Sie sind auf Seite 1von 4

SAP EDUCATION

SAMPLE QUESTIONS: C_TSCM42_65


SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP5
Disclaimer: These sample questions are for self-evaluation purposes only and do not appear on the actual certification
exams. Answering the sample questions correctly is no guarantee that you will pass the certification exam. The certification
exam covers a much broader spectrum of topics, so do make sure you have familiarized yourself with all topics listed in the
exam competency areas before taking the certification exam.
Questions


1. You set a rolling planning time fence (firming type = 1) for a material in an SAP ECC system. When an
unforeseen production failure occurs, firmed planned orders might fall into the past.

How can these firmed planned orders be deleted automatically?

Please choose the correct answer.

a) O
Activate demand adjustment in Customizing.
b) O
Use an MRP type in which the roll-forward.
c) O
Use reorganization.
d) O
Use an MRP type in which the roll-backwards mechanism is
activated.

2. You are using MRP controllers in an SAP ECC system.

Which of the following statements concerning MRP controllers are correct?

Note: There are 2 correct answers to this question.

a) O
The MRP controller is maintained in production versions.
b) O
In multilevel single-item planning, materials are selected
using the MRP controller.
c) O
An employee responsible for the planning of materials can
be assigned to multiple MRP controllers.
d) O
The MRP controller is a central selection criterion for
evaluating material requirements planning.
3.
Which SAP NetWeaver component realizes cross-system application processes?
Please choose the correct answer.
.
a) O
SAP Business Warehouse (SAP BW)
b) O
SAP Enterprise Portal (SAP EP)
c) O
SAP Master Data Management (SAP MDM)
d) O
SAP Exchange Infrastructure (SAP XI) / SAP Process Integration
(SAP PI)

4.
How can you convert planned orders into production orders in an SAP ECC system?

Note: There are 3 correct answers to this question.

a) O
Automatically, in the planning run (MRP)
b) O
Set the conversion indicator in Customizing for the planned
order.
c) O
Use mass processing.
d) O
Use the order progress report.
e) O
Use background processing.






5. Where can you maintain available capacities in an SAP ECC system?

Note: There are 2 correct answers to this question.

a) O
Routing
b) O
Production supply area
c) O
Pooled capacity
d) O
Work center


6.
You want to use production/resource tools in your manufacturing process.

Which production type do you use?
Please choose the correct answer.
a) O
Repetitive manufacturing
b) O
Production order
c) O
Process order
d) O
KANBAN

7.
When scheduling a routing in the SAP ECC system, which of the following time elements is a
interoperation time?
Please choose the correct answer.

a) O
Safety time
b) O
Float before production
c) O
Processing time
d) O
Setup time

8.
Which statements about the reorganization of planned independent requirements in SAP ECC are
true?
Note: There are 2 correct answers to this question
.
a) O
The reorganization only deletes planned independent
requirements that have no fixed planned orders assigned to
them.
b) O
The reorganization only affects planned independent
requirements that lie on a time axis on the left side of a specified
key date.
c) O
The reorganization can be defined using a plant-specific
reorganization interval.
d) O
The reorganization is a form of demand adjustment in which
non-consumed planned independent requirements are set to
inactive for the planning, but not deleted.
9.
Which of the following organizational units can be used for planning and manufacturing in an SAP ECC
system?
Note: There are 3 correct answers to this question.

a) O
Distribution channel
b) O
MRP area
c) O
Sales area
d) O
Sales area
e) O
Storage location


10. Which BOM selection possibilities are available for opening a production order?

Note: There are 2 correct answers to this question.

a) O
Selection by BOM number in the material master of the material
to be produced
b) O
Selection using a production version
c) O
Manual selection
d) O
Automatic selection controlled by Customizing settings
e) O
Selection using the production scheduling profile
Solutions
1 a) Incorrect 2 a) Incorrect 3 a) Incorrect 4 a) Incorrect 5 a) Incorrect
1 b) Correct 2 b) Incorrect 3 b) Incorrect 4 b) Incorrect 5 b) Incorrect
1 c) Incorrect 2 c) Correct 3 c) Incorrect 4 c) Correct 5 c) Correct
1 d) Incorrect 2 d) Correct 3 d) Correct 4 d) Correct 5 d) Correct
4 e) Correct
6 a) Incorrect 7 a) Incorrect 8 a) Incorrect 9 a) Incorrect 10 a) Incorrect
6 b) Correct 7 b) Correct 8 b) Correct 9 b) Correct 10 b) Correct
6 c) Incorrect 7 c) Incorrect 8 c) Correct 9 c) Incorrect 10 c) Incorrect
6 d) Incorrect 7 d) Incorrect 8 d) Incorrect 9 d) Correct 10 d) Correct
9 e) Correct 10 e) Incorrect