Sie sind auf Seite 1von 4

GPSC/201314/120/3164

Sr. No. 1

Pending Electrical Works: Internal Wiring works

Start Date

Completion Date

%wise Completion 60%

Remarks Pending due to HVAC supply & Office Facade Pending Due to False ceiling In progress Completed

01/02/2014 22/02/2014

Light fixture and on Fire wall and in SCADA room and Office area Fixing of Chequered plate in control room Control Cable in work of 66/33kV transformer Control Cable in work of 33kV Panel Control Cable in work of 11kV Panel AC-DC 11kV and 33kV panel wiring Control cable tie Power cable dressing work 33kV panel base repair work (damaged during installation) 11kV panel base repair work (damaged during installation) Toilet Wiring and light fixture Wiring for split AC units

07/01/2014

22/02/2014 0%

3 4 5 6 7 8 9 10 11 12 13

14/02/2014 22/02/2014 22/02/2014

10%

90%

In progress In progress In progress In progress In progress In progress In progress In progress In progress(Hold due to HVAC) In progress In progress(Due to panel design problem) In progress In progress (Hold due to clearance problem & Bending of Cable) In progress In progress

22/02/2014 50% 22/02/2014 27/02/2014 27/02/2014 18/02/2014 80% 10% 30% 20%

18/02/2014 80% 18/02/2014 10% 22/02/2014 0%

14 15

Earthing of 33kV Panel (outside and inside of panel) Earthing of 11V Panel (outside and inside of panel)

22/02/2014 70% 22/02/2014 0%

16 17

UPS installation and their cabling work 33kV cable termination

22/02/2014 60% 22/02/2014 40%

18 19

LT panels and ACDB welding work Cable tray support fixing on 3 different location

22/02/2014 60% 22/02/2014 50%

GPSC/201314/120/3164

20 21 22 23 24 25

Cable tray shifting in type G-G trench in control room Cable tray alignment Terminations in BMK lightning arrester and guard wire Future earthing work Conductor finishing work

26/02/2014 0% 26/02/2014 22/02/2014 26/02/2014 26/02/2014 26/02/2014 30% 60% 0% 40% 40%

In progress In progress In progress In progress In progress In progress

Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Tiles

Pending Civil Works:

Start Date

Completion Date

Trench Cover in switchyard False ceiling Toilet septic tank Water proofing work Furniture work Plinth protection work of control room Trench work nearby control room BMK cable hole covering Fencing work Elevation wall Main gate Doors for battery room, SCADA room and store room Finishing work of damages due to conduct work Supply of fencing material Tank slab Pump room column Pump room slab

GPSC/201314/120/3164

19 20 21 22 23 24 25 26 27

Gravel filing Storm water drainage Grading work nearby control room Control room entry and exit pathway Security cabin Rain water harvesting pit Connection of overhead tank to fire water tank including its pump Touching and finishing work Final paint work

Sr. No. 1 2 3 4 5 6

Pending from supplier side: Schneider for 66/33kV Transformer Pristine for 11kV and 33kV panel Hitachi Hi Rel for UPS and battery charger ABB for 66kV breaker Voltamp for Electrolite for 66kV Isolator

Start Date

Completion Date

Sr. No. Pending from HVAC side: Indoor unit of Split AC installation in SCADA room 1 Indoor unit of Split AC installation in Office room 2 Outdoor unit installation on terrace 3 Exhaust Fan in Battery room 4 5 6 7 8 Exhaust Fan in store room Exhaust Fan in control room Exhaust Fan in toilet Painting work of control room duct

Start Date

Completion Date

GPSC/201314/120/3164

Sr. No. Pending from Fire Alarm side: Microcontroller based 2 loop addressable panel 1 Smoke detector with mounting base, LED, Address switch, 2 complete as per specifications. Heat Detectors with Standard Base 3 Addressable manual call point complete with address switch 4 5 6 7 Addressable Hooters Analogue addressable fixed temperature heat detector Cables for FAS

Start Date

Completion Date

Sr. No. Pending from SCADA side: SCADA panel erection 1 SCADA system control cabling 2 SCADA control desk 3 SCADA panel internal wiring 4

Start Date

Completion Date

Sr. No. Pending from Telecommunication side: FCBC and Battery 1 Telephone cabling 2

Start Date

Completion Date

Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12

Miscellaneous work: Switchyard area grading drawing including pathways landscape works Pump room faade Road furniture (marking, kerb stone etc.) Relay setting calculation SCADA program Ladder Touching work of all panels and transformer RYB marking in switchyard Earhing pit and strip marking Cable rout marking Dewatering pumps

Start Date Completion Date

Remarks

Das könnte Ihnen auch gefallen