FOR INFORMATION

C
B A
REV.

20.Oct.2012 26.Sep.2012 16.Aug.2012

Issue for information Issue for information Issue for information


DESCRIPTION

H.M.KIM H.M.KIM H.M.KIM

S.H.KIM S.H.KIM S.H.KIM

Son.Joon Son.Joon Son.Joon

DATE

DSGN

CHKD

APPD

PROJECT :

TWO(2) x 500 MW MONG DUONG 1 THERMAL POWER PLANT


EMPLOYER :

CONSULTANT :

CONTRACTOR :

DESIGNED BY

DATE

TITLE :

H.M. Kim
CHECKED BY

20, Oct, 2012


DATE

Method Statement for STG Foundation Concrete Works


PROJECT NUMBER ADB/MD1-TPIP/EPC150911 DOCUMENT NUMBER MD1-0-T-052-05-00114 REV.

S.H. Kim
APPROVED BY

20, Oct, 2012


DATE

Son Joon

20, Oct, 2012

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works

Rev. C

TABLE OF CONTENTS

1.

PURPOSE

2.

SCOPE OF WORKS

3.

REFERENCE CODE & STANDARD

4.

MANPOWER & EQUIPMENT

5.

GENERAL

6.

WORK METHOD

7.

TEMPERATURE CONTROL

8.

SAFETY CONTROL AT SITE

9.

ATTACHMENT

Attach No# 1 - Turbine foundation Plan Attach No# 2 - Turbine foundation Section Attach No# 3 Pump car location arrangement Attach No# 4 Peri system formwork Attach No# 5 Foundation Interface Recommendations Attach No# 6 Nominate backup batch plan

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works 1.0 PURPOSE

Rev. C

This method statement has been prepared to provide a general guide, special considerations to be given in relation to the heat of hydration for concrete pours. This method statement describes the work procedures to be carried out during an execution stage of mass foundations/structures of which the character of the concrete is technically specified as a structure with large dimensions like identical Steam Turbine Foundation (2nos). In this case the cracks & temporary control is required both during the concrete mix control at concrete batching plant prior to concreting and its monitoring after the concrete is placed in order that the requirements stated in the Contract Specification for Concrete Works e.g. a temperature differential between the interior of the concrete and any outside face will not exceed 20 C as far as possible. The method statement also includes details of temperature difference control procedure and all necessary temporary works such as curing method by thermal quilts, precaution barricade, temporary access and related activities which are required to undertake during a certain period.

2.0

SCOPE OF WORKS

This method statement includes e.g. concrete batching plant control including supply and delivery to Site, casting sequence , the method to control and prevent the concrete cold joint being introduced during concrete placing and a proper curing to maintain ,control temperature difference not to exceed the specified tolerance stated in the ACI 301-10. Section 8 Mass Concrete Clause 8.1.2 , Specification for Concrete Works of which the method of monitoring will be included , and all incidentals necessary to complete the entire works.
2.1. 2.1.1.

Responsibilities Contractors Project Manager shall be responsible for overall construction activities inclusive ensuring that all safety measures are implemented. Contractors Project Engineer shall be responsible for co-ordination and supervision of construction activities and construction groups and ensure that work is done as per specification and approved drawings and all safety measures are implemented.
1

2.1.2.

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works 2.1.3.

Rev. C

Contractors designated Site Engineer shall be supervising closely the activities designated to them and ensure that all instructions are followed and all necessary work permits are in place prior to commencing the work and safety procedures of the project is strictly adhered to

2.1.4.

Contractors Safety Manager is responsible for the enforcement of safety and ensures that the works are carried out in accordance with HDECs Health & Safety Management Plan.(refer to MD1-0-T-070-01-00023) Contractors QC Engineer is responsible for inspecting the reinforcement p rior to pouring concrete to check the quality of work as per specification and approved drawings.

2.1.5.

3.0 3.1

REFERENCE CODE & STANDARD

ACI 305 Placing concrete in hot weather The STG foundation concrete work is to be expected around from January to September. In consideration of weather condition in Vietnam, Standard of Hot weather concrete will be only applied. Employer Requirement Chapter 23.3 Concrete

3.2

4.0 4.1

MANPOWER & EQUIPMENT

Manpower The number of official is arranged as follows: - Head of the steering committee: - Vice head of the steering committee: - Steering committee engineering (engineer): - Surveying and supervisor (engineer): - In charge of work labor safety: 01 person 01 person 02 persons 05 persons 02 persons

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works

Rev. C

The number of direct labor as follows: No. 1 2 3 4 5


4.1.1

Craft or employee Foreman Rebar worker Carpenter Concrete worker Common worker

mobilization 2 35 20 15 10

Team leader To execute the massive concrete, the contractor arranges 02 Construction teams for direct construction. The personnel of each team consist of 01 team leader (engineer) and 02 technicians (engineers).

4.2

Equipment Based on estimated volume of work, approximately machine like under tabulation: The number of equipments and machines as follow:
No. 1 2 3 4 5 6 7 8 9 10 11 12 Equipment name Water pump Excavator, capacity Bend machine Cutting machine Welding machine Vibrator Automatic level Total station Mobile crane Pump car Mixed truck Flood Light
3

Spec./ capacity 15 m3/h(110 mm)

Mobilization plan 4 2 4 4 6 16 4 1 1 04 (01 backup) 16 100ea(Setting around STG )

bucket

0,6 m3 2,2 KW 5 KW 23 KW 2,2 KW Typical Typical 12 T 60m3/h 6m3 250w

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works

Rev. C

5.0 5.1

GENERAL Location & FDN Figure

TURBINE FOUNDATION PLAN

Please refer: Attach No# 1 - Turbine foundation Plan Please refer: Attach No# 2 - Turbine foundation Section
Estimated Quantity & Placing Time

A. Total Volumn 1) V=44M x 12.7M x 3.0M = 1678 2) V/4 Pump Cars 420 / 6 70 Mixed Trucks / Pump Car B. Estimated Placing Time 1) 70 Mixed Trucks x 13Minutes 910Minutes 15.17Hrs 2) 3.0M (Height) / 15.17Hrs 0.2M / hr (Placing Speed)

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works

Rev. C

Concrete Mixed Truck Access Road Map

Slump house

Please refer: Attach No# 3 Pump car location arrangement

6.0 6.1

WORK METHOD

Concrete Mix Control Use of ice, chiller water as part of mixing water is effective in reducing concrete temperature, because on melting alone, to absorb heat. In this case there is no change in the previous approved design mix.

6.2

Concrete Delivering Since the temperature rise can be increased with a passage of time thus the period between mixing and delivery will be kept to an absolute minimum. Attention will be given to coordinating and dispatching of the mixing trucks with the rate of placement to avoid delays in delivery. At Site all existing facilities, which are within the construction site radius considered to obstruct any work activities, will be removed or be provided with protection against damage, dust and dirt in mixed truck delivering.

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works

Rev. C

6.2.1 Planning

A pre-concreting meeting will be held internally and with concrete supplier to finalize all of the proposed concreting procedure in advance
6.2.2 Access

Designated site access routes for concrete supply will be prepared and traffic control measures implemented. The proper access must be organized to enable a continuous transportation of the concrete during the entire period of pouring so that the required temperature of concrete pour will be maintained.
6.2.3 Supply

Concrete batching plant capacity and numbers of delivery trucks will be planned earlier to maintain a continuous supply of concrete so as to prevent cold joint. In addition to minimize temperature differentials occurred within the concrete mass during pour.
6.2.4 Pouring

Concrete will be placed in a predetermined layering sequence ; Approximately 30~40 cm to avoid any possibility of cold joint formation within the foundation. It is approximately the time spent in each poured layer will be not exceeded 60 minutes.
6.2.4 Casting Sequence (Section Layers)

6.2.5 Plant and Labor

A detailed equipment and manpower resources schedule will be prepared to ensure sufficient workforce in each pour. In case of workers, considering estimated placing time, 2~3shift work is expected.
6

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works 6.3

Rev. C

Formwork Sufficient forms and suitable access platforms to execute the work for the entire pouring will be provided. At least 2 nos access way to evacuate in emergency will be installed around the TG foundation. Forms will be made of certified materials and include all necessary support bracings and fixings, steel props etc. The scaffolding access erected will be in compliance with local regulation. The form components are to be enough strong to support and resist to concrete lateral pressure. Basically, TG foundation will be installed and set by PERI system as following reference drawing. In assembling of PERI system material, the supervisor will be scheduled to be dispatched to fully supervise in Site. All relevant structural calculation will be certified by PERI specialist. Please refer: Attach No# 4 Peri system formwork
6.4

Reinforcement Work Rebar will be supplied and fixed in accordance with the approved construction drawings. Unless otherwise specified, the rebar passing required test in the specification shall be only used. Rebar will be cut and bent at the designated yard close to the work site in accordance with the approved drawing. shall be free from cracks or splits on bends. No reinforcement shall be bent down into position in the Works without approval whether or not it is partially embedded in the hardened concrete. Unless otherwise specified in the drawings, minimum cover to reinforcement shall be in accordance with specified in the approved drawing. Reinforcement shall be furnished in full splice length as shown on the approved drawings. Field welding of reinforcement shall not be permitted without the prior written consent or approval. Bars

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works 6.5

Rev. C

Concrete Work In addition in case of high temperature during the pouring day is encountered the pouring is preferred to be carried out during the night time. In case of sudden rain, plastic sheeting or canvas will be used to cover the concrete top surface yet to set during concrete pouring. The plastic sheets will be provided sufficiently both for emergency case of sudden rain and for fully cover the whole concrete surface immediately once the concrete is reached its initial set. In case of the heavy rain continues during construction, it will be provided that temporary framework by rigid rope with proper slope to cover whole area. If it is rains, immediately drafted with prepared plastic sheet.

Pre-pour inspection of the rebar, form panels, embedded items and construction joints will be carried out before concrete pouring. Four (4) concrete pumps and One(1) back-up pump will be engaged for concrete pouring e.g. 4 pumps is organized for concrete pouring; 1pump will be at the workface for standby and will be on duty when the pouring pump is trouble or breakdown. The concrete pump arrangement will be prior
8

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works

Rev. C

arrangement for their highest efficiency when the concrete placement is to be carried. Internal-type concrete vibrators will be used for concrete compaction during concrete placing to ensure adequate vibration keeping each 50cm distance during the entire pouring stage with sufficient Quantity.

6.6

Protection & Curing Mechanical disturbance of concrete during the specified curing period and damaged to finished concrete shall be prevented. After completing placing and finishing operations, efforts must continue to protect the concrete from high temperature, direct sunlight, low humidity and drying winds. If possible, the work should be kept in a uniformly moderate temperature condition to allow the concrete to develop its full strength potential. The concrete should also be protected against thermal-shrinkage cracking from rapid temperature drops, particularly during the first 24hours. The combined protection material as below will be used for curing purposes. This will be done immediately once the concrete is reached its stiffening time by fully cover the whole concrete surface onto the whole to prevent concrete temperature loss too quick and result high temperature differential between the surface and at the middle.

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works

Rev. C

Care must be taken during the entire curing (for two weeks) to ensure by reading its temperature by a thermocouple that the temperature at the middle of the concrete is low enough to result the difference of temperature in comparison

with the surface not exceed 20 C.

7.0
7.1

TEMPERATURE CONTROL Expecting Hydration Temperature The maximum temperature can be estimated by adiabatic temperature rise test. The adiabatic test conducted with actual concrete used for determining heat generation. The test was conducted at R & D Center of Hyundai E&C Corporation and all concrete components were delivered to the R & D Center from Mong Duong 1 Project Site in Vietnam to Korea. Concrete mix proportion based on approved trial mix is shown the following Table with expecting temperature.

10

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works

Rev. C

Adiabatic temperature properties were determined by laboratory testing and other thermal properties used for this analysis were provided from 2009 Korea Concrete Standard Specification. To find out the relationship between various curing methods and hydration heat characteristics of concrete, basically curing method and curing period were chosen as analyzing variables. There are many methods for controlling the temperature and moisture content of freshly placed concrete, but only moist curing, water ponding and insulation curing were considered in the analysis. -Input Parameter of Numerical Analysis

Input data Adiabatic Temperature change Thermal properties Increased temp. () Conductivity (W/m) Specific heat (J/kg)

Turbine Foundation 47.7 2.7 1,155

11

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works w/ steel form Moist curing Convection 2 (kJ/Km day) Water ponding Insulation curing (thickness 50 mm, Styrofoam) Unit weight (kg/m ) Compressive strength(Cube) Physical properties Coefficient of expansion Poissons ratio Ambient temperature ( ) Station: Cua Ong, Aug. 2011 Placement temperature ( )
3

Rev. C 1,200 690 431

172

2,470 35 Mpa at 28 days 10.0 x 10 0.20 29.9 7 27


-6

Temperature

Temperature analyses of the Turbine Foundation were carried out with different curing method and period. The following Table and graph below shows the results of temperature in relation to curing method and period. At the center of the foundation, the highest temperature appeared in 3~4 days. After the highest temperature was reached, the temperature decreased slowly. On the surface, the highest temperature was reached within 3 days and it gradually reduced to the ambient temperature.

12

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works

Rev. C

-Temperature Results with different curing method and period


Curing Method Curing Period (days) 3 5 Moist curing 7 10 14 3 5 Water ponding 7 10 14 3 5 Insulation curing 7 10 14 Max. Temp () Time to Max. Temp. (days) 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 3.4 Temperature difference ( ) 28.4 27.3 25.7 24.4 24.4 28.3 26.8 25.4 23.1 20.3 28.1 26.8 25.4 23.5 21.4 Time to Max. Temp. difference (days) 5.0 7.0 8.0 5.0 5.0 6.0 8.0 9.0 12.0 16.0 6.0 8.0 10.0 13.0 17.0

71.9 71.9 71.9 71.9 71.9 72.0 72.0 72.0 72.0 72.0 72.2 72.2 72.2 72.2 72.2

-Temperature Analysis Results of Moist-curing by ponding.


80.0 Center 70.0 60.0 Surfa ce Tempera ture difference

Temperature( )

50.0 40.0 30.0 20.0 10.0 0.0 0.0 5.0 10.0 15.0 20.0 25.0 30.0

Days

13

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works

Rev. C

Results of temperature analyses of the Turbine Foundation are further discussed below. The highest temperature occurred at the center of the foundation concrete even if the different curing method. On the surface, the highest temperature was reached within 3 days and it gradually reduced to the ambient temperature. The surface temperature is lower than the center temperature but also higher than the atmosphere temperature. The temperature difference between the surface and the center of the concrete comes out differently depends largely on curing method and curing period. When the whole curing ended, the surface temperature decreased rapidly then the temperature difference shows highest. So if the curing period is long enough to keep the surface temperature high then the temperature difference could keep low. The lowest temperature difference is almost at 20 when keeping 14 days of Moist-curing by ponding method. So the water ponding method could be the most suitable curing method for the field. In accordance with this recommendation, combined curing method like Clause 6.6 PROTECTION & CURING will be provided at Site. Up to 5~6 days from placing concrete, warm water would be used as curing water and from the date to 14days later , normal sweet water could be used. At the end of the curing period for 14days, the covering should be left in place without wetting for 2days so that the concrete surface will dry slowly and be less subject to surface shrinkage cracking.

7.2

Test and Monitoring of the Concrete Mass after Placing To ensure that the temperature differential will be controlled a set of measuring apparatus will be set as shown by the below sketch. The measurement purposes are to finding the temperature development within the concrete mass. The results will show peak temperature and the temperature differential for such measuring points. Sets of thermocouples will be installed and embedded to the concrete at the bottom, middle and top e.g. top and bottom sets will be approximately 50 cm of measuring from the edges. The heat generated will be converted to the circuit and sent to the data logger which will record and show information of
14

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works

Rev. C

temperature measure. The maximum temperature of mass concrete will peak at 3.4days after placing of concrete and will be constant for 7 days and will decrease to the air temperature after 14 days.

7.3

Form Removal and Inspection Removal of forms is only carried out when concrete meets the required strength and avoid causing sudden stress or crack to affect to the concrete structure. After 16days from placing, the forms can be removed with shoring. After form removal, concrete surface shall be investigated and notify the Employer to
15

TWO(2) X 500MW Mong Duong 1 Thermal Power Plant Method statement for STG Foundation Concrete Works

Rev. C

inspect. In addition, form tie holes can be filled and any necessary repairs made by uncovering a small portion of the concrete at a time to carry on this work with approved materials. These repairs should be completed in the first few days after stripping so the repairs and tie-hole fillings can cure with the surrounding concrete.

8.0

SAFETY CONTROL AT SITE One of the main aspects of this procedure is Safety and Health Control. This is to control occurrence of injuries as well as damage to equipment and properties during the entire execution period. In order to ensure a safe working environment during the entire execution period, the following safety measures will be implemented as follows:

8.1

Machinery and Equipment Prior to using any machinerys/equipment at site, it will be inspected and certified by qualified person. Periodic Preventive Maintenance will be made on all equipment and machineries. All operators and drivers are to be equipped with valid drivers/operators license or permit from concerned government agency. Only authorized drivers or operators will be allowed to operate machineries or equipment. Only authorized signalman will be assigned together with the operator or driver. All lifting equipment as well as its accessories such as sling wire, nylon sling, shackles, chain blocks crane hook and latch shall be inspected periodically.

8.2

Personal Protective Equipment Personal Protective Equipment (PPE) will be issued to all workers such as safety shoes, hardhat, working gloves, earplug, safety goggles (if required) and safety harness for workers who will be assigned in elevated places 1.6 meter and above. Wearing of the basic PPE will be enforced fully. All new recruits will undergo proper orientation and safety induction before they could be deployed at site for work.

16

HYUNDAI ENGINEERING CONSTRUCTION CO., LTD Mong Duong 1 Thermal Power Plant Project

8.3

Job Safety Analysis


JOB SAFETY ANALYSIS (JSA)
JSA is a task planning, hazard identification and risk management programme

SECTION A : GENERAL INFORMATION Project : Mong Duong 1 Thermal Power Plant Project Location : STG Foundation Job Description Permit No : Emergency Contact No : 033-3962-320 Stop Work Conditions : (Tick as appropriate)
Adjacent Work Hazards Change in Conditions Pollutant Spills/Releases

Section : ARCHITECTURE

REBAR & FORM WORKS, CONCRETING Specific Training Required : TRAINED WORKERS Assembly Point : COMO MUSTER POINT

Extreme Weather Fires & Explosions Unusual Odors

Excessive Noise Excessive Dust Evacuation Alarm

SECTION B : TASK PLANNING - HAZARD IDENTIFICATION AND CONTROLS Task Steps


1. GENERAL

Potential Hazards
- MOVING EQUIPMENT HAZARDS - OCCURRENCE OF DUST - HEAT AND STRESS - SLIPS AND TRIPS

Mitigation Controls
- OBTAIN WORK PERMIT PRIOR TO START WORK AND CONDITIONS OF PERMIT MUST BE FOLLOWED - PROVIDE HIGH VISIBILITY VEST - WEARING OF APPROPRIATE PPE - TOOL BOX MEETING REQUIRED PRIOR TO START THE WORK - HOUSEKEEPING AND PROPER PILING OF MATERIALS\ - BRIEFING OF WORKERS PRIOR TO COMMENCE WORK - PROVIDE SUFFICIENT LIGHTING - PRE SITE DEPLOYMENT/SAFETY - INDUCTION TO ALL NEW WORKERS - FIRST AID AND EMERGENCY RESPONSE PROCEDURE - TRAINING FOR PROPER HANDLING OF TOOLS AND EQUIPMENT - SAFETY TALK CONFIRM AND UNDERSTAND THEM - LOCATE PINCH POINTS AND AVOID PINCH POINT/CAUGHT IN BETWEEN - ONLY COMPETENT PERSON TO DO ENTIRE ACTIVITY - USE PROPER/REQUIRED PPE - COMPETENTET PERSON TO SUPERVISE ENTIRE ACTIVITY

Responsible Party
PROJECT MANAGER : Mr. BUI VAN GIANG MOB NO. : 0977292595 SAFETY MANAGER : Mr. VU VAN NAM MOB NO. : 0904953675

2. DETOUR 3. MOBILIZATION OF MEN AND EQUIPMENT

4. TOOL BOX MEETING


5. REBAR & FORM WORKS - MOBILISING THE REQUIRED SHUTTERING MATERIALS - PROVIDE ACCESS TO THE WORK AREA - FIXING OF SHUTTERS - DISMANTLING THE SHUTTER - DEMOBILISATION OFSHUTTERS

- IMPROPER LOCATION OF WARNING SIGN - POOR ILLUMINATION - LACK OF KNOWLEDGE ABOUT THE JOB - MISCOMMUNICATION(LANGUAGE BARRIEER) - SLIP AND TRIP HAZARD - IMPROPER USE AND TOOLS AND EQUIPMENT - PEOPLE NOT FAMILIAR IN THEIR JOB AND HAZARD INVOLVED 1. CUTS FROM PINCH POINTS.

2. FIRE HAZARDS.

- PROVIDE FIRE EXTINGUISHER - PROVIDE PROPER WARNING SIGNAGE - PROPER ARRANGEMENT OF MATERIALS/KEEP AWAY FROM FIRE - DO NOT STORE FLAMABLE MATERIALS AT WORK SITE

3. ELECTRICAL SHOCK.

- USE PROPER PPE/REQUIRED PPE - PROVIDE PROPER CABLE MANAGEMENT - DO NOT USE DAMAGED OR JOINTED CABLE - ONLY COMPETENT PERSON TO DO ENTIRE ACTIVITY

4. SLIPS TRIPS AND FALLS

- GOOD HOUSEKEEPING AND PROPER PILING OF MATERIALS - PROVIDE PROPER WORKING PLATFORM - PROVIDE PROPER ACCESS PRIOR TO START WORK - FIX HANDRAILS AROUND THE PLATFORM - FOLLOW 100% TIE OFF

5. CUT INJURY DUE TO MISUSE OF TOOLS

- USE APPROPRIATE TOOLS ONLY - USE PROPER/REQUIRED PPE - ONLY COMPETENT PERSON TO DIO ENTIRE ACTIVITY - PROPER SUPERVISION AND TRIANED WORKERS

6. FALL FROM HEIGHT

- USE SAFETY HARNESS WHILE WORKING AT HEIGHT - PROVIDE PROPER ACCESS AND PLATFORM PRIOR TO START WORK - USE OF PROPER PPE - ENSURE PROPER SUPERVISION - ADOPT PROPER MANUAL HANDLING PRACTICE - AVOID CARRYING MATERIALS MANUALLY TO THE HEIGHT - PROPER SUPERVISION AND TRAINED WORKERS - USE MECHANICAL HELP FOR LIFTING MATERIALS WHENEVER POSSIBLE - USE PROPER/REQUIRED PPE - ONLY COMPETENT PERSON TO DO ENTIRE ACTIVITY - GUARDS SHOULD BE IN PLACE - PROPER SUPERVISION AND TRAINED WORKERS

7. POOR MANUAL HANDLING TECHNIQUE

8. CUT INJURY DUE TO ROTATING POINTS

6. CONCRETING - POSITIONING THE PUMP CAR - TRANSPORTING THE CONCRETE MIXER TRUCK - POURING THE CONCRETE - VIBRATING AND FINISHING WORK

1. DUST NUISANCE

- USE DUST MASK OR SUITABLE PPE - ADOPT PROPER DUST CONTROL MEASURES - PROPER SUPERVISION AT ALL TIMES - ONLY COMPETENT PERSON SHOULD DO ENIRE ACTIVITY - PROVIDE PROTECTIVE GUARDS FOR ALL ROTATING POINTS - PROVIDE FACE SHIELD OR REQUIRED PPE

2. CUT INJURY FROM ROTATING POINTS

3. ELECTRICAL SHOCK

- INSPECT ALL ELECTRICAL EQUIPMENT PRIOR TO START WORK - PROVIDE FIRE EXTINGUISHER - USE PROPER PPE/HAND GLOVES - DO NOT USE DAMAGED OR JOINTED CABLES - ONLY COMPETENT PERSON TO DO ENTIRE ACTIVITY - PROVIDE FIRE EXTINGUISHER - PROVIDE PROPER WARNING SIGNAGE - KEEP MATERIALS AWAY FROM FIRE - PROPER SUPERVISION

4. FIRE HAZARD

5. HEAVY RAIN

- PROVIDE TEMPORARY FRAME AND PLASTIC SHEET - PROVIDE SUMP PIT AND PUMP AROUND WORKING AREA - COVER WITH PLASTIC SHEET WHOLE CONCRETE SURFACE - STANDBY SUPERVISOR AND WORKER - STANDBY SAFETY ENGINEER AND AMBULANCE - PROVIDE ADDITIONAL BATCH PLANT - PROVIDE ENOUGH MIXER TRUCK - PREVENTION SUPPLY OF CONCRETE TO OTHER PLACE - STANDBY QA/QC ENGINEER - REJECT MIXER TRUCK IF FAIL OF SLUMP - PROVIDE ADDITIONAL BATCH PLANT

6. FAILURE OF FALSEWORK/FORMWORK 7. RACK OF CONCRETE

8. FAIL OF SLUMP

HYUNDAI ENGINEERING CONSTRUCTION CO., LTD Mong Duong 1 Thermal Power Plant Project

9. POOR ILLUMINATION AT NIGHT WORKS 10. PANIC IN CASE OF EMERGENCY

- PROVIDE SUFFICIENT LIGHTING - STANDBY ELECTRICAL ENGINEER - CONDUCT PRE JOB TALK & DISCUSS FOR EMERGENCY - STANDBY DOCTOR & AMBULANCE - FOLLOW EMERGENCY ROUTE AND PLAN - PRESTART CHECKLIST FOR EQUIPMENT PRIOR TO WORK - INSPECT THE EQUIPMENT PRIOR TO START WORK - DETAILING OF BAKSMAN/SIGNALMAN - OPERATOR AND EQUIPMENT SHOLD HAVE THIRD PATY CERTIFICCATE - OPERATOR MUST HAVE QATARI LICENSE - PROPER USE OF PPE - GOOD COMMUNICATION WITH OPERATOR AND SIGNALMAN/BANKSMAN - ASSIGN COMPETENT WORKERS ONLY - BARRICADE IF REQUIRED - NO LOOSE / UNSECURED MATERIALS ALLOWED AT HEIGHT - ENCLOSURE AREA BELOW WITH PERIMETER WARNING (RED / (RED/ WHITE) BARRICADE - PROVIDE WARNING SIGNS - HAND TOOLS BEING USED E.G. WRENCHES ETC TO BE STRING SECURED - SECURE FLOOR GRATINGS WHEN TEMPORARILY REMOVED. INSTALL RIGID BARRIER AROUND FLOOR OPENINGS, HOLES AND LEADING EDGES OF INCOMPLETE STRUCTURE

7. USE OF MOBILE EQUIPMENT

1. EQUIPMENT COLLAPSE 2. HYDRAULIC FAILURE 3. INTERFACE MAN/EQUIPMENT 4. VEHICLE ACCIDENT

8. WORKING AT HEIGHT ON SCAFFOLD

1. HAZARDS FROM FALLING OBJECTS TO PERSONNEL / EQUIPMENT BELOW 2. FALL HAZARDS TO PERSONNEL WORKING AT 3. UNDUARDED FLOOR OPENINGS / EDGE OF STRUCTURES 4. UNSECURED MATERIALS 5. INCOMPLETE ACCESS STAIRS

6. EXPOSED UNPROTECTED HOLES 7. LOOSE GRATINGS / HANDRAILS / STEPS

- LOWERING / RAISING OF TOOLS TO BE BY ROPE / BUCKET. THROWING PROHIBITED. - NO CROSSING INTO BARRICADED AREA. - MAINTAIN GOOD HOUSEKEEPING AT ELEVATED WORK PLATFORM - ROPE GRAB AT LADDERS DURING STRUCTURAL ERECTION REQUIRED(100% TIE-OFF) - BODY HARNESS HOOK AT ALL TIMES AT UNPROTECTED ELEVATED LOCATIONS. - PROVIDE ADEQUATE SUPERVISION AT ALL TIMES - DO NOT USE SCAFFOLD WITHOUT SCAFFTAG

Mandatory PPE The following is the minimum required Hard Hat Safety Boots or Shoes High Visiblity Jacket/Vest Safety Glasses/Goggles Safety Gloves (Isolate) SECTION C : RESPONSIBILITY ENGINEER : HSE Review by : HSE Review by :

Additional PPE FACE MASK FACE SHIELD SAFETY HARNESS

Tools and equipment - GENERATOR, WATER TANKER - TROWEL - FLOAT& HAND TOOLS - CONCRETE PUMP, OTHER ACCESSORIES - MIXER TRUCK - ELECTRICAL OPERATED GRINDERS, CUTTING MACHINE - VIBRATOR - BENDING MACHINE, CUTTING MACHINE - SCAFFOLDING, FIRE EXTINGUISHER

Date : 2012.10. Date : 2012.10. Date : 2012.10.

Signature : Signature : Signature :