DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPOSITOS DE RELAVES SAN JUAN DE AREQUIPA
Mayo 2009
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
(INFORME FINAL) NDICE RESUMEN EJECUTIVO 1 INTRODUCCIN ....................................................................................................... 1
1.1 1.2 1.3 1.4 1.5 ANTECEDENTES .............................................................................................................................. 1 OBJETIVO ........................................................................................................................................ 1 INFORMACIN DISPONIBLE ............................................................................................................. 1 UBICACIN Y ACCESO..................................................................................................................... 2 CRITERIOS DE DISEO ..................................................................................................................... 2
Proyecto 1-M-373-002
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
10
Proyecto 1-M-373-002
ii
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
ANEXOS
1. Perfiles Estratigrficos de Sondeos A.- Registro de Calicatas B.- Registro de Perforaciones con Sistema Wash Boring y Ensayos SPT 2. 3. Piezmetros de Tubo Abierto Ensayos de Laboratorio de Mecnica de Suelos A.- Campaa realizada por SVS B.- Campaa realizada por ACOMISA 4. 5. Anlisis de Estabilidad Fsica Anlisis Hidrolgico y Diseo Hidrulico A.- Clculos Hidrolgicos B.- Clculos Hidrulicos Morfolgicos C.- Clculos de Obras de Proteccin 6. 7. 8. 9. 10. Especificaciones Tcnicas de Construccin Metrados de Obra Presupuesto de Obra Cronograma de Ejecucin de Obra Archivo Fotogrfico
Proyecto 1-M-373-002
iii
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
PLANOS
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. Ubicacin del Proyecto Levantamiento Topogrfico y Ubicacin de Sondeos Geologa de Superficie Seccin Geolgica Geotcnica 1-1 Seccin Geolgica Geotcnica 2-2 Seccin Geolgica Geotcnica 3-3 Seccin Geolgica Geotcnica 4-4 Ubicacin de Cuencas Arreglo General del Proyecto - Planta Arreglo General del Proyecto: Corte A-A, Corte B-B y Corte C-C Arreglo General del Proyecto: Corte D-D y Corte E-E Defensa Riberea: Planta Defensa Riberea: Perfil Longitudinal Defensa Riberea: Seccin Tpica Defensa Riberea: Secciones Transversales 0+000 1+160 Defensa Riberea: Secciones Transversales 1+180 1+190.67 Ubicacin de Canteras Cantera N 1: Perfil Longitudinal Cantera N 1: Secciones Transversales 0+200 1+250 Cantera N 1: Secciones Transversales 1+300 2+026.9 Instrumentacin de Monitoreo Ubicacin y Detalles
Proyecto 1-M-373-002
iv
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
RESUMEN EJECUTIVO
La empresa Century Mining Per S.A.C., subsidiaria de la canadiense Century Mining Corporacin desarrolla sus operaciones en la Unidad de Produccin San Juan de Arequipa, donde cuenta con una Planta de beneficio para tratamiento de mineral aurfero por flotacin y cianuracin, producindose relaves que son transportados y depositados en los depsitos de relave 1, 2, 3, 4 y 5 y la poza de cianuracin respectivamente, los mismos que se ubican en la margen derecha de la quebrada de Chorunga, dispuestos en forma contigua, separados por diques del mismo material de relave y a diferentes cotas de cresta. Actualmente, Century Mining Per S.A.C. requiere aumentar la capacidad de almacenamiento de sus depsitos de relave de flotacin y protegerlos ante una avenida mxima probable del ro estacionario Chorunga, para lo cual ha solicitado a la empresa consultora SVS Ingenieros S.A.C. (SVS) el desarrollo del Estudio de Ingeniera de Detalle para el Recrecimiento y Defensa Riberea de los Depsitos de Relave San Juan de Arequipa, el cual debiendo preservar el medio ambiente circundante, resulte tcnica y econmicamente viable. La Unidad de Produccin San Juan de Arequipa se encuentra ubicado en el casero de San Juan de Arequipa, distrito de Ro Grande, provincia de Condesuyos, departamento de Arequipa. Los Depsitos de Relaves 1, 2, 3, 4 y 5 se encuentran entre las coordenadas UTM E 707,700.00 N 8239,500.00 y E 708,500.00 N 8240,500.00, a una altitud media de 680 m.s.n.m. La metodologa de trabajo del presente proyecto consisti en una primera fase de recopilacin de la informacin existente, seguida de una campaa de investigaciones de campo y finalmente la ejecucin de los diseos de recrecimiento y defensa riberea. Durante la campaa de investigaciones de campo se realizaron trabajos de levantamiento topogrfico de detalle, el mapeo geolgico-geotcnico de superficie y la exploracin geotcnica del subsuelo que incluy la ejecucin de perforaciones mediante el mtodo Wash Boring (mtodo por lavado) que alcanzaron 12.2 m de profundidad, la excavacin de calicatas hasta 3.0 m de profundidad, as como la ejecucin de ensayos de densidad in-situ. Asimismo, se instalaron tres piezmetros de tipo Casagrande para determinar la profundidad del nivel fretico en el depsito de relaves. El depsito de relaves se encuentra ubicado en la margen derecha del ro estacional Chorunga ocupando un rea de 26.6 has, sobre un gran depsito aluvial constituido predominantemente por una grava arenosa con boloneras y debajo de mismo se encuentra el basamento rocoso granodioritico que aflora en la ladera del cerro aledao. Los relaves
Proyecto 1-M-373-002 SVS INGENIEROS S.A.C.
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
estn constituidos por un material limo arcilloso ligeramente arenoso a arena limosa ligeramente arcillosa. Tras la evaluacin del peligro ssmico se estimo que la ubicacin del proyecto corresponde a una zona de alta sismicidad, donde se estim que la aceleracin ssmica mxima que podra presentarse para un sismo con periodo de retorno de 500 aos y una probabilidad de excedencia de 10% en 50 aos de exposicin asciende a 0.46g (g=aceleracin de la gravedad). El balance de agua fue realizado en la Cancha N 2, que representa la condicin ms desfavorable desde el punto de vista de balance de agua, evalundose los ingresos y salidas de agua. En vista que el aporte de agua por precipitacin es nula slo el agua que viene junto al relave fue considerado como ingreso. Sin embargo las salidas identificadas por la evaporacin, infiltracin y agua atrapada en los poros del relave. Tras el clculo de caudales de agua de ingreso, menos la evaporacin y el agua atrapada en los poros, se estim que el agua de infiltracin referencial estara en el orden de 824 a 911 m3/dia. El proyecto de recrecimiento plantea el transporte del relave de flotacin desde la planta concentradora hacia los depsitos de relaves mediante una tubera HDPE, en tanto que la descarga de relaves se efectuar desde la cresta de los diques perimetrales hacia la ladera del cerro, por un sistema de tuberas tipo Spigot, para aprovechar la segregacin de los relaves y as disponer las partculas ms gruesas en los diques perimetrales de los depsitos de relaves y mantener el agua de pondaje siempre alejado del dique perimetral, disminuyendo el riesgo de inestabilidad por tubificacin y licuacin. Manteniendo siempre la disposicin por celdas temporales para aprovechar la alta evaporacin de la zona. En los grficos siguientes se muestran la seccin tpica y la planta del arreglo general del recrecimiento del depsito de relaves San Juan de Arequipa.
Proyecto 1-M-373-002
vi
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Proyecto 1-M-373-002
vii
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
En recrecimiento del depsito de relaves a partir de la cresta del dique de defensa riberea se realizar con un talud de 2.5(H):1.0(V) hasta alcanzar las cotas de mxima elevacin del recrecimiento descritas a continuacin:
Cota de cresta (cancha de relave N 1): Cota de cresta (cancha de relave N 2): Cota de cresta (cancha de relave N 3): Cota de cresta (cancha de relave N 4): Cota de cresta (cancha de relave N 5):
680 msnm 685 msnm 690 msnm 795 msnm 700 msnm
En todos los casos se deber mantener una distancia mnima desde la cresta del talud hasta el borde al agua de pondaje igual a 20 m. Se recomienda continuar con el ciclo de disposicin del relave en forma de celdas o canchas temporales, es decir una vez colmatado un depsito se paralizar el ingreso de relave cerrando la tubera de conduccin a la altura de este depsito, para luego utilizar la cancha contigua y as sucesivamente hasta llegar al ltimo depsito. Una vez colmatado el ltimo depsito, nuevamente se iniciar el ciclo de disposicin de relave. Con las caractersticas del proyecto de recrecimiento planteadas en los anteriores prrafos, se estim que el volumen de almacenamiento de relaves asciende a 0.924 Mm3 de relave, que para una tasa de produccin de 350 tn/da se estim una vida til de 11.7 aos. Con la finalidad de garantizar la estabilidad fsica de los depsitos de relaves y con el propsito de evitar la erosin de stos depsitos como consecuencia de avenidas extraordinarias de la quebrada de Chorunga, se dise una estructura de defensa riberea que tendr el doble propsito de actuar como contrafuerte a fin de poder cumplir con los valores mnimos de FS que recomienda el MEM y como estructura que evite la erosin de los depsitos de relaves. La proteccin riberea de los depsitos de relaves consiste en la construccin de un dique compactado con material extrado del lecho del ro aledao, cuyos taludes laterales sern de 1.5H/1.0V. Debido a la escasa velocidad del flujo, ante la ocurrencia de un evento extraordinario un enrocado resulta apropiado para el revestimiento del talud externo. El revestimiento con enrocado consistira de roca dura y durable, deber tener un espesor de 0.60 m. As mismo en el lecho del ro, adyacente al revestimiento de enrocado, se colocara una capa de proteccin de 3.50 m de ancho y 0.6 m de espesor. La interface talud revestimiento, estara provista de un manto geotextil que impida la migracin de las partculas finas del talud. El material rocoso empleado para la construccin del enrocado deber cumplir la gradacin indicada en el cuadro siguiente:
Proyecto 1-M-373-002 SVS INGENIEROS S.A.C.
viii
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
D100
Max. Min. Max.
D50
Min. Max.
D20
Min.
0.50
0.35
0.30
0.25
0.25
0.20
El Costo directo para la construccin de la estructura de defensa riberea asciende a novecientos ochenta y ocho mil setecientos cincuenta y cinco y 96/100 dlares americanos (US$ 988,755.96). Se ha sumido un porcentaje de Gastos Generales (GG) de 25% distribuidos en 20% de GG Variables y 5% de GG Fijos, ms una utilidad del 10% para el contratista de obra, considerando adems el 19% del Impuesto General a la Ventas el Presupuesto final para la ejecucin de la Obra alcanza a un milln quinientos ochenta y ocho mil cuatrocientos sesenta y ocho y 58/100 dlares americanos (US$ 1588,468.58), el mismo que podr ser construido en 6 meses calendario, dividida en dos etapas de 3 meses cada uno, la primera etapa consistir para una altura de tirante de 100 aos de periodo de retorno y la segunda etapa para 500 aos de periodo de retorno. En el Cuadro siguiente se muestra el Presupuesto referencial para a la construccin de la Defensa Riberea.
Proyecto 1-M-373-002
ix
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
1 INTRODUCCIN
1.1 ANTECEDENTES
La empresa Century Mining Per S.A.C., subsidiaria de la canadiense Century Mining Corporacin desarrolla sus operaciones en la Unidad de Produccin San Juan de Arequipa, donde cuenta con una Planta de beneficio para tratamiento de mineral aurfero por flotacin y cianuracin, producindose relaves que son transportados y depositados en los depsitos de relave 1, 2, 3, 4 y 5 y la poza de cianuracin respectivamente, los mismos que se ubican en la margen derecha de la quebrada de Chorunga, dispuestos en forma contigua, separados por diques del mismo material de relave y a diferentes cotas de cresta. Actualmente, Century Mining Per S.A.C. requiere aumentar la capacidad de almacenamiento de sus depsitos de relave de flotacin y protegerlos ante una avenida mxima probable del ro estacionario Chorunga, para lo cual ha solicitado a la empresa consultora SVS Ingenieros S.A.C. (SVS) el desarrollo del Estudio de Ingeniera de Detalle para el Recrecimiento y Defensa Riberea de los Depsitos de Relave San Juan de Arequipa, el cual debiendo preservar el medio ambiente circundante, resulte tcnica y econmicamente viable.
1.2 OBJETIVO
El objetivo de este informe es elaborar el Diseo de Recrecimiento y Defensa Riberea de los Depsitos de Relave San Juan de Arequipa, el mismo que contemplar una evaluacin geolgica-geotcnica de la cimentacin, caracterizacin del material de relave, diseo del recrecimiento de los depsitos de relave y el diseo de las obras hidrulicas de proteccin o defensa riberea a nivel de construccin.
y Medio Ambiente Unidad de Produccin San Juan de Arequipa, ACOMISA, Julio del 2008.
Verificacin de la Estabilidad y Diseo Conceptual de las Obras de Defensa
Riberea de los Depsitos de Relaves San Juan de Chorunga, SVS Ingenieros S.A.C., Febrero del 2009.
Proyecto 1-M-373-002
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Volumen de agua de pulpa que se descarga al 1480 m3/d depsito Densidad promedio de relave in-situ Gravedad especfica de los relaves Ciclo de operacin de la planta concentradora 1.55 t/m3 2.6 g/cm3 24 h/d y 350 d/ao
Capacidad de almacenamiento del proyecto de 0.924 Mm3 recrecimiento Vida til de los depsitos B. Manejo de aguas
El relave ser transportado mediante tuberas HDPE, por gravedad hasta cada uno
7.4 aos
Proyecto 1-M-373-002
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
pegado hacia la ladera del cerro y alejado con un mnimo de 20 m de la cresta de recrecimiento.
El agua del relave una vez decantada en el depsito, ser captada y evacuada por un
sistema de conduccin y riego hacia los depsitos adyacentes para favorecer la evaporacin y humedecer la superficie de los mismos disminuyendo el transporte de los relaves debido a los vientos. C. Estabilidad fsica de los depsitos de relave
Factor de seguridad para condiciones estticas: Factor de seguridad para condiciones pseudo-estticas:
1.50 1.20
D. Diseo ssmico
Aceleracin ssmica mxima (periodo de retorno de 500 aos): Aceleracin ssmica de diseo:
0.46g 0.23g
Proyecto 1-M-373-002
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
2.1 TOPOGRAFA
Este trabajo fue realizado por una brigada de topografa de SVS, durante el mes de marzo del 2009, la misma que estuvo conformada por un topgrafo y asistentes provistos de una estacin total con sus respectivos accesorios. Para ello el levantamiento fue referido a coordenadas UTM, proporcionadas por Century Mining Per S.A.C. El levantamiento topogrfico de detalle fue efectuado cubriendo una extensin aproximada de 98.0 hectreas, lo cual comprendi el registro de 4,400 puntos del terreno y cubri el sector donde se emplaza actualmente los depsitos de relaves 1, 2, 3, 4 y 5, as como el cauce del ro Chorunga. Para el procesamiento de la base de datos obtenidos mediante la estacin total, se emple el programa Land Development, en su mdulo para levantamientos topogrficos, en tanto que la representacin grfica del cuadrillado de coordenadas y de los puntos del levantamiento se efectu mediante el programa AutoCad. En el Plano 2, se presenta el levantamiento topogrfico de la zona de estudio, el cual ha sido elaborado a escala 1/5,000, con curvas de nivel equidistantes a cada 1 m.
2.2 GEOTECNIA
El programa de investigacin geotcnica comprendi la ejecucin de cuatro (04) perforaciones con el sistema Wash Boring (perforacin por lavado), complementados con ensayos de penetracin estndar (SPT), con las cuales se alcanzaron profundidades entre 6.35 m y 12.20 m con respecto a la superficie del terreno, registrndose el perfil estratigrfico de los depsitos de relaves. Dichos sondeos se ubicaron en la parte superior de los taludes de los depsitos de relaves N 1, 2 y 4. En el Anexo 1b, se muestra el perfil estratigrfico de dichos sondeos. En tres de estas perforaciones se instal piezmetros de tubo abierto (tipo Casagrande) con la finalidad de monitorear el comportamiento del nivel fretico dentro del cuerpo de los depsitos de relaves (ver Anexo 2).
Proyecto 1-M-373-002
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
El programa de investigacin geotcnica comprendi tambin la ejecucin de siete (07) excavaciones manuales (calicatas), cuatro (04) de ellas ubicados dentro del cauce del ro Chorunga con la finalidad de determinar la granulometra del material del lecho, y el resto de calicatas se efectuaron junto a las perforaciones para realizar pruebas de densidad insitu mediante el mtodo del cono de arena (ASTM D-1556), espaciados cada 1.0 m en profundidad, los mismos que se presentan en el Anexo 1a. En el cuadro siguiente se indican las coordenadas de ubicacin y las profundidades alcanzadas por cada uno de dichos sondeos. Cuadro 2.1: Ubicacin de Calicatas y Perforaciones con el sistema Wash Boring
Sondeo C-1 C-2 C-3 C-4 CR-1 CR-2 CR-3 P-1 P-2 P-3 P-4 Tipo Calicata Calicata Calicata Calicata Calicata Calicata Calicata Perf. Wash Boring Perf. Wash Boring Perf. Wash Boring Perf. Wash Boring Coordenadas UTM Este (m) 708,368.194 708,162.870 707,822.251 707,504.784 707,230.978 707,414.361 707,509.283 707,216.588 707,403.739 707,494.322 707,956.467 Norte (m) 8'240,260.077 8'240,060.996 8'239,910.109 8'239,684.225 8239590.506 8239704.726 8239737.276 8'239,594.948 8'239,708.391 8'239,732.057 8'240,031.570 Profundidad (m) 2.80 2.60 2.40 2.90 3.00 3.00 3.00 6.35 12.20 9.20 9.00
En todas las calicatas y en las perforaciones ejecutadas se registr cuidadosamente el perfil estratigrfico del terreno, clasificndose visualmente los materiales encontrados, de acuerdo a los procedimientos del Sistema Unificado de Clasificacin de Suelos (SUCS), obtenindose muestras alteradas representativas, las mismas que debidamente protegidas e identificadas, fueron remitidas al laboratorio para sus respectivos anlisis y ensayos. En el Anexo 1 se presentan los perfiles estratigrficos correspondientes a las calicatas y a las perforaciones con el sistema Wash Boring y en el Planos 3 al 7 se muestra la ubicacin de dichos sondeos. Los resultados de los ensayos de auscultacin dinmica del tipo SPT, servirn para estimar los parmetros de resistencia del suelo.
Proyecto 1-M-373-002
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
El detalle de los resultados obtenidos en los diferentes ensayos de laboratorio se muestra en el Anexo 3a. Luego de realizados los ensayos de laboratorio, se procedi a comparar los resultados obtenidos con las caractersticas de los suelos estimados en el campo, efectundose las compatibilizaciones correspondientes en los casos en que fue necesario. De esta manera se obtuvieron los perfiles estratigrficos definitivos, que son los que se presentan en el Anexo 1.
Proyecto 1-M-373-002
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
3.1 GEOLOGA
3.1.1 Geomorfologa El rea de estudio se encuentra en la hoja de la carta nacional de Caravel. La geomorfologa del rea del proyecto est formada por altiplanicies, constituida por cerros sin ninguna vegetacin de 400 m a ms de elevacin, que se levantan por ambos lados en toda la extensin del valle de Chorunga, formando una quebrada con un ancho medio de 500 m, por donde corre el ro de Chorunga. 3.1.2 Estratigrafa
La estratigrafa a nivel regional est conformada por rocas gneas (basaltos y granitos). Los basaltos se muestran en corta extensin en los cerros de Chorunga, apareciendo solo en las partes bajas inmediatas al plano de la quebrada. Los granitos son de naturaleza granodioritica y se muestran claramente a lo largo de la quebrada de Chorunga. A nivel local, en la zona donde se emplazan los depsitos de relaves San Juan de Arequipa, se han identificado las siguientes unidades litolgicas, las cuales se describen a continuacin y se grafican en los Planos 3 al 7.
Depsito de Relaves, ubicado dentro de la quebrada de Chorunga y a la margen
derecha del ro de Chorunga, ocupando un rea de 26.6 ha. aproximadamente. Este depsito est constituido por un material limo-arcilloso arenoso.
Depsito Aluvial Reciente (Q-av1), que yace en el cauce de la quebrada de
Chorunga, compuesto por grava arenosa con cantos rodados y bolones, de los cuales el 20% aproximadamente corresponde a cantos rodados y bolones de naturaleza granodiorita. El espesor de este depsito supera los 20 m de profundidad, de modo que el agua del ro de Chorunga, en los meses de estiaje, no aparece en la superficie a causa del espesor y la permeabilidad de este depsito, obtenindose el agua slo de pozos.
Depsito Aluvial Antiguo (Q-av2), ubicado en las terrazas de ambas mrgenes del
Proyecto 1-M-373-002
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
la actividad minera, que yace frente a la cancha de relaves N 5 y a la derecha de la quebrada Chorunga.
Depsito Antrpico N 2 (Q-at2), compuestos de material del lecho de ro
de la quebrada de Chorunga, de color gris clara, dura a muy dura, ligeramente meteorizada y ligera a moderadamente fracturada; las juntas (fracturas) tienen superficies planas y/o rugosas, rellenadas con patinas de oxido y limo. 3.1.3 Riesgos geolgicos externos
Los fenmenos y procesos geodinmicos externos importantes que pueden representar un peligro para la estabilidad y la seguridad de los Depsitos de Relaves, no son de gran consideracin, ya que estos se presentaran lejos de ellos; como el que ocurri el da 15 de marzo de 1998, donde un huayco ocurrido en la zona de San Juan de Arequipa, Sector Cerro Colorado (Campamento Minero), ocasion cerca de 300 personas damnificadas, 58 viviendas destruidas y 211 viviendas afectadas1. No obstante, no se descarta el desprendimiento de fragmentos o bloques aislados de roca inestables, originados como consecuencia de la meteorizacin fsica de los afloramientos y facilitado por la accin de la gravedad y eventos ssmicos, los cuales no podrn comprometer la integridad fsica de los depsitos de relaves. 3.1.4 Hidrogeologa
El fondo de la quebrada de Chorunga, se halla cubierto por un extenso depsito aluvial conformado por cantos rodados, guijarros y arenas en una cantidad considerable, formando una cobertura de varios metros de espesor; de modo que el agua del ro de Chorunga, en los meses de estiaje, no aparece en la superficie a causa del espesor y permeabilidad de dicha capa que le sirve como filtro, obtenindose el agua para el consumo de la mina y el campamento minero, en dos pozos de hasta 10 m de profundidad cerca al campamento minero.
Descripcin de las Principales Emergencias Producidas a Nivel Nacional durante el Ao 1998. Oficina de Estadstica e Informtica INDECI.
Proyecto 1-M-373-002 SVS INGENIEROS S.A.C. 8
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
La Unidad Operativa San Juan de Arequipa para sus operaciones se abastece de agua subterrnea captada en dos pozos ubicados en la quebrada de Chorunga y el agua subterrnea que es bombeado desde los dos Piques de Profundizacin de la Mina ubicado a varios metros por debajo del nivel del ro Chorunga y en la margen derecha del mismo. Los dos pozos de agua denominados Principal y Huerta estn ubicados en las coordenadas UTM 8241,421.1N 709,901.2E a una altitud de 759,994 msnm y UTM 8240,962N y 709,077E a una altitud de 740,0 msnm respectivamente, donde segn comentarios de los pobladores del lugar el nivel del agua llega a los 2.0 m debajo de la superficie en temporada de lluvias y a 10.0 m debajo de la superficie en temporada de estiaje. Los piques denominados San Juan (Esperanza) ubicado en la coordenada UTM 8242,180.628 N 708,701.438 E con nivel de agua de bombeo en la cota 660 msnm y el pique Mercedes ubicado en 8241,280.158 N 707,802.443 E con nivel de agua de bombeo en la cota 550 msnm. Por otro lado, durante la presente exploracin de campo, el flujo de agua a travs de los depsitos de relaves slo podra darse dentro del cuerpo del Depsito de Relaves N 2 ya que slo en este depsito se est vertiendo relave, formando una zona de agua de decantacin o pondaje. Para averiguar el nivel de agua en los taludes del Depsito de Relaves N 2 se instalaron los piezmetros Pz-2 y Pz-3, registrndose la presencia de agua slo en el piezmetro Pz-3 a una profundidad de 8.0 m, por lo cual se prev que la lnea del nivel del agua de infiltracin discurre alejado al pie de talud del depsito, el mismo que fue corroborado con la no existencia de humedecimientos en la cara del talud exterior del depsito de relaves. En este contexto, se prev que el nivel fretico natural de la quebrada Chorunga est deprimido, el mismo que es alimentado por el flujo del ro Chorunga y no afectar a la estabilidad fsica del depsito de relaves. Para tener un mejor control de la variacin estacional del nivel fretico en la zona del depsito de relaves se proyecta la instalacin de dos piezmetros de tubo abierto tipo Casa Grande de hasta 25 m de profundidad, ubicados aguas arriba y aguas abajo de los depsitos de Relave San Juan de Arequipa (ver Plano 21).
3.2 GEOTECNIA
3.2.1 Depsitos de Relave Las investigaciones geotcnicas indican que el perfil estratigrfico del suelo en los Depsitos de Relaves, est constituido superficialmente por un estrato de material de relave clasificado como arena limosa (SM), suelta a muy suelta, seca a ligeramente
Proyecto 1-M-373-002
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
hmeda, de color plomo claro, con 42% de finos y un IP igual a 3%. Este estrato alcanza una profundidad que vara entre 4.7 y 8.0 m aproximadamente. Debajo se encuentra un estrato de material de relave clasificado como arcilla de baja plasticidad (CL) ligeramente arenosa, que vara de blanda a compacta, color plomo claro, ligeramente hmedo a hmedo, con un promedio de 76% de finos y un IP promedio igual a 11%. Dicho estrato se encuentra al fondo del depsito de relaves predominantemente en contacto con la cimentacin, entre profundidades que varan entre 6.4 y 12.2 m aproximadamente. 3.2.2 Suelo de Cimentacin
El suelo de cimentacin es el depsito aluvial reciente (Q-al1) que se encuentra en el lecho de la quebrada de Chorunga, clasificado como una grava pobremente gradada (GP) arenosa, densa, con 2% de finos no plstico y aproximadamente 20% de cantos y bolones redondeados a subredondeados de T.M. = 0.50 m.
3.3 SISMICIDAD
La zona de estudio est ubicada aproximadamente a 15.91 latitud Sur y 73.06 longitud Oeste, zona que de acuerdo a la clasificacin del Instituto Geofsico del Per (I. Bernal, H. Tavera e Y. Antayhua - 2002), es considerada como altamente ssmica, por la magnitud e intensidad de los sismos ocurridos a lo largo de su historia. Esta zona se ve afectada por la actividad tectnica que tiene su origen en sismos con hipocentros superficiales y profundos. Los ms profundos estn asociados al proceso de subduccin de la Placa de Nazca (ocenica) bajo la Placa Sudamericana (continental), generando frecuentemente terremotos de gran magnitud. Los sismos superficiales en cambio, estn relacionados con fallas regionales que existen a lo largo de la Cordillera Andina, siendo estos sismos menores, tanto en magnitud como en frecuencia. En el grafico 3.1 y en el cuadro 3.1, se muestra la relacin de fallas activas cercanas a la zona del proyecto.
Proyecto 1-M-373-002
10
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Grfico 3.1: Ubicacin de las fallas activas cercanas al proyecto (USGS y URS, 2003)
Cuadro 3.1: Relacin de fallas activas cercanas al proyecto (USGS y URS, 2003)
Slo desde 1963 se cuenta en el Per con registros instrumentales relativamente confiables de eventos ssmicos con los cuales se puede efectuar anlisis estadsticos y probabilsticas,
Proyecto 1-M-373-002 SVS INGENIEROS S.A.C. 11
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
sin embargo, la informacin histrica puede servir para ajustar dichos anlisis. Efectuando una seleccin de los sismos consignados en el Catlogo Ssmico de la NGDC/NOAA (National Geophysical Data Center/National Oceanic and Atmospheric Administration) y NEIC (National Earthquake Information Center), en un rea de 500 km de radio y con centro en la zona del proyecto, se encontr un total de 7,052 eventos ssmicos ocurridos desde Enero de 1963 hasta el presente y 148 eventos ssmicos representativos ocurridos desde el ao 1900 al 1962. En los Grficos 3.2 y 3.3 se muestran la ubicacin de los sismos cercanos al proyecto. Grfico 3.2: Ubicacin de los sismos ocurridos (USGS/NEIC (PDE) 1973 - Present).
ZONA DE PROYECTO
ZONA DE PROYECTO
Proyecto 1-M-373-002
12
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Con la informacin ssmica seleccionada, se procedi a calcular la aceleracin mxima del terreno en la zona de estudio, atribuible a eventos ssmicos, para lo cual se emplearon las frmulas de atenuacin de CASAVERDE y VARGAS (1980) para sismos cuyo origen est asociado a fenmenos de subduccin y la frmula de McGUIRE (1974) para sismos cuyo origen est asociado a fallas continentales. El anlisis de dicha informacin fue realizada empleando el mtodo de Valores Extremos (tipo Gumbel), siguiendo las metodologas recomendadas por LOMNITZ (1974) y GLASS (1981). Los resultados de dicho anlisis indican que para la zona del proyecto la aceleracin mxima es aproximadamente igual a 0.46g (g = aceleracin de la gravedad), que equivale a un sismo con periodo de retorno de 500 aos (ver Cuadro 3.2). Cuadro 3.2: Aceleraciones Ssmicas y Probabilidades de Excedencia para diferentes Periodos de Retorno.
Periodo de Retorno (aos) 2 5 10 50 100 150 200 300 400 500 1000 3000 10000
(*) Tiempo de exposicin
Aceleracin Ssmica (g) 0.06 0.14 0.19 0.30 0.35 0.37 0.39 0.42 0.44 0.46 0.50 0.58 0.66
Probabilidad de Excedencia 50 aos (*) 100% 100% 99% 64% 39% 28% 22% 15% 12% 10% 5% 2% 0%
No obstante, debido a que las aceleraciones ssmicas mximas se manifiestan slo durante un periodo muy corto, la aceleracin de diseo se define como una fraccin de la aceleracin mxima, Marcuson (1981) recomienda utilizar valores entre 1/3 a 1/2 de la aceleracin mxima esperada. Asimismo, el Cuerpo de Ingenieros del Ejrcito de los Estados Unidos (U.S. Army Corps of Engineers), recomienda el uso de un coeficiente ssmico igual al 50% de la aceleracin pico de diseo, la misma que est basada en numerosos estudios del comportamiento de terraplenes durante eventos ssmicos. Tambin, en la Gua Ambiental publicada por el Ministerio de Energa y Minas, se sugiere el uso de una fraccin comprendida entre 1/2 a 2/3 de la aceleracin pico de diseo.
Proyecto 1-M-373-002
13
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Considerando las recomendaciones descritas en el anterior prrafo y los niveles de riesgo en la zona del proyecto, se ha empleado una aceleracin de diseo igual a 0.23g, que equivale al 50% de la aceleracin pico de terreno.
Proyecto 1-M-373-002
14
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
4 BALANCE DE AGUAS
4.1 GENERALIDADES
La secuencia operativa para la disposicin de relaves es en forma de celdas o canchas de relaves temporales contiguas, para aprovechar la mxima evaporacin de las aguas de pondaje. Actualmente se viene operando la Cancha de Relaves N 2, que representa las condiciones ms desfavorables de operacin desde el punto de vista de balance de aguas, por tener el menor rea de evaporacin, por ello nos permitir predecir y estimar los caudales de ingreso y salida de agua en un ao promedio. Para efectos del balance de agua, los ingresos al depsito estaran constituidos por:
El agua para el transporte de los relaves (pulpa) La precipitacin directa sobre el depsito (playa de relaves y laguna de agua
decantada) Por otro lado, las salidas de agua estn compuestas por:
El agua de evaporacin El agua retenida en los vacos del depsito de relaves Agua de infiltracin a la cimentacin
En las secciones siguientes se precisan los valores de los componentes de ingreso y salidas de agua.
Proyecto 1-M-373-002
15
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
4.2.2
Precipitacin Directa
La zona del estudio se caracteriza por su clima seco y rido, donde las precipitaciones son escasas. Con los datos de las precipitaciones totales anuales correspondientes a los registros histricos de las estaciones pluviomtricas de la cuenca del ro Ocoa, se ha establecido una correlacin entre la precipitacin y la altitud, obtenindose un buen coeficiente de correlacin (r =0.99). El Grfico 4.1 y el Cuadro 4.2 muestran el grado de ajuste de la correlacin establecida y la precipitacin estimada para una altura de 650 msnm que corresponde a la zona del proyecto. Se observa que la correlacin establecida indica que para niveles por debajo de los 1785 msnm las precipitaciones son inexistentes. Grfico 4.1: Correlacin entre la Precipitacin y la Altitud para registros cercanos a la zona del proyecto
Precipitacin (mm)
Altitud (msnm)
Proyecto 1-M-373-002
16
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
4.2.3
Aguas Subterrneas
En vista que por lo general el nivel fretico de la zona del proyecto est muy deprimido, se considera que no existirn aportes de agua subterrnea hacia el depsito de relaves.
De acuerdo con la informacin proporcionada por Century Mining Per S.A.C. la pulpa de relave ser conducida al depsito con una relacin de slidos de 26.47%; a esta relacin le corresponde una densidad de pulpa igual a 1.2 t/m3. Una vez descargados los relaves, dicha densidad se incrementa gradualmente hasta valores comprendidos usualmente entre 1.5 y 1.8 t/m3, con la consiguiente liberacin de parte del agua contenida en sus poros. Para la presente evaluacin se ha considerado que la densidad promedio que adoptar el relave en el depsito ser igual a 1.55 t/m3, con lo cual se tiene que el agua que liberaran los relaves sera aproximadamente igual a 1015 m3/d y el agua que quedara retenida en los poros ser de 465 m3/d. 4.3.3 Agua de Recirculacin
Century Mining Per S.A.C., realiza una recirculacin del agua de pondaje hacia los depsitos de relaves adyacentes, con la finalidad de regar, minimizando la generacin de polvo y propiciar la evaporacin. Dentro la operacin, no se contempla la recirculacin de agua hacia la planta concentradora. 4.3.4 Filtraciones
En vista que la infiltracin estara dado por la diferencia del ingreso de agua del relave menos la salida de agua de evaporacin y el agua atrapada por el relave, estimndose un volumen de infiltracin entre 824 a 911 m3/da.
Proyecto 1-M-373-002
17
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Los resultados del balance de agua mensual durante un ao promedio, indican que la infiltracin es predominante por el rea de exposicin. En el Cuadro 4.2, se muestra el detalle del balance de aguas.
Proyecto 1-M-373-002
18
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
mm 0.0 0.0 0.0 m2 27,400 27,400 27,400 m3 0 0 0 m3 44,400 44,400 44,400 44,400 44,400 44,400 mm m2 m3 m3 m3 m3 m3 158 24,030 3,786 13,950 26,664 44,400 0 130 24,030 3,113 13,950 27,337 44,400 0 151 24,030 3,629 13,950 26,821 44,400 0
Proyecto 1-M-373-002
19
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
La red de estaciones meteorolgicas del rea del Proyecto, es relativamente escasa, habindose identificado las estaciones de Yanaquihua, Caravel y Urasqui, como las ms completas de la zona del Proyecto, que cuentan con registros continuos de precipitacin mxima en 24 horas. La estacin Yanaquihua, localizada en el sector medio de la cuenca de la quebrada se considera la ms representativa de las condiciones medias de la cuenca. La estacin Carvel, que cuenta con extensos registros, pero pertenece a una cuenca vecina, ha sido seleccionada como estacin de comparacin mientras la estacin Urasqui, situada aguas debajo de la zona del Proyecto y dentro del sector seco de la cuenca, fue desechada por cuanto sus registros no son apropiado para el anlisis estadstico. La ubicacin de estas estaciones y los perodos de registros correspondientes, se detallan en el Cuadro 5.1. Cuadro 5.1: Ubicacin de estaciones, periodos de registros y tipo de informacin obtenida
Estacin Yanaquihua Latitud 15 46 59 Longitud 72 52 57 Altitud 3130 msnm Perodo de registros 1964 - 2007 Tipo de registros Precipitacin mxima en 24 horas Precipitacin mxima en 24 horas Precipitacin mxima en 24 horas
20
Caravel
15 46
73 21
1779 msnm
1973 - 2006
Urasqui
16 2
73 10
330 msnm
1965 - 1976
Proyecto 1-M-373-002
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
5.1.3
Anlisis hidrolgico
5.1.3.1 Anlisis de Precipitacin Extrema Los registros de precipitacin mxima en 24 horas, de las estaciones pluviomtricas seleccionadas, fueron evaluados, mediante el modelo Smirnov Kolgoronov, con la finalidad de verificar las distribuciones matemticas a las que se ajustan los registros. Habindose seleccionado la distribucin ms representativa, en cada caso, los registros fueron analizados mediante el programa HEC SSP, formulado por el Hydrologic Engineering Center, adscrito al Cuerpo de Ingenieros del Ejrcito de los Estados Unidos de Norteamrica. Este programa ejecuta, previamente, la evaluacin de datos dudosos (outsiders) y genera, adems de la curva de probabilidad terica de ocurrencia de los eventos extremos, una curva de probabilidad esperada. Est ltima curva, conforme a lo explicado en el Bulletin 17B del antes referido Hydrologic Engineering Center, pretende contrarrestar las distorsiones introducidas por la extensin de los registros. Las distribuciones matemticas utilizadas, en cada caso, se detallan en el Cuadro 5.2. Cuadro 5.2: Distribuciones adoptadas por estacin
Estacin Yanaquihua Caravel Distribucin adoptada Log - normal Log - normal
Con los registros de precipitacin mxima en 24 horas, resultantes del anlisis anterior, se procedi a evaluar los niveles de precipitacin extrema probable en la estacin, para perodos de ocurrencia media de 100 y 500 aos en cada caso. Los valores de precipitacin extrema en 24 horas para las estaciones analizadas, se detalla en el Cuadro 5.3. Cuadro 5.3: Precipitacin Extrema en 24 Horas
Estacin Yanaquihua Caravel Precipitacin Tr = 100 aos (mm) 85.2 120.6 Precipitacin Tr = 500 aos (mm) 124.3 176.1
Partiendo de los valores detallados en la tabla anterior, se evaluaron los niveles de precipitacin para la cuenca de la quebrada Chorunga, tomndose en cuenta el tiempo de concentracin de la cuenca. Para el efecto, se delimitaron las cuencas y se midieron, en la carta geogrfica nacional a escala 1:100000, el rea, la longitud del curso principal, la
Proyecto 1-M-373-002 SVS INGENIEROS S.A.C. 21
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
distancia de la seccin de control al centroide de la cuenca y la pendiente media de la misma. El tiempo de concentracin se evalu conforme al modelo propuesto por el Soil Conservation Service de los Estados Unidos de Norteamrica, en funcin del rea, la longitud mxima y la pendiente de la cuenca. La reduccin de la precipitacin mxima en 24 horas a precipitacin mxima en el tiempo de concentracin fue estimada mediante la aplicacin del modelo del Convenio IILA SENAMHI UNI para duraciones de tormenta entre 3 y 24 horas. El Cuadro 5.4, contiene los valores de precipitacin extrema en la cuenca analizada, para perodos medios de recurrencia de 100 y 500 aos. Cuadro 5.4: Precipitacin Mxima en el Tiempo de Concentracin
Cuenca Qda. Chorunga Estacin Pluviomtrica Yanaquihua rea de cuenca (km2) 969.2 Precipitacin extrema (mm) Tr = 100 80.7 Tr = 500 117.7
5.1.3.2 Anlisis de Caudales Extremos No contndose con registros hidromtricos adecuados, para la evaluacin de caudales extremos se aplic el modelo de hidrograma de Snyder (utilizndose el programa computarizado HEC HMS, del Cuerpo de Ingenieros del Ejrcito de los Estados Unidos de Norteamrica). La extensin de la cuenca colectora, lo mismo que la longitud mxima de la cuenca y la distancia al centroide de la misma, se evalu en base a la previa identificacin de los lmites de la cuenca en los planos topogrficos, a escala 1:100 000, que cubren el rea del Proyecto. El plano N 8 presenta la cuenca analizada, cuya rea es de 969.2 km2. La seleccin de la curva de prdidas y dems parmetros requeridos para la determinacin de la lluvia efectiva, fue realizada mediante las tablas desarrolladas, para el efecto por el Soil Conservation Service de los Estados Unidos de Norteamrica. Debido a la falta de informacin continua de precipitacin (registros pluviogrficos), se adopt la distribucin tpica de la tormenta tipos II (vertiente del Pacfico), propuesta por el Weather Bureau de los Estados Unidos de Norteamrica. En el Cuadro 5.5 siguiente, se resumen los valores de caudales extremos evaluados para la cuenca de la quebrada de Chorunga, correspondientes a las recurrencias medias de 100 aos y 500 aos.
Proyecto 1-M-373-002 SVS INGENIEROS S.A.C. 22
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Proyecto 1-M-373-002
23
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Guijarros Grava
5.2.2
Los anlisis de socavacin potencial, se desarrollaron para determinar las dimensiones requeridas para la proteccin de las obras de defensa propuestas. Los anlisis comprendieron la evaluacin de la socavacin general del lecho mediante los modelos de Lacey, Blench y Neill. Para efectos de diseo, se adopt el valor promedio de los resultados obtenidos en cada caso, ajustado por el factor 1.25 para considerar eventuales variaciones locales de la socavacin. En el Cuadro 5.7, se registran las profundidades de socavacin, en la seccin ms crtica, para perodos de recurrencia de 100 aos y 500 aos. Cuadro 5.7: Niveles de Socavacin en el lecho
Cuenca rea de cuenca (km2) 969.2 Socavacin (m) Tr = 100 aos Qda. de Chorunga 1.28 Tr = 500 aos 1.65
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
del talud externo. El revestimiento con enrocado consistira de roca dura y durable, deber tener un espesor de 0.60 m. As mismo en el lecho del ro, adyacente al revestimiento de enrocado, se colocara una capa de proteccin de 3.50 m de ancho y 0.6 m de espesor. La interface talud revestimiento, estara provista de un manto geotextil que impida la migracin de las partculas finas del talud. El material rocoso empleado para la construccin del enrocado deber cumplir la gradacin indicada en el cuadro siguiente: Cuadro 5.8: Granulometra del enrocado D50 D20
Min. Max. Min. Max. Min.
D100
Max.
0.50
0.35
0.30
0.25
0.25
0.20
Proyecto 1-M-373-002
25
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Teniendo en cuenta las caractersticas topogrficas de dichos depsitos de relave, as como las caractersticas geotcnicas de la cimentacin y de los relaves contenidos por stos, se ha determinado que es factible realizar un recrecimiento adicional en cada uno de los depsitos. El proyecto de recrecimiento plantea el transporte del relave desde la planta concentradora hacia los depsitos de relaves mediante una tubera HDPE, en tanto que la descarga de relaves se efectuar desde la cresta de los diques perimetrales hacia la ladera del cerro, por un sistema de tuberas tipo Spigot, para aprovechar la segregacin de los relaves y as disponer las partculas ms gruesas en los diques perimetrales de los depsitos de relaves y mantener el agua de pondaje siempre alejado del dique perimetral, disminuyendo el riesgo de inestabilidad por tubificacin y licuacin (ver grfico 6.1). Manteniendo siempre la disposicin por celdas temporales para aprovechar la alta evaporacin de la zona. Grfico 6.1: Disposicin de la descarga de relaves
Proyecto 1-M-373-002
26
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Asimismo, se plantea la construccin de un dique de defensa riberea que a la vez se usara como dique de contencin. Dicho dique se extender a lo largo de todo el permetro de depsito de relaves. El recrecimiento a partir de la cresta del dique de defensa riberea se realizar con un talud de 2.5(H):1.0(V) hasta alcanzar las cotas de mxima elevacin del recrecimiento descritas a continuacin:
Cota de cresta (cancha de relave N 1): Cota de cresta (cancha de relave N 2): Cota de cresta (cancha de relave N 3): Cota de cresta (cancha de relave N 4): Cota de cresta (cancha de relave N 5):
680 msnm 685 msnm 690 msnm 795 msnm 700 msnm
En todos los casos se deber mantener una distancia mnima desde la cresta del talud hasta el borde al agua de pondaje igual a 20 m. Se recomienda continuar con el ciclo de disposicin del relave en forma de celdas o canchas temporales, es decir una vez colmatado un depsito se paralizar el ingreso de relave cerrando la tubera de conduccin a la altura de este depsito, para luego utilizar la cancha contigua y as sucesivamente hasta llegar al ltimo depsito. Una vez colmatado el ltimo depsito, nuevamente se iniciar el ciclo de disposicin de relave. Con las caractersticas del proyecto de recrecimiento planteadas en los anteriores prrafos, se estim que el volumen de almacenamiento de relaves asciende a 0.924 Mm3 de relave. En los Planos 9 al 16 se muestra la distribucin en planta del recrecimiento del depsito propuesto y las secciones tpicas.
Proyecto 1-M-373-002
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Para el anlisis esttico y pseudo-esttico se ha utilizado el mtodo de equilibrio lmite de Bishop simplificado, cuyo algoritmo de clculo est contenido en el programa Slide (versin 5.0). 6.2.2 Secciones de Anlisis
Para evaluar las condiciones de estabilidad global en el Estado Actual se han seleccionado secciones representativas. En los Planos 4 al 7 se presentan dichas secciones de anlisis. As mismo para evaluar las condiciones de estabilidad global en el Estado de Recrecimiento Propuesto se han seleccionado secciones representativas. En los Planos 10 y 11 se presentan dichas secciones de anlisis. 6.2.3 Aceleracin Ssmica de Diseo
De acuerdo a lo descrito en el Item 3.3, la aceleracin ssmica de diseo recomendada para el anlisis de estabilidad es de 0.23g, valor que equivale a 1/2 de la aceleracin mxima correspondiente a un sismo con una probabilidad excedencia de 10 % en 50 aos de exposicin y para un sismo con periodo de retorno de 500 aos. 6.2.4 Nivel Fretico
En base a los registros de las excavaciones (calicatas y perforaciones), as como a las condiciones geolgicas locales, se ha asumido un nivel fretico conservador para realizar el anlisis de estabilidad correspondiente, el cual representa la condicin ms desfavorable para estos depsitos. En el Anexo 4 se muestra la posicin de la napa fretica asumida para cada caso. 6.2.5 Parmetros Resistentes
La caracterizacin geotcnica de los materiales involucrados en el anlisis de estabilidad de los Depsitos de Relaves ha sido efectuada sobre la base de los resultados de los ensayos de laboratorio, las investigaciones in-situ y la revisin de la informacin existente, de donde se estimaron valores de las propiedades fsicas y mecnicas de cada uno de los materiales que intervienen en este anlisis, y que se presentan en el Cuadro 6.1. Cuadro 6.1: Propiedades Fsicas y Mecnicas de los Materiales
Material Relave Existente (arena limosa suelta) Relave Existente (arcilla ligeramente arenosa) Relave Existente (arena limo arcillosa) Clasificacin (SUCS) SM CL SM-SC Peso Unitario (kN/m3) 16.0 16.0 16.0 Angulo de Friccin Interna (grados) 28.0 14.0 30.0 Cohesin (kPa) 5.0 10.0 5.0
Proyecto 1-M-373-002
28
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Cimentacin (Depsito Aluvial, grava arenosa con bolonera) Material antrpico N 2 (Grava arenosa con botonera ) Relave Proyectado (Relave predominante grueso, arena limosa) Relave Proyectado (Relave predominante fino, limo arcilloso) Relleno Compactado (Grava arenosa) Enrocado
GP + B
22.0
38.0
0.0
GP + B
19.0
35.0
0.0
SM
16.0
30.0
5.0
ML GP B
6.2.6
Los factores de seguridad mnimos considerados en este estudio son los especificados en la Gua Ambiental para la Estabilidad de Taludes de Depsitos de Residuos Slidos Provenientes de Actividades Mineras del Ministerio de Energa y Minas (DGAA, Vol. XVI - 1998), y son los que se indican en el Cuadro 6.2. Cuadro 6.2: Valores Mnimos Admisibles del Factor de Seguridad Caso Anlisis esttico Anlisis pseudo-esttico
(*)
6.2.7
Los resultados obtenidos en los anlisis de estabilidad se resumen en el Cuadro 6.3, y el detalle de los mismos se presenta en el Anexo 3 de este informe. Cuadro 6.3: Resumen de los Factores de Seguridad Obtenidos Seccin de Factor de Seguridad ESTADO Anlisis Esttico Pseudo-Esttico E.A. (No Operativo) (Depsito N 1) E.A. (Operativo) (Depsito N 2) 1 - 1 2 - 2 1.9 1.5 1.1 0.8
Proyecto 1-M-373-002
29
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
E.A. (Operativo) (Depsito N 2) E.A. (No Operativo) (Depsito N 5) E.R.P (Depsito N 1) E.R.P (Depsito N 2) E.R.P (Depsito N 2) E.R.P (Depsito N 3) E.R.P (Depsito N 4) E.R.P A.M. (Depsito N 1) E.R.P A.M. (Depsito N 2) E.R.P A.M. (Depsito N 2) E.R.P A.M. (Depsito N 3) E.R.P A.M. (Depsito N 4)
3 - 3 4 - 4 AA BB CC DD EE AA BB CC DD EE
1.5 1.5 2.2 2.2 2.3 2.5 2.7 2.0 2.3 2.0 2.0 2.0
E.A.: Estado Actual E.R.P.: Estado de Recrecimiento Propuesto E.R.P. A.M.: Estado de Recrecimiento Propuesto en una Avenida Mxima del ro Chorunga (Tr = 500 aos)
El Factor de Seguridad para la condicin de equilibrio esttico del estado actual de los depsitos de relaves San Juan de Arequipa es mayor al mnimo requerido por la legislacin vigente, mientras que para el anlisis pseudo esttico presenta condicines de inestabilidad, con factores de seguridad cercanos a la unidad. El depsito de relaves N 2 representa la condicin ms desfavorable obtenindose un factor de seguridad pseudo-esttico por debajo de la unidad, esto debido a que el agua de pondaje se encontraba muy cercano a la cresta del talud. Los resultados de los factores de seguridad obtenidos, para la geometra final de recrecimiento propuesto, tanto para la condicin esttica como pseudo-esttica, son todos mayores o iguales que los factores de seguridad mnimos requeridos. Por lo tanto, se concluye que el recrecimiento propuesto permanecer estable durante la operacin y postcierre del depsito de relaves.
Proyecto 1-M-373-002
30
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Como parte de los trabajos auxiliares se realizar la excavacin y/o limpieza de todo el material de relave que quedar al exterior del dique perimetral del depsito de relaves, el mismo que deber ser depositado dentro del depsito de relaves de una manera ordenada sin perjudicar los recrecimientos proyectados.
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
la quebrada Chorunga. Los suelos no debern tener vegetacin, detritos u otros materiales inadecuados. El material utilizado para el relleno del cuerpo de la presa deber ser colocado en capas de espesor mximo suelto igual a 30 cm y deber ser compactado hasta alcanzar el 90% de la densidad mxima seca a ser obtenida mediante el ensayo Proctor Modificado (ASTM D1557). Al ser colocado y compactado, su contenido de humedad deber estar dentro del +2% y -2% de la humedad ptima obtenida mediante el ensayo Proctor Modificado. Previo a la colocacin de la primera capa de relleno la cimentacin, ste deber ser escarificado y compactado, hasta alcanzar el 90% de la densidad mxima seca a ser obtenida mediante el ensayo Proctor Modificado 7.3.2 Geotextil
Para evitar la migracin de finos del dique de defensa riberea hacia el enrocado, se proyecta la colocacin de una capa de geotextil no tejido de 200 gr/m2, sobre el talud aguas abajo del dique perimetral y previo perfilado del sobre ancho de construccin, el mismo que deber ser anclado en la cresta y el pie del talud de acuerdo a los planos de construccin. El geotextil deber cumplir con los requerimientos sealados por el ASTM y las especificaciones tcnicas de construccin. Asimismo, este material ser suministrado e instalado por un personal especializado y de acuerdo con los procedimientos, plan, control y aseguramiento de la calidad revisados y aprobados por el Ingeniero Supervisor. 7.3.3 Enrocado de Proteccin
El material de enrocado deber consistir en roca angulosa, resistencia dura a muy dura y una distribucin granulomtrica de acuerdo al Cuadro 5.8, extrado de la Cantera 2 con el uso de voladura por banqueo para no desestabilizar los taludes de corte o seleccionada de un material de desmonte inerte.
7.5 PRESUPUESTO
Los anlisis de precios unitarios de las diferentes partidas consideradas para la ejecucin de la Defensa Riberea de los Depsitos de Relave San Juan de Arequipa, al igual que el presupuesto referencial de obra, fueron estimados en base a las condiciones operativas de
Proyecto 1-M-373-002
32
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
la zona, precios de insumos actualizados a la fecha, rendimientos tpicos obtenidos en otros proyectos similares y metrados de obra calculados, el mismo que se detalla en el Anexo 8. El Costo directo de la Obra asciende a novecientos ochenta y ocho mil setecientos cincuenta y cinco y 96/100 dlares americanos (US$ 988,755.96). Se ha sumido un porcentaje de Gastos Generales (GG) de 25% distribuidos en 20% de GG Variables y 5% de GG Fijos, ms una utilidad del 10% para el contratista de obra, considerando adems el 19% del Impuesto General a la ventas el Presupuesto final para la ejecucin de la Obra alcanza a un milln quinientos ochenta y ocho mil cuatrocientos sesenta y ocho y 58/100 dlares americanos (US$ 1588,468.58). Cuadro 7.1: Presupuesto referencial para a la construccin de la Defensa Riberea
Proyecto 1-M-373-002
33
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
La primera etapa consistir en la construccin del dique de la defensa riberea para una altura de tirante de 100 aos de periodo de retorno, correspondiente para un periodo de operacin, y la segunda etapa para 500 aos de periodo de retorno, correspondiente a la etapa de cierre o abandono. En el Plano 14, se muestra los tirantes tpicos y los detalles de tirante por cada progresiva se muestra en el Anexo 5b. El cronograma detallado de ejecucin de obra se presenta en el Anexo 9 del presente informe.
Proyecto 1-M-373-002
34
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
8 PLAN DE OPERACIONES
8.1 GENERALIDADES
El grado de detalle con el que se documente la construccin del recrecimiento y la operacin del depsito de relaves constituirn componentes esenciales para el diseo definitivo del cierre. En esta seccin se resumen las consideraciones generales a tenerse en cuenta durante la fase de construccin y de operacin de los depsitos de relave.
Proyecto 1-M-373-002
35
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
los depsitos de relaves inoperativos minimizando a cero la generacin de polvo de relave a causa de los vientos.
El contenido del Manual de Operaciones deber incluir los siguientes aspectos: Descripcin del proyecto y organizacin Planeamiento Sistemas de operacin y procedimientos Inspeccin y mantenimiento Documentacin de la construccin y control de calidad Instrumentacin y monitoreo Evaluaciones del comportamiento de la instalacin Planes de prevencin de emergencias
El Manual de Operaciones deber ser preparado de acuerdo con las guas propuestas por la Asociacin de Minera de Canad (Mining Association of Canada) y las guas ambientales del Ministerio de Energa y Minas del Per.
Proyecto 1-M-373-002
36
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Adems de proveer una gua documentada para tratar las emergencias o condiciones inusuales, el PPE tambin servir para crear conciencia en los operadores sobre las condiciones a las que debern estar atentos.
Proyecto 1-M-373-002
37
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Proyecto 1-M-373-002
38
CENTURY MINING PERU S.A.C. DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVE SAN JUAN DE AREQUIPA
MAYO 2009
Proyecto 1-M-373-002
39
MAYO, 2009
ANEXOS
Proyecto 1-M-373-002
Anexos
MAYO, 2009
ANEXO 1
PERFILES ESTRATIGRAFICOS DE SONDEOS
Proyecto 1-M-373-002
Anexos
MAYO, 2009
A. REGISTRO DE
CALICATAS
Proyecto 1-M-373-002
Anexos
MAYO, 2009
Proyecto 1-M-373-002
Anexos
MAYO, 2009
ANEXO 2
PIEZOMETROS DE TUBO ABIERTO
Proyecto 1-M-373-002
Anexos
MAYO, 2009
ANEXO 3
ENSAYOS DE LABORATORIO DE MECANICA DE SUELOS
Proyecto 1-M-373-002
Anexos
MAYO, 2009
Proyecto 1-M-373-002
Anexos
HOJA :
RESUMEN DE ENSAYOS DE LABORATORIO - CARACTERIZACIONES FISICAS ASTM - D422 - 63, ASTM - D4318 - 0 0, ASTM - D2216 - 98
DE :
PROYECTO: CLIENTE :
Prof. (m)
Diseo de Recrecimiento y Defensa Riberea de los Depsitos de Relaves San Juan de Arequipa CENTURY MINING PERU S.A.C. Porcentaje Acumulado que Pasa la Malla ASTM 3" 2" 1 /2"
1
N PROYECTO:
OPERADOR:
UBICACIN : REVISADO :
LL LP % IP %
FECHA :
Mar-09 EVR
APROBADO:
SONDEO
SUCS 1"
3
/4"
/2"
/8"
#4
#10
#16
#30
#50
#100
#200
P-1 P-1 P-2 P-2 P-2 P-3 P-3 P-3 P-4 P-4 P-4 C-1 C-2 C-3 C-4
3.00-3.45 5.00-5.45 4.00-4.45 8.00-8.45 11.00-11.45 3.00-3.45 6.00-6.45 8.00-8.45 3.00-3.45 5.00-5.45 8.00-8.45 1.50-2.80 0.60-2.60 0.00-2.40 0.00-2.90
100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 89.3 89.0 87.1 100.0
100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 82.5 77.0 72.7 88.5
100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 89.0 100.0 67.6 57.6 59.8 69.6
100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 85.1 100.0 58.7 49.0 53.8 59.1
100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 84.0 100.0 48.4 37.4 48.2 46.0
100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 81.2 100.0 42.3 32.0 45.2 39.5
100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 72.7 100.0 32.3 24.8 39.4 29.6
100.0 100.0 99.9 100.0 100.0 99.8 100.0 100.0 100.0 65.2 100.0 26.3 20.8 33.5 21.4
99.9 100.0 99.8 100.0 100.0 99.7 99.9 99.9 99.9 61.3 100.0 21.7 17.7 29.4 17.4
98.3 99.9 96.8 99.7 99.4 98.3 98.4 99.9 97.8 56.7 99.7 14.2 12.3 21.5 11.8
86.4 99.9 82.5 96.7 92.9 88.0 91.3 99.5 86.8 47.3 93.6 7.3 6.2 11.1 6.3
59.0 99.4 60.2 85.4 78.3 62.2 82.2 94.6 68.2 34.0 77.2 3.2 2.4 4.3 2.7
40.1 97.2 43.9 75.7 65.0 42.1 76.1 82.3 52.8 25.3 62.3 1.8 1.2 2.0 1.5
17 40 18 28 23 16 29 27 20 17 23 0 0 0 0
14 23 15 18 15 13 18 15 14 13 15 0 0 0 0
3 17 3 10 9 3 12 12 6 4 8 NP NP NP NP
14.3 35.2 22.3 35.4 18.3 14.8 31.2 28.3 18.7 14.8 12.3 2.3 2.7 4.0 2.1
SM CL SM CL CL SM CL CL CL-ML SC-SM CL GW GP GP GW
Diseo de Recrecimiento y Defensa Riberea de los Depsitos de Relaves San Juan de Arequipa N PROYECTO: CENTURY MINING PERU SAC
GRAVA
GRUESA FINA GRUESA
UBICACIN :
ARENA
MEDIA FINA
LIMO Y ARCILLA
POR HIDROMETRO
0,007 0,005 0,004 0,003 0,002
0,297
19,05
9,525
0,149
0,074
38,1
1,18
50,8
76,2
25,4
12,7
4,75
100 90
0,59
2,0
0,001
0,05 0,04
0,03
0,02
0,01
SUCS 80
CL
: P-1 :
5.00-5.45
70
SM : P-2 : 4.00-4.45
60
CL : P-2 : 8.00-8.45
50
CL : P-2 : 11.00-11.45
40
SM : P-1 : 3.00-3.45
30 20 10 0
N10 N 100 N16 N30 N200 N 50 2" 11/2" 1" 3/4" 1/2" "3 3/8" N4
Diseo de Recrecimiento y Defensa Riberea de los Depsitos de Relaves San Juan de Arequipa N PROYECTO: CENTURY MINING PERU SAC
GRAVA
GRUESA FINA GRUESA
UBICACIN :
ARENA
MEDIA FINA
LIMO Y ARCILLA
POR HIDROMETRO
0,007 0,005 0,004 0,003 0,002
0,297
19,05
9,525
0,149
0,074
38,1
1,18
50,8
76,2
25,4
12,7
4,75
100 90
0,59
2,0
0,001
0,05 0,04
0,03
0,02
0,01
SUCS 80
SM
: P-3 :
3.00-3.45
70
CL : P-3 : 6.00-6.45
60
CL : P-3 : 8.00-8.45
50
CL-ML : P-4 : 3.00-3.45
40
SC-SM : P-4 : 5.00-5.45
30 20 10 0
N10 N 100 N16 N30 N200 N 50 2" 11/2" 1" 3/4" 1/2" "3 3/8" N4
Diseo de Recrecimiento y Defensa Riberea de los Depsitos de Relaves San Juan de Arequipa N PROYECTO: CENTURY MINING PERU SAC
GRAVA
GRUESA FINA GRUESA
UBICACIN :
ARENA
MEDIA FINA
LIMO Y ARCILLA
POR HIDROMETRO
0,007 0,005 0,004 0,003 0,002
0,297
19,05
9,525
0,149
0,074
38,1
1,18
50,8
76,2
25,4
12,7
4,75
100 90
0,59
2,0
0,001
0,05 0,04
0,03
0,02
0,01
SUCS 80
CL
: P-4 :
8.00-8.45
70
GW : C-1 : 1.50-2.80
60
GP : C-2 : 0.60-2.60
50
GP : C-3 : 0.00-2.40
40
GW : C-4 : 0.00-2.90
30 20 10 0
N10 N 100 N16 N30 N200 N 50 2" 11/2" 1" 3/4" 1/2" "3 3/8" N4
Proyecto : DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVES SAN JUAN DE AREQUIPA Ubicacin : RIO GRANDE - CONDESUYOS - AREQUIPA Cliente : CENTURY MINIG PERU SAC Nro Proyecto : 1- M 373 - 002 Operador : ZONA: MARGEN IZQUIERDA
VYU
UBICACIN
SONDAJE No MUESTRA PROFUNDIDAD FECHA HECHO POR:
DENSIDAD DE CAMPO
1 Densidad de la arena calibrada (gr/cm) 2 Peso inicial de arena calibrada (gr) 3 Peso de la arena calibrada en el cono (gr) 4 Peso de la arena calibrada sobrante (gr) 5 Peso de la arena calibrada en el orificio de prueba (gr) (2)-(3)-(4) 6 Volumen del orificio de prueba (cm) (5)/(1) 7 Peso total de la muestra hmeda (gr) 8 Peso material > 3/4" (grava) (gr) 9 Peso material < 3/4" (gr) (7)-(8) 10 Peso especifico de grava (gr/cm) 11 Volumen de grava (cm) (8)/(10) 12 Volumen de material < 3/4" (cm) (6)-(11) 13 Densidad hmeda del material < 3/4" (gr/cm) (9)/(12) 14 Densidad muestra seca (gr/cm) (13)/(1+(21)) 0.00 2613.19 1.56 1.53 K 148.75 145.85 2.90 11.76 134.09 2.16% U 171.90 167.90 4.00 12.97 154.93 2.58% 0.00 2423.61 1.84 1.79 I 132.85 123.98 8.87 11.25 112.73 7.87% 0.00 2354.17 1.44 1.33 4085.00 4459.00 3392.00 1.440 6000.00 1638.00 599.00 3763.00 2613.19 4085.00 1.440 6000.00 1638.00 872.00 3490.00 2423.61 4459.00 1.440 6000.00 1638.00 972.00 3390.00 2354.17 3392.00
CONTENIDO DE HUMEDAD
15 Cdigo del recipiente. 16 Peso del recipiente+suelo humedo (gr) 17 Peso del recipiente+suelo seco (gr) 18 Peso del agua (gr) (16)-(17) 19 Peso del recipiente (gr) 20 Peso del suelo seco (gr) (17)-(19) 21 Contenido de humedad 100x(18)/(20)
Proyecto : DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVES SAN JUAN DE AREQUIPA Ubicacin : RIO GRANDE - CONDESUYOS - AREQUIPA Cliente : CENTURY MINIG PERU SAC Nro Proyecto : 1- M 373 - 002 Operador : ZONA Coordenadas sistema WGS84 Coordenadas sistema PSAD56
VYU
UBICACIN
SONDAJE No MUESTRA PROFUNDIDAD FECHA HECHO POR:
DENSIDAD DE CAMPO
1 Densidad de la arena calibrada (gr/cm) 2 Peso inicial de arena calibrada (gr) 3 Peso de la arena calibrada en el cono (gr) 4 Peso de la arena calibrada sobrante (gr) 5 Peso de la arena calibrada en el orificio de prueba (gr) (2)-(3)-(4) 6 Volumen del orificio de prueba (cm) (5)/(1) 7 Peso total de la muestra hmeda (gr) 8 Peso material > 3/4" (grava) (gr) 9 Peso material < 3/4" (gr) (7)-(8) 10 Peso especifico de grava (gr/cm) 11 Volumen de grava (cm) (8)/(10) 12 Volumen de material < 3/4" (cm) (6)-(11) 13 Densidad hmeda del material < 3/4" (gr/cm) (9)/(12) 14 Densidad muestra seca (gr/cm) (13)/(1+(21)) 0.00 2406.25 1.36 1.26 K1 124.95 116.85 8.10 12.35 104.50 7.75% X 146.65 143.95 2.70 11.07 132.88 2.03% 0.00 2402.78 1.38 1.35 T 142.75 125.15 17.60 14.55 110.60 15.91% 0.00 2032.64 1.76 1.52 3266.00 3318.00 3574.00 1.440 6000.00 1638.00 897.00 3465.00 2406.25 3266.00 1.440 6000.00 1638.00 902.00 3460.00 2402.78 3318.00 1.440 6000.00 1638.00 1435.00 2927.00 2032.64 3574.00
CONTENIDO DE HUMEDAD
15 Cdigo del recipiente. 16 Peso del recipiente+suelo humedo (gr) 17 Peso del recipiente+suelo seco (gr) 18 Peso del agua (gr) (16)-(17) 19 Peso del recipiente (gr) 20 Peso del suelo seco (gr) (17)-(19) 21 Contenido de humedad 100x(18)/(20)
Proyecto : DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPSITOS DE RELAVES SAN JUAN DE AREQUIPA Ubicacin : RIO GRANDE - CONDESUYOS - AREQUIPA Cliente : CENTURY MINIG PERU SAC Nro Proyecto : 1- M 373 - 002 Operador : ZONA: MARGEN IZQUIERDA
VYU
UBICACIN
SONDAJE No MUESTRA PROFUNDIDAD FECHA HECHO POR:
DENSIDAD DE CAMPO
1 Densidad de la arena calibrada (gr/cm) 2 Peso inicial de arena calibrada (gr) 3 Peso de la arena calibrada en el cono (gr) 4 Peso de la arena calibrada sobrante (gr) 5 Peso de la arena calibrada en el orificio de prueba (gr) (2)-(3)-(4) 6 Volumen del orificio de prueba (cm) (5)/(1) 7 Peso total de la muestra hmeda (gr) 8 Peso material > 3/4" (grava) (gr) 9 Peso material < 3/4" (gr) (7)-(8) 10 Peso especifico de grava (gr/cm) 11 Volumen de grava (cm) (8)/(10) 12 Volumen de material < 3/4" (cm) (6)-(11) 13 Densidad hmeda del material < 3/4" (gr/cm) (9)/(12) 14 Densidad muestra seca (gr/cm) (13)/(1+(21)) 0.00 2103.47 1.54 1.52 K1 156.15 153.95 2.20 13.01 140.94 1.56% 0.00 2481.25 1.53 1.50 X 161.05 157.75 3.30 12.29 145.46 2.27% 0.00 2613.19 1.56 1.53 T 138.85 136.20 2.65 12.17 124.03 2.14% 3240.00 3791.00 4085.00 1.440 6000.00 1638.00 1333.00 3029.00 2103.47 3240.00 1.440 6000.00 1638.00 789.00 3573.00 2481.25 3791.00 1.440 6000.00 1638.00 599.00 3763.00 2613.19 4085.00
CONTENIDO DE HUMEDAD
15 Cdigo del recipiente. 16 Peso del recipiente+suelo humedo (gr) 17 Peso del recipiente+suelo seco (gr) 18 Peso del agua (gr) (16)-(17) 19 Peso del recipiente (gr) 20 Peso del suelo seco (gr) (17)-(19) 21 Contenido de humedad 100x(18)/(20)
Proyecto : Ubicacin : Cliente : N Proyecto : N Proctor: Muestra : Sondaje: SUCS : Prof. (m) :
1 Ensayo N
Recrecimiento y Defensas Ribereas de los Depositos de Relave San Juan de Arequipa Rio Grande - Condesuyos - Arequipa Century Mining Peru SAC 1 -M - 373-002 1 M-1 C-04 GW 0.00-2.90
1 7384 2797 4587 2123 2.16
VYU G.G.F
Abr-09
Proctor Tipo: N de Capas: N Golpes por Capa: Altura de caida: Peso del Martillo:
2 7557 2797 4760 2123 2.24 3 7691 2797 4894 2123 2.31
C 5 56 45,72cm 4,54kg.
4 7744 2797 4947 2123 2.33 5 7701 2797 4904 2124 2.31
2 Peso suelo + molde (g) 3 Peso del molde (g) 4 Peso suelo hmedo compactado (g) (2)-(3) 5 Volumen del molde (cm) 6 Peso volumtrico hmedo (g/cm) (5)/(4)
CONTENIDO DE HUMEDAD
7 Cdigo del recipiente. 8 Peso del recipiente+suelo hmedo (g) 9 Peso del recipiente+suelo seco (g) 10 Peso del agua (g) (8)-(9) 11 Peso del recipiente (g) 12 Peso del suelo seco (g) (9)-(11) 13 Contenido de humedad 100x(10)/(12) 14 Contenido de humedad promedio 100x(prom13) 15 Peso volumtrico seco (g/cm) (6)/1+(14) V19 246.20 239.35 6.85 V20 260.25 253.10 7.15 16.45 236.65 3.02 V11 211.19 203.95 7.24 16.50 187.45 3.86 4.0 2.16 V12 203.40 196.05 7.35 15.10 180.95 4.06 V13 225.95 216.35 9.60 14.85 201.50 4.76 4.9 2.20 V14 270.05 257.75 12.30 17.65 240.10 5.12 V15 227.75 214.50 13.25 14.70 199.80 6.63 6.5 2.19 V16 252.75 238.60 14.15 14.55 224.05 6.32 249.30 233.35 15.95 14.20 219.15 7.28 7.2 2.15 267.30 250.50 16.80 14.90 235.60 7.13
15.1
224.25 3.05 3.0 2.10
CURVA DE COMPACTACION
2.20
M.D.S
2.18
2.16
2.14
2.12
2.10
Humedad (%)
Fraccion gruesa : Retenido en el tamiz 3/4" :40.86 Gravedad de slidos :2.74 Contenido de Humedad :0.33 %
Correcciones por Grava : Norma ASTM - D 4718 Humedad Corregida :3.4 % Densidad Seca Corregida :2.40 g/cm
O.C.H.
MAYO, 2009
Proyecto 1-M-373-002
Anexos
MAYO, 2009
ANEXO 4
ANALISIS DE ESTABILIDAD FISICA
Proyecto 1-M-373-002
Anexos
MAYO, 2009
Proyecto 1-M-373-002
Anexos
MAYO, 2009
Proyecto 1-M-373-002
Anexos
MAYO, 2009
Proyecto 1-M-373-002
Anexos
MAYO, 2009
ANEXO 5
ANALISIS HIDROLOGICO Y DISEO HIDRAULICO
Proyecto 1-M-373-002
Anexos
MAYO, 2009
A. CALCULOS HIDROLOGICOS
Proyecto 1-M-373-002
Anexos
Distribucion Normal
N 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 Suma (mm) Media (mm) D.Est. (mm) Ao 1992 2003 1964 1978 1971 2007 1996 1988 1991 1982 2005 2004 1980 2006 1993 1985 1967 1979 1975 1990 2000 1974 1969 1965 1966 1976 1973 1981 1999 1968 2002 1994 2001 1977 1983 1998 1984 1970 1989 1995 1986 1972 1997 1987 P (mm) 0.30 6.70 7.20 9.30 10.10 10.60 11.30 11.50 11.90 12.10 12.10 13.40 13.50 13.60 13.80 14.00 14.10 15.10 15.90 16.90 17.10 17.20 17.50 17.60 17.60 18.70 20.90 21.60 22.20 23.80 26.20 27.90 30.10 34.50 38.00 39.40 41.00 42.60 43.10 44.10 53.00 55.00 63.90 68.50 749.70 35.70 15.22 P(x) 0.0222 0.0444 0.0667 0.0889 0.1111 0.1333 0.1556 0.1778 0.2000 0.2222 0.2444 0.2667 0.2889 0.3111 0.3333 0.3556 0.3778 0.4000 0.4222 0.4444 0.4667 0.4889 0.5111 0.5333 0.5556 0.5778 0.6000 0.6222 0.6444 0.6667 0.6889 0.7111 0.7333 0.7556 0.7778 0.8000 0.8222 0.8444 0.8667 0.8889 0.9111 0.9333 0.9556 0.9778 Z -2.33 -1.91 -1.87 -1.73 -1.68 -1.65 -1.60 -1.59 -1.56 -1.55 -1.55 -1.47 -1.46 -1.45 -1.44 -1.43 -1.42 -1.35 -1.30 -1.24 -1.22 -1.22 -1.20 -1.19 -1.19 -1.12 -0.97 -0.93 -0.89 -0.78 -0.62 -0.51 -0.37 -0.08 0.15 0.24 0.35 0.45 0.49 0.55 1.14 1.27 1.85 2.16 F(Z) 0.0004 0.0281 0.0307 0.0418 0.0465 0.0495 0.0548 0.0559 0.0594 0.0606 0.0606 0.0708 0.0722 0.0735 0.0749 0.0764 0.0780 0.0885 0.0968 0.1075 0.1112 0.1112 0.1551 0.1551 0.1170 0.1170 0.1314 0.1660 0.1762 0.2177 0.2766 0.3050 0.3557 0.4681 0.5596 0.5948 0.6368 0.6736 0.6879 0.7088 0.8729 0.8980 0.9678 0.9846 Dmx = Dx F(Z)-P(x) 0.0218 0.0164 0.0359 0.0471 0.0646 0.0839 0.1008 0.1219 0.1406 0.1617 0.1839 0.1959 0.2167 0.2376 0.2584 0.2792 0.2998 0.3115 0.3254 0.3370 0.3554 0.3777 0.3560 0.3783 0.4385 0.4608 0.4686 0.4562 0.4683 0.4490 0.4123 0.4061 0.3776 0.2874 0.2182 0.2052 0.1854 0.1708 0.1787 0.1800 0.0383 0.0354 0.0123 0.0068 0.4686
Distribucion Log-Normal
N 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 Suma (mm) Media (mm) D.Est. (mm) Ao 1992 2003 1964 1978 1971 2007 1996 1988 1991 1982 2005 2004 1980 2006 1993 1985 1967 1979 1975 1990 2000 1974 1969 1965 1966 1976 1973 1981 1999 1968 2002 1994 2001 1977 1983 1998 1984 1970 1989 1995 1986 1972 1997 1987 P (mm) X 0.30 6.70 7.20 9.30 10.10 10.60 11.30 11.50 11.90 12.10 12.10 13.40 13.50 13.60 13.80 14.00 14.10 15.10 15.90 16.90 17.10 17.20 17.50 17.60 17.60 18.70 20.90 21.60 22.20 23.80 26.20 27.90 30.10 34.50 38.00 39.40 41.00 42.60 43.10 44.10 53.00 55.00 63.90 68.50 1034.90 23.52 15.95 Ln P (Y) -1.2040 1.9021 1.9741 2.2300 2.3125 2.3609 2.4248 2.4423 2.4765 2.4932 2.4932 2.5953 2.6027 2.6101 2.6247 2.6391 2.6462 2.7147 2.7663 2.8273 2.8391 2.8449 2.8622 2.8679 2.8679 2.9285 3.0397 3.0727 3.1001 3.1697 3.2658 3.3286 3.4045 3.5410 3.6376 3.6738 3.7136 3.7519 3.7635 3.7865 3.9703 4.0073 4.1573 4.2268 127.75 2.90 0.87 P(x) 0.0222 0.0444 0.0667 0.0889 0.1111 0.1333 0.1556 0.1778 0.2000 0.2222 0.2444 0.2667 0.2889 0.3111 0.3333 0.3556 0.3778 0.4000 0.4222 0.4444 0.4667 0.4889 0.5111 0.5333 0.5556 0.5778 0.6000 0.6222 0.6444 0.6667 0.6889 0.7111 0.7333 0.7556 0.7778 0.8000 0.8222 0.8444 0.8667 0.8889 0.9111 0.9333 0.9556 0.9778 Z -4.75 -1.16 -1.07 -0.78 -0.68 -0.63 -0.55 -0.53 -0.49 -0.47 -0.47 -0.36 -0.35 -0.34 -0.32 -0.31 -0.30 -0.22 -0.16 -0.09 -0.07 -0.07 -0.05 -0.04 -0.04 0.03 0.16 0.20 0.23 0.31 0.42 0.49 0.58 0.74 0.85 0.89 0.94 0.98 0.99 1.02 1.23 1.28 1.45 1.53 F(Z) 0.0003 0.1230 0.1423 0.2177 0.2483 0.2644 0.2912 0.2981 0.3121 0.3192 0.3192 0.3594 0.3632 0.3669 0.3745 0.3783 0.3821 0.4129 0.4364 0.4641 0.4721 0.4721 0.5199 0.5160 0.5160 0.5120 0.5636 0.5793 0.5910 0.6217 0.6628 0.6879 0.7190 0.8159 0.8023 0.8133 0.8264 0.8365 0.8389 0.8461 0.8907 0.9357 0.9265 0.9370 Dmx = Dx F(Z)-P(x) 0.0219 0.0786 0.0756 0.1288 0.1371 0.1310 0.1356 0.1203 0.1121 0.0970 0.0747 0.0928 0.0743 0.0558 0.0411 0.0227 0.0043 0.0129 0.0142 0.0197 0.0054 0.0168 0.0088 0.0174 0.0396 0.0658 0.0364 0.0430 0.0535 0.0449 0.0261 0.0232 0.0143 0.0604 0.0246 0.0133 0.0042 0.0080 0.0278 0.0427 0.0205 0.0024 0.0291 0.0408 0.1371
Distribucion Gumbel
N 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 Suma (mm) Media (mm) D.Est. (S) alfa mu Ao 1992 2003 1964 1978 1971 2007 1996 1988 1991 1982 2005 2004 1980 2006 1993 1985 1967 1979 1975 1990 2000 1974 1969 1965 1966 1976 1973 1981 1999 1968 2002 1994 2001 1977 1983 1998 1984 1970 1989 1995 1986 1972 1997 1987 P (mm) (X) 0.30 6.70 7.20 9.30 10.10 10.60 11.30 11.50 11.90 12.10 12.10 13.40 13.50 13.60 13.80 14.00 14.10 15.10 15.90 16.90 17.10 17.20 17.50 17.60 17.60 18.70 20.90 21.60 22.20 23.80 26.20 27.90 30.10 34.50 38.00 39.40 41.00 42.60 43.10 44.10 53.00 55.00 63.90 68.50 1034.90 23.52 15.77 14.84 15.75 P(X) 0.0222 0.0444 0.0667 0.0889 0.1111 0.1333 0.1556 0.1778 0.2000 0.2222 0.2444 0.2667 0.2889 0.3111 0.3333 0.3556 0.3778 0.4000 0.4222 0.4444 0.4667 0.4889 0.5111 0.5333 0.5556 0.5778 0.6000 0.6222 0.6444 0.6667 0.6889 0.7111 0.7333 0.7556 0.7778 0.8000 0.8222 0.8444 0.8667 0.8889 0.9111 0.9333 0.9556 0.9778 z -1.04 -0.61 -0.58 -0.43 -0.38 -0.35 -0.30 -0.29 -0.26 -0.25 -0.25 -0.16 -0.15 -0.15 -0.13 -0.12 -0.11 -0.04 0.01 0.08 0.09 0.10 0.12 0.12 0.12 0.20 0.35 0.39 0.43 0.54 0.70 0.82 0.97 1.26 1.50 1.59 1.70 1.81 1.84 1.91 2.51 2.65 3.25 3.56 F(z) 0.0588 0.1587 0.1687 0.2134 0.2314 0.2429 0.2593 0.2640 0.2735 0.2783 0.2783 0.3098 0.3123 0.3147 0.3196 0.3245 0.3270 0.3517 0.3716 0.3963 0.4013 0.4037 0.4111 0.4136 0.4136 0.4405 0.4932 0.5095 0.5233 0.5592 0.6099 0.6434 0.6837 0.7538 0.7999 0.8162 0.8333 0.8490 0.8536 0.8624 0.9220 0.9315 0.9618 0.9718 Dmx = Dx F(z)-P(x) 0.0366 0.1143 0.1020 0.1245 0.1203 0.1096 0.1037 0.0862 0.0735 0.0561 0.0339 0.0432 0.0234 0.0036 0.0137 0.0310 0.0508 0.0483 0.0507 0.0481 0.0654 0.0852 0.1000 0.1197 0.1420 0.1373 0.1068 0.1127 0.1211 0.1075 0.0790 0.0677 0.0496 0.0018 0.0221 0.0162 0.0111 0.0045 0.0131 0.0264 0.0109 0.0019 0.0062 0.0059 0.0264
Ao 1987 1997 1972 1986 1995 1989 1970 1984 1998 1983 1977 2001 1994 2002 1968 1999 1981 1973 1976 1965 1966 1969 1974 2000 1990 1975 1979 1967 1985 1993 2006 1980 2004 1982 2005 1991 1988 1996 2007 1971 1978 1964 2003 1992
P(x) 0.0238 0.0476 0.0714 0.0952 0.1190 0.1429 0.1667 0.1905 0.2143 0.2381 0.2619 0.2857 0.3095 0.3333 0.3571 0.3810 0.4048 0.4286 0.4524 0.4762 0.5000 0.5238 0.5476 0.5714 0.5952 0.6190 0.6429 0.6667 0.6905 0.7143 0.7381 0.7619 0.7857 0.8095 0.8333 0.8571 0.8810 0.9048 0.9286 0.9524 0.9762 1.0000 1.0238 1.0476 0.1601
(*): De Tabla 12.3.1 del Libro de Hidrologia Aplicada de Ven Te Chow, Pag. 404; por interpolacin segn el valor de k T Coeficiente de Asimetria Ag Periodo de retorno, aos 5 10 Nivel de probabilidad, porcentaje 20 10 0.20 0.10 0.732 0.705 1.340 1.337
1.2335
-1.4271
-0.8420
-0.2000
0.7275
1.3395
2.0939
2.6394
3.1694
Ao 1987 1997 1972 1986 1995 1989 1970 1984 1998 1983 1977 2001 1994 2002 1968 1999 1981 1973 1976 1965 1966 1969 1974 2000 1990 1975 1979 1967 1985 1993 2006 1980 2004 1982 2005 1991 1988 1996 2007 1971 1978 1964 2003 1992
P(x) 0.0222 0.0444 0.0667 0.0889 0.1111 0.1333 0.1556 0.1778 0.2000 0.2222 0.2444 0.2667 0.2889 0.3111 0.3333 0.3556 0.3778 0.4000 0.4222 0.4444 0.4667 0.4889 0.5111 0.5333 0.5556 0.5778 0.6000 0.6222 0.6444 0.6667 0.6889 0.7111 0.7333 0.7556 0.7778 0.8000 0.8222 0.8444 0.8667 0.8889 0.9111 0.9333 0.9556 0.9778 0.1900
(*): De Tabla 12.3.1 del Libro de Hidrologia Aplicada de Ven Te Chow, Pag. 404; por interpolacin segn el valor de k T Coeficiente de Asimetria Ag Periodo de retorno, aos 5 10 Nivel de probabilidad, porcentaje 20 10 0.20 0.10 0.752 0.725 0.844 0.795
-2.2 -2.4
-2.3188
-3.7614
-0.5520 0.3425 Tabla Resumen Dmax 0.4686 0.1371 0.0264 0.1601 0.1900 Dcritico 0.2 0.2 0.2 0.2 0.2
0.7360
0.8149
0.8494
0.8584
0.8616
Distribucion Normal
N 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 Suma (mm) Media (mm) D.Est. (mm) Ao 1966 2003 1978 1996 1985 1993 1982 1983 1975 2006 1974 1971 1980 1977 1969 1999 1973 1988 1979 1994 1986 2001 2002 1967 1995 2000 2005 1998 1970 1981 1968 1976 1997 P (mm) 0.10 0.10 0.50 1.90 2.00 2.00 2.50 2.80 4.00 4.20 4.30 4.50 5.30 5.70 7.00 7.10 7.30 8.40 10.10 11.00 11.30 11.50 13.70 14.00 15.20 15.60 16.50 18.50 19.60 23.00 29.00 30.00 33.00 134.60 26.92 5.47 P(x) 0.0294 0.0588 0.0882 0.1176 0.1471 0.1765 0.2059 0.2353 0.2647 0.2941 0.3235 0.3529 0.3824 0.4118 0.4412 0.4706 0.5000 0.5294 0.5588 0.5882 0.6176 0.6471 0.6765 0.7059 0.7353 0.7647 0.7941 0.8235 0.8529 0.8824 0.9118 0.9412 0.9706 Z -4.90 -4.90 -4.83 -4.57 -4.55 -4.55 -4.46 -4.41 -4.19 -4.15 -4.13 -4.10 -3.95 -3.88 -3.64 -3.62 -3.59 -3.39 -3.07 -2.91 -2.86 -2.82 -2.42 -2.36 -2.14 -2.07 -1.90 -1.54 -1.34 -0.72 0.38 0.56 1.11 F(Z) 0.00003 0.00003 0.00003 0.00003 0.00003 0.00003 0.00003 0.00003 0.00003 0.00003 0.00003 0.00003 0.00004 0.00005 0.00015 0.00014 0.00017 0.00035 0.00107 0.01181 0.00212 0.00240 0.00776 0.00914 0.01618 0.01923 0.02872 0.06178 0.09012 0.23576 0.64803 0.71226 0.86650 Dmx = Dx F(Z)-P(x) 0.0294 0.0588 0.0882 0.1176 0.1470 0.1764 0.2059 0.2353 0.2647 0.2941 0.3235 0.3529 0.3823 0.4117 0.4410 0.4704 0.4998 0.5291 0.5578 0.5764 0.6155 0.6447 0.6687 0.6967 0.7191 0.7455 0.7654 0.7617 0.7628 0.6466 0.2637 0.2289 0.1041 0.6466
Distribucion Log-Normal
N 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 Suma (mm) Media (mm) D.Est. (mm) Ao 1966 2003 1978 1996 1985 1993 1982 1983 1975 2006 1974 1971 1980 1977 1969 1999 1973 1988 1979 1994 1986 2001 2002 1967 1995 2000 2005 1998 1970 1981 1968 1976 1997 P (mm) X 0.10 0.10 0.50 1.90 2.00 2.00 2.50 2.80 4.00 4.20 4.30 4.50 5.30 5.70 7.00 7.10 7.30 8.40 10.10 11.00 11.30 11.50 13.70 14.00 15.20 15.60 16.50 18.50 19.60 23.00 29.00 30.00 33.00 341.70 10.35 8.91 Ln P (Y) -2.3026 -2.3026 -0.6931 0.6419 0.6931 0.6931 0.9163 1.0296 1.3863 1.4351 1.4586 1.5041 1.6677 1.7405 1.9459 1.9601 1.9879 2.1282 2.3125 2.3979 2.4248 2.4423 2.6174 2.6391 2.7213 2.7473 2.8034 2.9178 2.9755 3.1355 3.3673 3.4012 3.4965 58.29 1.77 1.41 P(x) 0.0294 0.0588 0.0882 0.1176 0.1471 0.1765 0.2059 0.2353 0.2647 0.2941 0.3235 0.3529 0.3824 0.4118 0.4412 0.4706 0.5000 0.5294 0.5588 0.5882 0.6176 0.6471 0.6765 0.7059 0.7353 0.7647 0.7941 0.8235 0.8529 0.8824 0.9118 0.9412 0.9706 Z -2.89 -2.89 -1.74 -0.80 -0.76 -0.76 -0.60 -0.52 -0.27 -0.24 -0.22 -0.19 -0.07 -0.02 0.13 0.14 0.16 0.26 0.39 0.45 0.47 0.48 0.60 0.62 0.68 0.70 0.74 0.82 0.86 0.97 1.14 1.16 1.23 F(Z) 0.0019 0.0019 0.0409 0.2119 0.2236 0.2236 0.2743 0.3015 0.3936 0.4016 0.2776 0.4247 0.4721 0.4920 0.5517 0.5557 0.5636 0.6026 0.6517 0.6736 0.6808 0.6844 0.7258 0.7324 0.7518 0.7580 0.7704 0.7939 0.8051 0.8340 0.8729 0.8770 0.8907 Dmx = Dx F(Z)-P(x) 0.0275 0.0569 0.0473 0.0942 0.0766 0.0472 0.0684 0.0662 0.1289 0.1075 0.0459 0.0717 0.0897 0.0803 0.1105 0.0851 0.0636 0.0732 0.0929 0.0854 0.0632 0.0373 0.0493 0.0265 0.0165 0.0067 0.0238 0.0296 0.0478 0.0484 0.0389 0.0642 0.0799 0.1289
Distribucion Gumbel
N 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 Suma (mm) Media (mm) D.Est. (S) alfa mu Ao 1966 2003 1978 1996 1985 1993 1982 1983 1975 2006 1974 1971 1980 1977 1969 1999 1973 1988 1979 1994 1986 2001 2002 1967 1995 2000 2005 1998 1970 1981 1968 1976 1997 P (mm) (X) 0.10 0.10 0.50 1.90 2.00 2.00 2.50 2.80 4.00 4.20 4.30 4.50 5.30 5.70 7.00 7.10 7.30 8.40 10.10 11.00 11.30 11.50 13.70 14.00 15.20 15.60 16.50 18.50 19.60 23.00 29.00 30.00 33.00 341.70 10.35 8.78 8.26 6.03 P(X) 0.0294 0.0588 0.0882 0.1176 0.1471 0.1765 0.2059 0.2353 0.2647 0.2941 0.3235 0.3529 0.3824 0.4118 0.4412 0.4706 0.5000 0.5294 0.5588 0.5882 0.6176 0.6471 0.6765 0.7059 0.7353 0.7647 0.7941 0.8235 0.8529 0.8824 0.9118 0.9412 0.9706 z -0.72 -0.72 -0.67 -0.50 -0.49 -0.49 -0.43 -0.39 -0.25 -0.22 -0.21 -0.19 -0.09 -0.04 0.12 0.13 0.15 0.29 0.49 0.60 0.64 0.66 0.93 0.96 1.11 1.16 1.27 1.51 1.64 2.05 2.78 2.90 3.27 F(z) 0.1287 0.1287 0.1418 0.1923 0.1961 0.1961 0.2158 0.2280 0.2784 0.2871 0.2914 0.3001 0.3354 0.3532 0.4110 0.4154 0.4242 0.4721 0.5428 0.5782 0.5896 0.5971 0.6736 0.6832 0.7193 0.7306 0.7547 0.8018 0.8242 0.8797 0.9399 0.9466 0.9625 Dmx = Dx F(z)-P(x) 0.0993 0.0699 0.0536 0.0746 0.0491 0.0197 0.0099 0.0073 0.0137 0.0070 0.0321 0.0528 0.0469 0.0586 0.0302 0.0552 0.0758 0.0573 0.0160 0.0100 0.0280 0.0500 0.0028 0.0227 0.0160 0.0341 0.0395 0.0218 0.0288 0.0026 0.0281 0.0054 0.0080 0.0993
Ao 1997 1976 1968 1981 1970 1998 2005 2000 1995 1967 2002 2001 1986 1994 1979 1988 1973 1999 1969 1977 1980 1971 1974 2006 1975 1983 1982 1985 1993 1996 1978 1966 2003
kT 2.5404 2.2039 2.0917 1.4186 1.0372 0.9138 0.6894 0.5884 0.5436 0.4090 0.3753 0.1285 0.1061 0.0724 -0.0286 -0.2193 -0.3427 -0.3651 -0.3763 -0.5222 -0.5670 -0.6568 -0.6792 -0.6904 -0.7129 -0.8475 -0.8811 -0.9372 -0.9372 -0.9484 -1.1055 -1.1504 -1.1504
F(kT) 0.0210 0.0342 0.0370 0.0934 0.1513 0.1723 0.2198 0.2526 0.2671 0.3109 0.3218 0.4020 0.4093 0.4202 0.4530 0.5204 0.5752 0.5851 0.5901 0.6548 0.6747 0.7145 0.7244 0.7294 0.7393 0.4985 0.8140 0.8389 0.8389 0.8438 0.9135 0.9334 0.8820 Dmx =
P(x) 0.0060 0.0119 0.0179 0.0238 0.0298 0.0357 0.0417 0.0476 0.0536 0.0595 0.0655 0.0714 0.0774 0.0833 0.0893 0.0952 0.1012 0.1071 0.1131 0.1190 0.1250 0.1310 0.1369 0.1429 0.1488 0.1548 0.1607 0.1667 0.1726 0.1786 0.1845 0.1905 0.1964 0.7429
(*): De Tabla 12.3.1 del Libro de Hidrologia Aplicada de Ven Te Chow, Pag. 404; por interpolacin segn el valor de kT Coeficiente de Asimetria Ag Periodo de retorno, aos 5 10 Nivel de probabilidad, porcentaje 20 10 0.20 0.10 0.758 0.732 1.340 1.340
1.0594
-1.5467
-0.8496
-0.1732
0.7503
1.3400
2.0561
2.5670
3.0960
Ao 1997 1976 1968 1981 1970 1998 2005 2000 1995 1967 2002 2001 1986 1994 1979 1988 1973 1999 1969 1977 1980 1971 1974 2006 1975 1983 1982 1985 1993 1996 1978 1966 2003
kT 1.2274 1.1597 1.1357 0.9713 0.8578 0.8168 0.7356 0.6959 0.6774 0.6191 0.6037 0.4795 0.4671 0.4480 0.3875 0.2567 0.1571 0.1374 0.1274 -0.0184 -0.0700 -0.1861 -0.2183 -0.2350 -0.2696 -0.5226 -0.6030 -0.7613 -0.7613 -0.7977 -1.7448 -2.8865 -2.8865
F(kT) 0.0113 0.0329 0.0418 0.1195 0.1804 0.2024 0.2447 0.2654 0.2750 0.3054 0.3134 0.3781 0.3846 0.3945 0.4261 0.4942 0.5286 0.5349 0.5382 0.5852 0.6019 0.6394 0.6498 0.6552 0.6663 0.7480 0.7740 0.8055 0.8055 0.8081 0.8755 0.9567 0.9567 Dmx =
P(x) 0.0294 0.0588 0.0882 0.1176 0.1471 0.1765 0.2059 0.2353 0.2647 0.2941 0.3235 0.3529 0.3824 0.4118 0.4412 0.4706 0.5000 0.5294 0.5588 0.5882 0.6176 0.6471 0.6765 0.7059 0.7353 0.7647 0.7941 0.8235 0.8529 0.8824 0.9118 0.9412 0.9706 0.0742
(*): De Tabla 12.3.1 del Libro de Hidrologia Aplicada de Ven Te Chow, Pag. 404; por interpolacin segn el valor de kT Coeficiente de Asimetria Ag Periodo de retorno, aos 5 10 Nivel de probabilidad, porcentaje 20 10 0.20 0.10 0.832 0.817 1.041 0.994
-1.4 -1.6
-1.5422
-3.3542
-0.6837 0.2456 Tabla Resumen Dmax 0.6466 0.1289 0.0993 0.7429 0.0742 Dcritico 0.21 0.21 0.21 0.21 0.21
0.8213
1.0076
1.1397
1.1961
1.2320
Observaciones
Distribicin aceptada
--- Input Data --Analysis Name: Estacin Yanaquihua Description: Data Set Name: Estacin Yanaquihua DSS File Name: D:\Archivos Oso\Chorunga\Cuenca_Chorunga\Cuenca_Chorunga.dss DSS Pathname: /ESTACIN YANAQUIHUA//RAINFALL-PEAK//IR-CENTURY/REGISTROS/ Start Date: End Date: Project Path: D:\Archivos Oso\Chorunga\Cuenca_Chorunga Report File Name: D:\Archivos Oso\Chorunga\Cuenca_Chorunga\GeneralFrequencyResults\Estacin_Yanaquihua\Estaci n_Yanaquihua.rpt Result File Name: D:\Archivos Oso\Chorunga\Cuenca_Chorunga\GeneralFrequencyResults\Estacin_Yanaquihua\Estaci n_Yanaquihua.xml Plotting Position Type: Weibull Probability Distribution Type: Normal Use Log Transform Compute Expected Probability Curve Upper Confidence Level: 0.05 Lower Confidence Level: 0.95
Display ordinate values using 0 digits in fraction part of value --- End of Input Data ---
<< Skew Weighting >> --------------------------------------------------------------Based on 44 events, mean-square error of station skew = 0,663 Mean-square error of regional skew is undefined. ---------------------------------------------------------------
<< Frequency Curve >> Estacin Yanaquihua ------------------------------------------------------------------| Computed Expected | Percent | Confidence Limits | | Curve Probability | Chance | 0,05 0,95 | | RAINFALL, mm | Exceedance | RAINFALL, mm | |-------------------------|-------------|-------------------------| | 219,999 261,058 | 0,2 | 395,422 143,891 | | 169,364 192,788 | 0,5 | 289,202 114,634 | | 136,483 151,049 | 1,0 | 223,588 94,950 | | 107,808 116,349 | 2,0 | 168,973 77,200 | | 75,685 79,388 | 5,0 | 111,338 56,432 | | 55,272 56,956 | 10,0 | 77,184 42,536 | | 37,775 38,369 | 20,0 | 49,941 29,956 | | 18,237 18,237 | 50,0 | 22,680 14,665 | | 8,805 8,669 | 80,0 | 11,103 6,660 | | 6,018 5,840 | 90,0 | 7,819 4,309 | | 4,395 4,190 | 95,0 | 5,894 2,987 | | 2,437 2,202 | 99,0 | 3,503 1,488 | |-------------------------|-------------|-------------------------|
<< Systematic Statistics >> Estacin Yanaquihua ---------------------------------------------------------------| Log Transform: | | | RAINFALL, mm | Number of Events | |------------------------------|-------------------------------| | Mean 1,2610 | Historic Events 0 | | Standard Dev 0,3757 | High Outliers 0 | | Station Skew -2,3188 | Low Outliers 0 | | Regional Skew --- | Zero Events 0 | | Weighted Skew --- | Missing Events 0 | | Adopted Skew 0,0000 | Systematic Events 44 | |------------------------------|-------------------------------| --- End of Preliminary Results ---
---------------------<< Low Outlier Test >> ---------------------Based on 44 events, 10 percent outlier test value K(N) = 2,719 1 low outlier(s) identified below test value of 1,74 Statistics and frequency curve adjusted for 1 low outliers.
<< Systematic Statistics >> Estacin Yanaquihua ---------------------------------------------------------------| Log Transform: | | | RAINFALL, mm | Number of Events | |------------------------------|-------------------------------| | Mean 1,3024 | Historic Events 0 | | Standard Dev 0,2589 | High Outliers 0 | | Station Skew 0,3943 | Low Outliers 1 | | Regional Skew --- | Zero Events 0 | | Weighted Skew --- | Missing Events 0 | | Adopted Skew 0,0000 | Systematic Events 44 | |------------------------------|-------------------------------|
----------------------<< High Outlier Test >> ----------------------Based on 43 events, 10 percent outlier test value K(N) = 2,71 0 high outlier(s) identified above test value of 100,93
--- Final Results --<< Plotting Positions >> Estacin Yanaquihua -------------------------------------------------------------------| Events Analyzed | Ordered Events | | RAINFALL | Water RAINFALL Weibull | | Day Mon Year mm | Rank Year mm Plot Pos | |---------------------------|--------------------------------------| | 30 ene 1964 7,2000 | 1 1987 68,5000 2,22 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene ene 1965 1966 1967 1968 1969 1970 1971 1972 1973 1974 1975 1976 1977 1978 1979 1980 1981 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 17,6000 17,6000 14,1000 23,8000 17,5000 42,6000 10,1000 55,0000 20,9000 17,2000 15,9000 18,7000 34,5000 9,3000 15,1000 13,5000 21,6000 12,1000 38,0000 41,0000 14,0000 53,0000 68,5000 11,5000 43,1000 16,9000 11,9000 0,3000 13,8000 27,9000 44,1000 11,3000 63,9000 39,4000 22,2000 17,1000 30,1000 26,2000 6,7000 13,4000 12,1000 13,6000 10,6000 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 1997 1972 1986 1995 1989 1970 1984 1998 1983 1977 2001 1994 2002 1968 1999 1981 1973 1976 1966 1965 1969 1974 2000 1990 1975 1979 1967 1985 1993 2006 1980 2004 2005 1982 1991 1988 1996 2007 1971 1978 1964 2003 1992 63,9000 55,0000 53,0000 44,1000 43,1000 42,6000 41,0000 39,4000 38,0000 34,5000 30,1000 27,9000 26,2000 23,8000 22,2000 21,6000 20,9000 18,7000 17,6000 17,6000 17,5000 17,2000 17,1000 16,9000 15,9000 15,1000 14,1000 14,0000 13,8000 13,6000 13,5000 13,4000 12,1000 12,1000 11,9000 11,5000 11,3000 10,6000 10,1000 9,3000 7,2000 6,7000 0,3000* 4,44 6,67 8,89 11,11 13,33 15,56 17,78 20,00 22,22 24,44 26,67 28,89 31,11 33,33 35,56 37,78 40,00 42,22 44,44 46,67 48,89 51,11 53,33 55,56 57,78 60,00 62,22 64,44 66,67 68,89 71,11 73,33 75,56 77,78 80,00 82,22 84,44 86,67 88,89 91,11 93,33 95,56 97,78 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
|---------------------------|--------------------------------------| * Outlier
<< Skew Weighting >> --------------------------------------------------------------Based on 44 events, mean-square error of station skew = 0,146 Mean-square error of regional skew is undefined. ---------------------------------------------------------------
<< Frequency Curve >> Estacin Yanaquihua ------------------------------------------------------------------| Computed Expected | Percent | Confidence Limits | | Curve Probability | Chance | 0,05 0,95 | | RAINFALL, mm | Exceedance | RAINFALL, mm | |-------------------------|-------------|-------------------------| | 110,450 124,321 | 0,2 | 165,658 82,356 | | 92,179 100,815 | 0,5 | 133,440 70,379 | | 79,400 85,167 | 1,0 | 111,693 61,784 | | 67,454 71,105 | 2,0 | 92,032 53,548 | | 52,819 54,593 | 5,0 | 68,974 43,118 | | 42,503 43,394 | 10,0 | 53,540 35,464 | | 32,669 33,024 | 20,0 | 39,625 27,830 | | 19,747 19,747 | 50,0 | 22,960 16,985 | | 11,937 11,809 | 80,0 | 14,012 9,841 | | 9,175 8,986 | 90,0 | 10,996 7,284 | | 7,383 7,143 | 95,0 | 9,044 5,654 | | 4,911 4,579 | 99,0 | 6,312 3,491 | |-------------------------|-------------|-------------------------|
<< Synthetic Statistics >> Estacin Yanaquihua ---------------------------------------------------------------| Log Transform: | | | RAINFALL, mm | Number of Events | |------------------------------|-------------------------------| | Mean 1,2955 | Historic Events 0 | | Standard Dev 0,2598 | High Outliers 0 | | Station Skew 0,4037 | Low Outliers 1 | | Regional Skew --- | Zero Events 0 | | Weighted Skew --- | Missing Events 0 | | Adopted Skew 0,0000 | Systematic Events 44 | |------------------------------|-------------------------------|
--- Input Data --Analysis Name: Estacin Caravel Description: Data Set Name: Estacin Caravel DSS File Name: D:/Archivos Oso/Chorunga/Cuenca_Chorunga/Cuenca_Chorunga.dss DSS Pathname: /ESTACIN CARAVEL//RAINFALL-PEAK//IR-CENTURY/REGISTROS/ Start Date: End Date: Project Path: D:\Archivos Oso\Chorunga\Cuenca_Chorunga Report File Name: D:\Archivos Oso\Chorunga\Cuenca_Chorunga\GeneralFrequencyResults\Estacin_Caravel\Estacin_ Caravel.rpt Result File Name: D:\Archivos Oso\Chorunga\Cuenca_Chorunga\GeneralFrequencyResults\Estacin_Caravel\Estacin_ Caravel.xml Plotting Position Type: Weibull Probability Distribution Type: Pearson Type III Use Log Transform Compute Expected Probability Curve Upper Confidence Level: 0.05 Lower Confidence Level: 0.95 Skew Option: Use Station Skew Regional Skew: --Regional Skew MSE: --Display ordinate values using 0 digits in fraction part of value --- End of Input Data ---
<< Skew Weighting >> --------------------------------------------------------------Based on 33 events, mean-square error of station skew = 0,454 Mean-square error of regional skew is undefined. ---------------------------------------------------------------
<< Frequency Curve >> Estacin Caravel ------------------------------------------------------------------| Computed Expected | Percent | Confidence Limits | | Curve Probability | Chance | 0,05 0,95 | | RAINFALL, mm | Exceedance | RAINFALL, mm | |-------------------------|-------------|-------------------------| | 35,1761 35,6879 | 0,2 | 66,9443 21,6553 | | 34,2658 34,8769 | 0,5 | 64,8877 21,1513 | | 33,1748 33,8667 | 1,0 | 62,4391 20,5445 | | 31,5519 32,2524 | 2,0 | 58,8305 19,6363 | | 28,1660 28,8584 | 5,0 | 51,4380 17,7185 | | 24,2232 24,6973 | 10,0 | 43,0786 15,4411 | | 18,6308 18,9018 | 20,0 | 31,7398 12,1136 | | 8,2738 8,2738 | 50,0 | 12,7751 5,5251 | | 2,2300 2,1208 | 80,0 | 3,3903 1,3471 | | 0,8953 0,7996 | 90,0 | 1,4669 0,4630 | | 0,3714 0,3053 | 95,0 | 0,6766 0,1599 | | 0,0517 0,0304 | 99,0 | 0,1255 0,0140 | |-------------------------|-------------|-------------------------|
<< Systematic Statistics >> Estacin Caravel ---------------------------------------------------------------| Log Transform: | | | RAINFALL, mm | Number of Events | |------------------------------|-------------------------------| | Mean 0,7671 | Historic Events 0 | | Standard Dev 0,6122 | High Outliers 0 | | Station Skew -1,5422 | Low Outliers 0 | | Regional Skew --- | Zero Events 0 | | Weighted Skew --- | Missing Events 0 | | Adopted Skew -1,5422 | Systematic Events 33 | |------------------------------|-------------------------------| --- End of Preliminary Results ---
---------------------<< Low Outlier Test >> ---------------------Based on 33 events, 10 percent outlier test value K(N) = 2,604 2 low outlier(s) identified below test value of 0,15 Statistics and frequency curve adjusted for 2 low outliers.
<< Systematic Statistics >> Estacin Caravel ---------------------------------------------------------------| Log Transform: | | | RAINFALL, mm | Number of Events | |------------------------------|-------------------------------| | Mean 0,8811 | Historic Events 0 | | Standard Dev 0,4221 | High Outliers 0 | | Station Skew -0,6986 | Low Outliers 2 | | Regional Skew --- | Zero Events 0 | | Weighted Skew --- | Missing Events 0 | | Adopted Skew -1,5422 | Systematic Events 33 | |------------------------------|-------------------------------|
----------------------<< High Outlier Test >> ----------------------Based on 31 events, 10 percent outlier test value K(N) = 2,577 0 high outlier(s) identified above test value of 93,08
--- Final Results --<< Plotting Positions >> Estacin Caravel -------------------------------------------------------------------| Events Analyzed | Ordered Events | | RAINFALL | Water RAINFALL Weibull | | Day Mon Year mm | Rank Year mm Plot Pos | |---------------------------|--------------------------------------| | 30 ene 1966 0,1000 | 1 1997 33,0000 2,94 | | 30 ene 1967 14,0000 | 2 1976 30,0000 5,88 | | 30 ene 1968 29,0000 | 3 1968 29,0000 8,82 | | 30 ene 1969 7,0000 | 4 1981 23,0000 11,76 | | 30 ene 1970 19,6000 | 5 1970 19,6000 14,71 | | 30 ene 1971 4,5000 | 6 1998 18,5000 17,65 | | 30 ene 1973 7,3000 | 7 2005 16,5000 20,59 | | 30 ene 1974 4,3000 | 8 2000 15,6000 23,53 | | 30 ene 1975 4,0000 | 9 1995 15,2000 26,47 | | 30 ene 1976 30,0000 | 10 1967 14,0000 29,41 | | 30 ene 1977 5,7000 | 11 2002 13,7000 32,35 | | 30 ene 1978 0,5000 | 12 2001 11,5000 35,29 | | 30 ene 1979 10,1000 | 13 1986 11,3000 38,24 | | 30 ene 1980 5,3000 | 14 1994 11,0000 41,18 | | 30 ene 1981 23,0000 | 15 1979 10,1000 44,12 | | 30 ene 1982 2,5000 | 16 1988 8,4000 47,06 | | 30 ene 1983 2,8000 | 17 1973 7,3000 50,00 | | 30 ene 1985 2,0000 | 18 1999 7,1000 52,94 | | 30 ene 1986 11,3000 | 19 1969 7,0000 55,88 | | 30 ene 1988 8,4000 | 20 1977 5,7000 58,82 | | 30 ene 1993 2,0000 | 21 1980 5,3000 61,76 | | 30 ene 1994 11,0000 | 22 1971 4,5000 64,71 | | 30 ene 1995 15,2000 | 23 1974 4,3000 67,65 | | 30 ene 1996 1,9000 | 24 2006 4,2000 70,59 | | 30 ene 1997 33,0000 | 25 1975 4,0000 73,53 | | 30 ene 1998 18,5000 | 26 1983 2,8000 76,47 | | 30 ene 1999 7,1000 | 27 1982 2,5000 79,41 | | 30 ene 2000 15,6000 | 28 1993 2,0000 82,35 | | 30 ene 2001 11,5000 | 29 1985 2,0000 85,29 | | 30 ene 2002 13,7000 | 30 1996 1,9000 88,24 | | 30 ene 2003 0,1000 | 31 1978 0,5000 91,18 | | 30 ene 2005 16,5000 | 32 2003 0,1000* 94,12 | | 30 ene 2006 4,2000 | 33 1966 0,1000* 97,06 | |---------------------------|--------------------------------------| * Outlier
<< Skew Weighting >> --------------------------------------------------------------Based on 33 events, mean-square error of station skew = 0,218 Mean-square error of regional skew is undefined. ---------------------------------------------------------------
<< Frequency Curve >> Estacin Caravel ------------------------------------------------------------------| Computed Expected | Percent | Confidence Limits | | Curve Probability | Chance | 0,05 0,95 | | RAINFALL, mm | Exceedance | RAINFALL, mm | |-------------------------|-------------|-------------------------| | 55,7613 61,7761 | 0,2 | 104,7282 35,6787 | | 48,9987 53,4614 | 0,5 | 89,4403 31,8923 | | 43,5247 46,9415 | 1,0 | 77,4340 28,7640 | | 37,7521 40,1788 | 2,0 | 65,1657 25,3931 | | 29,6957 31,0924 | 5,0 | 48,8051 20,5386 | | 23,3214 24,0571 | 10,0 | 36,5917 16,5391 | | 16,7582 17,0657 | 20,0 | 24,8392 12,2190 | | 7,8677 7,8677 | 50,0 | 10,6939 5,8517 | | 3,1000 3,0058 | 80,0 | 4,2315 2,1147 | | 1,7690 1,6582 | 90,0 | 2,5350 1,0940 | | 1,0696 0,9600 | 95,0 | 1,6264 0,5962 | | 0,3764 0,2887 | 99,0 | 0,6628 0,1653 | |-------------------------|-------------|-------------------------|
<< Synthetic Statistics >> Estacin Caravel ---------------------------------------------------------------| Log Transform: | | | RAINFALL, mm | Number of Events | |------------------------------|-------------------------------| | Mean 0,8423 | Historic Events 0 | | Standard Dev 0,4458 | High Outliers 0 | | Station Skew -0,7266 | Low Outliers 2 | | Regional Skew --- | Zero Events 0 | | Weighted Skew --- | Missing Events 0 | | Adopted Skew -0,7266 | Systematic Events 33 | |------------------------------|-------------------------------|
CUENCA
ESTACION PLUVIOMETRICA
Yanaquihua
CUENCA
NC
Tc (hrs)
Tl (hrs)
Chorunga
70
108.86
20.04
9.56
Ecuacin del Tiempo de Concentracin Tiempo de concentracin = 1 x (mxima longitud de curso x 1000 x 3.28) ^ 0.8 x (S/25.4 + 1) ^ 0.7 / (1140 x pendiente ^ 0.38 ))) Ecuacin de tiempo de retardo Tiempo de retardo = ( (longitud mxima del curso / 1.6 x longitud desde centroide del rea hasta seccin de control / 1.6 / (pendiente / 100) ^ 0.5) ^ 0.38 ) Donde: Smbolo NC S Tc Tl
CUENCA
Td (min)
MAXIMA PRECIPITACION EN TIEMPO DE DURACION (mm) Tr = 50 67.3 Tr = 100 80.7 Tr = 500 117.7
Chorunga DISTRIBUCION TEMPORAL DE PRECIPITACION Si: td > 3hr n Distribucin de precipitacin : Pt = P 24hrs *(t/1440)^
1202
0.303
Si: td < 3hr n .25 Distribucin de precipitacin : Pt = P 24hrs *(180/1440)^ *(t/180)^ Pt = Precipitacin de duracin t t = duracin de la precipiacin n = constante regional
MAYO, 2009
Proyecto 1-M-373-002
Anexos
Plan: Plan 01
11/04/2009
Legend 27 26 25 WS Tr = 100 aos WS Tr = 500 aos Ground Bank Sta 24 23 22 21 20
19
18 17 16 15 14 13 12 11 10 9 7 5
2 4
Plan: Plan 01
11/04/2009
Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Crit Tr = 500 aos Crit Tr = 100 aos Ground
700
690
Elevation (m) 680 670 660 0 200 400 600 Main Channel Distance (m) 800 1000 1200 1400
Plan: Plan 01
11/04/2009
.55 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Crit Tr = 500 aos Crit Tr = 100 aos
672
670
-100
-50
50 Station (m)
100
150
200
250
Plan: Plan 01
.55
11/04/2009
Progresiva 1+800 682 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos 680 WS Tr = 100 aos Ground Bank Sta
678
676
-150
-100
-50
0 Station (m)
50
100
150
200
Plan: Plan 01
.55
11/04/2009
Progresiva 1+750 676 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground Bank Sta 674
672
-150
-100
50
100
150
Plan: Plan 01
11/04/2009
Progresiva1+700 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground Bank Sta 676
674
-150
-100
50
100
150
Plan: Plan 01
11/04/2009
Progresiva 1+650 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground 680 Bank Sta
678
Elevation (m)
676
674
672
670 -200
-150
-100
50
100
150
Plan: Plan 01
11/04/2009
Progresiva 1+600 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground 680 Bank Sta
678
Elevation (m)
676
674
672
670 -200
-150
-100
50
100
150
Plan: Plan 01
11/04/2009
Progresiva 1+550 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground Bank Sta 680
678
-150
-100
50
100
150
Plan: Plan 01
11/04/2009
Progresiva 1+500 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground Bank Sta 682
680
-150
-100
50
100
150
Plan: Plan 01
.55
11/04/2009
Progresiva 1+450 686 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground 684 Bank Sta
682
Elevation (m)
680
678
676
674 -250
-200
-150
-100
50
100
150
Plan: Plan 01
11/04/2009
Progresiva 1+400 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground Bank Sta 684
682
-200
-150
-100
50
100
150
Plan: Plan 01
11/04/2009
Progresiva 1+350 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground 686 Bank Sta
684
Elevation (m)
682
680
678
676 -250
-200
-150
-100
50
100
150
Plan: Plan 01
11/04/2009
Progresiva 1+300 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground 688 Bank Sta
686
Elevation (m)
684
682
680
678 -250
-200
-150
-100
50
100
150
Plan: Plan 01
11/04/2009
Progresiva 1+250 692 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground 690 Bank Sta
688
Elevation (m)
686
684
682
680 -250
-200
-150
-100
50
100
150
Plan: Plan 01
11/04/2009
Progresiva 1+200 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground Bank Sta 690
688
-200
-150
-100
50
100
150
Plan: Plan 01
11/04/2009
Progresiva 1+150 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground 694 Bank Sta
692
Elevation (m)
690
688
686
684 -250
-200
-150
-100
50
100
150
Plan: Plan 01
11/04/2009
Progresiva 1+100 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground 696 Bank Sta
694
Elevation (m)
692
690
688
686 -250
-200
-150
-100
50
100
150
Plan: Plan 01
11/04/2009
Progresiva 1+050 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground Bank Sta 696
694
-150
-100
50
100
150
Plan: Plan 01
11/04/2009
Progresiva 1+000 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground Bank Sta 696
694
-150
-100
50
100
150
Plan: Plan 01
11/04/2009
Progresiva 0+950 700 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground Bank Sta 698
696
-150
-100
50
100
Plan: Plan 01
11/04/2009
Progresiva 0+900 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground 700 Bank Sta
698
Elevation (m)
696
694
692
690 -200
-150
-100
50
100
Plan: Plan 01
11/04/2009
Progresiva 0+850 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground 702 Bank Sta
700
Elevation (m)
698
696
694
692 -200
-150
-100
50
100
Plan: Plan 01
11/04/2009
Progresiva 0+800 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground Bank Sta 702
700
-150
-100
50
100
Plan: Plan 01
.55
11/04/2009
Progresiva 0+750 706 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground Bank Sta 704
702
-150
-50
50
Plan: Plan 01
.55
11/04/2009
Progresiva 0+750 706 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground Bank Sta 704
702
-150
-50
50
Plan: Plan 01
11/04/2009
Progresiva 0+700 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground 706 Bank Sta
704
Elevation (m)
702
700
698
696 -150
-100
50
100
Plan: Plan 01
11/04/2009
Progresiva 0+650 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground Bank Sta 706
704
-100
50
100
Plan: Plan 01
11/04/2009
Progresiva 0+550 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground 710 Bank Sta
708
Elevation (m)
706
704
702
700 -150
-100
-50
0 Station (m)
50
100
150
Plan: Plan 01
11/04/2009
Progresiva 0+500 Legend EG Tr = 500 aos WS Tr = 500 aos EG Tr = 100 aos WS Tr = 100 aos Ground Bank Sta 710
708
-100
-50
0 Station (m)
50
100
150
200
HEC-RAS Plan: Plan 01 River: Chorunga Reach: Encauzamiento Reach River Sta Profile Q Total (m3/s) Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento Encauzamiento 28 28 27 27 26 26 25 25 24 24 23 23 22 22 21 21 20 20 19 19 18 18 17 17 16 16 15 15 14 14 13 13 12 12 11 11 10 10 9 9 8 8 7 7 6 6 5 5 4 4 3 3 2 2 1 1 Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos Tr = 100 aos Tr = 500 aos 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00 561.00 1020.00
Min Ch El (m) 703.10 703.10 701.60 701.60 700.20 700.20 698.70 698.70 697.60 697.60 696.40 696.40 695.20 695.20 693.70 693.70 691.60 691.60 690.50 690.50 689.20 689.20 688.00 688.00 686.60 686.60 684.60 684.60 683.00 683.00 681.60 681.60 679.90 679.90 677.80 677.80 676.30 676.30 675.30 675.30 674.20 674.20 673.00 673.00 671.50 671.50 670.10 670.10 668.70 668.70 667.00 667.00 665.50 665.50 664.50 664.50
W.S. Elev (m) 707.71 709.49 706.42 708.28 705.12 706.98 703.75 705.59 702.40 704.20 700.96 702.67 699.44 701.01 697.61 699.08 695.84 697.28 694.49 695.88 693.06 694.38 691.44 692.75 690.01 691.34 688.55 689.84 687.00 688.27 685.56 686.81 684.01 685.24 682.35 683.65 680.87 682.19 679.52 680.82 678.15 679.46 676.77 678.10 675.36 676.71 673.99 675.35 672.47 673.83 670.90 672.25 669.49 670.76 668.10 669.34
E.G. Elev (m) 707.73 709.52 706.45 708.32 705.15 707.03 703.78 705.64 702.43 704.24 701.00 702.73 699.47 701.06 697.65 699.13 695.87 697.32 694.51 695.92 693.08 694.42 691.47 692.79 690.03 691.37 688.57 689.88 687.02 688.30 685.58 686.84 684.03 685.27 682.37 683.68 680.89 682.22 679.53 680.85 678.17 679.49 676.79 678.13 675.38 676.74 674.01 675.38 672.49 673.87 670.92 672.28 669.51 670.80
E.G. Slope (m/m) 0.026728 0.024032 0.024870 0.024080 0.027153 0.027719 0.027496 0.028006 0.026537 0.027628 0.030976 0.033579 0.030097 0.033012 0.045072 0.045493 0.028725 0.029326 0.025582 0.026804 0.032218 0.033897 0.032375 0.031306 0.025615 0.025681 0.033681 0.035255 0.028744 0.028355 0.028850 0.030088 0.033352 0.032732 0.032847 0.030992 0.027069 0.027515 0.026988 0.027168 0.027545 0.027348 0.027703 0.027249 0.028718 0.028041 0.026191 0.026575 0.035448 0.034490 0.028043 0.029309 0.028634 0.030129 0.027024 0.027012
Vel Chnl (m/s) 0.68 0.81 0.72 0.89 0.77 0.96 0.77 0.97 0.76 0.97 0.82 1.05 0.77 0.99 0.85 1.06 0.69 0.87 0.64 0.82 0.68 0.86 0.66 0.82 0.61 0.77 0.69 0.86 0.62 0.78 0.63 0.80 0.65 0.81 0.65 0.80 0.62 0.78 0.62 0.77 0.62 0.78 0.62 0.78 0.64 0.80 0.63 0.79 0.71 0.89 0.66 0.83 0.64 0.82 0.61 0.76
Flow Area (m2) 826.65 1257.90 777.63 1139.95 728.57 1058.38 725.84 1052.20 735.60 1054.40 686.22 970.97 730.17 1035.12 661.56 965.35 817.54 1173.07 869.79 1237.50 822.17 1192.30 849.86 1241.90 920.80 1328.26 814.71 1181.06 904.28 1308.48 889.45 1276.50 866.69 1264.02 864.96 1274.84 904.35 1312.68 911.22 1319.59 903.60 1306.30 900.47 1305.64 877.58 1278.21 895.87 1290.24 788.45 1148.93 855.69 1223.07 872.30 1245.15 938.23 1358.85
Top Width (m) 236.48 252.56 191.91 197.82 174.03 182.38 173.98 181.27 175.00 179.89 164.91 169.01 190.34 198.51 201.87 212.78 244.38 248.87 261.50 265.94 270.25 289.69 295.57 302.93 303.10 308.97 273.85 292.12 315.08 319.75 303.57 314.89 317.59 327.81 312.24 321.20 301.65 315.77 306.92 317.06 305.05 310.38 303.23 308.64 292.37 299.33 287.06 294.11 261.85 267.58 269.25 276.75 287.75 296.49 335.41 341.19
Froude # Chl 0.12 0.12 0.11 0.12 0.12 0.13 0.12 0.13 0.12 0.13 0.13 0.14 0.13 0.14 0.15 0.16 0.12 0.13 0.11 0.12 0.12 0.13 0.12 0.13 0.11 0.12 0.13 0.14 0.12 0.12 0.12 0.13 0.13 0.13 0.12 0.13 0.11 0.12 0.11 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.11 0.12 0.13 0.14 0.12 0.13 0.12 0.13 0.11 0.12
665.79 666.15
668.12 669.37
ANALISIS DE SOCAVACION GENERALIZADA DEL CAUCE Quebrada de Chorunga Tr = 100 aos Q= b= d= A= Vm = q= D50 = Lacey: dm = 0.47 (Q/f) ^1/3 f = 1.76 (Dm)^ ds = Z1*dm dl = Z2* dm f= dm = ds = Blench: dfo = K q ^2/3 /Fbo^1/3 ds = Z1*dfo dl = Z2*dfo Fbo = K= 1.45 0.6 (Grfico de Blench) Z1= 0.6 Z2 = 1.25 dfo = ds = Neill: ds = d (Vm/Vc - 1) Vc = ds = dsm = 2.35 m/seg (Grfico de Neill) -2.50 m 1.02 m (Valor no aplicable) dsm corregido = 1.25 * dsm = 1.28 m 1.05 m 0.63 m 8.26 1.89 m 1.42 m
1/2
Z1 = 0.75 Z2 = 1.50
MAYO, 2009
Proyecto 1-M-373-002
Anexos
PROGRAM OUTPUT FOR A NATURAL CHANNEL SIDE SLOPE RIPRAP, BENDWAY INPUT PARAMETERS SPECIFIC WEIGHT OF STONE,PCF 165.0 MINIMUM CENTER LINE BEND RADIUS,FT 1000.0 WATER SURFACE WIDTH,FT 698.0 LOCAL FLOW DEPTH,FT 17.6 CHANNEL SIDE SLOPE,1 VER: 1.50 HORZ AVERAGE CHANNEL VELOCITY,FPS 3.50 COMPUTED LOCAL DEPTH AVG VEL,FPS 5.54 (LOCAL VELOCITY)/(AVG CHANNEL VEL) 1.58 SIDE SLOPE CORRECTION FACTOR K1 .71 CORRECTION FOR VELOCITY PROFILE IN BEND 1.22 RIPRAP DESIGN SAFETY FACTOR 1.25
SELECTED STABLE GRADATIONS ETL GRADATION NAME 1 D100(MAX) IN 9.00 COMPUTED D30(MIN) D30 FT FT .17 .37 D100(MAX) IN 9.00 D85/D15 1.70 N=THICKNESS/ D100(MAX) 1.00 D30(MIN) FT 2 .37 CT THICKNESS IN 1.00 9.0 D90(MIN) FT .53
EQUIVALENT SPHERICAL DIAMETERS IN INCHES D100(MAX) D100(MIN) D50(MAX) D50(MIN) D15(MAX) 9.0 6.6 6.0 5.3 4.8
D15(MIN) 3.6
MAYO, 2009
ANEXO 6
ESPECIFICACIONES TECNICAS DE CONSTRUCCION
Proyecto 1-M-373-002
Anexos
MAYO 2009
ESPECIFICACIONES TECNICAS
I. Alcances Las presentes Especificaciones Tcnicas tienen por objeto normar el programa constructivo de la Defensa Riberea de los Depsitos de Relaves San Juan de Arequipa, proyecto que pertenece a Compaa Minera CENTURY MINING PERU S.A.C. Las Especificaciones Tcnicas describen los procedimientos y metodologas de trabajo que debe seguir el Contratista responsable de las obras durante la ejecucin de las mismas, incluyndose adems las pautas para la elaboracin de sus precios unitarios, as como de medicin y pago de cada uno de los trabajos comprendidos en el presente proyecto de recrecimiento. La defensa riberea de los depsitos de relaves consiste en la construccin de un dique compactado con material extrado del lecho del ro aledao, cuyos taludes laterales sern de 1.5H/1.0V. Debido a la escasa velocidad del flujo, ante la ocurrencia de un evento extraordinario un enrocado resulta apropiado para el revestimiento del talud externo. El revestimiento con enrocado consistira de roca dura y durable, deber tener un espesor de 0.60 m. As mismo en el lecho del ro, adyacente al revestimiento de enrocado, se colocara una capa de proteccin de 3.50 m de ancho y 0.6 m de espesor. La interface talud revestimiento, estara provista de un manto geotextil que impida la migracin de las partculas finas del talud.
En la obra se debe contar obligatoriamente con un juego completo de Planos de Construccin del Proyecto, as como de las presentes Especificaciones Tcnicas.
MAYO 2009
II. Definiciones Las siguientes definiciones sern aplicadas en estas Especificaciones Tcnicas: Propietario: Compaa Minera CENTURY MINING PERU S.A.C. ser denominado el PROPIETARIO. El PROPIETARIO deber designar a un Representante Autorizado quin ser el representante debidamente identificado y autorizado para actuar como intermediario entre el PROPIETARIO, el CONTRATISTA y el INGENIERO. Ingeniero: El INGENIERO ser el responsable del diseo del proyecto, elegido y autorizado por el PROPIETARIO quien deber ser un ingeniero colegiado. El INGENIERO ser el nico autorizado para hacer cambios en el diseo y cambios de especificaciones previa aprobacin del PROPIETARIO. El PROPIETARIO deber presentar al INGENIERO, por escrito ante el CONTRATISTA. Supervisor: El SUPERVISOR ser el representante identificado y autorizado por el PROPIETARIO. El SUPERVISOR deber ser un ingeniero profesional colegiado. El SUPERVISOR ser el encargado de asegurar el estricto cumplimiento de las Especificaciones del Proyecto as como del Aseguramiento de la Calidad de la Construccin (QA), para la obra. El SUPERVISOR deber contar con suficiente experiencia en este tipo de Obras. Contratista: El CONTRATISTA es la parte o partes identificadas como tales por el PROPIETARIO y ser el responsable por la ejecucin del trabajo de acuerdo con estas especificaciones tcnicas y la buena prctica constructiva, realizando el Control de la Calidad (QC) de la obra en ejecucin. Subcontratista: El SUBCONTRATISTA es la parte o partes autorizadas como tales por el PROPIETARIO y ser el responsable del cumplimiento de las tareas bajo contrato con el CONTRATISTA. Proyecto: Construccin de la Defensa Riberea de los Depsitos de Relave San Juan de Arequipa. Obra: Sern todos los trabajos incluidos en el proyecto Construccin de la Defensa Riberea de los Depsitos de Relave San Juan de Arequipa, indicados en las especificaciones y planos de construccin, as como los trabajos adicionales que por necesidad de alcanzar el objetivo se pudieran efectuar en el desarrollo de la construccin.
MAYO 2009
III. Normas tcnicas y requisitos a adoptarse en la construccin La construccin de las obras comprendidas en el presente Proyecto se efectuar de conformidad con las presentes Especificaciones Tcnicas y las normas a las que se hace referencia a continuacin: ACI (American Concrete Institute) ASTM (American Society for Testing of Materials) GRI (Geosynthetic Research Institute) NSF Standards (National Sanitation Foundation) EPA Standards (Environmental Protection Agency)
Asimismo, ser obligatorio el cumplimiento de los Reglamentos, Cdigos y Normas nacionales vigentes en todo lo pertinente al tipo de obra a ejecutar como son, entre otras: Reglamento Nacional de Construcciones (RNC) Reglamento de Seguridad e Higiene Minera Nueva Legislacin de la Ley General de Industrias Normas Tcnicas Peruanas (NTP)
IV. Supervisin El PROPIETARIO contar con un profesional para que, en su representacin, ejecute la Supervisin de la Obra consistente en el aseguramiento de la calidad de todos los trabajos, as como el control econmico y avance de las obras que comprende el Proyecto. En el caso de obras complementarias y/o modificaciones al Proyecto, as como en las prestaciones no previstas en las presentes Especificaciones Tcnicas y que fueran requeridas al CONTRATISTA por el PROPIETARIO durante el desarrollo de los trabajos, valdrn las disposiciones que el PROPIETARIO dispondr en cada caso. El PROPIETARIO tendr la facultad, durante el curso de la ejecucin de las obras, de complementar o adaptar las presentes Especificaciones Tcnicas a situaciones especficas, con el fin de asegurar la mejor ejecucin de los trabajos. Cualquier complemento o adaptacin en los trabajos y/o Especificaciones Tcnicas, deber ser respaldada por una orden aprobada por el INGENIERO y refrendada por el
MAYO 2009
PROPIETARIO, as como debe estar en concordancia con la Condiciones Generales del Contrato. En el texto de las presentes especificaciones se menciona al PROPIETARIO aludiendo a las labores del SUPERVISOR, quin lo representar en la Obra. V. Informacin a Presentar El CONTRATISTA deber presentar la siguiente informacin para la aprobacin del PROPIETARIO, sin la cual, la Obra no podr iniciarse hasta que se obtengan las aprobaciones pertinentes por escrito. La programacin de Obra, cronogramas de uso de equipos, de adquisicin de materiales, de empleo de mano de obra as como el cronograma valorizado de Obra, actualizados a la fecha de inicio real de obra. La siguiente informacin a presentar se aplica a todas las Secciones de estas Especificaciones: Levantamientos Topogrficos: personal asignado y lista de equipos de topografa; metodologa a emplearse en el levantamiento; levantamientos topogrficos de la disposicin total y parcial de la Obra; levantamiento topogrfico inicial aplicable a cada tem de pago para los clculos de cantidades;
Durante el desarrollo de la Obra el CONTRATISTA presentar los levantamientos topogrficos provisionales, segn se requiera, para demostrar el cumplimiento con el diseo y sobre el cual se basarn los pagos por avances. Al trmino de la Obra, el CONTRATISTA presentar los levantamientos topogrficos finales para los registros como construido y sobre los cuales se basar el pago final. El PROPIETARIO ser el responsable de entregar los hitos monumentados que servirn para realizar el replanteo de la obra, as como para el control topogrfico horizontal y vertical de la misma. Ser responsabilidad del CONTRATISTA la topografa de construccin para asegurar el cumplimiento hasta las lneas y rasantes especificadas. La topografa de pre-construccin y las secciones transversales finales para determinar
MAYO 2009
cantidades de movimientos de tierra sern responsabilidad del CONTRATISTA. Es posible que la precisin de los planos y/o mapas necesite ligeros ajustes en las cotas indicadas en los planos debido a las condiciones actuales del terreno. Todo cambio estar sujeto al visto bueno del INGENIERO y a la aprobacin del PROPIETARIO. VI. Reporte Diario El reporte diario deber incluir: Descripcin de los trabajos ejecutados; Distribucin del personal y sus horas; Marca y modelo de los equipos; Horas de trabajo, de espera (stand-by) y de paralizacin de los equipos; Detalles de los retrasos y fallas; Resultados de las pruebas de control de calidad efectuados por el CONTRATISTA; Avances con respecto a cada partida de pago, incluyendo las cantidades estimadas para fines de pago. Observaciones en general, tales como correspondencia, visitas, estado del tiempo, precipitaciones, paralizaciones, incidentes, accidentes y otros de informacin.
El Reporte Diario deber estar escrito en forma clara y ntida de lo contrario, podra ser rechazado. El Reporte Diario deber mostrar el nmero del Contrato y llevar la fecha, nombre y la firma del CONTRATISTA, y ser entregado al PROPIETARIO para su aprobacin y firma antes del medioda del da siguiente. La aceptacin del Reporte Diario no constituir necesariamente la aprobacin de la calidad del trabajo o la aprobacin de las cantidades para fines de pago. Se podr requerir de una posterior verificacin. El formato para el Reporte Diario deber ser acordado con el PROPIETARIO. VII. Comunicaciones El CONTRATISTA deber considerar un sistema propio de comunicacin de la Obra mediante el sistema que sea conveniente, radios porttiles, celulares, telefona fija, etc. Deber asimismo proporcionar estas facilidades a la Supervisin de Obra.
MAYO 2009
El CONTRATISTA para la instalacin y operacin de sus equipos base, mviles, porttiles, en las reas operativas, deber tener la autorizacin del PROPIETARIO. El CONTRATISTA presentar su solicitud a la Jefatura del Proyecto. Se requiere por parte del solicitante la presentacin de: Resolucin Directoral, otorgada por la Direccin de Administracin de FrecuenciasDireccin General de Telecomunicaciones, del Ministerio de Transportes y Comunicaciones, sobre la autorizacin de su sistema de comunicaciones. Copia de las licencias de operacin, vigentes, de cada uno de los equipos de radio. Copia de la Licencia de Instalacin en el rea de trabajo. rea de cobertura de sus comunicaciones.
El PROPIETARIO constatar la veracidad de la informacin ante el MTC: frecuencias de operacin, potencia, ancho de banda y posibles interferencias. El PROPIETARIO determinar el lugar donde pueda ser ubicada la estacin de radio solicitada. El uso del lugar donde el PROPIETARIO tiene sus estaciones base de Radio, est totalmente restringido para concesiones a terceros. El PROPIETARIO, supervisar las instalaciones y la correcta operacin de los equipos de acuerdo a las normas y condiciones tcnicas estndares de las Comunicaciones Internacionales y dispuestas por el MTC. De existir alguna anormalidad en las instalaciones o uso, el PROPIETARIO se reserva el derecho de cancelar inmediatamente la concesin de uso de sus instalaciones. VIII. Secuencia de la Obra Los trabajos de Construccin de la Defensa Riberea de los Depsitos de Relave San Juan de Arequipa, se realizarn de preferencia de acuerdo con la siguiente secuencia de obra: Movilizacin de todo el equipo y personal del CONTRATISTA, requerido para completar el trabajo, tal como se define en las Especificaciones Tcnicas y en los Planos de Construccin. Construccin e instalacin de todos los trabajos auxiliares y logsticos requeridos para el cumplimiento satisfactorio del proyecto. Ejecucin de los trabajos topogrficos para el replanteo de la obra, de conformidad con los Planos de Construccin. Construccin del camino de acceso temporal.
MAYO 2009
Remocin y reubicacin de los relaves que se encuentran fuera del lmite proyectado los depsitos de relaves. Excavacin de los materiales geotcnicamente incompetentes para la cimentacin del dique de defensa riberea. Preparacin de la cimentacin del dique de defensa riberea, que consistir en la compactacin de la superficie segn energa de compactacin especificada en los Planos de Construccin. Construccin del terrapln de relleno compactado, a ser conformado con material granular, de conformidad con la geometra, alineamientos, niveles de cresta y energa de compactacin especificados en los Planos de Construccin. Perfilado del talud externo del dique de defensa riberea Instalacin del manto geotextil en el talud externo del dique de defensa riberea, anclado en la cresta del dique y en el pie del talud segn se indica en los Planos de Construccin. Colocacin de la capa de enrocado en el talud externo del dique de defensa riberea. Instalacin de la instrumentacin de control proyectada, consistente en dos piezmetros de tubo abierto, en las ubicaciones y con las caractersticas que se indican en los Planos de Construccin. Limpieza y/o retiro de materiales sobrantes, rechazados u otros del rea del proyecto. Desmovilizacin de todo el equipo y personal del CONTRATISTA, tal como se define en estas Especificaciones Tcnicas.
IX. Medicin y Pago Alcances Esta seccin cubre las consideraciones generales para la medicin y el pago de todas las partidas listadas en la Tabla Metrado Referencial de Obra. Las partidas listadas en la Tabla Metrados Referenciales de Obra incluyen las actividades conexas necesarias para la ejecucin del trabajo. Por consiguiente, cualquier trabajo requerido en las Especificaciones o mostrado en los Planos de Construccin o que sea necesario para la ejecucin de la Obra que no se encuentre listado especficamente como una partida de pago separada en la Tabla ser considerado incidental a la Obra y no se efectuar medicin o pago alguno por dicho trabajo. Sin embargo, el costo de todo ese trabajo incidental ser incluido por el Postor en los precios ofertados para las diversas partidas que aparecen en el Anexo respectivo del contrato. Las cantidades de trabajo o metrado correspondiente a cada partida de Obra que se muestra en el Anexo respectivo, han sido estimadas tomando como referencia los Planos de Construccin. No obstante, el PROPIETARIO se reserva el derecho de
MAYO 2009
incrementar o disminuir la cantidad de cualquier partida de trabajo segn se requiera en obra y el CONTRATISTA no podr hacer ningn reclamo por ganancias previstas, por prdida de ganancias, por daos y perjuicios o por algn pago extra de cualquier tipo, salvo que est contemplado en el Contrato. Medicin Las dimensiones y niveles indicados en los Planos de Construccin debern ser respetados y servirn como base de pago. Las cantidades de obra de los metrados son slo referenciales y stas debern ser calculadas en base a lo realmente ejecutado en obra, respetando rigurosamente los diseos y las indicaciones de los planos, o de acuerdo a lo instruido por el SUPERVISOR en el campo. Las cantidades de obra ejecutada estarn sujetas a una re-medicin luego de que la partida en consideracin haya sido llevada a cabo en forma satisfactoria. La cantidad final para la partida ser la cantidad realizada, a satisfaccin del PROPIETARIO. El CONTRATISTA ser responsable de todos los aspectos de medicin para el pago. Los mtodos de medicin debern estar en conformidad con los estndares normalmente aceptados por la industria de la construccin para los respectivos tipos de trabajo, o de acuerdo a lo indicado en las secciones de las especificaciones relevantes. El CONTRATISTA deber obtener la previa aprobacin de sus mtodos de clculo de cantidades incluyendo los formatos de presentacin y detalles. Esta aprobacin puede requerir que el PROPIETARIO participe en, o dirija la ejecucin de los clculos de cantidades. El PROPIETARIO efectuar los clculos de verificacin que l considere necesarios. Si el PROPIETARIO encontrara errores u omisiones en los clculos, el CONTRATISTA deber rectificarlos inmediatamente. No se deber proceder con un tipo de trabajo dado hasta que la metodologa de clculo sea aprobada por escrito por el PROPIETARIO. No se deber efectuar ningn trabajo que impida la verificacin de cualquier clculo de las condiciones iniciales. El CONTRATISTA deber preparar todos los estimados mensuales y un informe mensual del trabajo ejecutado junto con dichos clculos y datos de sustento que el
MAYO 2009
PROPIETARIO considere necesarios para determinar la precisin de los estimados, todos los cuales debern ser presentados en un formato aprobado. Todas las notas de campo, archivos electrnicos, clculos de cantidades, secciones transversales y otros registros originales obtenidos por el CONTRATISTA o requeridos por el PROPIETARIO para fines de clculo de cantidades, debern ser proporcionadas al PROPIETARIO y pasarn a ser de su propiedad. Adems de los clculos antes mencionados, el CONTRATISTA deber presentar un Reporte Diario (tal como se describe en el numeral VI) que contenga una descripcin completa y precisa de todo el avance del da anterior y permita sustentar los estimados de cantidades para control de avances y/o cumplimiento del cronograma. La medicin de los costos indirectos de obra se circunscribe a la exigencia y verificacin por parte del PROPIETARIO del adecuado cumplimiento de lo ofertado por el CONTRATISTA en la provisin, de acuerdo al calendario de Obra de los insumos de mano de obra (direccin tcnica, administracin, etc.), infraestructura de apoyo (laboratorio, talleres, maestranza, campamentos, oficinas, etc.), y otras instalaciones incluidas en su propuesta. Pago El pago por la cantidad de Obra ejecutada ser efectuado a los precios unitarios respectivos establecidos en el Contrato de Obra. Salvo que se especifique lo contrario, los precios fijados en el presupuesto para las diversas partidas de trabajo constituirn la plena compensacin por los costos directos, as mismo en el presupuesto se han fijado los costos indirectos y utilidades para efectuar todo el trabajo requerido por el Contrato. El pago por las diversas partidas slo se efectuar por el trabajo culminado en forma satisfactoria y de conformidad con los requerimientos del Contrato. No se efectuarn mediciones o pagos separados por ninguna partida que no se encuentre especificada en el Contrato, incluyendo: Cualquier actividad relacionada a las diversas partidas de pago establecidas en la Tabla; tiempo de viaje, bajo ninguna circunstancia;
MAYO 2009
control de contaminacin y disposicin de desechos; seguridad del CONTRATISTA; control de calidad del CONTRATISTA retrasos a causa del clima salvo que estn contemplados por las Condiciones Generales; retrasos a causa de mantenimiento y falla de los equipos o falta de materiales; consumibles; asistencia a reuniones de seguridad; y obtencin de permisos y licencias.
Todos estos costos debern ser incluidos en los precios unitarios del CONTRATISTA. Pago por trabajo adicional (Extra) Trabajo Adicional o Trabajo Extra significa el suministro de materiales y/o equipos y/o la ejecucin de trabajos de naturaleza distinta a los del Proyecto, que sin embargo fuera necesario ejecutar para lograr el objetivo de la Obra. El PROPIETARIO, sin invalidar el Contrato, puede ordenar efectuar trabajos adicionales o efectuar cambios alterando o haciendo adiciones a la Obra. El monto del contrato ser ajustado como corresponda. Dicho trabajo ser ejecutado bajo las condiciones del Contrato, salvo que alguna solicitud de extensin del plazo causada por ello sea ajustada en el momento en que se prepare la orden de modificacin de trabajo adicional. Al dar instrucciones, el PROPIETARIO tendr autoridad para efectuar cambios menores a la Obra que no impliquen costos adicionales, y que no sean inconsistentes con los objetivos de la construccin, los mismos que no sern considerados como trabajo adicional (extra). El precio a pagarse por cualquier trabajo adicional ser determinado por el PROPIETARIO, utilizando uno o ms de los mtodos especificados en las Condiciones Generales del Contrato. Se acuerda expresamente y se entiende que ninguna solicitud de adicin al monto del contrato ser vlida, salvo mediante la aceptacin de una Orden de Cambio escrita y salvo variaciones debidas a cambio de cantidades y costos relevantes aprobados.
MAYO 2009
Pago del contratista al propietario El CONTRATISTA deber reembolsar al PROPIETARIO por los costos incurridos debido a: Trabajo en horas extras efectuado por el personal del PROPIETARIO en obra para satisfacer las necesidades del CONTRATISTA. Rediseo de cualquier parte del trabajo generado por un error del CONTRATISTA. Perodo en espera (Stand-by) Cualquier perodo en espera pagado requerir aprobacin y se aplicar slo durante retrasos causados o solicitados por el PROPIETARIO. La suma de las horas de trabajo y horas en espera a causa de retrasos aprobados, no podrn exceder de ocho horas por da. Durante el tiempo en espera, el CONTRATISTA deber limpiar el rea de trabajo y dedicarse a algn otro trabajo que se apruebe o indique. Control de calidad No se realizar ninguna medida o pago separado por los ensayos y pruebas de control de calidad y/o laboratorios. Estos costos debern estar incluidos en los costos indirectos de obra. Penalidades por el incumplimiento de la proteccin ambiental Lo establecido respecto a la conservacin del ambiente ser de cumplimiento obligatorio por parte del CONTRATISTA. Para el debido cumplimiento del Contrato, se har pago directo por la conservacin del ambiente y restauracin de las reas disturbadas por la construccin de las obras. Por lo tanto, la no ejecucin o ejecucin insatisfactoria de estas labores dar lugar a una retencin del pago de las valorizaciones mensuales hasta que se restaure la zona y de persistir esta situacin se aplicarn las penalidades contempladas en el Contrato.
MAYO 2009
MAYO 2009
1.1.5 Mtodo de medicin La movilizacin y desmovilizacin se medir por da de viaje, considerando 8 horas de recorrido por cada da. 1.1.6 Bases de pago Se pagar en dos partes: el 50% al movilizar el equipo a obra, el cual se efectuar sobre camiones traylers, la tarifa de los equipos transportados ser el 40% de la tarifa en operacin y la tarifa de operacin completa para los equipos autotransportados, los cuales transportarn las herramientas y todo equipo liviano (martillos neumticos, vibradores, etc.) que no sea autotransportado; el otro 50% se pagar al desmovilizar el equipo una vez concluida la obra, previa autorizacin de la Supervisin. Asimismo, los pagos incluyen el montaje y desmontaje de las plantas procesadoras de materiales y seguros por el traslado del equipo e imprevistos necesarios para completar el tem.
MAYO 2009
No deber talarse ningn rbol o cualquier especie florstica que tengan un especial valor gentico y/o paisajstico. As tampoco, deber afectarse cualquier lugar de inters cultural o histrico. De ser necesario el retiro de material vegetal se deber transplantar a otras zonas desprotegidas, iniciando procesos de revegetacin. Los residuos de tala y desbroce no deben ser depositados en corrientes de agua, debiendo ser apiladas de manera que no causen desequilibrios en el rea. Estos residuos no deben ser incinerados, salvo excepciones justificadas y aprobadas por la Supervisin. 1.2.2 Materiales Los materiales para la construccin de todas las obras provisionales sern de preferencia desarmables y transportables, salvo que el Proyecto indique lo contrario. En la construccin del campamento se evitar al mximo los cortes de terreno, relleno, y remocin de vegetacin. En lo posible, los campamentos debern ser prefabricados y estar debidamente cercados. 1.2.3 Equipos Todos los equipos empleados debern ser compatibles con los procedimientos de construccin adoptados y requieren aprobacin previa de la Supervisin, teniendo en cuenta que su capacidad y eficiencia se ajusten al programa de ejecucin de las obras y al cumplimiento de esta especificacin. 1.2.4 Requerimientos de construccin Instalaciones Fijar la ubicacin de las instalaciones de las construcciones provisionales conjuntamente con la Supervisin, teniendo en cuenta las recomendaciones necesarias, de acuerdo a la morfologa y los aspectos atmosfricos de la zona. Instalar los servicios de agua, desage y electricidad necesarios para el normal funcionamiento de las construcciones provisionales.
MAYO 2009
Se debe instalar un sistema de tratamiento a fin de que garantice la potabilidad de la fuente de agua; adems, se realizarn peridicamente un anlisis fsico-qumico y bacteriolgico del agua que se emplea para el consumo humano. Incluir sistemas adecuados para la disposicin de residuos lquidos y slidos. Para ello se debe dotar al campamento de pozos spticos, pozas para tratamiento de aguas servidas y de un sistema de limpieza, que incluya el recojo sistemtico de basura y desechos y su traslado a un relleno sanitario construido para tal fin. El campamento deber disponer de instalaciones higinicas destinadas al aseo del personal y cambio de ropa de trabajo; aquellas debern contar con duchas, lavamanos, sanitarios, y el suministro de agua potable, los sanitarios, lavatorios, duchas y urinarios debern instalarse en la proporcin adecuada. Patio de mquinas Para el manejo y mantenimiento de las mquinas en los lugares previamente establecidos al inicio de las obras, se debe considerar algunas medidas con el propsito de que no alteren el ecosistema natural y socioeconmico, las cuales deben ser llevadas a cabo por la empresa contratista. Los patios de mquinas debern tener sealizacin adecuada para indicar el camino de acceso, ubicacin y la circulacin de equipos pesados. Los caminos de acceso, al tener el carcter provisional, deben ser construidos con muy poco movimiento de tierras y ponerles una capa de afirmado para facilitar el trnsito de los vehculos de la obra. El acceso a los patios de mquina y maestranzas deben estar independizadas del acceso al campamento. Si el patio de mquinas est totalmente separado del campamento, debe dotarse de todos los servicios necesarios sealados para stos, teniendo presente el tamao de las instalaciones, nmero de personas que trabajarn y el tiempo que prestar servicios. Al finalizar la operacin, se proceder al proceso de desmantelamiento tal como se ha indicado anteriormente. Instalar sistemas de manejo y disposicin de grasas y aceites. Para ello es necesario contar con recipientes hermticos para la disposicin de residuos de aceites y lubricantes, los cuales se dispondrn en lugares adecuados para su posterior manejo. En las zonas de lavado de vehculos y maquinaria debern construirse desarenadores y
MAYO 2009
trampas de grasa antes que las aguas puedan contaminar suelos, vegetacin, agua o cualquier otro recurso. El abastecimiento de combustible deber efectuarse de tal forma que se evite el derrame de hidrocarburos u otras sustancias contaminantes al suelo, ros, quebradas, arroyos, etc. Similares medidas debern tomarse para el mantenimiento de maquinaria y equipo. Los depsitos de combustible deben quedar alejados de las zonas de dormitorio, comedores y servicios del campamento. Las operaciones de lavado de la maquinaria debern efectuarse en lugares alejados de los cursos de agua. 1.2.5 Desmantelamiento Antes de desmantelar las construcciones provisionales, al concluir las obras, de ser posible, se debe considerar la posibilidad de donacin del mismo a las comunidades que hubiese en la zona o la venta de los mismos a Compaa Minera Century Mining Per S.A.C. En el proceso de desmantelamiento, el contratista deber hacer una demolicin total de los pisos de concreto, paredes o cualquier otra construccin y trasladarlos a un lugar de disposicin final de materiales excedentes, sealados por la Supervisin. El rea utilizada debe quedar totalmente limpia de basura, papeles, trozos de madera, etc.; sellando los pozos spticos, pozas de tratamiento de aguas negras y el desage. Una vez desmantelada las instalaciones, patio de mquinas y vas de acceso, se proceder a escarificar el suelo, y readecuarlo a la morfologa existente del rea, en lo posible a su estado inicial, pudiendo para ello utilizar la vegetacin y materia orgnica reservada anteriormente. En la recomposicin del rea, los suelos contaminados de patios de mquinas, plantas y depsitos de asfalto o combustible deben ser raspados hasta 10 cm por debajo del nivel inferior alcanzado por la contaminacin. Los materiales resultantes de la eliminacin de pisos y suelos contaminados debern trasladarse a los lugares de disposicin de deshechos. 1.2.6 Aceptacin de los trabajos Los trabajos para su aceptacin estarn sujetos a los siguientes controles:
MAYO 2009
Verificar que las reas de dormitorio y servicios sean suficientes para albergar al personal de obra, as como las instalaciones sanitarias. Verificar el correcto funcionamiento de los sistemas de agua potable, drenaje y desage del campamento, oficinas, patios de mquina, cocina y comedores. Verificar las condiciones higinicas de mantenimiento, limpieza y orden de las instalaciones. 1.2.7 Mtodo de medicin El mtodo de medicin para los campamentos ser mensual, de acuerdo con el detalle de ambientes considerado por el contratista en su anlisis de precios considerado. 1.2.8 Bases de pago El pago del trabajo ejecutado ser pagado de manera prorrateada o de una sola vez de acuerdo con el tiempo de construccin de la infraestructura, esta cantidad es la nica compensacin por la construccin y uso de los campamentos durante la total duracin de la obra y las posibles ampliaciones de plazo concedidas al contratista por cualquier causa. El Contratista est obligado a suministrar todos los materiales, equipos, herramientas e instalaciones con las cantidades y calidad indicadas en el proyecto, en esta especificacin y todas las acciones y operaciones para el mantenimiento, limpieza, montaje y desmontaje de las obras hasta la conclusin de la obra. El Contratista deber considerar todos los costos necesarios para la correcta ejecucin de los trabajos especificados dentro del costo de la obra y segn lo indique el Proyecto.
MAYO 2009
1.3.2 Materiales No se requieren materiales para la ejecucin de los trabajos objeto de la presente especificacin. 1.3.3 Equipos El Contratista propondr para consideracin de la Supervisin, los equipos ms adecuados para realizar esta actividad. La necesidad de intervencin del equipo ser dispuesta y ordenada por la Supervisin. 1.3.4 Requerimientos de construccin Antes de comenzar la construccin de los caminos de acceso temporal, el Contratista deber presentar para revisin de la Supervisin, los planos que indiquen la ubicacin y los detalles de los caminos. Cualquier cambio o variacin a los caminos temporales que sea requerido por el Contratista deber someterse a previa aprobacin de la Supervisin y ser considerado como parte de los caminos de construccin temporales del Contratista. Los caminos temporales sern mantenidos en buenas condiciones en todo momento y debern proveerse letreros, barreras, alumbrado y dems sealizacin y accesorios para asegurar el trnsito de todo vehculo sin peligro alguno. El Contratista permitir el libre paso de vehculos y personal de la Supervisin y sus empleados durante el cumplimiento de asuntos oficiales y de otras personas que la Supervisin autorice. 1.3.5 Aceptacin de los trabajos La habilitacin del camino de acceso temporal ser evaluada y aceptada segn lo establecido en los numerales anteriores de esta Especificacin. Si se detectan condiciones inaceptables de transitabilidad o de seguridad vial a criterio de la Supervisin de acuerdo a lo establecido en los anteriores numerales de esta Especificacin, la Supervisin ordenar la paralizacin de las obras en su totalidad, hasta que el Contratista efecte las acciones correctivas. En este caso todos los costos derivados de tal accin sern asumidos por el Contratista.
MAYO 2009
1.3.6 Mtodo de medicin El camino de acceso provisional se medir en Km. 1.3.7 Bases de pago Las cantidades medidas y aceptadas sern pagadas al precio de contrato de la partida Camino de acceso provisional. El pago constituir compensacin total por los trabajos prescritos en esta seccin.
MAYO 2009
Los formatos a utilizar sern previamente aprobados por la Supervisin y toda la informacin de campo, su procesamiento y documentos de soporte sern entregados a la Supervisin cuando este lo requiera. Los trabajos de Trazo y Replanteo comprenden las siguientes tareas: (a) Monumentacin Todos lo hitos de referencia o monumentacin permanente que se coloquen durante toda la ejecucin de la obra debern ser en concreto simple (fc = 100 kg/cm), en forma de tronco de pirmide, con una altura de 500 mm y bases de 300 mm (inferior) y 150 mm (superior). Una varilla de acero corrugado de de dimetro y 300 mm de largo ser empotrada al centro, sobresaliendo 100 mm y pintada de color naranja de preferencia. Los hitos principales contarn con una placa de bronce, indicando coordenadas, elevacin y fecha. (b) Establecimiento de la lnea del eje La lnea del eje ser establecida a partir de los puntos de control. El espaciamiento entre puntos del eje no debe exceder de 20 m. El estacado debe ser restablecido cuantas veces sea necesario para la ejecucin de cada etapa de la obra, para lo cual se deben resguardar los puntos de referencia. (c) Seccin transversal Las secciones transversales del terreno natural debern ser referidas al eje del dique de proteccin riberea. El espaciamiento entre secciones no deber ser mayor de 20 m. (d) Canteras Se debe establecer los trabajos topogrficos esenciales referenciados en coordenadas UTM de las canteras de prstamo. Se debe colocar una lnea de base referenciada, lmites de la cantera y los lmites de limpieza. Tambin se debern efectuar secciones transversales de toda el rea de la cantera referida a la lnea de base. Estas secciones debern ser tomadas antes del inicio de la limpieza y explotacin, y despus de concluida la obra y cuando hayan sido cumplidas las disposiciones de conservacin de medio ambiente sobre el tratamiento de canteras.
MAYO 2009
(e) Levantamientos miscelneos Se debern efectuar levantamientos, estacado y obtencin de datos esenciales para el replanteo, ubicacin, control y medicin de los siguientes elementos: Vas que se aproximan a la los Depsitos de Relaves Y cualquier elemento que est relacionado a la construccin y funcionamiento del dique de proteccin riberea.
(f) Trabajos topogrficos intermedios Todos los trabajos de replanteo, reposicin de puntos de control y estacas referenciadas, registro de datos y clculos necesarios que se ejecuten durante el paso de una fase a otra de los trabajos constructivos deben ser ejecutados en forma constante que permitan la ejecucin de las obras, la medicin y verificacin de cantidades de obra, en cualquier momento. (g) Planos Como Construido El Contratista deber de entregar a la Supervisin, al final de la obra, todos los planos Como Construido (As-Build) de las diferentes estructuras construidas, siendo la relacin de planos a presentar por el Contratista, la indicada por la Supervisin. Dichos planos debern ser entregados impresos y en versin electrnica, y debern tener la aprobacin de la Supervisin, los mismos que forman parte de la Entrega de Obra. 1.4.3 Aceptacin de los trabajos Los trabajos de replanteo, levantamientos topogrficos y todo lo indicado en esta seccin sern evaluados y aceptados segn los numerales 1.4.1.1 y 1.4.1.2 de esta especificacin. 1.4.4 Mtodo de medicin El trazo y replanteo se medir por mes de trabajo realizado. 1.4.5 Bases de pago Las cantidades medidas y aceptadas sern pagadas al precio de contrato en forma prorrateada de manera uniforme en los meses que dura la ejecucin del proyecto, siempre y cuando se cumpla a cabalidad con lo especificado en los numerales 2.2.1.1 y 2.2.1.2 de esta especificacin.
MAYO 2009
MAYO 2009
2.1.5 Aceptacin de los Trabajos Los trabajos para su aceptacin estarn sujetos a lo siguiente: Verificar que el Contratista disponga de todos los permisos requeridos para la ejecucin de los trabajos. Comprobar el estado y funcionamiento del equipo utilizado por el Contratista. Verificar la eficiencia y seguridad de los procedimientos adoptados por el Contratista. Vigilar el cumplimiento de los programas de trabajo. Verificar el alineamiento, perfil y seccin de las reas excavadas. Comprobar que toda superficie de cimentacin quede limpia y libre de materia orgnica. Medir los volmenes de trabajo ejecutado por el Contratista en acuerdo a la presente especificacin. El trabajo de remocin de relaves se dar por terminado y aceptado cuando el alineamiento, el perfil y/o la seccin estn de acuerdo con los planos del proyecto, estas especificaciones y las instrucciones de la Supervisin. 2.1.6 Mtodo de Medicin Los materiales que se vayan a excavar y remover se medirn de comn acuerdo entre la Supervisin y el Contratista, mediante procedimientos topogrficos, tomando secciones transversales del terreno antes y despus de la excavacin y calculando los volmenes en m entre las secciones de corte y la superficie original del terreno. 2.1.7 Bases de Pago La valorizacin, por m de excavacin, ser reconocida al precio unitario del contrato establecido para esta especificacin, en el cual estn incluidos los costos de la mano de obra, leyes sociales, equipos, maquinarias y cualquier otro concepto necesario para la correcta y completa ejecucin de los trabajos, en conformidad con las presentes Especificaciones Tcnicas, Planos del Proyecto y aceptada por la Supervisin.
MAYO 2009
MAYO 2009
efectuados por el Contratista, y si stos generan trabajos adicionales, le sern reconocidos al Contratista con los mismos precios unitarios. 2.2.5 Disposicin de los Materiales de Excavacin El Contratista deber disponer del material procedente de las excavaciones teniendo en cuenta las siguientes opciones: El material gravo-arenoso seleccionado (con tamao mximo de piedras 10") ser transportado y colocado como relleno a ser compactado para conformar el dique de defensa riberea. El material excedente (piedras con dimensiones > 10" cualquier material inadecuado) ser colocado en lugares adecuados autorizados por la Supervisin, los mismos que estarn ubicados entre 100 y 200 m del dique. Si el material extrado de la excavacin en los lugares adyacentes a la obra fuera apropiado para la construccin de las obras, la Supervisin ordenar al Contratista su transporte a la zona de utilizacin, a medida que se vaya efectuando la excavacin, previa habilitacin de la cimentacin de las obras. 2.2.6 Aceptacin de los Trabajos Los trabajos para su aceptacin estarn sujetos a lo siguiente: Verificar que el Contratista disponga de todos los permisos requeridos para la ejecucin de los trabajos. Comprobar el estado y funcionamiento del equipo utilizado por el Contratista. Verificar la eficiencia y seguridad de los procedimientos adoptados por el Contratista. Vigilar el cumplimiento de los programas de trabajo. Verificar el alineamiento, perfil y seccin de las reas excavadas. Comprobar que toda superficie de cimentacin quede limpia y libre de materia orgnica. Medir los volmenes de trabajo ejecutado por el Contratista en acuerdo a la presente especificacin.
MAYO 2009
El trabajo de excavacin se dar por terminado y aceptado cuando el alineamiento, el perfil y/o la seccin estn de acuerdo con los planos del proyecto, estas especificaciones y las instrucciones de la Supervisin. 2.2.7 Mtodo de Medicin Los materiales que se vayan a excavar en superficie se medirn de comn acuerdo entre la Supervisin y el Contratista, mediante procedimientos topogrficos, tomando secciones transversales del terreno antes y despus de la excavacin y calculando los volmenes en m entre las secciones de corte y la superficie original del terreno. 2.2.8 Bases de Pago La valorizacin, por m de excavacin, ser reconocida al precio unitario del contrato establecido para esta especificacin, en el cual estn incluidos los costos de los materiales, mano de obra, leyes sociales, equipos, maquinarias y cualquier otro concepto necesario para la correcta y completa ejecucin de los trabajos, en conformidad con las presentes Especificaciones Tcnicas, Planos del Proyecto y aceptada por la Supervisin.
MAYO 2009
cuenta que su capacidad y eficiencia se ajusten al programa de ejecucin de las obras y al cumplimiento de esta especificacin, previndose el uso de equipo pesado para esta actividad. 2.3.4 Requerimientos de Construccin Despus de que la remocin de relaves y la excavacin para la cimentacin del dique de defensa riberea ha sido sustancialmente terminada, la superficie total debe acondicionarse, removiendo materiales suaves o inestables que no puedan ser compactados de acuerdo con estas especificaciones o que, de alguna manera, sean perjudiciales a la obra. Las reas afectadas y cualesquiera otras depresiones, zonas bajas o huecos debern corregirse con material aprobado, hasta llegar a las gradientes establecidas segn las estacas de construccin. La superficie total deber, entonces, conformarse y compactarse hasta alcanzar el 90% de la mxima densidad seca ha ser obtenida mediante el ensayo Proctor Modificado. Para conseguir una explanacin totalmente plana y compacta de acuerdo con lneas, gradientes y seccin transversal mostradas en los planos, deber usarse la escarificacin, nivelacin con cuchilla, compactacin con rodillo u otros mtodos aceptables. La superficie conformada se mantendr en forma continua para asegurar la circulacin fluida del trfico, en tanto no se coloque el material de prstamo para la conformacin del dique defensa riberea, hasta la terminacin total y aceptacin del trabajo. 2.3.5 Aceptacin de los Trabajos Los trabajos para su aceptacin estarn sujetos a lo siguiente: Verificar que el Contratista disponga de todos los permisos requeridos para la ejecucin de los trabajos. Comprobar el estado y funcionamiento del equipo utilizado por el Contratista. Verificar la eficiencia y seguridad de los procedimientos adoptados por el Contratista. Vigilar el cumplimiento de los programas de trabajo. Verificar el alineamiento, perfil y seccin de las reas excavadas.
MAYO 2009
Comprobar que toda superficie de cimentacin quede limpia y libre de materia orgnica. El trabajo de preparacin de la cimentacin se dar por terminado y aceptado cuando el alineamiento, el perfil y/o la seccin estn de acuerdo con los planos del proyecto, estas especificaciones y las instrucciones de la Supervisin. 2.3.6 Mtodo de Medicin La superficie a preparar para la cimentacin del dique se medir de comn acuerdo entre la Supervisin y el Contratista, mediante procedimientos topogrficos y calculando las reas en m2. 2.3.7 Bases de Pago La valorizacin, por m2 de preparacin de la cimentacin, ser reconocida al precio unitario del contrato establecido para esta especificacin, en el cual estn incluidos los costos de la mano de obra, leyes sociales, equipos, maquinarias y cualquier otro concepto necesario para la correcta y completa ejecucin de los trabajos, en conformidad con las presentes Especificaciones Tcnicas, Planos del Proyecto y aceptada por la Supervisin.
MAYO 2009
Los materiales gravo-arenosos debern estar exentos de terrones de limo o arcilla, ramas de rboles, races de plantas, basura, etc. El contenido de materia orgnica no podr ser superior a 5% y el material que pasa la malla ASTM N 40 tendr un lmite lquido mximo de 40% y un ndice de plasticidad mximo de 10%. El tamao mximo de las piedras ser 10". 2.4.3 Equipos Todos los equipos empleados debern ser compatibles con los procedimientos de construccin adoptados y requieren aprobacin previa de la Supervisin, teniendo en cuenta que su capacidad y eficiencia se ajusten al programa de ejecucin de las obras y al cumplimiento de esta especificacin. 2.4.4 Requerimientos de Construccin Los rellenos tendrn que ser construidos segn el trazo, alineamientos y secciones transversales indicadas en los Planos del Proyecto o modificadas por la Supervisin. Cualquier material que despus de ser colocado en el relleno demuestre ser inadecuado, deber ser removido y reemplazado por un material adecuado, requirindose previamente la aprobacin de la Supervisin.
El material de relleno ser colocado una vez compactada la superficie de fundacin, en capas horizontales y uniformes de 0.30 m de espesor mximo en estado suelto,
MAYO 2009
extendindolo y distribuyndolo sobre la zona de terrapln, de acuerdo a los alineamientos y cotas establecidas en los Planos del Proyecto. El proceso incluye el riego y batido de cada capa de relleno, para lo cual se emplear repetida y alternadamente camiones cisterna con dispositivos de riego y motoniveladoras. La operacin se realizar hasta lograr uniformizar el material y la humedad contenida en l. A continuacin, se proceder a compactar dicha capa mediante la utilizacin de rodillos. Antes de colocar la siguiente capa de relleno, la Supervisin deber verificar y, de ser el caso, aprobar la compactacin de la capa precedente, luego de lo cual su superficie ser escarificada y humedecida superficialmente para aumentar la adherencia de la capa siguiente.
b) Compactacin
Antes de iniciar la compactacin deber verificarse que el material de relleno colocado en obra tenga el ptimo contenido de humedad, permitindose una tolerancia de 2%. El ptimo contenido de humedad ser obtenido en el laboratorio mediante el ensayo de compactacin Proctor Modificado. La humedad deber mantenerse uniforme en cada capa. Una vez preparado el material de relleno, se proceder a su compactacin mediante pasadas sucesivas de rodillos lisos vibratorios y autopropulsados, con un peso esttico mnimo de 10 toneladas. El nmero de pasadas del rodillo ser determinado en obra y ste deber contar con la aprobacin de la Supervisin. La compactacin de cada capa de relleno se efectuar segn las indicaciones que figuran en los planos del presente proyecto. El traslape lateral de cada pasada del equipo de compactacin no debe ser menor de 0.50 m. En los casos en que fuera requerido algn tipo de ensayo especial para el control del contenido de humedad y grado de compactacin, ste ser acordado con la Supervisin.
MAYO 2009
Para verificar el grado de compactacin se utilizar el ensayo de densidad de campo (Norma ASTM 1556). Se efectuar como mnimo un ensayo por cada 500 m2 de capa de terrapln compactado. 2.4.5 Aceptacin de Trabajos Los trabajos para su aceptacin estarn sujetos a lo siguiente: A. Controles Durante la ejecucin de los trabajos, la Supervisin efectuar los siguientes controles principales: Verificar el estado y funcionamiento de todo el equipo utilizado por el Contratista. Supervisar la correcta aplicacin de los mtodos de trabajo aceptados. Vigilar el cumplimiento de los programas de trabajo. Comprobar que los materiales por emplear cumplan los requisitos de calidad exigidos en el numeral 2.4.1.4 de la presente especificacin. Verificar la compactacin de todas las capas del terrapln. Realizar medidas para determinar espesores, levantar perfiles y comprobar la uniformidad de la superficie.
B. Calidad de los materiales De la cantera del material empleado para la construccin de rellenos, se tomarn cuatro (4) muestras representativas en el sector de acopio, las que sern mezcladas y cuarteadas, para efectuar los siguientes ensayos: Granulometra por tamizado. Lmite lquido.
MAYO 2009
Durante la etapa de produccin, la Supervisin examinar las descargas de los materiales y ordenar el retiro de aquellas que, a simple vista, presenten restos de tierra vegetal, materia orgnica o partculas de tamaos superiores al mximo especificado. C. Calidad del producto terminado Cada capa terminada de terrapln deber presentar una superficie uniforme. Los taludes terminados no debern acusar irregularidades a la vista. La distancia entre el eje del proyecto y el borde del terrapln no ser menor que la distancia sealada en los planos del proyecto. La cota de cualquier punto de la superficie final del terrapln (cresta), conformado y compactado, no deber variar en ms de veinte milmetros (20 mm) de la cota proyectada. No se tolerar en las obras concluidas, ninguna irregularidad que impida el normal escurrimiento de las aguas. En adicin a lo anterior, la Supervisin deber efectuar las siguientes comprobaciones: a) Compactacin La compactacin se har en capas de 30 cm de espesor mximo en estado suelto. Cada capa deber ser compactada hasta alcanzar en todo el espesor de la misma una densidad no menor al 90% de la mxima densidad seca obtenida mediante el ensayo Proctor Modificado. Para verificar el grado de compactacin se utilizar el ensayo de densidad de campo (Norma ASTM D1556) y eventualmente se harn verificaciones con ensayos de densidad por el mtodo de reemplazo de agua cuando lo requiera la Supervisin. Siempre que sea necesario, se efectuarn las correcciones por presencia de partculas gruesas, previamente al clculo de los porcentajes de compactacin. b) Irregularidades Todas las irregularidades que excedan las tolerancias de la presente especificacin debern ser corregidas por el Contratista, a su costo, de acuerdo con las instrucciones de la Supervisin y a plena satisfaccin de esta.
MAYO 2009
2.4.6 Mtodo de Medicin El material de relleno se medir en obra una vez compactado y de comn acuerdo entre la Supervisin y el Contratista, mediante procedimientos topogrficos, tomando secciones transversales del terrapln antes y despus de la colocacin del relleno compactado y calculando los volmenes correspondientes en m3. 2.4.7 Bases de Pago La valorizacin, por m3 de relleno compactado, ser reconocida al precio unitario del contrato establecida para esta especificacin. En el precio correspondiente a esta partida estn incluidos los costos de los materiales, mano de obra, leyes sociales, equipos, maquinarias y cualquier otro concepto necesario para la correcta y completa ejecucin de los trabajos, en conformidad con las presentes Especificaciones Tcnicas, Planos del Proyecto y aceptada por la Supervisin.
MAYO 2009
2.5.4 Requerimientos de Construccin El material extrado del proceso de perfilado del talud externo del dique, se utilizar en los rellenos que conformarn el terraplenado del dique. Este material se depositar dentro de los sectores designados por la Supervisin. 2.5.5 Aceptacin de los Trabajos Los trabajos para su aceptacin estarn sujetos a lo siguiente: Verificar que el Contratista disponga de todos los permisos requeridos para la ejecucin de los trabajos. Comprobar el estado y funcionamiento del equipo utilizado por el Contratista. Verificar la eficiencia y seguridad de los procedimientos adoptados por el Contratista. Vigilar el cumplimiento de los programas de trabajo. Verificar el alineamiento, perfil y seccin de las reas excavadas. Comprobar que toda superficie de cimentacin quede limpia y libre de materia orgnica. Medir los volmenes de trabajo ejecutado por el Contratista en acuerdo a la presente especificacin. El trabajo de excavacin se dar por terminado y aceptado cuando el alineamiento, el perfil y/o la seccin estn de acuerdo con los planos del proyecto, estas especificaciones y las instrucciones de la Supervisin. 2.5.6 Mtodo de Medicin La superficie a perfilar se medir de comn acuerdo entre la Supervisin y el Contratista, mediante procedimientos topogrficos y calculando las reas en m2. 2.5.7 Bases de Pago La valorizacin, por m2 de perfilado, ser reconocida al precio unitario del contrato establecido para esta especificacin, en el cual estn incluidos los costos de la mano de obra, leyes sociales, equipos, maquinarias y cualquier otro concepto necesario para la
MAYO 2009
correcta y completa ejecucin de los trabajos, en conformidad con las presentes Especificaciones Tcnicas, Planos del Proyecto y aceptada por la Supervisin.
Verificacin del estado y funcionamiento de las herramientas y equipos a ser utilizado por el Contratista.
MAYO 2009
Supervisin de la correcta aplicacin de los mtodos de construccin mencionados en el numeral 2.6.1.4. Verificacin de las dimensiones de la excavacin y determinacin de los metrados.
2.6.6 Mtodo de medicin La unidad de medida ser el metro cbico, aproximado al centsimo de metro cbico de excavacin ejecutado dentro de las lneas indicadas en los planos y en esta especificacin o autorizadas por la Supervisin. 2.6.7 Bases de pago El pago se har por metro cbico, al precio unitario del Contrato, por toda obra ejecutada conforme a sta especificacin y aceptada por la Supervisin. El precio unitario deber cubrir todos los costos de excavacin y la remocin de los materiales excavados, hasta los sitios de utilizacin o desecho y, en general, todo costo relacionado con la correcta ejecucin de los trabajos.
MAYO 2009
quin de ninguna manera permitir la construccin del relleno de la zanja de anclaje con materiales de caractersticas expansivas. 2.7.3 Equipos Los equipos de extensin, humedecimiento y compactacin de los rellenos para estructuras debern ser los apropiados para garantizar la ejecucin de los trabajos de acuerdo con las exigencias de esta especificacin. 2.7.4 Requerimientos de Construccin Antes de proceder a la colocacin del relleno compactado, la Supervisin deber verificar que el geotextil se encuentre correctamente instalado. El Contratista deber notificar al Supervisor, con suficiente antelacin al comienzo de la ejecucin de los rellenos, para que ste realice los trabajos topogrficos necesarios y verifique las caractersticas de los materiales por emplear y los lugares donde ellos sern colocados. El relleno compactado se realizar en capas de 20 cm de espesor suelto, hasta alcanzar un porcentaje mnimo de compactacin de 85% del ensayo Proctor Modificado. Extensin y compactacin del material Los materiales de relleno se extendern en capas sensiblemente horizontales y de espesor uniforme, las mismas que debern tener el espesor adecuado para obtener el grado de compactacin exigido mediante el uso de compactadores mecnicos livianos. Durante la ejecucin de los trabajos, la superficie de las diferentes capas deber tener la pendiente transversal adecuada, que garantice la evacuacin de las aguas superficiales sin peligro de erosin. Una vez extendida la capa, se proceder a su humedecimiento si es necesario. El contenido ptimo de humedad se determinar en la obra, a la vista de la maquinaria disponible y de los resultados que se obtengan en los ensayos realizados. Obtenida la humedad apropiada, se proceder a la compactacin mecnica de la capa mediante el empleo de compactadores mecnicos livianos o manuales, que permitan obtener el grado de compactacin exigido en la presente especificacin.
MAYO 2009
La construccin de los rellenos se deber efectuar con el cuidado necesario para evitar presiones y daos al geotextil no tejido. Acabado Al concluir cada jornada de trabajo, la superficie de la ltima capa deber estar compactada y bien nivelada, con declive suficiente que permita el escurrimiento de aguas de lluvia sin peligro de erosin. Limitaciones en la ejecucin Los trabajos de rellenos slo se llevarn a cabo cuando no haya lluvia o fundados temores de que ella ocurra y la temperatura ambiente a la sombra, no sea inferior a dos grados Celsius (2 C). 2.7.5 Aceptacin de los trabajos La aceptacin de los trabajos estar sujeta a los siguientes controles: (a) Controles Durante la ejecucin de los trabajos, la Supervisin efectuar los siguientes controles principales:
Verificar el estado y funcionamiento del equipo utilizado por el Contratista. Supervisar la correcta aplicacin de los mtodos de trabajo aceptados. Comprobar que los materiales cumplan los requisitos de calidad exigidos en la presente especificacin. Realizar medidas para determinar espesores y levantar perfiles y comprobar la uniformidad de la superficie. Verificar la densidad de cada capa compactada. Este control se realizar en el espesor de cada capa realmente construida, de acuerdo con el proceso constructivo aprobado. Medir los volmenes de relleno colocados por el Contratista en acuerdo a la presente especificacin.
(b) Calidad del producto terminado Los niveles de densidad por alcanzar en las diversas capas del relleno son los mismos que se indican en el numeral 2.7.1.4 de estas especificaciones.
MAYO 2009
2.7.6 Mtodo de medicin La unidad de medida para los volmenes de rellenos ser el metro cbico (m3), aproximado al centsimo de metro cbico, de material compactado, aceptado por la Supervisin, en su posicin final. Los volmenes sern determinados por el mtodo de reas promedios de secciones transversales del proyecto ubicado en su posicin final, verificadas por la Supervisin antes y despus de ser ejecutados los trabajos. No habr medida ni pago para los rellenos por fuera de las lneas del proyecto o de las establecidas por la Supervisin, efectuados por el Contratista, ya sea por error o por conveniencia para la operacin de sus equipos. 2.7.7 Bases de pago El trabajo de rellenos de zanja de anclaje se pagar al precio unitario del contrato, por toda obra ejecutada satisfactoriamente de acuerdo con la presente especificacin y aceptada por la Supervisin. La cantidad de metros cbicos medidos segn procedimiento anterior, ser pagada mediante un slo precio unitario contratado. Dicho precio y pago constituir compensacin completa por toda la mano de obra, equipos y herramientas necesarias para completar la partida.
MAYO 2009
partculas finas del talud durante la crecida del nivel del ro. El geotextil debe ser fabricado con material virgen y ser de polister, del tipo no-tejido, con un gramaje de 200 gr/m2, debiendo cumplir adems con las especificaciones tcnicas siguientes:
2.8.3 Equipos Todos los equipos empleados debern ser compatibles con los procedimientos de construccin adoptados y requieren aprobacin previa de la Supervisin, teniendo en cuenta que su capacidad y eficiencia se ajusten al programa de ejecucin de las obras y al cumplimiento de esta especificacin.
2.8.4 Requerimientos de Construccin La colocacin del geotextil deber realizarse sobre una superficie previamente preparada, emparejada, y libre de materiales punzocortantes. El geotextil deber colocarse cuidadosamente sin arrugas ni pliegues; no se permitir transitar el equipo sobre la tela sin proteccin. Los rollos extendidos debern unirse mediante cosido. Alternativamente, si el Supervisor o el fabricante lo autoriza, traslapada, en cuyo caso el traslape mnimo ser de 0,75 m. la unin podr ser
MAYO 2009
En las curvas, el geotextil podr ser plegado o cortado, para adaptarlo al trazado de la va. En general, el doblez o traslape ser en el sentido de avance de la construccin, y se mantendr unido mediante cosido o traslape, segn corresponda. Una vez que se coloque el geotextil, deber inspeccionarse en busca de posibles daos de instalacin. En caso de que los hubiese, estos sern reparados inmediatamente y se cubrirn con un pao de tela que se extienda como mnimo 1,0 m alrededor de toda la zona daada. 2.8.5 Aceptacin de los Trabajos La aceptacin de los trabajos estar sujeta a los siguientes controles: Verificacin del estado y funcionamiento de las herramientas y equipos a ser utilizado por el Contratista. Supervisin de la correcta aplicacin de los mtodos de construccin mencionados en los numerales precedentes. Verificacin de las dimensiones de la instalacin y determinacin de los metrados. 2.8.6 Mtodo de Medicin El mtodo de medicin de los geotextiles no tejidos ser por metros cuadrados (m2) colocados de acuerdo a las medidas indicadas en los planos y verificadas por el Supervisor. 2.8.7 Bases de Pago Las cantidades determinadas segn el mtodo de medicin sern pagadas de acuerdo a los precios unitarios del contrato establecidos para esta especificacin. Dichos precios y pagos constituirn compensacin total por el costo de los materiales, equipos, mano de obra y herramientas requeridas para la correcta ejecucin de esta partida. Los desperdicios de materiales no sern medidos, quedando entendido que sern incluidos dentro de los precios unitarios respectivos.
MAYO 2009
2.9 COLOCACIN DE ENROCADO CANTERA C/ VOLADURA 2.9.1 Descripcin Esta partida comprende la explotacin de cantera, el transporte y la colocacin del enrocado de proteccin en los sitios sealados en los planos del proyecto. Los enrocados tendrn las dimensiones y espesores que se indican en dichos planos. 2.9.2 Materiales El material para los enrocados de proteccin se extraer de la cantera autorizada por el Supervisor. El enrocado deber estar conformado por rocas sanas, duras, slidas y durables. El material ser razonablemente bien gradado. El material rocoso empleado para la construccin del enrocado deber cumplir la gradacin indicada en el cuadro siguiente: Granulometra del enrocado D50 Max. Min. Max. 0.30 0.25 0.25
2.9.3 Equipos Todos los equipos empleados debern ser compatibles con los procedimientos de construccin adoptados y requieren aprobacin previa de la Supervisin, teniendo en cuenta que su capacidad y eficiencia se ajusten al programa de ejecucin de las obras y al cumplimiento de esta especificacin. 2.9.4 Requerimientos de Construccin Todos los trabajos se ejecutarn de acuerdo con los planos, estas especificaciones y las instrucciones del Supervisor. Las reas en las cuales vayan a colocarse enrocados se pulirn y terminarn por las lneas tericas que se sealan en los planos, con una tolerancia mxima de ms o menos 10 cm. Al colocar los enrocado, stos quedarn del espesor final especificado, en una o dos operaciones segn lo determine el Supervisor. El enrocado colocado quedar bien
MAYO 2009
gradado, con un mnimo porcentaje de vacos y sin zonas con acumulacin de piedras de tamaos pequeos o grandes. Para colocar las rocas se recurrir a trabajo manual, cuando sea necesario, para obtener un enrocado de las caractersticas especificadas y para que los elementos adyacentes queden en contacto. La colocacin de las rocas se har en forma progresiva, logrando de esta manera que los intersticios existentes entre las rocas de mayor tamao puedan ser rellenados por los fragmentos de roca de tamao menor. Se deber evitar la excesiva fracturacin de las rocas al momento de la colocacin en su alineamiento con los equipos indicados. Los fragmentos de roca colocados no tendrn una compactacin especial y sern acomodados de manera que queden regularmente distribuidos, con el menor porcentaje de vacos posible entre ellos a fin de lograr una buena trabazn, para controlar la estabilidad y evitar la erosin lateral. Los huecos debern ser evitados en lo posible o rellenados por rocas y piedras de menores dimensiones para acuar slidamente las rocas mayores logrndose as un cuerpo estable y compacto. 2.9.5 Aceptacin de los Trabajos El supervisor aprobar los trabajos si se satisfacen las exigencias de los planos y de esta especificacin, y si el enrocado construido se ajusta a los alineamientos, pendientes y secciones indicados en los planos del proyecto. En caso de deficiencias de los materiales o de la ejecucin del trabajo, el Contratista deber realizar por su cuenta, las correcciones necesarias hasta cumplir lo especificado. 2.9.6 Mtodo de Medicin La medida ser el volumen en metros cbicos (m3) de roca colocado en su posicin final, obtenida mediante secciones transversales efectuadas y verificadas por el Supervisor. La aproximacin ser el dcimo de metro cbico.
MAYO 2009
2.9.7 Bases de Pago El metrado obtenido ser pagado al precio unitario establecido en el contrato. Dicho precio y pago constituirn compensacin completa del material, equipo, mano de obra (incluidas las leyes sociales), colocacin del material rocoso, todos los carguos y transportes de los materiales, herramientas e imprevistos necesarios para la ejecucin del trabajo a satisfaccin del Supervisor.
3. 3.1
3.1.1 Descripcin Esta partida comprende la perforacin e instalacin de piezmetros de tubo abierto en las ubicaciones que se indican en los planos del presente proyecto. Estos trabajos se ejecutarn de acuerdo a lo indicado en los planos, a las presentes especificaciones y a lo que ordene la Supervisin. 3.1.2 Materiales Todos los materiales empleados para la ejecucin de esta partida debern ser compatibles con los procedimientos de construccin adoptados y requieren la aprobacin previa de la Supervisin. La tubera piezomtrica de PVC ser de dos pulgadas de dimetro y deber contar con un tapn de PVC en su extremo inferior. El tramo ranurado tendr una extensin de 10 m y estar provisto de ranuras espaciadas cada centmetro. Dicho tramo ranurado ser cubierto con un manto de geotextil asegurado al tubo piezomtrico mediante hilo de nylon. 3.1.3 Equipos Todos los equipos empleados debern ser compatibles con los procedimientos de construccin adoptados y requieren aprobacin previa de la Supervisin, teniendo en cuenta que su capacidad y eficiencia se ajusten al programa de ejecucin de las obras y al cumplimiento de esta especificacin.
MAYO 2009
Bsicamente el Contratista deber contar para el trabajo con un equipo de perforacin rotativa con dimetro mnimo de perforacin de denominacin HQ, con broca tricnica. 3.1.4 Requerimientos de construccin Una vez instalado el equipo de perforacin en cada una de las ubicaciones seleccionadas, se proceder a efectuar la perforacin hasta alcanzar la profundidad indicada en los planos y memoria del proyecto. No se requerir la extraccin de muestras de perforacin. Finalizada la perforacin se proceder a instalar en el fondo de la misma la tubera piezomtrica de PVC, luego de lo cual se rellenar el espacio libre entre la perforacin y el tramo ranurado del piezmetro, con arena limpia comprendida entre las mallas ASTM nmero 10 y la nmero 30, la cual deber extenderse 1 m por encima del extremo superior del tramo ranurado. Luego, sobre dicho material de filtro, se colocar un sello de bentonita en pellets de 2.0 m de longitud, para luego continuar con material seleccionado menor a la malla ASTM nmero 4 hasta la boca de la perforacin. Finalmente, en el extremo superior del piezmetro se construir un bloque de concreto, de dimensiones 0.5 x 0.5 x 0.3 m, el cual permitir fijar una proteccin metlica de 5 de dimetro, la misma que tendr tapa y candado, tal como se indica en los planos del proyecto. 3.1.5 Aceptacin de los trabajos La aceptacin de los trabajos estar sujeta a los siguientes controles:
Verificacin del estado y funcionamiento de las herramientas y equipos a ser utilizado por el Contratista.
Verificacin de la profundidad de instalacin. Verificacin del correcto funcionamiento del piezmetro instalado.
3.1.6 Mtodo de medicin El mtodo de medicin ser por metro lineal de piezmetro instalado.
MAYO 2009
3.1.7 Bases de pago Las cantidades determinadas segn el mtodo de medicin sern pagadas de acuerdo a los precios unitarios del contrato establecidos para esta especificacin. Dichos precios y pagos constituirn compensacin total por el costo de los materiales, equipos, mano de obra y herramientas requeridas para la correcta ejecucin de esta partida. Los desperdicios de materiales no sern medidos, quedando entendido que sern incluidos dentro de los precios unitarios respectivos.
3.2
3.2.1 Descripcin Esta partida comprende la construccin de hitos de concreto simple, de resistencia a la compresin fc=210 Kg/cm, los mismos que se ubicarn segn se indican en los planos. Estos hitos tendrn la finalidad de proteger la parte saliente de la tubera piezomtrica. Esta partida deber incluir el costo de todos los materiales, el suministro, procesos y transporte de los agregados, y todo trabajo necesario y complementario para cumplir con xito lo indicado por los planos del proyecto y estas especificaciones 3.2.2 Mtodo de medicin Esta partida se medir por unidad de hito de concreto de 0.5 x 0.5 x0.3 m, terminado de acuerdo a lo indicado por los planos del proyecto y la presente especificacin y bajo aprobacin de la Supervisin. 3.2.3 Bases de pago La cantidad de hitos de concreto ser la que se seala en los planos del proyecto y el precio constituir compensacin total por el costo de la mano de obra, suministros de materiales hasta el lugar de instalacin, equipo, herramientas y cualquier actividad requerida para la completa ejecucin de la partida conforme a estas especificaciones.
MAYO, 2009
ANEXO 7
METRADOS DE OBRA
Proyecto 1-M-373-002
Anexos
RESUMEN DE METRADOS
Proyecto : Ubicacin : Cliente : Nro Proyecto : tem Construccin de la Defensa Riberea de los Depsitos de Relaves San Juan de Arequipa Ro Grande - Condesuyos - Arequipa Century Mining Peru S.A.C. 1-M-373-002 Descripcin
Fecha : Unidad
May-09 Metrado
1.00.00 Obras Provisionales 1.01.00 Movilizacin y Desmovilizacin 1.02.00 Campamento Oficinas Servicios Temporales de Obra 1.03.00 Camino de acceso provisional 1.04.00 Trazo y replanteo durante la ejecucin de la obra 2.00.00 Defensa Riberea 2.01.00 Remocin de relaves 2.02.00 Excavacin para cimentacin de dique 2.03.00 Preparacin de cimentacin de estructuras 2.04.00 Relleno con material de cauce 2.05.00 Perfilado de talud de dique 2.06.00 Excavacin de zanja de anclaje 2.07.00 Relleno de zanja c/mat propio 2.08.00 Geotextil no tejio 200 gr/m2 2.09.00 Colocacin de enrocado - cantera c/voladura 3.00.00 Instrumentacion 3.01.00 Suministro e instalacin de tubera piezometrica 3.02.00 Hito de concreto f'c=210 kg/cm2
M3 M3 M2 M3 M2 M3 M3 M2 M3
Ml Und
50.00 2.00
MAYO, 2009
ANEXO 8
PRESUPUESTO DE OBRA
Proyecto 1-M-373-002
Anexos
PCUWIN
L100510
VALOR REFERENCIAL
PRESUPUESTO UBICACION FECHA BASE PROPIETARIO CONSTRUCTOR CODIGO 1.00.00 1.01.00 1.02.00 1.03.00 1.04.00 2.00.00 2.01.00 2.02.00 2.03.00 2.04.00 2.05.00 2.06.00 2.07.00 2.08.00 2.09.00 3.00.00 3.01.00 3.02.00 Const. Defensa Riberea para los Dep. Relaves San Juan de Chorunga Arequipa Mayo - 2009 CENTURY MINNING PERU S.A.C. ZONA FECHA REPORTE HORA REPORTE PAGINA
UNIDAD NOMBRE DE LA PARTIDA OBRAS PROVISIONALES MOVILIZACION Y DESMOVILIZACION GLB CAMPAMENTO OFICINAS SERVICIOS TEMPORALES DE MES OBRA CAMINO DE ACCESO PROVISIONAL KM TRAZO Y REPLANTEO DURANTE LA EJECUCION DE LA MES OBRA
METRADO COSTO UNIT. 1.00 4.00 1.70 4.00 34,029.38 681.67 3,103.53 3,487.81
55,983.30 DEFENSA RIBEREA REMOCION DE RELAVES EXCAVACION PARA CIMENTACIN DE DIQUE PREPARACION DE CIMENTACION DE ESTRUCTURAS RELLENO CON MATERIAL DEL CAUCE PERFILADO DE TALUD DE DIQUE EXCAVACION DE ZANJA DE ANCLAJE RELLENO DE ZANJA C/MAT PROPIO GEOTEXTIL NO TEJIDO 200 GR/M2 COLOCACION DE ENROCADO - CANTERA C/VOLADURA INSTRUMENTACION SUM. E INST. DE TUBERIA PIEZOMETRICA HITO DE CONCRETO 210 KG/CM2 COSTO DIRECTO GASTOS GENERALES VARIABLES GASTOS GENERALES FIJOS UTILIDAD COSTO TOTAL (GRLS-UTL) I.G.V. COSTO TOTAL GENERAL M3 M3 M2 M3 M2 M3 M3 M2 M3 71,500.00 22,000.00 50,600.00 127,000.00 17,500.00 924.00 924.00 25,500.00 15,000.00 1.05 1.05 0.52 4.26 1.14 1.68 9.95 1.72 12.32 75,075.00 23,100.00 26,312.00 541,020.00 19,950.00 1,552.32 9,193.80 43,860.00 184,800.00 924,863.12 ML UND 50.00 2.00 157.39 30.02 7,869.50 60.04 7,929.54 988,775.96 197,755.19 49,438.80 98,877.60 1,334,847.55 253,621.03 1,588,468.58
( 20 % ) (5%) ( 10 % ) ( 19 % )
SON : UN MILLN QUINIENTOS OCHENTA Y OCHO MIL CUATROCIENTOS SESENTA Y OCHO 58 / 100 DOLARES AMERICANOS
PCUWIN
L1005
PAGINA 1 1494 PARTIDA 1.01.00 MOVILIZACION Y DESMOVILIZACION ANALISIS 11400 DESCRIPCION Equipo transportado (40% tarifa)+ Equipo Autotransportado (100% tarifa) Incluye limpieza y montaje de RENDIMIENTO 1.0000 GLB CODIGO RECURSOS UNIDAD CANTIDAD PRECIO UNITARIO SUBTOTAL TOTAL 2.0000 2,000.00 356901 MOVILIZACION CAMION CISTERNA 2000 GL UND 1,000.00 6.0000 3,000.00 356902 MOVILIZACION CAMION VOLQUETE 15 M3 UND 500.00 2.0000 3,000.00 356903 MOVILIZACION CARGADOR S/LL 4.0Y3 200-250HP UND 1,500.00 2.0000 3,000.00 356910 MOVILIZACION DE EQUIPOS MENORES UND 1,500.00 2.0000 4,000.00 356905 MOVILIZACION EXCAVADORA S/O 170-250HP UND 2,000.00 4.0000 6,000.00 356906 MOVILIZACION MOTONIVELADORA 145-150HP UND 1,500.00 4.0000 6,000.00 356907 MOVILIZACION RODILLO LISO VIB. AUTOPR. 136-170HP UND 1,500.00 2.0000 3,000.00 356908 MOVILIZACION TRACTOR DE ORUGAS 140-185HP UND 1,500.00 2.0000 4,000.00 356909 MOVILIZACION TRACTOR DE ORUGAS 300-330HP UND 2,000.00 34,000.00 3.2000 13.98 191000 CAPATAZ HH 4.37 4.0000 14.00 387000 PEON HH 3.50 27.98 0.0500 1.40 280800 HERRAMIENTAS (% MANO DE OBRA ) % 27.98 1.40 COSTO DIRECTO 34,029.38 PAGINA 1 1494 PARTIDA 1.02.00 CAMPAMENTO OFICINAS SERVICIOS TEMPORALES DE OBRA ANALISIS 10310 DESCRIPCION ALQUILER DE MODULOS PREFABRICADOS RENDIMIENTO 1.0000 MES CODIGO SUBTOTAL TOTAL RECURSOS UNIDAD CANTIDAD PRECIO UNITARIO 1.0000 155.00 210060 CONTENEDOR ALMACEN 2.40 x 6.00 MES 155.00 1.0000 216.67 210100 CONTENEDOR BAOS 2.40 x 6.00 (2 WC+2URI+3 LAV+3DU) MES 216.67 1.0000 155.00 210080 CONTENEDOR LABORATORIO 2.40 x 6.00 MES 155.00 1.0000 155.00 210000 CONTENEDOR OFICINA 2.40 x 6.00 m MES 155.00 681.67 COSTO DIRECTO 681.67 PAGINA 1 1494 PARTIDA 1.03.00 CAMINO DE ACCESO PROVISIONAL ANALISIS 10200 DESCRIPCION RENDIMIENTO 0.6000 KM CODIGO SUBTOTAL TOTAL RECURSOS UNIDAD CANTIDAD PRECIO UNITARIO 2.6667 93.33 185710 CAMION CISTERNA 2000GL.122HP HM 35.00 13.3333 850.93 355740 MOTONIVELADORA 145-150 HP HM 63.82 13.3333 466.67 445620 RODILLO LISO VIB. AUTOPR. 136 -170HP (CAT 533 C) HM 35.00 13.3333 1,422.27 487860 TRACTOR DE ORUGAS 300-330HP (CAT D-8) HM 106.67 2,833.20 6.6667 29.13 191000 CAPATAZ HH 4.37 66.6667 233.33 387000 PEON HH 3.50 262.46 0.0300 7.87 280800 HERRAMIENTAS (% MANO DE OBRA ) % 262.46 7.87 COSTO DIRECTO 3,103.53 PAGINA 1 1494 PARTIDA 1.04.00 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE LA OBRA ANALISIS 13300 DESCRIPCION RENDIMIENTO 1.0000 MES CODIGO SUBTOTAL TOTAL RECURSOS UNIDAD CANTIDAD PRECIO UNITARIO 500.0000 65.00 184100 CAL BLANCA KG 0.13 100.0000 67.00 247300 ESTACA DE MADERA UND 0.67 1.0000 1,033.33 247510 ESTACION TOTAL 5" DE PRECISION MES 1,033.33 2.0000 333.34 247520 PRISMA + BASTON PARA ESTACION TOTAL MES 166.67 1,498.67 320.0000 1,235.20 371000 OFICIAL HH 3.86 120.0000 696.00 486200 TOPOGRAFO HH 5.80 1,931.20 0.0300 57.94 280800 HERRAMIENTAS (% MANO DE OBRA ) % 1,931.20 57.94 COSTO DIRECTO 3,487.81
PCUWIN 2
L1005
1494
UNIDAD HM HM HM HH HH HH %
ANALISIS 2014 RENDIMIENTO 1,300.0000 M3 SUBTOTAL TOTAL PRECIO UNITARIO 0.12 40.00 0.22 72.19 0.66 106.67 1.00 0.01 4.37 3.41 0.04 3.50 0.05 0.05 2 1494 1.05
ANALISIS 21520 RENDIMIENTO 1,300.0000 M3 SUBTOTAL TOTAL PRECIO UNITARIO 0.12 40.00 0.22 72.19 0.66 106.67 1.00 0.01 4.37 3.41 0.04 3.50 0.05 0.05 2 1494 1.05
PARTIDA 2.03.00 PREPARACION DE CIMENTACION DE ESTRUCTURAS ANALISIS 22920 DESCRIPCION RENDIMIENTO 2,200.0000 M2 CODIGO SUBTOTAL TOTAL RECURSOS UNIDAD CANTIDAD PRECIO UNITARIO 0.0036 0.23 355740 MOTONIVELADORA 145-150 HP HM 63.82 0.0036 0.13 445620 RODILLO LISO VIB. AUTOPR. 136 -170HP (CAT 533 C) HM 35.00 0.36 0.0036 0.02 191000 CAPATAZ HH 4.37 0.0145 0.05 387000 PEON HH 3.50 0.07 0.0300 280800 HERRAMIENTAS (% MANO DE OBRA ) % 0.07 1100 AGUA DE RIEGO PARA RELLENO COMPACTADO (1 km) COSTO DIRECTO PAGINA PARTIDA 2.04.00 RELLENO CON MATERIAL DE PRESTAMO DESCRIPCION CODIGO RECURSOS UNIDAD 1020 CARGUIO MATERIAL APILADO M3 2400 EXTRACCION Y APILAMIENTO M3 23000 RELLENO COMPACTADO M3 3340 TRANSPORTE MATERIAL SUELTO d= 0.1 km M3 COSTO DIRECTO PARTIDA 2.05.00 PERFILADO DE TALUD DE DIQUE DESCRIPCION CODIGO RECURSOS 445620 RODILLO LISO VIB. AUTOPR. 136 -170HP (CAT 533 C) 1100 AGUA DE RIEGO PARA RELLENO COMPACTADO (1 km) 2212 CORTE DE SOBREANCHO EN TALUDES 21195 ELIMINACION LATERAL DE MATERIAL SEGREGADO COSTO DIRECTO 2 1494 M3 0.0300 2.90 0.09 0.09 0.52
ANALISIS 90000 RENDIMIENTO 1,050.0000 M3 SUBTOTAL TOTAL PRECIO UNITARIO 0.83 0.69 1.12 0.93 1.52 1.52 0.79 0.66 4.26 4.26 PAGINA 2 1494 ANALISIS 22910 RENDIMIENTO 2,500.0000 M2 SUBTOTAL TOTAL PRECIO UNITARIO 0.11 35.00 0.11 0.09 2.90 0.63 1.25 0.31 0.46 1.03 1.14
UNIDAD HM M3 M3 M3
PCUWIN 3
L1005
1494
ANALISIS 21720 RENDIMIENTO 500.0000 M3 SUBTOTAL TOTAL PRECIO UNITARIO 1.60 100.19 1.60 0.01 4.37 0.07 4.33 0.08 0.08 3 1494 1.68
ANALISIS 23110 RENDIMIENTO 20.0000 M3 SUBTOTAL TOTAL CANTIDAD PRECIO UNITARIO 0.4000 3.00 7.50 3.00 0.2000 0.87 4.37 1.6000 5.60 3.50 6.47 0.0300 0.19 6.47 0.19 0.1000 0.29 2.90 0.29 9.95 PAGINA 3 1494 ANALISIS 64400 RENDIMIENTO 250.0000 M2 SUBTOTAL TOTAL PRECIO UNITARIO 1.22 1.16 1.22 0.01 4.37 0.14 4.33 0.34 3.50 0.49 0.01 0.49 0.01 1.72 PAGINA 3 1494
UNIDAD M2 HH HH HH %
PARTIDA 2.09.00 COLOCACION DE ENROCADO - CANTERA C/VOLADURA ANALISIS 63205 DESCRIPCION RENDIMIENTO 300.0000 M3 CODIGO SUBTOTAL TOTAL RECURSOS UNIDAD CANTIDAD PRECIO UNITARIO 0.0267 2.67 248416 EXCAVADORA S/O. 170-250HP (CAT 330) HM 100.19 2.67 0.0533 0.23 191000 CAPATAZ HH 4.37 0.0533 0.23 372000 OPERARIO HH 4.33 0.3200 1.12 387000 PEON HH 3.50 1.58 0.0300 0.05 280800 HERRAMIENTAS (% MANO DE OBRA ) % 1.58 0.05 1.3000 0.74 1040 CARGUIO ENROCADO M3 0.57 1.3000 6.33 2600 PERFORACION Y DISPARO EN ROCA FIJA M3 4.87 1.3000 0.95 3361 TRANSPORTE MATERIAL GRUESO d= 1 km M3 0.73 8.02 COSTO DIRECTO 12.32 PAGINA 3 1494 PARTIDA 3.01.00 SUM. E INST. DE TUBERIA PIEZOMETRICA ANALISIS 80010 DESCRIPCION Provision e instalaci{on de Tuberia Piezometrica Standar RENDIMIENTO 0.5000 ML CODIGO SUBTOTAL TOTAL RECURSOS UNIDAD CANTIDAD PRECIO UNITARIO 0.0055 16.50 356900 MOVILIZACION PERFORADORA ROTATIVA UND 3,000.00 1.1000 66.00 389602 PERFORACION ROTAT. EN SUELO S/RECUPER DE ML 60.00 TESTIGOS 1.0500 45.50 507590 TUBERIA PIEZOMETRICA 2". ML 43.33 128.00 1.6000 6.99 191000 CAPATAZ HH 4.37 6.4000 22.40 387000 PEON HH 3.50 29.39 COSTO DIRECTO 157.39
PCUWIN 4
L1005
1494
280800 HERRAMIENTAS (% MANO DE OBRA ) 4930 CONCRETO F'c=175 kg/cm2 C/MEZCLADORA 62760 ENCOFRADO Y DESENCOFRADO COSTO DIRECTO PARTIDA CARGUIO MATERIAL APILADO DESCRIPCION Material esponjado. CODIGO RECURSOS 191470 CARGADOR S/LL 4.0Y3 200-250HP (CAT 966) 211000 CONTROLADOR COSTO DIRECTO PARTIDA CARGUIO ENROCADO DESCRIPCION Material en Cantera CODIGO RECURSOS 191470 CARGADOR S/LL 4.0Y3 200-250HP (CAT 966)
ANALISIS 61250 RENDIMIENTO 5.0000 UND SUBTOTAL TOTAL PRECIO UNITARIO 0.70 4.37 22.40 3.50 23.10 1.16 23.10 1.16 1.09 36.23 4.67 9.34 5.76 30.02 PAGINA 4 1494
UNIDAD HM HH
ANALISIS 1020 RENDIMIENTO 867.0000 M3 SUBTOTAL TOTAL CANTIDAD PRECIO UNITARIO 0.0092 0.67 72.19 0.67 0.0046 0.02 3.41 0.02 0.69 PAGINA 4 1494
ANALISIS 1040 RENDIMIENTO 1,040.0000 M3 SUBTOTAL TOTAL UNIDAD CANTIDAD PRECIO UNITARIO 0.0077 0.56 HM 72.19 0.56 0.0038 0.01 211000 CONTROLADOR HH 3.41 0.01 COSTO DIRECTO 0.57 PAGINA 4 1494 PARTIDA AGUA DE RIEGO PARA RELLENO COMPACTADO (1 km) ANALISIS 1100 DESCRIPCION DISTANCIA PROMEDIO 1 KM DESDE LA FUENTE DE AGUA RENDIMIENTO 120.0000 M3 CODIGO SUBTOTAL TOTAL RECURSOS UNIDAD CANTIDAD PRECIO UNITARIO 0.0667 2.33 185710 CAMION CISTERNA 2000GL.122HP HM 35.00 0.0667 0.27 355440 MOTOBOMBA 4" 12 HP PETROLEO HM 4.00 2.60 0.0067 0.03 191000 CAPATAZ HH 4.37 0.0667 0.26 371000 OFICIAL HH 3.86 0.29 0.0300 0.01 280800 HERRAMIENTAS (% MANO DE OBRA ) % 0.29 0.01 COSTO DIRECTO 2.90 PAGINA 4 1494 PARTIDA AGUA PARA CONCRETO ANALISIS 1110 DESCRIPCION RENDIMIENTO 120.0000 M3 CODIGO SUBTOTAL TOTAL RECURSOS UNIDAD CANTIDAD PRECIO UNITARIO 0.0667 2.33 185710 CAMION CISTERNA 2000GL.122HP HM 35.00 0.0667 0.27 355440 MOTOBOMBA 4" 12 HP PETROLEO HM 4.00 2.60 0.0067 0.03 191000 CAPATAZ HH 4.37 0.0667 0.26 371000 OFICIAL HH 3.86 0.29 0.0300 0.01 280800 HERRAMIENTAS (% MANO DE OBRA ) % 0.29 0.01 COSTO DIRECTO 2.90 PAGINA 4 1494 PARTIDA CORTE DE SOBREANCHO EN TALUDES ANALISIS 2212 DESCRIPCION RENDIMIENTO 700.0000 M3 CODIGO SUBTOTAL TOTAL RECURSOS UNIDAD CANTIDAD PRECIO UNITARIO 0.0114 1.15 248416 EXCAVADORA S/O. 170-250HP (CAT 330) HM 100.19 1.15 0.0023 0.01 191000 CAPATAZ HH 4.37 0.0023 0.01 211000 CONTROLADOR HH 3.41 0.0229 0.08 387000 PEON HH 3.50 0.10 0.0300 280800 HERRAMIENTAS (% MANO DE OBRA ) % 0.10 COSTO DIRECTO 1.25
PCUWIN 5
L1005
1494
UNIDAD HM HH HH HH %
ANALISIS 2400 RENDIMIENTO 675.0000 M3 SUBTOTAL TOTAL PRECIO UNITARIO 0.83 70.00 0.83 0.01 4.37 0.01 3.41 0.08 3.50 0.10 0.10 5 1494 0.93
CANTIDAD 0.0170 0.2500 1.0000 1.0000 0.0250 0.1000 0.0125 0.0250 0.1000 0.0500
ANALISIS 2600 RENDIMIENTO 320.0000 M3 SUBTOTAL TOTAL PRECIO UNITARIO 1.90 111.67 0.71 2.83 0.15 0.15 0.16 0.16 2.92 1.08 43.13 0.16 1.59 1.24 0.05 4.37 0.09 3.41 0.39 3.86 0.18 3.50 0.71 4.87 PAGINA 5 1494
ANALISIS 3340 RENDIMIENTO 490.0000 M3 SUBTOTAL TOTAL CANTIDAD PRECIO UNITARIO 0.0163 0.65 40.00 0.65 0.0033 0.01 3.41 0.01 0.66 PAGINA 5 1494 ANALISIS 3361 RENDIMIENTO 442.0000 M3 SUBTOTAL TOTAL CANTIDAD PRECIO UNITARIO 0.0181 0.72 40.00 0.72 0.0036 0.01 3.41 0.01 0.73 PAGINA 5 1494 ANALISIS 4930 RENDIMIENTO 16.0000 M3 SUBTOTAL TOTAL PRECIO UNITARIO 1.50 5.00 19.32 4.83 1.80 6.00 22.62 2.19 4.37 10.50 3.50 12.69 0.38 12.69 0.38 0.54 2.90 0.54 36.23
PCUWIN
L1005
PAGINA 6 1494 PARTIDA ELIMINACION LATERAL DE MATERIAL SEGREGADO ANALISIS 21195 DESCRIPCION RENDIMIENTO 2,000.0000 M3 CODIGO SUBTOTAL TOTAL RECURSOS UNIDAD CANTIDAD PRECIO UNITARIO 0.0040 0.16 186820 CAMION VOLQUETE 15 M3. HM 40.00 0.0040 0.29 191470 CARGADOR S/LL 4.0Y3 200-250HP (CAT 966) HM 72.19 0.45 0.0020 0.01 211000 CONTROLADOR HH 3.41 0.01 COSTO DIRECTO 0.46 PAGINA 6 1494 PARTIDA RELLENO COMPACTADO ANALISIS 23000 DESCRIPCION RENDIMIENTO 1,050.0000 M3 CODIGO SUBTOTAL TOTAL RECURSOS UNIDAD CANTIDAD PRECIO UNITARIO 0.0076 0.49 355740 MOTONIVELADORA 145-150 HP HM 63.82 0.0076 0.27 445620 RODILLO LISO VIB. AUTOPR. 136 -170HP (CAT 533 C) HM 35.00 0.0038 0.27 487830 TRACTOR DE ORUGAS 140-185HP (CAT D-6) HM 70.00 1.03 0.0076 0.03 191000 CAPATAZ HH 4.37 0.0457 0.16 387000 PEON HH 3.50 0.19 0.0300 0.01 280800 HERRAMIENTAS (% MANO DE OBRA ) % 0.19 0.01 0.1000 0.29 1100 AGUA DE RIEGO PARA RELLENO COMPACTADO (1 km) M3 2.90 0.29 COSTO DIRECTO 1.52 PAGINA 6 1494 PARTIDA ENCOFRADO Y DESENCOFRADO ANALISIS 62760 DESCRIPCION RENDIMIENTO 16.0000 M2 CODIGO SUBTOTAL TOTAL RECURSOS UNIDAD CANTIDAD PRECIO UNITARIO 0.2000 0.20 113300 ALAMBRE NEGRO # 08 KG 1.00 0.1500 0.15 197800 CLAVO PROMEDIO CONSTRUCCION KG 1.00 3.5000 4.45 341700 MADERA TORNILLO HASTA L=12' P2 1.27 4.80 0.0500 0.22 191000 CAPATAZ HH 4.37 0.5000 1.93 371000 OFICIAL HH 3.86 0.5000 2.17 372000 OPERARIO HH 4.33 4.32 0.0500 0.22 280800 HERRAMIENTAS (% MANO DE OBRA ) % 4.32 0.22 COSTO DIRECTO 9.34
MAYO, 2009
ANEXO 9
CRONOGRAMA DE EJECUCION DE OBRA
Proyecto 1-M-373-002
Anexos
SVS Ingenieros S.A.C. Const. Defensa Riberea para los Dep. Relaves San Juan de Arequipa - ETAPA I Id 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 FIN
Tarea Divisin Hito
Item
S2
S3
S4
S6
S7
S8
S11
S12
S13
1.00 OBRAS PROVISIONALES 1.01 1.02 1.03 1.04 Movilizacin y desmovilizacin de equipos Campamento Oficinas Servicios Temporales de Obra Camino de acceso temporal Trazo y replanteo durante la ejecucion de la obra
2.00 DEFENSA RIBEREA 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 Remocion de relaves Excavacion para cimentacion de dique Preparacion de cimentacion de estructuras Relleno con material de cauce Perfilado de talud de dique Excavacion de zanja de anclaje Relleno de zanja c/mat propio Geotextil no tejido 200 gr/m2 Colocacion de enrocado - cantera c/voladura
85 das 30 das 8 das 8 das 50 das 12 das 3 das 6 das 5 das 11 das
3.00 INSTRUMENTACION 3.01 3.02 Suministro e instalacion de tuberia piezometrica Hito de concreto f'c = 210 kg/cm2
7 das 7 das 1 da
0 das
Resumen
FIN
SVS Ingenieros S.A.C. Const. Defensa Riberea para los Dep. Relaves San Juan de Arequipa - ETAPA II Id 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 FIN 0 das 2.00 DEFENSA RIBEREA 2.04 2.05 2.06 2.07 2.08 2.09 Relleno con material de cauce Perfilado de talud de dique Excavacion de zanja de anclaje Relleno de zanja c/mat propio Geotextil no tejido 200 gr/m2 Colocacion de enrocado - cantera c/voladura 88 das 60 das 12 das 3 das 6 das 5 das 11 das 1.00 OBRAS PROVISIONALES 1.01 1.02 1.03 1.04 Movilizacin y desmovilizacin de equipos Campamento Oficinas Servicios Temporales de Obra Camino de acceso temporal Trazo y replanteo durante la ejecucion de la obra 90 das 4 das 3 das 4 das 86 das Item Nombre de tarea INICIO Duracin S-1 0 das NICIO mes 1 S1 S2 S3 S4 mes 2 S5 S6 S7 S8
S11
S12
S13
FIN
Tarea
Divisin
Hito
Resumen
MAYO, 2009
ANEXO 10
ARCHIVO FOTOGRAFICO
Proyecto 1-M-373-002
Anexos
Foto N 1: Vista de una de las 04 perforaciones con el sistema Wash Boring (Perforacin por Lavado) realizadas en los taludes de los Depsitos de Relaves de San Juan de Arequipa
Foto N 2: Vista de una de las muestras de relave obtenida de la perforacin Pz-1. Se aprecia la textura arenosa de la muestra.
DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPOSITOS DE RELAVES SAN JUAN DE AREQUIPA FOTOS DE LOS TRABAJOS DE SONDEO 05-2009
Foto N 3: Vista interior de una de las excavaciones ejecutadas con anterioridad al presente estudio, en los Depsitos de Relaves
Foto N 4: Vista interior de la calicata CR-1. Al fondo se aprecia el ensayo de densidad in situ realizado a los 3.0 m de profundidad.
DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPOSITOS DE RELAVES SAN JUAN DE AREQUIPA FOTOS DE EXCAVACIONES 05-2009
Foto N 5: Vista panormica del cauce del ro vista hacia aguas arriba. A la izquierda se encuentran los depsitos de relaves.
Depsitos de Relaves
DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPOSITOS DE RELAVES SAN JUAN DE AREQUIPA FOTOS PANORAMICAS 05-2009
Foto N 7: Vista interior de la calicata C-1, realizada en el cauce del ro cerca al depsito de relaves N 5
Foto N 8: Vista interior de la calicata C-3, realizada en el cauce del ro cerca al depsito de relaves N 3
DISEO DE RECRECIMIENTO Y DEFENSA RIBEREA DE LOS DEPOSITOS DE RELAVES SAN JUAN DE AREQUIPA FOTOS DE EXCAVACIONES 05-2009
MAYO, 2009
PLANOS
Proyecto 1-M-373-002
Anexos