Present status of Work Front Date: 22-04-14 S.

No 1 2 3 4 5 6 7 Observation Points GIS Floor U-3 Bus Duct U-4 Bus Duct U-5 Bus Duct U-6 Bus Duct 400KV XLPE cable support Unit - 1 Target Date Handed over (Two bays) Handed Over Handed Over Handed Over Handed Over 3/20/2014 Handed Over Handed Over (inside barrel) 4/30/2014 4/30/2014 Handed Over (inside barrel) Responsibilities CPL/Andritz Andritz Andritz Andritz Andritz Andritz Andritz Status 1) Bracing welding is in progress. 6 sets completed out of 8. 2)1no Girder joint completed of 10T EOT crane. 6 nos rail lifted. Scaffolding for erecting bus ducts from 11th & 12th elements completed on 15-04-14. No work on 16-04-14 due to manpower shortage. No work due to man power shortage. Painting of welded joints is in progress. Enclosure welding between MW2 & MW3 completed and between MW3 & MW4 is in progress. AHPL has given information that cable supports will be reaching site by 10th of Feb. No further information. 1) Cable tray erection for Excitation panel is in progress. 2) Main header to cooler trial assembly & tacking completed inside barrel. remove point 4 3) 80 NB Pipeline works from Accumulator station to OPU completed. 1) Stator centering is in progress. 2) MIV concreting works withheld due to non availability of base plate. 3) Scaffolding is in progress from cooling water sump for cable tray erection. 1) Slab shuttering works is in progress. Handed over for Upper bracket sole plate erection. Slab staging removal is in progress. 1) Grinding of fitting flange is in progress. 5 nos completed out of 10. 1) Removal of screen protection from screened cables is in progress in Generator marshalling box & UCB is in progress. 2) Cable termination is in progress in UAB. 3) Cable glanding is in progress in UCB. 4) Angles fixed in the neutral side cut out outside the barrel. Neutral side element (N-EL-1) shifted. 5) Lower bearing housing and Bearing housing bottom plate erection completed. 6) Aeration housing erection is in progress. Remove point 5 7) Air coolers are being shifted & cleaned. Compensator fixing and trial checking is in progress for D & D pipeline. Pipeline assembly work is in progress. 13 bay handed over. 1) One blast taken for GT3 foundation excavation. 1) GT #2 tower erection is in progress.Bracing fixing is in progress. Present height of tower is 22.5m. 1) Cable glanding is in progress in Unit protection panel - 2 2) Gland plate fixed in Unit protection panel - 1. 6 cables laid from DC DB-2 to unit protection panel 1,2 & 3 Scaffolding is in progress for cable tray erection from EL 777.90 to EL 770.50 No work. Rotor #2: Pole lead connection to Item #6 & 7 completed. Final lead connection trial assembly is in progress. Rotor #3: Tangential key fixing is in progress. Stator #4: 1st intermediate pressing completed. Upper bracket-U#1: Cleaning of thrust bearing platform completed. Pivot & spring plate cleaning is in progress. Stator #5: Stator intermediate sole plate blue matching completed. Fire fighting pipeline welding work is in progress in CAT. 7 No's pipe joint root welding completed.

8 9 10 11

Unit - 2 Unit-3 (EL 777.90 slab completion) Unit-4 (EL 777.90 slab completion) Unit-5 (EL 777.90 Slab completed)

AHPL CPL CPL AHPL/AIPL

12

Unit-6

3/31/2014

Andritz

13 14 15 16 17 18 19 20 21

Unit-6 (MIV) U-6 heat exchanger Balance GT foundation Pothead yard Civil Work Pothead yard EBOP Work Control block Floor (EL 783.00) Control Block Floor (EL 777.90) Control Block Floor (EL 770.50) Control Block Floor (EL 764.80)

Handed Over 3/15/2014 4/30/2014 3/31/2014 4/15/2014 Handed Over Handed Over Handed Over Handed Over 07-04-14

Andritz CPL AIPL/Andritz AIPL Andritz AHPL/AIPL Andritz Andritz Andritz

22

Service Bay Jobs

4/16/2014 4/14/2014

Andritz

23 24

Fire Fighting system Storage

Andritz Andritz