Sie sind auf Seite 1von 8

PERIODIC FIELD OBSERVATION REPORT

Project: _Two-Storey Academic Bldg__


Owner: _NDDU IBED Espina________
Re: _Field Observation Report________

Weather

Report Number:: _____1_______________


Date:_____Sept. 17, 2013______________
Time:_____6:40-8:40__________________

Site Conditions

Day

Clear
Clear
Monday
Overcast
Muddy
Tuesday
Rain
Dusty
Wednesday
Foggy
_______
Thursday
Cold
Temperature Range
Friday
Warm
_____________
__________
Hot
______________________________________________________________________________
Persons Contacted:
Bro. Nino
Engr. Faisal Kusain
______________________________________________________________________________
Work Observed:
Setting of Steel Deck
Setting of slab reinforcement
______________________________________________________________________________
Items Discussed:
Request for set of plan and specifications
Current work done: setting of steel deck for slab and slab reinforcement.
Specifications of steel used in construction.
Slab concreting on the second floor is expected on September 25.
______________________________________________________________________________
Remarks:
This is the first field visit on site of the construction project.
The construction is on-going for two months now, starting on July 15, 2013, according to the
project Engineer on site.
The project is contracted for P25.5 M , 10-month period.
Attachments:
______________________________________________________________________________
Signed By:
Date:
_____________________________________________________________________________
Copies:
Owner
A/E Contractor Consultants __________ File

PERIODIC FIELD OBSERVATION REPORT

Project: _Two-Storey Academic Bldg__


Owner: _NDDU IBED Espina________
Re: _Field Observation Report________

Weather

Report Number:: _____2_______________


Date:_____Sept. 19, 2013______________
Time:_____3:00______________________

Site Conditions

Day

Clear
Clear
Monday
Overcast
Muddy
Tuesday
Rain
Dusty
Wednesday
Foggy
_______
Thursday
Cold
Temperature Range
Friday
Warm
_____________
__________
Hot
______________________________________________________________________________
Persons Contacted:
Engr. Faisal Kusain
______________________________________________________________________________
Work Observed:
Setting of slab reinforcement
Slab reinforcement is 10mm both for one-way and two-way slabs. The 12mm as per plan
was erroneously written, instead, it should be 10mm as mentioned by Engr. Kusain
______________________________________________________________________________
Items Discussed:
Current work done: setting of steel deck for slab and slab reinforcement.
Specifications of steel deck used, 0.80mm thickness.
Slab reinforcement is 10mm both for one-way and two-way slabs and not 12mm.
The number of reinforcing steel bars for columns 1-3.
______________________________________________________________________________
Remarks:
Eskumbro soil type is on-site for back-filling.
Attachments:
______________________________________________________________________________
Signed By:
Date:
_____________________________________________________________________________
Copies:
Owner
A/E Contractor Consultants __________ File

PERIODIC FIELD OBSERVATION REPORT

Project: _Two-Storey Academic Bldg__


Owner: _NDDU IBED Espina________
Re: _Field Observation Report________

Weather

Report Number:: _____3_______________


Date:_____Sept. 20, 2013______________
Time:_____4:30______________________

Site Conditions

Day

Clear
Clear
Monday
Overcast
Muddy
Tuesday
Rain
Dusty
Wednesday
Foggy
_______
Thursday
Cold
Temperature Range
Friday
Warm
_____________
__________
Hot
______________________________________________________________________________
Persons Contacted:
Engr. Faisal Kusain
______________________________________________________________________________
Work Observed:
Setting of slab reinforcement
Electrical-setting for electrical connections
Start of back-filling for a portion of the natural ground line.

______________________________________________________________________________
Items Discussed:

______________________________________________________________________________
Remarks:

Attachments:
______________________________________________________________________________
Signed By:
Date:
_____________________________________________________________________________
Copies:
Owner
A/E Contractor Consultants __________ File

PERIODIC FIELD OBSERVATION REPORT

Project: _Two-Storey Academic Bldg__


Owner: _NDDU IBED Espina________
Re: _Field Observation Report________

Weather

Report Number:: _____4_______________


Date:_____Sept. 24, 2013______________
Time:_____4:30______________________

Site Conditions

Day

Clear
Clear
Monday
Overcast
Muddy
Tuesday
Rain
Dusty
Wednesday
Foggy
_______
Thursday
Cold
Temperature Range
Friday
Warm
_____________
__________
Hot
______________________________________________________________________________
Persons Contacted:
Engr. Faisal Kusain
______________________________________________________________________________
Work Observed:
Electrical-setting for electrical connections
Setting of slab reinforcement

______________________________________________________________________________
Items Discussed:
______________________________________________________________________________
Remarks:

Attachments:
______________________________________________________________________________
Signed By:
Date:
_____________________________________________________________________________
Copies:
Owner
A/E Contractor Consultants __________ File

PERIODIC FIELD OBSERVATION REPORT

Project: _Two-Storey Academic Bldg__


Owner: _NDDU IBED Espina________
Re: _Field Observation Report________

Weather

Report Number:: _____5_______________


Date:_____Sept. 25, 2013______________
Time:_____9:30__________________

Site Conditions

Day

Clear
Clear
Monday
Overcast
Muddy
Tuesday
Rain
Dusty
Wednesday
Foggy
_______
Thursday
Cold
Temperature Range
Friday
Warm
_____________
__________
Hot
______________________________________________________________________________
Persons Contacted:
Engr. Faisal Kusain
______________________________________________________________________________
Work Observed:
Pouring / Concreting of Second Floor Slab

______________________________________________________________________________
Items Discussed:

Specifications of steel used in construction.


Specifications of premix concrete for slab concreting on the second floor (14 days, 3000 psi)
______________________________________________________________________________
Remarks:

Attachments:
______________________________________________________________________________
Signed By:
Date:
_____________________________________________________________________________
Copies:
Owner
A/E Contractor Consultants __________ File

PERIODIC FIELD OBSERVATION REPORT

Project: _Two-Storey Academic Bldg__


Owner: _NDDU IBED Espina________
Re: _Field Observation Report________

Weather

Report Number:: _____6_______________


Date:_____Sept. 27, 2013______________
Time:_____10:30__________________

Site Conditions

Day

Clear
Clear
Monday
Overcast
Muddy
Tuesday
Rain
Dusty
Wednesday
Foggy
_______
Thursday
Cold
Temperature Range
Friday
Warm
_____________
__________
Hot
______________________________________________________________________________
Persons Contacted:
Leadman Joel Mabagat
______________________________________________________________________________
Work Observed:
Setting of Steel Deck/Reinforcement for the remaining portion of second floor slab
Setting of column reinforcements for second floor
Setting of forms for second floor columns.

______________________________________________________________________________
Items Discussed:
______________________________________________________________________________
Remarks:
Attachments:
______________________________________________________________________________
Signed By:
Date:
_____________________________________________________________________________
Copies:
Owner
A/E Contractor Consultants __________ File

PERIODIC FIELD OBSERVATION REPORT

Project: _Two-Storey Academic Bldg__


Owner: _NDDU IBED Espina________
Re: _Field Observation Report________

Weather

Report Number:: _____7_______________


Date:_____Sept. 30, 2013______________
Time:_____9:30__________________

Site Conditions

Day

Clear
Clear
Monday
Overcast
Muddy
Tuesday
Rain
Dusty
Wednesday
Foggy
_______
Thursday
Cold
Temperature Range
Friday
Warm
_____________
__________
Hot
______________________________________________________________________________
Persons Contacted:
Leadman Joel Mabagat
______________________________________________________________________________
Work Observed:
Setting of Steel Deck/Reinforcement for the remaining portion of second floor slab
Setting of column reinforcements for second floor
Setting of forms for second floor columns.

______________________________________________________________________________
Items Discussed:
Splicing of column reinforcements
______________________________________________________________________________
Remarks:
The following items were counter-checked by actual measuring/counting:
a. The dimensions of columns
b. The diameter and the number of reinforcing steel bars for columns.
c. The dimensions of : hallway and classrooms
Attachments:
______________________________________________________________________________
Signed By:
Date:
_____________________________________________________________________________
Copies:
Owner
A/E Contractor Consultants __________ File

Das könnte Ihnen auch gefallen