Beruflich Dokumente
Kultur Dokumente
Corporate Affairs
i
Ref.: INV137
18 May 2006 I / 68
FAS Corporate Affairs Investigation
1. Introduction
Internal Audit was made aware of an anonymous letter containing
allegations relating to the Director of Corporate Affairs in October 2004.
The letter had been passed to the organisation from the Department of
Enteiprise Trade & Employment where the original recipient was the then
. Minister, Ms Harney. Internal Audit commenced its investigation in early
| November 2004. The following report details the findings of Internal
Audit on this matter and in relation to matters, which were
raised/identified during the investigation work.
From the outset of the investigation it was recognised that the allegations
were of a highly sensitive nature and that they were potentially extremely
damaging both to the individual named and to the organisation as a
whole. Internal Audit decided that the investigation would be conducted
by two staff, the Director Corporate Governance / Internal Audit and the
Manager IT Audit & Support. The initial phase of the investigation
involved an internal examination of transactions relating to the two most
recent advertising agencies, Euro RSCG (contracted between November
2001 and November 2003) and AFA O'Meara (contracted from
November 2003 to date).
Arising from its initial meeting with the current advertising agency (AFA
O'Meara), Internal Audit was approached by the Managing Director of
that agency in relation to serious concerns he had regarding the operation
of the FAS contract. In due course, statements were provided by a
number of staff from AFA O'Meara. The content of these statements was
investigated in detail by Internal Audit. 'Interviews were also held with a
number of senior ex-employees of the previous FAS advertising agency
(Euro RSCG) but these individuals were unwilling to make detailed
statements to Internal Audit at the conclusion of discussions. A number of
individuals who had provided services to FAS via the current advertising
agency were interviewed and where necessary, statements were taken.
Internal Audit attempted to interview a sufficient number of people
external to FAS bearing in mind the sensitivity of the allegations.
Arising from the examination of material from 2000 and 2001, which
largely related to the interaction between Helm O'Connor O'Sullivan and
FAS, interviews were held with two former staff members of Corporate
Affairs who now work elsewhere in the organisation. Statements were
also taken from these individuals.
On the basis of the work completed up until that time, Internal Audit met
with the Director of Corporate Affairs in late April 2005 and provided
him with copies of material which had arisen during the investigation that
required either comment or clarification. This material included
statements, correspondence, copy invoices and other schedules. Internal
Audit then met' with the Director of Corporate Affairs in May 2005 to
discuss these issues. The Director of Corporate Affairs brought a
substantial amount of information to this meeting and arising out a
number of discussion points he agreed to follow-up and provide Internal
Audit with some further information, material and clarifications. This
After seeking legal advice, Internal Audit decided to review the FAS e-
mail correspondence to and from the Director of Corporate Affairs for the
calendar year end of 2002, 2003 and 2004. Internal Audit requested that
the Director of Information Technology provide these files to Internal
Audit. These files were reviewed by Internal Audit exclusively in regard
to areas where there were differences between the views expressed by the
Director of Corporate Affairs and, either views expressed in statements
made to Internal Audit by individuals or material available to Internal ^
Audit.
The investigative and audit work covered by this report, and the bulk of
the drafting of the report and its main findings, was carried out over the
period November 2004 to December 2005 by Joe Roe, Manager IT Audit
and Support, and Tony Killeen, Director Corporate Governance / Internal
Audit.
Internal Audit found that there was no evidence to support the allegation
made that Greg Craig received money from j j j g ^ g g g g g g ^ of
Kingram Studios.
Internal Audit found no evidence that fraud was being conducted via the
current advertising agency. ^ '\L/0 '
* In the case of the Science Challenge review in late 2004 OSK, while itself
tendering for this project, provided*******-whowasmanagingthe
tender - with the names of two other companies to who tender documents
should be sent. The contract was subsequently awarded to OSK. One of
these two companies suggested to ****** had also been
unsuccessful in a separate tender process for the evaluation of the
temporary AFA O'Meara contract. This latter tender process was handled
via FAS Procurement and again the successful company was OSK.
The contract for the budget management of FAS Opportunities 2005 was
also awarded, via AFA O'Meara, to OSK. This process again featured a
company that appeared as an unsuccessful applicant for a separate
internal tendering process handled by FAS Procurement. This company
had no previous track record of working with FAS'.
i
When interviewed by Internal Audit ***** stated that OSK had
been awarded the contract for the previous year's Opportunity event, that
in his view that they had done a good job and would be awarded the work
again for 2005 as long as their price was reasonable. He stated that he
therefore contacted ********************************************
OSK and one other group to submit tenders.
OSK submitted tenders and OSK was subsequently
selected. ***** accepted that there were other accountancy firm with
the expertise to manage the budget for the Opportunities event but that
they were not asked to tender.
FAS Opportunities
The FAS Opportunities event represents by far the single biggest piece of
expenditure for Corporate Affairs in any given year. For Opportunities
2005 the expenditure budget for the event was close to €2 million. In the
context of the Opportunities event the investigation concentrated on a
discrete number of issues that had either been raised in the course of
statements or which came to the attention of Internal Audit as a result of
the review of Corporate Affair's transactions.
In the view of Internal Audit, the over-riding reason for the award of the
contract for the exhibition build to just one company, Display Contracts,
for every year since 1995 was on the basis of familiarity. ^—
Deirdre Lynam was awarded the contract for exhibition sales at the
Opportunities 2002 event via the then advertising agency Euro RSCG.
The total cost to FAS of this service was approximately €250,000. This
fee appeared to be very high when compared to those awarded for the
sales contracts for Opportunities in previous and subsequent years. It was
The tender process handled by FAS Procurement for the sales contract at
Opportunities 2003 was bypassed by Greg Craig in the awarding of the
contract to an individual who had not been one of the parties that
submitted a tender. E-mail correspondence reviewed by Internal Audit
indicated that the Director of Corporate Affairs had been in
communication with this individual both before and after the tendering
process,
Jobs Ireland
Jobs Ireland was a FAS campaign that had at its centre a number of
recruitment fairs run in places such as North America, Europe and South
Africa. The overseas fairs commenced in approximately April 2000 and
the last fair occurred in approximately April 2001. At some stage during
the latter part of 2000, Corporate Affairs took the decision that a separate
website specifically for Jobs Ireland would be developed.
The Jobs Ireland website when developed did not appear to address the
shortcomings of the Job Bank as perceived by Greg Craig insofar as \
many clients details were not actually entered onto the website online but \
rather recorded on paper at the job fairs and then keyed onto the system at j
a later stage (in Ireland) and at an additional cost to FAS. The Jobs
Ireland website was not integrated with the existing systems and services-^
available to FAS Employment Services, neither from a client nor from a
staff viewpoint. After the demise of the Jobs Ireland campaign the /
vacancies and client details were never integrated into the mainstream /
FAS systems and any residual value of the investment was lost.
The contract with Ultimate Communications for the Jobs Ireland website
was more likely than not based on a verbal agreement for 36 months, the
details of which Greg Craig was probably aware of from the outset. The
agreement was unlikely to have commenced without his approval.
FAS Procurement handled the tendering process for the Jobs Ireland
programme and website in January 2001. This tendering process ignored
the fact that there was a de facto 36-month contract in place from
September 2000 for the website. This tender process may have been an
attempt by Corporate Affairs to retrospectively justify the role of
Ultimate Communications in regard to the Jobs Ireland website.
Secondly, allied to the requirement for a media audit there is a need for
FAS to develop a medium term (3-4 years) communications and publicity
strategy in a similar way that a multi-annual strategy was produced for
ICT within the organisation. The strategy should address the issues of key
communications objectives (e.g. corporate/identity advertising;
promotion of individual programmes; discharging FAS' broader public
information responsibilities) and how these relate to overall FAS strategy;
key messages and their target groups; preferred channels for each type of
message/target group; indicative budgets for spend by channel/campaign;
and metrics for impact
FAS must therefore identify the key services where the advertising
agency or agencies provide expertise and capabilities that FAS lacks, e.g.
concepts, design work, media planning and monitoring, TV, radio,
outdoor advertising, etc. These key services, once specified, must be
contracted for with the agency or agencies and provided at an agreed fee
with the necessary controls put in place.
All other services i.e. those not handled by the agency or agencies must
be handled via the Procurement function directly. With the separation of
media and PR handling from advertising (as recommended at 3.3.3
below), the Procurement function must have a much greater involvement
in the acquisition of advertising services and products in the future.
The current Corporate Affairs structure is such that it handles two distinct
tasks. On the one hand it handles media and public relations for FAS. On
the other hand it is responsible for advertising and the procurement of
related services and products. The findings of the report point towards a
conflict between these roles in the FAS case. It is recommended that
these two functions be separated and that the reporting structure be
amended so that these functions report separately at ADG level.
The evaluation should examine the event in terms of overall value for
money for the organisation. It should also look in detail at the specific
cost centres associated with the event; budget management, event
management, event sales, web design, advertising campaigns, event
location, event build, event staffing and other costs.
It should also consider what role the advertising agency should play in the
event.
The findings in relation to Jobs Ireland and the FAS corporate website
have shown that where Corporate Affairs has been involved in
commissioning web related work of a technical nature this has been less
than successful. It is recommended that in future its role be restricted to
managing the corporate image and that matters that involve web
development, hosting and maintenance are approached on the basis of
relying on the technical expertise of the FAS IT Department.
Technical web related work should not be processed through the FAS
advertising agency as this has added little to the process previously but
incurred significant costs.
c
Joe Roe Tony Killeen Terry Corcoran
Manager IT Audit/Support Director Corporate Director Corporate
- Internal Audit Governance/Internal Audit Governance/Internal
Audit
(to December ] 6 2005) (from December 19 2005)
18 May 2006 21 / 68
4. Detailed Findings
The detailed findings of this report cover the Internal Audit investigation
into the allegations contained in the anonymous letter. The detailed
findings also cover other matters that Internal Audit have examined
arising from various statements made and interviews held with
individuals and also from an examination of Corporate Affairs
transactions and related documents between 2000 and 2005.
8 May 2006 22 / 68
• 6. Mr Craig has appointed ****** as an advertising
consultant being paid €80,000 per annum and that half of that fee is
being paid in cash to Mr Craig.
(* Arks was one of the previous names for the advertising agency which
FAS contracted with as Euro RSCG. O'Connor O'Sullivan became Helm
O'Connor O'Sullivan in the last year of its contract with FAS)
18 May 2006 23 / 68
4.2.2 Mr Craig had arrangement with individuals in Arks RSCG
and O'Connor O'Sullivan.
Mr Craig denied that at any point in time did ****** resign the FAS
account and Internal Audit found no evidence to support this allegation.
18 May 2006 24 / 68
4.2.5 Fraud was being conducted via the current advertising agency
Internal Audit found no evidence that FAS were paying /***** his
salary directly. Nor did Internal Audit find evidence that FAS were
paying AFA O'Meara for ******* services. In addition no evidence
was found to support the allegation that Mr Craig was receiving half
salary.
Internal Audit found that Print & Display had been used exclusively to
print FAS posters for outdoor campaigns for the last number of years.
in his statement to Internal Audit maintained that Greg
In the latter part of 2003 Euro RSCG resigned the advertising contract
with FAS. As there were a number of ongoing media campaigns it was
necessary to appoint an interim advertising agency until a formal process
of appointing a new advertising agency could be completed. The
selection and appointment of this interim agency was handled by the
Director of Corporate Affairs. According to a memo sent to the Director
of Internal Audit in December 2003 by Greg Craig, the interim agency
was selected by contacting 3 agencies that had done some business
previously with FAS by phone, asking them to submit their credentials
and making a selection based on criteria used in previous evaluations of
advertising agencies. As a result of this process a contract was signed
between AFA O'Meara and FAS dated 7 November 2003. This interim
contract between FAS and the advertising agency stayed in place for 12
months until November 2004 when the current contract was signed
between FAS and Aubrey Fogarty Associates Ltd (AFA O'Meara) as a
result of the full tendering process.
8 Mav 2006 26 / 68
said that had played a key role in sorting out problems in
regard to the Job Ireland web site (see Section 4.9 below), Deirdre
Lynam's sales contract for the FAS Opportunities 2002 (see Section 4.6
below) and for renegotiating the Euro RSCG contract terms in mid 2003.
Up until approximately one year before the take over of Euro RSCG and
the end of the contract with FAS, had been an employee of
Euro RSCG.
From that time on (late 2002),
RSCG
on the FAS account. Payments were made by Euro RSCG to
Some staff who had been formerly employed by Euro RSCG stated that
***** may have been employed in this consultancy role at the
behest of Greg Craig and FAS.
********** had been employed within Euro RSCG, working on the FAS
account. However, she had left some time before the FAS contract
ceased. In a statement made to Internal Audit she maintained that she left
Euro RSCG in response to being removed from the FAS account by Greg
Craig but that she was subsequently approached by Greg Craig on a
number of occasions with a view to working as a consultant on various
pieces of FAS work. stated that in October / November
2003 she held discussions with Greg Craig with a view to working for
AFA O'Meara. Greg Craig responded to Internal Audit that while he had
spoken to about the position of *******
AFA O'Meara, he had only done so at the request of ****** who was
then a director with AFA O'Meara. Material from e-mails between Greg
18 May 2006 29 / 68
longer have any dealings with the FAS account. Greg Craig insisted that
where he no longer wished to deal with AFA O'Meara staff that there
were genuine reasons on his part.
Notwithstanding this,
the timing of this accusation appeared unusual, coming as it did
shortly after the signing of the contract with AFA O'Meara and the
comprehensive tendering process during which time the issue was
never raised. Throughout the tender process Greg Craig at all times
spoke of AFA O'Meara in positive terms.
18 May 2006 32 / 68
4.4 Role of within AFA O'Meara.
18 May 2006 33 / 68
4.4.2 Relationship between and Greg Craig
4.4.3 Conclusions
1 8 May 2006 35 / 68
4.5.3 Level of Outdoor media in 2004
This issue was also raised with ****** and he stated that in his view
it was not possible to generalise as to what percentage of total media
spend outdoor media should be.
4.6 OSK and Corporate Affairs
OSK are a firm of accountants and business consultants that have
completed a considerable amount of consultancy type work for FAS over
the last 5 years, the majority of which related to Corporate Affairs. OSK
have been awarded consultancy work by Corporate Affairs in the areas of
Jobs Ireland (twice), Science Challenge, Financial evaluation of
advertisers contracts (twice), Budget management of Opportunities (4
times including the recent award of the 2006 contract), Employers
Conference and the evaluation of internal controls within Corporate
Affairs.
Corporate Affairs have dealt with a number of staff within OSK over the
5 year period but the main contact has been H H I I ^ ^ ^ ^ H H I i H I
with OSK.
OSK have been awarded contracts with FAS via 3 routes; directly with
Corporate Affairs without tenders, through FAS Procurement by means
of a tender and lastly via the advertising agencies. From a review by
Internal Audit covering the period up until early 2005 it seemed that OSK
have been consistently successful when they have been required to tender
competitively for FAS work. This applies equally via FAS Procurement
or via the advertising agencies. There is evidence to suggest that there
18 May 2006 41 / 68
/ may have been a collaborative approach by Corporate Affairs to
I consultancy work handled by OSK. When the matter was raised with
Greg Craig he responded that because Corporate Affairs has not had
adequate internal financial and administrative expertise it has used OSK
as a support to the department's work. This approach had not been
formally approved by the organisation but it was a decision that Greg
Craig stated he took in the absence of resources.
'7 have sorted out the job sir eland proposal and I need to sit down with
you so on ETP so that we can prepare a. proposal".
"this is not what 1 want, I need a 4 page paper not unlike the draft paper
that 1 gave you when we started this".
This material does not suggest that proposals and tenders were developed
and submitted against a particular specification. Nor does it suggest that
this was a competitive tender.
Bearing in mind the size of the consultancy fee, Internal Audit requested
that Corporate Affairs provide the documentation supporting the selection
of OSK as part of this tender evaluation process. In response Greg Craig
said that this and other material relating to the evaluation of tenders
received via Head Office Procurement was no longer available. When
queried on this point, Greg Craig stated that he believed that all tender
18 May 2006 42 / 68
documents received by Corporate Affairs from Procurement were copies
of the originals and that there was no need to keep these after the tender
evaluations were complete as Procurement kept the originals. On that
basis, no material on the selection of OSK for the Employers Conference
was available to Internal Audit.
At the time of this process the Purchasing Policies & Procedures policy
number FAS-02-08 (dated November 2001) stated that Materials Control
(Procurement) had the responsibility for ensuring that
/The Financial Authority Levels that were in place at the time of this
/ contract state that contracts with a value greater than €30,000 must be
I approved by the Board of FAS. The contract for the Employers
I Conference was not brought before the Board of FAS for approval.
! The approval of contracts within the control of the Coiporate Affairs
I section is covered in more detail below.
[/-••In relation to the tenders for this work, there is also some material from e~
\ mails to suggest that the relationship between FAS and OSK was not at
arms length. On 30 September 2002, B M of OSK wrote to Greg
| Craig and said
I " Thanks for meeting me this morning to sort out the details of the two
\ projects. I sent the letter to m as discussed and will post our first
\ invoice to him tomorrow.
\ We are due to meet |HH this week and I will discuss the tendering
\process for the conference project with her then"
18 May 2006 43 / 68
| and m were working for Euro RSCG at this point
in time. This e-mail was unusual on two points. Firstly, FAS Procurement
did not issue the tender specification to OSK until 8 October 2002 and
this e-mail was sent on 30 September and secondly, it is unclear why
OSK should speak to an individual from the agency when the tender was
being handled via FAS Procurement.
18 May 2006 45 / 68
However, AFA O'Meara claimed to have received an invoice from OSK
covering the first instalment of the Science Challenge payment (€15,000)
in early December 2004. This invoice was dated 6 December 2004. This
date is two weeks before the outcome of the tender evaluation process
was communicated to OSK and the other companies. When this matter
was raised by H I H I ^ I H wrote to AFA O'Meara and
claimed the original invoice date should have been January 2005 and not
December 2004.
m m i l also accepted that the initial invoice was received from OSK in
December 2004 and not January 2005.
As outlined above, the majority of work completed by OSK has not been
based on genuinely competitive tendering. One element of competitive
tendering is the question of price. From the tender and contract
information reviewed by Internal Audit it is not obvious as to how
particular figures have been arrived at.
Another aspect of most OSK contracts has been the agreement to pay
between 33% and 50% of the fee immediately after the contract is signed
This represents a very generous approach and would not be typical of
consultancy contracts in the experience of Internal Audit.
18 May 2006 46 / 68
When Internal Audit initially interviewed Greg Craig in November 2004
regarding the letter of allegation, great emphasis was placed by Greg
Craig regarding the potential damage to his reputation if the allegations
contained in the letter were to be circulated, either internally within FAS
but more significantly, externally within the media and advertising
industry. In that context Greg Craig said that he had not discussed the
contents of the letter with any of those named in the letter but that he had
taken legal advice on his position.
I have gone through the clients file — before I go ahead and submit the
file for approval, I just want to check the figures. How much do they
require in total to refinance both properties "
See w m m below. All the stuff she requires is very recent and 1
do not have it. Please scrape together and get it to me "
4.6.8 Conclusion
18 May 2006 48 / 68
but as a separate exercise. The investigation concentrated on a discrete
number of issues that had either been raised in the course of statements or
which came to the attention of Internal Audit as a result of the review of
Corporate Affair's transactions.
The Opportunities event was originally launched in 1995 and has been
run in a number of locations, Jury's Hotel, the R.D.S. and most recently
Croke Park. During that time the single largest expenditure per event has
generally been the cost of building the exhibition stands. The budgeted
cost for the exhibition build for Opportunities 2005 alone was €386,000.
Deirdre Lynam was awarded the contract for exhibition sales at the
Opportunities 2002 via the then advertising agency Euro RSCG. The total
cost to FAS of this service was approximately €250,000. This figure
represents at least twice as much as was paid to those providing the
exhibition sales service at Opportunities events both before and after
2002. According to material supplied by d H I ^ ^ I
|) and from Euro RSCG, the
timing and financial arrangements of this service were controversial.
In her statement maintained that interviews and tender
reviews in regard to various contracts for Opportunities were merely
"going through the motions" as everyone was aware who was going to
get a specific contract for Opportunities. According to Greg Craig this
I I ^ ^ H did not accept that discussions took place between FAS, the
advertising agency and those tendering for contract before tenders were
submitted.
8 May 2006 50 / 68
4.7.3 Donna O'Connor - Sales Contract, Opportunities 2003
The Bravo Group were selected as the Event Managers for Opportunities
2005. This selection process was completed in Corporate Affairs via a
competitive tendering process and those participating from a selection
viewpoint included staff from Corporate Affairs, H H H H (AFA
O'Meara) and a representative from OSK previously selected as
Opportunities Budget Managers.
Five companies tendered for the event management role and the Bravo
Group were selected. One of the selection criteria was obviously the fee
submitted by the companies. The fee submitted by Bravo was €67,475
(including VAT) and this seemed to have been a competitive figure when
compared to others submitted. However, at the end of the Opportunities
event Bravo submitted a claim for additional costs associated with the
event. Staff from Corporate Affairs met with Bravo and agreed to pay
them an extra €34,000 on top of the tendered fee. This brought the gross
charge to FAS for event management at Oppoztunities 2005 up from
€81,645 to €122,784. This option to increase fees was not something that
was built into the contract between Bravo and AFA O'Meara. Nor did it
appear to have been mentioned to other companies tendering as part of
the process. When this matter was raised with Greg Craig he said that
while he was not directly involved in these negotiations himself, he felt
that this approach was not satisfactory.
From the material supplied by AFA O'Meara to Internal Audit, there was
no sales contract signed before the Opportunities event. This was
confirmed by Bravo and Corporate Affairs. The contract that AFA
O'Meara were asked to sign after the event contained an incentive based
plan in addition to a fixed fee. This incentive based plan provided for an
extra payment to Bravo of €200 per stand sold if stand sales exceeded
€180,000, or alternatively an extra €400 per stand sold if total revenue
exceeded €230,000. The gross cost of this incentive based plan to FAS
was €27,442 and the total cost of the sales contract payment to Bravo of
€110,400. This contract was eventually signed after the event by 3
parties, Bravo, AFA O'Meara and FAS (Corporate Affairs). When this
matter was raised with Greg Craig he said that he was unclear as to why a
sales contract was not negotiated and signed prior to the Opportunities
event and that this was an oversight.
18 May 2006 52 / 68
willing to do the work and Bravo was asked to complete a difficult task
which they managed to do well.
4.7.7 Conclusion
18 May 2006 53 / 68
Display Contracts, for every year since 1995 was on the basis of
familiarity.
• In the case of Opportunities 2005 event management, the process
of tendering was undermined by the increases awarded to Bravo
after the completion of the work.
• In addition, Bravo was also awarded the sales contract for
Opportunities 2005. However, the sales contract, which included
incentive payments, was not signed until after the event and the
sales had been completed.
• The gross additional cost to FAS of these transactions (additional
event management fee and sales incentive payments) was in excess
of 667,000.
• In the case of the sales contract for Opportunities 2002, awarded to
Deirdre Lynam, it was not possible to determine who agreed her
fee. This fee appeared to be very high when compared to those
awarded for the sales contracts for Opportunities in previous and
\ subsequent years.
\ • The tender process handled by FAS Procurement for the sales
contract at Opportunities 2003 was bypassed by Greg Craig in the
awarding of the contract. The contract was awarded to an
individual who had not tendered.
When these points were discussed with Greg Craig he said that he felt
that all AFA O'Meara brought in terms of newspaper and magazine
media buying was extra costs and that therefore he accepted that he did
book directly with newspapers, Greg Craig justified the direct approach
on two main grounds. Firstly, the ability to be seen to have a media spend
could potentially influence how FAS was portrayed in the newspaper or
magazine in question. The second point that justified the direct purchase
of advertising was that Greg Craig felt that he was able to obtain
substantial reductions on the standard rate card amounts. He felt that AFA
O'Meara would not be able to match the reductions achieved.
From an analysis of the FAS media spend in 2004 one newspaper was
unusual in that it was not a national paper. The Lucan & Blanchardstown
Gazette is part of the Gazette Group and has Mr Michael McGovern as
one of its directors and principal shareholders. As discussed above in
When this matter was raised with Greg Craig he maintained that the e-
mail did not give an accurate reflection of what was agreed in regard to
the Gazette Group. When asked about why business should be done with
I a local paper when all other advertising was conducted with national
i titles, Greg Craig told Internal Audit that he had been requested to place
; business with this group by the Director General of FAS. At a
subsequent meeting with Internal Audit, the Director General of FAS
denied that he had ever requested or directed Greg Craig to place business
with the Gazette Group.
However, in order to restrict the scope of the audit bearing in mind its
sensitivity, it was decided not to interview staff in the Services to
Business division of FAS who were responsible for allocating this
business, in order to determine why Kingram and OSK were used.
For the remainder of 2004 AMAS invoiced FAS for a number of different
pieces of web-related work none of which was tendered for in a
competitive manner. These elements included
In addition, contact reports with AFA O'Meara also mention some work
completed in regard to Opportunities and Jobs Ireland. The total cost to
FAS of these invoices from AMAS amounted to approximately € 65,000.
However, from an examination of the FAS Corporate website, it appeared
that very little has been achieved for this expenditure. The home page of
the web site has been changed to a new look and feel but many of the
other pages linked from the home page remained unchanged. It appeared
One of the issues that Internal Audit became aware of during the course
of the investigation was a history of internal disputes and conflict
between the FAS Information Technology Department and Corporate
Affairs. The IT Department have responsibility for what might be loosely
called the technical element of the FAS web site and various links to FAS
data, whereas Corporate Affairs have responsibility for the corporate
image as portrayed via the FAS corporate website. The origins of these
disputes between the two FAS groups are dealt with in more detail in
Section 4.9 below dealing with the Jobs Ireland web site development.
FAS has now commenced the process of tendering via the European
Journal for the design, redevelopment and ongoing maintenance of the
corporate website. The previous approach of channelling this type of
work through the advertising agencies who had no expertise in regard to
web development did not make sense other than to avoid complying
directly with general procurement procedures.
4.8.5 Conclusion
18 May 2006 59 / 68
The existing FAS IT systems in the form of the WAITS / Job Bank,
Client Database and other systems already provided the functionality to
be provided by the proposed Jobs Ireland system. The Job Bank system in
particular was the subject of significant FAS investment through the FAS
IT Department. The decision to invest in a separate Jobs Ireland website
created a second corporate website for FAS and led to very significant
associated costs.
When interviewed by Internal Audit, Greg Craig said that he was unable
to rely on the systems supplied by the Information Technology
Department within FAS and that he had been embarrassed by the
unavailability of the corporate website at one high profile overseas event
and had therefore taken the decision, in conjunction with senior
management, to develop a separate Jobs Ireland website. Greg Craig
maintained that the FAS IT Department were openly hostile to Jobs
Ireland and that this was the reason that he never approached them to
tailor the Job Bank system to meet the specific Jobs Ireland requirements.
In addition, Greg Craig said that, in his view, the FAS IT Department did
not have the capability to deliver what he required. Greg Craig
maintained that the Jobs Ireland was an acclaimed success and had a very
high level of foreign registrants.
The Jobs Ireland website, because of the way in which it was developed
externally to the organisation, did not integrate into the other FAS
18 May 2006 60 / 68
systems and databases, particularly those operated by Employment
Services. This meant that the database was not available to clients using
FAS Employment Services offices and FAS staff other than via the
Internet and this represented a significant weakness. It appeared to
Internal Audit that many overseas clients did not actually register on-line
on the Jobs Ireland website but rather that their manually completed
forms were brought back to Ireland and then keyed into the Jobs Ireland
system at an additional cost to FAS. This fact is reflected in the data entry
charges levied by Ultimate Communications (see below 4.9.2).
With the completion of the overseas events in April 2001, the impetus for
the Jobs Ireland website waned. As a result the existence of two corporate
websites was addressed by internal working groups that examined
content, specification and merits of both the Job Bank and the Jobs
Ireland website. Despite a number of meetings on the matter the two
systems were never integrated and the material registered onto the Jobs
Ireland website was never integrated into the main corporate information
systems, it therefore became outdated and the investment was effectively
lost.
Ultimate Events were the event managers for Opportunities 2000 (see
above Section 4.7.6). The following year they were succeeded as event
managers by Ultimate Communications which was incorporated on 21
July 2000. Ultimate Communications was effectively an offspring of
Ultimate Events and both companies shared the same two directors,
Audrey Browne and Niall Gallen, company address, etc. Ultimate
Communications was awarded the contract to manage the Jobs Ireland
Programme on 3 August 2000 (less than 10 working days after it was
incorporated), up until 31 December 2000.
18 May 2006 61 / 68
were the only customers that Ultimate Communications had during this
time. In addition, FAS also paid the cost of Ultimate Communications
finance on a number of occasions.
Part of the solution that Corporate Affairs and Euro RSCG put in place
was to continue the hosting of the Jobs Ireland website in Euro RSCG.
This arrangement continued to cost FAS money right up until the latter
end of 2003 but at a much lower level than was the case with Ultimate
Communications.
From a review of O'Connor O'Sullivan invoices from the year 2000 and
2001 it appeared to Internal Audit that a large percentage of FAS
advertising expenditure was directed towards promoting the Jobs Ireland
website and little evidence of any expenditure on promoting the Job Bank
system.
While the Board of FAS was kept informed to some extent regarding the
overseas Jobs Ireland events, the development of the Jobs Ireland website
and the significant levels of expenditure involved were not put before the
Board of FAS at any stage for approval or consideration.
As in the case of AMAS (Section 4,8.4) the development for the Jobs
Ireland website was channelled through the advertising agency at an
additional cost to FAS of €130,000 in agency fees. In the case of the Jobs
Ireland website, Ultimate Communications did not provide the end
services but rather subcontracted the work of web hosting and other
related work to groups such as Wolfe and Metamedia. Rather than the site
being hosted by FAS it was hosted by Wolfe and others who invoiced
Ultimate Communications who in turn invoiced Helm O'Connor
O'Sullivan or Euro RSCG who finally invoiced FAS.
4.9.5 Conclusions
18 May 2006 64 / 68
should have been possible to meet their web requirements from
internal FAS IT resources.
The Jobs Ireland website when developed did not appear to address
the shortcomings of the Job Bank as perceived by Greg Craig
insofar as many clients details were not actually entered onto the
website online but rather recorded on paper at the job fairs and then
keyed onto the system at a later stage (in Ireland) and at an
additional cost to FAS. The Jobs Ireland website was not integrated
with the existing systems and services available to FAS
Employment Services, neither from a client nor from a staff
viewpoint. After the demise of the Jobs Ireland campaign the
vacancies and client details were never integrated into the
mainstream FAS systems and any residual value of the investment
was lost.
From an analysis of invoices from 2000 to 2003 Internal Audit
estimate that the total cost of developing, maintaining and hosting
the FAS Jobs Ireland website was €1.7 million. The amount of
investment in the Jobs Ireland website was far in excess of what
was warranted and FAS probably paid at least €1 million more than
should have been the case. In addition the organisation spent a
large amount of its advertising budget promoting the Jobs Ireland
website during this time. The Board of FAS were never informed
of the external development of the Job Ireland website and the
costs involved.
Ultimate Communications was awarded the contract to manage for
the Jobs Ireland Programme on 3 August 2000, less than 10
working days after they were incorporated. In total, FAS paid
Ultimate Communications €3.55 million in the first 12 months
after the date of their incorporation for Jobs Ireland events, web
development and Opportunities.
Based on the timing of the contract for the Jobs Ireland programme
it seemed likely that
18 May 2006 65 / 68
• The FAS Procurement tendering process in January 2001 for the
Jobs Ireland programme and website ignored the fact that there was
a de facto 36-month contract in place from September 2000 for the
website. This may have been an attempt to retrospectively justify
the role of Ultimate Communications in regard to the Jobs Ireland
website.
• The circumstances of the overpayment in relation to Ultimate
Communications of €32,000 in mid 2002 were very difficult to
understand. Considering the level of interest in this settlement
within Corporate Affairs, the large volume of correspondence, the
threat of legal action, the fact that an original single invoice was
returned from FAS to Euro RSCG with a request that it be split into
5 separate invoices and the number of hands that all this passed
through, it is hard to understand how the error occurred and was
approved for payment by Greg Craig.
\ • The process of using advertising agencies as a medium to develop
\ and host websites with third parties makes little sense from a value
\ for money viewpoint. This was never part of what the core
functionality of an advertising agency was supposed to be. The
view of Internal Audit is that this approach was taken by Coiporate
Affairs so that the cover of agency contracts could be used without
having to formally go through a procurement process.
18 May 2006 66 / 68
*****. While Greg acknowledged that he had requested
meet him on that day and that they had met, he denied the allegation
regarding the material requested by Internal Audit.
Can you text me your home address so I can get the tickets delivered to
you. "
When this was put to Greg Craig in June 2005 he admitted that he had
indeed requested tickets but stated that he had never personally benefited
from them. He stated that at all times he had himself been requested to
supply tickets for events by other parties within FAS and generally at a
level more senior to him.
4.10.3 Conclusions