21 May 2013 ARC 4710 Architectural Practice 2nd Semester 2012/ 2013
POST CONSTRUCTION
Project Completion
Certificate of Practical Completion (CPC) issued: Project has been completed End of Interim Certificate Defects Liability Period (DLP) commences End of Contractors insurances coverage Release of of retention sum Building handed over to Client Final measurement & Valuation begins
ARC4710-2nd Semester 2012/2013
Project Completion
Handing Over to Client:As-Built dwgs to be prepared by Consultants and submitted to Client: - basis for Final Measurement - record of what have been built O&M Manual normally compiled by M&E contractor and supervise by M&E Engr. Training for Clients personnel Keys
ARC4710-2nd Semester 2012/2013 3
Project Completion
Application for Certificate of Fitness for Occupation (CFO): Apply CFO vide Borang E to LA C&S and M&E Engr. to endorse on Borang E Client cannot occupy building without CFO LA will visit site for CFO inspection As-Built Drawings to be submitted to LA
before inspection
Project Completion
CFO will only be issued by LA when : Building is considered safe for occupation Water and Electricity is available Support Letter from various authorities
CFO vs CCC
After April 2007 CFO had been replaced with Cert. Of Completion & Compliance (CCC) CFO Issued by Local Authority CCC Issued by PSP
Reasons For Change? To remove bureaucracy To expedite the process of occupying new bldgs To give better protection to house buyers
ARC4710-2nd Semester 2012/2013 6
CFO vs CCC
Acts/ Laws that were amended Architects Act 1967 (Act 113) - Architects Rules 1986 Street, Drainage & Building Act 1974 (Act 133) - UBBL 1984 Housing Developers Act 1966 Strata Title Act 1985 Engineers Act and many more.
ARC4710-2nd Semester 2012/2013
Project Completion
Defects Liability Period (DLP):a period of time where by any defects (bounded by the contract) during this period (as agreed in the contract document) on the building shall be rectified by the contractor at his own cost. Duration of DLP - as per Appendix 1. DLP for Housing projects has been extended to 24 months after April 2007 Clients representative to provide list of defects & Contractor to rectify. Within 14 days of DLP Architect to issue Schedule of Defects to Contractor for rectification works
ARC4710-2nd Semester 2012/2013 11
Project Completion
Cert. Of Making Good Defects (CMGD):will be issued once all defects have been rectified by the Contractor release of the balance of retention sum.
12
NO
CPC
ANY DEFECT? YES ISSUE INSTRUCTIONS CONTRACTOR MAKE GOOD DEFECTS END OF DLP SCHEDULE OF DEFECTS CONTRACTOR MAKE GOOD DEFECTS
Project Completion
Final Certificate (FC)
QS statement of final account for the work which take into account: the variations to the work as ordered from time to time PC sums EOT LAD Etc It will be presented through the Architect to the Client as a statement agreed with the Contractor. The issuance of a Final Certificate assumes that everything is acceptable. Signed copies of the account to be issued to both the Client and Contractor.
ARC4710-2nd Semester 2012/2013
14
Borang B Site Possession Mtg Performance Bond Contractors All Risk Workmans Compensation
Setting Out
Borang C
Borang D
Site Meeting Valuation
Interim Certificates
ARC4710-2nd Semester 2012/2013 15
End of DLP
CPC Issued
End of DLP
ARC4710-2nd Semester 2012/2013
Works Completed
End of DLP
ARC4710-2nd Semester 2012/2013
Final Certificate
Final Payment
ARC4710-2nd Semester 2012/2013 19