Beruflich Dokumente
Kultur Dokumente
374
Frequency of Intervals of R Projects fi (1) (2) R<0.88 0.88<R<0.90 0.90<R<0.92 0.92<R<0.94 0.94<R<0.96 0.96<R<0.98 0.98<R<1.00 1.00<R<1.02 1.02<R<1.04 1.04<R<1.06 1.06<R<1.08 1.08<R<1.10 1.10<R<1.12 1.12<R Totals
R=
Interval Midpoint Ri (3) 0.89 0.91 0.93 0.95 0.97 0.99 1.01 1.03 1.05 1.07 1.09 1.11
f i x Ri (4) 0.00 0.89 0.00 2.79 5.70 11.64 15.84 14.14 9.27 3.15 2.14 1.09 1.11 0.00 67.76
Percentage Interval Cumulative Variance Cumulative Frequency Frequency 2 F (Ri - R) x fi F n x 100 (5) (6) (7) 0 1 1 4 10 22 38 52 61 64 66 67 68 68 0 1.47 1.47 5.88 14.71 32.35 55.88 76.47 89.71 94.12 97.06 98.53 100.00 100.00 0.0000 0.0113 0.0000 0.0133 0.0130 0.0084 0.0007 0.0026 0.0101 0.0086 0.0108 0.0087 0.0129 0.0000 0.1004
2
0 1 0 3 6 12 16 14 9 3 2 1 1 0 n = 68
Actual Project Cost Estimated Project Cost 67.76 68 = 0.9965 s = Standard Deviation = s=
(Ri R) x fi
n 1
0.1004 = 0.039 681
Average Value of R = R =
frequency polygon is now smoothed by sketching in a smooth curve that closely approximates the linear segments of the polygon. The resulting curve affords a quick and nonquantitative grasp of the companys bidding accuracy over the past ve years, as will now be explained. It is reasonable to assume that estimating errors should be essentially random in nature and conform to the well-known normal distribution. Another way of saying this, perhaps, is that there should be an equal tendency to overprice and underprice a construction estimate. Consequently, it is suggested that a good estimating system is one whose ratios, R, are normally distributed with a mean value of 1.0 and a small range of larger and smaller values. If the smoothed polygon obtained from the histogram of R-values resembles a normal distribution of small variance and with its mode at or very near a value of 1.0, such as that shown by curve A of Figure F.3, the overall bidding accuracy of the contractor has been good. Although curve B has its mode at 1.0, the large dispersion of values indicates loose estimating with a serious tendency to both underestimate and overestimate. A biased distribution such as curve C is indicative of systematic estimating errors or procedures that result in a pronounced
375
R=
Figure F.2 Histogram of R-values
Number of projects
C B
1.00
R
Figure F.3 Bidding accuracy distribution
376
Cumulative frequency, F
R=
Figure F.4 Cumulative frequency of R-values
tendency to consistently either underestimate or overestimate a majority of the jobs bid. If a smoothed polygon were to be sketched onto Figure F.2, the resulting curve would closely resemble a normal distribution with its mode at or very near a value, R, of 1.0. Another plot of interest is cumulative frequency versus values of R. The values of cumulative frequency are computed in Figure F.1 and are plotted in Figure F.4. Figure F.4 is actually a less-than curve. To illustrate, this gure discloses that 38 of the 68 projects had an R-value of less than 1.00. This means that on 38 of the completed projects, the actual costs were less than those estimated.
377
1.0. The signicance of this is that, despite the fact that more jobs were overestimated than underestimated (38-30), there has been no consistent tendency to estimate too high or too low insofar as R-values are concerned. The other measure of accuracy has to do with the dispersion or scatter of values of R. In our case, there were no values of R less than 0.88 nor larger than 1.12. This indicates, in a general fashion, that during the past years, projects have been both underestimated and overestimated by as much as approximately 12 percent. These values are indicative of extreme range, however, and do not tell the entire story. A much better measure of dispersion is the standard deviation that is computed in Figure F.1 and has a value of 0.039. The signicance of this value will be discussed subsequently. Another way discrete data can be checked for normal distribution is to plot them on normal probability paper. This is a special graph paper available at technical bookstores and similar outlets. Figure F.5 shows a plot on normal probability paper of percentage cumulative frequency verus the ratio, R. The values of percentage cumulative frequency have been calculated in Figure F.1. The closer the points plot to a straight line, the better the normality of a set of data. R-values deviating from a straight
s 0.039 s 0.039
Mean 1.0
0.96
0.98
1.00
1.02
1.08
R=
Figure F.5 Normal probability plot
1.10
378
Equipment Material $57,028 $237,922 $78,867 $370,277 $3,884 $26,018 $71,165 $52,934 $21,034 $310,225 $194,280 $605,308 $36,950 $76,541 $86,416 $215,880 $71,074 $220,315 $129,532 $415,658 $750,230 $2,531,078
Overhead $41,338 $64,066 $11,825 $50,751 $80,288 $104,596 $41,080 $66,014 $71,949 $112,371 $644,278
Equipment Material $56,030 $228,643 $78,173 $361,279 $3,794 $24,683 $71,983 $51,510 $20,923 $306,037 $195,601 $582,367 $36,780 $75,500 $85,336 $212,966 $71,458 $219,456 $128,677 $404,477 $748,755 $2,466,918
Overhead $38,986 $62,022 $12,824 $52,502 $79,622 $100,600 $40,550 $67,922 $76,129 $111,382 $642,540
Labor 1.070 1.036 0.995 1.049 1.027 1.016 0.997 1.016 0.998 1.031 1.023 0.024
Equipment 0.983 0.991 0.977 1.012 0.995 1.007 0.995 0.988 1.005 0.993 0.995 0.011
Material 0.961 0.976 0.949 0.973 0.987 0.962 0.986 0.987 0.996 0.973 0.975 0.015
Overhead 0.943 0.968 1.085 1.035 0.992 0.962 0.987 1.029 1.058 0.991 1.005 0.045
379
line indicate where the distribution is departing from normal. Figure F.5 shows that the distribution of R-values is close to normal except for the two extreme end points. The standard deviation of the R-values is found by the dashed line construction shown in Figure F.5, starting from the ordinate values of 84 and 16. The mean value of R is found from the ordinate value of 50. The data plot in Figure F.5 shows a mean value of very close to 1.00 and a standard deviation of 0.039, the same values as previously calculated in Figure E.1. Having established that the R-values are very close to being normally distributed, the following observations can be made concerning the companys long-term bidding accuracy using well-known properties of the normal distribution curve. First, about 68 percent of the projects bid lie within plus or minus a standard deviation from the mean. Having established that the mean is essentially 1.0, this means that approximately 68 percent of the projects have a ratio, R, of between 0.961 and 1.039. Another way of saying this is that about two-thirds of the projects have a bidding error no larger than 3.9 percent of the total project cost. In this regard, the error can be either plus or minus. It is also true that about 95 percent of the projects are located within plus or minus two standard deviations from the mean. This says that the maximum bidding error for 95 percent of the jobs bid is no larger than plus or minus 7.8 percent. What constitutes acceptable values of standard deviation is now a matter for management decision.