Sie sind auf Seite 1von 58

Alcatel-Lucent 9370 RNC Physical Installation

Installation Method 08-9696

May 25, 2009 Issue Number: 3.08

Pkgid: 0000003 UNCONTROLLED COPY: The master of this document is stored on an electronic database and is "write protected"; it may be altered only by authorized persons. While copies may be printed, it is not recommended. Viewing of the master electronically ensures access to the current issue. Any hardcopies taken must be regarded as uncontrolled copies. ALCATEL-LUCENT CONFIDENTIAL: The information contained in this document is the property of Alcatel-Lucent. Except as expressly authorized in writing by AlcatelLucent, the holder shall keep all information contained herein confidential, shall disclose the information only to its employees with a need to know, and shall protect the information from disclosure and dissemination to third parties. Except as expressly authorized in writing by Alcatel-Lucent, the holder is granted no rights to use the information contained herein. If you have received this document in error, please notify the sender and destroy it immediately. 2003-2007 Alcatel-Lucent All Rights Reserved

May 25, 2009

Method 08-9696

Table of Contents
1.0 General Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 1.1 Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 2.0 Material Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 2.1 Required Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 3.0 Precautions and Preparations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.1 Precautions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.2 Preparations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.3 Check List . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 7 7 7

4.0 Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 4.1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 4.2 Equipment Reception. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 Procedure 1 Equipment Reception . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 4.3 Cabinet Handling. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 Procedure 2 Cabinet Handling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 4.4 Cabinet Securing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 Procedure 3 Cabinet Securing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 4.5 Ground Wiring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 Procedure 4 Ground Wiring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 4.6 Power Cables Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22 Procedure 5 Power Cables Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22 4.7 Fabric Module Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 Procedure 6 Fabric Module Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 4.8 Alarm Module Connection And PIM Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29 Procedure 7 Alarm Module Connection and PIM Connection . . . . . . . . . . . . . . 29 4.9 Board Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30 Procedure 8 Board Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30 4.10 External Connection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31 Procedure 9 External Connection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31 4.11 Brackets Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33 Procedure 10 Brackets Installation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33 4.12 Installation of the Panels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36 Procedure 11 Installation of the Panels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36 5.0 9370 RNC Single Shelf to Dual Shelf Upgrade . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Procedure 12 9370 RNC Single Shelf to Dual Shelf Upgrade . . . . . . . . . . . . . . 5.1 Final Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Procedure 13 Final Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.0 Appendix . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Appendix A Hardware Configuration of the Alcatel-Lucent 9370 RNC . . . . . . . . . . . . . . . . Appendix B External Cabling of The 9370 RNC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.0.1 9370 RNC PCM Out-of-Band OAM Connectivity . . . . . . . . . . . . . . . . . . . . . . . . . . 6.0.2 9370 RNC PCM In-Band OAM Connectivity. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Appendix C Glossary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Appendix D Abbreviation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Appendix E Report Sheet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Last Page . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37 37 50 50 51 51 52 52 52 53 53 55 57

Alcatel-Lucent 9370 RNC Physical Installation / 1

Method 08-9696

May 25, 2009

Figures
Figure 1 Example of Trolley to Move the 9370 RNC Cabinet . . . . . . . . . . . . . . . . . . . . . . Figure 2 Footprint Measurements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 3 Location of The Frame Levelers and Anchor Openings . . . . . . . . . . . . . . . . . . . Figure 4 Anchor Kit for Concrete Floor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 5 Anchor Kit for Raised Floor. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 6 Junction Between two Cabinets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 7 Leveling of the Frame . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 8 Ground Connection on Rear Top of the Cabinet . . . . . . . . . . . . . . . . . . . . . . . . Figure 9 Equipotentiality Connection on the Top of the Frame (CBN Network). . . . . . . . . Figure 10 Protective Cover Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 11 DC Power Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 12 Access to the Individual Studs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 13 Placing the Main Feed Cables. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 14 Securing the Lugs. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 15 Securing the protective Boot.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 16 Securing the Cables. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 17 Power Cabling to the BIP from Overhead. . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 18 Power Cabling To The BIP from the Floor . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 19 Fabric Modules Installed. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 20 Alarm/BITS Module Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 21 Power Interface Module Connection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 22 Population of the 9370 RNC PS1 or DCPS . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 23 Insertion of a Module . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 24 CP3 (CP4) Board Front Face . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 25 16p OC-3 FP Card . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 26 Assembly of a Side Bracket, Left and Right, Upper and Lower . . . . . . . . . . . . Figure 27 Upper Brackets for Cabinet Panels. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 28 Lower Brackets for Cabinet Panels. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 29 Top Bracket and Side Panel Grounding Cable . . . . . . . . . . . . . . . . . . . . . . . . Figure 30 Location of Front, Rear and Side Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 31 Cables Covers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 32 Shelf Fillers Front & Rear. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 33 Placement of the BIMS, Front View . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 34 Front and rear views of the upper and lower cooling units . . . . . . . . . . . . . . . . Figure 35 Upper Shelf Assembly . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 36 Protective Cable Cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 37 Upper Shelf DC Connection: Rear View . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 38 Locations of the Alarm Cable Connectors and Paths . . . . . . . . . . . . . . . . . . . . Figure 39 Power Schematic - RNC1500 Dual (Rear View) . . . . . . . . . . . . . . . . . . . . . . . . Figure 40 Upper Shelf Rear Cabinet with Fabric Cards Cages . . . . . . . . . . . . . . . . . . . . . Figure 41 Fabric Card Front View . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 42 Population of the 9370 RNC PS1 or DCPS Upper Shelf . . . . . . . . . . . . . . . . . . Figure 43 CP3 Board Front Face . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 44 16p OC-3 FP Card . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Figure 45 Location of Front, Rear and Side Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 13 15 16 17 18 19 20 21 23 23 24 24 24 25 25 26 26 28 29 29 30 30 31 32 33 33 34 35 36 37 38 39 40 41 42 43 43 44 45 46 47 47 48 49

2 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

Tables
Table 1 Tools & Test Sets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 Table 2 9370 RNC Configuration UTRAN UA5.x . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51 Table 3 9370 RNC Configuration UTRAN UA6.x . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51

Alcatel-Lucent 9370 RNC Physical Installation / 3

Method 08-9696

May 25, 2009

1.0 General Information


Description
Purpose: This method describes the operations to physically install the Alcatel-Lucent 9370 RNC cabinet, The Alcatel-Lucent 9370 RNC is one component of the UTRAN. The 9370 RNC manages the link between the Core Network and the Node Bs Equipment: This method applies to the 9370 RNC cabinet. Application: The 9370 RNC configuration may include a POC (Point of Concentration). Standalone 15k POC, standalone 7k POC and Access Node presented in this document are for user reference only and are not Alcatel-Lucent 9370 RNC Market Packages. They are Multi-Service Switch packages and components available from Nortels MSS 7k Product Order Guide. Product integrity testing of these configurations is owned solely by Nortel. This transport Node may be based on Alcatel-Lucent platform (7670 RSP, 7670 ESE). In UA5.x: 9370 RNC VSS with MSS 7k POC and 9370 RNC VSS with MSS15k POC Market Packages are discontinued by RNC For the installation of the 7K POC or the PCM-Access Node, refer to Passport 6440/7440/6480/7480 Series Physical Installation. IM:050603; which can be found at: https://wcdma-ll.app.alcatellucent.com/livelink/ livelink.exe?func=ll&objId=36528788&objAction=browse&sort=na me&viewType=1 Service Impact: There is no service impact on initial sites.

1.1 Sequence
This method is to be performed after Method Alcatel-Lucent 9370 RNC Site Specification, IM 06-9699, which can be found at: https:// wcdma-ll.app.alcatel-lucent.com/livelink/ livelink.exe?func=ll&objId=36528788&objAction=browse&sort=na me&viewType=1 Available updates to this method can be found at https://wcdmall.app.alcatel-lucent.com/livelink/ livelink.exe?func=ll&objId=36528788&objAction=browse&sort=na me&viewType=1

4 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

2.0 Material Requirements


2.1 Required Documents
IM 45-9399 Alcatel-Lucent 9370 RNC Product Safety Installation Requirements, can be found at:https://wcdma-ll.app.alcatellucent.com/livelink/ livelink.exe?func=ll&objId=36528788&objAction=browse&sort=na me&viewType=1 IM 10-9018 Alcatel-Lucent 9370 RNC IRM Kits Specification, can be found at: https://wcdma-ll.app.alcatel-lucent.com/livelink/ livelink.exe?func=ll&objId=36528788&objAction=browse&sort=na me&viewType=1 IM 03-9062 Fiber Optic Cable Requirements can be found at:https:// wcdma-ll.app.alcatel-lucent.com/livelink/ livelink.exe?func=ll&objId=36528788&objAction=browse&sort=na me&viewType=1 Tool & Test Sets The Tools and Test Sets listed in Table 1 are required to perform this method.
Table 1 Tools & Test Sets Tool / Test Set # Digital Multimeter Drill Hammer Hilti TE52 for MSS Cabinet/ Seismic Cabinet anchoring Torque Wrench Brother P-touch Printer Fork lift truck Trolley Nail claw Diamond punch Drilling machine with its mandrel carrier Various drills for concrete, wood metal... (up to = 16mm) Portable workbench with vice Qty. 1 1 Description Electrical measurement Cabinet Securing

3/8 Dial Torque Wrench, Proto, 0-250 inchlbs. Wire Labelling Handling Handling Unpacking Drilling Drilling Drilling Securing preparation

Set 1 1 1 1 1 1 Set 1

Alcatel-Lucent 9370 RNC Physical Installation / 5

Method 08-9696

May 25, 2009

Table 1 Tools & Test Sets Tool / Test Set # Metal cutting saw Spirit level Tape rule (2m) Ratchet wrenches with lead and sockets: 3-5.5-7-10-12-13-15-17 Flat blade screwdrivers Phillips screwdrivers Vacuum cleaner Stepladder Cable tie plier Electrician's shears Electrician's knife 6 to 70 MM. crimping pliers Sleeving pliers Qty. 1 1 1 1 Set 1 1 Set 1 1 1 1 1 1 1 Description Securing preparation Cabinet securing Cabinet securing Cabinet securing Cabinet securing Cabinet securing Cleaning Wire connection Wire connection Wire connection Wire connection Wire connection Wire connection

Refer to IM 10-9018 Alcatel-Lucent 9370 RNC IRM Kits Specification to verify the standards kits need for these installation, this IM can be found at: https://wcdma-ll.app.alcatel-lucent.com/ livelink/ livelink.exe?func=ll&objId=36528788&objAction=browse&sort=na me&viewType=1 No other materials are required to perform this method.

6 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

3.0 Precautions and Preparations


3.1 Precautions
Observe the general safety precautions against personal injury and equipment damage outlined in the regional Installation Safety Manual at all times.

3.2 Preparations
It is strongly recommended that this method be read in its entirety before starting the operations presented herein. Prior to starting the operations presented in this method, arrange all materials, tools, and test equipment at the work location so as to minimize fatigue and inconvenience. The following instructions must be observed: the use of the antistatic wrist strap is mandatory when handling electronic modules,

EMC sealing joints being fragile, shocks and hand contact must be avoided, the equipment must be protected from dusts resulting of the cabinets securing operations, whatever the circumstances, the mechanical parts of the cabinets must never be, modified on site (holes, etc....).

3.3 Check List


Verify the following items have been received and/or accomplished before proceeding with the procedure. Upon arrival, read the safety guidelines specific to the site. Check that the site complies with IM 06-9699 Alcatel-Lucent 9370 RNC Site Specification Check that the site is equipped with lights, main sockets, ventilation or air conditioning as mentioned in site preparation and installation

Alcatel-Lucent 9370 RNC Physical Installation / 7

Method 08-9696

May 25, 2009

document. Check that the external physical interfaces (- 48V power supply cabinet, PCM distribution cabinet, cable ways) are installed and located as indicated in site preparation and installation document. Check for presence and polarity of the - 48 V supply upstream the fuses (fuse holder open) on the customer power supply box, using a multimeter. Locate the cable way and check that it complies with current standards (the separation between high current and low current) according to the site preparation and installation document. Check that the access to the work area (passages, stairways, floors,...) does not present any obstacle which may block or slow down the cabinets installation. Check that the area foreseen for the cabinet installation is clean and tidy and complies with Alcatel-Lucent RNC Site Specification.

8 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

4.0 Procedure
4.1 Overview
The information presented in this method covers the following topics: Cabinet reception Cabinet handling Brackets installation Cabinet securing Ground wiring Power cables connection Fabric module installation Alarm module connection and PIM connection. Board installation External cables connection Installation of the panels 9370 RNC Single Shelf to Dual Shelf Upgrade Final checks.

Alcatel-Lucent 9370 RNC Physical Installation / 9

Method 08-9696

May 25, 2009

4.2 Equipment Reception


The objective of this procedure is to check the cabinet reception and to check that it complies with the packing list.
Procedure 1 Equipment Reception Step 1 2 3 4 5 Action Check that the cabinet packages (those with a wooden pallet or in a plywood crate) are upright or lying delivered in their initial packing. Use the fork lift truck (or equivalent) to get the cabinet packages out of the vehicle, and move them as close as possible to the site. Check that the packages do not show any visible sign of faulty storing or handling (wooden packages rotten, saturated with water, cracked, distorted...). Check that the site number or the site name as well as the package number are marked on each package and that the number of packages complies with the one given in the packing list. Check that the shock indicator, specific label stuck on the external packing of the cabinets, is not red and therefore remains transparent. Should the indicator be missing or red, the equipment has been subjected to a faulty handling during transportation and has to be replaced. From the side of the cabinet packaging (the largest one), remove the packet of shipping info and put it aside for office records. Open the packages except those with the wooden pallet (or in the plywood crate). Without removing the modules located inside each package, check that the quantity complies with the packing list. Save the container in case the cabinet must be returned.

6 7 8 9

10 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

4.3 Cabinet Handling


The objective of this procedure is to move the cabinet until the sites room.
Procedure 2 Cabinet Handling (Page 1 of 2) Step Action Removing an Horizontal Cabinet from the Pallet. Remove the four bolts in the pallet that fasten the cabinet to pallets shipping brackets. Remove the shipping brackets from the cabinet. Gently tap with a hammer if required. Ensure that each leveling foot at the bottom end of the cabinet is screwed all the way in. The following should be performed by at least 3 people: lift the top of the cabinet until the cabinet feet touch the foot plate of the trolley. While tilting, be sure that neither the trolley, the cabinet, nor the pallet slides along the floor. Avoid allowing the full weight of the cabinet to sit on the leveling feet. When the cabinet is vertical, check by a gentle push whether it vibrates. If it vibrates more than slightly, have a helper tilt the cabinet while to adjusting appropriate corner leveler downwards until the vibrations stops. Save the bolts, the brackets, and the pallet in case the cabinet has to be returned. Move the cabinet into the site room. Removing a Vertical Cabinet from the Pallet. Undo the four bolts in the pallet that fasten the cabinet-to-pallet shipping brackets. Remove the shipping brackets from the cabinet. Gently tap with a hammer if required. While 3 handlers slightly tilt and hold the cabinet to raise the side with the red cables off the pallet, put the trolley on the pallet and slide the foot-plate under the edge of the cabinet. Avoid allowing the full weight of the cabinet to sit on the leveling feet. Lower the cabinet gently onto the foot-plate. Tightly, strap the cabinet to the trolley. Route the straps around the cabinet and cabinets so that no cable is pinched and no handle is overlapped. The doors, handles, and cables are not designed to withstand pulling from the weight of the cabinet. With 3 handlers, tilt the cabinet and trolley towards the wheels. Allow the extended wheels to gently touch the floor. While still holding the trolley and cabinet, pull the trolley away from the pallet and lower the other set of wheels gently onto the floor. When the trolley is on the floor, adjust the positions of the corner leveling feet to be relatively even with the 2 on the foot-plate. Adjust all middle leveling feet (up to 4) to be in more than the corners. Turn only the threaded part of the feet. The cabinet is ready to be moved

A.
1 2 3 4

6 7

B.
1 2 3

4 5

Alcatel-Lucent 9370 RNC Physical Installation / 11

Method 08-9696

May 25, 2009

Procedure 2 Cabinet Handling (Page 2 of 2) Step 9 10 Action Save the bolts, the brackets, and the pallet in case the cabinet must be returned. Move the cabinet into the site room.

Figure 1 - Example of Trolley to Move the 9370 RNC Cabinet

12 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

4.4 Cabinet Securing


The objective of this procedure is to anchor the 9370 RNC cabinet.
Procedure 3 Cabinet Securing (Page 1 of 7) Step Action Floor Preparation 1 2 Use the drilling template provided in the bottom of the cabinet Set on the floor the drilling template.

Figure 2 - Footprint Measurements.

Alcatel-Lucent 9370 RNC Physical Installation / 13

Method 08-9696

May 25, 2009

Procedure 3 Cabinet Securing (Page 2 of 7) Step 3 Action Mark on the floor the outline of the cabinet and the different holes to drill.

Note: To check the type of the site bonding networks refer to Table 6.3 Appendix C
Glossary on page 53 For Isolated Bonding Network (IBN) the cabinet must be isolated from the floor by the use of rubber shims or groundsheet and isolated anchoring system (bushing washer). For the Common Bonding Network (CBN): there is no specific recommendation to secure the cabinet

a
1 2 3

Case of Concrete Floor


Drill according to the marks on the drilling template. Make sure to drill just the depth Clean the holes. Insert the suitable mounting pegs.

b
1 2 3 4 5 6 7 8 9

Case of Raised Floor


Drill according to the marks on the floor. Make sure to drill just the depth corresponding to the suitable mounting pegs. In turn, vertically insert the threaded rod then strongly press on it in order to leave a mark on the concrete floor. Remove the threaded rods and the floor tile(s), and then drill according to the marks on the floor. Clean the holes. Insert the suitable mounting pegs. Put back the floor tile(s) to its (their) initial place If necessary, cut the floor tile(s) for the cable access and put a protection on the sharp edges. Prepare the stainless steel threaded rods (once in place, they must top the nuts inside the cabinet, 6 threads). Clean the cabinet location. Securing the Cabinet

a
1 2 3 4 5

Case of Concrete Floor


Put the cabinet in its precise location Remove the cover plate from the front and the rear of the bottom cabinet. Disconnect the yellow/green cable from each cover plate. Adjust alignment, verticality and fit using a spirit level by adjusting foot height. For each hole located at the bottom of the cabinet, insert a M12 screw with a wide flat washer.

14 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

Procedure 3 Cabinet Securing (Page 3 of 7) Step Action

Figure 3 - Location of The Frame Levelers and Anchor Openings

Alcatel-Lucent 9370 RNC Physical Installation / 15

Method 08-9696

May 25, 2009

Procedure 3 Cabinet Securing (Page 4 of 7) Step Figure 4 - Anchor Kit for Concrete Floor Action

b
1 2 3 4 5 6 7 8

Case of Raised Floor


Put the cabinet in its precise location. Remove cover plate in the front and the rear of the bottom cabinet. Disconnect the yellow/green cable from each cover plate Adjust alignment, verticality and fit using a spirit level to adjust foot height. Remove the nearest floor tile(s) in order to access the holes under the cabinet. According to the securing type, insert and screw on the 6 specific bolts or 6 threaded rods with their wide flat washers in each hole located at the bottom of the cabinet. Put back the nearest floor tiles. For installations where the power cabling is routed upwards from the floor, remove the plate from the bottom of the cabinet close to where the cable comes through the floor.

16 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

Procedure 3 Cabinet Securing (Page 5 of 7) Step Figure 5 - Anchor Kit for Raised Floor Action

Fastening Adjacent Cabinets Together Before Levelling 1 2 Before a pair of cabinets together can be appropriately leveled or anchored, they must be fastened. Before starting the procedure, have the appropriate number of kits referenced NTRU6101. Ensure that the cabinets are positioned side-by-side and touching on the footprints where they are to be anchored. The upper pair of brackets have the same symmetry as the lower pair, and there is a pair both at the front and at the rear where the cabinets are joined. Align an L-shaped bracket. Fasten the bracket to the cabinet using the 4 provided self-tapping 6-mm (1/4-inch) bolts. Tighten to snug plus a 1/5 turn. Repeat step 3 and step 4 for the upper right bracket. Place the U-shaped bracket over the arm created by the left and right brackets. Fasten it to both cabinets using the 4 provided bolts and washers. You may need to temporarily shim some cabinet feet to align both the left and right bracket holes. Align an L-shaped bracket on the middle upper right front (long arm outwards). Fasten the bracket to the cabinet using 4 bolts and washers. Place the U-shaped bracket over the arm created by the left and right brackets. Fasten it to both cabinets using the 4 provided bolts and washers. You may need to temporarily shim some cabinet feet to align both the left and right bracket holes. Repeat step 4 to step 9 for the upper and lower rear joining brackets. Remove any shim from under the cabinet feet that were used to align bracket holes for fastening.

3 4 5 6

7 8 9

10 11

Alcatel-Lucent 9370 RNC Physical Installation / 17

Method 08-9696

May 25, 2009

Procedure 3 Cabinet Securing (Page 6 of 7) Step Figure 6 - Junction Between two Cabinets Action

Levelling the Cabinet or Cabinet Pair 1 2 Unfasten the 2 large captive flat-blade screws per kick plate at both the front and the rear bottoms of the cabinet or cabinet pair. Reach through the side openings of the cabinet (or front, depending on ease of access) to adjust the middle levelers so that each foot is away from the floor. Adjust a leveler by turning the threaded shaft counter-clockwise. If the shaft cannot be turned manually, use an 8-cm (5/16- inch) hex driver at the top of the threaded shaft. Lay a level vertically against the side of a middle upright cabinet or pair of cabinet to identify which side of the cabinet is the highest (the cabinet feet are the levelers). Reach past the kick plate opening to adjust the foot downwards at the highest side of the cabinet. Each foot is adjustable by an 8-cm (5/16- inch) hex driver at the top of the threaded shaft. Monitor the level while adjusting. Stop when that face of the cabinet is levelled. Lay the level vertically along the front of the middle upright cabinet to identify which is the highest, the front or the rear of the cabinet. Adjust the highest corner feet downwards until the cabinet or cabinet pair is leveled. Reach through the side openings of the cabinet (or front, depending on ease of access) to adjust the middle levelers so that each foot touches the floor. Adjust each leveler by turning the threaded shaft clockwise. If the shaft cannot be turned manually, use an 8-cm (5/16- inch) hex driver at the top of the threaded shaft. Once the levelers touch the floor, turn each with the hex driver 1/8 turn clockwise The cabinet is ready to be anchored.

3 4

5 6 7

8 9

18 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

Procedure 3 Cabinet Securing (Page 7 of 7) Step Figure 7 - Leveling of the Frame Action

Note: Anchor the cabinet securely to the floor


In all cases, tighten the 6 screws to ensure a good cabinet securing.

Alcatel-Lucent 9370 RNC Physical Installation / 19

Method 08-9696

May 25, 2009

4.5 Ground Wiring


The objective of this procedure is connect the ground of the 9370 RNC cabinet.
Procedure 4 Ground Wiring (Page 1 of 2)

Note: To check the type of the site bonding networks refer to Table 6.3 Appendix C
Glossary on page 53 For Isolated Bonding Network (IBN) the cabinet must be grounded only by one unique ground cable directly connected to the SPC site. For the Common Bonding Network (CBN) the cabinet must be grounded by the ground cable and equipotentiality braids.

Note: There is no bend radius for electrical cable, however, observe a 1.5-inch bend radius for the 6 AWG (13.3 mm) cable. The BIP can accommodate a cable up to 6 AWG cable and it must be flexible enough:
To do right-angle bends from the lugs onto and along the horizontal 7 mm (0.25inch) thick steel cable-supporting bracket at the rear of the BIP. To do a right-angle bend up from the cable-supporting bracket to an overhead cable trough or down along the side of the cabinet. The following operations have to be performed:

Note: The ground cable NTQG03CF is an component of standard IRM kits for the 9370 RNC, defined
in the document: IM:10-9018. Step 1 2 3 4 5 6 7 Action Route the cable according to site preparation and installation document. Cut the cable to the correct length and crimp the lugs with the proper tool. Connect the ground cable directly to the earth plate. Connect the ground cable to the ground bus bar located at the rear top of the cabinet. Label the cable. The label printed with Wheelie-Bin symbol is to be used if the country applies the WEEE directive (European Directive) Attach the cable to the cable tray using cable ties. Check the connection tightening.

Figure 8 - Ground Connection on Rear Top of the Cabinet

Ground cable
3JR60042AAAA

20 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

Procedure 4 Ground Wiring (Page 2 of 2) 8 In case of CBN network the main frame should be connected to the cable tray with two equipotentiality braids. Tighten the braids on the cable tray with the screws and bolts provided. Screw down the braids on the rear of the main frame, one at each side. Screw them at the top or at the bottom of the frame, depending on the position of the cable tray. See Figure 9 Figure 9 Equipotentiality Connection on the Top of the Frame (CBN Network)

Alcatel-Lucent 9370 RNC Physical Installation / 21

Method 08-9696

May 25, 2009

4.6 Power Cables Connection


The Objective of this procedure is to connect the 9370 RNC cabinet power cables.
Procedure 5 Power Cables Connection (Page 1 of 5)

Note: The BIP can accommodate a cable up to 2 AWG (35 mm) and it must be flexible enough:
To do right-angle bends from the lugs onto and along the horizontal 7 mm (0.25-inch) thick steel cable-supporting bracket at the rear of the BIP. To do a right-angle bend up from the cable-supporting bracket to an overhead cable trough or down along the side of the cabinet. Make sure that the breakers or fuses located in the customer DC distribution panel are switched off.

Note: The power cable is an component of standard IRM kits for the 9370 RNC, defined in the document: IM:10-9018
Step Action

Caution / Warning: Risk of equipment damage by reverse polarity


Use the plus (+) and minus (-) symbols on the rear of the (BIP) to ensure that the polarity of each A and B battery (-57/-43 V dc) and battery return for the input power feeds is correct, the minus (-) is -48V and plus (+) is -48V return When powering up the BIP, reversed polarity will damage circuits inside it the BIP would have to be replaced. 1 Verify the voltage between the A1- and A1+ pair is negative and ranges within: Nominal power 48 Vdc: min. 40 Vdc max 57.6 Vdc Nominal Power 60 Vdc: min. 50 Vdc max 72 Vdc

Note: The minus (-) is -48V and plus (+) is -48V return for nominal power 48 Vdc
2 Verify the voltage between the B1- and B1+ pair is negative and ranges within: Nominal power 48 Vdc: min. 40 Vdc max 57.6 Vdc Nominal Power 60 Vdc: min. 50 Vdc max 72 Vdc

Note: The minus (-) is -48V and plus (+) is -48V return for nominal power 48 Vdc
3 4 5 6 Route the cable according to site preparation and installation document, between the 9370 RNC cabinet and the customer distribution box. Cut the cable to the correct length at the customer distribution side. Crimp a lug onto each wire of the cable. Insert a sleeve on each wire and one at the end of the sheath. Type of signal Color of wire 0V Black -48 V Blue or Black (Blue for North America & Black for EMEA)

22 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

Procedure 5 Power Cables Connection (Page 2 of 5) 7 At the bottom of the 9370 RNC cabinet, there is a bag with 4 plastic protective covers, refer to Figure 10.

Figure 10 - Protective Cover Installation

On the cabinet side, slide a protective cover on each end of the power cable.

Figure 11 - DC Power Connection

9 10 11

Use the 2 AWG (35 mm) cables for the 9370 RNC power supply: A1 and B1 connectors (Lower Shelf) Loosen the insulation boot clamp from the rear of the BIP to access the individual studs. Swing these out of the way, and re-tighten, refer to Figure 12 Unbolt the two lug retaining nuts from each stud on the BIP and remove the two Belleville washers. Place the main feed cables on the studs, starting on the left with -, which is A1 BATT, then + , which is A1 RTN, then to the right for the B1pairs, refer to Figure 13

Alcatel-Lucent 9370 RNC Physical Installation / 23

Method 08-9696

May 25, 2009

Procedure 5 Power Cables Connection (Page 3 of 5) Figure 12 Access to the Individual Studs

Figure 13 Placing the Main Feed Cables.

Secure the lugs with the washers and nuts. The Belleville washers must be placed on the studs with the convex side outwards before securing the nuts. Using the Dial Torque wrench , torque each nut to 6.5 Nm (57 inch-pounds), refer to Figure 14

Figure 14 Securing the Lugs.

24 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

Procedure 5 Power Cables Connection (Page 4 of 5)

Caution/Warning: Risk of damage to power connections


Use of properly calibrated torque wrench is required to ensure that you do not overtight the studs. Damaging a stud can mean the BIP must be replaced.
10 Once the power cables are attached, secure the protective boot over the lug. The boot is held in place by a small bracket, refer to Figure 15

Figure 15 Securing the protective Boot.

12

Use cable ties to secure all the cables on the frame, refer to

Figure 16 Securing the Cables.

13

Label all the cables.The label printed with Wheelie-Bin symbol is to be used if the country applies the WEEE directive (European Directive)

Alcatel-Lucent 9370 RNC Physical Installation / 25

Method 08-9696

May 25, 2009

Procedure 5 Power Cables Connection (Page 5 of 5) Figure 17 - Power Cabling to the BIP from Overhead

Figure 18 - Power Cabling To The BIP from the Floor

26 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

4.7 Fabric Module Installation


The objective of this procedure is to install the fabric module on the rear of the 9370 RNC cabinet.
Procedure 6 Fabric Module Installation (Page 1 of 2)

Note: Each 9370 RNC cabinet contains two Fabric modules, refer to Figure 19
Step 1 Action Unpack the fabric. A fabric weighs about 6.8 kg (15 lbs.).

Important: Use caution when handling.


2 3 4 Wearing a wrist strap, hold the fabric module by the edges so that the U-shaped lever faces you. Unfasten the captive screw with a large flat-blade screwdriver and open the casing using the large lever. Stop when the lever touches the casing on the opposite side. At the rear of the shelf where the fabric module is to be installed, align the position of the four guide pins from the backplane with the four holes in the fabric module The guide pin pattern is asymmetrical so that either fabric module can be installed in only one way. Use the alignment markings on the fabric to assist with orienting it. Insert the hinge pegs of the pair of covers into the curved channels at the center shaped . Ensure that the pegs are seated all the way in; otherwise, damage can occur to the fabric when the casing is closed. You may have to jiggle the pins very gently into place.

Important: Do not force the card onto the backplane


6 7 Slowly move the fabric module to insert the four guide pins through the holes. Press the fabric onto the backplane using gentle, even pressure, and simultaneously close the casing while holding the lever. One side of the fabric module is set sooner than the other. If you feel resistance against the fabric module while seating it, do not force it. Re-set it and if there is still some resistance, remove the fabric module and look for an obstruction or bent guide pin. Close the casing flush with the sides of the cage. Align and fasten the captive screw using the screwdriver until snug plus a 1/5 turn.

8 9

Alcatel-Lucent 9370 RNC Physical Installation / 27

Method 08-9696

May 25, 2009

Procedure 6 Fabric Module Installation (Page 2 of 2) Figure 19 - Fabric Modules Installed.

28 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

4.8 Alarm Module Connection And PIM Connection


The objective of this procedure is to connect the alarm module of the 9370 RNC cabinet.
Procedure 7 Alarm Module Connection and PIM Connection Step 1 2 Action At the rear of the cabinet, in the Alarm/BITS module, connect the DB25 red alarm cable into the connector labeled J1 and the DB9 alarm cable into the connector labelled J2. Secure both connectors to the module by tightening the two screws, refer to Figure 20.

Figure 20 - Alarm/BITS Module Connection

Alarm/BITS cable

At the side of the cabinet, connect the power cable to both PIM of the lower shelf, refer to Figure 21.

Figure 21 - Power Interface Module Connection

Alcatel-Lucent 9370 RNC Physical Installation / 29

Method 08-9696

May 25, 2009

4.9 Board Installation


The objective of this procedure is to populate the 9370 RNC cabinet.
Procedure 8 Board Installation Step 1 2 3 Action Wear an antistatic wrist straps and connect it to the cabinet, the wrist strap is located in the bottom of the cabinet. Withdraw the modules from the package. It is recommended to populate the 9370 RNC as following, refer to Figure 22 Figure 22 Population of the 9370 RNC PS1 or DCPS

or CP4

or CP4

or GigE 4 5 6 Insert very carefully the modules inside the cabinet, refer to Figure 23. Close the locking levers to secure the module. Figure 23 - Insertion of a Module Step 1 Step 2 airflow patterns to ensure proper cooling. 30 / Alcatel-Lucent 9370 RNC Physical Installation

Note: PS_FP = PS1 or DCPS, Packet Server maybe either legacy PS1 or DCPS. Mixing is not supported, slot 14 & 15 may also be Gig E cards.CP4 is introduced in UA6.0 (CP3 & CP4 mixing is not supported)

Using your thumbs, push on the upper and lower edges of the faceplate to ensure that the module is fully seated in the shelf.

Step 3

Important: Equip all unused slots with filler modules. They maintain shelf

or GigE

May 25, 2009

Method 08-9696

4.10 External Connection


The objective of this procedure is to connect the 9370 RNC cabinet with its environment.
Procedure 9 External Connection (Page 1 of 2) Step Action

Note: For ethernet connection refer to 6.2 Appendix B -, "External Cabling of The 9370 RNC,"
on page 52
1 Connect the Ethernet cable between the HUB (If its present) and each CP3 (CP4) board of the 9370 RNC, refer to Figure 24

Figure 24 - CP3 (CP4) Board Front Face

Optical Connection
Identify the label on each cable end.

2 3 4 5

With an aerosol, clean the optical fiber connectors and board connectors before connecting them. Connect the optical fibers on the 16p OC3 board of the 9370 RNC, refer to Figure 25. Connect the other end of the optical cable to the dedicated distribution cabinet. Secure the optical cable along the cable tray using ty-wraps or similar.

Alcatel-Lucent 9370 RNC Physical Installation / 31

Method 08-9696

May 25, 2009

Procedure 9 External Connection (Page 2 of 2) Figure 25 16p OC-3 FP Card

MTRJ Connector

16p OC-3 SmIrAtm FP MTRJ: NTHW21 (Manufacture Discontinued)

LC Connector

16p OC-3 SmIrAtm LC: NTHW31

FP

16p OC-3 PosAtm

FP

LC: NTHW48

32 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

4.11 Brackets Installation


The objective of this procedure is the installation of the mounting brackets for the cabinet panel.
Procedure 10 Brackets Installation (Page 1 of 3) Step 1 2 Unpack the mounting brackets and bolts. Secure both elements of the side panel bracket, refer to Figure 26 Action

Figure 26 - Assembly of a Side Bracket, Left and Right, Upper and Lower

Refer to Figure 27, Figure 28 and Figure 29, and secure all the brackets to the cabinet. In case of several cabinets side to side, secure the brackets only on both ends.

Figure 27 - Upper Brackets for Cabinet Panels

Alcatel-Lucent 9370 RNC Physical Installation / 33

Method 08-9696

May 25, 2009

Procedure 10 Brackets Installation (Page 2 of 3) Step Action

Figure 28 - Lower Brackets for Cabinet Panels

4 5

To install a bracket for front top or rear panel, remove the 2 screws on each side before placing the bracket. Put the bracket and tighten the 2 screws, refer to Figure 29 Using 2 of the provided 10-mm (3/8-inch) bolts and lock washers, fasten the ground cable assembly from the upright cabinet to an upper bracket. Position a toothed lock washer between each end-cable eye loop and the cabinet or the bracket. Use the third hole from the top of the cabinet at one end of the cable and a lower middle hole on the side of the upper bracket nearest the upright.

34 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

Procedure 10 Brackets Installation (Page 3 of 3) Step Action

Figure 29 - Top Bracket and Side Panel Grounding Cable

Alcatel-Lucent 9370 RNC Physical Installation / 35

Method 08-9696

May 25, 2009

4.12 Installation of the Panels


The objective of this procedure is to install the front, rear and side panels of the 9370 RNC cabinet.
Procedure 11 Installation of the Panels

Side panel
1 2 3 4 Loosely fasten screw and washer through the opposite end hole so that the panel is evenly supported. Align the holes with the holes in the brackets and insert the screws into the panel mounting holes, beginning with the upper brackets, refer to Figure 30 Tighten all the screws. Eight screws are required for each panel. Install a plastic cap onto each special washer by lightly tapping it into place.

Cable Covers
1 2 Insert cable covers into the bracket at the bottom of the main cabinet (insert into the slot closest to the front of the cabinet), refer to Figure 30 Tighten the screw of each cable cover.

Note: While holding panel aligned in position (of the floor), loosely fasten a screw and special washer through a corner hole.
Figure 30 - Location of Front, Rear and Side Panel

36 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

5.0 9370 RNC Single Shelf to Dual Shelf Upgrade


The objective of this procedure is to upgrade an 9370 RNC single shelf to an 9370 RNC dual shelf.
Procedure 12 9370 RNC Single Shelf to Dual Shelf Upgrade (Page 1 of 13)

Unpacking the Upper Shelf Assembly


1 Carefully move the shipping container to where the 9370 RNC lower shelf frame is installed. Plug in an anti-static wrist strap or equivalent device into a properly grounded receptacle and wear the strap whenever handling a hardware part. Open the container of the shelf assembly. The PEC of the assembly is labeled on the outside of the container. When cutting the tape or straps that seal the container, make very shallow cuts. Do the box ends before the sides so that you can raise the middle slightly to cut it. Gently remove any loose padding surrounding the contents, if present. Avoid contacting the rows of exposed pins or connectors with the packing material. Do not touch any pins or connectors. Remove the shelf from all packaging so that you can see all sides. At the rear of the shelf assembly, use a flashlight to examine the rows of pins on the backplane connectors inside the fabric card slots. Also examine the rows of pins inside the shelf assembly. If at least one pin seems to be bent even slightly, do not install the shelf. Contact your Nortel technical support representative for the installation to report the damage. Inform the network operator that you are ready to proceed with starting the removal procedure. Have the operator confirm that traffic has been rerouted from the entire node, and lock all function processor (FP) cards and the 2 fabrics.

Sides Panels & Cables Covers Removal


2 Refer to Figure 30 to remove the side panels. The cables covers are located on the left and right sides of the RNC frame, refer to Figure 31 Figure 31 Cables Covers Cables Covers 9370 RNC Upper Shelf

Screw fastener

9370 RNC Lower Shelf

Lower end has a tab that inserts into the base

Alcatel-Lucent 9370 RNC Physical Installation / 37

Method 08-9696

May 25, 2009

Procedure 12 9370 RNC Single Shelf to Dual Shelf Upgrade (Page 2 of 13) 3 Unscrew the fastener at the top of one of the cable covers, lean the top out slightly and lift until the tab on the bottom of the cover pulls out of the base, refer to Figure 31 Repeat this action for the cable cover on the other side of the frame.

Shelf Fillers Removal


Figure 32 Shelf Fillers Front & Rear

Front Shelf Filler panel Bolts holes in the panel for mounting onto the front (rear) face of the frame uprights

Rear Shelf Filler Panel

Use socket and driver to remove all bolts from the frame mounting ears that secure the shelf filler assembly to the front frame. Start from the bottom bolts on both sides and work upwards. Before removing the last 2 bolts. Remove the last 2 bolts while the filler shelf assembly is supported. Pull the filler shelf assembly straight out and away from the frame. Repeat theses actions for the rear shelf filler panel.

Second BIMS (Upper Shelf BIMs) Installation


5 At the front of the BIP, unfasten the two captive screws at both ends holding the lower cover and swing it downwards from its upper edge. See Figure 33

38 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

Procedure 12 9370 RNC Single Shelf to Dual Shelf Upgrade (Page 3 of 13) Figure 33 Placement of the BIMS, Front View

Upper Shelf

Lower Shelf BIM B1 BIM A1

Alarm Test Module

Filler Panel

Filler Panel

At the front left of the BIP, remove both filler panels covering the BIM openings. Unfasten the captive screw until the panel comes off. Ensure all of the breakers on the new BIM are off (that is, the O on each breaker switch is pressed in). Hold the BIM with the screws on top and the end without breakers closest to the opening. Insert the BIM into the slot in the BIP. Keeping the BIM level, slide it gently into the slot until it connects with the backplane at the inside rear of the BIP. If there is resistance and the BIM is not fully seated, pull it out and inspect the backplane pins and the BIM connector for anything bent. You may need a flashlight to see inside the BIP. On the lower front of the BIM, align and fasten the captive screw until snug plus a 1/5 turn against the BIP chassis. Do not strip the threads or hole because the module cannot seat properly. Repeat steps above for the second BIM. At the front of the BIP, swing the lower cover upwards from its upper edge and fasten the two captive screws.

Upper Cooling Unit Installation


7 Open the container identifying the cooling unit and remove the cooling unit. a. b. c. d. Hold the ends of the cooling unit so that: You face the fans The open side is at the top A hand holds the narrow rear end A hand holds the fan end

Facing the rear of the switch, insert the narrow end of the cooling unit between the frame uprights, and above the lower (rear) cooling unit.

Alcatel-Lucent 9370 RNC Physical Installation / 39

Method 08-9696

May 25, 2009

Procedure 12 9370 RNC Single Shelf to Dual Shelf Upgrade (Page 4 of 13) Without pinching your fingers, rest the narrow end of the cooling unit on the top of the lower cooling unit. Figure 34 Front and rear views of the upper and lower cooling units

Slide the cooling unit inwards and downwards until the mounting ears near the fan end touch the frame uprights. The top of the lower cooling unit becomes the bottom of the upper cooling unit. Shift the cooling unit mounting-ear holes to align with bolt holes on the frame uprights. While holding the cooling unit in position, have a helper loosely fasten a 10-mm (3/8-inch) bolt through an upper mounting-ear hole.

40 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

Procedure 12 9370 RNC Single Shelf to Dual Shelf Upgrade (Page 5 of 13) Loosely fasten another bolt through the other upper mounting-ear hole, then the bottom 2. While turning the bolt, ensure that it is perpendicular to the hole to prevent cross-threading. Tighten all bolts to snug plus a 1/4 turn. If any cable for the F1, F2, or F3 connectors is unplugged, plug it in. The connectors fit only one way. Ensure the tab on the side engages. Plug in the A and B power cable assembly connectors into the appropriate connector on the unit. Each connector fits only one way. Ensure that the tab on each side of a connector fully engages.

Upper Shelf Assembly Installation


Figure 35 Upper Shelf Assembly

Have the helpers hold the replacement shelf assembly in front of the frame or rack so that the large deeper opening is facing you and the cable channel is at the bottom. This is the same orientation as the removed shelf assembly. Insert the shelf above the cooling unit and between the frame uprights. Do not let the shelf rest against the cooling unit. While holding the shelf, align its 16 bolt holes (8 per vertical side) on the 2 mounting ears with the previous holes on the frame uprights or racks adapter brackets. Ensure that the bottom holes are as close to the cooling unit as possible without touching it.

Alcatel-Lucent 9370 RNC Physical Installation / 41

Method 08-9696

May 25, 2009

Procedure 12 9370 RNC Single Shelf to Dual Shelf Upgrade (Page 6 of 13) Loosely fasten a bolt through 1 of the top mounting holes on 1 upright or adapter bracket. Loosely fasten the top bolt on the other side.

Note: If you use a pair of the eye holes that allows threading 2 bolts before placing the shelf
assembly against the uprights, and then passing the mounting ears over the bolts to hang there until other bolts are fastened, you must use only the top two, thread at least four-fifths of the each bolt into the upright, and hang the shelf assembly on both bolts simultaneously. Otherwise the weight of the assembly can bend the mounting ear. Orient, place, and loosely fasten each mounting bracket back where it was on top of the mounting ears of the shelf assembly. Check that all remaining mounting ear holes are still aligned with the previous upright or adapter bracket holes, then loosely fasten the remaining bolts through the shelf mounting ears. From bottom to top, tighten all bolts to snug plus a 1/4 turn. Power Cables Connection

Note: The BIP can accommodate a cable up to 2 AWG (35 mm) and it must be flexible enough:
To do right-angle bends from the lugs onto and along the horizontal 7 mm (0.25-inch) thick steel cable-supporting bracket at the rear of the BIP. To do a right-angle bend up from the cable-supporting bracket to an overhead cable trough or down along the side of the cabinet. Make sure that the breakers or fuses located in the customer DC distribution panel are switched off. The power cable is an component of standard IRM kits for the 9370 RNC, defined in the document: IM:10-9018 9 Route the cable according to site preparation and installation document, between the upper shelf cabinet and the customer distribution box. Cut the cable to the correct length at the customer distribution side. Insert a sleeve on each wire and one at the end of the sheath. Type of signal Color of wire 0V Black -48 V Blue or Black (Blue for North America & Black for EMEA) Use the 4 plastic protective covers and slide them on each end of the power cable. Figure 36 Protective Cable Cover

Use the 2 AWG (35 mm) cables for the 9370 RNC power supply: A2 and B2 connectors (Upper Shelf) Unbolt the nuts and washers from each stud of the BIP at the rear top of the cabinet, refer to Figure 37

42 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

Procedure 12 9370 RNC Single Shelf to Dual Shelf Upgrade (Page 7 of 13) Figure 37 Upper Shelf DC Connection: Rear View

A2 B2

A1 & B1 Lower Shelf

Upper Shelf

Secure the lugs with washers and nuts. Secure the protective cover on the lug. The protective cover is held in place by a bracket. Use cable ties to secure all the cables on the frame. Label all the cables.The label printed with Wheelie-Bin symbol is to be used if the country applies the WEEE directive (European Directive)

Alarm Module Connection and PIM Connection


Figure 38 Locations of the Alarm Cable Connectors and Paths

Sync. B J3 Sync. A J4 Cooling unit Alarm J2 BIP Alarm J1

Alcatel-Lucent 9370 RNC Physical Installation / 43

Method 08-9696

May 25, 2009

Procedure 12 9370 RNC Single Shelf to Dual Shelf Upgrade (Page 8 of 13) 10 At the rear of the cabinet, in the Alarm/BITS module, connect the DB25 red alarm cable into the connector labeled J1 and the DB9 alarm cable into the connector labelled J2. Secure both connectors to the module by tightening the two screws, refer to Figure 39. At the side of the cabinet, connect the power cable to both PIM of the Upper shelf, refer to Figure 39 Figure 39 Power Schematic - RNC1500 Dual (Rear View)

11

Fabric Module Installation


12 Wear an antistatic wrist straps and connect it to the cabinet, the wrist strap is located in the bottom of the cabinet. Unpack the fabric. A fabric weighs about 6.8 kg (15 lbs.).

Important: Use caution when handling.


Wearing a wrist strap, hold the fabric module by the edges so that the U-shaped lever faces you Unfasten the captive screw with a large flat-blade screwdriver and open the casing using the large lever. Stop when the lever touches the casing on the opposite side.

44 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

Procedure 12 9370 RNC Single Shelf to Dual Shelf Upgrade (Page 9 of 13) At the rear of the shelf where the fabric module is to be installed, align the position of the four guide pins from the backplane with the four holes in the fabric module The guide pin pattern is asymmetrical so that either fabric module can be installed in only one way. Use the alignment markings on the fabric to assist with orienting it. Insert the hinge pegs of the pair of covers into the curved channels at the center shaped. Ensure that the pegs are seated all the way in; otherwise, damage can occur to the fabric when the casing is closed. You may have to jiggle the pins very gently into place.

Important: Do not force the card onto the backplane


Slowly move the fabric module to insert the four guide pins through the holes. Press the fabric onto the backplane using gentle, even pressure, and simultaneously close the casing while holding the lever. One side of the fabric module is set sooner than the other. If you feel resistance against the fabric module while seating it, do not force it. Re-set it and if there is still some resistance, remove the fabric module and look for an obstruction or bent guide pin Close the casing flush with the sides of the cage. Figure 40 Upper Shelf Rear Cabinet with Fabric Cards Cages

Alcatel-Lucent 9370 RNC Physical Installation / 45

Method 08-9696

May 25, 2009

Procedure 12 9370 RNC Single Shelf to Dual Shelf Upgrade (Page 10 of 13) Figure 41 Fabric Card Front View

Align and fasten the captive screw using the screwdriver until snug plus a 1/5 turn.

Boards Installation
13 Wear an antistatic wrist straps and connect it to the cabinet, the wrist strap is located in the bottom of the cabinet. Withdraw the modules from the package It is recommended to populate the 9370 RNC as following, refer to Figure 42

46 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

Procedure 12 9370 RNC Single Shelf to Dual Shelf Upgrade (Page 11 of 13) Figure 42 Population of the 9370 RNC PS1 or DCPS Upper Shelf

or CP4

or CP4

or GigE airflow patterns to ensure proper cooling.

Note: PS_FP = PS1 or DCPS, Packet Server maybe either legacy PS1 or DCPS. Mixing is not supported, slot 14 & 15 may also be Gig E cards. CP4 is introduced in UA6.0 (CP3 & CP4 mixing is not supported) Important: Equip all unused slots with filler modules. They maintain shelf
External Connections
14 Connect the Ethernet cable between the HUB (If its present) and each CP3 board of the 9370 RNC refer to Figure 43 Figure 43 - CP3 Board Front Face

15

Optical Connection
Identify the label on each cable end. With an aerosol, clean the optical fiber connectors and board connectors before connecting them Connect the optical fibers on the16p OC31 board of the 9370 RNC, refer to Figure 44. Connect the other end of the optical cable to the dedicated distribution cabinet Secure the optical cable along the cable tray using ty-wraps or similar

Alcatel-Lucent 9370 RNC Physical Installation / 47

or GigE

Method 08-9696

May 25, 2009

Procedure 12 9370 RNC Single Shelf to Dual Shelf Upgrade (Page 12 of 13) Figure 44 16p OC-3 FP Card

MTRJ Connector

16p OC-3 SmIrAtm FP MTRJ: NTHW21 (Manufacture Discontinued)

LC Connector

16p OC-3 SmIrAtm LC: NTHW31

FP

16p OC-3 PosAtm

FP

LC: NTHW48

48 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

Procedure 12 9370 RNC Single Shelf to Dual Shelf Upgrade (Page 13 of 13)

Sides Panels & Cables Covers Installation


Refer to Procedure 11 , "Installation of the Panels," on page 36 to reinstall the panels & the cables covers removed in the beginning of this procedure. Figure 45 - Location of Front, Rear and Side Panel

Alcatel-Lucent 9370 RNC Physical Installation / 49

Method 08-9696

May 25, 2009

5.1 Final Checks


The objective of this procedure is describe the operations to be performed before you leaving the site.
Procedure 13 Final Checks Step 1 2 3 4 5 6 Close all the cabinet doors. Clean up the site. Fill up the Report Sheet. Leave one copy on site and send one copy to the co-ordinator. Write down on the report sheet the serial number of the cabinet(s). All non-compliance have to be physically spotted on site and recapitulated on the Report Sheet. For any corrective action, refer to the co-ordinator. Action

50 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

6.0 Appendix
6.1 Appendix A - Hardware Configuration of the Alcatel-Lucent 9370 RNC
1- UTRAN UA5.x
Table 2 9370 RNC Configuration UTRAN UA5.x UTRAN UA5.x SDH/Sonet
1504 1506 1507 1510 1512

Configuration/Provisioning Node Redundancy

CP3 OC3 PS-FP

1+1 1 + 1+ LAPS N +1, load Sharing

2 2 4

2 2 6

2 2 7

2 2 10

2 2 12

2- UTRAN UA6.x
Table 3 9370 RNC Configuration UTRAN UA6.x UTRAN UA6.x SDH/Sonet
1504 1506 1508 1510 1512

Configuration/Provisioning Node Redundancy

CP3 OC3 PS-FP

1+1 1 + 1+ LAPS N +1, load Sharing

2 2 4

2 2 6

2 2 8

2 2 10

2 2 12

Alcatel-Lucent 9370 RNC Physical Installation / 51

Method 08-9696

May 25, 2009

6.2 Appendix B - External Cabling of The 9370 RNC


6.2.1 9370 RNC PCM Out-of-Band OAM Connectivity

PWI: Preside for Wireless Internet (Common user interface for OMC-R, OMC-B & MDM)

6.2.2 9370 RNC PCM In-Band OAM Connectivity

PWI: Preside for Wireless Internet (Common user interface for OMC-R, OMC-B & MDM)

52 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

6.3 Appendix C - Glossary


Installer Co-ordinator Supervisor IBN Person in charge of installation Person in charge to co-ordinating the project installation Person in charge to supervising a site installation Isolated Bonding Networks: A bonding network that has a single point of connection (SPC) to either the common bonding network or another isolated bonding network. All IBNs have a unique connection to earth via SPC. Common Bonding Network: The CBN is the principal means for performing bonding and earthing inside a telecommunication building. It is the set of metallic components that are intentionally or incidentally interconnected to form the principal BN in a building. The CBN always has a mesh topology and is connected to the grounding electrode system.

CBN

6.4 Appendix D - Abbreviation


A BIP CBN CEC CP DDF EMC GND IBN IM RNC MDM NEC OAM OC-3 OMC-B Ampere Breaker Interface Panel Common Bonding Network Canadian Electrical Code part I Control Processor Dedicated Distribution Frame Electromagnetic Compatibility GrouND Isolated Bonding Network Installation Method Radio Network Controller Multiservice Device management National electrical code Operation, Administration, Maintenance Optical Carrier level 3 Centralized Node B implementation specific OAM center

Alcatel-Lucent 9370 RNC Physical Installation / 53

Method 08-9696

May 25, 2009

OMC-R PIM PS STM1 TBD UMTS ULRAN V

Centralized UTRAN OAM center Power Interface Module Packet Switched Synchronous Transport To Be Defined Universal Mobile Telecommunication System UMTS Terrestrial Radio Access Network Volt

54 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

6.5 Appendix E - Report Sheet


Input parameters (new parameters may be added) Number of cabinet............................ 9370 RNC Serial Number........................ Access Node Serial Number........... 9370 RNC Configuration SDH/Sonet

1504 1506 1507 (1508 in UA6.0) 1510 1512


Power supply connection with redundancy

Yes No
In Case of PCMx configuration, connection between the 9370 RNC and Access Node.

Directly Through an optical DDF


Adjacent frames must be fastened

Yes No

The Action following chart, To Use column MUST be filled by the co-ordinator before the site operation.
Procedure Initials Checks Condition To Use Procedure N OK NOK

Alcatel-Lucent 9370 RNC Physical Installation / 55

Method 08-9696

May 25, 2009

Equipment reception Cabinet Handling Brackets Installation Cabinet Securing Ground Wiring Power Cables Connection Fabric Module Installation Alarm Module Connection And PIM Connection Board Installation External Connection Installation Of The Panels 9370 RNC Single Shelf to Dual Shelf Upgrade Finals Checks

1 2 3 4 5 6 7 8 9 10 11 12 13

This folio MUST be filled during the site operation. Additional results: 9370 RNC Serial Number:. /UMTS POC Serial Number:. Comments:

Sign off:
Coordinator Company Name Fitter Customer representative

56 / Alcatel-Lucent 9370 RNC Physical Installation

May 25, 2009

Method 08-9696

Functions Name Signature Date

Last Page

Alcatel-Lucent 9370 RNC Physical Installation / 57

Das könnte Ihnen auch gefallen