.136)
(214.309)
(349.552)
(475.119)
(645.793)
(504.544)
3.291.262
(964.389)
5.363.238
(1.747.760)
8.368.812
(2.613.155)
10.851.620
(3.874.758)
14.026.611
(1.760.000)
1.531.262
(1.760.000)
3.603.238
(1.760.000)
6.608.812
(1.760.000)
9.091.620
(1.760.000)
12.266.611
Depreciation &
Amortization
EBIT
Year 0
10.000
11
(825.000)
(781.788)
(962.500)
(1.038.026)
(689.867)
(1.844.413)
(928.921)
140.037
(541.221)
(3.288.757)
(883.590)
1.895.244
(377.710)
(5.251.943)
(822.393)
2.639.573
(197.848)
(7.920.352)
(739.777)
3.408.635
0
(1.038.026)
(76)
42.011
98.026
5
299.176
1.596.067
64
1.091.048
1.548.525
45
1.022.590
2.386.044
51
Year 1
13.592
3.291.262
Year 2
18.475
5.363.238
Year 3
25.111
8.368.812
Year 4
34.132
10.851.620
Year 5
46.393
14.026.611
(987.379)
(1.608.971)
(2.510.644)
(3.255.486)
(4.207.983)
2.303.883
3.754.266
5.858.168
7.596.134
9.818.628
(240.670)
(139.028)
(436.049)
(289.776)
(625.314)
Year 0
10.000
Additions to NWC
Initial Investment
Terminal Value
(22.000.000)
(22.000.000)
NPV @ 36,06%
IRR
27.228.531
2.063.213
3.615.238
5.422.119
7.306.358
36.421.845
(Rp6.435.034)
24,5%
Semen Indonesias Remittance and Capital Budget: Parent Viewpoint (million RP & million
US$)
Project Year
Spot Rate (Rp/$)
Dividend Remittance
Dividends paid (RP)
Withholding tax @ 15%
Net dividend remitted (RP)
Net dividend remitted ($)
License Fees Remittance
Fees remitted
Withholding tax @ 5%
Net dividend remitted (RP)
Net license fees remitted ($)
Debt Service Remittance
Promised interest paid ($)
Withholding tax @ 10%
Net interest remitted ($)
Principal payments remitted ($)
Year 0
10.000
Year 1
12.621
Year 2
15.930
Year 3
20.106
Year 4
25.376
Year 5
32.028
0
0
0
0
0
0
0
0
798.034
(119.705)
678.329
34
774.263
(116.139)
658.123
26
1.193.022
(178.953)
1.014.069
32
126.136
(6.307)
119.829
9,5
214.309
(10.715)
203.593
12,8
349.552
(17.478)
332.074
16,5
475.119
(23.756)
451.363
17,8
645.793
(32.290)
613.503
19,2
82,5
(8,25)
74,3
135,1
69,0
(6,90)
62,1
148,6
54,1
(5,41)
48,7
163,5
37,8
(3,78)
34,0
179,9
19,8
(1,98)
17,8
197,8
Dividends
License fees
Debt service
Total
0,0
9,5
209,4
218,9
Initial Investment
Terminal Value
0,0
12,8
210,7
223,5
33,7
16,5
212,2
262,5
25,9
17,8
213,9
257,6
31,7
19,2
215,7
266,5
(1.925)
586,91
(1.925)
(912,79)
-2%
218,9
223,5
262,5
257,6
853,4
33%
2%
35%
24.50%
28%
19.71%
50%
Cemex Indonesia
Equity premium
Cost of equity
% equity
1
7%
40%
50%
WACC
30.4533%
Year 0
10,000
Additions to NWC
Initial Investment
Terminal Value
(22,000,000)
(22,000,000)
NPV @30.4533%
IRR
Year 1
11,650
2,666,796
Year 2
13,573
3,708,909
Year 3
15,814
4,936,898
Year 4
18,424
5,457,526
Year 5
21,464
6,009,723
(800,039)
(1,112,673)
(1,481,070)
(1,637,258)
(1,802,917)
1,866,757
2,596,237
3,455,829
3,820,268
4,206,806
(240,670)
(139,028)
(436,049)
(289,776)
(625,314)
13,813,958
1,626,087
2,457,209
3,019,780
3,530,492
17,395,450
($12,126,108)
6.1%
Year 0
10,000
Year 1
12,621
Year 2
15,930
Year 3
20,106
Year 4
25,376
Year 5
32,028
0
0
0
0
0
0
0
0
798,034
(119,705)
678,329
34
774,263
(116,139)
658,123
26
1,193,022
(178,953)
1,014,069
32
126,136
(6,307)
214,309
(10,715)
349,552
(17,478)
475,119
(23,756)
645,793
(32,290)
13
119,829
9.5
203,593
12.8
332,074
16.5
451,363
17.8
613,503
19.2
82.5
(8.25)
74.3
135.1
69.0
(6.90)
62.1
148.6
54.1
(5.41)
48.7
163.5
37.8
(3.78)
34.0
179.9
19.8
(1.98)
17.8
197.8
0.0
9.5
209.4
218.9
0.0
12.8
210.7
223.5
33.7
16.5
212.2
262.5
25.9
17.8
213.9
257.6
31.7
19.2
215.7
266.5
(1,925)
586.91
(1,925)
(912.79)
-2%
218.9
223.5
262.5
257.6
853.4
Year 0
10,000
Year 1
12,621
10,000
58
732,039
7,320,388
Year 2
15,930
12,000
58
923,933
11,087,190
Year 3
20,106
14,000
58
1,166,128
16,325,798
Year 4
25,376
16,000
58
1,471,813
23,549,001
Year 5
32,028
18,000
58
1,857,627
33,437,295
(1,150,000)
(200,000)
(252,427)
(1,262,136)
(2,864,563)
(1,794,000)
(312,000)
(393,786)
(1,968,932)
(4,468,718)
(2,720,900)
(473,200)
(597,243)
(2,986,214)
(6,777,556)
(4,042,480)
(703,040)
(887,332)
(4,436,660)
(10,069,512)
(5,912,127)
(1,028,196)
(1,297,723)
(6,488,616)
(14,726,662)
Gross Profit
4,455,825
6,618,472
9,548,241
13,479,489
18,710,633
License Fees
General & Admin
Expenses
EBITDA
(146,408)
(221,744)
(326,516)
(470,980)
(668,746)
(585,631)
3,723,786
(997,847)
5,398,881
(1,632,580)
7,589,146
(2,590,390)
10,418,119
(4,012,475)
14,029,412
(1,760,000)
1,963,786
(1,760,000)
3,638,881
(1,760,000)
5,829,146
(1,760,000)
8,658,119
(1,760,000)
12,269,412
(825,000)
(570,494)
(962,500)
(689,867)
(1,290,535)
(928,921)
(541,221)
(2,199,325)
(883,590)
(377,710)
(3,346,341)
(822,393)
(197,848)
(4,794,031)
(739,777)
Depreciation &
Amortization
EBIT
Interest on Cemex
Debt
Forex Losses on Debt
Interest on Local Debt
14
EBT
(394,208)
729,557
2,205,010
4,111,675
6,537,756
0
(394,208)
0
729,557
0
2,205,010
1,995,610
2,116,064
1,961,327
4,576,429
(31)
46
110
83
143
Year 1
12,621
3,723,786
Year 2
15,930
5,398,881
Year 3
20,106
7,589,146
Year 4
25,376
10,418,119
Year 5
32,028
14,029,412
(1,117,136)
(1,619,664)
(2,276,744)
(3,125,436)
(4,208,824)
2,606,650
3,779,217
5,312,402
7,292,683
9,820,588
(240,670)
(139,028)
(436,049)
(289,776)
(625,314)
Year 0
10,000
(22,000,000)
29,529,388
(22,000,000)
NPV @ 33.257%
IRR
($4,677,058)
25.4%
2,365,980
3,640,189
4,876,353
7,002,907
38,724,662
Year 0
10,000
Dividend Remittance
Dividends paid (RP)
Withholding tax @ 15%
Net dividend remitted
(RP)
Net dividend remitted ($)
License Fees Remittance
Fees remitted
Withholding tax @ 5%
Net dividend remitted
(RP)
Net license fees remitted
($)
Debt Service Remittance
Promised interest paid ($)
Withholding tax @ 10%
Net interest remitted ($)
Principal payments
remitted ($)
Year 1
12,621
Year 2
15,930
Year 3
20,106
Year 4
25,376
Year 5
32,028
0
0
0
0
1,102,505
(165,376)
1,058,032
(158,705)
2,288,215
(343,232)
0
0
0
0
937,129
47
899,327
35
1,944,982
61
146,408
(7,320)
221,744
(11,087)
326,516
(16,326)
470,980
(23,549)
668,746
(33,437)
139,087
210,657
310,190
447,431
635,309
11.0
13.2
15.4
17.6
19.8
82.5
(8.25)
74.3
69.0
(6.90)
62.1
54.1
(5.41)
48.7
37.8
(3.78)
34.0
19.8
(1.98)
17.8
135.1
148.6
163.5
179.9
197.8
Dividends
License fees
Debt service
Total
0.0
11.0
209.4
220.4
Initial Investment
Terminal Value
Free Cash Flow (FCF)
NPV @ 17.98%
IRR
0.0
13.2
210.7
224.0
46.6
15.4
212.2
274.3
35.4
17.6
213.9
266.9
60.7
19.8
215.7
296.2
(1,925)
921.98
(1,925)
(739.57)
3.54%
220.4
224.0
274.3
266.9
1,218.2
Changing
598,54%
-30,00%
-30,00%
-30,00%
-30,00%
-30,00%
Inflation Rate
77,54%
54,28%
37,99%
26,60%
18,62%
13,03%
Information
Risk-free rate
Credit spread
Cost of debt
Cost of debt, after-tax
Debt proportion
Cemex Beta
Equity premium
Cost of equity
Equity proportion
11.5%*(1 0.35)
(9.5% + 8.41%)*1.5
Result
9.5%
2%
11.5%
7.48%
40%
1.5
8.41%
22.12%
60%
Result
48.28%
2%
50.28%
35.2%
8.79%
50.49%
35.34%
26.518%
35.31%
50%
1
10.16%
58.44%
50%
Semen Indonesias Debt Service Schedules and Foreign Exchange Losses (millions of Rp and
US$)
Project Year
Year 0
Year 1
Year 2
Year 3
Year 4
Year 5
16
10,375
15,692
21,230
26,349
30,642
33,956
2,654,061
(962,500)
(95,939)
(1,058,439)
2,524,543
(928,921)
(129,518)
(1,058,439)
2,349,694
(883,590)
(174,849)
(1,058,439)
2,113,648
(822,393)
(236,046)
(1,058,439)
1,794,985
(739,777)
(318,662)
(1,058,439)
689,9
(82,5)
(135,1)
(217,6)
541,2
(69,0)
(148,6)
(217,6)
377,7
(54,1)
(163,5)
(217,6)
197,8
(37,8)
(179,9)
(217,6)
0,0
(19,8)
(197,8)
(217,6)
(825,000)
(1,351,329)
(2,176,329)
(689,867)
(1,486,462)
(2,176,329)
(541,221)
(1,635,108)
(2,176,329)
(377,710)
(1,798,619)
(2,176,329)
(197,848)
(1,978,481)
(2,176,329)
(1,294,619)
(2,120,553)
(3,415,172)
(1,464,577)
(3,155,736)
(4,620,313)
(1,426,066)
(4,308,356)
(5,734,422)
(1,157,364)
(5,511,256)
(6,668,619)
(671,806)
(6,718,058)
(7,389,864)
(3,415,172)
(4,620,313)
(5,734,422)
(6,668,619)
(7,389,864)
(469,619)
(769,224)
(774,710)
(1,669,274)
(884,845)
(2,673,248)
(779,654)
(3,712,637)
(473,958)
(4,739,577)
(1,238,843)
(2,443,984)
(3,558,093)
(4,492,290)
(5,213,535)
Year 0
10,375
Year 1
15,693
10,000
58
910,176
9,101,764
Year 2
21,230
12,000
58
1,231,326
14,775,910
Year 3
26,350
14,000
58
1,528,293
21,396,098
Year 4
30,643
16,000
58
1,777,314
28,437,032
Year 5
33,957
18,000
58
1,969,508
35,451,151
(1,150,000)
(200,000)
(313,854)
(1,752,600)
(304,800)
(524,800)
(2,012,500)
(350,000)
(782,728)
(2,244,800)
(390,400)
(1,071,514)
(2,463,300)
(428,400)
(1,375,882)
(1,569,270)
(2,623,998)
(3,913,641)
(5,357,571)
(6,879,411)
17
Total
(3,233,124)
(5,206,197)
(7,058,870)
(9,064,285)
(11,146,993)
Gross Profit
5,868,640
9,569,713
14,337,228
19,372,747
24,304,158
License Fees
General & Admin
Expenses
EBITDA
(182,035)
(295,518)
(427,922)
(568,741)
(709,023)
(728,141)
4,958,464
(1,329,832)
7,944,363
(2,139,610)
11,769,696
(3,128,074)
15,675,932
(4,254,138)
19,340,997
Depreciation &
Amortization
EBIT
(1,760,000)
3,198,464
(1,760,000)
6,184,363
(1,760,000)
10,009,696
(1,760,000)
13,915,932
(1,760,000)
17,580,997
(825,000)
(1,238,918)
(962,500)
172,046
(689,867)
(2,443,965)
(928,921)
2,121,610
(541,221)
(3,558,271)
(883,590)
5,026,614
(377,710)
(4,492,673)
(822,393)
8,223,156
(197,848)
(5,213,841)
(739,777)
11,429,531
51,614
120,432
8
636,483
1,485,127
70
2,196,081
2,830,533
107
4,663,028
3,560,128
116
3,428,859
8,000,672
236
Capital Budget: Cemex Indonesia (million RP & million US$) Project Viewpoint
Project Year
Spot Rate (Rp/$)
EBITDA
Recalculated taxes
(@30%)
Net Operating cashflow
Year 0
10,375
Additions to NWC
Initial Investment
Terminal Value
(22,000,000)
(22,000,000)
NPV @ 45,29%
IRR
Year 1
15,693
4,958,464
Year 2
21,230
7,944,363
Year 3
26,350
11,769,696
Year 4
30,643
15,675,932
Year 5
33,957
19,340,997
(1,487,539)
3,470,925
(2,383,309)
5,561,054
(3,530,909)
8,238,787
(4,702,780)
10,973,153
(5,802,299)
13,538,698
(240,670)
(139,028)
(436,049)
(289,776)
(625,314)
40,709,318
3,230,255
5,422,026
7,802,738
10,683,377
53,622,702
(Rp3,983,785)
37.7%
Year 0
10,000
Year 1
12,621
Year 2
15,930
Year 3
20,106
Year 4
25,376
Year 5
32,028
0
0
0
0
0
0
0
0
1,415,267
(212,290)
1,202,977
60
1,780,064
(267,010)
1,513,055
60
4,000,336
(600,050)
3,400,286
106
182,035
(9,102)
172,934
13,7
295,518
(14,776)
280,742
17,6
427,922
(21,396)
406,526
20,2
568,741
(28,437)
540,304
21,3
709,023
(35,451)
673,572
21,0
18
82,5
(8,25)
74,3
69,0
(6,90)
62,1
54,1
(5,41)
48,7
37,8
(3,78)
34,0
19,8
(1,98)
17,8
135,1
148,6
163,5
179,9
197,8
0,0
13.7
209.4
223.1
0.0
17.6
210.7
228.4
59,8
20.2
212.2
292.3
59.6
21.3
213.9
294.8
106.2
21.0
215.7
342.9
(1,925)
614,70
(1,925)
(947,35)
0.97%
223.1
228.4
292.3
294.8
957.6
19