Sie sind auf Seite 1von 40

Parmly Billings Library Feasibility Study

May 18, 2009

Parmly Billings Library Primary Contact


• Bill Cochran, Director
Parmly Billings Library
510 N. Broadway
Billings, MT 59101

Gainan’s Floral Primary Contact


• Chuck Gainan
Gainan’s Floral
502 N. 30th Street
Billings, MT 59101

CTA, Inc.
• Keith Rupert, Principal in Charge
• Karl DeCock, Project Manager
• Mike Tuss, Designer

Parmly Billings Library Feasibility Study i


Billings, Montana
Parmly Billings Library Feasibility Study

Table of Contents

Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 1

Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pages 2-5


Narrative
• Parmly Billings Library Program
• Gainan’s Floral Program

Building Assessment . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 6

Preliminary Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pages 7-19


Narrative
• Option 1 – Proposed Plan Information
• Option 2 – Proposed Plan Information

Cost Estimate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pages 20-28


Narrative
• Cost Estimate

Preliminary Project Schedule . . . . . . . . . . . . . . . . . . . . . . Pages 29-30


Narrative
• Preliminary Project Schedule

Appendix
• Progress Drawings – Option 1 & Option 2
• Vision Notes from Parmly Billing Library Board Meeting 3/12/09

Parmly Billings Library Feasibility Study ii


Billings, Montana
Parmly Billings Library Feasibility Study

Executive Summary:
At the request of Bill Cochran of Billings Parmly Library, CTA performed a feasibility
study to relocate the Parmly Billings Library into the existing downtown Gainan’s
building. The extents of the feasibility study included creating a new library program,
building assessment of the existing Gainan’s building, preliminary plans, 3D massing
model, and cost estimate. Because Gainan’s wishes to maintain a downtown presence on
the same site, CTA also included a program and cost estimate of their needs in the study.

This feasibility study is intended to help determine if relocating the existing Parmly
Billings Library to the existing downtown Gainan’s building is both feasible and
beneficial for all parties involved. This study will provide useful information to both
parties to help facilitate discussions for this potential project.

*Vision notes from Parmly Billings Library Board Meeting held March 12, 2009 are
located in the Appendix at the end of this study.

Parmly Billings Library Feasibility Study 1


Billings, Montana
Program:
Library -
Programming meetings with the Library included reviewing previous studies conducted
for the Library and meeting with key staff members to discuss specific needs. Possible
future Library branches were also discussed and taken into account in the final program.
Once finalized, the new Libraries program showed that the size of the existing Gainan’s
building would be inadequate without expansion. The current Gainan’s building has
approximately 33,500 sf of space including the greenhouse located on the South side of
the building. An addition of approximately 27,000 sf would be required to fulfill the
libraries programmatic needs. This addition would be added to the North side of the
existing building and would include expanding the basement, main and second floor.
This new addition would also require redesigning the North end of the site to provide
access and parking.

Gainan’s -
Programming meetings were also held with Gainan’s. Early discussions with Gainan’s
revealed the need to explore two separate options of where the Gainan’s retail space
would be located. The first option provides retail space for Gainan’s within the extents of
the Library. The second option provides a separate building to the North of the Library.
Gainan’s program needs for either option remained the same along with their need to
have a distinct identity to set it apart from the Library.

Parmly Billings Library Feasibility Study 2


Billings, Montana
PARMLY BILLINGS LIBRARY
PROPOSED PROGRAM
BILLINGS, MONTANA

Program Comparison
Proposed Potential
Allocated Spaces Existing Proposed Proposed Notes w/ Branches Location
Public Areas
Public Entrance/Lobby 515 sf 600 sf 600 sf Main Floor

Circulation Desk Area -


744 sf 600 sf 600 sf Main Floor

Access Services Workroom -


1,656 sf 1,930 sf 1,930 sf Basement

Youth Services -
4,959 sf 6,565 sf Potential Decrease of 565sf for 6,000 sf Main Floor
Branch Libraries

Listening/Viewing Area -- sf 240 sf 6 Stations - 40sf each (Carol 240 sf Main Floor
Layout)

Young Adult -
1,152 sf 1,500 sf Includes Computer Section & 1,500 sf 2nd Floor
Diner Seating

Adult Fiction Collection -


2,939 sf 3,000 sf Potential Decrease of 1000sf for 2,000 sf Basement
Branch Libraries

A/V Collection Area (Non-Print) -


1,746 sf 1,500 sf Potential Decrease of 400sf for 1,100 sf Main Floor
Branch Libraries

Public Access Catalog Computers -


358 sf 300 sf 15 Stations (2/3 Standup) 300 sf Dispersed
Throughout

Genealogy -
288 sf 300 sf Adjacent to Montana Rm. 300 sf 2nd Floor

Montana Room -
2,155 sf 1,500 sf Adjacent to Genealogy 1,500 sf 2nd Floor

Magazine/Newspaper Area -
415 sf 250 sf 250 sf Anywhere

Non-Fiction Collection (Includes Biography) -


4,020 sf 5,800 sf Potential Decrease of 3,300sf for 2,500 sf 2nd Floor
Branch Libraries

General Public Seating -


4,065 sf 9,000 sf Potential Decrease of 3,000sf for 6,000 sf Dispersed
Branch Libraries Throughout

Reference Collection -
654 sf 850 sf 850 sf Basement

Reference Services -- sf 150 sf 150 sf 2nd Floor

Computer Lab (25 Computers) -


1,224 sf 1,000 sf 1,000 sf 2nd Floor

Computer Teaching Space (12 Computers) -- sf 500 sf 500 sf 2nd Floor

New Release Area -


716 sf 800 sf Potential Decrease of 300sf for 500 sf Main Floor
Branch Libraries

Large Type Area -


812 sf 800 sf 800 sf Main Floor

General Display Area -- sf 200 sf 200 sf Main Floor

Reserve Area -- sf 100 sf 100 sf Main Floor

Study Rooms (3ea @ 150sf) -- sf 450 sf 450 sf Anywhere

Large Meeting Room (100p) -


2,520 sf 1,500 sf Dividable 1,500 sf Main Floor

Conference Room (15-20p) -- sf 500 sf 500 sf Anywhere


-
Total Public Allocated Space 30,938 sf 39,935 sf 31,370 sf

m:\jobs\plibfs09\pre\Programs_03-06-09.xls 5/22/200912:33 PM
PARMLY BILLINGS LIBRARY
PROPOSED PROGRAM
BILLINGS, MONTANA

Proposed Potential
Allocated Spaces Existing Proposed Proposed Notes w/ Branches Location
Non-Public Areas
Mending & Technical Service Area 2,142 sf 1,500 sf 1,500 sf Basement

Computer Service Area 633 sf 700 sf Including Closets for Network 700 sf Basement
Equip.

Custodial Supply/Work & Office Area -


1,488 sf 1,200 sf 1,200 sf Basement

Garage/Loading Dock -
1,290 sf 0 sf 0 sf
Outreach Services - Offices - sf 200 sf 200 sf Basement

Outreach Services - Bookmobile Loading Garage -


1,469 sf 800 sf 800 sf Main Floor

Bike Storage -- sf 200 sf 200 sf Main Floor

Equipment Storage - Above


Included 350 sf 350 sf Main Floor

Receiving Area - Above


Included 200 sf 200 sf Main Floor

Vehicle Storage - Above


Included 0 sf Off Site Vehicle Storage 0 sf
Meeting Area Lobby & Expanded Restrooms -
1,188 sf 0 sf Included in Non-/Assignable Area 0 sf

Library Staff Offices (30 Staff Total) -


1,219 sf
Directors Office - Above
Included 200 sf 200 sf 2nd Floor

Assistant Director - Above


Included 150 sf 150 sf 2nd Floor

Administrator - Above
Included 150 sf 150 sf 2nd Floor

Tech. Manager - Above


Included 150 sf 150 sf Basement

Reference Staff (4staff) - Above


Included 320 sf 320 sf Basement

Children's Staff (2 Offices) - Above


Included 350 sf 350 sf Main Floor

Admin. Workspace -- sf 200 sf Attached/Adjacent to Children's 200 2nd Floor


Offices

"Friends" Space/Office -
4,925 sf
Retail Space - 200 sf 200 sf Main Floor

Work Space - 400 sf 400 sf Anywhere

Conference Rm. (12-15p) -- sf 400 sf 400 sf Anywhere

Staff Break Room (10p) -- sf 250 sf 250 sf Anywhere

Shower/Locker Room -- sf 200 sf 200 sf Anywhere


-
Total Non-Public Allocated Space 14,354 sf 8,120 sf 8,120 sf

TOTAL ASSIGNABLE AREA 45,292 sf 48,055 sf 39,490 sf


NON-ASSIGNABLE AREA 8,280 sf * 16,018 sf 13,163 sf
(Including Walls, Hallways, Stairs, Restrooms, Etc.) (Actual Area) (25% of Gross Area) (25% of Gross Area)

TOTAL GROSS AREA 53,572 sf 64,073 sf 52,653 sf


* Comparable non-assignable ratio using 1st & 2nd floor only plus their share of mechanical space approximately 20%.

m:\jobs\plibfs09\pre\Programs_03-06-09.xls 5/22/200912:33 PM
GAINAN'S FLOWERS AND GIFTS
PROPOSED PROGRAM
BILLINGS, MONTANA

Gainan's Downtown Store

Spaces Number Area Total SF

MAIN FLOOR
General Retail Space 1 @ 1,400 sf 1,400 sf
Cooler 1 100 sf 100 sf
Utility/Workroom 1 @ 100 sf 100 sf
ADA Restrooms 2 45 sf 90 sf
Small Conference Room 1 @ 150 sf 150 sf
Loading Bay 1 350 sf 350 sf

TOTAL ASSIGNABLE AREA 2,190 sf


NON-ASSIGNABLE AREA 10% of gross area 219 sf
TOTAL GROSS AREA 2,409 sf
Greenhouse Area Pop-Out 300 sf

m:\jobs\plibfs09\pre\Programs_03-06-09.xls 5/22/200912:34 PM
Building Assessment:
A building assessment of the existing Gainan’s building was done in order to understand
the extents of the work needed for the change in building function.

The existing building is wood construction and structurally designed for floor loading of
100 lbs/sf. This is a higher floor loading capacity than standard office buildings but is
not adequate for high stack loading. Book stacks located in the existing building would
be limited in height to remain under the design load capacity. The proposed addition’s
structure would be steel with concrete floors to allow for the additional floor load
required for library stacks.

The existing mechanical and electrical systems are not adequate for the size of the new
building and would need to be replaced with the exception of a few electrical panels. The
proposed new mechanical system would be a VAV system with a rooftop air-handler
contained within a penthouse on the roof. A new electrical transformer would be needed
for the power requirement of the new building along with new light fixtures and layout to
better accommodate the new building layout.

The existing site will need to be modified in order to accommodate the new building
function and layout. The Southern portion of the site will be able to stay primarily intact
with the majority of the major site work being done on the North side of the existing
building.

Parmly Billings Library Feasibility Study 6


Billings, Montana
Preliminary Design:
Library -
The preliminary design of the new Library was back and forth effort between the Library
and CTA. One larger factor in the design was loading and storage of the Bookmobile.
One option was to have the Bookmobile be stored off site and loaded on the South side of
the building using an inflatable rail seal for protection from the elements. The other
option utilized a garage on the North side of the building for both loading and storage of
the Bookmobile.

The greenhouse space was given careful consideration given its existing use. Early on,
Chuck Gainan expressed his concern that the greenhouse space may need to be addressed
mechanically to maintain a comfortable temperature level. A large component of the
greenhouse’s environmental quality is its roof structure. After looking at several options,
it was decided that in order to provide a comfortable space with still maintaining the
openness of the greenhouse, the existing greenhouse roof would need to be replaced. The
new roof would implement a ridge skylight down the entire length of the roof. This
would allow large amounts of natural light to penetrate into the space while better
controlling heat gain and allowing for better light control in the large meeting space on
the West end of the greenhouse. Replacing the greenhouse roof is also the least
expensive alternative to address drift loading which was not required to be addressed
when this building was originally designed.

The floor layouts for the programmed Library spaces were determined from various
meetings with the Library.

The Main Floor would consist of spaces such as the A/V Collection and New Release
which are high traffic spaces, Large Type which needs to be easily located by the visually
impaired and Youth Services which holds numerous public programs. The main
Circulation Desk would be located adjacent to the main entrance to control pedestrian
flow and overall building security. A large Reading Space would be located just inside
the greenhouse with “Friends” Retail and a potential coffee space. A Large Public
Meeting Room would be located at the West end of the greenhouse with public toilets
serving the entire greenhouse space to allow for use during off Library hours.

The Basement would house a large portion of the Non-Public spaces such as Access
Services, Reference Services & Offices, Mending & Technical Services, Custodial
Supply/Work Area and the “Friends” Work Space. The main Mechanical and Electrical
Rooms would be located in the basement as well. Adult Fiction, Reading Space and a
smaller public Conference Room would account for the public areas located in the
Basement.

The Second Floor would primarily accommodate the research portion of the Library
program. Spaces such as Non-Fiction, Newspaper/Magazine, and the Montana &
Genealogy Room would make up a large portion of the second floor public space along
with the majority of the computer services such as the Computer Lab and Computer
Teaching Area. The Young Adult Area is located on this floor to allow separation

Parmly Billings Library Feasibility Study 7


Billings, Montana
between the teen and youth areas and would be designed to allow for public exposure
while providing a sense of privacy. The Library Staff Offices would be located on the
second floor as well as an Administrative Workspace, a small Circulation Desk and
additional Reading Space.

All floors are connected by an open staircase which allows natural daylight to penetrate
into each floor. This staircase would be the main circulation of the building with a new
elevator located just North of the staircase. Public restrooms would also be located on
each floor along with Public Access Catalog Computers and General Public Seating.

Gainan’s -
The Gainan’s layout was done as two separate options.

The first option has Gainan’s located within the Library shell with Library space
extending above and below. Gainan’s would be located on the North side of the building
extending towards 6th Street which would allow for more design opportunity for creating
it’s own identity while also allowing for prominent public exposure. The greenhouse
space would extend off the North side further defining Gainan’s presence on the site.
The main entrance and parking would be off the East side with delivery access off the
alley to the West. Gainan’s mechanical service would be fed off the Library’s
mechanical system served by individual zones. Electrical service could be separately
metered and billed.

The second option is a freestanding Gainan’s building located on the North side of the
site. This option would allow Gainan’s design to be completely independent of the
Library including its mechanical and electrical systems. The main entrance and parking
would be located on the South side of the building with delivery access off the alley to
the West. The greenhouse space is shown directly connected to the main entrance on the
North side creating a natural separation between public and non-public space while also
drawing attention due to its prominent exposure to the street.

Parmly Billings Library Feasibility Study 8


Billings, Montana
Option 1 - SE Aerial

Parmly Billings Library Feasibility Study 9


Billings, Montana
Option 1 - NE Aerial

Parmly Billings Library Feasibility Study 10


Billings, Montana
Option 1 - Library Main Floor

Parmly Billings Library Feasibility Study 11


Billings, Montana
Option 1 - Library Basement

Parmly Billings Library Feasibility Study 12


Billings, Montana
Option 1 - Library Upper Floor

Parmly Billings Library Feasibility Study 13


Billings, Montana
Option 2 - SE Aerial

Parmly Billings Library Feasibility Study 14


Billings, Montana
Option 2- NE Aerial

Parmly Billings Library Feasibility Study 15


Billings, Montana
Option 2 - Library Main Floor

Parmly Billings Library Feasibility Study 16


Billings, Montana
Option 2 - Gainan's Main Floor

Parmly Billings Library Feasibility Study 17


Billings, Montana
Option 2 - Library Basement

Parmly Billings Library Feasibility Study 18


Billings, Montana
Option 2 - Library Upper Floor

Parmly Billings Library Feasibility Study 19


Billings, Montana
Cost Estimate:
The cost estimate for this feasibility study is divided into two separate options with those
options being separated into four individual pieces. The four pieces of each option
included construction of the New Addition Shell and Site, Infrastructure Upgrades to
Existing Gainan’s Building, Library Tenant Improvements and either Gainan’s Tenant
Improvements or Gainan’s Building & Site depending on the option.

Research for the cost estimate information for this project was a combination of methods.
Information from Means building cost square foot number, past project cost and pricing
information from a local contractor all played a role in determining our final square
footage costs. Taking all this information into account, we derived division square
footage costs which were then used to help compose the cost of each piece of the option.
The cost for each piece is broken down on a separate sheet showing the square foot
numbers used along with any lump sum amounts needed for items specific to that piece.

In both the New Addition Shell and the Infrastructure Upgrades to Existing Building it
was assumed that the space would be finished to leasable shell standards. Because
specific information as to which party would be financing the cost of the infrastructure
upgrades to the existing building, these costs were broken out separate. The cost to
upgrade the infrastructure remains the same in both options as the total square footage
remains the same.

The Library Tenant Improvements is the cost for the Library to fit out both the existing
building and new addition to fit its needs. This number remains the same in both options
as the total square footage of Library space remains the same.

Option 1 includes the Gainan’s building within the Library building shell. Costs for the
New Addition Shell and Site was slightly more in this option due to the additional square
footage of exterior wall needed to include Gainan’s within the shell of the building.
Since this option includes Gainan’s within the building shell, the Gainan’s Tenant
Improvements is the cost for Gainan’s to fit out their space to fit their needs.

Option 2 separates Gainan’s into their own building on the North end of the site. Costs
for the New Addition and Shell are slightly less in this option since only the Library is
contained within the addition shell. All construction costs for the separate Gainan’s
building and associated site are included in the Gainan’s Building & Site number.

Parmly Billings Library Feasibility Study 20


Billings, Montana
Billings Parmly Library May 18, 2009
Billings, MT

Option Cost Comparision

OPTION 1: GAINAN'S RETAIL IN LIBRARY BUILDING SHELL

NEW ADDITION SHELL AND SITE $ 3,945,306

INFRASTRUCTURE UPGRADES TO EXISTING BUILDING $ 2,371,503

LIBRARY TENANT IMPROVEMENTS $ 4,332,698

GAINAN'S TENANT IMPROVEMENTS $ 172,098

TOTAL OPTION 1 $ 10,821,606

OPTION 2: GAINAN'S FREE STANDING BUILDING

NEW ADDITION SHELL AND SITE $ 3,544,194

INFRASTRUCTURE UPGRADES TO EXISTING BUILDING $ 2,371,503

LIBRARY TENANT IMPROVEMENTS $ 4,332,698

GAINAN'S BUILDING & SITE $ 678,390

TOTAL OPTION 2 $ 10,926,785

m:\jobs\plib09\cost\costs-div costs.xls
Billings Parmly Library May 14, 2009
Billings, MT

Project Cost Estimate

Project: OPTION 1-OWNER ADDITION TO GAINAN'S FOR NEW LIBRARY & GAINAN'S RETAIL

Description: Add 2 stories + basement to north finished to leasable shell standards. 2,709 sf Gainan's retail on 1st floor.
sf existing 26,904 sf new

A. Land & Offsite Development


1. Land Purchase = $ -
2. Off Site Development ea = $ 20,000
3. sf x = $ -

Subtotal Land & Development $ 20,000

B. Construction
1. Site Development 8,000 sf x $ 10.00 = $ 80,000
2. New Construction 26,904 sf x $ 113.00 = $ 3,040,152
3. Book Drop Tunnel 70 lf x $ 970.00 = $ 67,900
4. Reno, Demo + Infrastructure sf x $ 51.00 = $ -
5. Tenant Improvements 0 sf x $ 51.00 = $ -
6. Addl Exterior Wall vs Option 2 2,000 sf x $ 25.00 = $ 50,000
Subtotal Construction Costs $ 3,238,052
$ 120 /sf
C. Architect Engineer Fees & Expenses
1. New Construction 9% = $ 286,925
2. Renovation 12% = $ -
3. Reimbursibles 0.50% = $ 16,190

Subtotal A/E Fees & Expenses $ 303,115

D. Equipment & Furnishings


1. Furniture sta x $ 1,200 = $ -
2. Computers/AV/Office Equipment sta x $ 500 = $ -
3. Equip = $ -
4. Misc & Contingency sta x $ 100 = $ -

Subtotal Equip. & Furnishings $ -

E. Miscellaneous Expenses
1. Soils Investigation/Survey = $ 15,000
2. Testing/ Special Insp 0.50% = $ 16,190
3. Commissioning =
4. Moving/ Final Cleaning 57,615 sf x $ 3.00 =
5. sf x = $ -
Subtotal Misc. Expenses $ 31,190

Subtotal Project Cost $ 3,592,357

F. Contingency 15% $ 538,854

TOTAL PROJECT COST - 4/09 $ 4,131,211

G. Escalation to Mid Point Const - 1.5 years @ -3.0% per year $ (185,904)

TOTAL PROJECT COST - Bid 3/11 $ 3,945,306

M:\jobs\ashelemstudy\cost\const div cost.xls Page 2 Costs-Div Costs.xls


Billings Parmly Library May 14, 2009
Billings, MT

Project Cost Estimate

Project: OPTION 1-INFRASTRUCTURE UPGRADES TO EXISTING GAINAN'S FOR NEW LIBRARY & GAINAN's

Description: Demolish interiors and systems, rebuild infrastructure to leaseable shell standards. Replace greenhouse roof structure and roofing.
33,420 sf existing sf new

A. Land & Offsite Development


1. Land Purchase = $ -
2. Off Site Development ea =
3. sf x = $ -

Subtotal Land & Development $ -

B. Construction
1. Site Development sf x $ 10.00 = $ -
2. New Construction sf x $ 113.00 = $ -
3. Reno, Demo + Infrastructure 33,420 sf x $ 51.00 = $ 1,704,420
4. Tenant Improvements sf x $ 51.00 =
5. New Greenhse Roof, Skylight & Struct 3,500 sf x $ 50.00 = $ 175,000
6. Relocate Brace Frame 1 ea $ 40,000 = $ 40,000
Subtotal Construction Costs $ 1,919,420
$ 57 /sf
C. Architect Engineer Fees & Expenses
1. New Construction 9% = $ -
2. Renovation 12% = $ 230,330
3. Reimbursibles 0.50% = $ 9,597

Subtotal A/E Fees & Expenses $ 239,928

D. Equipment & Furnishings


1. Furniture sta x $ 1,200 = $ -
2. Computers/AV/Office Equipment sta x $ 500 = $ -
3. Equip = $ -
4. Misc & Contingency sta x $ 100 = $ -

Subtotal Equip. & Furnishings $ -

E. Miscellaneous Expenses
1. Soils Investigation/Survey =
2. Testing/ Special Insp 0.50% =
3. Commissioning =
4. Moving/ Final Cleaning 57,615 sf x $ 3.00 =
5. sf x = $ -
Subtotal Misc. Expenses $ -

Subtotal Project Cost $ 2,159,348

F. Contingency 15% $ 323,902

TOTAL PROJECT COST - 4/09 $ 2,483,250

G. Escalation to Mid Point Const - 1.5 years @ -3.0% per year $ (111,746)

TOTAL PROJECT COST - Bid 3/11 $ 2,371,503

M:\jobs\ashelemstudy\cost\const div cost.xls Page 3 Costs-Div Costs.xls


Billings Parmly Library May 14, 2009
Billings, MT

Project Cost Estimate

Project: OPTION 1-LIBRARY TENANT IMPROVEMENTS

Description: Tenant standard improvements + Library upgrades


sf 33,420 sf existing 24,195 sf new

A. Land & Offsite Development


1. Land Purchase = $ -
2. Off Site Development ea = $ -
3. sf x = $ -

Subtotal Land & Development $ -

B. Construction
1. Site Development sf x $ 10.00 = $ -
2. New Construction sf x $ 113.00 = $ -
3. Reno, Demo + Infrastructure sf x $ 51.00 = $ -
4. Tenant Improvements 57,615 sf x $ 51.00 = $ 2,938,365
5. Paging System 57,615 sf x $ 1.00 = $ 57,615
6. Emergency Generator 1 ea $ 70,000.00 = $ 70,000
Subtotal Construction Costs $ 3,065,980
$ 53 /sf
C. Architect Engineer Fees & Expenses
1. New Construction 9% = $ 275,938
2. Renovation 12% =
3. Reimbursibles 0.50% = $ 15,330

Subtotal A/E Fees & Expenses $ 291,268

D. Equipment & Furnishings


1. Furniture 300 sta x $ 1,200 = $ 360,000
2. Computers/AV/Office Equipment 50 sta x $ 500 = $ 25,000
3. Equip = $ -
4. Misc & Contingency 300 sta x $ 100 = $ 30,000

Subtotal Equip. & Furnishings $ 415,000

E. Miscellaneous Expenses
1. Soils Investigation/Survey =
2. Testing/ Special Insp 0.50% =
3. Commissioning =
4. Moving/ Final Cleaning 57,615 sf x $ 3.00 = $ 172,845
5. sf x = $ -
Subtotal Misc. Expenses $ 172,845

Subtotal Project Cost $ 3,945,093

F. Contingency 15% $ 591,764

TOTAL PROJECT COST - 4/09 $ 4,536,857

G. Escalation to Mid Point Const - 1.5 years @ -3.0% per year $ (204,159)

TOTAL PROJECT COST - Bid 3/11 $ 4,332,698

M:\jobs\ashelemstudy\cost\const div cost.xls Page 4 Costs-Div Costs.xls


Billings Parmly Library May 14, 2009
Billings, MT

Project Cost Estimate

Project: OPTION 1-GAINAN'S TENANT IMPROVEMENTS

Description: Tenant standard improvements + Gainan's upgrades


sf sf existing 2,709 sf new w/ greenhouse

A. Land & Offsite Development


1. Land Purchase = $ -
2. Off Site Development ea = $ -
3. sf x = $ -

Subtotal Land & Development $ -

B. Construction
1. Site Development sf x $ 10.00 = $ -
2. New Construction sf x $ 113.00 = $ -
3. Reno, Demo + Infrastructure sf x $ 51.00 = $ -
4. Tenant Improvements 2,709 sf x $ 51.00 = $ 138,159
Subtotal Construction Costs $ 138,159
$ 51 /sf
C. Architect Engineer Fees & Expenses
1. New Construction 9% = $ 12,434
2. Renovation 12% =
3. Reimbursibles 0.50% = $ 691

Subtotal A/E Fees & Expenses $ 13,125

D. Equipment & Furnishings


1. Furniture 0 sta x $ 1,200 = $ -
2. Computers/AV/Office Equipment 0 sta x $ 500 = $ -
3. Equip = $ -
4. Misc & Contingency 0 sta x $ 100 = $ -

Subtotal Equip. & Furnishings $ -

E. Miscellaneous Expenses
1. Soils Investigation/Survey =
2. Testing/ Special Insp 0.50% =
3. Commissioning =
4. Moving/ Final Cleaning 2,709 sf x $ 2.00 = $ 5,418
5. sf x = $ -
Subtotal Misc. Expenses $ 5,418

Subtotal Project Cost $ 156,702

F. Contingency 15% $ 23,505

TOTAL PROJECT COST - 4/09 $ 180,207

G. Escalation to Mid Point Const - 1.5 years @ -3.0% per year $ (8,109)

TOTAL PROJECT COST - Bid 3/11 $ 172,098

M:\jobs\ashelemstudy\cost\const div cost.xls Page 5 Costs-Div Costs.xls


Billings Parmly Library May 13, 2009
Billings, MT

Project Cost Estimate

Project: OPTION 2-OWNER ADDITION TO GAINAN'S FOR NEW LIBRARY WITH SEPARATE GAINAN'S RETAIL

Description: Add 2 stories + basement to north finished to leasable shell standards.


sf existing 24,195 sf new lib sf new store

A. Land & Offsite Development


1. Land Purchase = $ -
2. Off Site Development ea = $ 20,000
3. sf x = $ -

Subtotal Land & Development $ 20,000

B. Construction
1. Site Development 10,000 sf x $ 10.00 = $ 100,000
2. Gainan's separate utilities 0 ls $ 6,000 = $ -
3. New Construction - Library Shell 24,195 sf x $ 113.00 = $ 2,734,035
4. New Construction - Gainan's Shell 0 sf x $ 194.00 = $ -
5. Book Drop Tunnel 70 lf x $ 970.00 = $ 67,900
6. Reno, Demo + Infrastructure sf x $ 51.00 = $ -
7. Tenant Improvements 0 sf x $ 51.00 =
Subtotal Construction Costs $ 2,901,935
$ 120 /sf
C. Architect Engineer Fees & Expenses
1. New Construction 9% = $ 261,174
2. Renovation 12% = $ -
3. Reimbursibles 0.50% = $ 14,510

Subtotal A/E Fees & Expenses $ 275,684

D. Equipment & Furnishings


1. Furniture sta x $ 1,200 = $ -
2. Computers/AV/Office Equipment sta x $ 500 = $ -
3. Equip = $ -
4. Misc & Contingency sta x $ 100 = $ -

Subtotal Equip. & Furnishings $ -

E. Miscellaneous Expenses
1. Soils Investigation/Survey = $ 15,000
2. Testing/ Special Insp 0.50% = $ 14,510
3. Commissioning =
4. Moving/ Final Cleaning 57,615 sf x $ 3.00 =
5. sf x = $ -
Subtotal Misc. Expenses $ 29,510

Subtotal Project Cost $ 3,227,129

F. Contingency 15% $ 484,069

TOTAL PROJECT COST - 4/09 $ 3,711,198

G. Escalation to Mid Point Const - 1.5 years @ -3.0% per year $ (167,004)

TOTAL PROJECT COST - Bid 3/11 $ 3,544,194

M:\jobs\ashelemstudy\cost\const div cost.xls Page 6 Costs-Div Costs.xls


Billings Parmly Library May 14, 2009
Billings, MT

Project Cost Estimate

Project: OPTION 2-OWNER ADDITION TO GAINAN'S FOR NEW LIBRARY WITH SEPARATE GAINAN'S RETAIL

Description: 2,709 sf Gainan's separate retail on corner.


sf existing - sf new lib 2,709 sf new store

A. Land & Offsite Development


1. Land Purchase = $ -
2. Off Site Development ea = $ -
3. sf x = $ -

Subtotal Land & Development $ -

B. Construction
1. Site Development 3,000 sf x $ 10.00 = $ 30,000
2. Gainan's separate utilities 1 ls $ 6,000 = $ 6,000
3. New Construction - Library Shell 0 sf x $ 120.00 = $ -
4. New Construction - Gainan's Building 2,709 sf x $ 194.00 = $ 525,546
5. Book Drop Tunnel 0 lf x $ 970.00 = $ -
6. Reno, Demo + Infrastructure sf x $ 51.00 = $ -
7. Tenant Improvements 0 sf x $ 51.00 =
Subtotal Construction Costs $ 561,546
$ 207 /sf
C. Architect Engineer Fees & Expenses
1. New Construction 9% = $ 50,539
2. Renovation 12% = $ -
3. Reimbursibles 0.50% = $ 2,808

Subtotal A/E Fees & Expenses $ 53,347

D. Equipment & Furnishings


1. Furniture sta x $ 1,200 = $ -
2. Computers/AV/Office Equipment sta x $ 500 = $ -
3. Equip = $ -
4. Misc & Contingency sta x $ 100 = $ -

Subtotal Equip. & Furnishings $ -

E. Miscellaneous Expenses
1. Soils Investigation/Survey = $ -
2. Testing/ Special Insp 0.50% = $ 2,808
3. Commissioning =
4. Moving/ Final Cleaning 2,709 sf x $ 3.00 =
5. sf x = $ -
Subtotal Misc. Expenses $ 2,808

Subtotal Project Cost $ 617,701

F. Contingency 15% $ 92,655

TOTAL PROJECT COST - 4/09 $ 710,356

G. Escalation to Mid Point Const - 1.5 years @ -3.0% per year $ (31,966)

TOTAL PROJECT COST - Bid 3/11 $ 678,390

M:\jobs\ashelemstudy\cost\const div cost.xls Page 7 Costs-Div Costs.xls


Billings Parmly Library Library Facility Cost Benchmarks Rev 5/14/09
Billings, MT

Date Last Updated: Apr-09 ENR 4761


RENO EXIST
WORLAND MIDDLE GREEN RIVER HIGH SKYVIEW HIGH R. S. MEANS 2009 CODY LIBRARY NEW GAINAN'S GAINAN'S- TENANT FREESTANDING
SCHOOL SCHOOL SCHOOL 2 STORY LIBRARY RENO SHELL INFRAST IMPROVMNTS GAINAN'S BUILDING
BUILDING AREA 101,245 SF 262,000 SF 255,000 SF 22,000 SF 44,435 SF 26,904 SF 33,420 SF 57,711 SF 2,709 SF

SITE AREA 16.5 AC 45 AC 38 AC 0 AC 1.5 AC 0..2 AC 0 AC 0 AC 0.2 AC


DIVISION
1 General Conditions $ 17.08 SF $ 9.08 SF $ 4.83 SF $ 11.00 SF $ 13.10 SF $ 9.50 SF $ 4.00 SF $ 2.50 SF $ 15.00 SF

2 Demo/Site Work $ 26.21 SF $ 19.56 SF $ 15.35 SF $ 0.13 SF $ 20.62 SF $ 2.00 SF $ 6.00 SF SF $ 4.00 SF

3 Concrete $ 8.94 SF $ 12.95 SF $ 5.17 SF $ 25.26 SF $ 2.36 SF $ 9.00 SF $ 1.00 SF SF $ 10.00 SF

4 Masonry $ 6.47 SF $ 12.84 SF $ 13.18 SF $ 15.95 SF $ - SF $ 13.00 SF SF SF $ 25.00 SF

5 Metal $ 12.20 SF $ 15.87 SF $ 11.59 SF $ 0.83 SF $ 1.65 SF $ 20.00 SF $ 2.00 SF SF $ 3.00 SF

6 Wood $ 2.90 SF $ 3.58 SF $ 3.11 SF $ - SF $ 1.79 SF $ 2.00 SF $ 2.75 SF $ 2.00 SF $ 25.00 SF

7 Thermal & Moisture $ 11.23 SF $ 6.81 SF $ 3.63 SF $ 2.46 SF $ 3.19 SF $ 8.00 SF $ 2.00 SF $ 1.00 SF $ 14.00 SF

8 Doors & Windows $ 5.61 SF $ 3.40 SF $ 4.43 SF $ 5.03 SF $ 6.33 SF $ 7.00 SF $ 3.00 SF $ 2.00 SF $ 30.00 SF

9 Finish $ 23.79 SF $ 10.93 SF $ 12.67 SF $ 15.34 SF $ 20.38 SF $ 4.00 SF $ 2.00 SF $ 15.00 SF $ 12.00 SF

10 Specialties $ 1.47 SF $ 1.10 SF $ 1.93 SF $ - SF $ 1.44 SF $ 1.00 SF SF SF $ 3.00 SF

11 Equipment $ 7.73 SF $ 3.32 SF $ 8.25 SF $ - SF $ 1.68 SF SF SF SF SF

12 Furnishings $ 1.10 SF $ 1.57 SF $ 0.05 SF $ - SF $ 2.27 SF SF $ - SF $ 3.00 SF $ 3.00 SF

13 Special Constr/ FP $ - SF $ 0.26 SF $ 0.45 SF $ 2.46 SF $ 2.85 SF $ 3.60 SF $ 3.00 SF SF $ 5.00 SF

14 Conveying Systems $ - SF $ 0.49 SF $ 0.16 SF $ 3.83 SF $ - SF $ 3.00 SF SF SF $ - SF

15.1 Plumbing $ 8.08 SF $ - SF $ - SF $ 2.66 SF $ 6.49 SF $ 3.50 SF $ 3.50 SF $ 0.25 SF $ 10.00 SF

15.2 HVAC $ 16.77 SF $ 22.45 SF $ 24.85 SF $ 19.30 SF $ 10.51 SF $ 10.00 SF $ 10.00 SF $ 14.00 SF $ 10.50 SF

16 Electrical $ 15.32 SF $ 16.47 SF $ 13.10 SF $ 13.00 SF $ 16.63 SF $ 10.25 SF $ 8.50 SF $ 8.80 SF $ 12.00 SF

GC/CM Fee (6%) $ 9.73 SF $ 8.98 SF $ 7.79 SF $ 12.00 SF $ 7.23 SF $ 7.00 SF $ 3.10 SF $ 2.25 SF $ 12.00 SF

TOTAL: $ 174.62 $ 149.65 $ 130.54 $ 129.00 $ 119.00 $ 113.00 $ 51.00 $ 51.00 $ 194.00

1 Division 1, General Conditions includes Direct Cost Items (bonds, permits, builder's risk, and taxes)

Worland Middle School: 1 story, Steel Framing & Metal Studs with EIFS & Block/Brick Veneer Exterior. Sloped Metal Roofs.
Includes Security System, Commercial Kitchen & Auditorium. High Quality Finishes. Div 13 incl. Fire Sprinkler.
Green River High School: 2 story, Steel Framing. Metal Studs with Block Brick Veneer Class Wing. Block/Brick PE. Very
high quality.
Skyview High School: 2 story, Steel Framing. Metal Studs with Brick Veneer Class Wing. Block/Brick PE/Auditorium. High
quality.
Cody Library: Div 2- Demo= $5.70, Site=$15.00. Div 15.1- Selective Plumbing Reno, Div 15.2-HVAC Reno used exist central plant, Div 16- Elect Reno used exist MDP & Distribution.

M:\jjobs\sd2bwstudy\costs\costbenchmarks\constdivcosts.xls
Preliminary Project Schedule:
A preliminary project schedule was created for this project to illustrate the difference
between a Fast Track project schedule and a Conventional project schedule.

The Fast Track schedule assumes construction of the New Shell to start approximately a
year prior to Gainan’s vacating the existing building. The Conventional schedule
assumes construction of the New Shell to start possibly a month before Gainan’s vacating
the existing building. While the Fast Track schedule has the project being completed
approximately five months earlier than the Conventional, it’s overall construction time is
approximately four months longer which means additional costs for General Conditions
for the contractor. It would also add costs due to the contractor having to work around
the existing mechanical space located on the NW side of the existing building.
Discussions with a local contractor confirmed that doing the project in the Conventional
manner would be much cleaner, easier and more cost effective for everyone.

*All cost estimates illustrated in this study have assumed the Conventional
approach to this project.

Parmly Billings Library Feasibility Study 29


Billings, Montana
Parmly Billings Library / Gainan's May 18, 2009
Schedule

FAST TRACK

2009 2010 2011 2012


M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
Design
Price
Construct Shell
Reno. Exist. Infra.
Tenant Finishes
Move In
Jan. 2012

Gainan's
Move Out

CONVENTIONAL

2009 2010 2011 2012


M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
Design
Price
Construct Shell
Reno. Exist. Infra.
Tenant Finishes
Move In
June. 2012

Gainan's
Move Out

m:\jobs\plibfs09\cost\tentative schedule.xls
Parmly Billings Library Board Meeting March 12, 2009

Vision
• Viable, vital community space
• Attractive, competitive environment
• Building literacy – with bold print and elec. Media
• Improve children/youth services and teen environment
• Provide adequate space for expanding programs
• Better outreach to business
• Improve physical image – both inside and outside
• Free and convenient parking

Goals
1. Public Presence:
• Environment sustainable – LEED
• Efficient workflow
• After hour meetings
• Technologically current
• God signage and reader board
2. Evolution of Services
• Flexibility – systems, furniture
• Flow
• Increase self service
3. Budget
• Open
• Mill Levy
• Lease Payments

4. Time
• Mesh with Gainan’s 2 year +/- schedule
5. Unique Goals
• Lease – easier to sell
• Building stays on tax roll
• Library stays downtown
• 25 year “reset” opportunity

Das könnte Ihnen auch gefallen