Sie sind auf Seite 1von 4

A rticle

Your Contractual Questions Answered

What Is A Quantum Meruit Claim?


By The Entrusty Group

Entrusty Group, a multi-displinary group of companies, of which, one of their specialisation is in project,
commercial and contractual management, has been running a regular contractual questions and answers
section for Master Builders members in the Master Builders Journal.

In this instalment of this series, Entrusty Group will provide the answer to another frequently asked
question above.

T
his is a topic where contracting been agreed or quantified, and cases, the contract payment terms
parties have an agreement or usually a claim being assessed of a reasonable remuneration or
when one party has performed in a ‘reasonable sum’, ‘reasonable sum will be implied by common
services and/or works but there has remuneration’, ‘fair market rates’, law. For example, additional
been no agreement on the price ‘fair commercial rates’ or on similar expenses by the Contractor due
or payment terms. Such situations terms. to a significant change in the
frequently occur in the construction quantity of the work which was
industry where the Contractor often An entitlement for quantum meruit supposed to be carried out and
commences the works on the basis claim is not applicable if there is paid, accordingly.
of a letter in intent or verbal or even an agreement between the parties
written instruction issued by the in the existing contract to pay for 2. Where the contract contains
Employer or S.O./Architect/Engineer/ the work done. However, there may an express agreement to pay
Project Director (depending on the be quantum meruit claims under reasonable sum or on similar
forms of construction contract used). the contract. This usually arises in ter ms. For example, var iation
In some cases, the Contractor is two circumstances, namely: rules of variation work of similar
required by the Employer or S.O./ character but not similar conditions
Architect/Engineer/Project Director 1. When the contract is silent to be valued as far as may be
to carry out additional works on an on how wor k done is to be reasonable with a fair adjustment/
existing contract as a variation to remunerated or paid. In such allowance for the difference in
the contract, however the existing
contract prices/rates do not cater
for the said variation works. Thus,
the Contractor will have to claim
on a fair and/or reasonable basis,
commonly k nown as quantum
meruit.

What is Quantum Meruit?

Before we discuss further on this


topic let us define what is a claim
on quantum meruit basis and under
what circumstance it is applicable.
The expression quantum meruit
basically means ‘the amount he
deserves’ or ‘what the job is worth’.
It is a claim for a payment for the
work executed where no price has Bridge

100

3rd Quarter 2007


A rticle

conditions or where the works is Standard Forms Of Contract bound to make compensation to the
dissimilar in character and conditions And Malaysia Contracts Act former in respect of, or to restore, the
to be valued as a fair market rate or 1950 thing so done or delivered.
price or a fair valuation.
Many standard construction contract Case Law
Claim for quantum meruit in restitution forms in Malaysia allow for the above
is usually presented as an alternative quantum meruit circumstances to The following case laws shed some
claim if indeed there is no contract. be claimed by the Contractor which light to this question as to what
It is a quasi-contractual claim under utilise the principle of ‘reasonableness’ circumstances a quantum meruit
which the claimant merely seeks with fair adjustment/allowance, fair claim is applicable.
to be compensated for an amount market rate or fair valuation. Whilst
representing the reasonable sum if the Employer is in default, the (a) W h e r e t h e c o n t r a c t i s
of the work which he has already Contractor can choose to claim silent on how work done is
completed. This may arise under the under loss and/or expense clauses remunerated or to be paid
following circumstances: 1 in the contract or bring legal action I n t h e c a s e o f Pa r k i n s o n v s
to recover his expenses and losses Commissioners of Works (1949) 2
● Where the parties proceed on the under the principle of quantum K.B. 632, the Contractor had agreed
mistaken basis that there is an meruit. Table 1 below indicates the under a contract to carr y out
enforceable contract, but there relevant clauses of the standard certain work on a cost-plus-profit
is no contract; forms of construction contract, where basis subject to the total profit
● One party requested for services quantum meruit may be applicable, recoverable limit. The Commissioners
from the other party which are when monetary claims arise. were entitled under the contract
not governed by any contract; to instruct work up to £5m, but
● Where the contract has been It is pertinent to note that under instructed work actually totalled
discharged by the operation of Section 71 of the Contracts Act 1950 up to £6.6m, thus exceeding the
the doctrine of frustration; provides for the following:- contract value. The Court of Appeal
● Where the contract has been found that the additional work was
repudiated by the Employer and Where a person lawfully does anything outside the contract and thus the
the Contractor choose to claim for for another person, or delivers Contractor was allowed to be paid
damages for breach of contract or anything to him, not intending to do on a quantum meruit basis, which is
quantum meruit in restitution for so gratuitously, and such other person beyond the total fixed profit under
the work performed. enjoys the benefit thereof, the latter is the contract.

Table 1 - Relevant provisions where quantum meruit claims may be applicable under the various Standards
Forms of Construction C Construction Contracts in Malaysia
Contract Clauses
Brief of Description of Relevent Contract Clauses PAM PAM JKR IEM CIDB
2006 1998 203A 1989 2000
1 Variation 11.0 11.0 25.0 24.0 29.0
2 Additional expenses or loss and/or expense caused by Variation 11.7 11.6 5(d) 5(d) & 31.1(h)
24(e)
3 Loss and expense 24.0 24.0 44 44 31
4 Suspention of work for non payment 24.3(m) 42.10

5 Termination/Determination by Contractor 26.0 26.0 52 45

6 Contractor to recover additional expenses or loss and/or damage 27.13 27.2(vi)


from Nominated Sub-Contractor
7 Fluctuation of Price 53 54

8 Arbitration 34.0 34.0 54 55 47


9 Governing Law 38.0 56 49

101

3rd Quarter 2007


A rticle

(b) Where the contract contains


an express agreement to pay
reasonable sum or in similar
terms
In Laserbore Ltd vs Morrison Biggs
Wall Ltd (1993) CILL 896, the learned
Judge in deciding the meaning
of the term ‘Fair and reasonable
payments for all works executed’,
considered that costs plus basis was
wrong in principle even though it
may sometimes produce the right
result. The learned Judge held that
in assessing quantum meruit claim
the appropriate approach was to
adopt general market rates or fair
commercial rates.

Highway
(c) Where the parties proceeded
on the mistaken basis that there
is an enforceable contract, but The decision in BSC was approved not constitute a binding contract
there is no contract in Herman Suerken Gmbh & Co KG at law but was only a record terms
In the case of British Steel Corporation v Selco (Shipyard) Pte Ltd (1991) 3 agreed by the parties as basis for
vs Cleveland Bridge & Engineering Co CLJ 2289 which the learned Judge a contract negotiation.
Ltd (1981) 24 BLR 94, where the Court summarised that the implication
held that two types of contract of a letter of intent ‘would be to As for the question of compensation
could arise following a letter of enable the Defendants to recover for work done prior to the dispute,
intent, first, an ‘executory’ contract on a quantum meruit for work done the learned Judge held that a
and secondly an ‘if’ contract. There pursuant to the direction.’3 claim on a quantum meruit basis
was no ‘executory’ contract (where for the preliminary works carried
each party has reciprocal obligations) In a Malaysian case, Ayer Itam Tin out on the site was successful but
since material terms remained in a Dredging Malaysia Berhad vs YC was subject to a maximum limit of
state of negotiation. There was also Chin Enterprise Sdn Bhd (1994) 2 RM300,000. 3
no ’if’ contract (where the letter of AMR 32:1631, the learned Judge
intent constituted a standing offer in deciding whether there was a (d) One par ty requests for
which would result in a contract if concluded contract between the services from the other party
acted upon) since work was being parties, dealt with both the nature where these were governed by
done pending a contract whose of letters of intent and quantum a contract
terms were still being negotiated. meruit. In case of Constain Civil Engineering
Of particular importance was the Ltd vs Zanen Dredging & Contracting
lack of agreement as to British He held that arrangement made Co (1997) 85 BLR 77, the instructions
Steel Corporation’s (BSC) liability ‘subject to contract’ or ‘subject given did not constitute authorized
for consequential loss and delay. to the preparation and approval variations of the subcontract works
BSC had commenced work in order of a formal contract’, or in similar because they required work to
to expedite per formance under terms, would mean that the parties be done outside the scope of
the anticipated contract. Because were still negotiating and did not the subcontract entitling the
the work was not referable to any intend to be bound until a formal Subcontractor to payment on a
contractual terms, Cleveland was contract was made. ‘Subject to quantum meruit basis.
obliged to pay a reasonable sum contract clause’ terms would not
for the work done. There was no prevent the formation of a contract (e) Where the contract has been
contract and could therefore be no in exceptional circumstances. In discharged by the operation of
contractual obligation to complete the learned Judge’s view, with the doctrine of frustration
the work within a reasonable time, the several essential matters still In case of BP Exploration Co (Libya)
meaning Cleveland’s counterclaim remaining to be settled between vs Hunt (No 2) (1982) 1 All ER 125,
for late delivery cannot succeed. 2 the parties, the letter of intent did where the Plaintiff was engaged

102

3rd Quarter 2007


A rticle

to develop an oil field on the ”benefited” from the services/works preferably in writing, the essential
Defendant’s land and was to executed. terms such as the scope of works,
be paid by oil from the wells. payment, time period, contractual
The learned Judge gave BP a In view of the above, it is obligations and other pertinent
sum of US$35m representing as adviseable that the party who terms. This is to avoid any costly
the compensation or ‘benefit’ requires the services/works to be and lengthy disputes between
received by the Defendant prior executed by another party on an the parties concern when it is
to the wells, which were already urgent basis should at least ensure referred to arbitration/litigation
commissioned but before BP that both parties have agreed subsequently.
could have received all the oil as
payment, were nationalised by the
Government of Libya. REFERENCES

(f) Where the contract has 1. Atkinson, Daniel, Quantum Meruit, Atkinson Law Articles, May 12,
been repudiated by the 2006.
Employer and the Contractor 2. Speechly Bircham, Construction Contracts and Payment in the Absence
choose to claim for damages of Formal Agreement, In-House Lawyer Magazine 2003, April.
for breach of contract or 3. B Marican, Pawancheek, Letter of Intent: Intending the Unintended?,
quantum meruit in restitution CLJ Articles, 1994.
for the work performed 4. Keenan, Denis, Smith & Keenan’s English Law, 12th Edition, Financial
In case of Renard Construction Ltd
Times, Pitman Publishing, 1998.
vs Minister of Public Works (1992)
5. May, Anthony, Williamson, Adrian, Uff, John, Keating on Building
26 NSWLR 234, the Court held
that a claim in quantum meruit Contracts, 6th Edition, London Sweet & Maxwell, 1995.
following a wrongful termination 6. Ong, H.T., Practical Construction Claims in Malaysia – One Day Intensive
should be quantified on reasonable Seminar/Workshop organised by Entrusty Management Sdn Bhd and
remuneration basis, not value of BK Burns & Ong Sdn Bhd, November 2, 2004.
the work basis. 7. Wallacc, I.N. Duncan, Hudson’s Building and Engineering Contracts,
11th Edition, London Sweet & Maxwell, 1995, Vol. 1.
CONCLUSION

Whether a quantum meruit claim


is derived under the contract or In the next issue of the MBAM journal the article will answer the
restitution or letter of intent, the question on ‘Can A Letter Of Intent Be Construed As An Enforceable
precise wording in the agreement Contract?’
or the specified obligations of
the parties are pertinent. If one
party acted on it in speculation The Entrusty Group includes Entrusty
that they are entitled for the Consultancy Sdn Bhd (formerly known
payment of the services/works as J.D. Kingsfield (M) Sdn Bhd), BK
executed in the absent express Burns & Ong Sdn Bhd (a member of the Asia wide group BK Asia Pacific),
agreement to payment and the Pro-Value Management, Proforce Management Services Sdn Bhd / Agensi
other party had benefited from Pekerjaan Proforce Sdn Bhd and International Master Trainers Sdn Bhd.
it, then the principle of quantum providing project, commercial and contractual management services, risk,
meruit which entitled the injured resources, quality and value management, recruitment consultancy services
party to a claim for payment on a and corporate training programmes to various industries, particularly in
reasonable sum for services/works construction and petrochemical, both locally and internationally.
executed shall apply as per Section
71 of the Contracts Act 1950. Entrusty Group provide 30 minutes of free consultancy (with prior
However, there are some pitfalls appointment) to MBAM members on their contractual questions. The
and uncertainties should the Group also provides both in-house and public seminars/workshops in its
matter be brought to the court, various areas of expertise. For further details, please visit website: www.
as it will need to consider whether entrusty.com. or contact HT Ong or Wing Ho at 22-1& 2 Jalan 2/109E, Desa
the services/works executed are Business Park, Taman Desa, 58100 Kuala Lumpur, Malaysia. Tel: 6(03)-7982
not gratuitous or one party has 2123 Fax: 6(03)-7982 3122 Email: enquiry@entrusty.com.my.

103

3rd Quarter 2007

Das könnte Ihnen auch gefallen