Activity

ID
Activity Name Original
Duration
Remaining
Duration
BL1 Early
Start
Actual Start Total
Float
Free
Float
C120 Procure Forms 7 0 03-Mar-12 03-Mar-12
C160 Bored Pile F... 5 2 06-Mar-12 06-Mar-12 0 0
C170 Slabs on Gr... 6 6 17-Mar-12 1 0
C180 Columns 2 2 23-Mar-12 1 0
C190 Roof Slab 12 12 25-Mar-12 1 1
C200 Finishes 15 15 23-Mar-12 0 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
Day
Procure Forms
Bored Pile Fdns
Slabs on Grade
Columns
Roof Slab
Finishes
ID Standard Activity Status 21-Mar-12 15:26
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Charbel El Helou
P6 , 2.) b.)
Page 1 of 1
Date Revision Checked Approved
21-Mar-12 00... P6 , 2.) b.) Charbel El He...
Activity ID Activity Name Original
Duration
Remaining
Duration
BL1 Early
Start
Actual Start Total
Float
Free
Float
For man For man For man For man For man For man For man For man
Concret Concrete Sub Concrete Sub Concrete Sub Concrete Sub Concrete Sub Concrete Sub Concrete Sub
Hoist Hoist Hoist Hoist Hoist Hoist Hoist Hoist
C190 Roof Slab 12 12 25-Mar-12 1 1
No Eqpt No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment
C180 Columns 2 2 23-Mar-12 1 0
C200 Finishes 15 15 23-Mar-12 0 0
Excavat Excavation Sub Excavation Sub Excavation Sub Excavation Sub Excavation Sub Excavation Sub Excavation Sub
Backhoe Backhoe Backhoe Backhoe Backhoe Backhoe Backhoe Backhoe
C140 Site Work 8 8 19-Mar-12 0 0
Superi nt e Superi nt endant Superi nt endant Superi nt endant Superi nt endant Superi nt endant Superi nt endant Superi nt endant
Concret Concrete Sub Concrete Sub Concrete Sub Concrete Sub Concrete Sub Concrete Sub Concrete Sub
Backhoe Backhoe Backhoe Backhoe Backhoe Backhoe Backhoe Backhoe
C150 Pad Footings 8 0 08-Mar-12 08-Mar-12
No Eqpt No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment
C120 Procure Forms 7 0 03-Mar-12 03-Mar-12
C160 Bored Pile F... 5 2 06-Mar-12 06-Mar-12 0 0
C170 Slabs on Gr... 6 6 17-Mar-12 1 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
7
Day
06-Apr-12, Forman
06-Apr-12, Concrete Sub
05-Apr-12, Hoist
Roof Slab
06-Apr-12, No Eqpt - Equipment
Columns
Finishes
26-Mar-12, Excavation Sub
26-Mar-12, Backhoe
Site Work
22-Mar-12, Superintendant
22-Mar-12, Concrete Sub
13-Mar-12 A, Backhoe
Pad Footings
22-Mar-12, No Eqpt - Equipment
Procure Forms
Bored Pile Fdns
Slabs on Grade
ID Standard Activity Status 21-Mar-12 15:44
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Charbel El Helou
P6 , 2.) C.)
Page 1 of 1
Date Revision Checked Approved
21-Mar-12 00:... P6 , 2.) C.) Charbel El He...
Activity
ID
Activity Name Original
Duration
Remaining
Duration
BL1 Early
Start
Actual Start Total
Float
Free
Float
C120 Procure Forms 7 0 03-Mar-12 03-Mar-12
C160 Bored Pile F... 5 2 06-Mar-12 06-Mar-12 0 0
C170 Slabs on Gr... 6 6 17-Mar-12 1 0
C180 Columns 2 2 23-Mar-12 1 0
C190 Roof Slab 12 12 25-Mar-12 1 1
C200 Finishes 15 15 23-Mar-12 0 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
Day
Procure Forms
Bored Pile Fdns
Slabs on Grade
Columns
Roof Slab
Finishes
ID Standard Activity Status 21-Mar-12 15:26
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Charbel El Helou
P6 , 2.) b.)
Page 1 of 1
Date Revision Checked Approved
21-Mar-12 00... P6 , 2.) b.) Charbel El He...
Activity ID Activity Name Original
Duration
Remaining
Duration
BL1 Early
Start
Actual Start Total
Float
Free
Float
For man For man For man For man For man For man For man For man
Concret Concrete Sub Concrete Sub Concrete Sub Concrete Sub Concrete Sub Concrete Sub Concrete Sub
Hoist Hoist Hoist Hoist Hoist Hoist Hoist Hoist
C190 Roof Slab 12 12 25-Mar-12 1 1
No Eqpt No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment
C180 Columns 2 2 23-Mar-12 1 0
C200 Finishes 15 15 23-Mar-12 0 0
Excavat Excavation Sub Excavation Sub Excavation Sub Excavation Sub Excavation Sub Excavation Sub Excavation Sub
Backhoe Backhoe Backhoe Backhoe Backhoe Backhoe Backhoe Backhoe
C140 Site Work 8 8 19-Mar-12 0 0
Superi nt e Superi nt endant Superi nt endant Superi nt endant Superi nt endant Superi nt endant Superi nt endant Superi nt endant
Concret Concrete Sub Concrete Sub Concrete Sub Concrete Sub Concrete Sub Concrete Sub Concrete Sub
Backhoe Backhoe Backhoe Backhoe Backhoe Backhoe Backhoe Backhoe
C150 Pad Footings 8 0 08-Mar-12 08-Mar-12
No Eqpt No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment No Eqpt - Equipment
C120 Procure Forms 7 0 03-Mar-12 03-Mar-12
C160 Bored Pile F... 5 2 06-Mar-12 06-Mar-12 0 0
C170 Slabs on Gr... 6 6 17-Mar-12 1 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
7
Day
06-Apr-12, Forman
06-Apr-12, Concrete Sub
05-Apr-12, Hoist
Roof Slab
06-Apr-12, No Eqpt - Equipment
Columns
Finishes
26-Mar-12, Excavation Sub
26-Mar-12, Backhoe
Site Work
22-Mar-12, Superintendant
22-Mar-12, Concrete Sub
13-Mar-12 A, Backhoe
Pad Footings
22-Mar-12, No Eqpt - Equipment
Procure Forms
Bored Pile Fdns
Slabs on Grade
ID Standard Activity Status 21-Mar-12 15:44
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Charbel El Helou
P6 , 2.) C.)
Page 1 of 1
Date Revision Checked Approved
21-Mar-12 00:... P6 , 2.) C.) Charbel El He...
Activity
ID
Activity Name Original
Duration
Remaining
Duration
BL1 Early
Start
Actual Start Total
Float
Free
Float
C120 Procure Forms 7 0 03-Mar-12 03-Mar-12
C160 Bored Pile F... 5 2 06-Mar-12 06-Mar-12 0 0
C170 Slabs on Gr... 6 6 17-Mar-12 1 0
C180 Columns 2 2 23-Mar-12 1 0
C190 Roof Slab 12 12 25-Mar-12 1 1
C200 Finishes 15 15 23-Mar-12 0 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
Day
Procure Forms
Bored Pile Fdns
Slabs on Grade
Columns
Roof Slab
Finishes
ID Standard Activity Status 21-Mar-12 15:26
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Charbel El Helou
P6 , 2.) b.)
Page 1 of 1
Date Revision Checked Approved
21-Mar-12 00... P6 , 2.) b.) Charbel El He...