Sie sind auf Seite 1von 4

5/8/13 Setting Out

www.gmsurveys.co.uk/setting_out#as set out survey 1/4


Home
Ser vi ces
About Us
News
Contact us
el evati ons
fl oor _pl ans
GM Surveys Ltd
Setting Out
According to many Insurance Underwriters setting out carries a high risk
which is reflected in premium costs when arranging Professional
Indemnity.
In any form of geo-spatial engineering there are three main categories of
error which are generally described as mistakes, systematic errors and
random errors. At GM Surveys we aim to reduce the risk of errors and
mistakes by operating a strict Quality Control system consisting of a
simple Ten Point Check sequence. Our TPC identifies and eliminates the
different kinds of error that can lead to expensive delays and correction
costs therby minimising the risk to our clients. From the moment we are
engaged to set out any structure or infrastructure we investigate as
many apsects of the design and setting out data as possible to ensure
the project runs smoothly and on time.
Our Ten Point Check (TPC) sequence is shown below. Click on the links to
find out more.
1 Sur vey I nstr uments
2 T opogr aphi c Sur vey
3 Ar chi tects and Engi neer s dr awi ngs
4 Setti ng Out Data
5 Setti ng Out Contr ol
6 Automated Setti ng Out
7 On Si te Computati ons
8 Gr oss Er r or Checks
9 Fi ne Checks
5/8/13 Setting Out
www.gmsurveys.co.uk/setting_out#as set out survey 2/4
10 As Set Out Sur vey and Repor t
Survey Instruments
Without accurate and correctly adjusted equipment a Surveyor or Site Engineer cannot perform his tasks to the satisfaction of the client. It is
therefore of the utmost importance that the equipment used on site is adequate for its purpose. All total stations owned by GM Surveys are
calibrated annually by professionally trained technicians and are covered by service maintenance contracts. Calibration certificates are issued at
the time of service and can be forwarded to our clients upon request. Other equipment such as optical plummets, tribrachs and levels are also
serviced on an annual basis by local dealers. We consider every part of our kit to be equally important - it does not matter how accurate an
expensive total station is if the tribrach that attaches it to the tripod is out of adjustment. It is a simple matter to ensure survey accessories are kept
accurate and in top condition all the time so our staff are trained to check and adjust them if required. Optical levels are checked at least once a
month and before any major levelling exercise using the recognised 'two peg test'. For setting out where low accuracy is required a standard detail
pole is used and the verticality of the pole is checked daily. When a higher degree of accuracy is needed a laser plummet is used on a quick set
tripod. The laser is also checked for accuracy before each days work. Survey Control Units are kept on maintenance contracts to ensure they are up
to date with the latest software from the manufacturers. GPS equipment does not need to be serviced as there are no moving parts although we do
maintain an annual subscription which allows us to receive GPS data quickly and efficiently using the Trimble VRS now system.

Topographic Survey
Probably the most important drawing to ensure any construction project is located correctly within the boundaries of the site and at the correct
level is the T opogr aphi c Sur vey. Our first visit to the proposed development will include a check on the physical boundaries of the site and other
hard points of detail such as building corners as shown on the Survey. The client should have previously confirmed that the physical boundaries are
the same as the legal boundaries. This is important as it sometimes happens that a fence or a wall can be erected and assumed by a new landowner
to be a legal boundary when in fact that may not be the case. See the section on Boundar y Sur veys for more information regarding boundaries.
We also check general ground levels in the area of proposed construction to ensure existing levels agree with design levels. ten minutes doing this
can prevent costly delays if drainage has to be redesigned due to incorrect levels shown on the Survey.

Architects and Engineers Drawings
We realise that great care has been taken by the Architects, Structural and Drainage Engineers in the production of their drawings but it is inevitable
that the odd discrepancy between drawings will get through so there is no harm in an extra pair of eyes checking them. Before we begin processing
our setting out data we will request copies of all drawings in CAD format. The Architects and Engineers site layouts will be overlaid and we will check
for general continuity before rotating them (if necessary) to fit perfectly over the original Survey grid. It is often the case that a critical dimension is
missing from the drawings when we are asked to set out points on site that have not been previously processed with the rest of our setting out data.
If the Architect or Engineer are not available at the time it could lead to delays before they can be contacted and we can return to site. However if
we have the CAD drawings loaded onto our laptops and/or tablet PC's we can quickly interrogate the drawings whilst on site to obtain the
additional dimensions we require. We also ensure that the drawings we have used to process the setting out data are the same revision as the
drawings on site. If we find the drawings we have are vastly different from the latest revisions we can request they are e-mailed directly to us on site
from the Architect.

Setting Out Data
We aim to process as much setting out data as possible in the office prior to our first site visit. It is far easier to concentrate in a quite office than in
the noisy and dusty environment of a busy construction site. Having previously overlaid the Architects and Engineers layouts to match the Survey grid
every foundation, wall, kerbline and drainage point is now directly related to the position of the control stations. Using Trimble T er r amodel software
we assign each point to be set out a unique name and co-ordinate in either 2D or 3D as required then store them in entity specific files. When all the
data has been processed it is transferred to the fi el d contr ol uni t by USB, data stick or e-mail. This eliminates the possibilty of human error that can
occur when typing co-ordinates manually and the time saving can be substantial if the files contain hundreds, or even thousands, of points. Finally we
produce setti ng out dr awi ngs for each phase of the construction which can be left on site with the contractors as a permanent record of the
points we have set out.

Setting Out Control
The old 'grid' system which has been used for many years and is still favoured by a few companies is outdated and inefficient. Many sites are squeezed
onto the smallest plots of land where there is barely enough room to work, let alone store materials and ensure the safety of the setting out control. A
site engineer will spend hours carefully placing grid pegs and profiiles around the site knowing they will almost certainly be disturbed or obstructed
5/8/13 Setting Out
www.gmsurveys.co.uk/setting_out#as set out survey 3/4
at some stage of the construction. The use of theodolites and tape measures can also be counter productve due the amount of set-ups required to
complete a relatively simple task on a busy site with materials stacked on every spare metre. Accurate control is essential for any setting out
project. A network of control stations and reference objects will be established using the original Topographic Survey control as a base. Where
possible we will relate these stations to OS National Grid using GPS equipment so that in the event of a total loss of control we can quickly replace
them without the loss of accuracy. RO's will be placed around the site on solid, immovable objects (i.e. walls, buildings etc.). The combination of
control stations and RO's enable us to establish temporary 'virtual' stations for a days work in almost any position on site. If a contractor decides our
total station is in the way it only takes minutes to move it and quickly establish a new virtual station. Our control units have powerful on board
software which immediately indicate any errors every time the instrument is set up. If the errors are within a pre-determined tolerance the software
will make adjustments to the instrument readings to ensure that a high degree of accuracy is maintained.

Automated Setting Out
Having previously processed the setting out data there is no need, in most cases, for a Surveyor to spend hours sitting in a site office with a pile of
drawings and a calculator. Our Surveyors will already have the necessary information loaded onto the field control units and will be seting out within
minutes of arriving on site. Once the total station has been positioned and checks made to the surrounding control points the control unit will, quite
literally, speak to the Surveyor and tell him which direction to move until he is in the precise location of the point to be set out. Robotic instruments
mean we can use one man teams for some projects although when a large volume of setting out is needed in a short time we recommend a two
man team to speed things up even more. By pre-processing the co-ordinates of each point there are very few manual calculations to be made on
site and taping errors are non-existent as all angular and distance measurements are carried out automatically by the total station.

On Site Computations
Despite all our efforts to pre-process the setting out data it is inevitable that someone on site will ask us to set out something that we have not co-
ordinated. A laptop or tablet pc holds the current drawings for the site while the control unit is in itself a computer with software that can handle
almost any trigonometric calculation. If we get to the site and we find we have out of date drawings we simply phone the Architect and ask them to
e-mail the latest drawing direct to the laptop. Alternatively someone in our office can e-mail an up to date co-ordinate file direct to the laptop or
even to the control unit. However since our aim is to reduce the risk of error from human error we ensure that every point computed on site is
immediately checked as described in the 'fine checks' section and checked against the original setting out drawing as described in the 'as set out
survey' section.

Gross Error Checks
Gross error checks are simple taped dimensions that are compared to written or scaled dimensions on the Architects layout. On our first visit to the
site we will set out crucial elements of the proposed structure and check dimensions to the site boundaries or other permanent points of detail. These
checks will immediately tell us if the building is in the correct position, the right way round and orientated correctly to the survey grid. They are
recorded on a printout of the layout and stored on file.

Fine Checks
Once the days setting out is complete the distances between points are checked by tape to prove they have been set out correctly in relation to
each other. These can be random checks or a complete record of distances between every point. They are compared to the relevant Architects
drawing and can be written on a paper copy of the setting out drawing for storage on file. This check has the added bonus of proving the instruments
used in the setting out are in adjustment as any mis-alignment of tribrachs and optical or laser plummets would be revealed if the distances between
points proved different to the design distances.

As Set Out Survey and Report.
The final check of our TPC system is the 'as set out' survey. By usimg a total station linked to a dedicated control unit the position of each point as set
out is stored automatically in an ASO (as set out) file. At the end of each day the ASO file is downloaded onto a laptop or PC at the office,
porocessed and overlaid onto the master setting out drawing. Each point is compared to the original design position and the file is stored to give us
a permanent record of the date and accuracy of every point we set out. Any discrepencies found are reported immediately to the relevant
authority on site and corrected at the earliest possible opportunity. relevant discussions held on site are written down in a report and stored on file
along with the fine checks taken previously in section 9.

5/8/13 Setting Out
www.gmsurveys.co.uk/setting_out#as set out survey 4/4
HOM E | SERVI CES | ABOUT US | NEWS | CONT ACT US

Das könnte Ihnen auch gefallen