Sie sind auf Seite 1von 1

Type

Name of the Project/Tender

Brief Scope of Work


Provide an adequate F&G detection and alarm system to replace the existing aging system at Zirku with a new F&G system to increase the level of safety on the facility. ZR Airport expansion shall accommodate the following while keeping existing facilities intact: * Four helipads. * Two taxiways. * One access way. * Lighting and marking associated with above P-8276: Gas Injection and Gas Lift Facilities

Location of the Project

Planned start & finish Dates


Planned Award : Q4 2012 Planned Finish : Q4 2014

Construction P-8363 : Fire & Gas detection system at Zirku

Zirku

Construction P 8381 - Zirku Airport Upgrade

Zirku

Planned Award : Q3 2012 Planned Finish : Q1 2014

Construction UZ750 Brownfiled Projects

Upper Zakum

Planned Award : Q1 2012 Planned Finish : Q1 2013 Planned Award : Q2 2013 Planned Finish : Q1 2015

EPC

Installation of RO type desalination plants with total capacity of ~ 4450m3/day, new centralised STP, decentralied STUs and associated P-8362 :Potable Water & Sewage Treatment infrastructure/ piping upgrade to meet acute shortage of potable water and Plant at Zirku sewage treatment plant at Zirku. EPC works to be carried for this project.

Zirku

FEED & EPC

UZ750 Brownfiled Projects

P-8385 Switchgear Replacement in Upper Zakum field.

Upper Zakum

EPC

UZ750 Brownfiled Projects

P-8341 Water Injection Plant Upgrade & P-8361 Cooling Water System Upgrade Installation of additional power generation facilities at Zirku Island since the existing power generation facilities enhancement due to the operational constraints for maintenance of aging turbines, increase in demand for the future projects and improve flexibility of operations Construct an air conditioned hanger (23m X 23m) complet with offices, electrical/water/drainage utilities, communication facilities, standby generator, fire detection and fighting system, ..etc. Installation of jet fuel facility including but not necessary limited to civil foundations, associated piping system, electrical, instrumentation, fire detection and protection system (Pumps & tanks will be free issued by ZADCO ). To build a seventh Crude oil storage tank on Zirku island with a capacity of Barrels 1 million. Engineer, procure and construct the offshore facilities for the UZ750 Project Engineer, procure and construct the onshore (on island) facilities for the UZ750 Project Level island surface and construct the early civil work structures, trenches, roads and other requirements on the islands Design and construct camp facilities for each island

Upper Zakum

FEED Planned Award : Q1 2012 Planned Finish : Q1 2013 EPC Planned Award : Q4 2013 Planned Finish : Q1 2018 EPC Planned Award : Q1 2013 Planned Finish : Q4 2014 EPC Planned Award : Q2 2013 Planned Finish : Q2 2015

Project

P 8374 - Power upgrade at ZIRKU

Zirku

Project

P 8442 - Helicopter Maintenance Hanagr P8417 - Aviation Fuel Facility

Zirku

EPC Planned Award : Q1 2013 Planned Finish : Q4 2014

9 10 11 12

EPC EPC EPC EPC

(P8382) - 7th Crude Oil Storage Tank at Zirku UZ750 Sub-sea Pipelines, Cables, Offshore Structures & Brownfied Work (EPC-1) UZ750 Island Surface Facilities Early Civil Works

Zirku Upper Zakum Upper Zakum Upper Zakum

Planned Award : Q1 2013 Planned Finish : Q2 2015 Planned Award : Q2 2012 Planned Finish : Q2 2015 Planned Award : Q3 2012 Planned Finish : Q1 2016 Planned Award : Q1 2012 Planned Finish : Q22015 Planned Award : Q2 2012 Planned Finish : Q2 2015

13

EPC

Temporary Containerized Camp Facilities

Upper Zakum