Beruflich Dokumente
Kultur Dokumente
ISSUED: 01/06/2011
TABLE OF CONTENTS
1.0 PURPOSE ........................................................................................................3
2.0 SCOPE..............................................................................................................3
3.0 PROCEDURE - ROAD CROSSING:................................................................3
4.0 METHOD STATEMENT .................................................................................4
4.1 Consultation ............................................................................................................................................4
4.2 Planning ...................................................................................................................................................4
4.3 Before Work Commences ......................................................................................................................5
4.4 Hazards .....................................................................................................................................................6
4.5 Control Measures .....................................................................................................................................6
4.6 Safety measures to comply with during construction works ...............................................................7
4.7 Visual Test ................................................................................................................................................7
4.8 Safe Access/ Egress ..................................................................................................................................8
4.9 Completion of Work ................................................................................................................................8
ISSUED: 01/06/2011
1.0 PURPOSE
This Method Statement provides guidance to prevent injury to persons
engaged in excavation works on ANSA Technologies worksite.
2.0 SCOPE
This document outlines the procedures and method related to construction
of road crossings.
4.0
4.1
ISSUED: 01/06/2011
METHOD STATEMENT
Consultation
The Client, ANSA Technologies and Sub contractors doing the work will
consult with each and determine the provision of all safeguards. The
consultation process will be used during the planning and preparation
stages to determine safe systems of work based on the assessment of the
risks. Engineers will be involved in the consultation process when
appropriate.
The consultation process will at least cover the following:
(a) Nature and condition of the ground or working environment;
(b) Nature of the work and other activities that may affect safety;
(c) Static and dynamic loads near road crossing excavation;
(d) Interaction with other trades;
(e) Workplace access;
(f)
4.2
Planning
Planning and preparation will be the first essential step in ensuring that
work is done safely.
4
ISSUED: 01/06/2011
Planning and preparation will involve consultation with all relevant persons
engaged in the work and will include hazard identification, risk assessment
and risk control processes. Where appropriate, the advice of the
ANSA Technologies in its capacity will:
1. Provide such information, instruction, training and supervision as may
be necessary to ensure the health and safety of its employees
/subcontractors; and
2. Provide or maintain means of access to and egress from the work
place safe and without risks.
4.3
ISSUED: 01/06/2011
4. Locate and flag overhead power lines on or near the work site to be
avoided by plant equipment.
5. Create an emergency plan and discuss the plan with all team members.
6. Determine the soil type and anticipate what worker protection will be
required.
7. Arrange to have barricades and warning signage delivered to site
before work commences.
9. Arrange the delivery to the worksite before work commences of ladders
of the correct length (or other equipment) required for correct
access/egress into the excavation/trench
10. Ensure that all team members are trained appropriately.
11. Ensure that all team members have the appropriate Personal
Protective Equipment.
12. Review proposed work & safety controls.
4.4
Hazards
Before the initial construction work starts, hazards shall be identified, and
assessed by the competent person assigned to the work or project. All of
the control measures made by the competent person shall be in writing
and kept on file, (refer to JHA for potential hazards).
A copy of the control measures shall also be kept on site at all times until
after the completion of the work. These control measures shall be
establish and maintain before and during the construction works in
accordance with the scope of works and drawing specifications.
The competent person assigned to the project shall inspect all control
measures including those for existing hazards at least once a day,
preferably more.
4.5
Control Measures
ISSUED: 01/06/2011
4.6
4.7
Visual Test
The visual test is to be carried out by the competent person before, during
and after construction works. In a visual test, the entire work areas are
observed, including the surroundings adjacent to the site. During the
visual test, the competent person shall:
1. Look for existing petroleum lines, electrical cables, water lines etc.
7
ISSUED: 01/06/2011
2. Observe the open side of the road crossing excavation works for
indications of possible cave in;
4. Look for signs of surface water seeping from the sides of the
excavation.
4.8
4.9
Completion of Work
When the construction of the road crossings have been completed,
backfilling shall start and support systems shall be removed from the
bottom of the excavation. It shall be carried out in a manner that protects
employees, the public and any equipment or adjacent structures from
cave-ins, structural collapses or being struck by components of the
support system.