Questions

1. You set a rolling planning time fence (firming type = 1) for a material in an SAP ECC system. When an
unforeseen production failure occurs, firmed planned orders might fall into the past.
How can these firmed planned orders be deleted automatically?
Please choose the correct answer.
a) O Activate demand adjustment in Customizing.
b) O Use an MRP type in which the roll-forward.
c) O Use reorganizacin.
d) O Use an MRP type in which the roll-backwards mechanism is activated.
2. You are using MRP controllers in an SAP ECC system.
Which of the following statements concerning MRP controllers are correct?
Note: There are two (2) correct answers to this question.
a) O The MRP controller is maintained in production versions.
b) O In multilevel single-item planning, materials are selected using the MRP
controller.
c) O An employee responsible for the planning of materials can be assigned to
multiple MRP controllers.
d) O The MRP controller is a central selection criterion for evaluating
material requirements planning.
3. Which SAP NetWeaver component realizes cross-system application processes?
Please choose the correct answer.
a) O SAP Business Warehouse (SAP BW)
b) O SAP Enterprise Portal (SAP EP)
c) O SAP Master Data Management (SAP MDM)
d) O SAP Exchange Infrastructure (SAP XI) / SAP Process Integration (SAP
PI)
4. How can you convert planned orders into production orders in an SAP ECC system?
Note: There are three (3) correct answers to this question.
a) O Automatically, in the planning run (MRP)
b) O Set the conversion indicator in Customizing for the planned order.
c) O Use mass processing.
d) O Use the order progress report.
e) O Use background processing.
5. Where can you maintain available capacities in an SAP ECC system?
Note: There are two (2) correct answers to this question.

a) O Routing
b) O Production supply area
c) O Pooled capacity
d) O Work center
6. You want to use production/resource tools in your manufacturing process.
Which production type do you use?
Please choose the correct answer.
a) O Repetitive manufacturing
b) O Production order
c) O Process order
d) O KANBAN
7. When scheduling a routing in the SAP ECC system, which of the following time elements is a interoperation
time?
Please choose the correct answer.

a) O Safety time
b) O Float before production
c) O Processing time
d) O Setup time
8. Which statements about the reorganization of planned independent requirements in SAP ECC are true?
Note: There are two (2) correct answers to this question.
a) O The reorganization only deletes planned independent requirements that have
no fixed planned orders assigned to them.
b) O The reorganization only affects planned independent requirements that
lie on a time axis on the left side of a specified key date.
c) O The reorganization can be defined using a plant-specific reorganization
interval.
d) O The reorganization is a form of demand adjustment in which non-consumed
planned independent requirements are set to inactive for the planning, but not
deleted.
9. Which of the following organizational units can be used for planning and manufacturing in an SAP ECC
system?
Note: There are three (3) correct answers to this question.

a) O Distribution channel
b) O MRP area
c) O Sales area
d) O Sales area
e) O Storage location
10. Which BOM selection possibilities are available for opening a production order?
Note: There are two (2) correct answers to this question.
a) O Selection by BOM number in the material master of the material to be
produced
b) O Selection using a production version
c) O Manual selection
d) O Automatic selection controlled by Customizing settings
e) O Selection using the production scheduling profile
Solutions
1 a) Incorrect 2 a) Incorrect 3 a) Incorrect 4 a) Incorrect 5 a) Incorrect
1 b) Correct 2 b) Incorrect 3 b) Incorrect 4 b) Incorrect 5 b) Incorrect
1 c) Incorrect 2 c) Correct 3 c) Incorrect 4 c) Correct 5 c) Correct
1 d) Incorrect 2 d) Correct 3 d) Correct 4 d) Correct 5 d) Correct
4 e) Correct
6 a) Incorrect 7 a) Incorrect 8 a) Incorrect 9 a) Incorrect 10 a) Incorrect
6 b) Correct 7 b) Correct 8 b) Correct 9 b) Correct 10 b) Correct
6 c) Incorrect 7 c) Incorrect 8 c) Correct 9 c) Incorrect 10 c) Incorrect
6 d) Incorrect 7 d) Incorrect 8 d) Incorrect 9 d) Correct 10 d) Correct