MMSL-013
Amendment Detail
Prepared
By
E Joefield
Page 1 of 5
Approved
By
J Main
Date
May
2005
Category
Equipment Description
Specification/Legislation
Application Test
NOTE:
Proof Loads
Davit Test
Winch Brake Test Static
Winch Brake Test Dynamic
Examination Requirement
Internal Examination
Identification
Certification
EC Declaration of Conformity
Declaration of Incorporation
Davit Certification, Life Boat Certification
Wire Rope Certification and all Ancillary Certificates
Wire Termination Certificates
NDT Examination Report
SWL x 2.2
SWL x 1.5
SWL x 1.1
MMSL-013
Equipment Description
Examination
Page 2 of 5
The thorough examination will comprise of but not be limited to the following:
Examination Procedure
1.0
Safety
1.1
During any work being carried out on life boats and davits, safety harness will be
worn and attached to a secure anchorage.
2.0
Davits
2.1
Check the main davit structure for mechanical damage, weld cracking, and bolt
security.
Check the condition of all sheaves, for sheave groove wear, cracking, loose/worn
sheaves, bearings.
Check all lifting accessories, maintenance pennants, shackles, D ring/master
links, etc.
Check the wire rope falls for broken wires lubrication etc, also check terminations
i.e. resin socket / open wedge sockets, inspect using Bridon Examination and Test
Procedure for wire rope and terminations.
Check davit specification plate for details and check against actual specification i.e
does the plate information match the actual boat and davit details.
2.2
2.3
2.4
2.5
3.0
Winches
3.1
3.2
3.3
3.4
3.5
MMSL-013
Equipment Description
Test
Page 3 of 5
Test Procedure
1.0
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
Test Complete
2.0
2.1
2.2
2.3
2.4
Remove wire rope sling from sheave at top of davit and refit winch wire.
Connect calibrated load cell/test clock and water bag to winch wire.
Insert supply hose in water bag and slew outboard.
Mark the winch drum position in relation to the davit structure (i.e. two chalk marks)
to enable detection of any creep.
Fill water bag until a weight of SWL x 1.5 is indicated and leave suspended for
approximately 5 minutes. Check the position of chalk marks mentioned above.
2.5
MMSL-013
Equipment Description
Test
Page 4 of 5
b)
c)
2.6
Lower the load for at least 1 complete revolution of the winch drum and check the
winch brake efficiency.
Discharge contents of water bag and slew inboard.
Carry out visual examination to ensure that testing has not exposed any defects.
Carry out post-load test NDT.
2.7
2.8
2.9
Test Complete
3.0
3.1
Slew davit outboard and proceed to fill water bag until a load of SWL x 1.1 is
obtained.
Withdraw supply hose and if using a load cell with remote readout, disconnect
cable or ensure it is long enough for the descent rate test (approx. 10m).
Mark with winch drum with a corresponding mark on the davit structure to enable
the counting of drum revolutions during drop test.
3.2
3.3
MMSL-013
Equipment Description
Test
Page 5 of 5
Release brake/start stop watch simultaneously and allow to free fall for six
seconds.
By whatever method used in (3), obtain the rope measurement and ensure the
descent rate falls between 90 180ft/min. (27.4m 54.8m).
If all satisfactory, discharge contents of water bag, spool in winch wire with testing
equipment and slew inboard.
Re-examine to ensure that testing has not exposed any defects and where
appropriate employ NDT techniques.
Test Complete
4.0