LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM Construction Status Report June 30, 2012

1001 SOUTH VALLEY VIEW BOULEVARD LAS VEGAS, NEVADA 89153 702-870-2011

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM

CONSTRUCTION STATUS REPORT

June 30, 2012

LVVWD ENGINEERING DEPARTMENT PLANNING DIVISION

PREFACE

The Las Vegas Valley Water District (District) maintains a long range facility planning process to determine the capital facilities necessary to continue meeting water requirements within the District's service area. As these capital facilities are defined, they are incorporated into the Major Construction Program (MCP). On February 8, 1995, the Board approved the consolidation of the uncompleted portion of two existing major construction programs, MCP IIIR and MCP IV, with 16 new projects under a single ongoing MCP. The existing program is entitled the Las Vegas Valley Water District Major Construction Program. The existing projects of MCP IIIR and MCP IV will keep their old numbering system, but all new projects will have a four digit numbering system; the first two digits will designate the calendar year the project was approved by the Board, the second two will be in sequential order. The MCP is a dynamic rather than static program; projects will be added, changed, or deleted as necessary to meet changing conditions in the District's service area. This Construction Status Report details the current status of projects in the MCP; it does not report on other District capital improvement projects. Expenditures shown in this report are on an accrual basis.

TABLE OF CONTENTS

PART I Table I Table II Table III

MAJOR CONSTRUCTION PROGRAM Project Listings and Projected Expenditures Project Data for Well Drilling and Development Projects Project Data for Well Equipping Projects Project Data Sheets

PAGE 1 5 6 7 156 157

Table IV Table V

Well Locations Project Schedules for Reservoirs, Pumping Stations, Pipelines, and Miscellaneous Projects Completed Projects Cancelled Projects

Table VI Table VII

160 164

PART II Water Usage and Production Data for the LVVWD Service Area

TABLE I LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM PROJECT LISTINGS AND PROJECTED EXPENDITURES
PROJECTED EXPENDITURES (Thousands) FY 12/13 FIRST QUARTER $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0.00 $0.00 $7,392,253.42 $369,792.57 $0.00 $0.00 $0.00 Completed Completed Completed Under Design Pending Pending Pending Pending Pending Completed Under Design Under Design Pending Under Design Completed Completed Completed Pending Pending Pending Completed Under Construction $143,587.46 $248,699.50 $12,910,854.28 $116,986.82 $0.00 $0.00 $16,136.38 $0.00 $0.00 $2,793,653.47 $242,295.39 $874,181.22 $0.00 $126,694.55 $257,080.81 $1,696,693.06 $807,261.56 $0.00 $0.00 $0.00 $27,605,671.64 $834,109.07 $0.00 $0.00 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 FY 12/13 SECOND QUARTER FY 12/13 THIRD QUARTER AFTER THIRD QUARTER $1,166 $140 $800 $1,287 $162 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,320 $8 $634 $21,614 $331 $0 $0 $0 $0 $401 $2,900 $3,000 $534 $5,000 $1,909 $0 $9,394 $11,499 $156 $1,565 $0 $0 $0 $1,980 $1,000 $2,750 $0 $0 $0 Reported Under MCP 04-04 Reported Under MCP 04-04 $0 PROJECT COST (b) (Thousands) $5,000 $140 $800 $1,287 $162 $848 $1,100 $0 $0 $0 $582 $972 $915 $0 $1,320 $7,400 $1,004 $21,614 $331 $0 $144 $249 $12,911 $518 $2,900 $3,000 $550 $5,000 $1,909 $2,794 $9,636 $12,373 $156 $1,692 $257 $1,697 $807 $1,980 $1,000 $2,750 $27,606 $834 $0 $0

Construction Status Report


PROJECT TITLE STATUS (a) AS OF 06/30/2012 Under Construction Pending Pending Pending Pending Completed Completed Cancelled $0.00 $0.00 $582,342.08 $971,949.88 $915,244.46 $0.00 $1,099,728.07 $847,866.14 $0.00 $0.00 $0.00 $3,833,646.92 $0.00 ACTUAL EXPENDITURES AS OF 06/30/2012 Reported Under MCP 4-3 Cancelled Completed Completed Completed Reported Under MCP 4-68 Pending Pending Pending Pending Pending Cancelled

MCP NO.

CONT. NO.

4-17 4-53

(c) (c)

Water Resource Research and Development Acquire Sites for Future Wells

4-57

(c)

SCADA System Expansion and Upgrade

4-58

(c)

Artificial Recharge Wells (e)

4-58

(c)

Artificial Recharge Wells (d)

4-58

674

Artificial Recharge Wells (d)

4-58

675

Artificial Recharge Wells (d)

4-58

676

Equip Artificial Recharge Wells, AR-2 thru AR-9 (e)

4-58

694

Artificial Recharge Wells (e)

4-58

706

Artificial Recharge Wells (e)

4-58

707

Artificial Recharge Wells (e)

4-58

711

Artificial Recharge Wells (d)

4-58

712

Artificial Recharge Wells (d)

4-58

783

Artificial Recharge Wells (e)

97-01

(c)

Reservoir Site Acquisitions Phase I

97-10

(c)

3665 Zone Reservoir

97-11

(c)

3665 Zone Reservoir Inlet/Outlet Pipeline

99-04

(c)

Jean Transmission System

00-02

(c)

North Well Field/Las Vegas Springs Preserve Infrastructure

00-02

(c)

North Well Field/Las Vegas Springs Preserve Infrastructure: Charleston Heights Site Remediation

00-02

1015

North Well Field/Las Vegas Springs Preserve Infrastructure: North Well Field Site Clean Up

00-02

1020

North Well Field/Las Vegas Springs Preserve Infrastructure: Las Vegas Springs Preserve Cienega

00-02

1024

North Well Field/Las Vegas Springs Preserve Infrastructure: Las Vegas Springs Preserve Site Infrastructure

00-02

1245

North Well Field/Las Vegas Springs Preserve Infrastructure: Las Vegas Springs Preserve Trail Extension and Realignment

00-03

(c)

North Well Field Archeological and Historical Stabilization

00-04

(c)

North Well Field Environmental Stabilization

01-02

(c)

Replacement Well No. 38A

02-05

(c)

Reservoir Site Acquisition

02-06

(c)

Purchase of Groundwater Rights in the Las Vegas Valley

03-09

1185

Bermuda 2745 Zone Pumping Station Discharge Pipeline

03-09

1242

Bermuda 2745 Zone Pumping Station Discharge Pipeline Phase II

03-10

1212

Sloan 2745 Zone Reservoir

03-12

(c)

Security System Upgrades

03-12

1169

Security System Upgrades: Communication Network Upgrade, Phase II

03-12

1177

Security System Upgrades: Security Telecommunications Network Infrastructure

03-12

1254

Security System Upgrades: Communication Network Upgrade, Phase I

03-12

1263

Security System Upgrades: Communication Network Upgrade, Phase III

03-14

(c)

System Communication Network Improvements

04-02

(c)

Sunrise Mountain 2150 Zone Reservoir Site Acquisition

04-03

(c)

Stewart 2150 Zone Pumping Station Improvements

04-04

1150

Cactus 2538 Zone Reservoir

04-04

1323

Cactus 2538 Zone Reservoir On-Site Improvements

04-06

1150

Cactus 2635 Zone Pumping Station

04-06

1323

Cactus 2538 Zone Reservoir On-Site Improvements

MCP NO. PROJECT TITLE STATUS (a) AS OF 06/30/2012 Under Design $0.00 $29,106.91 $0.00 $0.00 $11,778,479.74 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $501,423.11 $1,828,434.57 $158.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Pending Pending Pending Pending Pending Pending Pending Pending Completed Completed Completed Completed Completed Pending Pending Pending Completed Completed Under Design Pending Pending Pending Under Design Pending Completed Completed $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $885,769.58 $160,369.54 $691,299.50 $329,063.30 $495,379.96 $0.00 $0.00 $0.00 $0.00 $719,616.37 $60,040.06 $0.00 $0.00 $0.00 $141,179.79 $0.00 $576,331.32 $451,960.69 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $125 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,434 $14,194 $0 $0 $0 $10,567 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $314 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $13,471 $5,636 $14,644 $1,728 $20,128 $6,376 $406 $4,617 $1,120 $3,642 $1,706 $5,000 $5,000 $2,000 $2,133 $37,222 $1,520 $0 $0 $6,561 $15,500 $3,100 $8,800 $500 $15,500 $2,500 $7,200 $1,100 $3,516 $444 $159 $0 $0 $0 $0 $0 $0 $0 $0 $1,572 $0 $769 $2,100 $13,100 $4,000 $219 $10,267 $0 $0

CONT. NO.

04-08

1232

Centennial 2635 Zone Reservoir

PROJECTED EXPENDITURES (Thousands) ACTUAL PROJECT FY 12/13 FY 12/13 FY 12/13 AFTER EXPENDITURES COST (b) AS OF FIRST SECOND THIRD THIRD (Thousands) 06/30/2012 QUARTER QUARTER QUARTER QUARTER $29,280 $2,810,542.06 $0 $0 $0 $26,469 $0 $13,500 $5,636 $14,644 $48,701 $20,128 $6,376 $406 $4,617 $1,120 $3,642 $1,706 $5,000 $5,000 $2,000 $2,634 $39,050 $1,520 $0 $0 $7,000 $15,500 $3,100 $8,800 $500 $15,500 $2,500 $7,200 $1,100 $3,516 $444 $162 $886 $160 $691 $329 $495 $0 $0 $0 $1,572 $720 $829 $2,100 $13,100 $4,000 $360 $10,267 $576 $452

04-09

1232

Centennial 2745 Zone Pumping Station

04-10 Pending Pending Under Design Under Design Under Design Under Design Pending Pending Pending Pending Pending Pending Pending Under Design Under Design Pending

1213

Log Cabin 3205 Zone Reservoir

Reported Under MCP 04-08 Pending

Construction Status Report


Reported Under MCP 05-10 Reported Under MCP 05-10 Pending Pending Pending Pending

04-11

(c)

Log Cabin 3205 Zone Reservoir Inlet/Outlet Pipeline

04-12

(c)

Leonard R. Fayle Water Facility Improvements

04-12

1206

Leonard R. Fayle Water Facility Improvements: Fayle Water Facility Improvements

04-12

1257

Leonard R. Fayle Water Facility Improvements: Fayle 2168 Zone Satellite Reservoir

04-12

1258

Leonard R. Fayle Water Facility Improvements: Fayle 2168 Zone Satellite Reservoir Inlet/Outlet Pipeline

04-15

1182

Pressure Monitoring Stations

04-17

(c)

Sunrise Mountain 2150 Zone Reservoir

04-18

(c)

Sunrise Mountain 2150 Zone Reservoir Inlet/Outlet Pipeline

04-19

(c)

Bonanza 2150 Zone Pipeline

04-20

(c)

Washington 2150 Zone Pumping Station Discharge Pipeline

04-24

(c)

PRV Metering Improvements

05-05

(c)

Site Security Sensor Installation

05-06

(c)

Security Surveillance Center

05-09

1196

Luce 2635 Zone Pumping Station Improvements

05-10

1244

Frias 2635 Zone Reservoir

05-10

1309

Frias 2635 Zone Reservoir: Frias 2635 Zone Reservoir Off-Site Power Service

05-11

1244

Frias 2745 Zone Pumping Station

05-11

1309

Frias 2635 Zone Reservoir: Frias 2635 Zone Reservoir Off-Site Power Service

05-14

(c)

Necessary Site Acquisitions

05-15

(c)

Rome 2745 Zone Reservoir

05-16

(c)

Rome 2745 Zone Reservoir Inlet/Outlet Pipeline

05-17

(c)

Rome 2860 Zone Pumping Station

05-18

(c)

Rome 2860 Zone Pumping Station Discharge Pipeline

05-19

(c)

Dorrell 2860 Zone Reservoir

05-20

(c)

Dorrell 2860 Zone Reservoir Inlet/Outlet Pipeline

05-21

(c)

Dorrell 2975 Zone Pumping Station

05-22

(c)

Dorrell 2975 Zone Pumping Station Discharge Pipeline

05-23

(c)

Necessary System Improvements, Phase VII

05-23

(c)

Necessary System Improvements, Phase VII: Small Diameter Pipeline Installations, Phase II

05-23

(c)

Necessary System Improvements, Phase VII: Flamingo Road and Nellis Boulevard

05-23

1214

Necessary System Improvements, Phase VII: Necessary System Improvements, Phase VII, Flamingo/Paradise Pressure Reducing Valve

05-23

1216

Necessary System Improvements, Phase VII: Necessary System Improvements, Phase VIII, Levi Avenue Pressure Reducing Valve

05-23

1235

Necessary System Improvements, Phase VII: Necessary System Improvements, Phase VII, Campbell Mason Valve Replacement

05-23

1267

Necessary System Improvements, Phase VII: Miscellaneous Main Extensions and Water Service Installations, Phase VI

05-23

1301

Necessary System Improvements, Phase VII: Necessary System Improvements, Phase VII, Small Diameter Pipeline Installations

05-24

(c)

LVVWD Campus Infrastructure

05-24

(c)

LVVWD Campus Infrastructure: LVVWD Campus Warehouse Facility

05-24

(c)

LVVWD Campus Infrastructure: Information Systems Facility

05-24

1178

LVVWD Campus Infrastructure: Modifications to Operations Building

05-24

1202

LVVWD Campus Infrastructure: LVVWD Campus Improvements Phase I

05-24

1251

LVVWD Campus Infrastructure: LVVWD Campus Improvements, Phase II

05-25

(c)

Chemical Storage Facility

06-01

(c)

Cougar 3090 Zone Reservoir

06-02

(c)

Cougar 3090 Zone Reservoir Inlet/Outlet Pipeline

06-04

1236

LVVWD Modular Office Facilities: LVVWD Campus Off-Site Sewer Improvements

06-06

(c)

Polyethylene Service Replacements Phase I

06-06

1207

Polyethylene Service Replacements Phase I: Polyethylene Service Replacement, The Grove and Woodcroft

06-06

1268

Polyethylene Service Replacements Phase I: Polyethylene Service Replacement, Spring Valley and Laurel Park

MCP NO. PROJECT TITLE STATUS (a) AS OF 06/30/2012 Under Design Pending Under Design Pending Pending Completed Completed Completed Completed Completed Completed Under Design Completed Under Design Pending Pending Pending Under Construction $498,073.97 $0.00 $18,659.45 $0.00 $0.00 $0.00 $0.00 $0.00 $2,428,724.69 $108,394.10 $351,682.12 Pending Pending Pending Pending Completed Completed Under Construction Under Design Under Design Under Design Pending Cancelled Pending Pending Pending Pending Pending Under Design Pending Pending Pending Pending Pending Completed $0.00 $0.00 $0.00 $0.00 $39,979.54 $1,531,484.94 $594,908.80 $41,766.02 $52,265.28 $17,717.81 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $13,592.49 $0.00 $2,846.31 $0.00 $0.00 $0.00 $510,339.12 $0.00 $0.00 $0.00 $53,635.29 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $192 $0 $0 $0 $0 $0 $0 $0 $411 $376 $108 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $47 $0 $0 $641,404.62 $0 $59,287.21 $34 $380,754.66 $0 $357,440.82 $0 $0 $0 $177 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $178 $178 $325 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $218 $0 $0 $886,863.52 $0 $0 $571,495.55 $0 $0 $542,960.62 $0 $0 $511,093.58 $0 $0 $0 $0 $0 $0 $0 $0 $210 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $7 $13 $342 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $234 $0 $0 $0.00 $0 $0 $0 $0.00 $0 $0 $0 $51,826.45 $0 $0 $0 $0.00 $0 $0 $0 $648 $3,300 $1,020 $0 $0 $0 $0 $0 $0 $0 $85 $0 $697 $4,000 $9,090 $745 $0 $0 $3,600 $18,400 $3,564 $12,050 $405 $0 $0 $1,295 $1,394 $5,874 $0 $1,262 $0 $0 $0 $417 $462 $190 $157 $3,432 $0 $2,700 $1,300 $1,500 $0 $1,300 $15,486 $3,500 $29,597 $29,000 $501 $923 $0

CONT. NO.

06-06

1302

Polyethylene Service Replacements Phase I: Polyethylene Service Replacement, Charleston Rainbow and Charleston Heights

PROJECTED EXPENDITURES (Thousands) ACTUAL PROJECT FY 12/13 FY 12/13 FY 12/13 AFTER EXPENDITURES COST (b) AS OF FIRST SECOND THIRD THIRD (Thousands) 06/30/2012 QUARTER QUARTER QUARTER QUARTER $537 $37,331.31 $0 $0 $0 $500 $648 $3,352 $1,020 $0 $511 $543 $571 $887 $357 $381 $565 $641 $751 $4,000 $9,090 $745 $498 $0 $3,619 $18,400 $3,564 $12,050 $405 $0 $2,429 $1,403 $1,938 $5,874 $0 $1,262 $0 $40 $1,531 $1,012 $1,100 $809 $950 $3,432 $0 $2,700 $1,300 $1,500 $0 $1,300 $15,500 $3,500 $29,600 $29,000 $1,000 $923 $510

06-07

(c)

Chemical Storage Facility Phase II

06-07

1273

Chemical Storage Facility Phase II: Tropical Satellite Facility Campus

06-08

(c)

Electrical Equipment Improvements

Construction Status Report


Reported Under MCP 03-10 Under Design Pending Pending Pending Pending Pending Completed Under Design Under Construction

06-09

(c)

Miscellaneous Vaults, Reconstruction And Repair Phase III

06-09

1209

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XI

06-09

1210

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XII

06-09

1211

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XIII

06-09

1249

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XIV

06-09

1250

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XV

06-09

1266

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XVI

06-09

1282

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XVII

06-09

1283

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XVIII

06-09

1294

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XIX

06-10

(c)

Sunrise Mountain 2380 Zone Pumping Station

06-11

(c)

Rome 2975 Zone Pumping Station

06-12

(c)

Rome 2975 Zone Pumping Station Discharge Pipeline

06-13

1280

Cheyenne 2975 Zone Motor Operated Valves

06-14

1212

Sloan 3205 Zone South Pumping Station

06-15

1312

Summit 3205 Zone South Tanks

08-01

(c)

Richmar 2860 Zone Reservoir

08-02

(c)

Richmar 2860 Zone Reservoir Inlet/Outlet Pipeline

08-03

(c)

Richmar 2975 Zone Pumping Station

08-04

(c)

Richmar 2975 Zone Pumping Station Discharge Pipeline

08-05

(c)

Trihalomethanes Treatment Project

08-05

1293

Trihalomethanes Treatment Project: Trihalomethanes Treatment Project, Phase I - Alta 3205 Zone Reservoir

08-05

1329

Trihalomethanes Treatment Project: Trihalomethanes Treatment Project, Phase II - Elkhorn 2975 Zone Reservoir

08-05

1330

Trihalomethanes Treatment Project: Trihalomethanes Treatment Project, Phase III - Levi 2745 Zone Reservoir

08-06

(c)

Necessary System Improvements, Phase VIII

08-06

(c)

Necessary System Improvements, Phase VIII: Valley View/Maule 2300 Zone Motor Operated Valve

08-06

(c)

Necessary System Improvements, Phase VIII: Rampart/Alta Pipeline Relocation, Phase II

08-06

(c)

Necessary System Improvements, Phase VIII: Washington 2420 Zone Emergency Check Valve Installations

08-06

1306

Necessary System Improvements, Phase VIII: Miscellaneous Main Extensions and Water Service Installations, Phase VII

08-06

1307

Necessary System Improvements, Phase VIII: Rampart/Alta Pipeline Relocation, Phase I

08-06

1338

Necessary System Improvements, Phase VIII: Miscellaneous Main Extensions and Water Service Installations, Phase VIII

08-06

1353

Necessary System Improvements, Phase VIII: Miscellaneous Main Extensions and Water Service Installations, Phase IX

08-06

1354

Necessary System Improvements, Phase VIII: Oakey/I-15 Pipeline Relocation

08-06

1358

Necessary System Improvements, Phase VIII: Necessary System Improvements, Railroad Pass Pipeline Relocation

08-07

(c)

Production Well Capacity Addition

08-07

(c)

Production Well Capacity Addition Phase II - Well No. 128

08-07

1290

Production Well Capacity Addition: Equip Well Nos. 124, 125, and 126

08-07

1299

Production Well Capacity Addition: Equip Wells Nos. 127 and 128

08-07

1303

Production Well Capacity Addition: Drill and Develop Well Nos. 124, 125, and 126

08-07

1304

Production Well Capacity Addition: Drill and Develop Well Nos. 127 and 128

08-07

1305

Production Well Capacity Addition: Well No. 126 Discharge Pipeline

08-08

1255

LVVWD Campus Warehouse Facility

08-09

(c)

Child Care Facility

08-10

1256

LVVWD Campus Information Technology Facility: Information Systems Facility

08-11

(c)

Renewable Energy Project Phase II

08-11

1341

Renewable Energy Project, Phase II

08-12

(c)

Backflow Assembly Installation Phase II

08-12

1332

Backflow Assembly Installation Phase II: Miscellaneous Backflow Installations, Phase XIII

MCP NO. PROJECT TITLE STATUS (a) AS OF 06/30/2012 Pending Under Construction Under Design Completed Pending Pending Pending Completed Under Design Under Design Under Design Under Design Under Design Under Design Pending Pending Pending Under Design Pending Pending Under Design TOTALS $102,142.39 $1,423.14 $0.00 $96,996.53 $99,040,517 $0.00 $0.00 $0.00 $33,257.80 $0 $0 $0 $0 $164 $0 $0 $0 $11,799 $21,774.15 $0 $16,690.62 $0 $31,036.18 $0 $414,590.03 $0 $0 $0 $0 $0 $0 $0 $0 $0 $58 $0 $0 $0 $15,744 $81,823.88 $0 $0 $641,054.34 $0 $0 $0.00 $0 $0 $0.00 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $31 $1 $0 $31 $222 $12,422 $0.00 $22 $138 $221 $544,888.32 $0 $0 $0 $38,572.74 $11 $153 $226 $495,546.32 $0 $0 $0 $86 $41 $0 $119 $500 $301 -$5 $2,116 $2,338 $277 $701 $478 $12,567 $500 $3,300 $1,969 $675 $1,659 $1,969 $681 $509,080

CONT. NO.

08-12

1333

Backflow Assembly Installation Phase II: Miscellaneous Backflow Installations, Phase XIV

PROJECTED EXPENDITURES (Thousands) ACTUAL PROJECT FY 12/13 FY 12/13 FY 12/13 AFTER EXPENDITURES COST (b) AS OF FIRST SECOND THIRD THIRD (Thousands) 06/30/2012 QUARTER QUARTER QUARTER QUARTER $1,210 $70,308.60 $0 $0 $0 $1,140 $582 $470 $545 $500 $500 $301 $636 $2,198 $2,753 $308 $718 $500 $12,600 $500 $3,300 $2,000 $1,000 $1,660 $2,000 $1,000 $648,086

08-12

1334

Backflow Assembly Installation Phase II: Miscellaneous Large Backflow Installations, Phase II

08-12

1350

Backflow Assembly Installation Phase II: Miscellaneous Large Backflow Installations, Phase III

08-12

M0155 Backflow Assembly Installation Phase II: Miscellaneous Backflow Installations, 2008-2009, Phase XII

Construction Status Report

08-12

M0160 Backflow Assembly Installation Phase II: Miscellaneous Backflow Installations, 2012-2013, Phase XV

08-12

M0161 Backflow Assembly Installation Phase II: Miscellaneous Backflow Installations, 2011-2012, Phase XVI

08-13

(c)

Necessary Site Improvements, Phase II

08-13

1194

Necessary Site Improvements, Phase II: Miscellaneous Site Improvements, FY 2005/2006, Phase I

08-13

1260

Necessary Site Improvements, Phase II: Necessary Site Improvements, Angel Park Disinfection System Addition

08-13

1261

Necessary Site Improvements, Phase II: Necessary Site Improvements, Pico, Stewart, Washington, and 3205 Zone North Interim Perimeter Fencing

08-13

1295

Necessary Site Improvements, Phase II: Necessary Site Improvements, Well Perimeter Fencing, Phase I

08-13

1296

Necessary Site Improvements, Phase II: Necessary Site Improvements, LVSP Perimeter Fencing, Phase II

08-14

1291

Equip Well AR-100

08-15

1292

Campbell 1985 and 2168 Zone Pumping Station Improvements

08-16

(c)

Asset Management Pilot Project

08-17

(c)

Polyethylene Service Replacements Phase II

10-01

(c)

Steel Pipeline Rehabilitation and Replacement

10-01

1339

Steel Pipeline Rehabilitation and Replacement: Steel Pipeline Rehabilitation and Replacement, Phase I

10-01

1357

Steel Pipeline Rehabilitation and Replacement: Lamb Blvd. 1985 Zone Pipeline Rehabilitation Phase I - Wyoming to Vegas Valley

10-02

(c)

Asbestos Cement Pipeline Replacement

10-02

1340

Asbestos Cement Pipeline Replacement: Large Diameter Asbestos Cement Pipe Replacement/Rehabilitation, Phase I

Note:

(a) A project is considered "completed" if the construction contract has been accepted as completed by the Board of Directors. A project is considered "under construction" if a Notice to Proceed has been issued for the construction contract, but the construction contract has not been accepted as "completed" by the Board of Directors. A project is considered "under design" if a project team has been formed and the project is in the process of being designed, but a Notice to Proceed has not yet been issued. A project is considered "pending" if it has been approved in concept, but no work has been done to date.

(b) Includes design, construction, inspection, right-of-way/land acquisition, and administrative costs. Costs for projects not completed are estimated and escalated to the projected year of construction.

(c) Contract number has not been assigned.

(d) Refer to Table II for project data.

(e) Refer to Table III for project data.

TABLE II LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM PROJECT DATA FOR WELL DRILLING AND DEVELOPMENT PROJECTS
Well No. Right-of-Way Existing Existing Existing Existing Existing Existing Existing 02/09/1994 07/01/1994 $772,910 08/17/1994 09/30/1994 05/17/1995 4 (52,250.00) 0 02/09/1994 07/25/1994 $903,775 08/17/1994 09/30/1994 02/17/1995 5 (83,759.50) 0 02/01/1993 04/01/1993 $967,700 04/20/1993 05/24/1993 09/24/1993 2 (83,420.94) 0 $718,140 04/20/1993 05/24/1993 11/12/1993 01/05/1994 11/03/1993 06/20/1995 09/05/1995 $847,866 $1,099,728 $971,950 $915,244 $162,000 $550,000 $1,500,000 Estimated Cost Contract Amount Award Date Date of Completion Notice to Proceed Acceptance Date

MCP NO.

CONT NO.

4-58

674

AR-2, AR-3, AR-4, AR-5

DESIGN Begin Complete Design Design 02/01/1993 04/01/1993

CHANGE ORDERS Total Dates No. Amount Added 9 (63,680.52) 0

PROJECT COS Construction In-House Cost Cost (a) $643,629 $891,850 $820,016 $709,946

Construction Status Report

4-58

675

AR-6, AR-7, AR-8, AR-9, AR-10

4-58

711 (b)

AR-74, AR-111

4-58

712

AR-98, AR-108, AR-113

4-58

(c)

AR-91

01-02

(c)

Replacement Well No. 38A

08-07

1304

Production Well Capacity Addition: Drill and Develop Well Nos. 127, 128

08-07

1303

Production Well Capacity Addition: Drill and Develop Well Nos. 124, 125, and 126

Note:

(a) In-house cost includes design and overhead costs.

(b) This contract combines MCP IIIR and MCP IV Projects. Actual expenditures and estimated costs have been distributed as follows 1/3 to MCP 3-128 and 2/3 to MCP 4-28.

(c) Contract number has not been assigned.

TABLE III LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM PROJECT DATA FOR WELL EQUIPPING PROJECTS
DESIGN Estimated Cost Begin Design No. Complete Design Total Amount Dates Added Contract Amount Date of Completion Award Date Notice to Proceed Acceptance Date Construction Cost CHANGE ORDERS PROJECT COSTS In-house Cost (a) Total Project Cost

Construction Status Report


$582,342 $1,287,000 $2,700,000 $1,300,000 $500,000 06/17/2008 01/04/1994 03/30/1994 $337,547 05/18/1994 06/20/1994 10/27/1994 5 $12,985 0 11/16/1994 $350,531.86

MCP No.

Cont. No.

Well No.

4-58

676

Cancelled

4-58

694

AR-10 Reported Under MCP 4-3 $8,995 $582,342

4-58

706

AR-4, AR-5 Cancelled

4-58

707

AR-6, AR-7, AR-8, AR-9

4-58

783

AR-109, AR-111, AR-1, AR-98, AR-108 Reported under MCP 4-68.

4-58

(b)

AR-74, AR-91, AR-97, AR-107

08-07

1290

08-07

1299

Production Well Capacity Addition: Equip Well Nos. 124, 125, and 126 Production Well Capacity Addition: Equip Well Nos. 127 and 128

08-14

1291

Equip Well AR-100

Note:

(a) In-house cost includes design and overhead costs.

(b) Contract number has not been assigned.

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Construction CONTRACT NUMBER (1) MCP NUMBER 4-17

PROJECT TITLE: WATER RESOURCE RESEARCH AND DEVELOPMENT

PROJECT DESCRIPTION:
Conduct studies of future additional water resource alternatives and methods of developing those water resources.

ESTIMATED PROJECT COST $5,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Not Required NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract number not assigned.

Construction Summary Report

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: ACQUIRE SITES FOR FUTURE WELLS CONTRACT NUMBER (2) MCP NUMBER 4-53

PROJECT DESCRIPTION:
Acquire sites for future wells at the following locations: 1) Hualapai Way north of Cheyenne Avenue; 2) Alexander Road west of Durango Drive; 3) near the intersection of Craig Road and El Capitan Way; 4) northwest of Westcliff Drive and Cimarron Road; and 5) El Capitan Way south of Lone Mountain Road.

ESTIMATED PROJECT COST $140,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: SCADA SYSTEM EXPANSION AND UPGRADE CONTRACT NUMBER (2) MCP NUMBER 4-57

PROJECT DESCRIPTION:
Expand and upgrade the District's existing Supervisory Control and Data Acquisition System (SCADA).

ESTIMATED PROJECT COST $800,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Not Required NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: RESERVOIR SITE ACQUISITIONS PHASE I CONTRACT NUMBER (2) MCP NUMBER 97-01

PROJECT DESCRIPTION:
This project will provide for the acquisition of four (4) future reservoir sites to be located in the northern portion of the 2538 Pressure Zone, and the southern portions of the 2538, 2745, and 2975 Pressure Zones.

ESTIMATED PROJECT COST $1,320,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

10

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: 3665 ZONE RESERVOIR CONTRACT NUMBER (2) MCP NUMBER 97-10

PROJECT DESCRIPTION:
This project consists of the design and construction of a 20 MG below grade reinforced concrete reservoir to provide gravity storage for the 3550 and 3665 Pressure Zones, and to transfer storage for pressure zones to the west. The improvements will enhance operational efficiency and system reliability in the central portion of the 3550 and 3665 Pressure Zones.

ESTIMATED PROJECT COST $7,400,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

11

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 97-11

PROJECT TITLE: 3665 ZONE RESERVOIR INLET/OUTLET PIPELINE

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 2,000 LF of 42-inch diameter pipeline to distribute water to the 3665 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the 3665 Pressure Zone.

ESTIMATED PROJECT COST $1,004,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

12

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: JEAN TRANSMISSION SYSTEM CONTRACT NUMBER (2) MCP NUMBER 99-04

PROJECT DESCRIPTION:
This project consists of the design and construction of pumping stations, storage tanks, and a pipeline to convey potable water from the existing Bermuda 2420 Zone Reservoir to Jean, Nevada.

ESTIMATED PROJECT COST $21,614,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

13

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 00-02

PROJECT TITLE: NORTH WELL FIELD/LAS VEGAS SPRINGS PRESERVE INFRASTRUCTURE

PROJECT DESCRIPTION:
This project consists of the construction of infrastructure within the District's North Well Field that will provide a solid base for the efficient, orderly, and least disruptive and damaging approach to future development of the Las Vegas Springs Preserve, and continued operation of critical water facilities in the North Well Field.

ESTIMATED PROJECT COST $331,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

14

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Cancelled CONTRACT NUMBER (1) MCP NUMBER 00-02

PROJECT TITLE: NORTH WELL FIELD/LAS VEGAS SPRINGS PRESERVE INFRASTRUCTURE: CHARLESTON HEIGHTS SITE REMEDIATION

PROJECT DESCRIPTION:
This project consists of the repair of concrete panels as a result of settlement. This project will repair and replace concrete slabs in the lower parking area and viewing plaza, stabilize walls in the entry plaza, and install drainage improvements along the perimeter of the parking area to mitigate future settlement.

ESTIMATED PROJECT COST

LAND OR RIGHT-OFWAY STATUS

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

AWARD OF CONTRACT AMOUNT DATE

NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract number not assigned.

Construction Summary Report

15

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1015 (1) MCP NUMBER 00-02

PROJECT TITLE: NORTH WELL FIELD/LAS VEGAS SPRINGS PRESERVE INFRASTRUCTURE: NORTH WELL FIELD SITE CLEAN UP

PROJECT DESCRIPTION:
This project consists of the construction of approximately 3,500 LF of chain link fencing and gates, and removal of miscellaneous items and debris from the North Well Field.

ESTIMATED PROJECT COST $143,587.00 AWARD OF CONTRACT AMOUNT $114,801.00 CONTRACT ACCEPTANCE DATE 9/18/2001 DATE 3/6/2001 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 4/2/2001 5/14/2001 CONSTRUCTION COST $111,100.25 LAND ACQUISITION COST

BEGIN DESIGN (2) 8/14/2000

COMPLETE DESIGN 1/8/2001 CHANGE ORDERS

RECEIPT OF BIDS 2/6/2001

TOTAL NUMBER 1 IN-HOUSE COST $15,427.00

TOTAL AMOUNT ($3,470.75)

DAYS EXTENDED

TOTAL PROJECT COST $143,587.46

NOTES: (1) Contract No. 1015 is titled North Well Field Site Clean Up, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

16

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1020 (1) MCP NUMBER 00-02

PROJECT TITLE: NORTH WELL FIELD/LAS VEGAS SPRINGS PRESERVE INFRASTRUCTURE: LAS VEGAS SPRINGS PRESERVE CIENEGA

PROJECT DESCRIPTION:
This project consists of the design and construction of a riparian area including habitat for flora and fauna, and a cauldron pool exhibit within the newly expanded Meadows Detention Basin, located in the North Well Field.

ESTIMATED PROJECT COST $248,700.00 AWARD OF CONTRACT AMOUNT $2,545,635.00 CONTRACT ACCEPTANCE DATE 3/2/2004 DATE 11/19/2002 DESIGN COST $145,230.00

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 3/8/2003 12/20/2003 CONSTRUCTION COST (3) $2,710,765.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 2/23/2001

COMPLETE DESIGN 9/12/2002 CHANGE ORDERS

RECEIPT OF BIDS 10/31/2002

TOTAL NUMBER 2 IN-HOUSE COST $29,764.00

TOTAL AMOUNT $510,765.00

DAYS EXTENDED 167

TOTAL PROJECT COST $248,699.50

NOTES: (1) Contract No. 1020 is titled Las Vegas Springs Preserve Cienega, by the LVVWD Design Division. (2) Designed by Natural Systems, Inc. (3) The contractor donated $2,979,571.00 to the Las Vegas Springs Preserve Foundation.

Construction Summary Report

17

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1024 (1) MCP NUMBER 00-02

PROJECT TITLE: NORTH WELL FIELD/LAS VEGAS SPRINGS PRESERVE INFRASTRUCTURE: LAS VEGAS SPRINGS PRESERVE SITE INFRASTRUCTURE

PROJECT DESCRIPTION:
This project consists of the construction of site infrastructure for the Las Vegas Springs Preserve, including potable water, fire protection, gas, power, communication and data distribution system, sound wall along U.S. 95, emergency call-boxes, access roads and streetscapes along Valley View Boulevard and Alta Drive. The work also includes the construction of the main 4,160 volt electrical power grid for the facilities located within the North Well Field.

ESTIMATED PROJECT COST $12,910,854.00 AWARD OF CONTRACT AMOUNT $11,015,084.00 CONTRACT ACCEPTANCE DATE 7/5/2005 DATE 4/2/2002 DESIGN COST $806,319.00

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 5/13/2002 9/1/2003 CONSTRUCTION COST $12,338,355.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 11/9/2000

COMPLETE DESIGN 3/14/2002 CHANGE ORDERS

RECEIPT OF BIDS 3/14/2002

TOTAL NUMBER 13 IN-HOUSE COST $83,785.00

TOTAL AMOUNT $1,323,271.00

DAYS EXTENDED 402

TOTAL PROJECT COST $12,910,854.28

NOTES: (1) Contract No. 1024 is titled Las Vegas Springs Preserve Site Infrastructure, by the LVVWD Design Division. (2) Designed by Poggemeyer Design Group.

Construction Summary Report

18

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1245 (1) MCP NUMBER 00-02

PROJECT TITLE: NORTH WELL FIELD/LAS VEGAS SPRINGS PRESERVE INFRASTRUCTURE: LAS VEGAS SPRINGS PRESERVE TRAIL EXTENSION AND REALIGNMENT

PROJECT DESCRIPTION:
This project consists of the design and construction of site resin pavement trail extension, landscaping and irrigation system along Valley View Boulevard, trail realignment, including demolition of existing portions of trail, caliche boulder retaining walls, demolition of portions of existing landscape and irrigation, new landscaping and irrigation systems, and repair of disturbed landscaping and irrigation systems.

ESTIMATED PROJECT COST $518,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 01/29/2007

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1245 is titled Las Vegas Springs Preserve Trail Extension And Realignment, by the LVVWD Design Division. (2) Designed by Poggemeyer Design Group.

Construction Summary Report

19

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 00-03

PROJECT TITLE: NORTH WELL FIELD ARCHEOLOGICAL AND HISTORICAL STABILIZATION

PROJECT DESCRIPTION:
This project consists of the stabilization of the North Well Field in order to identify and to protect priceless prehistoric, cultural, archeological, and biological resources.

ESTIMATED PROJECT COST $2,900,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

20

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 00-04

PROJECT TITLE: NORTH WELL FIELD ENVIRONMENTAL STABILIZATION

PROJECT DESCRIPTION:
This project will ensure stabilization and protection of environmental assets of the North Well Field. It is necessary to reduce and/or to stop the deterioration of the environmental aspect of the North Well Field and to preserve it for future generations.

ESTIMATED PROJECT COST $3,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

21

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: RESERVOIR SITE ACQUISITION CONTRACT NUMBER (2) MCP NUMBER 02-05

PROJECT DESCRIPTION:
This project consists of the site selection and land acquisition costs associated with the acquisition of sites for future reservoirs. In a subsequent agenda item, the Board of Directors will be asked to approve the acquisition of real property for the future Centennial 2635 Zone Reservoir.

ESTIMATED PROJECT COST $5,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

22

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 02-06

PROJECT TITLE: PURCHASE OF GROUNDWATER RIGHTS IN THE LAS VEGAS VALLEY

PROJECT DESCRIPTION:
This project consists of the water rights purchase agreement between OB Sports, LLC, Angel Park, LLC, and the District, which provides for the District to purchase 200.96 acre-feet of the certified groundwater rights from OB Sports, LLC.

ESTIMATED PROJECT COST $1,909,120.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Not Required NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

23

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1185 MCP NUMBER 03-09

PROJECT TITLE: BERMUDA 2745 ZONE PUMPING STATION DISCHARGE PIPELINE

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 6,700 LF of 48-inch diameter pipeline to distribute water to the southern portion of the 2745 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the southern portion of the 2745 Pressure Zone.

ESTIMATED PROJECT COST $2,793,653.00 AWARD OF CONTRACT AMOUNT $2,616,080.00 CONTRACT ACCEPTANCE DATE 09/02/2008 DATE 07/03/2007 DESIGN COST $106,605.44

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 08/06/2007 07/30/2008 CONSTRUCTION COST $2,616,080.00 LAND ACQUISITION COST

BEGIN DESIGN (1) 08/03/2005

COMPLETE DESIGN 04/11/2007 CHANGE ORDERS

RECEIPT OF BIDS 05/16/2007

TOTAL NUMBER

TOTAL AMOUNT

DAYS EXTENDED

IN-HOUSE COST $70,968.03

TOTAL PROJECT COST $2,793,653.47

NOTES: (1) Designed by G. C. Wallace, Inc.

Construction Summary Report

24

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1242 (1) MCP NUMBER 03-09

PROJECT TITLE: BERMUDA 2745 ZONE PUMPING STATION DISCHARGE PIPELINE PHASE II

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 18,600 LF of 48-inch diameter pipeline to distribute water to the southern portion of the 2745 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the southern portion of the 2745 Pressure Zone.

ESTIMATED PROJECT COST $9,636,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 01/17/2009

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1242 is titled Bermuda 2745 Zone Pumping Station Discharge Pipeline Phase II, by the LVVWD Design Division. (2) Designed by the LVVWD Design Division.

Construction Summary Report

25

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design PROJECT TITLE: SLOAN 2745 ZONE RESERVOIR CONTRACT NUMBER 1212 (1) MCP NUMBER 03-10

PROJECT DESCRIPTION:
This project consists of the design and construction of one (1) 5 MG below grade reinforced concrete tank with plans for future expansion to two (2) 5 MG tanks to provide gravity storage for the 2745 Pressure Zone, and to transfer storage for pressure zones to the south and to the west. The improvements will enhance operational efficiency and system reliability in the southern portion of the 2745 Pressure Zone.

ESTIMATED PROJECT COST $22,380,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 3/20/2009

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1212 is titled Sloan 2745 Zone Reservoir and 3205 Zone South Pumping Station, by the LVVWD Design Division. (2) Designed by the LVVWD Design Division.

Construction Summary Report

26

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: SECURITY SYSTEM UPGRADES CONTRACT NUMBER (2) MCP NUMBER 03-12

PROJECT DESCRIPTION:
This project consists of the design, administration, permitting, construction, and inspection of security upgrades at various facilities as a result of completing the vulnerability assessment mandated under the United States of America Presidential Decision Directive No. 63, and the Bioterrorism Preparedness and Response Act of 2002.

ESTIMATED PROJECT COST $156,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

27

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1169 (1) MCP NUMBER 03-12

PROJECT TITLE: SECURITY SYSTEM UPGRADES: COMMUNICATION NETWORK UPGRADE, PHASE II

PROJECT DESCRIPTION:
This project consists of the design and installation of fiber optic cable in existing fiber optic conduit. The fiber optic cable will connect numerous sites across the Las Vegas Valley with the new security room in the operations building. The new fiber optic cable along with existing SNWA fiber optic cable and fiber optic cable purchased from IDACOMM will be used to feed real time images from security cameras at the various sites back to the Valley View campus.

ESTIMATED PROJECT COST $1,692,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 5/31/2005

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1169 is titled Communication Network Upgrade, Phase II, by the LVVWD Design Division. (2) Designed by Westin Engineering, Inc.

Construction Summary Report

28

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1177 (1) MCP NUMBER 03-12

PROJECT TITLE: SECURITY SYSTEM UPGRADES: SECURITY TELECOMMUNICATIONS NETWORK INFRASTRUCTURE

PROJECT DESCRIPTION:
This project consists of the design and construction of surveillance equipment and communication portals for reporting to central control from existing reservoir and pumping station sites.

ESTIMATED PROJECT COST $257,081.00 AWARD OF CONTRACT AMOUNT $4,293,752.00 CONTRACT ACCEPTANCE DATE 08/05/2008 DATE 01/18/2005 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 01/18/2005 12/31/2005 CONSTRUCTION COST $4,293,752.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 07/21/2005

COMPLETE DESIGN 01/18/2005 CHANGE ORDERS

RECEIPT OF BIDS 01/18/2005

TOTAL NUMBER

TOTAL AMOUNT

DAYS EXTENDED

IN-HOUSE COST

TOTAL PROJECT COST $257,080.81

NOTES: (1) Contract No. 1177 is titled Security Telecommunications Network Infrastructure, by the LVVWD Design Division. (2) Designed by IDACOMM, Inc.

Construction Summary Report

29

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1254 (1) MCP NUMBER 03-12

PROJECT TITLE: SECURITY SYSTEM UPGRADES: COMMUNICATION NETWORK UPGRADE, PHASE I

PROJECT DESCRIPTION:
This project consists of the installation of fiber optic conduit in various parts of the Las Vegas Valley. The new reaches of fiber optic conduit will tie together previously installed segments of fiber optic conduit that do not connect with one another, and tie existing LVVWD and SNWA sites together so a portion of the SNWA fiber optic system can be utilized for District purposes.

ESTIMATED PROJECT COST $1,696,693.00 AWARD OF CONTRACT AMOUNT $785,590.00 CONTRACT ACCEPTANCE DATE 06/02/2009 DATE 03/18/2008 DESIGN COST $184,897.73

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 05/12/2008 01/14/2009 CONSTRUCTION COST $777,344.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 05/31/2005

COMPLETE DESIGN 10/03/2007 CHANGE ORDERS

RECEIPT OF BIDS 02/05/2008

TOTAL NUMBER 7 IN-HOUSE COST $734,451.33

TOTAL AMOUNT ($8,246.00)

DAYS EXTENDED 18

TOTAL PROJECT COST $1,696,693.06

NOTES: (1) Contract No. 1254 is titled Communication Network Upgrade, Phase I, by the LVVWD Design Division. (2) Designed by Wright Engineers.

Construction Summary Report

30

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1263 (1) MCP NUMBER 03-12

PROJECT TITLE: SECURITY SYSTEM UPGRADES: COMMUNICATION NETWORK UPGRADE, PHASE III

PROJECT DESCRIPTION:
This project consists of the installation of approximately 7,500 LF of dual 4-inch diameter fiber optic conduit (approximately 2,000 feet in Buffalo Drive between Robindale Road and Warm Springs Road and 5,500 feet in Centennial Parkway between Hualapai Way and Fort Apache Road).

ESTIMATED PROJECT COST $807,262.00 AWARD OF CONTRACT AMOUNT $663,000.00 CONTRACT ACCEPTANCE DATE 11/03/2009 DATE 07/01/2008 DESIGN COST $124,329.16

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 07/28/2008 06/01/2009 CONSTRUCTION COST $633,343.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 08/13/2007

COMPLETE DESIGN 04/15/2008 CHANGE ORDERS

RECEIPT OF BIDS 06/05/2008

TOTAL NUMBER 2 IN-HOUSE COST $49,589.40

TOTAL AMOUNT ($29,657.00)

DAYS EXTENDED

TOTAL PROJECT COST $807,261.56

NOTES: (1) Contract No. 1263 is titled Communication Network Upgrade, Phase III, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

31

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 03-14

PROJECT TITLE: SYSTEM COMMUNICATION NETWORK IMPROVEMENTS

PROJECT DESCRIPTION:
This project consists of the design and installation of fiber-optic conduit in conjunction with major developer oversized pipeline projects. The conduit will enhance the District's communication network.

ESTIMATED PROJECT COST $1,980,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

32

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 04-02

PROJECT TITLE: SUNRISE MOUNTAIN 2150 ZONE RESERVOIR SITE ACQUISITION

PROJECT DESCRIPTION:
This project consists of the acquisition of the Sunrise Mountain 2150 Zone Reservoir site.

ESTIMATED PROJECT COST $1,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

33

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 04-03

PROJECT TITLE: STEWART 2150 ZONE PUMPING STATION IMPROVEMENTS

PROJECT DESCRIPTION:
This project consists of the design and construction of improvements to the Stewart 2150 Zone Pumping Station. The project will enhance operational efficiency and reliability of the facilities providing water to the 2150 Pressure Zone.

ESTIMATED PROJECT COST $2,750,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

34

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed PROJECT TITLE: CACTUS 2538 ZONE RESERVOIR CONTRACT NUMBER 1150 (1) MCP NUMBER 04-04

PROJECT DESCRIPTION:
This project consists of the design and construction of a 30 MG below grade reinforced concrete reservoir to provide additional gravity storage for the 2538 Pressure Zone, and to transfer storage for pressure zones to the west. The improvements will enhance operational efficiency and system reliability in the southern portion of the 2538 Pressure Zone.

ESTIMATED PROJECT COST $37,305,000.00 AWARD OF CONTRACT AMOUNT $35,271,500.00 CONTRACT ACCEPTANCE DATE 07/06/2010 DATE 05/20/2008 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 06/24/2008 05/29/2010 CONSTRUCTION COST $34,419,928.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 04/04/2006

COMPLETE DESIGN 02/26/2008 CHANGE ORDERS

RECEIPT OF BIDS 04/15/2008

TOTAL NUMBER 13 IN-HOUSE COST $2,885,130.20

TOTAL AMOUNT ($851,572.00)

DAYS EXTENDED 60

TOTAL PROJECT COST $37,305,058.20

NOTES: (1) Contract No. 1150 is titled Cactus 2538 Zone Reservoir and 2635 Zone Pumping Station, by the LVVWD Design Division. (2) Designed by Black & Veatch Engineers.

Construction Summary Report

35

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Construction CONTRACT NUMBER 1323 MCP NUMBER 04-04

PROJECT TITLE: CACTUS 2538 ZONE RESERVOIR ON-SITE IMPROVEMENTS

PROJECT DESCRIPTION:
This project consists of the design and construction of roadway improvements on Rainbow Boulevard, street lighting, perimeter fencing, demolishing a concrete drainage channel and filling the channel to grade, on-site paving, demolishing temporary fencing, site access gate, fugitive dust control measures, and other ancillary work.

ESTIMATED PROJECT COST $825,000.00 AWARD OF CONTRACT AMOUNT $606,300.00 CONTRACT ACCEPTANCE DATE DATE 12/28/2010 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 02/03/2011 08/02/2011 CONSTRUCTION COST LAND ACQUISITION COST

BEGIN DESIGN (1) 02/28/2010

COMPLETE DESIGN 09/27/2010 CHANGE ORDERS

RECEIPT OF BIDS 11/09/2010

TOTAL NUMBER 2 IN-HOUSE COST

TOTAL AMOUNT $94.00

DAYS EXTENDED

TOTAL PROJECT COST

NOTES: (1) Designed by the LVVWD Design Division.

Construction Summary Report

36

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Reported Under MCP 04-04 PROJECT TITLE: CACTUS 2635 ZONE PUMPING STATION CONTRACT NUMBER 1150 MCP NUMBER 04-06

PROJECT DESCRIPTION:
This project consists of the design and construction of a 47 MGD pumping station, based on a 16 hour per day operation. Five (5) constant speed pumping units will be installed to transfer water from the 2538 Pressure Zone into the 2635 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the southern portion of the 2635 Pressure Zone.

ESTIMATED PROJECT COST

LAND OR RIGHT-OFWAY STATUS

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

AWARD OF CONTRACT AMOUNT DATE

NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE NOTES:

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

Construction Summary Report

37

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Reported Under MCP 04-04 CONTRACT NUMBER 1323 MCP NUMBER 04-06

PROJECT TITLE: CACTUS 2538 ZONE RESERVOIR ON-SITE IMPROVEMENTS

PROJECT DESCRIPTION:
This project consists of the design and construction of roadway improvements on Rainbow Boulevard, street lighting, perimeter fencing, demolishing a concrete drainage channel and filling the channel to grade, on-site paving, demolishing temporary fencing, site access gate, fugitive dust control measures, and other ancillary work.

ESTIMATED PROJECT COST

LAND OR RIGHT-OFWAY STATUS

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

AWARD OF CONTRACT AMOUNT DATE

NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE NOTES:

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

Construction Summary Report

38

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design PROJECT TITLE: CENTENNIAL 2635 ZONE RESERVOIR CONTRACT NUMBER 1232 (1) MCP NUMBER 04-08

PROJECT DESCRIPTION:
This project consists of the design and construction of a 30 MG below grade reinforced concrete reservoir to provide additional gravity storage for the 2635 Pressure Zone, and to transfer storage for pressure zones to the west. The improvements will enhance operational efficiency and system reliability in the northern portion of the 2635 Pressure Zone.

ESTIMATED PROJECT COST $29,280,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 3/8/2007

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1232 is titled Centennial 2635 Zone Reservoir and 2745 Zone Pumping Station, by the LVVWD Design Division. (2) Designed by G.C. Wallace, Inc.

Construction Summary Report

39

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Reported Under MCP 04-08 PROJECT TITLE: CENTENNIAL 2745 ZONE PUMPING STATION CONTRACT NUMBER 1232 MCP NUMBER 04-09

PROJECT DESCRIPTION:
This project consists of the design and construction of a 36 MGD pumping station, based on a 16 hour per day operation. Five (5) constant speed pumping units will be installed to transfer water from the 2635 Pressure Zone into the 2745 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the northern portion of the 2745 Pressure Zone.

ESTIMATED PROJECT COST

LAND OR RIGHT-OFWAY STATUS

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

AWARD OF CONTRACT AMOUNT DATE

NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE NOTES:

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

Construction Summary Report

40

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: LOG CABIN 3205 ZONE RESERVOIR CONTRACT NUMBER 1213 MCP NUMBER 04-10

PROJECT DESCRIPTION:
This project consists of the design and construction of a 20 MG below grade reinforced concrete reservoir to provide additional gravity storage for the 3205 Pressure Zone, and to transfer storage for pressure zones to the west. The improvements will enhance operational efficiency and system reliability in the northern portion of the 3205 Pressure Zone.

ESTIMATED PROJECT COST $13,500,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change.

Construction Summary Report

41

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 04-11

PROJECT TITLE: LOG CABIN 3205 ZONE RESERVOIR INLET/OUTLET PIPELINE

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 15,250 LF of 42-inch diameter pipeline to distribute water to the northern portion of the 3205 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the northern portion of the 3205 Pressure Zone.

ESTIMATED PROJECT COST $5,636,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

42

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 04-12

PROJECT TITLE: LEONARD R. FAYLE WATER FACILITY IMPROVEMENTS

PROJECT DESCRIPTION:
This project consists of the design and construction of improvements to the Leonard R. Fayle water facilities. The project will provide for the necessary replacement of, and improvements to, the reservoir, pumping stations, and pipelines serving the 2168, 2300, and 2420 Pressure Zones.

ESTIMATED PROJECT COST $14,644,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

43

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1206 (1) MCP NUMBER 04-12

PROJECT TITLE: LEONARD R. FAYLE WATER FACILITY IMPROVEMENTS: FAYLE WATER FACILITY IMPROVEMENTS

PROJECT DESCRIPTION:
This project consists of the design and construction of a 40 MG below grade reinforced concrete reservoir to replace the existing 40 MG reservoir. The design and construction of a new 2300 Pressure Zone pumping station will include the installation of four (4) 400 HP pumping units rated at 7,800 gpm at 140 feet dynamic head (TDH). The design and construction of a new 2420 Pressure Zone pumping station will include the installation of four (4) 600 HP pumping units rated at 6,450 gpm at 260 feet dynamic head (TDH).

ESTIMATED PROJECT COST $48,701,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 07/11/2011

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1206 is titled Fayle Water Facility Improvements, by the LVVWD Design Division. (2) Designed by Black and Veatch Engineers.

Construction Summary Report

44

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1257 (1) MCP NUMBER 04-12

PROJECT TITLE: LEONARD R. FAYLE WATER FACILITY IMPROVEMENTS: FAYLE 2168 ZONE SATELLITE RESERVOIR

PROJECT DESCRIPTION:
This project consists of the design and construction of a 10 MG below grade reinforced concrete reservoir to provide additional gravity storage for the 2168 Pressure Zone, and to transfer storage for pressure zones to the west. The improvements will enhance operational efficiency and system reliability in the central portion of the 2168 Pressure Zone.

ESTIMATED PROJECT COST $20,120,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 06/19/2008

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1257 is titled Fayle 2168 Zone Satellite Reservoir, by the LVVWD Design Division. (2) Designed by Black and Veatch Engineers.

Construction Summary Report

45

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1258 (1) MCP NUMBER 04-12

PROJECT TITLE: LEONARD R. FAYLE WATER FACILITY IMPROVEMENTS: FAYLE 2168 ZONE SATELLITE RESERVOIR INLET/OUTLET PIPELINE

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 3,000 LF of 72-inch diameter pipeline to connect the Fayle 2168 Zone Satellite Reservoir to the existing SNWS Fayle ROFC in the central portion of the 2168 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the central portion of the 2168 Pressure Zone.

ESTIMATED PROJECT COST $6,376,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 06/19/2008

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1258 is titled Fayle 2168 Zone Satellite Reservoir Inlet/outlet Pipeline, by the LVVWD Design Division. (2) Designed by Black and Veatch Engineers.

Construction Summary Report

46

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design PROJECT TITLE: PRESSURE MONITORING STATIONS CONTRACT NUMBER 1182 MCP NUMBER 04-15

PROJECT DESCRIPTION:
This project consists of the design and installation of five (5) pressure and chlorine monitoring stations throughout the distribution system. The monitoring stations will transmit pressure and chlorine residual readings to the SCADA system.

ESTIMATED PROJECT COST $406,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (1) 10/27/2008

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Designed by the LVVWD Design Division.

Construction Summary Report

47

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: SUNRISE MOUNTAIN 2150 ZONE RESERVOIR CONTRACT NUMBER (2) MCP NUMBER 04-17

PROJECT DESCRIPTION:
This project consists of the design and construction of a 5 MG above grade welded steel tank to provide gravity storage for the 2150 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the 2150 Pressure Zone.

ESTIMATED PROJECT COST $4,617,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

48

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 04-18

PROJECT TITLE: SUNRISE MOUNTAIN 2150 ZONE RESERVOIR INLET/OUTLET PIPELINE

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 3,150 LF of 36-inch diameter pipeline to distribute water to the 2150 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the 2150 Pressure Zone.

ESTIMATED PROJECT COST $1,120,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

49

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: BONANZA 2150 ZONE PIPELINE CONTRACT NUMBER (2) MCP NUMBER 04-19

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 9,300 LF of 30-inch diameter pipeline to distribute water to the 2150 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the 2150 Pressure Zone.

ESTIMATED PROJECT COST $3,642,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

50

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 04-20

PROJECT TITLE: WASHINGTON 2150 ZONE PUMPING STATION DISCHARGE PIPELINE

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 4,800 LF of 36-inch diameter pipeline to distribute water to the 2150 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the 2150 Pressure Zone.

ESTIMATED PROJECT COST $1,706,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

51

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: PRV METERING IMPROVEMENTS CONTRACT NUMBER (2) MCP NUMBER 04-24

PROJECT DESCRIPTION:
This project consists of the design and installation of metering equipment at pressure reducing stations located in key areas of the distribution system. The project will provide improved system operations, data acquisition, and system security.

ESTIMATED PROJECT COST $5,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

52

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: SITE SECURITY SENSOR INSTALLATION CONTRACT NUMBER (2) MCP NUMBER 05-05

PROJECT DESCRIPTION:
This project consists of the design and construction of surveillance equipment and communication portals for reporting to central control from existing reservoir and pumping station sites.

ESTIMATED PROJECT COST $5,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

53

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: SECURITY SURVEILLANCE CENTER CONTRACT NUMBER (2) MCP NUMBER 05-06

PROJECT DESCRIPTION:
This project consists of the design and construction of a facility to be located in the existing operations building at the Valley View campus. The facility will monitor the increased security measures being installed at existing reservoir and pumping station sites.

ESTIMATED PROJECT COST $2,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

54

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1196 MCP NUMBER 05-09

PROJECT TITLE: LUCE 2635 ZONE PUMPING STATION IMPROVEMENTS

PROJECT DESCRIPTION:
This project consists of the design and construction for the replacement of existing valves, pumps, and motors that have a high failure rate and have become costly to maintain.

ESTIMATED PROJECT COST $2,634,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (1) 02/26/2007

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Designed by CH2M Hill.

Construction Summary Report

55

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design PROJECT TITLE: FRIAS 2635 ZONE RESERVOIR CONTRACT NUMBER 1244 (1) MCP NUMBER 05-10

PROJECT DESCRIPTION:
This project consists of the design and construction of a 30 MG below grade reinforced concrete reservoir to provide additional gravity storage for the 2635 Pressure Zone, and to transfer storage for pressure zones to the west. The improvements will enhance operational efficiency and system reliability in the southern portion of the 2635 Pressure Zone.

ESTIMATED PROJECT COST $39,050,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 08/09/2007

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1244 is titled Frias 2635 Zone Reservoir and 2745 Zone Pumping Station, by the LVVWD Design Division. (2) Designed by RBF Consulting Engineering.

Construction Summary Report

56

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER 1309 MCP NUMBER 05-10

PROJECT TITLE: FRIAS 2635 ZONE RESERVOIR: FRIAS 2635 ZONE RESERVOIR OFF-SITE POWER SERVICE

PROJECT DESCRIPTION:
This project consists of the design and construction of all electrical facilities for the Frias 2635 Zone Reservoir and the Frias 2745 Pumping Station.

ESTIMATED PROJECT COST $1,520,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change.

Construction Summary Report

57

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Reported Under MCP 05-10 PROJECT TITLE: FRIAS 2745 ZONE PUMPING STATION CONTRACT NUMBER 1244 MCP NUMBER 05-11

PROJECT DESCRIPTION:
This project consists of the design and construction of a 53 MGD pumping station, based on a 16 hour per day operation. Six (6) constant speed pumping units will be installed to transfer water from the 2635 Pressure Zone into the 2745 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the southern portion of the 2745 Pressure Zone.

ESTIMATED PROJECT COST

LAND OR RIGHT-OFWAY STATUS

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

AWARD OF CONTRACT AMOUNT DATE

NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE NOTES:

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

Construction Summary Report

58

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Reported Under MCP 05-10 CONTRACT NUMBER 1309 MCP NUMBER 05-11

PROJECT TITLE: FRIAS 2635 ZONE RESERVOIR: FRIAS 2635 ZONE RESERVOIR OFF-SITE POWER SERVICE

PROJECT DESCRIPTION:
This project consists of the design and construction of all electrical facilities for the Frias 2635 Zone Reservoir and Frias 2745 Pumping Station.

ESTIMATED PROJECT COST

LAND OR RIGHT-OFWAY STATUS

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

AWARD OF CONTRACT AMOUNT DATE

NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE NOTES:

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

Construction Summary Report

59

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: NECESSARY SITE ACQUISITIONS CONTRACT NUMBER (2) MCP NUMBER 05-14

PROJECT DESCRIPTION:
This project consists of the site selection and land acquisition costs associated with acquisition of sites for future potable and non-potable distribution system facilities.

ESTIMATED PROJECT COST $7,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

60

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: ROME 2745 ZONE RESERVOIR CONTRACT NUMBER (2) MCP NUMBER 05-15

PROJECT DESCRIPTION:
This project consists of the design and construction of a 20 MG below grade reinforced concrete reservoir to provide additional gravity storage for the 2745 Pressure Zone, and to transfer storage for pressure zones to the west. The improvements will enhance operational efficiency and system reliability in the northern portion of the 2745 Pressure Zone.

ESTIMATED PROJECT COST $15,500,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

61

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 05-16

PROJECT TITLE: ROME 2745 ZONE RESERVOIR INLET/OUTLET PIPELINE

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 5,000 LF of 48-inch diameter pipeline to distribute water to the northern portion of the 2745 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the northern portion of the 2745 Pressure Zone.

ESTIMATED PROJECT COST $3,100,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

62

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: ROME 2860 ZONE PUMPING STATION CONTRACT NUMBER (2) MCP NUMBER 05-17

PROJECT DESCRIPTION:
This project consists of the design and construction of a 23 MGD pumping station, based on a 16 hour per day operation. Five (5) constant speed pumping units will be installed to transfer water from the 2745 Pressure Zone into the 2860 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the northern portion of the 2860 Pressure Zone.

ESTIMATED PROJECT COST $8,800,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

63

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 05-18

PROJECT TITLE: ROME 2860 ZONE PUMPING STATION DISCHARGE PIPELINE

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 1,200 LF of 42-inch diameter pipeline to distribute water to the northern portion of the 2860 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the northern portion of the 2860 Pressure Zone.

ESTIMATED PROJECT COST $500,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

64

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: DORRELL 2860 ZONE RESERVOIR CONTRACT NUMBER (2) MCP NUMBER 05-19

PROJECT DESCRIPTION:
This project consists of the design and construction of a 20 MG below grade reinforced concrete reservoir to provide additional gravity storage for the 2860 Pressure Zone, and to transfer storage for pressure zones to the west. The improvements will enhance operational efficiency and system reliability in the northern portion of the 2860 Pressure Zone.

ESTIMATED PROJECT COST $15,500,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

65

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 05-20

PROJECT TITLE: DORRELL 2860 ZONE RESERVOIR INLET/OUTLET PIPELINE

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 3,900 LF of 42-inch diameter pipeline to distribute water to the northern portion of the 2860 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the northern portion of the 2860 Pressure Zone.

ESTIMATED PROJECT COST $2,500,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

66

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: DORRELL 2975 ZONE PUMPING STATION CONTRACT NUMBER (2) MCP NUMBER 05-21

PROJECT DESCRIPTION:
This project consists of the design and construction of a 28 MGD pumping station, based on a 16 hour per day operation. Five (5) constant speed pumping units will be installed to transfer water from the 2860 Pressure Zone into the 2975 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the northern portion of the 2975 Pressure Zone.

ESTIMATED PROJECT COST $7,200,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

67

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 05-22

PROJECT TITLE: DORRELL 2975 ZONE PUMPING STATION DISCHARGE PIPELINE

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 2,200 LF of 42-inch diameter pipeline to distribute water to the northern portion of the 2975 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the northern portion of the 2975 Pressure Zone.

ESTIMATED PROJECT COST $1,100,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

68

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 05-23

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VII

PROJECT DESCRIPTION:
This project consists of the design and construction of improvement projects to reinforce weak areas of the distribution system where connections are not expected to be installed by developers due to the level of existing development.

ESTIMATED PROJECT COST $3,516,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

69

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 05-23

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VII: SMALL DIAMETER PIPELINE INSTALLATIONS, PHASE II

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 3,000 LF of 8-inch diameter pipeline, a zone conversion, and the connection and abandonment of pipelines at various locations to strengthen portions of the distribution system. This project will enhance hydraulic reliability and provide improved pressures within the distribution system, reinforce weak areas of the distribution system where connections are not expected to be installed by developers due to the level of existing development. The primary areas of concern consist mostly of small diameter "dead-end" pipelines. Benefits will include improved fire flow, improved pressure during high demand periods, and increase the ability to move water within the distribution system. The reliability of the system will be improved by the elimination of many "single-feed" conditions and the associated water quality problems.

ESTIMATED PROJECT COST $444,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

70

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 05-23

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VII: FLAMINGO ROAD AND NELLIS BOULEVARD

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 160 LF of 24-inch diameter pipeline in Flamingo Road to strengthen portions of the distribution system.

ESTIMATED PROJECT COST $162,375.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

71

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1214 (1) MCP NUMBER 05-23

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VII: NECESSARY SYSTEM IMPROVEMENTS, PHASE VII, FLAMINGO/PARADISE PRESSURE REDUCING VALVE

PROJECT DESCRIPTION:
This project consists of the design and construction of one (1) 16-, and one (1) 12-inch Pressure Reducing Valves (PRVs) to provide emergency supply from the 2300 Pressure Zone to the 2168 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the 2168 Pressure Zone.

ESTIMATED PROJECT COST $885,770.00 AWARD OF CONTRACT AMOUNT $638,500.00 CONTRACT ACCEPTANCE DATE 07/02/2009 DATE 06/17/2008 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 08/06/2008 03/08/2009 CONSTRUCTION COST $668,975.50 LAND ACQUISITION COST

BEGIN DESIGN (2) 10/18/2005

COMPLETE DESIGN 04/07/2008 CHANGE ORDERS

RECEIPT OF BIDS 05/28/2008

TOTAL NUMBER 4 IN-HOUSE COST $78,581.14

TOTAL AMOUNT $30,675.50

DAYS EXTENDED 34

TOTAL PROJECT COST $885,769.58

NOTES: (1) Contract No. 1214 is titled Necessary System Improvements, Phase VII, Flamingo/Paradise Pressure Reducing Valve, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

72

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1216 (1) MCP NUMBER 05-23

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VII: NECESSARY SYSTEM IMPROVEMENTS, PHASE VIII, LEVI AVENUE PRESSURE REDUCING VALVE

PROJECT DESCRIPTION:
This project consists of the design and construction of an 8-inch Pressure Reducing Valve (PRV) to provide emergency supply from the 2745 Pressure Zone to the 2635 Pressure Zone, located in Levi Avenue, at Torrey Pines Drive. The project will enhance operational efficiency and system reliability in the distribution system.

ESTIMATED PROJECT COST $160,370.00 AWARD OF CONTRACT AMOUNT $110,900.00 CONTRACT ACCEPTANCE DATE 12/18/2007 DATE 05/24/2007 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 06/18/2007 11/30/2007 CONSTRUCTION COST $101,000.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 10/18/2005

COMPLETE DESIGN 03/19/2007 CHANGE ORDERS

RECEIPT OF BIDS 05/08/2007

TOTAL NUMBER 1 IN-HOUSE COST $25,831.96

TOTAL AMOUNT ($9,900.20)

DAYS EXTENDED

TOTAL PROJECT COST $160,369.54

NOTES: (1) Contract No. 1216 is titled Necessary System Improvements, Phase VIII, Levi Avenue Pressure Reducing Valve, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

73

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1235 (1) MCP NUMBER 05-23

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VII: NECESSARY SYSTEM IMPROVEMENTS, PHASE VII, CAMPBELL MASON VALVE REPLACEMENT PROJECT DESCRIPTION:
The project consists of the replacement of an existing 36-inch diameter motor operated butterfly valve (known as the Campbell Mason Valve) in Vault No. 59 located along Campbell Drive, south of Ashby Avenue.

ESTIMATED PROJECT COST $691,300.00 AWARD OF CONTRACT AMOUNT $498,190.00 CONTRACT ACCEPTANCE DATE 06/10/2009 DATE 04/29/2008 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 05/28/2008 03/06/2009 CONSTRUCTION COST $529,106.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 10/06/2006

COMPLETE DESIGN 02/05/2008 CHANGE ORDERS

RECEIPT OF BIDS 04/08/2008

TOTAL NUMBER 4 IN-HOUSE COST $67,826.79

TOTAL AMOUNT $31,916.00

DAYS EXTENDED 58

TOTAL PROJECT COST $691,299.50

NOTES: (1) Contract No. 1235 is titled Necessary System Improvements, Phase VII, Campbell Mason Valve Replacement, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

74

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1267 (1) MCP NUMBER 05-23

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VII: MISCELLANEOUS MAIN EXTENSIONS AND WATER SERVICE INSTALLATIONS, PHASE VI

PROJECT DESCRIPTION:
This project consists of the design and construction of 6-inch, 8-inch, and 12-inch inside diameter pipelines; 1-inch, 1-1/2-inch, and 2-inch water service assemblies; backflow prevention devices; fire hydrants; placement of temporary and permanent asphalt pavement and all related valves, fittings, connections, and appurtenances to provide complete water main extensions for residential service.

ESTIMATED PROJECT COST $329,063.00 AWARD OF CONTRACT AMOUNT $1,529,100.00 CONTRACT ACCEPTANCE DATE 08/04/2009 DATE 01/02/2008 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 02/04/2008 01/29/2009 CONSTRUCTION COST $1,181,770.75 LAND ACQUISITION COST

BEGIN DESIGN (2) 08/01/2007

COMPLETE DESIGN 10/10/2007 CHANGE ORDERS

RECEIPT OF BIDS 11/28/2007

TOTAL NUMBER 5 IN-HOUSE COST $11,540.69

TOTAL AMOUNT ($187,865.00)

DAYS EXTENDED 95

TOTAL PROJECT COST $329,063.30

NOTES: (1) Contract No. 1267 is titled Miscellaneous Main Extensions And Water Service Installations, Phase VI, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

75

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1301 (1) MCP NUMBER 05-23

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VII: NECESSARY SYSTEM IMPROVEMENTS, PHASE VII, SMALL DIAMETER PIPELINE INSTALLATIONS

PROJECT DESCRIPTION:
This project consists of the design and construction of improvement projects to replace existing cast iron main, relocate an existing air valve, relocate an existing valve vault, and install an in-line valve. Benefits will include improved safety and reliability of the distribution system.

ESTIMATED PROJECT COST $495,380.00 AWARD OF CONTRACT AMOUNT $175,401.50 CONTRACT ACCEPTANCE DATE 01/17/2012 DATE 02/21/2011 DESIGN COST $153,496.29

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 04/05/2011 11/02/2011 CONSTRUCTION COST $166,464.80 LAND ACQUISITION COST

BEGIN DESIGN (2) 08/11/2008

COMPLETE DESIGN 12/14/2010 CHANGE ORDERS

RECEIPT OF BIDS 02/01/2011

TOTAL NUMBER 3 IN-HOUSE COST $175,126.95

TOTAL AMOUNT ($8,936.70)

DAYS EXTENDED 13

TOTAL PROJECT COST $495,379.96

NOTES: (1) Contract No. 1301 is titled Necessary System Improvements, Phase VII, Small Diameter Pipeline Installations, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

76

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: LVVWD CAMPUS INFRASTRUCTURE CONTRACT NUMBER (2) MCP NUMBER 05-24

PROJECT DESCRIPTION:
This project consists of the design and construction of modifications to the operations building and campus infrastructure improvements as part of the overall campus master plan.

ESTIMATED PROJECT COST

LAND OR RIGHT-OFWAY STATUS Existing

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

AWARD OF CONTRACT AMOUNT DATE

NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

77

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 05-24

PROJECT TITLE: LVVWD CAMPUS INFRASTRUCTURE: LVVWD CAMPUS WAREHOUSE FACILITY

PROJECT DESCRIPTION:
This project consists of the design and construction of modifications to the operations building and campus infrastructure improvements as part of the overall campus master plan.

ESTIMATED PROJECT COST

LAND OR RIGHT-OFWAY STATUS Existing

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

AWARD OF CONTRACT AMOUNT DATE

NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

78

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 05-24

PROJECT TITLE: LVVWD CAMPUS INFRASTRUCTURE: INFORMATION SYSTEMS FACILITY

PROJECT DESCRIPTION:
This project consists of the design and construction of modifications to the operations building and campus infrastructure improvements as part of the overall campus master plan.

ESTIMATED PROJECT COST

LAND OR RIGHT-OFWAY STATUS Existing

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

AWARD OF CONTRACT AMOUNT DATE

NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

79

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1178 (1) MCP NUMBER 05-24

PROJECT TITLE: LVVWD CAMPUS INFRASTRUCTURE: MODIFICATIONS TO OPERATIONS BUILDING

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 7,000 square feet of office space to house both the major construction division and the development inspection division staff. Improvements will be to both the existing first and second story of the operations building.

ESTIMATED PROJECT COST $1,572,000.00 AWARD OF CONTRACT AMOUNT $1,021,000.00 CONTRACT ACCEPTANCE DATE 03/20/2007 DATE 12/15/2005 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 02/06/2006 01/13/2007 CONSTRUCTION COST $1,494,581.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 08/31/2005

COMPLETE DESIGN 08/31/2005 CHANGE ORDERS

RECEIPT OF BIDS 09/13/2005

TOTAL NUMBER 10 IN-HOUSE COST $77,818.35

TOTAL AMOUNT $473,581.00

DAYS EXTENDED 170

TOTAL PROJECT COST $1,572,399.35

NOTES: (1) Contract No. 1178 is titled Modifications To Operations Building, by the LVVWD Design Division. (2) Designed by Purvis Architects.

Construction Summary Report

80

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1202 (1) MCP NUMBER 05-24

PROJECT TITLE: LVVWD CAMPUS INFRASTRUCTURE: LVVWD CAMPUS IMPROVEMENTS PHASE I

PROJECT DESCRIPTION:
This project consists of a sanitary sewer analysis, parking, and drainage study for existing conditions and proposed facility expansions.

ESTIMATED PROJECT COST $719,616.00 AWARD OF CONTRACT AMOUNT $759,779.00 CONTRACT ACCEPTANCE DATE 02/19/2008 DATE 07/17/2007 DESIGN COST $50,400.00

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 08/06/2007 12/29/2007 CONSTRUCTION COST $746,593.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 12/15/2005

COMPLETE DESIGN 04/27/2007 CHANGE ORDERS

RECEIPT OF BIDS 06/12/2007

TOTAL NUMBER 2 IN-HOUSE COST $61,668.97

TOTAL AMOUNT ($13,186.00)

DAYS EXTENDED 11

TOTAL PROJECT COST $719,616.37

NOTES: (1) Contract No. 1202 is titled LVVWD Campus Improvements Phase I, by the LVVWD Design Division. (2) Designed by Wright Engineers.

Construction Summary Report

81

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1251 (1) MCP NUMBER 05-24

PROJECT TITLE: LVVWD CAMPUS INFRASTRUCTURE: LVVWD CAMPUS IMPROVEMENTS, PHASE II

PROJECT DESCRIPTION:
This project consists of a campus wide drainage study and the full design of a flood wall along the eastern boundary of the campus to mitigate ponding and flooding.

ESTIMATED PROJECT COST $829,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 12/15/2006

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1251 is titled LVVWD Campus Improvements, Phase II, by the LVVWD Design Division. (2) Designed by Wright Engineers.

Construction Summary Report

82

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: CHEMICAL STORAGE FACILITY CONTRACT NUMBER (2) MCP NUMBER 05-25

PROJECT DESCRIPTION:
This project consists of the design and construction of a chemical storage facility and administrative office space. The improvements will enhance operational efficiency and system reliability.

ESTIMATED PROJECT COST $2,100,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

83

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: COUGAR 3090 ZONE RESERVOIR CONTRACT NUMBER (2) MCP NUMBER 06-01

PROJECT DESCRIPTION:
This project consists of the design and construction of a 10 MG below grade reinforced concrete reservoir to provide additional gravity storage for the 3090 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the southern portion of the 3090 Pressure Zone.

ESTIMATED PROJECT COST $13,100,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

84

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 06-02

PROJECT TITLE: COUGAR 3090 ZONE RESERVOIR INLET/OUTLET PIPELINE

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 10,900 LF of 42-inch diameter pipeline to distribute water to the southern portion of the 3090 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the southern portion of the 3090 Pressure Zone.

ESTIMATED PROJECT COST $4,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

85

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1236 (1) MCP NUMBER 06-04

PROJECT TITLE: LVVWD MODULAR OFFICE FACILITIES: LVVWD CAMPUS OFF-SITE SEWER IMPROVEMENTS

PROJECT DESCRIPTION:
This project consists of the design and construction of a new 8-inch sanitary sewer outfall from the easterly property line of the Valley View campus, east in Hastings Avenue to Cashman Drive, then south in Cashman Drive to Charleston Boulevard, then east in Charleston Boulevard to connect to an existing 12-inch sanitary sewer in Charleston Boulevard. The new sewer will provide capacity for expansion at the Valley View campus, based on the proposed master plan.

ESTIMATED PROJECT COST $360,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 03/01/2007

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1236 is titled LVVWD Campus Off-site Sewer Improvements, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

86

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 06-06

PROJECT TITLE: POLYETHYLENE SERVICE REPLACEMENTS PHASE I

PROJECT DESCRIPTION:
This project consists of the design and construction of 6-inch, 8-inch, and 12-inch inside diameter pipelines; 1-inch, 1-1/2-inch, and 2-inch water service assemblies; backflow prevention devices; fire hydrants; placement of temporary and permanent asphalt pavement, and all related valves, fittings, connections and appurtenances to provide complete water main extensions for residential service.

ESTIMATED PROJECT COST $10,267,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

87

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1302 (1) MCP NUMBER 06-06

PROJECT TITLE: POLYETHYLENE SERVICE REPLACEMENTS PHASE I: POLYETHYLENE SERVICE REPLACEMENT CHARLESTON RAINBOW AND CHARLESTON HEIGHTS

PROJECT DESCRIPTION:
This project consists of the design and construction of 6-inch, 8-inch, and 12-inch inside diameter pipelines; 1-inch, 1-1/2-inch, and 2-inch water service assemblies; backflow prevention devices; fire hydrants; placement of temporary and permanent asphalt pavement, and all related valves, fittings, connections and appurtenances to provide complete water main extensions for residential service.

ESTIMATED PROJECT COST $537,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 8/11/2008

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1302 is titled Polyethylene Service Replacement, Charleston Rainbow And Charleston Heights, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

88

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1207 (1) MCP NUMBER 06-06

PROJECT TITLE: POLYETHYLENE SERVICE REPLACEMENTS PHASE I: POLYETHYLENE SERVICE REPLACEMENT, THE GROVE AND WOODCROFT

PROJECT DESCRIPTION:
This project consists of the replacement of existing polyethylene services within The Grove and Woodcroft communities, and American Village community.

ESTIMATED PROJECT COST $576,331.00 AWARD OF CONTRACT AMOUNT $597,515.00 CONTRACT ACCEPTANCE DATE 11/20/2007 DATE 03/06/2007 DESIGN COST $65,078.12

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 04/30/2007 10/02/2007 CONSTRUCTION COST $474,838.20 LAND ACQUISITION COST

BEGIN DESIGN (2) 02/17/2006

COMPLETE DESIGN 01/04/2007 CHANGE ORDERS

RECEIPT OF BIDS 02/13/2007

TOTAL NUMBER 2 IN-HOUSE COST $36,415.00

TOTAL AMOUNT ($104,770.00)

DAYS EXTENDED

TOTAL PROJECT COST $576,331.32

NOTES: (1) Contract No. 1207 is titled Polyethylene Service Replacement, The Grove And Woodcroft, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

89

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1268 (1) MCP NUMBER 06-06

PROJECT TITLE: POLYETHYLENE SERVICE REPLACEMENTS PHASE I: POLYETHYLENE SERVICE REPLACEMENT, SPRING VALLEY AND LAUREL PARK

PROJECT DESCRIPTION:
This project consists of the replacement of existing polyethylene services within the Spring Valley and Laurel Park communities. The work consists of the replacement of approximately 191 polyethylene service assemblies with copper water tube and new corporation stops, service saddles, and angle meter stops as required. Additional work includes the installation of one (1) new backflow assembly (RPPA) on an irrigation service.

ESTIMATED PROJECT COST $451,961.00 AWARD OF CONTRACT AMOUNT $481,125.00 CONTRACT ACCEPTANCE DATE 05/14/2009 DATE 08/22/2008 DESIGN COST $36,403.18

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 09/24/2008 12/26/2008 CONSTRUCTION COST $373,006.40 LAND ACQUISITION COST

BEGIN DESIGN (2) 08/20/2007

COMPLETE DESIGN 06/25/2008 CHANGE ORDERS

RECEIPT OF BIDS 08/05/2008

TOTAL NUMBER 1 IN-HOUSE COST $42,551.11

TOTAL AMOUNT ($124,585.00)

DAYS EXTENDED

TOTAL PROJECT COST $451,960.69

NOTES: (1) Contract No. 1268 is titled Polyethylene Service Replacement, Spring Valley And Laurel Park, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

90

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: CHEMICAL STORAGE FACILITY PHASE II CONTRACT NUMBER (2) MCP NUMBER 06-07

PROJECT DESCRIPTION:
This project consists of the design and construction of a chemical storage facility in the northwest portion of the Las Vegas Valley.

ESTIMATED PROJECT COST $648,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

91

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1273 (1) MCP NUMBER 06-07

PROJECT TITLE: CHEMICAL STORAGE FACILITY PHASE II: TROPICAL SATELLITE FACILITY CAMPUS

PROJECT DESCRIPTION:
This project consists of the design and construction of a master site plan for additional facilities and buildings proposed to be built within this site, including the Northwest Disinfection Storage Facility, an administration building for District staff from the production, construction, and distribution divisions, a vehicle maintenance building, a vehicle fueling facility, and a 60,000 square foot warehouse with office space attached to the building. The master plan will consider the requirements for the site including access roads, parking spaces, landscaping, and site security.

ESTIMATED PROJECT COST $3,352,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 12/12/2007

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1273 is titled Tropical Satellite Facility Campus, by the LVVWD Design Division. (2) Designed by Domingo Cambeiro Corp.

Construction Summary Report

92

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: ELECTRICAL EQUIPMENT IMPROVEMENTS CONTRACT NUMBER (2) MCP NUMBER 06-08

PROJECT DESCRIPTION:
This project consists of the design and construction of electrical equipment improvements at Broadbent, Luce, Ronzone, and District campus facilities.

ESTIMATED PROJECT COST $1,020,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

93

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 06-09

PROJECT TITLE: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR PHASE III

PROJECT DESCRIPTION:
This project consists of the repair, modification, or replacement of existing meter vaults within the distribution system.

ESTIMATED PROJECT COST

LAND OR RIGHT-OFWAY STATUS Existing

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

AWARD OF CONTRACT AMOUNT DATE

NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

94

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1209 (1) MCP NUMBER 06-09

PROJECT TITLE: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR PHASE III: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR, PHASE XI

PROJECT DESCRIPTION:
This project consists of the installation of a new aboveground pressure reducing station complete with control valve with metering feature, gate valves, connecting piping, electrical power and telemetry, enclosure, and the abandonment of an existing belowground pressure reducing station. The work includes permanent pavement replacement, and all related valves, fittings, connections and appurtenances.

ESTIMATED PROJECT COST $511,094.00 AWARD OF CONTRACT AMOUNT $405,074.00 CONTRACT ACCEPTANCE DATE 10/07/2008 DATE 11/14/2007 DESIGN COST $86,242.16

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 01/02/2008 06/16/2008 CONSTRUCTION COST $367,886.53 LAND ACQUISITION COST

BEGIN DESIGN (2) 05/11/2006

COMPLETE DESIGN 09/05/2007 CHANGE ORDERS

RECEIPT OF BIDS 10/25/2007

TOTAL NUMBER 1 IN-HOUSE COST $56,964.89

TOTAL AMOUNT ($37,002.12)

DAYS EXTENDED

TOTAL PROJECT COST $511,093.58

NOTES: (1) Contract No. 1209 is titled Miscellaneous Vaults, Reconstruction And Repair, Phase XI, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

95

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1210 (1) MCP NUMBER 06-09

PROJECT TITLE: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR, PHASE III: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR, PHASE XII

PROJECT DESCRIPTION:
This project consists of the repair, reconstruction or modification of six (6) existing underground meter vaults. A new roof and hatch will be constructed for one (1) of the vaults; new backflow assemblies and aboveground enclosures will be installed for three (3) of the vaults; new underground concrete meter vaults will be installed for four (4) of the meters; and one (1) site will have stairs installed for access.

ESTIMATED PROJECT COST $542,961.00 AWARD OF CONTRACT AMOUNT $453,490.00 CONTRACT ACCEPTANCE DATE 09/02/2008 DATE 09/18/2007 DESIGN COST $43,223.59

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 10/17/2007 08/06/2008 CONSTRUCTION COST $453,711.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 05/11/2006

COMPLETE DESIGN 07/09/2007 CHANGE ORDERS

RECEIPT OF BIDS 08/22/2007

TOTAL NUMBER 3 IN-HOUSE COST $46,026.03

TOTAL AMOUNT $221.00

DAYS EXTENDED

TOTAL PROJECT COST $542,960.62

NOTES: (1) Contract No. 1210 is titled Miscellaneous Vaults, Reconstruction And Repair, Phase XII, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

96

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1211 (1) MCP NUMBER 06-09

PROJECT TITLE: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR PHASE III: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR, PHASE XIII

PROJECT DESCRIPTION:
This project consists of the repair, modification, or replacement of existing meter vaults within the distribution system.

ESTIMATED PROJECT COST $571,496.00 AWARD OF CONTRACT AMOUNT $504,704.00 CONTRACT ACCEPTANCE DATE 05/14/2009 DATE 02/26/2008 DESIGN COST $91,096.75

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 04/15/2008 01/14/2009 CONSTRUCTION COST $415,568.21 LAND ACQUISITION COST

BEGIN DESIGN (2) 05/11/2006

COMPLETE DESIGN 11/16/2007 CHANGE ORDERS

RECEIPT OF BIDS 01/15/2008

TOTAL NUMBER 4 IN-HOUSE COST $64,830.59

TOTAL AMOUNT ($82,572.20)

DAYS EXTENDED 22

TOTAL PROJECT COST $571,495.55

NOTES: (1) Contract No. 1211 is titled Miscellaneous Vaults, Reconstruction And Repair, Phase XIII, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

97

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1249 (1) MCP NUMBER 06-09

PROJECT TITLE: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR PHASE III: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR, PHASE XIV

PROJECT DESCRIPTION:
This project consists of the repair, modification, or replacement of existing meter vaults within the distribution system.

ESTIMATED PROJECT COST $886,864.00 AWARD OF CONTRACT AMOUNT $1,199,765.00 CONTRACT ACCEPTANCE DATE 08/03/2010 DATE 01/05/2009 DESIGN COST $120,563.00

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 03/02/2009 02/25/2010 CONSTRUCTION COST $688,644.20 LAND ACQUISITION COST

BEGIN DESIGN (2) 02/21/2007

COMPLETE DESIGN 10/08/2008 CHANGE ORDERS

RECEIPT OF BIDS 11/13/2008

TOTAL NUMBER 8 IN-HOUSE COST $198,219.32

TOTAL AMOUNT ($315,231.50)

DAYS EXTENDED 92

TOTAL PROJECT COST $886,863.52

NOTES: (1) Contract No. 1249 is titled Miscellaneous Vaults, Reconstruction And Repair, Phase XIV, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

98

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1250 (1) MCP NUMBER 06-09

PROJECT TITLE: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR PHASE III: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR, PHASE XV

PROJECT DESCRIPTION:
This project consists of relocating an existing below grade pressure reducing station from street rights-of-way to an above grade location on private property. The new station will include flow meters and pressure transmitters, along with electrical and telemetry to send flow rates and pressure information to the District SCADA system. One (1) station will be constructed: Pressure Reducing Station No. 10 on 5048 Stewart Avenue.

ESTIMATED PROJECT COST $357,441.00 AWARD OF CONTRACT AMOUNT $193,391.00 CONTRACT ACCEPTANCE DATE 06/10/2010 DATE 06/24/2008 DESIGN COST $113,427.60

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 07/28/2008 09/21/2009 CONSTRUCTION COST $198,111.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 02/21/2007

COMPLETE DESIGN 04/25/2008 CHANGE ORDERS

RECEIPT OF BIDS 06/04/2008

TOTAL NUMBER 6 IN-HOUSE COST $159,329.82

TOTAL AMOUNT $5,680.00

DAYS EXTENDED 120

TOTAL PROJECT COST $357,440.82

NOTES: (1) Contract No. 1250 is titled Miscellaneous Vaults, Reconstruction And Repair, Phase XV, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

99

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1266 (1) MCP NUMBER 06-09

PROJECT TITLE: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR PHASE III: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR, PHASE XVI

PROJECT DESCRIPTION:
This project consists of the installation of one (1) new aboveground pressure reducing station and one (1) belowground pressure reducing station complete with valves, pressure control valves with metering feature, connecting piping, electrical power and telemetry, enclosure, reinforced concrete vault, and the abandonment of two (2) existing belowground pressure reducing stations. The work includes permanent pavement replacement, and all related valves, fittings, connections and appurtenances.

ESTIMATED PROJECT COST $381,000.00 AWARD OF CONTRACT AMOUNT $169,891.00 CONTRACT ACCEPTANCE DATE 08/17/2011 DATE 11/15/2010 DESIGN COST $104,177.76

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 01/19/2011 08/17/2011 CONSTRUCTION COST $185,849.77 LAND ACQUISITION COST

BEGIN DESIGN (2) 11/01/2007

COMPLETE DESIGN 05/24/2010 CHANGE ORDERS

RECEIPT OF BIDS 09/30/2010

TOTAL NUMBER 1 IN-HOUSE COST $194,904.89

TOTAL AMOUNT $15,958.56

DAYS EXTENDED

TOTAL PROJECT COST $380,754.66

NOTES: (1) Contract No. 1266 is titled Miscellaneous Vaults, Reconstruction And Repair, Phase XVI, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

100

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1282 (1) MCP NUMBER 06-09

PROJECT TITLE: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR PHASE III: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR, PHASE XVII

PROJECT DESCRIPTION:
This project consists of the abandonment of three (3) existing belowground pressure reducing stations; the installation of one (1) new aboveground 10-inch by 6-inch pressure reducing station complete with valves, pressure control valves with metering feature, connecting piping, electrical power and telemetry, and an insulated enclosure; and the relocation of a 1-1/2-inch meter and an 8-inch DCDA. The work includes installation of 28 residential pressure reducing valves, one (1) 6-inch cut in zone valve, placement of temporary and permanent asphalt pavement, milling and asphaltic concrete open-graded surface, and all related valves, fittings, connections and appurtenances.

ESTIMATED PROJECT COST $565,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 02/29/2008

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1282 is titled Miscellaneous Vaults, Reconstruction And Repair, Phase XVII, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

101

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1283 (1) MCP NUMBER 06-09

PROJECT TITLE: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR PHASE III: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR, PHASE XVIII

PROJECT DESCRIPTION:
This project consists of the repair and reconstruction of at least six (6) existing underground meter vaults. New roofs and hatches will be constructed as required, and new backflow assemblies and aboveground enclosures will be installed as required.

ESTIMATED PROJECT COST $641,000.00 AWARD OF CONTRACT AMOUNT $348,700.00 CONTRACT ACCEPTANCE DATE 06/25/2012 DATE 07/13/2011 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 07/05/2011 03/22/2012 CONSTRUCTION COST $375,370.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 02/27/2008

COMPLETE DESIGN 04/06/2011 CHANGE ORDERS

RECEIPT OF BIDS 05/19/2011

TOTAL NUMBER 2 IN-HOUSE COST $266,034.62

TOTAL AMOUNT $26,670.00

DAYS EXTENDED 51

TOTAL PROJECT COST $641,404.62

NOTES: (1) Contract No. 1283 is titled Miscellaneous Vaults, Reconstruction And Repair, Phase XVIII, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

102

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1294 (1) MCP NUMBER 06-09

PROJECT TITLE: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR PHASE III: MISCELLANEOUS VAULTS, RECONSTRUCTION AND REPAIR, PHASE XIX

PROJECT DESCRIPTION:
This project consists of the repair, modification, or replacement of existing meter vaults within the distribution system.

ESTIMATED PROJECT COST $751,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 07/17/2008

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1294 is titled Miscellaneous Vaults, Reconstruction And Repair, Phase XIX, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

103

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 06-10

PROJECT TITLE: SUNRISE MOUNTAIN 2380 ZONE PUMPING STATION

PROJECT DESCRIPTION:
This project consists of the design and construction of a 6 MGD pumping station, based on 24 hour per day operation. Two (2) variable speed pumping units and one (1) constant speed pumping unit for fire protection will be installed to transfer water from the 2150 Pressure Zone into the 2380 Pressure Zone.

ESTIMATED PROJECT COST $4,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

104

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: ROME 2975 ZONE PUMPING STATION CONTRACT NUMBER (2) MCP NUMBER 06-11

PROJECT DESCRIPTION:
This project consists of the design and construction of three (3) constant speed pumping units at the Rome 2975 Pressure Zone Pumping Station, located at the proposed Rome 2745 Zone Reservoir site, to transfer water from the 2745 Pressure Zone into the 2975 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the northern area of the 2975 Pressure Zone.

ESTIMATED PROJECT COST $9,090,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

105

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 06-12

PROJECT TITLE: ROME 2975 ZONE PUMPING STATION DISCHARGE PIPELINE

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 1,700 LF of 42-inch diameter pipeline to distribute water to the northern portion of the 2975 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the 2975 Pressure Zone.

ESTIMATED PROJECT COST $745,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

106

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Construction CONTRACT NUMBER 1280 MCP NUMBER 06-13

PROJECT TITLE: CHEYENNE 2975 ZONE MOTOR OPERATED VALVES

PROJECT DESCRIPTION:
This project consists of the retrofit of two (2) existing valves in the 2975 Pressure Zone for remote motor-operated control, providing operational flexibility to the direct water pumped from the Grand Canyon 2975 Zone Pumping Station to either the existing Elkhorn 2975 Zone Reservoir or to the existing Anasazi 2975 Zone Reservoir.

ESTIMATED PROJECT COST $498,000.00 AWARD OF CONTRACT AMOUNT $219,088.00 CONTRACT ACCEPTANCE DATE DATE 09/02/2010 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 11/01/2010 07/24/2012 CONSTRUCTION COST LAND ACQUISITION COST

BEGIN DESIGN (1) 02/28/2008

COMPLETE DESIGN 05/12/2010 CHANGE ORDERS

RECEIPT OF BIDS 06/24/2010

TOTAL NUMBER

TOTAL AMOUNT

DAYS EXTENDED

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Designed by LVVWD Design Division.

Construction Summary Report

107

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Reported Under MCP 03-10 PROJECT TITLE: SLOAN 3205 ZONE SOUTH PUMPING STATION CONTRACT NUMBER 1212 MCP NUMBER 06-14

PROJECT DESCRIPTION:
This project consists of the design and construction of a 6 MGD pumping station, based on a 24 hour per day operation. Four (4) constant speed pumping units will be installed to transfer water from the 2745 Pressure Zone into the 3205 Pressure Zone. Provisions will be made for the future installation of eight (8) additional constant speed pumping units to provide an ultimate capacity of 26 MGD based on a 24 hour per day operation. The improvements will enhance operational efficiency and system reliability in the southern portion of the 3205 Pressure Zone.

ESTIMATED PROJECT COST

LAND OR RIGHT-OFWAY STATUS

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

AWARD OF CONTRACT AMOUNT DATE

NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE NOTES:

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

Construction Summary Report

108

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design PROJECT TITLE: SUMMIT 3205 ZONE SOUTH TANKS CONTRACT NUMBER 1312 MCP NUMBER 06-15

PROJECT DESCRIPTION:
This project consists of the design and construction of one (1) 5 MG above grade reinforced concrete tank with plans for future expansion to two (2) 5 MG tanks to provide gravity storage for the 3205 Pressure Zone, and to transfer storage for pressure zones to the south and to the west to serve the Ivanpah Airport. The improvements will enhance operational efficiency and system reliability in the southern portion of the 3205 Pressure Zone.

ESTIMATED PROJECT COST $3,619,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (1) 01/31/2009

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Designed by the LVVWD Design Division.

Construction Summary Report

109

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: RICHMAR 2860 ZONE RESERVOIR CONTRACT NUMBER (2) MCP NUMBER 08-01

PROJECT DESCRIPTION:
This project consists of the design and construction of a 20 MG below grade reinforced concrete reservoir to provide additional gravity storage for the 2860 Pressure Zone, and to transfer storage for pressure zones to the west. The improvements will enhance operational efficiency and system reliability in the southern portion of the 2860 Pressure Zone.

ESTIMATED PROJECT COST $18,400,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

110

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 08-02

PROJECT TITLE: RICHMAR 2860 ZONE RESERVOIR INLET/OUTLET PIPELINE

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 7,200 LF of 42-inch diameter pipeline to distribute water to the southern portion of the 2860 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the southern portion of the 2860 Pressure Zone.

ESTIMATED PROJECT COST $3,564,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS To Be Acquired NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

111

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: RICHMAR 2975 ZONE PUMPING STATION CONTRACT NUMBER (2) MCP NUMBER 08-03

PROJECT DESCRIPTION:
This project consists of the design and construction of a 29 MGD pumping station, based on a 16 hour per day operation. Five (5) constant speed pumping units will be installed to transfer water from the 2860 Pressure Zone into the 2975 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the southern portion of the 2975 Pressure Zone.

ESTIMATED PROJECT COST $12,050,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

112

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 08-04

PROJECT TITLE: RICHMAR 2975 ZONE PUMPING STATION DISCHARGE PIPELINE

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 750 LF of 42-inch diameter pipeline to distribute water to the southern portion of the 2975 Pressure Zone. The improvements will enhance operational efficiency and system reliability in the southern portion of the 2975 Pressure Zone.

ESTIMATED PROJECT COST $405,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

113

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: TRIHALOMETHANES TREATMENT PROJECT CONTRACT NUMBER (2) MCP NUMBER 08-05

PROJECT DESCRIPTION:
This project consists of the design and construction of air stripping and aeration systems to remove excessive concentrations of THMs in targeted areas of the existing distribution system.

ESTIMATED PROJECT COST

LAND OR RIGHT-OFWAY STATUS Existing

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

AWARD OF CONTRACT AMOUNT DATE

NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

114

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1293 (1) MCP NUMBER 08-05

PROJECT TITLE: TRIHALOMETHANES TREATMENT PROJECT: TRIHALOMETHANES TREATMENT PROJECT, PHASE I - ALTA 3205 ZONE RESERVOIR

PROJECT DESCRIPTION:
This project consists of the design and construction of a fine bubble aeration system to treat trihalomethanes at the existing Alta 3205 Zone Reservoir. The fine bubble aeration system consists of blowers, air header pipelines, and aeration grids.

ESTIMATED PROJECT COST $2,428,725.00 AWARD OF CONTRACT AMOUNT $1,239,445.00 CONTRACT ACCEPTANCE DATE 12/07/2010 DATE 07/07/2009 DESIGN COST $843,680.35

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 07/16/2009 07/08/2010 CONSTRUCTION COST $1,338,328.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 07/15/2008

COMPLETE DESIGN 03/13/2009 CHANGE ORDERS

RECEIPT OF BIDS 05/08/2009

TOTAL NUMBER 7 IN-HOUSE COST $246,716.34

TOTAL AMOUNT $98,883.00

DAYS EXTENDED 90

TOTAL PROJECT COST $2,428,724.69

NOTES: (1) Contract No. 1293 is titled Trihalomethanes Treatment Project, Phase I - Alta 3205 Zone Reservoir, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

115

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1329 (1) MCP NUMBER 08-05

PROJECT TITLE: TRIHALOMETHANES TREATMENT PROJECT: TRIHALOMETHANES TREATMENT PROJECT, PHASE II - ELKHORN 2975 ZONE RESERVOIR

PROJECT DESCRIPTION:
This project consists of the design and construction of a fine bubble aeration system at the existing Elkhorn 2975 Zone Reservoir. The aeration system will consist of two (2) turbo air blowers, each with a rated capacity of approximately 1,900 standard cubic feet per minute (scfm), and approximately 2,000 fine pore-air diffusers assembled in grids and installed on the floor of two (2) existing reservoir basins.

ESTIMATED PROJECT COST $1,403,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 07/22/2010

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1329 is titled Trihalomethanes Treatment Project, Phase II - Elkhorn 2975 Zone Reservoir, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

116

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Construction CONTRACT NUMBER 1330 (1) MCP NUMBER 08-05

PROJECT TITLE: TRIHALOMETHANES TREATMENT PROJECT: TRIHALOMETHANES TREATMENT PROJECT, PHASE III - LEVI 2745 ZONE RESERVOIR

PROJECT DESCRIPTION:
This project consists of the design and construction of a fine bubble aeration system at the existing Levi 2745 Zone Reservoir. The aeration system will consist of two (2) turbo air blowers, each with a rated capacity of 5,800 standard cubic feet per minute (scfm), and approximately 5,800 fine pore-air diffusers assembled in grids and installed on the floor of two (2) existing reservoir basins.

ESTIMATED PROJECT COST $1,938,000.00 AWARD OF CONTRACT AMOUNT $1,447,486.00 CONTRACT ACCEPTANCE DATE DATE 04/03/2012 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 05/30/2012 05/25/2013 CONSTRUCTION COST LAND ACQUISITION COST

BEGIN DESIGN (2) 07/22/2010

COMPLETE DESIGN 01/14/2012 CHANGE ORDERS

RECEIPT OF BIDS 02/14/2012

TOTAL NUMBER

TOTAL AMOUNT

DAYS EXTENDED

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1330 is titled Trihalomethanes Treatment Project, Phase III - Levi 2745 Zone Reservoir, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

117

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 08-06

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VIII

PROJECT DESCRIPTION:
This project consists of the design and construction of improvement projects to reinforce weak areas of the distribution system where connections are not expected to be installed by developers due to the level of existing development. The improvements will enhance pressure and fire flow availability, as well as eliminate many single-feed connections and the associated water quality problems.

ESTIMATED PROJECT COST $5,874,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

118

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 08-06

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VIII: VALLEY VIEW/MAULE 2300 ZONE MOTOR OPERATED VALVE

PROJECT DESCRIPTION:
This project consists of the design and retrofit of one (1) existing valve in the 2300 Pressure Zone for remote motor operated control, providing flexibility to direct water from the newly installed Valley View/Maule PRVs to either the Maule 2300 Zone Reservoir or to the Pico 2300 Zone Reservoir.

ESTIMATED PROJECT COST

LAND OR RIGHT-OFWAY STATUS Existing

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

AWARD OF CONTRACT AMOUNT DATE

NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

119

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 08-06

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VIII: RAMPART/ALTA PIPELINE RELOCATION, PHASE II

PROJECT DESCRIPTION:
This project consists of the relocation of approximately 1,300 LF of 36-inch diameter pipeline near the intersection of Alta Drive and Rampart Boulevard.

ESTIMATED PROJECT COST $1,262,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

120

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 08-06

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VIII: WASHINGTON 2420 ZONE EMERGENCY CHECK VALVE INSTALLATIONS

PROJECT DESCRIPTION:
This project consists of the design and construction of two (2) 8-inch check valves to provide an emergency supply to the 2420 Pressure Zone from the 2300 Pressure Zone.

ESTIMATED PROJECT COST $145,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

121

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1306 (1) MCP NUMBER 08-06

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VIII: MISCELLANEOUS MAIN EXTENSIONS AND WATER SERVICE INSTALLATIONS, PHASE VII

PROJECT DESCRIPTION:
This project consists of the installation of 6-inch, 8-inch and 12-inch inside diameter pipelines; 1-inch, 1-1/2-inch, and 2-inch water service assemblies; backflow prevention devices; fire hydrants; placement of temporary and permanent asphalt pavement, and all related valves, fittings, connections and appurtenances to provide complete water main extensions for residential service. The horizontal length of each extension will not be less than approximately 50 feet or greater than approximately 1,000 feet. It is anticipated that the total contract will consist of the installation of approximately 12,000 LF of pipeline and 55 water service assemblies at approximately 30 separate locations throughout the District service area.

ESTIMATED PROJECT COST $39,980.00 AWARD OF CONTRACT AMOUNT $969,480.00 CONTRACT ACCEPTANCE DATE 11/3/2010 DATE 06/02/2009 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 07/01/2009 06/26/2010 CONSTRUCTION COST $416,995.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 09/15/2008

COMPLETE DESIGN 02/09/2009 CHANGE ORDERS

RECEIPT OF BIDS 03/25/2009

TOTAL NUMBER 7 IN-HOUSE COST $23,103.68

TOTAL AMOUNT ($520,849.00)

DAYS EXTENDED 31

TOTAL PROJECT COST $39,979.54

NOTES: (1) Contract No. 1306 is titled Miscellaneous Main Extensions And Water Service Installations, Phase VII, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

122

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1307 (1) MCP NUMBER 08-06

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VIII: RAMPART/ALTA PIPELINE RELOCATION, PHASE I

PROJECT DESCRIPTION:
This project consists of the relocation of approximately 1,000 LF of 36-inch diameter pipeline near the intersection of Alta Drive and Rampart Boulevard.

ESTIMATED PROJECT COST $1,531,000.00 AWARD OF CONTRACT AMOUNT $1,073,837.00 CONTRACT ACCEPTANCE DATE 03/01/2011 DATE 4/7/2009 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 4/29/2009 01/01/2010 CONSTRUCTION COST $1,293,654.86 LAND ACQUISITION COST

BEGIN DESIGN (2) 9/18/2008

COMPLETE DESIGN 1/21/2009 CHANGE ORDERS

RECEIPT OF BIDS 2/19/2009

TOTAL NUMBER 3 IN-HOUSE COST $237,830.08

TOTAL AMOUNT $219,818.00

DAYS EXTENDED 138

TOTAL PROJECT COST $1,531,484.94

NOTES: (1) Contract No. 1307 is titled Rampart/Alta Pipeline Relocation, Phase I, by the LVVWD Design Division. (2) Designed by the LVVWD Design Division.

Construction Summary Report

123

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Construction CONTRACT NUMBER 1338 (1) MCP NUMBER 08-06

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VIII: MISCELLANEOUS MAIN EXTENSIONS AND WATER SERVICE INSTALLATIONS, PHASE VIII

PROJECT DESCRIPTION:
This project consists of the design and construction of 6-inch, 8-inch, 10-inch, and 12-inch inside diameter pipelines, 1-inch, 1-1/2-inch, and 2-inch water service assemblies; backflow prevention devices; fire hydrants; and placement of temporary and permanent asphalt pavement and all related valves, fittings, connections and appurtenances to provide complete water main extensions for residential service.

ESTIMATED PROJECT COST $1,012,000.00 AWARD OF CONTRACT AMOUNT $898,825.00 CONTRACT ACCEPTANCE DATE DATE 04/05/2011 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 05/03/2011 05/02/2012 CONSTRUCTION COST LAND ACQUISITION COST

BEGIN DESIGN (2) 10/18/2010

COMPLETE DESIGN 01/12/2011 CHANGE ORDERS

RECEIPT OF BIDS 02/15/2011

TOTAL NUMBER 5 IN-HOUSE COST

TOTAL AMOUNT ($159,075.00)

DAYS EXTENDED 30

TOTAL PROJECT COST

NOTES: (1) Contract No. 1338 is titled Miscellaneous Main Extensions And Water Service Installations, Phase VIII, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

124

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1353 (1) MCP NUMBER 08-06

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VIII: MISCELLANEOUS MAIN EXTENSIONS AND WATER SERVICE INSTALLATIONS, PHASE IX

PROJECT DESCRIPTION:
This project consists of the design and construction of 6-inch, 8-inch, 10-inch, and 12-inch inside diameter pipelines, 1-inch, 1-1/2 inch, and 2-inch water service assemblies and backflow prevention devices, fire hydrants, and placement of temporary and permanent asphalt pavement and all related valves, fittings, connections and appurtenances to provide complete water main extensions for residential service.

ESTIMATED PROJECT COST $1,100,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 12/11/2011

COMPLETE DESIGN 05/17/2012 CHANGE ORDERS

RECEIPT OF BIDS 06/20/2012

TOTAL NUMBER

TOTAL AMOUNT

DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1353 is titled Miscellaneous Main Extensions And Water Service Installations, Phase IX, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

125

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1354 (1) MCP NUMBER 08-06

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VIII: OAKEY/I-15 PIPELINE RELOCATION

PROJECT DESCRIPTION:
This project consists of the design and construction of relocating an underground storm drain structure that will intersect with the existing 36-inch steel cylinder concrete pipe (SCCP) located at I-15 and Oakey Boulevard.

ESTIMATED PROJECT COST $809,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 10/12/2011

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1354 is titled Oakey/I-15 Pipeline Relocation, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

126

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1358 (1) MCP NUMBER 08-06

PROJECT TITLE: NECESSARY SYSTEM IMPROVEMENTS, PHASE VIII: NECESSARY SYSTEM IMPROVEMENTS, RAILROAD PASS PIPELINE RELOCATION

PROJECT DESCRIPTION:
This project consists of the design and construction of a new 12-inch PVC pipeline, along with other necessary control valves, in a new highway frontage road to be designed and constructed by NDOT. The 12-inch PVC pipeline will be connected to a pipeline that is being designed concurrently by the City of Henderson.

ESTIMATED PROJECT COST $950,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 05/15/2012

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1358 is titled Necessary System Improvements, Railroad Pass Pipeline Relocation, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

127

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER 1305 (2) MCP NUMBER 08-07

PROJECT TITLE: PRODUCTION WELL CAPACITY ADDITION: WELL NO. 126 DISCHARGE PIPELINE

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 1,600 LF of 16-inch diameter pipeline and 1,550 LF of 24-inch diameter pipeline, with all associated fittings and outlets, valves, and related appurtenances. The pipeline will connect the proposed Well No. 126 to an existing portion of the distribution system.

ESTIMATED PROJECT COST $1,300,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract No. 1305 is titled Well No. 126 Discharge Pipeline, by the LVVWD Design Division.

Construction Summary Report

128

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design PROJECT TITLE: LVVWD CAMPUS WAREHOUSE FACILITY CONTRACT NUMBER 1255 MCP NUMBER 08-08

PROJECT DESCRIPTION:
This project consists of the design and construction of a new LEED certified 86,000 square foot warehouse facility, and a 40,000 square foot outside storage area, adjacent to the Desert Demonstration Gardens. This project also includes a 10,000 square foot child care facility that will be located in place of the old Desert Demonstration Gardens. The work also requires some on-site utility relocations.

ESTIMATED PROJECT COST $15,500,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (1) 03/25/2008

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Designed by the LVVWD Design Division.

Construction Summary Report

129

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: CHILD CARE FACILITY CONTRACT NUMBER (2) MCP NUMBER 08-09

PROJECT DESCRIPTION:
This project consists of the design and construction of a LEED certified child care facility to be located at the Valley View campus.

ESTIMATED PROJECT COST $3,500,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

130

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER 1256 (2) MCP NUMBER 08-10

PROJECT TITLE: LVVWD CAMPUS INFORMATION TECHNOLOGY FACILITY: INFORMATION SYSTEMS FACILITY

PROJECT DESCRIPTION:
This project consists of the design and construction of a LEED certified office and computer equipment space for the District central data storage and computer system infrastructure.

ESTIMATED PROJECT COST $29,600,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract No. 1256 is titled Information Systems Facility, by the LVVWD Design Division.

Construction Summary Report

131

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: RENEWABLE ENERGY PROJECT PHASE II CONTRACT NUMBER (2) MCP NUMBER 08-11

PROJECT DESCRIPTION:
This project consists of the design and construction of solar power systems at five (5) reservoir and pumping station sites.

ESTIMATED PROJECT COST $29,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

132

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending PROJECT TITLE: RENEWABLE ENERGY PROJECT, PHASE II CONTRACT NUMBER 1341 MCP NUMBER 08-11

PROJECT DESCRIPTION:
This project consists of the design and construction of a 100kw solar power system at the Elkhorn 2975 Zone Reservoir site.

ESTIMATED PROJECT COST $1,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

133

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 08-12

PROJECT TITLE: BACKFLOW ASSEMBLY INSTALLATION PHASE II

PROJECT DESCRIPTION:
This project consists of the design and installation of backflow assemblies at various locations.

ESTIMATED PROJECT COST $923,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

134

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1332 (1) MCP NUMBER 08-12

PROJECT TITLE: BACKFLOW ASSEMBLY INSTALLATION PHASE II: MISCELLANEOUS BACKFLOW INSTALLATIONS, PHASE XIII

PROJECT DESCRIPTION:
This project consists of the design and installation of approximately 550 either 1-inch, 1-1/2-inch, or 2-inch diameter backflow prevention assemblies at various locations.

ESTIMATED PROJECT COST $510,339.00 AWARD OF CONTRACT AMOUNT $396,215.00 CONTRACT ACCEPTANCE DATE 03/22/2012 DATE 05/18/2011 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 06/27/2011 01/23/2012 CONSTRUCTION COST $319,695.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 05/12/2010

COMPLETE DESIGN 03/02/2011 CHANGE ORDERS

RECEIPT OF BIDS 04/12/2011

TOTAL NUMBER 2 IN-HOUSE COST $108,939.34

TOTAL AMOUNT ($105,040.00)

DAYS EXTENDED

TOTAL PROJECT COST $510,339.12

NOTES: (1) Contract No. 1332 is titled Miscellaneous Backflow Installations, Phase XIII, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

135

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending CONTRACT NUMBER 1333 (1) MCP NUMBER 08-12

PROJECT TITLE: BACKFLOW ASSEMBLY INSTALLATION PHASE II: MISCELLANEOUS BACKFLOW INSTALLATIONS, PHASE XIV

PROJECT DESCRIPTION:
This project consists of the design and installation of approximately 500 either 1-inch, 1-1/2-inch, or 2-inch diameter backflow prevention assemblies at various locations.

ESTIMATED PROJECT COST $1,210,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1333 is titled Miscellaneous Backflow Installations, Phase XIV, by the LVVWD Design Division.

Construction Summary Report

136

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Construction CONTRACT NUMBER 1334 (1) MCP NUMBER 08-12

PROJECT TITLE: BACKFLOW ASSEMBLY INSTALLATION PHASE II: MISCELLANEOUS LARGE BACKFLOW INSTALLATIONS, PHASE II

PROJECT DESCRIPTION:
This project consists of the design and installation of 3- through 10-inch backflow prevention assemblies. The installed assemblies will be above grade within a metallic or fiberglass enclosure on a concrete pad. Work will include replacement of existing concrete or asphalt, fittings, appurtenances, and relocation of fencing around the newly installed device. The total contract will consist of the installation of approximately 18 backflow prevention assemblies throughout the District's service area.

ESTIMATED PROJECT COST $582,000.00 AWARD OF CONTRACT AMOUNT $482,945.00 CONTRACT ACCEPTANCE DATE DATE 10/25/2011 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 12/06/2011 10/21/2012 CONSTRUCTION COST LAND ACQUISITION COST

BEGIN DESIGN (2) 06/29/2010

COMPLETE DESIGN 08/06/2011 CHANGE ORDERS

RECEIPT OF BIDS 09/08/2011

TOTAL NUMBER 2 IN-HOUSE COST

TOTAL AMOUNT $25,173.00

DAYS EXTENDED 38

TOTAL PROJECT COST

NOTES: (1) Contract No. 1334 is titled Miscellaneous Large Backflow Installations, Phase II, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

137

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1350 (1) MCP NUMBER 08-12

PROJECT TITLE: BACKFLOW ASSEMBLY INSTALLATION PHASE II: MISCELLANEOUS LARGE BACKFLOW INSTALLATIONS, PHASE III

PROJECT DESCRIPTION:
This project consists of the design and construction of 12 backflow prevention devices, with sizes ranging from 6- through 10-inches, located at various sites within the City of Las Vegas and Clark County. Each proposed new backflow prevention assembly will be installed within an aboveground enclosure situated on a concrete pad.

ESTIMATED PROJECT COST $470,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 08/17/2011

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1350 is titled Miscellaneous Large Backflow Installations, Phase III, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

138

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER M0155 (1) MCP NUMBER 08-12

PROJECT TITLE: BACKFLOW ASSEMBLY INSTALLATION PHASE II: MISCELLANEOUS BACKFLOW INSTALLATIONS, 2008-2009, PHASE XII

PROJECT DESCRIPTION:
This project consists of the design and installation of approximately 400 either 1-inch, 1-1/2-inch, or 2-inch diameter backflow prevention assemblies at various locations.

ESTIMATED PROJECT COST $544,888.00 AWARD OF CONTRACT AMOUNT $408,618.80 CONTRACT ACCEPTANCE DATE 08/30/2010 DATE 07/22/2009 DESIGN COST

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 09/15/2009 05/20/2010 CONSTRUCTION COST $422,459.80 LAND ACQUISITION COST

BEGIN DESIGN (2) 01/14/2008

COMPLETE DESIGN 11/08/2008 CHANGE ORDERS

RECEIPT OF BIDS 07/02/2009

TOTAL NUMBER 3 IN-HOUSE COST $122,428.52

TOTAL AMOUNT $13,841.00

DAYS EXTENDED

TOTAL PROJECT COST $544,888.32

NOTES: (1) Contract No. M0155 is titled Miscellaneous Backflow Installations, 2008-2009, Phase XII, by the LVVWD Maintenance Engineering Division. (2) Designed by the LVVWD Maintenance Engineering Division.

Construction Summary Report

139

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER M0160 MCP NUMBER 08-12

PROJECT TITLE: BACKFLOW ASSEMBLY INSTALLATION PHASE II: MISCELLANEOUS BACKFLOW INSTALLATIONS, 2012-2013, PHASE XV

PROJECT DESCRIPTION:
This project consists of the design and installation of approximately 640 either 1-inch, 1-1/2-inch, or 2-inch diameter backflow prevention assemblies at various locations.

ESTIMATED PROJECT COST $500,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change.

Construction Summary Report

140

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER M0161 MCP NUMBER 08-12

PROJECT TITLE: BACKFLOW ASSEMBLY INSTALLATION PHASE II: MISCELLANEOUS BACKFLOW INSTALLATIONS, 2011-2012, PHASE XVI

PROJECT DESCRIPTION:
This project consists of the design and installation of approximately 440 either 1-inch, 1-1/2-inch, or 2-inch diameter backflow prevention assemblies at various locations.

ESTIMATED PROJECT COST $500,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change.

Construction Summary Report

141

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: NECESSARY SITE IMPROVEMENTS, PHASE II CONTRACT NUMBER (2) MCP NUMBER 08-13

PROJECT DESCRIPTION:
This project consists of the design and construction of safety, security, and efficiency enhancements at various District facility sites.

ESTIMATED PROJECT COST $301,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

142

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Completed CONTRACT NUMBER 1194 (1) MCP NUMBER 08-13

PROJECT TITLE: NECESSARY SITE IMPROVEMENTS, PHASE II: MISCELLANEOUS SITE IMPROVEMENTS, FY 2005/2006, PHASE I

PROJECT DESCRIPTION:
This project consists of miscellaneous site improvements located at Well No. 119, Well No. 97, Tropical Well Nos. 74 and 75, West Central Well Field, Richard J. Ronzone Reservoir, Thomas R. Rice Reservoir, and Harvey E. Luce Reservoir. The improvements at the Well No. 119 site consist of replacing the perimeter chain link fence with a masonry block wall and construction of a new tubular steel access gate and fence. Improvements at the Well No. 97 site consist of replacing the perimeter chain link fence with a masonry block wall. Improvements at the Tropical Well Nos. 74 and 75 sites consist of the installation of a new access road. The West Central Well Field work consists of miscellaneous grading of the existing site, installation of concrete valley gutter, replacement, and relocation of sections of perimeter chain link fence. Improvements at the Richard J. Ronzone Reservoir site consist of the installation of new tubular steel access gates and additional site entrance. Improvements at the Thomas R. Rice Reservoir site consist of the replacement and relocation of sections of perimeter chain link fence, and the installation of tubular steel fence. Improvements at Harvey E. Luce Reservoir site consist of the installation of a new tubular steel fence.

ESTIMATED PROJECT COST $636,110.00 AWARD OF CONTRACT AMOUNT $275,980.00 CONTRACT ACCEPTANCE DATE 09/14/2010 DATE 09/10/2009 DESIGN COST $126,903.20

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION 10/12/2009 03/08/2010 CONSTRUCTION COST $288,890.00 LAND ACQUISITION COST

BEGIN DESIGN (2) 02/01/2006

COMPLETE DESIGN 05/08/2009 CHANGE ORDERS

RECEIPT OF BIDS 06/18/2009

TOTAL NUMBER 3 IN-HOUSE COST $220,316.40

TOTAL AMOUNT $12,910.00

DAYS EXTENDED 35

TOTAL PROJECT COST $636,109.60

NOTES: (1) Contract No. 1194 is titled Miscellaneous Site Improvements, FY 2005/2006, Phase I, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

143

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1260 (1) MCP NUMBER 08-13

PROJECT TITLE: NECESSARY SITE IMPROVEMENTS, PHASE II: NECESSARY SITE IMPROVEMENTS, ANGEL PARK DISINFECTION SYSTEM ADDITION

PROJECT DESCRIPTION:
This project consists of the upgrades to the existing Angel Park 2860 Zone Reservoir and 2975 Zone Pumping Station site. The project consists of four (4) components: 1) addition of a new masonry building to house a sodium hypochlorite disinfection system, electrical equipment and air compressor; 2) addition of an automatic surge tank control system; 3) replacing the existing chain link fence on the north, east, and west project site boundaries with a tubular steel fence; and 4) converting the electrical service to primary metering from secondary metering.

ESTIMATED PROJECT COST $2,198,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 07/02/2007

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1260 is titled Necessary Site Improvements, Angel Park Disinfection System Addition, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

144

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1261 (1) MCP NUMBER 08-13

PROJECT TITLE: NECESSARY SITE IMPROVEMENTS, PHASE II: NECESSARY SITE IMPROVEMENTS, PICO, STEWART, WASHINGTON, AND 3205 ZONE NORTH INTERIM PERIMETER FENCING PROJECT DESCRIPTION:
This project consists of the design and construction of permanent fencing at Stewart 1985 Zone Reservoir, Pico 2300 Zone Reservoir, Washington 1985 Zone Tank, and the 3205 Zone Interim Tank.

ESTIMATED PROJECT COST $2,753,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 10/8/2007

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1261 is titled Necessary Site Improvements, Pico, Stewart, Washington, And 3205 Zone North Interim Perimeter Fencing, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

145

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1295 (1) MCP NUMBER 08-13

PROJECT TITLE: NECESSARY SITE IMPROVEMENTS, PHASE II: NECESSARY SITE IMPROVEMENTS, WELL PERIMETER FENCING, PHASE I

PROJECT DESCRIPTION:
This project consists of the design and construction of perimeter fencing with tube steel fences at the following well sites: 1A, 17, 24, 26, 27, 52 (Smoke Ranch Pumping Station), and 88. Approximately 2,000 LF of eight (8) foot tall tube steel fence will be installed.

ESTIMATED PROJECT COST $308,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1295 is titled Necessary Site Improvements, Well Perimeter Fencing, Phase I, by the LVVWD Design Division. (2) Designed by the LVVWD Design Division.

Construction Summary Report

146

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1296 (1) MCP NUMBER 08-13

PROJECT TITLE: NECESSARY SITE IMPROVEMENTS, PHASE II: NECESSARY SITE IMPROVEMENTS, LVSP PERIMETER FENCING, PHASE II

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 4,800 LF of eight (8) foot tall tube steel fencing along the eastern border of the Las Vegas Springs Preserve (LVSP). This new fencing will replace the existing chain link fence.

ESTIMATED PROJECT COST $719,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1296 is titled Necessary Site Improvements, LVSP Perimeter Fencing, Phase II, by the LVVWD Design Division.

Construction Summary Report

147

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1292 MCP NUMBER 08-15

PROJECT TITLE: CAMPBELL 1985 AND 2168 ZONE PUMPING STATION IMPROVEMENTS

PROJECT DESCRIPTION:
This project consists of the design and conversion of 12 existing pumping units from natural gas power to electric power, upgrade of the electrical power service, reconfiguration of the pumping units and necessary piping, and telemetry and control improvements.

ESTIMATED PROJECT COST $12,600,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE NOTES:

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

Construction Summary Report

148

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: ASSET MANAGEMENT PILOT PROJECT CONTRACT NUMBER (2) MCP NUMBER 08-16

PROJECT DESCRIPTION:
This project consists of the assessment of different rehabilitation and condition assessment technologies available for small diameter (8-inch and less) asbestos cement pipelines (ACP).

ESTIMATED PROJECT COST $500,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

149

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 08-17

PROJECT TITLE: POLYETHYLENE SERVICE REPLACEMENTS PHASE II

PROJECT DESCRIPTION:
This project consists of the replacement of polyethylene service laterals in the distribution system.

ESTIMATED PROJECT COST $3,300,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

150

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) CONTRACT NUMBER (2) MCP NUMBER 10-01

PROJECT TITLE: STEEL PIPELINE REHABILITATION AND REPLACEMENT

PROJECT DESCRIPTION:
This project consists of the design, the rehabilitation, and the replacement of aging and deteriorating steel pipelines in the distribution system.

ESTIMATED PROJECT COST $2,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

151

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending CONTRACT NUMBER 1357 (1) MCP NUMBER 10-01

PROJECT TITLE: STEEL PIPELINE REHABILITATION AND REPLACEMENT: LAMB BLVD. 1985 ZONE PIPELINE REHABILITATION PHASE I - WYOMING TO VEGAS VALLEY

PROJECT DESCRIPTION:
This project consists of the design and construction of approximately 4,500 linear feet of 30-inch diameter fusible polyvinyl chloride (PVC) pipeline within an existing 48-inch diameter mortar lined and coated steel pipeline (MLCP) located within the dedicated right-of-way of Lamb Boulevard, between Vegas Valley Drive and Wyoming Avenue.

ESTIMATED PROJECT COST $1,660,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1357 is titled Lamb Blvd. 1985 Zone Pipeline Rehabilitation Phase I - Wyoming To Vegas Valley, by the LVVWD Design Division. (2) Designed by the LVVWD Design Division.

Construction Summary Report

152

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1339 (1) MCP NUMBER 10-01

PROJECT TITLE: STEEL PIPELINE REHABILITATION AND REPLACEMENT: STEEL PIPELINE REHABILITATION AND REPLACEMENT, PHASE I

PROJECT DESCRIPTION:
This project consists of the design, the rehabilitation, and the replacement of aging and deteriorating steel pipelines in the distribution system.

ESTIMATED PROJECT COST $1,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 08/22/2011

COMPLETE DESIGN 04/26/2012 CHANGE ORDERS

RECEIPT OF BIDS 06/19/2012

TOTAL NUMBER

TOTAL AMOUNT

DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1339 is titled Steel Pipeline Rehabilitation And Replacement, Phase I, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

153

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Pending (1) PROJECT TITLE: ASBESTOS CEMENT PIPELINE REPLACEMENT CONTRACT NUMBER (2) MCP NUMBER 10-02

PROJECT DESCRIPTION:
This project consists of the replacement of asbestos cement pipelines in the distribution system.

ESTIMATED PROJECT COST $2,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) This project as described above is pending and is conceptual in nature; therefore, all parameters are subject to change. (2) Contract number not assigned.

Construction Summary Report

154

LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM


PROJECT STATUS Under Design CONTRACT NUMBER 1340 (1) MCP NUMBER 10-02

PROJECT TITLE: ASBESTOS CEMENT PIPELINE REPLACEMENT: LARGE DIAMETER ASBESTOS CEMENT PIPE REPLACEMENT/REHABILITATION, PHASE I

PROJECT DESCRIPTION:
This project consists of the rehabilitation of approximately 3,100 linear feet of 16-inch diameter asbestos cement pipe (ACP) with cured-in-place pipe (CIPP).

ESTIMATED PROJECT COST $1,000,000.00 AWARD OF CONTRACT AMOUNT DATE

LAND OR RIGHT-OFWAY STATUS Existing NOTICE TO PROCEED DATE OF DATE OF ISSUE COMPLETION

BEGIN DESIGN (2) 03/31/2012

COMPLETE DESIGN

RECEIPT OF BIDS

CHANGE ORDERS TOTAL NUMBER TOTAL AMOUNT DAYS EXTENDED

CONTRACT ACCEPTANCE DATE

DESIGN COST

CONSTRUCTION COST

LAND ACQUISITION COST

IN-HOUSE COST

TOTAL PROJECT COST

NOTES: (1) Contract No. 1340 is titled Large Diameter Asbestos Cement Pipe Replacement/Rehabilitation, Phase I, by the LVVWD Design Division. (2) Designed by LVVWD Design Division.

Construction Summary Report

155

TABLE IV LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM WELL LOCATIONS
WELL NO.
038A 088 091 098 110 112 AR-004 AR-005 AR-006 AR-007 AR-008 AR-009 AR-010 AR-074A AR-093 AR-094 AR-095 AR-098 AR-100 AR-108 AR-109 AR-111 AR-113 AR-118 AR-119 AR-120 AR-121 124 125 126 127 128

CONT. NO.
(a) 694 788 790 790 792 4-58 4-68 4-68 4-68 4-68

MCP NO.
01-02 6612 West Brandywine Road. Located in the Well No. 88 compound, intersection of Tenaya Way and Peak Drive. Located on the northwest corner of the intersection of Tee Pee Lane and Alexander Road. Located on the south side of Craig Road, east of El Capitan Way. Located on the south side of Alexander Road, east of El Capitan Way. Located at the intersection of Helena Avenue and Juliano Road.

LOCATION

706/674 4-58/4-58 706/674 4-58/4-58 707/675 4-58/4-58 707/675 4-58/4-58 707/675 4-58/4-58 707/675 4-58/4-58 675/694 4-58/4-58 711/(a) 4-58/4-58 873/855 4-68/95-23 873/817 4-68/95-23 873/817 4-68/95-23 712/783 4-58/4-68 846 95-23 712/783 4-58/4-68 783/712 4-68/4-58 711/783 4-58/4-68 873/712 4-68/4-58 926/856 96-18/96-18 856/926 96-18/96-18 927/857 96-18/96-18 857/927 96-18/96-18 1303 1303 1303 1304 1304 08-07 08-07 08-07 08-07 08-07

Spring Mountain/Durango Reservoir and Pumping Station, located at the southeast corner of the reservoir. Spring Mountain and Durango Reservoir. Well plugged in 1997. The well was located at the northeast side of the reservoir where the current pumping station building is located. Underhill Reservoir, southwest corner near Charleston Boulevard. Underhill Reservoir, northeast side of compound near Buffalo Drive. West Central Well Field - Tank and Pumping Station. The well is located in the northwest corner of compound (near Well No. 70). West Central Well Field - Tank and Pumping Station. The well is located on the east side of the compound, near the center of the block wall. Located in the Well No. 88 compound, intersection of Tenaya Way and Peak Drive. Southern well at the Well No. 74 compound. Well located in the southeast side of the Well No. 93 compound. Well located in the west side of the Well No. 94 compound. Well located at Fort Apache Reservoir, southeast corner of the compound. Well No. 95 on the northeast side of the compound. Well located in the southern half of the Well No. 98 compound. Between Durango Drive and Soaring Gulls Drive, north of Cheyenne Avenue. Northern well on compound. Southern well on compound. Is old Well No. 108, converted to recharge Well AR-109. 7850 West Oakey Boulevard. Well at south end of the Well No. 113 compound. NW Water Resource Center, intersection of Cheyenne Avenue and Durango Drive. NW Water Resource Center, intersection of Cheyenne Avenue and Durango Drive. NW Water Resource Center, intersection of Cheyenne Avenue and Durango Drive. NW Water Resource Center, intersection of Cheyenne Avenue and Durango Drive. Located at the Luce 2420 Zone Reservoir site, at the intersection of Buffalo Drive and Smoke Ranch Road. Located at the Ronzone 2300 Zone Reservoir site, at the intersection of Torrey Pines Drive and Lake Mead Boulevard. Located at the Well No. 116 site, approximately 450 LF west of the intersection of Rainbow Boulevard and Peak Drive. Located approximately 500 LF north of the intersection of Buffalo Drive and Peak Drive. Located approximately 850 LF west of the intersection of Tenaya Way and Peak Drive.

Construction Status Report

156

TABLE V LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM PROJECT SCHEDULES FOR RESERVOIRS, PUMPING STATIONS, PIPELINES AND MISCELLANEOUS PROJECT

Construction Status Report


PROJECT TITLE CONSULTANT CONCEPTUAL CRITERIA ISSUE DATE BEGIN DESIGN AWARD DATE NOTICE TO PROCEED DATE OF COMPLETION RECEIPT OF BIDS CHANGE ORDERS DAYS ADDED 01/31/2006 11/15/2006 G. C. Wallace, Inc. 03/08/2007 Black & Veatch Engineers 04/04/2006 04/15/2008 05/20/2008 06/24/2008 05/24/2010 13 60 03/31/2007 03/30/2007 12/29/2006 RBF Consulting Engineering 08/09/2007 Black & Veatch Engineers 06/19/2008 Black & Veatch Engineers 12/21/2010 01/31/2006 11/15/2006 06/01/2006 CH2M Hill G. C. Wallace, Inc. Black & Veatch Engineers 04/04/2006 03/08/2007 02/26/2007 04/15/2008 05/20/2008 06/24/2008 05/24/2010 13 60 05/31/2008 LVVWD Design Division 06/24/2005 G. C. Wallace, Inc. 08/03/2005 05/16/2007 07/03/2007 08/06/2007 07/30/2008 03/30/2007 Black & Veatch Engineers. 06/19/2008 08/31/2008 05/06/2008 10/10/2011 05/15/2012 08/22/2011 04/30/2012 12/21/2010 LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division 09/15/2008 09/18/2008 10/12/2011 05/15/2012 08/22/2011 04/30/2012 04/21/2011 03/25/2009 02/19/2009 06/02/2009 04/07/2009 07/01/2009 04/29/2009 06/26/2010 10/26/2010 7 3 31 138

MCP NO.

CONT NO.

ACCEPTANCE DATE

Reservoirs

97-10

(a)

3665 Zone Reservoir 07/06/2010

03-10

1212

Sloan 2745 Zone Reservoir

04-04

1150

Cactus 2538 Zone Reservoir

04-08

1232

Centennial 2635 Zone Reservoir

04-10

1213

Log Cabin 3205 Zone Reservoir

04-12

(a)

Leonard R. Fayle Water Facility Improvements

04-12

1206

Leonard R. Fayle Water Facility Improvements: Fayle Water Facility Improvements

04-12

1257

Leonard R. Fayle Water Facility Improvements: Fayle 2168 Zone Satellite Reservoir

04-17

(a)

Sunrise Mountain 2150 Zone Reservoir

05-10

1244

Frias 2635 Zone Reservoir

05-15

(a)

Rome 2745 Zone Reservoir

05-19

(a)

Dorrell 2860 Zone Reservoir

06-01

(a)

Cougar 3090 Zone Reservoir

06-15

1312

Summit 3205 Zone South Tanks

08-01

(a)

Richmar 2860 Zone Reservoir

Pumping Stations 07/06/2010

04-03

(a)

Stewart 2150 Zone Pumping Station Improvements

04-06

1150

Cactus 2635 Zone Pumping Station

04-09

1232

Centennial 2745 Zone Pumping Station

05-09

1196

Luce 2635 Zone Pumping Station Improvements

05-11

1244

Frias 2745 Zone Pumping Station

05-17

(a)

Rome 2860 Zone Pumping Station

05-21

(a)

Dorrell 2975 Zone Pumping Station

06-10

(a)

Sunrise Mountain 2380 Zone Pumping Station

06-11

(a)

Rome 2975 Zone Pumping Station

06-14

1212

Sloan 3205 Zone South Pumping Station

08-03

(a)

Richmar 2975 Zone Pumping Station

08-15

1292

Campbell 1985 and 2168 Zone Pumping Station Improvements

Pipelines

97-11

(a)

3665 Zone Reservoir Inlet/Outlet Pipeline 09/02/2008

99-04

(a)

Jean Transmission System

03-09

1185

Bermuda 2745 Zone Pumping Station Discharge Pipeline

03-09

1242

Bermuda 2745 Zone Pumping Station Discharge Pipeline Phase II

04-11

(a)

Log Cabin 3205 Zone Reservoir Inlet/Outlet Pipeline

04-12

1258

Leonard R. Fayle Water Facility Improvements: Fayle 2168 Zone Satellite Reservoir Inlet/Outlet Pipeline

04-18

(a)

Sunrise Mountain 2150 Zone Reservoir Inlet/Outlet Pipeline

04-19

(a)

Bonanza 2150 Zone Pipeline

04-20

(a)

Washington 2150 Zone Pumping Station Discharge Pipeline

05-16

(a)

Rome 2745 Zone Reservoir Inlet/Outlet Pipeline

05-18

(a)

Rome 2860 Zone Pumping Station Discharge Pipeline

05-20

(a)

Dorrell 2860 Zone Reservoir Inlet/Outlet Pipeline

05-22

(a)

Dorrell 2975 Zone Pumping Station Discharge Pipeline

06-02

(a)

Cougar 3090 Zone Reservoir Inlet/Outlet Pipeline

06-12

(a)

Rome 2975 Zone Pumping Station Discharge Pipeline

08-02

(a)

Richmar 2860 Zone Reservoir Inlet/Outlet Pipeline

08-04

(a)

Richmar 2975 Zone Pumping Station Discharge Pipeline 11/03/2010 03/01/2011

08-06

(a)

Necessary System Improvements, Phase VIII: Rampart/Alta Pipeline Relocation, Phase II

08-06

1306

Necessary System Improvements, Phase VIII: Miscellaneous Main Extensions and Water Service Installations, Phase VII

08-06

1307

Necessary System Improvements, Phase VIII: Rampart/Alta Pipeline Relocation, Phase I

08-06

1354

Necessary System Improvements, Phase VIII: Oakey/I-15 Pipeline Relocation

08-06

1358

Necessary System Improvements, Phase VIII: Necessary System Improvements, Railroad Pass Pipeline Relocation

10-01

(a)

Steel Pipeline Rehabilitation and Replacement

10-01

1339

Steel Pipeline Rehabilitation and Replacement: Steel Pipeline Rehabilitation and Replacement, Phase I

10-01

1357

Steel Pipeline Rehabilitation and Replacement: Lamb Blvd. 1985 Zone Pipeline Rehabilitation Phase I - Wyoming to Vegas Valley

10-02

(a)

Asbestos Cement Pipeline Replacement

10-02

1340

Asbestos Cement Pipeline Replacement: Large Diameter Asbestos Cement Pipe Replacement/Rehabilitation, Phase I

157

MCP NO. PROJECT TITLE CONSULTANT

CONT NO.

CONCEPTUAL CRITERIA ISSUE DATE BEGIN DESIGN AWARD DATE NOTICE TO PROCEED DATE OF COMPLETION CHANGE ORDERS RECEIPT OF BIDS DAYS ADDED

ACCEPTANCE DATE

Miscellaneous

4-17

(a)

Water Resource Research and Development

4-53

(a)

Acquire Sites for Future Wells

4-57

(a)

SCADA System Expansion and Upgrade

Construction Status Report


08/14/2000 02/23/2001 11/09/2000 Poggemeyer Design Group 01/29/2007 Poggemeyer Design Group 11/09/2000 03/14/2002 04/02/2002 05/13/2002 Natural Systems, Inc. 02/23/2001 10/31/2002 11/19/2002 03/08/2003 LVVWD Design Division 08/14/2000 02/06/2001 03/06/2001 04/02/2001 05/14/2001 12/20/2003 09/01/2003 1 2 13 0 167 402 05/31/2005 08/19/2005 07/26/2005 08/13/2007 LVVWD Design Division 08/13/2007 Wright Engineers 05/31/2005 02/05/2008 06/05/2008 IDACOMM, Inc. 07/21/2005 01/18/2005 Westin Engineering, Inc. 05/31/2005 01/18/2005 03/18/2008 07/01/2008 01/18/2005 05/12/2008 07/28/2008 12/31/2005 01/14/2009 06/01/2009 7 2 18 0 01/11/2010 01/11/2010 10/27/2008 LVVWD Design Division LVVWD Design Division LVVWD Design Division 02/28/2010 02/28/2010 10/27/2008 11/09/2010 11/09/2010 12/28/2010 12/28/2010 02/03/2011 02/03/2011 08/02/2011 08/02/2011 1 1 0 0 11/30/2009 11/30/2009 10/18/2005 10/18/2005 02/28/2007 07/31/2007 07/25/2008 LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division 10/18/2005 10/18/2005 10/06/2006 08/01/2007 08/11/2008 05/28/2008 05/08/2007 04/08/2008 11/28/2007 02/01/2011 06/17/2008 05/24/2007 04/29/2008 01/02/2008 02/21/2011 08/06/2008 06/18/2007 05/28/2008 02/04/2008 04/05/2011 03/08/2009 11/30/2007 03/06/2009 01/29/2009 11/10/2011 4 1 4 5 3 34 0 58 95 13 08/31/2005 12/01/2005 12/01/2005 03/01/2007 03/14/2006 08/15/2007 08/31/2008 01/01/2009 Purvis Architects Wright Engineers Wright Engineers LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division Domingo Cambeiro Corp. 08/31/2005 12/15/2005 12/15/2006 03/01/2007 02/17/2006 08/20/2007 08/11/2008 12/12/2007 02/13/2007 08/05/2008 03/06/2007 08/22/2008 04/30/2007 09/24/2008 10/02/2007 12/26/2008 2 1 0 0 09/13/2005 06/12/2007 12/15/2005 07/17/2007 02/06/2006 08/06/2007 01/13/2007 12/29/2007 10 2 170 11 06/05/2006 06/05/2006 06/05/2006 02/21/2007 02/21/2007 08/31/2007 02/29/2008 02/29/2008 LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division 05/11/2006 05/11/2006 05/11/2006 02/21/2007 02/21/2007 11/01/2007 02/29/2008 02/27/2008 05/19/2011 06/13/2011 07/05/2011 01/31/2012 2 51 10/25/2007 08/22/2007 01/15/2008 11/13/2008 06/04/2008 11/14/2007 09/18/2007 02/26/2008 01/05/2009 06/24/2008 11/15/2010 01/02/2008 10/17/2007 04/15/2008 03/02/2009 07/28/2008 12/30/2010 06/16/2008 08/06/2008 01/14/2009 05/27/2010 09/21/2009 08/27/2011 1 3 4 8 6 1 0 0 22 92 120 0

97-01

(a)

Reservoir Site Acquisitions Phase I Cancelled 09/18/2001 03/02/2004 07/05/2005

00-02

(a)

North Well Field/Las Vegas Springs Preserve Infrastructure

00-02

(a)

North Well Field/Las Vegas Springs Preserve Infrastructure: Charleston Heights Site Remediation

00-02

1015

North Well Field/Las Vegas Springs Preserve Infrastructure: North Well Field Site Clean Up

00-02

1020

North Well Field/Las Vegas Springs Preserve Infrastructure: Las Vegas Springs Preserve Cienega

00-02

1024

North Well Field/Las Vegas Springs Preserve Infrastructure: Las Vegas Springs Preserve Site Infrastructure

00-02

1245

North Well Field/Las Vegas Springs Preserve Infrastructure: Las Vegas Springs Preserve Trail Extension and Realignment

00-03

(a)

North Well Field Archeological and Historical Stabilization

00-04

(a)

North Well Field Environmental Stabilization

02-05

(a)

Reservoir Site Acquisition

02-06

(a)

Purchase of Groundwater Rights in the Las Vegas Valley

03-12

(a)

Security System Upgrades 08/05/2008 06/02/2009 11/03/2009

03-12

1169

Security System Upgrades: Communication Network Upgrade, Phase II

03-12

1177

Security System Upgrades: Security Telecommunications Network Infrastructure

03-12

1254

Security System Upgrades: Communication Network Upgrade, Phase I

03-12

1263

Security System Upgrades: Communication Network Upgrade, Phase III

03-14

(a)

System Communication Network Improvements

04-02

(a)

Sunrise Mountain 2150 Zone Reservoir Site Acquisition

04-04

1323

Cactus 2538 Zone Reservoir On-Site Improvements

04-06

1323

Cactus 2538 Zone Reservoir On-Site Improvements

04-15

1182

Pressure Monitoring Stations

04-24

(a)

PRV Metering Improvements

05-05

(a)

Site Security Sensor Installation

05-06

(a)

Security Surveillance Center

05-10

1309

Frias 2635 Zone Reservoir: Frias 2635 Zone Reservoir Off-Site Power Service

05-11

1309

Frias 2635 Zone Reservoir: Frias 2635 Zone Reservoir Off-Site Power Service

05-14

(a)

Necessary Site Acquisitions

05-23

(a)

Necessary System Improvements, Phase VII

05-23

(a)

Necessary System Improvements, Phase VII: Flamingo Road and Nellis Boulevard 07/02/2009 12/18/2007 06/10/2009 08/04/2009 01/17/2012

05-23

(a)

Necessary System Improvements, Phase VII: Small Diameter Pipeline Installations, Phase II

05-23

1214

Necessary System Improvements, Phase VII: Necessary System Improvements, Phase VII, Flamingo/Paradise Pressure Reducing Valve

05-23

1216

Necessary System Improvements, Phase VII: Necessary System Improvements, Phase VIII, Levi Avenue Pressure Reducing Valve

05-23

1235

Necessary System Improvements, Phase VII: Necessary System Improvements, Phase VII, Campbell Mason Valve Replacement

05-23

1267

Necessary System Improvements, Phase VII: Miscellaneous Main Extensions and Water Service Installations, Phase VI

05-23

1301

Necessary System Improvements, Phase VII: Necessary System Improvements, Phase VII, Small Diameter Pipeline Installations

05-24

(a)

LVVWD Campus Infrastructure

05-24

(a)

LVVWD Campus Infrastructure: LVVWD Campus Warehouse Facility 03/20/2007 02/19/2008

05-24

(a)

LVVWD Campus Infrastructure: Information Systems Facility

05-24

1178

LVVWD Campus Infrastructure: Modifications to Operations Building

05-24

1202

LVVWD Campus Infrastructure: LVVWD Campus Improvements Phase I

05-24

1251

LVVWD Campus Infrastructure: LVVWD Campus Improvements Phase II

05-25

(a)

Chemical Storage Facility

06-04

1236

LVVWD Modular Office Facilities: LVVWD Campus Off-Site Sewer Improvements

06-06

(a)

Polyethylene Service Replacements Phase I 11/20/2007 05/14/2009

06-06

1207

Polyethylene Service Replacements Phase I: Polyethylene Service Replacement, The Grove and Woodcroft

06-06

1268

Polyethylene Service Replacements Phase I: Polyethylene Service Replacement, Spring Valley and Laurel Park

06-06

1302

Polyethylene Service Replacements Phase I: Polyethylene Service Replacement, Charleston Rainbow and Charleston Heights

06-07

(a)

Chemical Storage Facility Phase II

06-07

1273

Chemical Storage Facility Phase II: Tropical Satellite Facility Campus

06-08

(a)

Electrical Equipment Improvements 10/07/2008 09/02/2008 05/14/2009 08/03/2010 06/10/2010 08/17/2011 06/25/2012

06-09

(a)

Miscellaneous Vaults, Reconstruction And Repair Phase III

06-09

1209

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XI

06-09

1210

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XII

06-09

1211

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XIII

06-09

1249

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XIV

06-09

1250

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XV

06-09

1266

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XVI

06-09

1282

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XVII

06-09

1283

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XVIII

158

MCP NO. PROJECT TITLE CONSULTANT LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division 07/22/2010 02/14/2012 04/03/2012 05/30/2012 05/25/2013 07/22/2010 1 07/15/2008 05/08/2009 07/07/2009 07/16/2009 07/08/2010 7 02/28/2008 06/24/2010 09/02/2010 11/01/2010 05/20/2011 90 07/17/2008 08/31/2008 01/31/2008 07/25/2008 06/13/2010 05/13/2010

CONT NO.

CONCEPTUAL CRITERIA ISSUE DATE BEGIN DESIGN AWARD DATE NOTICE TO PROCEED DATE OF COMPLETION CHANGE ORDERS RECEIPT OF BIDS DAYS ADDED

ACCEPTANCE DATE

06-09

1294

Miscellaneous Vaults, Reconstruction And Repair Phase III: Miscellaneous Vaults, Reconstruction And Repair, Phase XIX

06-13

1280

Cheyenne 2975 Zone Motor Operated Valve

08-05

(a)

Trihalomethanes Treatment Project 12/7/2010

08-05

1293

Trihalomethanes Treatment Project: Trihalomethanes Treatment Project, Phase I - Alta 3205 Zone Reservoir

Construction Status Report


10/18/2010 12/27/2011 04/24/2010 12/01/2009 06/30/2011 03/28/2010 11/01/2010 06/30/2010 08/17/2011 02/01/0009 Maintenance Engineering 03/05/2009 LVVWD Design Division 08/17/2011 07/02/2009 07/22/2009 09/15/2009 05/20/2010 3 0 LVVWD Design Division 06/29/2010 LVVWD Design Division 09/08/2011 10/25/2011 12/06/2011 10/21/2012 2 38 LVVWD Design Division 05/05/2010 04/12/2011 LVVWD Design Division 05/18/2011 06/27/2011 01/23/2012 2 0 LVVWD Design Division LVVWD Design Division 10/12/2011 06/20/2012 LVVWD Design Division 10/18/2010 02/15/2011 04/05/2011 05/03/2011 05/02/2012 5 30 11/01/2005 07/11/2007 09/04/2007 08/27/2008 08/04/2008 LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division LVVWD Design Division 02/01/2006 07/02/2007 10/08/2007 06/18/2009 09/10/2009 10/12/2009 03/08/2010 3 35

08-05

1329

Trihalomethanes Treatment Project: Trihalomethanes Treatment Project, Phase II - Elkhorn 2975 Zone Reservoir

08-05

1330

Trihalomethanes Treatment Project: Trihalomethanes Treatment Project, Phase III - Levi 2745 Zone Reservoir

08-06

(a)

Necessary System Improvements, Phase VIII

08-06

(a)

Necessary System Improvements, Phase VIII: Washington 2420 Zone Emergency Check Valve Installations

08-06

(c)

Necessary System Improvements, Phase VIII: Valley View/Maule 2300 Zone Motor Operated Valve

08-06

1338

Necessary System Improvements, Phase VIII: Miscellaneous Main Extensions and Water Service Installations, Phase VIII

08-06

1353

Necessary System Improvements, Phase VIII: Miscellaneous Main Extensions and Water Service Installations, Phase IX

08-07

1305

Production Well Capacity Addition: Well No. 126 Discharge Pipeline

08-08

1255

LVVWD Campus Warehouse Facility

08-09

(a)

Child Care Facility

08-10

1256

LVVWD Campus Information Technology Facility: Information Systems Facility

08-11

(a)

Renewable Energy Project Phase II

08-11

1341

Renewable Energy Project Phase II

08-12

(a)

Backflow Assembly Installation Phase II 03/22/12

08-12

1332

Backflow Assembly Installation Phase II: Miscellaneous Backflow Installations, Phase XIII

08-12

1333

Backflow Assembly Installation Phase II: Miscellaneous Backflow Installations, Phase XIV

08-12

1334

Backflow Assembly Installation Phase II: Miscellaneous Large Backflow Installations, Phase II

08-12

1350

Backflow Assembly Installation Phase II: Miscellaneous Large Backflow Installations, Phase III

08-12

M0155 Backflow Assembly Installation Phase II: Miscellaneous Backflow Installations, 2008-2009, Phase XII

08/30/2010

08-12

M0160 Backflow Assembly Installation Phase II: Miscellaneous Backflow Installations, 2012-2013, Phase XV

08-12

M0161 Backflow Assembly Installation Phase II: Miscellaneous Backflow Installations, 2011-2012, Phase XVI 09/14/2010

08-13

(a)

Necessary Site Improvements, Phase II

08-13

1194

Necessary Site Improvements, Phase II: Miscellaneous Site Improvements, FY 2005/2006, Phase I

08-13

1260

Necessary Site Improvements, Phase II: Necessary Site Improvements, Angel Park Disinfection System Addition

08-13

1261

Necessary Site Improvements, Phase II: Necessary Site Improvements, Pico, Stewart, Washington, and 3205 Zone North Interim Perimeter Fencing

08-13

1295

Necessary Site Improvements, Phase II: Necessary Site Improvements, Well Perimeter Fencing, Phase I

08-13

1296

Necessary Site Improvements, Phase II: Necessary Site Improvements, LVSP Perimeter Fencing, Phase II

08-16

(a)

Asset Management Pilot Project

08-17

(a)

Polyethylene Service Replacements Phase II

Note:

(a) Contract number has not been assigned.

159

TABLE VI LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM COMPLETED PROJECTS
MCP CONT. NO. NO.
3-120 3-128 515 534 (a) 543 544 549 637 686 711 3-129 (a) 571 572 578 580 683 3-130 (a) 558 Gowan Reservoir Renovation Rehabilitation of Charleston Heights 10MG Steel Reservoirs Drill and Develop Four Wells Drill and Develop Water Well Nos. 74 and 75 Drill and Develop Water Well No. 77 Drill and Develop 2635 Zone Four Well No. 76 Drill Monitor Well No. 75M Well No. 76 Blast Stimulation Project Drill and Develop Artificial Recharge Wells AR-1, AR-74A, AR-74B, and AR-111 Equip Seven Wells Equip Well Nos. 68, 72, and 73 Equip Well Nos. 74 and 75 Equip 2538 Zone Well Nos. 70 and 71 Equip Well No. 77 Equip 2635 Zone Well No. 76 Reservoir Piping and Structure Repair 2420 Zone South Reservoir Piping Modification 04/17/1990 $40,164.20 10/06/1992 07/21/1992 02/04/1992 07/07/1992 02/04/1997 $1,995,848.63 $967,878.81 $679,368.92 $451,658.53 $577,309.42 08/07/1990 06/19/1990 11/03/1992 09/01/1992 12/19/1995 06/20/1995 $553,304.87 $266,444.70 $305,909.02 $54,421.92 $430,516.20 $323,983.29

PROJECT TITLE

Acceptance Date
04/02/1989 04/15/1990

Acceptance Amount
$220,337.43 $479,348.03

Comment

4-1 4-2

513 (a) 665 745

2635 Zone Reservoir Drill and Develop 2538 Zone Wells, Phase I Drill and Develop 2538 Zone Well No. 88 Drill and Develop Production Well Nos. 86 and 92 Equip 2538 Zone Wells Phase I Equip 2538 Pressure Zone Well No. 88 Equip Well No. 92 Drill and Develop 2745 Zone Wells Drill and Develop Production Well Nos. 90, 93, and 97 Drill and Develop Production Well Nos. 102 and 105 Equip 2745 Zone Wells Equip Well Nos. 93 and 94 Equip Well Nos. 102 and 105 Drill and Develop 2420 Zone Wells, Phase I Drill and Develop 2420 Zone Well No. 89, Phase I Drill and Develop Production Wells Nos. 104 and 108 Drill and Develop Production Well Nos. 86 and 92 Equip 2420 Zone Wells, Phase I Equip Well No. 89 Equip Well Nos. 86 and 104 Phase 2 Wells Off-Site Improvements Miscellaneous Vaults, Reconstruction, and Repair Miscellaneous Vaults, Reconstruction, and Repair Phase I Miscellaneous Vaults, Reconstruction, and Repair Phase II Miscellaneous Vaults, Reconstruction, and Repair Phase III Miscellaneous Vaults, Reconstruction, and Repair Phase IV Miscellaneous Vaults, Reconstruction, and Repair Phase V Well Nos. 2A and 5A Improvements Well Nos. 2A and 5A Improvements: Well Discharge Storm Drain Ties Expand Existing Office Building Complex Construct Additional District Office Building Facility East Parking Lot Improvements Parking Facility Expansion Valley View Boulevard/Fulton Place Off-Site Improvements Well Discharge Storm Drain Ties, Phase IV Drill, Develop, and Equip 2168 Zone Well Nos. 79 and 80 Drill and Develop 2168 Zone Well Nos. 81 and 82 Equip Well Nos. 81 and 82 2538 Zone Reservoir 2538 Zone Reservoir Inlet/Outlet Pipeline 2635 Zone South Pipeline Warm Springs 2975 Zone Pumping Station Addition 2860 Zone Pumping Station Meranto 3090 Zone Pumping Station 2860 and 2745 Zone Pumping Station Discharge Pipeline Luce 2635 Zone Pumping Station Addition Drill and Develop 2300 Zone Wells Equip 2300 Zone Wells Equip Well Nos. 83 and 84 Equip Well No. 85 Equip Well No. 3A Drill and Develop 2420 Zone Wells, Phase II Drill and Develop Production Well Nos. 101 and 103 Drill and Develop Production Well Nos. 116 and 117 Equip 2420 Zone Wells, Phase II Equip Well Nos. 101 and 103 Phase 2 Wells Off-Site Improvements Equip Well Nos. 116 and 117 Drill and Develop 2635 Zone Wells, Phase I Drill and Develop 2635 Zone Wells, Phase I Drill and Develop Production Well Nos. 102 and 105 Drill and Develop Production Well Nos. 91 and 113 Equip 2635 Zone Wells, Phase I Equip 2745 Zone Well No. 87 Equip Well Nos. 102 and 105 Equip Well Nos. 91 and 113 2635 Zone Well Collector Pipeline, Phase I Cimarron Road 2538 Zone Pipeline, Phase I 3090 Zone Pumping Station Addition

12/21/1994

$7,445,375.48

08/18/1993 02/20/1996 02/20/1996 03/18/1997 05/02/1995 11/21/1995 02/06/1996 06/18/1996 08/17/1994 03/05/1995

$374,518.48 $1,140,227.02 $896,419.14 $415,659.92 $1,687,020.00 $1,133,576.94 $1,564,526.80 $1,293,669.78 $441,059.25 $882,046.82 Reported Under MCP 4-2

4-3

(a) 694 772

4-4

(a) 708 742

4-5 714 737 4-7 (a) 677 744 745 4-8 (a) 715 751 778 04-13 04-13 04-13 04-13 04-13 04-13 04-14 4-16 (a) 1116 1127 1128 1155 1159 1252 1253 (a) 631 663 682 693 1171 4-18 4-19 4-20 4-21 4-22 4-22 4-23 4-24 4-25 4-26 4-27 599 600 609 618 619 588 1173 513 1192 620 621 601 (a) 610 611 746 4-28 (a) 743 781 4-29 (a) 738 778 789 4-30 (a) 649 742 774 4-31 (a) 688 737 788 4-32 4-34 (a) 719 (a)

12/19/1995 08/06/1996 05/20/1997

$624,699.58 $1,051,310.24 $477,985.94 Cancelled

06/20/2006 11/08/2006 03/21/2006 06/06/2006 10/06/2009 01/05/2009

$520,950.62 $1,481,384.83 $434,068.60 $598,877.23 $561,479.85 $1,276,740.42

08/18/1993 10/06/1993 01/19/1994 05/16/2006 12/15/1992 02/04/1992 09/08/1993 04/02/1996 02/08/1995 02/04/1992 07/17/2007 10/06/2009 02/16/1994 04/04/1995 04/17/1992 12/15/1992 09/15/1992 05/21/1996 02/20/1996

$458,654.17 $506,686.11 $433,173.14 $226,947.06 $1,307,184.66 $567,138.90 $1,847,018.21 $10,438,243.89 $2,051,688.50 $1,653,903.29 $901,365.02 Reported Under MCP 4-1 $10,723,554.40 $856,930.65 $187,573.29 $908,826.31 $838,372.78 $417,332.15 $606,183.38 $1,268,294.82 Reported Under MCP 4-67

12/17/1996

$1,026,088.93 Reported Under MCP 4-8 Reported Under MCP 4-68

04/20/1993 10/01/1996 09/19/1995 04/15/1997 04/05/1997

$458,307.06 Reported Under MCP 4-4 $1,252,450.60 $529,835.96 Reported Under MCP 4-5 $1,228,587.20 $1,496,822.82

Construction Status Report

160

TABLE VI LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM COMPLETED PROJECTS
MCP CONT. NO. NO.
622 4-35 4-36 623 (a) 708 710 4-37 (a) 646 713 717 731 4-39 4-40 4-41 647 647 (a) 708 710 743 4-42 713 714 717 732 738 782 4-43 4-45 4-46 4-47 4-48 4-49 4-50 4-51 4-52 4-53 4-54 4-55 4-56 4-57 4-58 799 618 652 620 653 654 655 656 657 656 657 622 (a) 595 658 602 602 b (a) (a) 674 675 707 711 712 783 4-59 4-60 4-64 4-64 4-65 4-66 4-67 720 721 723 724 725 735 (a) 744 774 775 776 780 781 4-68 (a) 783 788 789 790 791 792 4-69 4-71 95-01 95-02 95-03 95-04 95-06 95-07 95-07 95-08 95-09 95-10 95-11 773 749 763 757 764 765 756 766 767 768 760 760 769 809 818 827 836 861 928 95-12 95-14 804 770 2975 Zone Reservoir and 3090 Zone Pumping Station 2975 Zone Reservoir Inlet/Outlet Pipeline Drill and Develop 2635 Zone Wells, Phase II Drill and Develop Production Well Nos. 90, 93, and 97 Drill and Develop Production Well Nos. 94, 95, and 96 Equip 2635 Zone Wells, Phase II Equip 2635 Zone Well No. 78 Equip Well No. 90 Equip Well Nos. 96 and 97 Miscellaneous Well Discharge Pipelines, Phase I Fayle 2300 Zone Pumping Station Addition Fayle 2420 Zone Pumping Station Addition Drill and Develop 2538 Zone Wells, Phase II Drill and Develop Production Wells Nos. 90, 93, and 97 Drill and Develop Production Well Nos. 94, 95, and 96 Drill and Develop Production Well Nos. 101 and 103 Equip 2538 Zone Wells, Phase II Equip Well No. 90 Equip Well Nos. 93 and 94 Equip Well Nos. 96 and 97 Miscellaneous Well Discharge Pipelines, Phase II Equip Well Nos. 101 and 103 Well No. 95 Modifications Miscellaneous Well Discharge Pipelines, Phase III 2635 Zone Pumping Station at the 2538 Zone Reservoir 2975 Zone Pumping Station at the 2635 Zone Reservoir 2860 and 2745 Zone Pumping Station Discharge Pipeline Campbell Reservoir Outlet Pipeline 2300 Zone Reservoir 2300 Zone South Reservoir Inlet/Outlet Pipeline 2300 Zone South Pipeline, Phase II 2420 and 2300 Zone South Pipelines, Phase II 2420 Zone South Pipeline, Phase II 2420 and 2300 Zone South Pipelines, Phase II 3090 Zone Pumping Station Acquire Site for Future Wells 2300 Zone South Pipeline, Phase III 2420 Zone South Pipeline, Phase III 2168 Zone South Pipeline 2168 Zone South Pipeline SCADA System Expansion and Upgrade Artificial Recharge Wells Drill and Develop Artificial Recharge Wells AR-2, AR-3, AR-4, and AR-5 Drill and Develop Artificial Recharge Wells AR-6, AR7, AR-8 , AR-9, and AR-10 Equip Artificial Recharge Wells AR-6, AR-7, AR-8 , and AR-9 Drill and Develop Artificial Recharge Wells AR-1, AR-74A, AR-74B, and AR-111 Drill and Develop Artificial Recharge Wells AR-98, AR-108, AR-113 Equip Artificial Recharge Wells AR-1, AR-98, AR-108, AR-109, and AR-111 3090 Zone Reservoir 3090 Zone Reservoir Inlet/Outlet Pipeline Ronzone 2420 Zone Pumping Station Ronzone 2420 Zone Pumping Station and Discharge Pipeline 3090 Zone Pumping Station Addition Luce 2538 Zone Pumping Station Drill and Develop Nine Additional Wells Drill and Develop Production Well Nos. 104 and 108 Drill and Develop Production Well Nos. 91 and 113 Drill and Develop Production Well Nos. 98 and 110 Drill and Develop Production Well No. 112 Drill and Develop Production Well Nos. 114 and 115 Drill and Develop Production Well Nos. 116 and 117 Equip Nine Additional Wells Equip Artificial Recharge Wells AR-1, AR-98, AR-108, AR-109, and AR-111 Equip Well Nos. 91 and 113 Equip Well Nos. 116 and 117 Equip Well Nos. 98 and 110 Equip Well Nos. 114 and 115 Equip Well No. 112 1930 Pressure Zone Improvements 3090 Zone Pumping Station Addition, Phase II Cimarron Road 2538 Zone North Pipeline Carlton Square 2538 Zone Pumping Station and Forebay Carlton Square 2538 Zone Pumping Station and Forebay Cimarron Road 2745 Zone South Pipeline 2538 Zone South Pumping Station at the 2420 Zone South Reservoir 2420 Zone South Reservoir Outlet Pipeline 2538 Zone South Pumping Station Discharge Pipeline 2538 Zone South Reservoir Inlet/Outlet Pipeline 2538 Zone South Reservoir and 2635 Zone South Pumping Station 2538 Zone South Reservoir and 2635 Zone South Pumping Station 2635 Zone South Pumping Station Discharge Pipeline Spring Mountain-Durango 2860 Zone Pumping Station Modification and Interim 2745 Zone Pumping Station Power Service to Spring Mountain-Durango 2745, 2860, and 2975 Zone Pumping Stations, Phase I Spring Mountain-Durango Reservoir and Pumping Station Expansion Perimeter Block Wall Power Service to Spring Mountain-Durango 2745, 2860, and 2975 Zone Pumping Stations, Phase II Spring Mountain-Durango Reservoir and Pumping Station Expansion Perimeter Landscaping Spring Mountain-Durango Reservoir On-Site Landscaping Spring Mountain-Durango Reservoir Expansion and Spring Mountain-Durango 2745, 2860, and 2975 Zone Pumping Stations 3205 Zone Reservoir Inlet/Outlet Pipeline 10/20/1998 04/15/1997 04/01/1997 06/17/1997 08/05/1997 04/01/1997 12/02/1997 03/04/1997 03/04/1997 02/03/1998 05/05/1998 07/01/1997 08/21/1997 06/17/1997 07/01/1997 08/05/1997 11/18/1997 02/17/1998 05/20/1997 07/15/1997 02/18/1997 02/03/1998 11/18/1997 04/06/1999 10/06/1998 08/19/1997 $886,756.88 $1,228,356.91 $1,249,532.17 $1,346,640.41 $1,160,472.38 $528,191.05 $1,515,159.74 $293,923.31 $2,671,893.95 $5,000,048.00 $10,540,527.67 $555,764.73 $7,475,478.75 $2,210,801.94 $2,684,522.91 $2,369,503.32 $14,181,576.61 Reported Under MCP 95-09 $15,665,880.79 $288,310.00 $383,193.30 $223,936.25 $220,132.00 $95,549.74 $499,116.00 $19,505,442.51 $1,412,900.00 10/21/1996 05/20/1997 05/20/1997 09/17/1996 $1,134,227.02 $593,793.49 $1,193,974.49 $1,263,445.13 Reported Under MCP 4-7 Reported Under MCP 4-30 06/06/1995 11/21/1995 11/04/1997 $726,820.91 $154,066.36 $2,215,926.46 08/20/1996 08/20/1996 $10,121,039.09 $1,235,360.83 Reported Under MCP 4-64 09/05/1995 $914,854.08 Reported Under MCP 4-68 01/05/1994 11/03/1993 11/16/1994 $847,866.14 $1,099,728.07 $582,342.08 Reported Under MCP 3-128 03/07/1995 07/18/1995 03/14/1991 11/21/1995 $672,792.01 $2,885,020.35 $48,998.20 $1,439,871.95 11/05/1996 04/19/1995 11/02/1994 03/07/1995 07/06/1994 $2,668,977.28 $7,337,796.49 $1,991,346.64 $1,994,990.34 $3,666,387.10 Reported Under MCP 4-50 Reported Under MCP 4-50 Reported Under MCP 4-34 05/21/1996 03/19/1996 01/06/1997 $163,841.66 $186,792.65 Reported Under MCP 4-20 $1,748,319.81 Reported Under MCP 4-24 05/07/1996 $465,448.34 Reported Under MCP 4-29 Reported Under MCP 4-37 Reported Under MCP 4-5 Reported Under MCP 4-37 Reported Under MCP 4-4 Reported Under MCP 4-36 Reported Under MCP 4-28 09/09/1994 12/19/1995 02/06/1996 02/06/1996 11/21/1995 $672,695.87 $1,114,284.84 $1,133,654.48 $713,652.17 $1,678,670.31 Reported Under MCP 4-39 05/02/1995 $1,698,071.48 Reported Under MCP 4-4

PROJECT TITLE

Acceptance Date
05/18/1994 10/04/1993

Acceptance Amount
$7,489,196.04 $663,541.71

Comment

Construction Status Report

161

TABLE VI LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM COMPLETED PROJECTS
MCP CONT. NO. NO.
95-15 95-16 95-17 95-18 95-19 95-20 95-21 95-22 95-23 759 822R 787 802 804 804 804 803 (a) 817 846 96-01 96-02 96-03 96-04 96-05 96-06 96-07 96-08 96-10 96-13 96-15 96-16 96-17 96-18 855 811 812 813 804 806 815 807 824 838 840 842 843 997 854 856 857 893 894 895 896 897 898 916 926 927 1021 1022 1023 1097 97-02 97-02 97-02 97-02 97-02 97-02 97-02 97-03 97-04 97-05 97-07 97-08 97-12 98-02 98-02 98-03 98-03 98-03 98-04 98-05 98-06 98-06 98-06 98-06 98-06 98-06 98-06 98-06 98-06 99-05 99-06 99-07 99-08 99-09 00-01 00-05 (a) 918 959 962 967 1006 1055 901 901 865 905 906 1120 991 992 940 955 969 943 945 (a) 947 948 949 950 951 952 953 998 984 1032 974 975 1044 1000 1014 (a) 1140 1144 1103 00-07 00-08 00-09 00-10 00-11 00-12 1012 1095 984 992 1059 1058 3205 Zone Pumping Station at the 2975 Zone Reservoir Operation, Maintenance and Repair Complex Fort Apache Road 2860 Zone South Pipeline and Spring Mountain-Durango 2860 Zone and 2975 Zone Pumping Station Discharge Pipelines Pebble Road 2300 Zone Pipeline Spring Mountain-Durango Reservoir Expansion Spring Mountain-Durango Reservoir 2860 Zone Pumping Station Spring Mountain-Durango Reservoir 2975 Zone Pumping Station, Phase I Fort Apache Road 2860 Zone South Pipeline and Spring Mountain-Durango 2860 Zone and 2975 Zone Pumping Station Discharge Pipelines Artificial Recharge Wells Drill and Develop Artificial Recharge Wells AR-94 and AR-95 Drill and Develop Artificial Recharge Well AR-100 Drill and Develop Artificial Recharge Well AR-93 Bermuda Road 2300 Zone South Pipeline Torrey Pines Drive, Phase I, and Jones Boulevard, Phases I and II, 2420 Zone North Pipelines Valley View Boulevard 2420 Zone South Pipeline, Phase I Spring Mountain-Durango 2975 Zone Pumping Station, Phase II 3435 Zone Reservoir 3435 Zone Reservoir Inlet/Outlet Pipeline 3435 Zone Pumping Station at 3205 Zone Reservoir Central Sodium Hypochlorite Storage Facility Bermuda 2420 Zone Reservoir Tropicana 2860 Zone Reservoir 2975 Zone South Reservoir Inlet/Outlet Pipeline 1845 Pressure Zone Improvements Child Development Facility Water Resource Center Recycled Water Distribution System Water Resource Center Recycled Water Distribution System Drill and Develop Recharge/Recovery Well Nos. 118 and 119 Water Resource Center Recycled Water Distribution System Drill and Develop Recharge/Recovery Well Nos. 120 and 121 Water Resource Center Recycled Water Distribution System Cheyenne Avenue Pipeline Water Resource Center Recycled Water Distribution System Rampart Boulevard Pipeline Water Resource Center Recycled Water Distribution System Northeast Branch Pipeline Water Resource Center Recycled Water Distribution System WRC Pumping Station, Reservoir, and Satellite Booster Pumping Station Water Resource Center Recycled Water Distribution System Cheyenne Booster Pumping Station Water Resource Center Recycled Water Distribution System On-Site User Irrigation Water Resource Center Recycled Water Distribution System On-Site User Irrigation Water Resource Center Recycled Water Distribution System Well Nos. 118, 119, 120, 121 Water Resource Center Recycled Water Distribution System Equip Recharge/Recovery Well Nos. 120 and 121 Recycled Water Distribution System Canyon Gate Pipeline Recycled Water Distribution System Angel Park Palm, Angel Park Mountain, Badlands, Outlaw and TPC The Canyons Pipelines Recycled Water Distribution System Eagle Crest Pipeline Northwest Recycled Water Distribution System Miscellaneous Improvements Necessary System Improvements, Phase I Necessary System Improvements, Phase IA Necessary System Improvements, Phase II Necessary System Improvements, Phase IB Necessary System Improvements, Phase IC Necessary System Improvements, Phase III Necessary System Improvements, Phase IV 2975 Zone South Reservoir 3205 Zone South Pumping Station Bermuda/Serene 2300 Zone South Pipeline Meranto 2975 Zone Reservoir Inlet/Outlet Pipeline Warm Springs 2975 Zone Pumping Station 3665 Zone Pumping Station Tropical 2538 Zone North Reservoir Inlet/Outlet Pipeline, Phase I Tropical 2538 Zone North Reservoir Inlet/Outlet Pipeline, Phase II and Tropical 2635 Zone Pumping Station Discharge Pipeline Tropical 2538 Zone North Pipeline, Phase I Tropical 2538 Zone North Pipeline, Phase II Tropical 2538 Zone North Pipeline, Phase III Cimarron 2538 Zone North Pipeline, Phase II Fayle Reservoir Rehabilitation Desert Breeze Recycled Water Distribution System Desert Breeze Recycled Water Distribution System Pumping Station and Forebay Desert Breeze Recycled Water Distribution System Flamingo Pipeline, Phase I Desert Breeze Recycled Water Distribution System Durango Pipeline, Phase I Desert Breeze Recycled Water Distribution System Cimarron/Buffalo Pipeline Desert Breeze Recycled Water Distribution System Flamingo Pipeline, Phase II Desert Breeze Recycled Water Distribution System On-Site Irrigation Services Desert Breeze Recycled Water Distribution System Hualapai Booster Pumping Station Desert Breeze Recycled Water Distribution System Durango Pipeline, Phase II Tropical 2538 Zone Reservoir Azure 2538 Zone North Pipeline, Phase II Reno 2745 Zone Reservoir Reno 2745 Zone Reservoir Inlet/Outlet Pipeline and Reno/Fort Apache 2745 Zone South Pipeline 2150 Pressure Zone Improvements Charleston Heights Water Facilities Improvements 2168 Zone Well Collector Pipeline District's Participation in the Las Vegas Springs Preserve Charleston Heights 2168 Zone Reservoir Inlet/Outlet Pipeline Relocation Las Vegas Springs Preserve Buildings Nevada State Museum at the Las Vegas Springs Preserve Charleston Heights 2420 Zone Pumping Station Discharge Pipeline Bermuda 2538 Zone Pumping Station Tropical 2635 Zone Pumping Station Tropical 2635 Zone Pumping Station Discharge Pipeline Warm Springs 2538 Zone Pumping Station Addition Montessouri 2635 Zone Pumping Station Addition 09/08/2004 06/15/2004 05/17/2005 $2,772,506.10 $1,173,953.59 $1,561,637.88 10/04/2005 12/18/2007 11/19/2009 11/05/2002 04/07/2009 $452,569.09 $124,101,485.38 $773,854.77 $1,230,246.01 $13,532,539.60 Reported Under MCP 99-05 10/30/2003 06/19/2001 06/19/2001 10/16/2001 06/19/2001 06/04/2002 07/06/2004 12/04/2001 12/06/2005 11/18/2003 09/17/2002 05/07/2002 08/19/2003 12/07/2004 11/19/2002 $3,826,651.61 $804,412.00 $8,975,051.00 $3,687,692.00 $274,405.00 $5,332,402.00 $930,208.00 $1,346,072.32 $1,436,715.00 $650,676.00 $1,133,082.00 $2,176,624.01 $1,081,623.58 10/06/1998 04/04/2006 11/16/2004 05/02/2006 03/20/2001 09/08/2004 11/02/1999 03/02/2004 10/17/2000 10/17/2000 11/07/2000 $1,563,903.52 $2,418,115.00 $4,438,553.00 $7,925,342.90 $1,004,814.00 $2,500,540.00 $951,600.00 $1,354,589.00 $947,422.00 $574,020.00 $745,765.00 09/19/2000 12/07/1999 11/05/2002 02/15/2000 06/05/2001 04/16/2002 06/19/2001 $457,405.90 $583,464.00 $1,133,334.00 $159,280.00 $113,604.70 $173,495.00 $14,756,811.70 Reported Under MCP 97-03 05/21/2002 01/12/2003 03/01/2005 $2,056,080.69 $1,334,030.43 $259,816.92 09/01/1998 10/06/1998 05/04/2000 11/07/2000 11/02/1999 09/26/2002 04/15/2003 05/07/2002 10/06/1998 02/05/2002 $1,047,455.32 $1,026,496.91 $1,186,617.13 $3,659,677.81 $843,020.34 $9,384,434.79 $2,862,929.51 $4,890,023.27 $387,930.19 $1,806,127.76 11/18/2003 10/02/2002 05/16/2000 11/03/1998 12/05/2000 09/07/1999 02/15/2000 11/07/2000 09/19/2000 $6,645,792.00 $385,052.00 $4,435,591.00 $1,677,774.00 $7,954,762.00 $7,878,991.00 $2,077,629.25 $4,952,093.60 $526,435.00 11/18/1997 10/21/1997 02/03/1997 12/02/1997 04/21/1998 10/06/1998 $720,161.14 $395,112.42 $339,145.00 $692,447.32 $1,870,215.00 $1,474,079.97 Reported Under MCP 95-12 10/07/1997 $3,106,403.75

PROJECT TITLE

Acceptance Date
09/16/1997 11/19/2002 12/02/1997 12/17/1996

Acceptance Amount
$1,497,765.00 $10,900,879.95 $692,447.32 $199,094.24

Comment

Reported Under MCP 95-12 Reported Under MCP 95-12 Reported Under MCP 95-12

Cancelled

Cancelled Cancelled

Construction Status Report

162

TABLE VI LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM COMPLETED PROJECTS
MCP CONT. NO. NO.
00-13 (a) 1063 1079 1098 00-14 00-15 00-16 01-01 02-01 02-02 02-02 02-03 02-04 02-07 02-08 02-09 02-10 02-11 02-12 03-01 03-02 03-03 03-04 03-05 03-06 03-07 03-08 03-11 03-11 03-11 03-11 03-11 03-11 03-11 03-11 03-11 03-13 1102 1010 1064 1046 1075 1085 1087 1100 1088 1165 1102 1102 1102 1106 1105 1107 1123 1107 1107 1151 1246 1151 1174 (a) 1137 1138 1146 1149 1164 1186 1187 1195 (a) 1099 1233 1234 04-01 04-13 1162 (a) (a) 1127 1128 1155 1159 04-14 04-16 04-22 04-23 05-01 05-02 05-03 05-04 05-07 05-08 05-12 05-13 1252 1253 1171 1173 1192 1203 1183 1186 1183 1205 1179 1190 (a) 1160 1161 1188 1189 1199 06-03 06-05 06-05 06-05 06-05 06-05 06-05 06-16 06-16 06-16 06-16 06-16 06-16 1208 (a) Necessary System Improvements, Phase II Necessary System Improvements, Phase V Necessary System Improvements, Well Discharge Storm Drain Ties Necessary System Improvements, Campbell Station Site Improvements Montessouri 2538 Zone Reservoir Expansion, 2745 Zone Pumping Stations and Satellite Facility Meadows Detention Basin Improvements 2300 Zone Transmission System Improvements 3205 Zone Reservoir Expansion Tropical 2635 Zone Pumping Station Discharge Pipeline, Phase II Centennial 2635 Zone Reservoir Inlet/Outlet Pipeline, Phase I Centennial 2635 Zone Reservoir Inlet/Outlet Pipeline, Phase II Bermuda 2538 Zone Pumping Station Discharge Pipeline Valley View 2420 Zone South Pipeline, Phase II El Capitan 2745 Zone Reservoir Expansion Montessouri 2538 Zone Reservoir Expansion Montessouri 2745 Zone Pumping Station Montessouri 2860 Zone Pumping Station Montessouri 2745 Zone Pumping Station Discharge Pipeline Montessouri 2860 Zone Pumping Station Discharge Pipeline Elkhorn 2975 Zone Reservoir and 3090 Zone and 3205 Zone Pumping Stations Elkhorn 2975 Zone Reservoir Inlet/Outlet Pipeline Elkhorn 3090 Zone Pumping Station Elkhorn 3205 Zone Pumping Station Levi 2745 Zone Reservoir and 2860 Zone Pumping Station Levi 2745 Zone Reservoir and 2860 Zone South Pipeline, Phase III Levi 2860 Zone Pumping Station Bermuda 2745 Zone Pumping Station Necessary System Improvements, Phase VI: La Cienaga Street 2055 Zone PRV at the Campbell 1845 Zone Reservoir Site Vegas Heights Water System Improvements Valved Outlets at the Campbell 1845 Zone Reservoir Site Necessary System Improvements, Ford Avenue Pipeline Relocation Necessary System Improvements, Phase VI: Boulder Highway Crossing Necessary System Improvements, Phase VI: 2538 and 2420 Zone South Pipeline Improvements Necessary System Improvements, Phase VI: Sahara Avenue Necessary System Improvements, Phase VI: Searchlight Pipeline Relocation East Administration Building Electrical System Upgrade East Administration Building Electrical Power Service East Administration Building Power and Information Systems Additions East Administration Building Electrical Service Upgrade Renewable Energy Project Phase I: Development and Construction of Solar Electric Systems, Phase I Miscellaneous Vaults, Reconstruction, and Repair Miscellaneous Vaults, Reconstruction, and Repair, Phase I Miscellaneous Vaults, Reconstruction, and Repair, Phase II Miscellaneous Vaults, Reconstruction, and Repair, Phase III Miscellaneous Vaults, Reconstruction, and Repair, Phase IV Miscellaneous Vaults, Reconstruction, and Repair, Phase IV Well Nos. 2A and 5A Improvements Well Discharge Storm Drain Ties, Phase V Well Discharge Storm Drain Ties, Phase IV Warm Springs 2975 Zone Pumping Station Addition Meranto 3090 Zone Pumping Station Fayle 2300 to 2168 Zone Pressure Reducing Valves 2538 Zone and 2420 Zone South Pipeline and Pressure Reducing Station Improvements 2538 and 2420 Zone South Pipeline Improvements, Silverado Ranch and Jones 2538 Zone and 2420 Zone South Pipeline and Pressure Reducing Station Improvements East Desert Inn 1985 Zone Improvements Charleston Boulevard 2300/2420 Zone Pumping Station Suction Pipeline Rehabilitation Well Nos. 13 and 34 Improvements Miscellaneous Vaults, Reconstruction, and Repair, Phase II Miscellaneous Vaults, Reconstruction, and Repair, Phase VI Miscellaneous Vaults, Reconstruction, and Repair, Phase VII Miscellaneous Vaults, Reconstruction, and Repair, Phase VIII Miscellaneous Vaults, Reconstruction, and Repair, Phase IX Miscellaneous Vaults, Reconstruction, and Repair, Phase X Hydrogen Fueling Station Demonstration Project Backflow Assembly Installation Phase I 05/01/2007 07/17/2007 02/05/2008 01/02/2008 11/05/2008 07/03/2007 12/01/2009 10/3182009 09/16/2008 07/07/2011 $1,265,258.19 $1,017,277.30 $876,243.00 $1,098,921.42 $1,474,149.56 $641,868 $1,999,354 $684,795 $185,735 $107,850 Maintenance Engineering Maintenance Engineering Maintenance Engineering Maintenance Engineering Maintenance Engineering 08/07/2007 02/05/2008 11/06/2007 03/18/2008 12/02/2008 04/14/2007 $967,568.78 $1,118,201.54 $1,098,791.16 $732,690.55 $1,394,939.58 $369,977.53 07/17/2007 06/05/2007 11/05/2008 $641,977.05 $1,344,416.18 $512,771.06 06/20/2006 11/08/2006 03/21/2006 06/06/2006 10/06/2009 01/05/2008 05/16/2006 07/17/2007 10/06/2009 04/01/2008 06/02/2009 07/15/2008 $520,950.62 $1,481,384.83 $434,068.60 $598,877.23 $5,614,179.85 $1,277,112.88 $251,619.42 $901,365.02 $10,723,554.40 $1,024,532.96 $8,266,380.18 $1,567,490.68 Reported Under MCP 05-02 11/15/2005 07/07/2009 01/05/2010 04/01/2008 $2,742,243.91 $1,620,625.64 $3,677,154.51 $24,417,460.39 09/18/2007 04/17/2007 $841,725.00 $682,990.00 07/17/2007 12/19/2006 12/20/2005 04/04/2006 07/18/2006 $363,200.00 $1,082,960.00 $294,959.00 $289,400.00 $175,120.00 Reported Under MCP 05-03 07/07/2009 $12,472,663.00 01/05/2010 10/06/2009 $25,340,480.00 $6,285,210.00 Reported Under MCP 03-05 11/08/2006 04/03/2007 09/18/2007 05/16/2006 $1,860,074.00 $3,910,835.39 $21,316,758.00 $1,332,359.00 Reported Under MCP 03-01 Reported Under MCP 03-01 02/17/2004 11/03/2004 04/05/2005 03/04/2008 06/01/2004 07/19/2005 06/07/2005 11/03/2004 07/20/2004 05/16/2006 03/06/2007 07/19/2005 02/05/2008 $641,460.84 $514,721.01 $1,262,463.32 $27,090,487.81 $655,129.37 $5,691,523.23 $8,034,969.54 $1,037,000.00 $865,445.00 $2,421,979.00 $1,522,000.00 $3,786,507.00 $10,397,577.28 Reported Under MCP 00-14 Reported Under MCP 00-14 Reported Under MCP 00-14

PROJECT TITLE

Acceptance Date

Acceptance Amount

Comment

Cancelled

M0145 Backflow Assembly Installation Phase I: Miscellaneous Backflow Installations 2006-2007 Phase VII M0146 Backflow Assembly Installation Phase I: Miscellaneous Backflow Installations 2006-2007 Phase VIII M0149 Backflow Assembly Installation Phase I: Miscellaneous Backflow Installations 2007-2008 Phase IX M0150 Backflow Assembly Installation Phase I: Miscellaneous Backflow Installations 2007-2008 Phase X M0154 Backflow Assembly Installation Phase I: Miscellaneous Backflow Installations 2008-2009 Phase XI (a) 1193 1198 1238 1239 1313 Necessary Site Improvements Necessary Site Improvements: Disinfection Building Upgrades at Spring Mountain-Durango and Grand Canyon Reservoirs and Gowan Well Field Necessary Site Improvements: Multi-Site Surge Tank Upgrades Necessary Site Improvements: Necessary Site Improvements, LVSP Perimeter Fencing Necessary Site Improvements: Necessary Site Improvements, Well No. 116 Perimeter Fencing Necessary Site Improvements: Desert Inn 3205 Zone Pumping Station Facility Improvements

TOTAL Note: (a) Contract number not assigned.

$3,619,600.98

Construction Status Report

163

TABLE VII LAS VEGAS VALLEY WATER DISTRICT MAJOR CONSTRUCTION PROGRAM CANCELLED PROJECTS
MCP NO.
4-6 4-38 97-09 99-01 99-02 99-03 00-06 TOTAL NOTE: (a) Contract number not assigned.

CONT. NO.
617 (a) (a) 963 964 965 (a)

PROJECT TITLE
2745 Zone Well Collector Pipeline 2635 Zone Well Collector Pipeline Phase II Warm Springs 2975 Zone Pumping Station Discharge Pipeline 2285 Zone Reservoir 2285 Zone Reservoir Inlet/Outlet Pipeline Stewart 2285 Zone Pumping Station Fayle Reservoir Rehabilitation Phase II

Date of Cancellation
09/01/1998 09/01/1998 09/01/1998 06/15/2004 06/15/2004 06/15/2004 06/15/2004

Total Project Cost


$698,000.00 $259,000.00 $696,000.00 $2,200,000.00 $235,000.00 $713,000.00 $5,000,000.00 $9,801,000.00