Sie sind auf Seite 1von 39

TECHNICAL SPECIFICATION

FOR PROCUREMENT OF
VALVES








CONTRACT No. DOCUMENT No. REV No. SHEET
14333 PS14333-G0000-PD-SP-A4-0009 2 Page 2 of 15
FORMAT: PS 14333/PLL/Doc REV.0

CONTENTS
1.0 SCOPE 3
2.0 GENERAL REQUIREMENTS 3
2.1 REFERENCE CODES AND STANDARDS 4
2.2 ENDS 6
2.3 FACE FINISH 6
2.4 CARBON STEEL 6
2.5 AUSTENITIC STAINLESS STEEL 7
3.0 DESIGN 7
4.0 MATERIAL 11
5.0 INSPECTION AND TESTING 11
6.0 MARKING AND PAINTING 14
7.0 DESPATCH / PREPARATION FOR SHIPMENT 14
ANNEXURE-01 (Terms of delivery, General requirements, LB-08-901) 14 Pages
ANNEXURE-02 (Surface treatment of stainless austenitic steel PS-08-008) 10 Pages






TECHNICAL SPECIFICATION
FOR PROCUREMENT OF
VALVES








CONTRACT No. DOCUMENT No. REV No. SHEET
14333 PS14333-G0000-PD-SP-A4-0009 2 Page 3 of 15
FORMAT: PS 14333/PLL/Doc REV.0

REQUIREMENTS
BIDDERS
COMPLIANCE
1.0 SCOPE:
The document lists the mandatory technical and associated requirements for
purchase of various piping valves to be used in QSTec Polysilicon Project -
Phase I, Qatar. These requirements are in tandem with requirements of
Piping Material Specification (PMS).
2.0 GENERAL REQUIREMENTS:
2.0.1 All valves and their dimensions, tolerances, chemical composition, physical
properties, heat treatment, hydrotest and other testing and marking
requirement shall confirm to the latest codes and standards specified in the
valve material requisition (MR). Vendor shall strictly comply with the
stipulation and no deviations shall be permitted.
2.0.2 The requirement given below is to be read in conjunction with the Valve
Specification Data Sheet.
2.0.3 Vendor shall supply valves in accordance with the valve specification sheets
along with auxiliaries if any, such as gear operator, bypass, drains etc.
Whenever specified in the specification sheets, subject notes and other
enclosures to the material requisition (MR).
2.0.4 All flanged valves shall have flanges integral with the valve body, flange finish
shall be normally specified in valve specification sheet as serrated finish, 125-
250 ARRH etc. Forged valves can have weld on flanges with 100%
radiography.
2.0.5 Any scale and oxides on valves resulting from heating operation shall be
removed.
2.0.6 Valve body / bonnet shall be forged / cast as specified. Forgings are
acceptable in place of castings but not vice-versa.
2.0.7 Valves heavier than 500 kg and 250 kg shall be supplied with supporting lugs
and lifting lugs respectively and such standard devices shall be provided as
per manufacturer standard.







TECHNICAL SPECIFICATION
FOR PROCUREMENT OF
VALVES








CONTRACT No. DOCUMENT No. REV No. SHEET
14333 PS14333-G0000-PD-SP-A4-0009 2 Page 4 of 15
FORMAT: PS 14333/PLL/Doc REV.0
REQUIREMENTS
BIDDERS
COMPLIANCE
2.0.8 Where gear operator is not called for as per clause 3.14 but vendor
recommends a gear operator, he shall highlight such case(s) and quote
separate prices for the valve and gear operator.
2.0.9 Gate valves shall be provided with by- pass arrangement as per the following:
Class Size
150 DN 650 and above
300 DN 400 and above
600 DN 150 and above
By-pass piping, Fitting and Valves shall be of compatible material and design.
The by-pass piping arrangement shall be such that clearance between main
valve body and by-pass assembly shall be the minimum possible for the
layout reasons.
2.0.10 By-pass valve shall be a globe valve. The sizes shall be as under:
Main Valve Size
By-pass Valve
Size
DN 100 & smaller DN 15
DN 150 to DN 200 DN 20
DN 250 & Larger DN 25

Vendor shall supply by-pass valve duly tested and fitted to the main valve.
Valves with by-pass shall have the direction of flow marked on the main
valve. By-pass attachment to the main valve body shall not be screwed. All
fillet welds for by-pass installation shall be 100% examined by DP/MP test.
NDT of by-pass valve shall be in line with main valve.
2.0.11 Service such as oxygen, cryogenic and other special process applications
may require valves to be thoroughly degreased, cleaned and assembled in a
clean and dry room.
2.1 REFERENCE STANDARDS AND CODES:
The latest editions along with addenda (if applicable) of all the international,
national, state and local codes and standards shall be applied, unless






TECHNICAL SPECIFICATION
FOR PROCUREMENT OF
VALVES








CONTRACT No. DOCUMENT No. REV No. SHEET
14333 PS14333-G0000-PD-SP-A4-0009 2 Page 5 of 15
FORMAT: PS 14333/PLL/Doc REV.0
REQUIREMENTS
BIDDERS
COMPLIANCE
otherwise specified.
CODE/STANDARD DESCRIPTION
ASME/ANSI CODES AND STANDARDS
B 16.5 Pipe Flanges and Flanged Fittings
B 16.10 Face -To-Face and End-To-End Dimensions of Valves
B 16.25 Butt-Welding Ends
B 16.34 Valves - Flanged, Threaded and Butt Welding End
B 16.47 Large Diameter Steel Flanges
B 46.1 Surface Texture
ASTM STANDARDS
A 105 Carbon Steel Forgings for Piping Applications
A 182 Forged or Rolled Alloy Steel Pipe, Flanges, Forged Fittings
and Valves and Parts for High Temperature Services.
A 216 Steel Castings Suitable for Fusion Welding for High
Temperature Service.
A 262 Standard Practices For Detecting Susceptibility
to Intergranular Attack in Austenitic Stainless Steel
A 351 Steel Castings, Austenitic for high temperature service
API STANDARDS
API 594 Wafer and Wafer Lug Check Valves
API 598 Valve Inspection and Testing
API 600 Steel Gate Valves - Flanged and Butt Welding Ends, Bolted
and Pressure Seal Bonnet
API 602 Compact Steel Gate Valves - Flanged, Threaded, Welding and
Extended Body End
API 607 Fire Test for Soft Seated Quarter Turn Valves
API 609 Butterfly Valves: Double Flanged, Lug and Wafer Type
API 6FA Specification for Fire Test for Valves






TECHNICAL SPECIFICATION
FOR PROCUREMENT OF
VALVES








CONTRACT No. DOCUMENT No. REV No. SHEET
14333 PS14333-G0000-PD-SP-A4-0009 2 Page 6 of 15
FORMAT: PS 14333/PLL/Doc REV.0
REQUIREMENTS
BIDDERS
COMPLIANCE
MSS STANDARDS
SP-25 Standard Marking System for Valves, Fittings, Flanges and
Unions
BS STANDARD
BS 1868 Spec for Steel Check Valves (Flanged & Butt Welding Ends)
BS 1873 Steel Globe Valves (Flanged and Butt Welding Ends)
BS EN ISO Specification for Ball valves
17292
BS 5156 Diaphragm Valves
BS 6755 P 2 Testing of valves : Specification for fire type-testing
requirements
BS 6364 Valves for Cryogenic Service
AWWA STANDARDS
C 207 Steel Pipe Flanges for Waterworks Service-Sizes 4 in through
144 in
C 504 Rubber-Seated Butterfly valves
2.2 ENDS:
Unless otherwise specified, the ends shall be to the following standard:
B.W. ENDS : ASME B 16.25
FLANGED : ASME B 16.5 AND AWWA C207 Cl. D
2.3 FACE FINISH:
Face finish for flanges shall be Serrated Finish to 125-250 in AARH shall be
to MSS-SP-6 / ASME B46.1 / ASME B16.5.
2.4 CARBON STEEL
2.4.1 All forging material shall be normalized.
2.4.2 Wall thickness of all carbon steel valves shall be as per respective design
standard.






TECHNICAL SPECIFICATION
FOR PROCUREMENT OF
VALVES








CONTRACT No. DOCUMENT No. REV No. SHEET
14333 PS14333-G0000-PD-SP-A4-0009 2 Page 7 of 15
FORMAT: PS 14333/PLL/Doc REV.0
REQUIREMENTS
BIDDERS
COMPLIANCE
2.5 AUSTENITIC STAINLESS STEEL:
2.5.1 All items / parts shall be supplied in solution annealed condition.
2.5.2 Intergranular Corrosion (IGC) Test shall be conducted as per the following for
all the grades of Austenitic stainless steels.
ASTM A262 Practice B with acceptance criteria of 60mils/ year (max) for
casting.
ASTM A262 Practice E with acceptance criteria of No cracks as observed
from 20X magnification and microscopic structure to be observed from 250X
magnification for other than casting.
2.5.3 For IGC test, two sets shall be drawn from each solution annealed lot; one
set corresponding to highest carbon content and other set corresponding to
the highest rating / thickness. When testing is conducted as per practice E,
photograph of microscopic structure shall be submitted for record.
3.0 DESIGN
3.1 Gate and globe valves shall have backseat arrangement to permit repacking
while valve is fully opened and under service pressure.
3.2 Face-to-face and end-to-end dimensions shall be in accordance with ASME B
16.10.
3.3 Hardness difference between wedge and seat/seat ring of valves shall be
minimum 50 BHN. Seat rings shall have higher hardness. Stelliting / hard
facing by deposition shall be minimum 1.6mm. Renewable seat rings shall be
seal welded for valves of size DN50 & above to prevent loosening in service.
3.4 Cryogenic ball, butterfly, gate and globe valves shall be supplied with the
extended stems / bonnets because extended bonnet allows a reasonable
temperature gradient up to the gland and point of operation. Stem / bonnet
extention shall be as per the following:
Size (DN) 15-50 80-100 150-200 250-300 350-400 450-600
Up to -100C (MM) 125 150 175 200 225 250






TECHNICAL SPECIFICATION
FOR PROCUREMENT OF
VALVES








CONTRACT No. DOCUMENT No. REV No. SHEET
14333 PS14333-G0000-PD-SP-A4-0009 2 Page 8 of 15
FORMAT: PS 14333/PLL/Doc REV.0
REQUIREMENTS
BIDDERS
COMPLIANCE
3.5 No leakage is permitted from the stems in cryogenic service as leakage
could freeze affecting the plant balance. Stem leakage may result in stem
seizure and packing failure.
3.6 Valves shall be as per the following standards.

3.7 All soft seated ball valve shall be supplied with antistatic devices.
3.8 The ball valves shall be of floating ball / trunnion mounted type as per
following.
Valve Size Rating Design Std.
Testing
Std.
Gate / Globe
/ Lift Check
DN15 - DN40
150 /300
/600
API-602 API-598
Gate
DN50
DN600
150 /300
/600
API-600 API-598
Globe
DN50
DN600
150 /300
/600
BS-1873 API-598
Swing Check
DN50
DN600
150 /300
/600
BS-1868 API-598
Dual Plate
Check
DN300
DN1200
150 /300
/600
API-594 API-598
Dual Plate
Check
DN1600
DN2200
150 MNF STD API-598
Ball
DN15
DN200
150 / 300
BS EN ISO
17292
API-598
Butterfly
DN200
DN600
150 /300
/600
API-609 API-598
Butterfly
DN650
DN1600
150 /300
/600
AWWA C504 API-598
Butterfly
DN2200
DN2200
150 MNF STD API-598
Diaphragm
DN50
DN200
150 BS-5156 API-598






TECHNICAL SPECIFICATION
FOR PROCUREMENT OF
VALVES








CONTRACT No. DOCUMENT No. REV No. SHEET
14333 PS14333-G0000-PD-SP-A4-0009 2 Page 9 of 15
FORMAT: PS 14333/PLL/Doc REV.0
REQUIREMENTS
BIDDERS
COMPLIANCE
150#
DN 200 and smaller Floating Ball
DN 250 and larger Trunnion Mounted (Soft Seat)
DN 50 and larger Trunnion Mounted (Metal Seat)
300# &
600#
DN 40 and smaller Floating Ball
DN 50 and larger Trunnion Mounted

3.9 Bore of the reduced bore ball valve shall be as per ISO 17292.
3.10 Face to face dimension of double flanged butterfly valve shall be as per
AWWA C 504.
3.11 Generally the valves shall be hand wheel or lever/wrench operated. However
suitable gear operator in enclosed gearbox shall be provided for valves as
follows.
For Gate / Globe
Valves
Totally enclosed bevel in grease case with
grease nipples / plugs
For Ball / Butterfly /
Diaphragm Valves
Totally enclosed helical worm or
combination of helical worm and spur gear
in grease case with grease nipples / plugs

3.12 Gear operation shall be provided as under :
Valve type Class
Size Requiring
Gear Operator
Gate / Globe /
Diaphragm Valve
150 / 300 DN 350 and larger
600 DN 300 and larger
Ball / Butterfly Valve
150 / 300 DN 150 and larger
600 DN 100 and larger
For sizes lower than these ranges, hand wheel, lever / wrench shall be
provided.
3.13 Hand wheel diameter shall not exceed 750mm and lever length shall not
exceed 500mm on each side. Effort to operate valve shall not exceed 35kgf
at hand wheel periphery. However, failing to meet the above requirement,
vendor shall offer gear operation.






TECHNICAL SPECIFICATION
FOR PROCUREMENT OF
VALVES








CONTRACT No. DOCUMENT No. REV No. SHEET
14333 PS14333-G0000-PD-SP-A4-0009 2 Page 10 of 15
FORMAT: PS 14333/PLL/Doc REV.0
REQUIREMENTS
BIDDERS
COMPLIANCE
3.14 Quarter turn valves shall have open position indicators with limit stops.
3.15 Gear operator shall be so designed to operate effectively differential pressure
across the closed valve equal to maximum permissible pressure as per the
class rating.
3.16 All Valves shall have a facility to Pad-lock in open or close position.
3.17 All Valves shall be suitable for full vacuum condition.
3.18 The ball of Ball valve and disc of Butterfly valve shall not protrude outside the
end flanges.
3.19 Bellow seal is required for globe valve for valve tag numbers VL11FS,
VL31FS, VL12FST, VL12FKST, VL32FST, VL32FKST, VL32FHST and
VL32FHKST.
3.20 Bellow seal valves shall have non-rotating stem to prevent torsion of bellows.
3.21 Packing shall be a minimum five ring packing system with inconel and
corrosion inhibitor. Packing material shall be as follows:
ASME Class150:- Graphite Yarn Braided Packing
ASME Class 300 & 600:- Pre- Formed Die-moulded Graphite Packing with
stem finish as per 32 micro finish AARH
3.22 Lantern ring to be provided in between stem packing ring.
3.23 Valve design shall ensure repair of gland packing under full line pressure.
3.24 Blowout-proof stems that do not rely on gland components for stem retention.
3.25 Stem packing for all ball & butterfly valves shall be flexible Graphite (Fire
safe).
3.26 Seal and internals for ball valve shall be suitable for the fluid composition and
Pressure / Temperature rating of valve.
3.27 Diaphragm valve shall have weir pattern body configuration to ensure tight
shut-off.
3.28 All diaphragm valves shall have spindle isolated from service fluid.
3.29 Diaphragm shall be capable of being replaced.
3.30 Vendor shall provide Recess or Groove inside bolt hole circle for fixing /
restricting rubber lining on flanged end of the valves.
3.31 Weld repair on casting and forging is not allowed.






TECHNICAL SPECIFICATION
FOR PROCUREMENT OF
VALVES








CONTRACT No. DOCUMENT No. REV No. SHEET
14333 PS14333-G0000-PD-SP-A4-0009 2 Page 11 of 15
FORMAT: PS 14333/PLL/Doc REV.0
REQUIREMENTS
BIDDERS
COMPLIANCE
4.0 MATERIAL
4.1 Material of construction of Yoke shall be at least equal to body material.
4.2 Stem shall be forged or machined from forged/ rolled bar. No casting is
permitted.
4.3 If an overlay weld-deposit is used for the body seat ring, seating surface, the
seat ring base material shall be at least equal to the corrosion resistance of
the material of the shell.
4.4 Hand wheels shall not be made of gray iron or non-metallic materials. Butt
Welding Carbon Steel Valves shall have a 0.25% maximum Carbon Content;
Free machining Steel is not acceptable.
4.5 Lined Valves
4.5.1 EPDM Rubber Lined Valves
Material : EPDM Rubber
Hardness : SHORE A 70
Lining Thickness : 3 mm
4.5.2 PTFE / PFA Lined Valves
Material : PTFE / PFA
Lining Thickness : 3 mm
5.0 INSPECTION AND TESTING
5.1 Every valve, its components and auxiliaries must be subjected to all the
mandatory tests and checks called for in the respective codes, data sheets
etc. by the manufacturer.
5.2 Material test certificates (physical property, chemical composition and heat
treatment report) shall also be furnished according to EN10204 type 3.1 for
the valves supplied for all pressure containing parts. However certification to
EN10204 type 2.2 shall be acceptable for all non pressure wetted parts.
5.3 Though the extent of inspection shall be as under but extent with hold points
shall be decided by purchaser and recorded in the form of inspection plan. In
case of third party inspection the inspection plan shall be approved by the






TECHNICAL SPECIFICATION
FOR PROCUREMENT OF
VALVES








CONTRACT No. DOCUMENT No. REV No. SHEET
14333 PS14333-G0000-PD-SP-A4-0009 2 Page 12 of 15
FORMAT: PS 14333/PLL/Doc REV.0
REQUIREMENTS
BIDDERS
COMPLIANCE
purchaser.
a Visual and dimensional inspection.
b Review of material test certificates.
c Any mandatory or supplementary test.
d Review of radiographs/radiographic reports or any other NDT tests for cast
valves
e Hydrostatic test 100% for body, 10% seat leakage selected on random basis.

5.4 Gate and globe valves shall be subjected to back seat test.
5.5 Fire safe test as per API 607 / API 6FA shall be supplied for a previously
tested soft-seated valve. The test should have been witnessed and certified
by a third party inspection agency for the same design of the valve offered.
5.6 All supplied valves shall be of radiographic quality. Valve castings shall
undergo radiographic examination as specified below.
Material Rating Size Range Radiography
All
150#
DN 50 DN 600 5%
DN 650 and larger 100%
300#
DN 50 DN 400 10%
DN 450 and larger 100%
600# All sizes 100%
5.7 Valves used in hydrogen service are applicable for following requirements
- 50% of the valve castings shall be radiographed for sizes up to DN 600 in
150# class rating and up to DN 400 in 300# class rating. For all remaining
size and rating 100% radiography is required.
- Whenever random radiography is specified, at least one valve against
that item shall be radiographed.
- Casting and test bar shall be heat treated together. Valves casting shall
be in solution heat treated and pickled condition.
5.8 Valves used in low temperature / cryogenic service are applicable for
following requirements
- 20% of the valve castings shall be radiographed for sizes up to DN 600 in






TECHNICAL SPECIFICATION
FOR PROCUREMENT OF
VALVES








CONTRACT No. DOCUMENT No. REV No. SHEET
14333 PS14333-G0000-PD-SP-A4-0009 2 Page 13 of 15
FORMAT: PS 14333/PLL/Doc REV.0
REQUIREMENTS
BIDDERS
COMPLIANCE
150# class rating and up to DN 400 in 300# class rating.
- For all remaining size and rating 100% radiography is required.
5.9 Acceptance criteria and areas to be radiographed, for valve castings shall be
as per ASME B16.34. However for type of valves not covered in ASME B
16.34, vendor shall enclose details in line with ASME B 16.34.
5.10 For random radiography wherever specified, the sampling shall be per size of
the quantity ordered on each foundry.
5.11 Radiography shall be done by X-ray to get the required sensitivity.
5.12 EPDM Rubber Lined Valves
a Visual Inspection
Lining shall be free from blisters, cracks or other surface imperfections,
porosity, voids, inclusions or other defects which would impair satisfactory
performance.
b Lining Thickness Test
Lining thickness test shall be carried out by magnetic thickness gauge at
minimum 3 locations arbitrarily.
c Adhesive Strength Test
Adhesion between rubber lining and substrate shall be homogenous and
without any defect or air pocket. At locations where adhesion is broken or air
pocket has occurred, curing of lining shall be done.
5.13 PTFE / PFA Lined Valves
a Visual Inspection
Lining shall be free from blisters, cracks or other surface imperfections,
porosity, voids, inclusions or other defects which would impair satisfactory
performance.
b Lining Thickness Test
Lining thickness test shall be carried out by magnetic thickness gauge at
minimum 3 locations arbitrarily.
c Electrostatic / Spark Test
Electrostatic / Spark Test shall be done before pressure testing of valve.
Lining shall be inspected for defects with high voltage alternating current






TECHNICAL SPECIFICATION
FOR PROCUREMENT OF
VALVES








CONTRACT No. DOCUMENT No. REV No. SHEET
14333 PS14333-G0000-PD-SP-A4-0009 2 Page 14 of 15
FORMAT: PS 14333/PLL/Doc REV.0
REQUIREMENTS
BIDDERS
COMPLIANCE
spark tester. Lining should not produce spark when clean and dry surface is
tested at 25 KV.
5.14 Fugitive emission test, wherever specified in valve material specification, shall
be carried out as per ISO 15848-2 & tightness Class B shall be achieved.
5.15 In case of motor operated or actuator operated valves, functional /
operational checks as per the requirements of the specifications shall be
made on each valve.
5.16 PMI shall be performed as per the scope and procedures as defined in
PS1053-G0000-04-SP-A4-0011 Specification for PMI of piping at site and at
supplier Works.
6.0 MARKING AND PAINTING
6.1 All items shall be marked (stamped/ etched) in accordance with the
applicable code/ standard/ specification.
6.2 Valves marking, symbols, abbreviations etc. shall be in accordance with
MSS-SP-25 or the referred in specification sheet as applicable, Vendors
name, valve rating, material designation, nominal size, direction of flow (if
any) etc. shall be integral on the body.
6.3 Carbon steel valves shall have surface preparation to Sa 2 1/2 and shall be
painted with one coat of inorganic zinc silicate (min DFT 65 to 75 microns).
6.4 All items shall have attached corrosion resistant tag providing salient features
6.5 Fire safe markings wherever applicable shall be clearly marked.
6.6 Steel die marking with round bottom punch may be permitted on body of butt
weld CS, but for SS fitting, the same should be marked by electro-etching
only.
6.7 Paint or ink for marking painting shall not contain any harmful metal salts
such as zinc, lead or copper which causes corrosive attack on heating.
7.0 DESPATCH / PREPARATION FOR SHIPMENT
7.1 The product touched surface may neither contain oil and grease nor oxygen
grease or other impurities.






TECHNICAL SPECIFICATION
FOR PROCUREMENT OF
VALVES








CONTRACT No. DOCUMENT No. REV No. SHEET
14333 PS14333-G0000-PD-SP-A4-0009 2 Page 15 of 15
FORMAT: PS 14333/PLL/Doc REV.0
REQUIREMENTS
BIDDERS
COMPLIANCE
7.2 Medium touched interior zones may not be blasted respectively retreated with
anticorrosive agents.
7.3 Every tool and adjuvant which is used for production and/or cleaning must be
completely free from non-ferrous metal (i.e. revising tools, mandrels, welding
materials etc.)
7.4 Additional requirement for cleanness shall be as per clause no. 9 of
ANNEXURE-01 (Terms of delivery, General requirements, LB-08-901) and
ANNEXURE-02 (Surface treatment of stainless austenitic steel PS-08-008)
7.5 All valves shall be dry, clean and free from moisture, dirt and loose foreign
material of all kinds.
7.6 All valves shall be protected from rust, corrosion, and mechanical damage
during transportation, shipment and storage.
7.7 Rust preventive used on machined surfaces to be welded shall not be
harmful to welding and shall be easily removable with the petroleum solvent.
7.8 Ends shall be suitably protected, and the protectors shall be securely and
tightly attached.
Beveled end : Metal or plastic cap
Flange face : Metal or plastic cover
7.9 Valves procured as per clause no. 7.4 shall be supplied in individual separate
packaging so that valve internals should not be contaminated by any means
during transportation, handling and storage. Valve packet shall be marked
with purchase order no., tag number, size.
7.10 End protectors to be used on flange faces shall be attached by at least three
bolts or wiring through bolt holes and shall not be smaller than the outside
diameter of the flange.









centrotherm SiTec GmbH Terms of delivery no.: 08-901
Page 1 of 14



Terms of delivery

General requirements

No.: 08-901


Purchasing, production, delivery and conformity assessment
Pressure devices and plant components


Content Page

Further Specifications and terms of delivery ........................................................... 2
1 Application area .............................................................................................. 2
2 Terms and abbreviations ................................................................................ 3
3 Processing of orders ....................................................................................... 4
3.1 Manufacturer .................................................................................................. 4
3.2 Subcontractor ................................................................................................. 4
3.3 Monitoring of dates ......................................................................................... 4
3.4 Correspondence / contact person ................................................................... 4
3.5 Complete delivery ........................................................................................... 4
3.6 Acceptance ..................................................................................................... 4
4 General ........................................................................................................... 5
5 Classification of fluids ..................................................................................... 6
5.1 Classification in groups ................................................................................... 6
5.2 Classification according to condition of aggregation gas or fluid................ 6
5.3 Instable gases ................................................................................................ 6
6 Material selection and processing .................................................................. 7
7 Surface treatment ........................................................................................... 8
8 Examinations .................................................................................................. 9
9 Cleanness .................................................................................................... 10
9.1 General requirements ................................................................................... 10
9.2 Additional requirements free of oil and grease execution ........................... 10
10 Preparation for delivery, transportation ......................................................... 12
Quoted documents and normative references ...................................................... 13
Annex instable gases ........................................................................................ 14




Passing on as well as duplication of this document, utilization and report of its content is not permitted, if not expressly entitled in
written form. All rights reserved in case of patent or utility model registration as well as from this resulting in patent rights.
Offence obligate to compensation.
This document is property of centrotherm SiTec GmbH.
Creation: Inspection: Approval: Revision: 0
date 2009-02-26 date date
from MM from from
ANNEXURE01 TO DOC. NO. PS14333G0000PDSPA40009



centrotherm SiTec GmbH Terms of delivery no.: 08-901
Page 2 of 14

Further terms of delivery (LB) and specifications (PS)

LB 08-902 Supply and production vessels
LB 08-903 Piping
LB 08-904 Fittings
PS 08-001 Leakage test for reactor and converter
PS 08-002 Machines, tanks and columns
PS 08-003 Insulation
PS 08-004 Corrosion prevention
PS 08-005 Heat exchanger standard requirement
PS 08-006 Heat exchanger high demands
PS 08-007 Steel construction
PS 08-008 Surface treatment of stainless austenitic steel
VA 08-100 Leakage test
VA 08-101 Welded connections at pressure apparatus from metallic materials




1 Application area

These terms of delivery are valid for the purchasing, production, delivery of plant
components and the execution of the conformity assessment procedure of pressure
devices, which have to be in conformity with the general safety requirements of guideline
97/23/EG.
Pressure devices for plants in the Chemical Industry must be safe and cost-effective
within the provided operation time. To ensure this, it is necessary to lay down a detailed
procedural design and above all the definition of the quality.

Besides the general requirements of these terms of delivery, further specifications
determine the specific quality requirements (see further terms of delivery and
specifications). These specific quality requirements have to be used for purchasing and
production in connection with the General requirements. When placing the order, they
will be part of it. This centrotherm SiTec specification must also be applied for pressure
devices and plant components, which have been constructed for a pressure of
0 < PS 0.5 bar or they are part according to PED, article 3, paragraph 3
(designed and produced according to good engineering knowledge).




centrotherm SiTec GmbH Terms of delivery no.: 08-901
Page 3 of 14

2 Terms and abbreviations

Vessel see guideline 97/23/EG article 1, paragraph 2.1.1
i.e. columns, tanks, heat exchangers etc.

PED Guideline 97/23/EG (Pressure Equipment Directive)

DN Nominal diameter according to DIN EN ISO 6708

Fluid gases, fluids and vapours in pure stat as well as in mixtures.
Fluids may contain solids. Producer is in terms of this standard
the contractor, who markets the pressure device and/or plant
equipment on its behalf.

Instable gases See section 5.3

Category Classification (I, II, III or IV) of pressure devices
according to risk potential

PN Nominal pressure according to DIN EN 1333

PS Admissible pressure (design pressure according to DIN EN 764-1)

Pipes see Guideline 97/23/EG, article 1, paragraph 2.1.2

TS Admissible minimum/maximum temperature
(C according to DIN EN 764-1)

V Volume in litres



centrotherm SiTec GmbH Terms of delivery no.: 08-901
Page 4 of 14

3 Processing of orders

3.1 Manufacturer
If there are several production sites, the manufacturer must name the intended site in the
offer. A change in production site needs to be approved by centrotherm SiTec in written
form. If the supplier assigns subcontractors for the production, he must proceed according
to section 3.2.

3.2 Subcontractor
If work shall be executed by any subcontractor, the supplier must keep supervision of the
product and make sure that the subcontractor receives all necessary information which is
important to fulfil his obligations according to PED.
Therefore the supplier must have assigned an explicit procedure (i.e. Quality
management system). He must ensure that the subcontractor is able to fulfil all quality
requirements. Sub-orders may only be forwarded, if the subcontractors are admitted by
centrotherm SiTec. All subcontractors must be named by the contractor in the offer and
must be approved by centrotherm SiTec in written form before placement of orders.
In case that the particular subcontractor is not admitted by centrotherm SiTec,
centrotherm SiTec will accomplish an on-site inspection at the subcontractor. The
resulting costs will be born by the contractor. The subcontractors chosen by the supplier
must also be named in the technical documentation for design assessment including
indication of scope of delivery and service. This specification does also oblige for the
subcontractor.

3.3 Monitoring of dates
centrotherm SiTec reserves its right to carry out monitoring of dates, building inspection
and inspection at the supplier and if necessary at its subcontractors according to the
existing manufacturing and material procurement. Therefore free access to all production
rooms and offices must be guaranteed after prior notice. If circumstances may be
recognised which may delay the date of delivery, the customer must be informed by
written form including detailed information about the reasons.

3.4 Correspondence / contact person
All questions (technical or commercial such as time of delivery, dispatch etc.) have to be
placed directly to the departments or persons named in the order. The centrotherm SiTec
order number must be indicated in each case.

3.5 Complete delivery
The delivery according to the order will be regarded as complete, if all necessary
documents arrived at centrotherm SiTec.

3.6 Acceptance
In each case, the final, contractual inspection takes place of receipt or after end of
installation at the production site at earliest.



centrotherm SiTec GmbH Terms of delivery no.: 08-901
Page 5 of 14

4 General


4.1
Plant components must comply to the state of the art and with all centrotherm SiTec
specifications regarding material, calculation, production, inspection and equipment.
Deviations must be agreed by centrotherm SiTec in written form.

4.2
In case that commitments in the applicable specifications for the strength of the unit
components (general stress and stability check) are not sufficient, only calculation
methods may be used, which are approved as state of the art. Stress analysis and
stability checks have to be provided to centrotherm SiTec on demand.





centrotherm SiTec GmbH Terms of delivery no.: 08-901
Page 6 of 14

5 Classification of fluids

5.1 Classification in groups
For consideration of material property, fluids are classified into group 1 and group 2.
The classification may be made via the danger criterion characteristics of each medium
(R-phrases) which can be seen in the respective safety data sheets.

Fluids
Danger attributes
R-phrases
Characteristic according to 67/548/EWG and adaptations
Group 1
(dangerous
medium)
explosive E R2, R3 (R1, R4, R5, R6, R16, R18, R19, R44)1)
highly flammable F+ R12
easily flammable F R11, R15, R17
flammable (if max.
allowable temperature TS
lies above flashpoint)
- Accurate inspection necessary
very toxic T+ R26, R27, R28, R26/27, R26/28, R26/27/28, R27/28,
R39/26, R39/27, R39/28, R39/26/27, R39/26/28,
R39/27/28, R39/26/27/28
toxic T R23, R24, R25, R23/24, R23/25, R23/24/25, R24/25,
R39/23, R39/24, R39/25, R39/23/24, R39/23/25,
R39/24/25, R39/23/24/25, R48/23, R48/24, R48/25,
R48/23/24, R48/23/25, R48/24/25, R48/23/24/25
oxidizing O R7, R8, R9
Group 2 all fluids which not
count into group 1
- -
1) For R-phrases in brackets, a special control of the classification in one fluid group is necessary


5.2 Classification according to condition for aggregation gas and fluid
5.2.1 Gases
This contains gases, liquefied gases, by pressure dissolved gases, vapours and those
fluids whose vapour pressure at the admissible maximal temperature TS lies above the
normal atmospheric pressure (1013 mbar) by more than 0.5 bar. Gases may contain
fluids or solid materials.
5.2.2 Fluids
This contains fluids, whose steam pressure at the admissible maximal temperature TS
lies above the normal atmospheric pressure (1013 mbar) by 0.5 bar at most. Fluids may
contain solid materials or gases according to their solubility (not by pressure dissolved
gases).

5.3 Instable gases
Instable are gases which may cause an exothermic reaction during storage or under
operation, caused by energy or catalytic impurity effects even under exclusion of
oxygen (currently instable classified gases see annex)



centrotherm SiTec GmbH Terms of delivery no.: 08-901
Page 7 of 14

6 Material selection and processing


In case that the material is presented in the technical specification, the
purchaser/consumer takes the responsibility for the stability of the used fluid. In this case,
a reference in the manual is necessary according to annex I, section 3.4 of PED. See also
AD 2000 data sheet HP 511, section 5.3.1, period 13.
The responsibility for special and professional processing of the material is with the
manufacturer.
Plates, forgings, flanges, pipes etc. needed for the production of the pressure devices
may only be purchased from manufacturers which are certified in the VdTV-data sheet
1253/1 to /4. Welding consumable materials may only be used of certified from VdTV.
Deviations are only permissible after written agreement and permission by centrotherm
SiTec.





centrotherm SiTec GmbH Terms of delivery no.: 08-901
Page 8 of 14

7 Surface treatment

All surfaces of unalloyed and low-alloyed steel components must be derusted and painted
with a priming coat if not indicated differently before assembling according to centrotherm
SiTec specification.
Stainless steel must be treated according to centrotherm SiTec specification, if not
indicated differently.
For all other materials, the respective centrotherm SiTec specifications are valid.



centrotherm SiTec GmbH Terms of delivery no.: 08-901
Page 9 of 14

8 Examinations

Assessments have to be accomplished completely and according to manufacturing
process. Exceeding demands of other applicable legislation and set of rules to this
specification have to be considered. In case that theres no test specification indicated in
the order, the test extent must be made in accordance to the AD 2000 data sheets.
In case of a final inspection at printing devices respectively plant components by
centrotherm SiTec-representatives at the producers facilities, they have to be prepared
accordingly (vertical installation, for functional inspection supply of connections etc.).
All fees, i.e. for draft examination, acceptance (compression test, final examination,
examination of the safety devices) and documentation must be shown and included in the
purchase order price.



centrotherm SiTec GmbH Terms of delivery no.: 08-901
Page 10 of 14

9 Cleanness

9.1 General requirements
All instruments and plant components must be well-swept, dry and free from visible oil
and grease adhesions.

9.2 Addition requirements free of oil and grease execution
This must be agreed in the order/specification separately.
9.2.1 General
- The product touched surface may neither contain oil and grease nor oxygen grease or
other impurities.
- Medium touched interior zones may not be blasted respectively retreated with
anticorrosive agents.
- Every tool and adjuvant which is used for production and/or cleaning must be completely
free from non-ferrous metal (i.e. revising tools, mandrels, welding materials etc.).
9.2.2 Cleanness
As cleaning agent, fully demineralized water by means of a hot water high-pressure
device with non-ferrous injectors at 90 to 95 degree centigrade or vapour must be used.
In case of hard adhesive contaminations it may be pre-cleaned by the use of adequate
agents. After cleaning, the medium touched surfaces (machines inner surfaces, sealing
surfaces etc.) may only be touched with oil- and grease free gloves.
9.2.3 Drying and evacuating
If N2 or compressed air is used for pre-drying, it must be considered, that gas does not
contain any oil respectively residential moisture. Subsequently, all medium touched rooms
must be evacuated by means of a vacuum pump (equipment design for vacuum [-1 bar]
necessary).
Note: Seals, which have been used during the hydrostatic test, must NOT be used any
more during the evacuation. If the temperature lies less than 15 degree centigrade during
the drying procedure, the vacuum drying must occur in a heated room. The equipment
temperature must also not lie less than 15 degree centigrade. When pre-drying by means
of a compressor, the air must be aspirated via an air filter to avoid contaminations on the
inner surface. During the drying process, the equipment may be heated lightly (no open
fire). The following steps must be kept during evacuation/drying:





centrotherm SiTec GmbH Terms of delivery no.: 08-901
Page 11 of 14


Complete emptying of the apparatuses after high-pressure cleaning (attention to
dead spaces and undercuts)
When closing the notches, material conform flanges have to be used (steel type
steel flange, stainless steel stainless steel and/or plated steel flange)
Flushing by means of N2 or compressed air (free from humidity and oil) for pre-
drying
Ambient air temperature and object temperature must be detected and
documented directly before and after evacuation as well as after operating life (i.e.
at tube plates on WT). Evacuation to the absolute pressure indicated in the table in
addiction to the object temperature.


Object
temperature C
(5) 1) (10) 1) 15 20 25 30 35 40
Evacuation
pressure mbar
(abs)
(4) (7) 12 18 27 37 51 69
1) Drying at machine temperature of less than 15 degree centigrade after acceptance
from centrotherm SiTec


Drying process may only be finished if pressure in closed, evacuated room does
not rise more than 2mbar (in case of switched off vacuum pump and closed in-
between valve).
Test of this stable condition by means of a manometer and documentation with test
chart
Immediate filling of the device with dry nitrogen without opening any flanges
N2 overpressure must be adjusted at 0.5 bar (however, PS at maximum)
Do not demount charging and back pressure valves as well as manometer for the
transportation to centrotherm SiTec.

The correct cleaning and drying procedure must be certified by the contractor and sent to
centrotherm SiTec before delivery. The following advice is necessary on the container
drawings as well as on the delivered devices:

ATTENTION!
Danger of suffocation Nitrogen atmosphere!
Container under pressure!

NOTE: The adherence of the requirements will be examined by centrotherm SiTec during
the reception control. Each cleaning examination will take place by means of a wipe test
with a lint-free, white drapery. The drapery must not show any colour changes after the
wipe test.



centrotherm SiTec GmbH Terms of delivery no.: 08-901
Page 12 of 14

10 Preparation for delivery, transportation

All pressure devices and equipment components must be well cleaned and well dried. For
un- and low-alloyed steel, blank surfaces as i.e. shaft ends, seal contact surfaces etc.
must be covered with an easy removable corrosion protection.

Seal contacts must be protected against damages during the transportation.
All outside notches must be sealed i.e. with protective caps according to DIN 3444, DIN
EN 12351 or with blanking flanges according to DIN EN 1092-1.
Railroad railway cars must be equipped with leaded shock indicators for the transportation
of shock-sensitive pressure devices and plant components as i.e. glass, vitreous enamel
or graphite. Shock indicators may only be moved by railroad agents. Shock-sensitive
components must be offloaded according to defaults of the supplier.

In case that the actual transport- respectively installation weight deviates from the weight
indicated in the drawing, this must be communicated to the purchaser as soon as possible
still before arrival of the pressure device / the plant component.









centrotherm SiTec GmbH Terms of delivery no.: 08-901
Page 13 of 14

Quoted Documents and Normative references

The following quoted documents are necessary for the use of this document. For dated
normative references, only the referred issues are valid. For undated references, the
latest version of the referred issue is valid (including all changes). See also: Further
centrotherm SiTec specifications and terms of delivery.


67/548/EWG: 1967-06-27 Guideline of the council from 1967-06-27 for the
adaptation of right and administrative regulations for
classification, packing and marking of dangerous
materials
97/23/EG: 1997-05-29 Guideline of the European Parliament and the council
from 1997-05-29 for the adaptation of legal rules
concerning pressure devices for all member states
AD 2000-Data sheet
HP 511:2001-01 Design Examination
DIN 3444 Protective caps for pipe fittings with welded and
threaded ends
DIN EN 764-1 Pressure equipment Terminology pressure
temperature, volume, nominal size
DIN EN 1092-1 Flanges and their joints Circular flanges for pipes,
valves, fittings and accessories, PN designated,
steel flanges
DIN EN 1333 Flanges and their joints pipe work components
Definition and selection of PN
DIN EN 12351 Industrial valves protective caps for valves with
flanges connections
DIN EN ISO 6708 Pipe work components definition and selection of DN
(Nominal size)
TRG 100: 1985-03 Pressure gases: general regulation for pressure gases
VDTV MB WERK 1253/1 List including producers
approved by technical inspection agency (German: TV)
VDTV MB WERK 1253/2 List including material agents
approved by technical inspection agency (German: TV)
VDTV MB WERK 1253/3 List including producers of flanges
approved by technical inspection agency
(German: TV)
by abandonment of an inspection document
VDTV MB WERK 1253/4 List including producers or agents of screws and nuts
approved by technical inspection agency
(German: TV)
by abandonment of an inspection document
centrotherm SiTec PS 08-004 Corrosion prevention by means of colour coating
centrotherm SiTec PS 08-008 Surface treatment of stainless austenitic steel



centrotherm SiTec GmbH Terms of delivery no.: 08-901
Page 14 of 14

Annex instable gases

Description according to IUPAC-rules Description according to TRG 100
Acetylen, gelst Acetylen
Bromtrifluorethen
Butadien-1,2 Butadien-1,2
Butadien-1,3 Butadien-1,3
Butin-1
Chlorcyan Chlorcyan
1-Chlor-2,2,2-trifluorethan Chlorfluorthan (R 133 a)
Chlortrifluorethen Chlortrifluorthylen (R 1113)
Cyanwasserstoff Cyanwasserstoff (Blausure)
Diboran
Dicyan Dicyan
1,1-Difluorethen 1,1-Difluorthylen (R 1132 a)
Distickstoffoxid Distickstoffoxid (Stickoxydul)
Ethylenoxid thylenoxid
Jodwasserstoff
Methylnitrit
Methylvinylether Vinylmethylther
Ozon
Propadien
Propin
Stibin
Stickstoffmonoxid Stickstoffoxid
Tetrafluorethen
Tetrafluorhydrazin
Vinylbromid Vinylbromid (R 1140B1)
Vinylchlorid (nicht stabilisiert) Vinylchlorid (R 1140) (nicht stabilisiert)
Vinylfluorid Vinylfluorid (R 1141)






Creation: Inspection: Approval: Revision: 0
date 2008-12-04 date 2009-01-26 date 2009-01-29
from MM from HR from RIE


Passing on as well as duplication of this document, utilization and report of its content is not permitted, if not expressly entitled
in written form. All rights reserved in case of patent or utility model registration as well as from this resulting in patent rights.
Offence obligate to compensation.
This document is property of centrotherm SiTec GmbH.

centrotherm SiTec GmbH Specification No.: 08-008
Page 1 of 10



Specification

Surface treatment
of stainless austenitic steel

No.: 08-008



Content Page
1 Application area .................................................................................. 2
2 Purposes ............................................................................................. 2
3 Different Treatments ........................................................................... 3
3.1 Brushing .............................................................................................. 3
3.2 Grinding............................................................................................... 3
3.3 Blasting ............................................................................................... 4
3.4 Pickling ................................................................................................ 5
3.4.1 General ............................................................................................... 5
3.4.2 Cleaning .............................................................................................. 5
3.4.3 Pickling as a Cleaning Method ............................................................ 5
3.4.3.1 Cleaning with Pickling Solution ........................................................... 5
3.4.3.2 Cleaning with Pickling Paste ............................................................... 5
3.4.4 Pickling as a Material Removal Method .............................................. 5
3.4.4.1 Material Removal with Pickling Solution .............................................. 5
3.4.4.2 Material Removal with Pickling Paste ................................................. 5
3.4.5 Follow-up treatment ............................................................................ 5
3.4.5.1 Rinsing ................................................................................................ 5
3.4.5.2 Neutralization ...................................................................................... 5
3.5 Anti-Corrosion Coating ........................................................................ 6
3.6 Special Methods .................................................................................. 6
3.6.1 Pressure Shot Blasting with Austenitic Blasting Agent ........................ 6
3.6.2 Blasting with Glass Shot for Compacting ............................................ 6
3.6.3 Electro polishing .................................................................................. 6
4 Selecting and Applying the Method ..................................................... 7
4.1 Basic surface Treatment Conditions ................................................... 7
4.2 Surface Outside (Atmosphere Side) ................................................. 8
4.3 Surface Inside (Medium Side) .......................................................... 8
5 Safety precautions .............................................................................. 9
6 Quoted Documents ........................................................................... 10

ANNEXURE02 TO DOC. NO. PS14333G0000PDSPA40009



centrotherm SiTec GmbH Specification No.: 08-008
Page 2 of 10

1 Application area

This specification applies to the treatment of all surfaces including the welding seam
ranges of stainless austenitic steel of material groups 6, 7 or 8 according to AD-data
sheet HP 0, board 1.
Typically used materials of these groups are i.e. the German material numbers
W-No.: 1.4541, 1.4401, 1.4571, 1.4404, 1.4539 and 1.4462.












2 Purposes

The stainless austenitic materials according to section 1 provide a smooth, close
passive coat to air, thereby they are not attacked by certain media or the
atmosphere, and they are chemically resistant.
During treatment of those materials i.e. by welding, reshaping, drilling, turning or
milling, the passive layer may be damaged or destroyed by scale, tempering colors,
welding cinder residue, scoring etc. Thus, the material looses its corrosion resistance
and begins to corrode. In order to reconstruct the corrosion resistance after the
treatment, the materials must be treated subsequently with one of the procedures as
described in section 4.




centrotherm SiTec GmbH Specification No.: 08-008
Page 3 of 10

3 Different Treatments

3.1 Brushing
Brushing is no methodical treatment for the purpose of this specification and may be
used for cleaning purposes only. For brushing, austenitic steel brushes are
permissible only. Austenitic steel wire brushes must not be used for cleaning of other
ferrous materials.

3.2 Grinding
Grinding disks or rotor fan grinders are normally used for grinding. The selected grain
size has to be adapted stepwise and in adequate form to the grit of the final cut and
the cleaning effect. If no superior requirements are appointed to the surface finish, the
surface must be completed with an averaged roughness depth of Rz 4m. This
roughness depth can usually be obtained by grinding with a granulation of 240 or finer.
It must be pointed out, that no added or blunt abrasives are used and the material
surface is not strongly warmed up. Temper colors are not permissible. The abrasives
my only be used for austenitic materials.
The surface must be cleaned after grinding.

3.3 Blasting
Blasting as surface treatment for the purpose of this specification is permissible only
if its followed subsequently by acid cleaning according to section 3.4.3. For vapour-
blasting, the following points must be considered:
- For blasting of austenitic materials, fe-free abrasives may be used only.
- Abrasives, blasting pressure, blasting time and distance between nozzle head and
surface material have to be adapted to the material in an appropriate way and if
necessary be determined by preliminary tests.
- Via blasting, a surface roughness of Ry5 ) < 30m must be kept.
- The blasting material may not be contaminated, i.e. when working with pressure
blast plants, a dressing plant must be present; when working according to the
injection principle, only abrasives in mint conditions may be used.
If the material is provided with a corrosion-protective coating after blasting, a surface
roughness Ry5 of at least 30m up to maximum 60m must be obtained in order to
enable a sufficient adhesion for the corrosion-protective coating.












1) The roughness value Ry5 corresponds to the mean peak to valley height Rz as per DIN 4768



centrotherm SiTec GmbH Specification No.: 08-008
Page 4 of 10

3.4 Pickling
3.4.1 General
- The mixture of the pickling solution must be adapted to the chemical composition of
the working material, the desired working temperature and the effect desired by the
contractor.
- Chloride containing solutions are permissible for gap-free constructions only.
- The bath temperature must not exceed 50 degrees. In general, ambient
temperature is sufficient. The pickling time depends on bath composition and
temperature and has to be extended only until the desired effect has been reached.
- Moving the work- piece or the bath promotes the pickling process.
- The pickling process must be monitored
3.4.2 Cleaning
Before pickling, all materials which prevent a constant wetting of the surface as for
example oil, fat, glue or color must be removed by an adequate procedure.
3.4.3 Pickling as a Cleaning Method
During pickling-cleaning, no appreciable material strip will be occurred ( 3m).
This procedure is usually used with a previous mechanical procedure.
3.4.3.1 Cleaning with Pickling Solution
The following weak pickling solutions can, for example, be used to clean material
W-No. 1.4541 or 1.4571:

a) 5 volume parts nitric acid (1.39 g/cm3 65 mass-%),
0.5 volume parts hydrofluoric acid (1.23 g/cm3 70 mass-%),
94.5 volume parts water

b) 20 volume parts nitric acid (1.18 g/cm3 37 mass-%),
3 volume parts hydrofluoric acid (1.39 g/cm3 65 mass-%),
77 volume parts water

3.4.3.2 Cleaning with Pickling Paste
The etching solutions indicated in section 3.4.3.1 can be prepared to a brushable
paste by using an adequate, hydrofluoric acid resistant thickener as i.e. barium
sulfate or aluminium oxide.
3.4.4 Pickling as a Material Removal Method
Pickling is to be carried out such that from 3 to 5m material is removed.



centrotherm SiTec GmbH Specification No.: 08-008
Page 5 of 10

3.4.4.1 Material Removal with Pickling Solution
The following pickling solutions can, for example, be used to remove materials
W-No. 1.4541 or 1.4571:

a) For W-No. 1.4541:
8 volume parts nitric acid (1.39 g/cm3 65 mass-%),
1.5 volume parts hydrofluoric acid (1.23 g/cm3 70 mass-%)
90.5 volume parts water
b) For W-No. 1.4571:
8 volume parts nitric acid (1.39 g/cm3 65 mass-%),
12 volume parts hydrofluoric (1.23 g/cm3 70 mass-%),
80 volume parts water

A pickling time of 30 minutes in the bath at room temperature is required in cases.

c) For W-No. 1.4541 or 1.4571:
50 volume parts nitric acid (1.18 g/cm3 37 mass-%),
10 volume parts hydrofluoric acid (1.39 g/cm3 65 mass-%),
40 volume parts water

The water used for the pickling solution must be drinking water (chlorine ion content
50ppm). If damages can be expected according to remaining chlorides (as for
example stress corrosion cracking), a chloride-free pickling solution has to be used
and prepared with demineralized water or clean condensate.
3.4.4.2 Material Removal with Pickling Paste
For the pickling with paste with acid mixtures according to section 3.4.4.1, for a
temperature of 20 degrees, an etching duration of 3 hours is necessary, in order to
clear away a surface layer from 3 to 5m. Lower temperatures require an extended
pickling time. According to the limited acid content in a paste, there will be no pickling
damages if the respective minimum pickling time is exceeded (i.e. appealing over
night).
3.4.5 Follow-up treatment
3.4.5.1 Rinsing
After etching, all parts must be cleaned with drinking water (chlorine ion content
50ppm) until no more acid can be determined at the etched parts. Neutrality has to
be proven by the use of indicator paper, if necessary.
For the support of the cleaning process, wire brushes may only be used if they are
consisting of austenitic material and if they are free from any impurities.
An additional passivation after cleaning is not necessary, since the desired passive
coating will be accumulated during cleaning and the effect of atmospheric oxygen






centrotherm SiTec GmbH Specification No.: 08-008
Page 6 of 10

Table 1 Anti-Corrosion Coating

Working temperature)

[ in degrees ]

Type of coating

Description of coating

Nominal
coat
thickness)
[ in m ]



up to 150


Base coat
1x

2-component epoxide resin-
iron/mica paint

60

Top coat
1x

2-component
Polyurethane top coat

60

150 up to 400

Painted coat
2x

silicone resin paint

2 x 50
1) Down to a temperature of -60 degrees, the choice of coating depends on the maximum
operating temperature.
Coatings at temperatures of < -60 C must be adjust ed with centrotherm SiTec.
2) Coating thickness to be guaranteed after drying

3.4.5.2 Neutralization
Form-difficult parts with areas difficult to access whereby pickling remains cannot be
removed completely by flushing must be neutralized in a neutralization bath of at
least pH 8 (i.e. drinking water with soda).
Subsequently, it will be flushed with drinking water again, according to section 3.4.5.1.
3.5 Anti-Corrosion Coating
Before putting on the coating, a surface roughness Ry5 of at least 30m up to 60m
must be present.
The anti-corrosion coating must be executed according to table 1.
3.6 Special Methods
3.6.1 Pressure Shot Blasting with Austenitic Blasting Agent
During ball pressure blasting, defined compressive stresses are brought into the
material surface. Thus, danger of stress cracking can be reduced. The method may
be used with the agreement of centrotherm SiTec.
3.6.2 Blasting with Glass Shot for Compacting
The points noted under section 3.3 must be noted when blasting with glass shot. If
the angle is kept close to 90when blasting with g lass shot, this induces compressive
residual tension into the material surface. The residual compressive stress cannot be
induced as precisely as with pressure shot blasting, but it does also reduce the
danger of stress cracking. The method may only be used with the agreement of
centrotherm SiTec.
3.6.3 Electro-polishing
If there are highest demands on the corrosion resistance, purity or surface
roughness, the materials have to be polished electrochemically. The method may
only be used with the agreement of centrotherm SiTec.





centrotherm SiTec GmbH Specification No.: 08-008
Page 7 of 10

4 Selecting and Applying the Method

The executed procedure can be chosen by the client after the respective range of
application. The choice may be supported by centrotherm SiTec, if necessary.
If there are no additional agreements made within an application or order, for the
internal and external surface treatment, one of the methods characterized with in
table 2 or 3 has to be chosen. If other procedures are necessary due to the range of
application, they must be agreed separately by the client.

Ordering example 1:
Surface treatment according to centrotherm SiTec VA 08-008
That is, the contractor can select a method characterized with for internal and
external surface treatment according to section 4.2 and 4.3.

Ordering example 2:
Surface treatment according to centrotherm SiTec VA 08-008, outside procedure O
inside procedure G
That is, the contractor doesnt need to accomplish a surface treatment on the outside
(the atmosphere side); on the inside (the medium side), the surface treatment must
be glass shot blasting with a subsequent etch-cleaning.

4.1 Basic Surface Treatment Conditions
The materials have been treated according to the state of the art appropriate
procedure and show no inadmissible material damages.
Inadmissible material damages are in example:
- deep scratches or rough stress marks or
- material oxidation as can occur if not enough inert gas protection is used when
welding or tacking.

Machined sealing surface must generally be pickled (material removal) prior to use.
This also applies to sealing surfaces that have been cleaned with a spatula or wire
brush (damage to the passivated layer).






centrotherm SiTec GmbH Specification No.: 08-008
Page 8 of 10

4.2 Surface Outside (Atmosphere Side)

Table 2

4.3 Surface Inside (Medium Side)

Table 3

Application area
in/at

Component

Process

Description
Treatment steps
according to chapter

Normal loading









Tubing parts


O

Surface treatment not necessary, if temper colors
up to color golden yellow are existent; otherwise
treatment like instrument


Instruments




S Grinding (Rz 4 m) 3.2
AB
Blasting 3.4 without 3.4.3

STRB
Blasting and pickling
(cleaning)
3.3 and 3.4 without 3.4.4
SRB
Grinding and pickling
(cleaning)
3.2 und 3.4 without 3.4.4

High loading (danger of
cavity corrosion)
Tubing parts /
instruments
AB
Pickling 3.4 without 3.4.3

High loading (danger of
stress cracking)
Instruments
G
Glass shot blasting and
pickling (cleaning)
3.6.2 and 3.4
without 3.4.4
D
Pressure shot blasting
and pickling (cleaning)
3.6.2 and 3.4
without 3.4.4

Application area
in/at

Component

Process

Description
Treatment steps
according to chapter

Normal industrial
atmosphere

Tubing parts/
instruments
O
Surface treatment not necessary
S Grinding (Rz 4 m) 3.2
AB
Pickling (material removal) 3.4 without 3.4.3
STRB
Blasting and pickling
(cleaning)
3.3 and 3.4 without 3.4.4
SRB
Grinding and pickling
(cleaning)
3.2 and 3.4 without 3.4.4

Industrial
atmosphere with
added chloride

Tubing parts /
instruments
K Blasting and anti-corrosive
coating
3.3 and 3.5
Insulated plant
components in
open air
Pickling and anti-corrosive
coating
3.4 and 3.5 without 3.4.3



centrotherm SiTec GmbH Specification No.: 08-008
Page 9 of 10

5 Safety precautions

All surface treatment methods may only be carried out by briefed and experienced
personnel, considering the appropriate safety requirements.
Particularly, the following instructions and data sheets must be regarded:

General
Threshold values of chemicals in the working place air TRSG 900
Biological maximum limits TRGS 903
List of carcinogenic and mutagenic substances as well
As substances impairing the fertility TRGS 905

Grinding
Polishing and brushing instruments VBG 49

Blasting
Blasting agents TRGS 503
Protective measures to be implemented when
degreasing and abrasive-blasting surfaces prior to
thermal spraying DVS 2307 part 1

Pickling
Electrolytic and chemical surface treatment;
electro deposition VBG 57
Dangerous chemical substances Data sheet BG-Chemie M051
Regulations on dangerous materials Federal Law Gazette I
dating 11
th
Feb. 1982 (ArbStoffV 1982) page 144 to 154
Data sheet Handling with health hazardous substances Data sheet BG-Chemie M502)
Data sheet Handling with nitric acid, nitrogen acids Data sheet BG-Chemie M014
Data sheet for working with hydrofluoric acids and
inorganic fluorides Data sheet BG-Chemie M0053)




centrotherm SiTec GmbH Specification No.: 08-008
Page 10 of 10

Quoted documents

AD HP 0 General principles of design, manufacture and associated tests
DIN 4768 Determination of roughness parameters by means of stylus
instruments, terms, measuring conditions
DVS 2307 T1 Protective measures when degreasing and abrasive-blasting
of surfaces prior to thermal spraying
M 005 Hydrofluoric acid and inorganic fluorides
M 014 nitric acid, nitrogen acids
M 050 Handling with health hazardous substances
TRGS 900 Threshold values of chemicals in the working place air
MAK- and TRK-values
TRGS 903 Biological maximum limits, BAT-values
TRGS 905 List of carcinogenic and mutagenic substances as well
as substances impairing the fertility
VBG 49 Polishing and brushing instruments
VBG 57 Electrolytic and chemical surface treatment; electro deposition
ZH 1/161 Hydrofluoric acid and inorganic fluorides
ZH 1/229 Irritative materials, versicant materials

Das könnte Ihnen auch gefallen