Subsea Field Development - Challenges and Solutions
for Tie-In and Connection Systems Session: Focus on Technology Subsea Australasia Conference 19-21 February 2014 Zahid Hasan AOG 2014 Outline Subsea Field Development- Introduction, Top Down Approach and Options Tie-In and Connections Systems- Introduction and Options Comparison and Selection of Tie-In and Connection Systems Field Development with alternate Tie-In and Connection systems Available Connection Systems (New Generation ) 1 AOG 2014 Subsea Field Development Custom configuration of Subsea equipment providing a variety of system designs Develop field architecture Well design and placement Host facilities and specification Configuration and routing of flowlines, umbilicals and risers Installation Options Reduce risk with credible and proven solutions 2 AOG 2014 3 Reservoir & Field System Solution Sub-system solution Available Products The proposed system solution will be based on Technical decision factors, Location and Geographical condition Regulatory and political factors Operators preference Contractors preference Individual suppliers preferences Available products and competence Subsea Field Development- Top Down Approach AOG 2014 Subsea Field Development Top Down Approach Level Main Factors Tie-in & Connection topics Reservoir, Field, location + Government and Company requirements (= Design Basis) Reservoir parameters (pressure, temperatures, gas/oil, size, water depth, well locations etc) Process requirements Geographic location/Environmental conditions Availability of vessels in region Connection parts qualified for parameters Connection system meets installation and operational requirements Can be used/maintained from small vessels in remote locations System Solution Flow assurance philosophy Hydraulic and injection distribution philosophy Pigging/commissioning requirements Retrieval of modules without pulling jumpers/spools Injection volumes, thermal insulation Multibore vs Monobore System Subsea Parking of jumpers/spools for module Pre-installation and/or batch setting of jumpers/spools. Sub-system solution Horizontal and/or vertical System Simple, complex tooling or hydraulic connectors Guiding, installation requirements External forces (installation and operation) Rigid- and/or flexible lines and umbilicals Qualified and preferably field proven solutions Injection and/or hydraulic distribution through connectors Swivel functionality to handle torsion in flexible lines Available Products Sizes and capabilities (pressure, temp, capacity, insulation etc) Qualification requirements, track record Installation vessel, methods and procedures Commissioning requirements Contingency operations Qualified and preferably field proven System Handling, installation, guiding Connectors, seals, caps, tools Procedures 4 AOG 2014 5 Typical Subsea Field Developments Options Satellite Tieback Cluster Manifold Cluster Manifold with Satellite Tieback Mixture of Manifold Cluster and remote/inline tiebacks Daisy Chained Tieback Integrated Template/Manifold AOG 2014 Outline 6 Subsea Field Development- Introduction, Top Down Approach and Options Tie-In and Connections Systems- Introduction and Options Comparison and Selection of Tie-In and Connection Systems Field Development with alternate Tie-In and Connection systems Available Connection Systems (New Generation ) AOG 2014 7 What is a Tie-In and Connection System In reference to Oil and Gas Industry the connection system: Joins two pieces of equipment (e.g. tree to wellhead, jumper to hub, etc.) Prevent fluid leakage to the environment Establish and maintain a seal on a gasket Withstand external loading (internal pressure, bending, tension, torsion) AOG 2014 Tie-in and Connection System Options Orientation Application Connector type/actuation Horizontal Pipe sizes Non insulated Insulated Mono-bore Multi-bore Mechanical w/large tool Mechanical w/small tools Hydraulic w/contingency Vertical Pipe sizes Non insulated Insulated Mono-bore Multi-bore Mechanical w/large tool Mechanical w/small tools Hydraulic w/contingency Small-bore Injection lines ROV installation, FLOT + Torque tool or hydraulic Flying leads Hydraulic distribution and/or injection lines El/FO jumpers ROV installation, FLOT + Torque tool Module connectors Sizes Non insulated Insulated Mono-bore Multi-bore Mechanical small tool Hydraulic w/contingency 8 AOG 2014 Outline 9 Subsea Field Development- Introduction, Top Down Approach and Options Tie-In and Connections Systems- Introduction and Options Comparison and Selection of Tie-In and Connection Systems Field Development with alternate Tie-In and Connection systems Available Connection Systems (New Generation ) AOG 2014 Selection of Connection System Challenges: Design Basis and Customer Requirements Many needs in one field Intervention Strategy Reuse of existing tooling Cost evaluation criteria Interfaces Internal interfaces in Subsea Production System Interfaces to pipeline/flowline External forces Physical interfaces Handling and installation Installation procedures Knowledge and experience of involved personnel Personal and cultural preferences based on experience Reservoir, Design Basis, Field layout System, Flow assurance, Hydraulic and injection fluid distribution Pipe sizes Horizontal Multi-bore or Flying Leads+ small-bore Insulated connectors Not insulated Vertical Multi-bore or Flying Leads+ small-bore Insulated connectors Not insulated Module 10 AOG 2014 Vertical vs Horizontal Tie-In Systems Selection Regional preferences and customer preferences Total installed cost Field architecture (on-template wells, off-template well clusters and wide area distribution wells) Ease of fabrication (onshore/ offshore) Lifting capacity of the installation vessel Ease of performing jumper installation Ease of Tree and / or Manifold retrieval Regional requirement for overtrawlability and hence minimum height protection structures (i.e. North Sea applications). Avoidance of trapped water and potential hydrate formation Multi-phase and Wet Gas meters location (Need to be in a vertical leg for proper performance) 11 AOG 2014 Rigid Vs Flexible Jumpers Selection of Rigid or Flexible jumpers is dependant on Field Layout Design Requirement (Pressure, Temperature etc.) Material Philosophy Insulation Requirement Fluid in bore Total Installed Cost 12 AOG 2014 Outline 13 Subsea Field Development- Introduction, Top Down Approach and Options Tie-In and Connections Systems- Introduction and Options Comparison and Selection of Tie-In and Connection Systems Field Development with alternate Tie-In and Connection systems Available Connection Systems (New Generation ) Typical Production DC Layout Vertical Mono-bore connections SDU SRM UTH EFL and HFL jumpers (elec, hyd, chem) FCM EHXT SCM M spools and vertical connections 10 PLET Jumpers (Vecon Connectors) MCM Manifold 10 Flowline (PIP) 10 Flowline (PIP) UTH Methanol 2 jumpers KC4-3 vertical connections Umbilical (elec+fibre+hyd+chem+ 5x1.5 for methanol) 14 Typical Production Drill Centre with vertical connections 15 AOG 2014 Drill Center with Vertical Rigid Spools 16 Typical Production DC Layout with Horizontal multi-bore well jumpers/connectors No SDU (Distribution in manifold) All horizontal connections Multi-bore connections (XT to manifold) Umbilical (elec+f ibre+hyd+chem+ 5 x1.5 f or methanol) SRM FCM EHXT SCM XT Jumpers 6 prod + 2 methanol + elec + hyd UCON multi bore horizontal 10 PLET Jumpers (UCON mono bore horizontal) MCM Manifold 10 Flowline (PIP) 10 Flowline (PIP) SCM MCM Manifold Mono-bore DC Multi-bore DC 17 AOG 2014 Typical Production Drill Centre with horizontal connections 18 Drill Center with Horizontal Rigid Spools 19 Drill Centre with Vertical Rigid Spools 20 As Built Drill Centre 21 AOG 2014 Outline 22 Subsea Field Development- Introduction, Top Down Approach and Options Tie-In and Connections Systems- Introduction and Options Comparison and Selection of Tie-In and Connection Systems Field Development with alternate Tie-In and Connection systems Available Connection Systems (New Generation ) Different Connection Systems Historical - Integral Hydraulic and Mechanical / CAT Tie-in Systems UCON ROV-Tool Mechanical Tie-in System TORUS IV ROVCON STACON TORUS III MA! - CAT " CAT-#ite UTIS Used Large tools Longer installation time UCON-H UCON-V Collet or Clamp Clamp Collet 23 AOG 2014 Standard Connection Systems Connection Systems Horizontal UCON-H UCON-H-12 UCON-H-12 INS UCON-H-18 UCON-H-18 INS UCON-H-22 Stabcon MK2 Rovcon MK2 Vertical UCON-V-KC UCON-V--KL KLV-8 (MAX) KLV-10 KLV-14 KLV-16 Torus-III Smallbore Module Connectors Manifold System Well Completion Systems (XTs) Well Access Systems (Riser) Process UCON Family UCON-H, Horizontal UCON-V, Vertical Based on the same family of standards Collet Connectors (KC) Clamp Connectors (KL) The core collet and clamp connectors use the same mono-bore and multi-bore hubs/connector bodies and Seals The design and qualification philosophy is that qualified seals can be used in all connectors. 24 AOG 2014 KC/KL connector family KC4-10 KC4-12 KC4-14 KC4-27 KL4-10 KL4-12 KL4-18 KL4-27 KC4-34 KC4-18 KL4-16 Max pipe OD (Inches) KC4-16 KL4-14 KC4-22 12.75 14 16 18 20 24 30 36 25 AOG 2014 UCON-H Product Family 4 versions available today UCON-H-22 is available Q1 2014 UCON-H-22 UCON-H-18 UCON-H-12, insulated UCON-H-12 UCON-H-18, insulated Basic ROV manipulator held tooling Mono-bore and Multi-bore Integral Insulated or non-insulated Horizontal or Vertical Guideline or guideline-less operations No interface with seabed during installation and connection 26 AOG 2014 UCON-H Multibore Connections Umbilical Termination Head (UTH) Insulated Multibore Welljumper Termination Head (6 + 2x1.5 + 8 HL) 27 AOG 2014 UCON-H Connection System Multi-bore KC4 Connector 6 + 2x1.5 + Hyd + chem + EL Stroke-in and connect Rigid Spools (mono/multi bore) Flexible lines / umbilicals Pig Launchers /Receivers Pig Loops 28 AOG 2014 Connection System Installation UCON-H System ROVCON System 29 UCON-H Video AOG 2014 Installation/Parking of Connection System without Production Equipment Tubing Head (U Loop) Flowbase System (Flexible Flowloop) Tubing Head (Without U Loop) for UCON System Simpler Parking/pre-installation of well jumper Direct interface with Tree hub 30 Installation of UCON System without Production Equipment 31 Conclusions Tie-in and Connection system selection is fundamental to an economic field development Vertical & or Horizontal tie-ins with rigid and or flexible pipe may be selected feature common connectors and hubs UCON Connection system reduces total installed cost Simplified ROV deployed Tooling reduces installation time Integral Thermal Insulation available vs. adding dog houses improves thermal performance and reduces cost Subsea parking & pre-installation of jumpers without Subsea production equipment is enabled Reduced personnel onboard vessels and simplified maintenance Wide Pipe range available 32 Thank You