KBC ADVANCED TECHNOLOGIES, INC.

Final Report
Refinera de Cartagena
Modernization Project
Energy Anal ysis


Prepared for





RCSA
Cartagena, Colombia


Prepared by:
Ref No: 103020A

March 2008

KBC Advanced Technologies, Inc. 2007 All rights reserved


Proprietary Information
By accepting this document, the recipient confirms that all information contained herein will be kept
confidential, and this information will not be disclosed to third parties without the prior written agreement of
KBC Advanced Technologies, Inc.



KBC Advanced Technologies, Inc.
14701 St Mary's Lane
Suite 300
Houston, Texas 77079
USA


T +1 281 293 8200
F +1 281 293 8290

REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 3 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A

Table of Contents
1.0 Executive Summary.................................................................................. 5
1.1 Executive Summary Recommendations ......................................................6
2.0 Introduction and Objectives...................................................................... 7
3.0 Basis of the Study..................................................................................... 7
3.1 Energy Prices...............................................................................................7
3.2 Best Technology (BT) Energy Benchmarking..............................................8
4.0 Actual Refinery......................................................................................... 9
4.1 Energy Performance ....................................................................................9
4.2 Utility System..............................................................................................11
4.3 Cycle Efficiency and R-curve Analysis.......................................................12
5.0 Future Refinery Performance................................................................. 13
5.1 Utility Balances...........................................................................................13
5.2 Energy Performance ..................................................................................15
5.3 First quartile performance justification........................................................17
6.0 Preliminary Utility System....................................................................... 17
6.1 Key Issues..................................................................................................17
6.2 Equipment List............................................................................................20
6.3 Control Philosophy.....................................................................................20
6.4 Sparing Philosophy....................................................................................21
6.5 Interconnecting Philosophy........................................................................21
6.6 Normal Operation (all equipment available)...............................................21
6.7 Operation with largest generator down......................................................22
6.8 Operation with the two largest generators down........................................24
6.9 Cost Estimation..........................................................................................25
7.0 Additional Cases..................................................................................... 26
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 4 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
7.1 Minimum Capex Case................................................................................26
7.2 Power Export Case ....................................................................................28
7.3 Integration of Gas Turbine and Hydrogen Plant Case...............................29
7.4 Propane as Marginal Fuel Case.................................................................30
7.5 165 KBPSD Case.......................................................................................31
7.6 190 KBPSD Case.......................................................................................33
8.0 Conclusions ............................................................................................ 36

REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 5 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
Final Report
Refinera de Cartagena Modernization Project Energy
Anal ysis
1.0 Executi ve Summary
Refinera de Cartagena SA (RCSA) is evaluating a project to expand and modernize the Cartagena
Refinery. Acting as owners representative, KBC Advanced Technologies Inc. (KBC) defined a state-of-
the-art integrated fuels refinery configuration and estimated the capital expenditure. This work is the
basis for the information to licensors for unit designs.
Based on the 2012 configuration, KBC subsequently carried out an Energy Analysis to produce a
preliminary utility system design for the RCSA Modernization Project. KBC completed the analysis and
found that a 1
st
quartile energy performance is economically justified for the future system.
The configuration is suggested based on available information on process units steam, power and fuel
demands. While Schedule A figures were available in some cases, typical literature figures and
estimations from KBC database have been used for the other process units. The calculations should be
updated with data received from the licensors to further refine the quality of the configuration.
On the 150 KBPSD basis, the total power consumption is estimated to be 73.9 MW. Importantly, it is
assumed that sufficient natural gas (NG) will be available to meet the projected total demand of 57
MMSCFD.
The utility system features cogeneration consisting of four (4) frame gas turbines combined with two (2)
duct fired HRSG and two backpressure steam turbogenerators. The main equipment total installed cost
(TIC) is estimated to be 240 MMUSD.
The five existing STGs are scrapped, yielding a substantial capital expenditure avoidance (2.0-2.5
MMUSD per unit is needed to upgrade the machines).
The above system basis is sufficient for a case of operation of 190 KBPSD, using the existing CDU/
VDU and increased crude run. The downstream assets would be pushed to ~10% overdesign.
The system is highly reliable. During normal operation (all equipment available) and also when the
largest generator is out of service, it operates in island mode, with enough steam and power reserve
capacity to respond with no external support. This is required to achieve the 92% on line service factor
goal.
If the two largest generators are down, the system operates synchronized to the grid in power import
mode. In this case, the grid acts as backup. In this scenario, a load shedding program or investment in
additional power import capacity infrastructure would be needed.
This report summarizes the work carried out in the Energy Analysis.
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 6 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
1.1 Executi ve Summary Recommendations
KBC recommends the following equipment or equivalent for the ISBL:
Power system of the refinery (LLE):
Four (4) Frame Gas Turbines. Listed features as per General Electrics heavy duty MS5001
(although this is not a recommendation to purchase that particular equipment):
o Power output ~21.6 MW at Cartagena conditions per turbine
Two (2) Duct Fired HRSG - Maximum steam generation (with GTs at maximum) =520 klb/h
o 2 GT exhaust into 1 HRSG
o Duct fired to produce additional steam to meet the overall steam balance.
Two (2) Steam Turbo Generators
o Maximum power output =9.5 MW each
o Isentropic efficiency =65%
o Normal operating conditions:
Steam inlet at HPS (600 psig) =534 klb/h
Extraction at MPS (50 psig) =318 klb/h
Exhaust at LPS (150 psig) =216 klb/h
Fuel Balance:
The amount of natural gas import ranges from 51-57 MMSCFD depending upon crude rate and
operational severity. The accuracy of this number depends heavily on the licensor data, and operating
furnaces efficiencies. Therefore, the natural gas availability should be defined at 60 MMSCFD with
refining of this value as licensor data is provided.
Cooling Water:
The estimated cooling water load for the whole refinery is 120,000 GPM. This value encompasses the
existing refinery systems. Section 7.6 details the circulation rate per unit and can be used as a starting
point for new cooling water systems layout and usage.
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 7 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
2.0 Introducti on and Obj ecti ves
Ecopetrol and Glencore International AG (Glencore) are joint owners of the Cartagena refinery in
Colombia. Refinera de Cartagena Sociedad Annima (RCSA) has defined a project to modernize and
enlarge the distillation and conversion capacities at the Cartagena Refinery. KBC Advanced
Technologies, Inc (KBC) defined a configuration for the new 150 KBPSD refinery. The work completed
by KBC is the basis for the information to licensors for unit designs.
As part of this effort, KBC is also carrying out an Energy Analysis. After evaluating the current energy
performance and likely targets, the main objective of this portion of the work is to suggest a utility
system configuration for the RCSA Modernization Project, based on KBCs configuration. This energy
system must be reliable and energy efficient. An estimation of the main equipment total installed cost
(TIC) for the suggested design is also provided.
At this stage, limited information is available from the licensors. With KBCs estimations as the main
data source for utilities consumption, the configuration presented in this report can only be regarded as
a preliminary one.
3.0 Basi s of the Study
3.1 Energy Prices
The energy analysis is based on the 2012 refinery configuration defined by KBC in the Refinery
Modernization Project Detailed Modeling Phase Basis for Engineering Process Design report.

The marginal mechanisms and energy prices are key to assess the economics of the proposed
configurations. The prices used for the Energy Analysis are discussed below.

Power import. The average 2007 price was 150 COP/kWh (75 USD/MWh). Corrected for a 7% yearly
inflation, the 2012 price used for this study is 105.2 USD/MWh.

Power export. The estimated 2007 export price is 90 COP/kWh (45 USD/MWh). Corrected for a 7%
yearly inflation, the 2012 price used for this study is 63.1 USD/MWh.

Natural Gas (NG). The average 2007 price was 3.75 USD/MMBTU. Corrected for a 7% yearly inflation,
the 2012 price used for this study is 5.26 USD/MMBTU. The NG composition (% mol) is:

Methane CH4 97.94
Ethane C2H6 0.25
Propane C3H8 0.06
IsoButane iC4H10 0.03
n-Butane C4H10 0.01
IsoPentane iC5H12 0.01
n-Hexane C6H14 0.02
Nitrogen N2 1.46
Carbon Dioxide CO2 0.22
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 8 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A

Propane. Current price is 46.24 USD/bbl. Corrected for a 7% yearly inflation, the 2012 price used for
this study is 18.0 USD/MMBTU. A Low Heating Value (LHV) of 3.61 MMBTU/BBL is used for propane.

Current NG import is 14 MMSCFD, the supply line being close to the maximum capacity of 20
MMSCFD. It is assumed that a new 250 mile pipeline will be installed making enough NG available for
both fuel usage and hydrogen plant feed. However, there is some uncertainty this will happen and
additional NG gas price escalation could occur to cover capital recovery for the new pipeline. As a fall
back position (i.e. in the event NG is late in coming), an alternative to provide the fuel to the refinery
has to be studied. This study considers NG is the marginal fuel, but a propane as marginal fuel case
is also analyzed.

A note of caution must be made on the uncertainty in identifying the marginal fuel and the one
associated with fuel and power prices, as it will have a dramatic impact on the preferred utility system
configuration.

Typically, refineries marginal power is imported from the grid. KBC uses the Price Equivalent Efficiency
(PEE) concept to calculate the energy equivalent of power. The PEE is defined as:

Cost of marginal fuel ($/MWh)
PEE = ---------------------------------------------- * 100
Cost of marginal power ($/MWh)

For the prices described above, the PEE for NG is calculated as (5.26 x 3.41) / 105.2 =17%

The PEE represents the cycle efficiency of the marginal power (typical PEE is ~35%). In this case,
power is expensive relative to fuel. In other words, power generated on-site at efficiency higher than
17% will be economic for the refinery. Even inherently inefficient condensing cycles would be more
economic to the refinery than importing power at the given prices.

Other parameters used in the evaluation are:

Exchange rate =2000 COP/$
Operating period =8400 h/y
Ambient temperature =100F
3.2 Best Technology (BT) Energy Benchmarking
To assist in their energy conservation studies within refineries and petrochemical plants, KBC have
developed a specific methodology encapsulated in the Best Technology (BT) energy efficiency
standards and associated energy valuation methods. These concepts are briefly described below.

The BT standards have been developed by fundamental analysis and design studies on individual
process units and take into consideration key process parameters affecting energy consumption such
as feed quality, conversion and fractionation performance. Process units with an energy performance of
100% BT would be supported by a highly efficient steam and power system and present the following
energy efficiency features:

REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 9 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
Fired heater efficiency of 92%
All power generated internally at 80% cycle efficiency by using combination of backpressure
turbines and gas turbine generators
All rotating equipment operating at high efficiency
Preheat trains designed using Pinch technology methodology and featuring optimum approach
temperatures of 36F.
Optimized, energy-efficient process configurations

The Best Technology standards can be applied to individual process units or across a complete refinery
and have been used in all of KBCs energy surveys (over 150 to date).
4.0 Actual Refinery
4.1 Energy Performance
The following process units and throughputs are utilized to asses the energy performance
of the existing refinery



The total energy consumption is 1,220 MMBTU/h split into:
Power import =8 MMBTU/h (0.4 MW at 17% PEE)
Fuel Gas =869 MMBTU/h
Coke =343 MMBTU/h

The calculated Best Technology (BT) energy allowance is 572 MMBTU/h. By comparing
the actual and benchmark numbers, the BT index is 213%.

This figure is in line with reported Solomons Energy Intensity Index (EII). The two graphs
below show that this corresponds to a 4
th
quartile performance both in the global league
(i.e. against all the refineries studied by KBC) and also when compared only to facilities in
the Americas.

An increase in cycle efficiency to a best-in-class figure of 75% would improve the BT index
down to 177%, equivalent to a 2
nd
quartile performance.
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 10 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A

Current energy performance comparison against all sites studied by KBC



Current energy performance comparison against sites studied by KBC in the Americas
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 11 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
4.2 Utility System
The current utility system is defined as described in this section of then report after
discussion with RCSA.

Steam Balance. Based on Foster Wheeler study, the steam balance is defined as
depicted in the diagram below.



Power/Shaft Balance. The total demand of 22.5 MW is mainly provided by steam turbines
(drivers and power generators) with a small power import ensuring the refinery stays
synchronized to the grid, as per the following table.




Fuel Balance. In addition to the generated off-gases and out of the 869 MMBTU/h of total
fuel gas burnt, 524 MMBTU/h of NG are imported. This is 14 MMSCFD of NG.
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 12 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
Energy bill. As summarized in the below table, the energy operating cost for the study
prices is 24.1 MMUSD/y.


4.3 Cycl e Efficiency and R-curve Anal ysis
There are three distinctive cycles generating power/shaftwork in the refinery.
Backpressure Steam Turbines (BPST) with boiler cycle efficiency, assumed to be 85%
Condensing Steam Turbines (CTS) with low cycle efficiency, assumed to be 20%
Power import with a Price Equivalent Efficiency (PEE) of 17%.

Rearranging the power balance presented in the previous section in a Cycle Efficiency manner, the
average cycle efficiency is calculated to be 25%, as shown below.



The calculated cycle efficiency is very low compared to industry standards. The large generation in
condensing cycles is the main reason for this inefficiency. Condensing cycles are inherently inefficient
as most of the energy contained in the fuel burnt ends up rejected against cooling water and only a
small fraction (i.e. the 20% above) is recovered as useful power.

The 25% average cycle efficiency is plotted alongside the calculated 0.6 power-to-heat ratio in the
below R-curve, and it is represented by the actual dot.

The comparison of actual operation to the targets shows significant scope for cycle efficiency
improvement for constant power-to-heat ratio:
Target of 51% without gas turbines installation (solid red line)
Target of 76% with gas turbines installation (solid blue line)

REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 13 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A


The R-curve analysis reveals what the maximum achievable cycle efficiency is (76% for the
cogeneration case) while illustrates that the installation of gas turbines coupled with supplementary
fired waste heat boiler is probably the best route to become a pacesetter performer.

The potential for current cycle efficiency improvement through the installation of new backpressure
turbines is limited for existing steam levels due to the absence of letdowns.
5.0 Future Refinery Performance
5.1 Utility Balances
The estimated unit-by-unit power, fuel, steam and cooling water (CW) consumptions are summarized in
the table below. The essential totals are:
Power consumption =73.9 MWe
NG import =56.55 MMSCFD
Net process units steam consumption =195 klb/h
CW circulation =110,000 GPM (24,884 m3/h)

REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 14 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A












REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 15 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
5.2 Energy Performance
Translating the above balances into their equivalent MMBTU/h and including the utility system, the total
energy consumption is estimated, as detailed in the following table:

From the above table, the total energy consumption including all fuels, power and steam is estimated to
be 3,134MMBTU/h
The Best Technology (BT) allowance is 1,929 MMBTU/h, resulting in a BT index 163%. As shown in
the graphs below, this is a first quartile performance both in the Americas region and globally.
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 16 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A

Future energy performance comparison against all sites studied by KBC


Future energy performance comparison against sites studied by KBC in the Americas
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 17 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
5.3 First quartile performance j ustification
With a relatively cheap marginal fuel (NG) price, the question may arise as to whether a first quartile
energy performance is economically justified. Three different scenarios have been compared: first,
second and third quartile operation, as shown in the comparative table below. The methodology used
for the comparison is to select a representative BT for the quartile and attribute the difference in
performance to a change in cycle efficiency. To achieve the desired cycle efficiency, a utility system
configuration is selected that maintains a similar level of reliability.



To provide the refinery energy demands with a 3
rd
quartile energy performance (cycle efficiency of 25%,
similar to the actual performance) requires an estimated investment of 95 MMUSD through a
combination of new equipment and upgrades of existing STGs and results in an operating cost of 62
MMUSD.

To move from 3
rd
to 2
nd
quartile (52% cycle efficiency) requires an additional investment of 26 MMUSD.
Considering the operating savings, the simple Internal Rate of Return (IRR) is 35%.

Likewise, the jump from 2
nd
to 1
st
quartile (78% cycle efficiency) performance needs 27 MMUSD of
extra capex. The more efficient configuration reduces the operating cost by 9 MMUSD/y, resulting in a
simple Internal Rate of Return (IRR) of 33%.

As a conclusion, and with a typical cost of capital in the 10% - 12% range (to be confirmed by RCSA),
the calculated IRRs would justify the required investment to achieve a 1
st
quartile energy performance.
6.0 Preliminary Utilit y System
6.1 Key Issues
General
Need to design a reliable system, able to operate when largest steam or power generator fails
during normal operation (all equipment available).
Operation with the largest generator out of service (e.g. scheduled maintenance) needs to be
also studied.
This study is based on process units steam, power and fuel demands from various sources:
o Schedule A (hydrocracker, ULSD HTs, NHT, reformer, butamer)
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 18 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
o Typical figures from literature
o KBC database
The calculations should be revisited and fined-tuned as more Schedule A figures are received
from the licensors.
Different designs (e.g. hydrogen plant) can have a significant impact on estimated demands and,
in turn, this variability in demands can change the preferred configuration of the utility system

Power
A key decision is whether to operate in island mode (i.e. not connected to the grid) or connected
to grid. Many refineries operate connected to the grid on import mode, while low grid reliability is
the overriding justification for those operating in island.
Reliability at this end of the national grid is very low, as the main generators in Colombia are
hydroelectric plants remote from Cartagena. Furthermore, there is no obligation on the existing
power suppliers to guarantee reliability.
These considerations led to the consensus of the parties involved in the review meeting to
function in island mode during normal operation (i.e. all generators available). This is
required to achieve the 92% on line service factor goal.
When one of the largest generators is out of service (e.g. in scheduled maintenance), the
refinery operates synchronized to the grid in a minimum import mode, the grid acting as back-up.
The maximum power import with existing line is 10 MW.
Power reserve to react to unscheduled failure of the largest generator has to come from either
gas turbines or grid import. Steam turbines response is deemed sluggish and thus not reliable
enough.
Existing steam turbine generators TG-1/2/3/4/5 are old and need an estimated 2.0-2.5 MMUSD
investment each to bring them back to standards by replacing/upgrading/repairing stationary
parts. Also, maintenance/upgrading costs are high as the age of the machines means they no
longer are standard machines. This, alongside the low efficiency of condensing cycles, leads to
the consensus of the parties involved in the review meeting to scrap all five turbine
generators.
Cogeneration cycles consisting of Gas Turbines (GT) plus Heat Recovery Steam Generators
(HRSG) are needed to achieve the desired efficiency and reliability. There are two types of GT:
o Aero-derivative GT (e.g. MS5002E)
Low specific weight, streamlined shape, smaller footprint
Higher electric efficiency (40%), higher power/heat ratio
Higher maintenance costs (falls after long periods)
Higher investment cost ($ per kW)
o Heavy duty / frame GT (e.g. MS5001)
Robust unit for stationary duty and continuous operation
Lower efficiency (30-35%), lower power/heat ratio
Lower maintenance costs (maintains performance)
Lower specific investment
It is assumed that a 9MW turboexpander will be installed in the FCC unit.
It is assumed that no Power Recovery Turbine (PRT) in will be installed in the hydrocracker
Driver selection.
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 19 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
o It is assumed that FCCs Main Air Blower (MAB) will be motorized as part of the unit
revamp.
o It is assumed that FCCs Wet Gas Compressor (WGC) will remain driven by a
condensing steam turbine (CST) as it is a1999 turbine designed for 35 KBPSD and is in
good condition.
o The steam balance should be reviewed when more reliable vendor data is available to
review major driver selection (motor/turbine) from both a steam balance and an
operability/reliability standpoint.
o Unless specifically stated, electric motors will be the default drivers
o Backpressure Turbines (BPST) are a good option. In this analysis, they are equivalent to
the suggested new steam turbogenerator (STG)
o Condensing Turbines (CST) are inefficient and are not recommended unless there is an
unavoidably steam excess.

Steam
As in the actual refinery, the utility system will have three (3) refinery-wide steam headers:
o HPS at 600 psig (superheated at 715F)
o MPS at 150 psig
o LPS at 50 psig
There is an option to have a local VHPS (say 900 psig) to maximize power generation from
backpressure steam turbines. This may have significant implications on the quality of
demineralized water
Heat Recovery Steam Generators (HRSG) will be coupled with GT. There are three options:
o Unfired HRSG, generating steam from the hot turbine exhaust gases. It presents lower
efficiency and lower flexibility
o Duct firing HRSG, where additional fuel is added to a metallurgical temperature limit of
about 1500F. It is more efficient and generates about twice the amount of steam of an
unfired HRSG. This seems to be the best fit for the heat and power demands under
study
o Fully fired HRSG, equivalent to a package boiler where the exhaust gases are depleted
from oxygen to 2-3%). It generates about five (5) times the amount of steam of the
unfired HRSG. It is a flexible but expensive option and it is difficult to justify in this case,
as there is plenty of steam generation capacity already installed
The existing boilers are in good conditions, except for SG104. This would be the first candidate
to be scrapped

Fuel
Imported natural gas (NG) is the marginal fuel
All the process units off-gases are combined in a centralized fuel mix drum
The Gas Turbines (GTs) will burn NG. This premises may be revised under a fuel gas (FG)
excess situation
The HRSGs will burn refinery fuel gas (FG) from the centralized mix drum

Water
Boiler Feed Water (BFW) is currently provided at demineralized water quality (i.e. no soft water)
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 20 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
There are three existing 600 GPM (300 klb/h) demineralized water trains. Typical operation is 1
operating, 1 regenerating and 1 in standby
Out of the two existing deaerators, one is in good condition and will be kept, will the other will be
scrapped
A 60% condensate return is assumed in the future configuration. Current condensate recovery
appears too low and that no capital is included here to alleviate that
Current total raw water demand is approximately 2200 GPM. The line capacity is 2500 GPM
6.2 Equipment List
Gas Turbine 1 Frame GT. Listed features as per General Electrics heavy duty MS5001
(although this is not a recommendation to purchase that particular equipment):
o Power output =26.8 MW at ISO conditions, 21.6 MW at Cartagena conditions
o Heat rate =12,687 kJ /kWh
o Electric efficiency =28.4%
o Exhaust temperature =901 F
o Pressure ratio =10
Gas Turbine 2 same as Gas Turbine 1
Gas Turbine 3 same as Gas Turbine 1
Gas Turbine 4 same as Gas Turbine 1
Duct fired HRSG 1 - Maximum generation (GT at maximum) =520 klb/h of HPS
Duct fired HRSG 2 Same as Duct fired HRSG 1
STG 1
o Maximum power output =9.5 MW
o Isentropic efficiency =65%
o Normal operating conditions:
Steam inlet at HPS (600 psig) =534 klb/h
Extraction at MPS (50 psig) =318 klb/h
Exhaust at LPS (150 psig) =216 klb/h
STG 2 Same as STG 1
6.3 Control Philosophy
The system is designed to operate in island mode (i.e. not connected to the grid) during both normal
operation and when the largest generator is down for maintenance. This makes the system very robust
and reliable. If the second largest generator is also out of service, the system operates synchronized to
the grid, which provides the power backup within the constraints of the existing infrastructure.

REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 21 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
The three steam headers will be balanced as follows:
HPS (600 psig), balanced by the HRSG steam generation
MPS (50 psig), balanced with the STG extraction
LPS (150 psig) , balanced with the STG extraction
6.4 Sparing Philosophy
The goal is to operate with a N+1 boiler philosophy, where N boilers are operating and one (1) is down
for maintenance. The studied scenarios require a maximum of one boiler operating. This suggests that
3 of the existing boiler could be scrapped. SG104 is the first choice to be taken out of service.

Special situations like start-up and large steam generation units shutdown should be analyzed in more
detail before a final decision can be taken on the number of boiler to be scrapped.
6.5 Interconnecting Philosophy
With the same pressure levels, the system is an expansion of the current HPS and MPS network and
works interconnected to it. The LPS header is new and has no connections to the existing pipework.
6.6 Normal Operation (all equipment available)
Key items during normal operation are:
Operation in island mode
Equipment operating:
o GTs = 4x10.9 MW (51% of max.)
o HRSGs =2x194 klb/h
o STGs =2x8.7 MW
o Boilers =0x0 klb/h
Make-up Boiler Feed Water (BFW) =430 klb/h
Total BFW =1,217 klb/h
Power reserve
o Required =10.9 MW
o Actual =32.6 MW
Cycle efficiency =78%
NG (fuel) =25.5 MMSCFD
Energy operating cost =43.9 MMUSD/y (excludes NG raw material)


REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 22 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A


The demineralized water make-up requirement increases from current 142 klb/h to 430 klb/h. This
demand is above the existing demineralized water trains capacity (600 GPM or 300 klb/h each). There
are two options available to alleviate this:
Challenged current philosophy where out of the 3 trains, 1 is operating, 1 is regenerating and 1
is in standby.
Install a 4
th
train

The total Boiler Feed Water (BFW) demands jumps from current 510 klb/h to 1217 klb/h. Information on
the existing deaerators capacity is needed before a recommendation can be made on whether and how
much investment is needed on this area.
6.7 Operation with largest generator down
When a GT is down, the other three cogeneration sets increase their loads and the system and
operating philosophy remains essentially unchanged. One conventional boiler is started and operated
at minimum turndown to procure the required steam reserve. The system is just marginally less efficient
and more expensive to operate than during normal operation. The system reliability is not affected.

Operation in island mode
Equipment operating:
o GTs = 3x14.6 MW (67% of max.)
o HRSGs =2x177 klb/h
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 23 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
o STGs =2x8.7 MW
o Boilers =1x35 klb/h
Make-up Boiler Feed Water (BFW) =430 klb/h
Total BFW =1,217 klb/h
Power reserve
o Required =14.6 MW
o Actual =14.6 MW
Cycle efficiency =77%
NG (fuel) =25.8 MMSCFD
Energy operating cost =44.5 MMUSD/y (excludes NG raw material)







REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 24 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
6.8 Operation with the two largest generators down
When 2 GTs are down, the other two cogeneration sets maximize their loads. The operating philosophy
changes from island mode to synchronized, with the national grid acting as backup. One conventional
boiler is still operated at minimum turndown to ensure an adequate steam reserve. The system is just
marginally less efficient and more expensive to operate than during normal operation. The system
reliability decreases.

Operation synchronized, grid as power backup. Power import =0.5 MW
Equipment operating:
o GTs = 2x21.6 MW (100% of max.)
o HRSGs =2x177 klb/h
o STGs =2x8.7 MW
o Boilers =1x35 klb/h
Make-up Boiler Feed Water (BFW) =430 klb/h
Total BFW =1,217 klb/h
Power reserve provided by grid. Load shedding program would be required.
o Required =21.6 MW
o Actual =10.0 MW (max power import)
Cycle efficiency =76%
NG (fuel) =25.7 MMSCFD
Energy operating cost =44.7 MMUSD/y (excludes NG raw material)



REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 25 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A


6.9 Cost Esti mation
The main equipment installed cost (excluding FCCs turboexpander) is estimated to be close to 240
MMUSD, as detailed in the table below.



The cost estimation is based on preliminary General Electric (GE) quotes for equipment cost and an
installation factor of 2.5.

This level of investment ensures a reliable system which also has the flexibility to work under different
scenarios such as start-up, power export or 190 KBPSD case.
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 26 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
7.0 Additi onal Cases
7.1 Minimum Capex Case
To try and minimize the required capital investment, the case is studied where only three (3)
cogeneration sets are installed. The features listed below correspond to General Electric aeroderivative
MS5002E gas turbine.

Power output =32.0 MW at ISO conditions, 27.7 MW at Cartagena conditions
Heat rate =10,000 kJ /kWh
Electric efficiency =36.0%
Exhaust temperature =951 F
Pressure ratio =17

The GTs are coupled to duct fired HRSGs with a maximum generation capacity of 220 klb/h of HPS.

The same two STGs are installed (power output 9 MW, isentropic efficiency 65%).

During normal operation, with all installed equipment available, the key operating items are:
Operation in island mode
Equipment operating:
o GTs = 3x14.6 MW (53% of max.)
o HRSGs =3x117 klb/h
o STGs =2x8.7 MW
o Boilers =1x38 klb/h
Make-up Boiler Feed Water (BFW) =430 klb/h
Total BFW =1,217 klb/h
Power reserve
o Required =14.6 MW
o Actual =26.8 MW
Cycle efficiency =82%
NG (fuel) =24.1 MMSCFD
Energy operating cost =41.7 MMUSD/y (excludes NG raw material)





REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 27 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A

.

This less capital intensive scheme is also more economic to operate, in part due to the higher
power/heat ratio of the aeroderivative gas turbines. But reliability should be also factored in.

When the largest generator (GT plus associated HRSG) is out of service, the other two cogeneration
sets increase their loads (2 x 21.9 MW, 79% of max) while the other equipment operation remains
unchanged. The limited power reserve (6.4 MW vs. required 21.9 MW) makes island operation not
viable and the refinery would need to work connected to the grid. In short, the system efficiency and
operating cost remains low but the reliability is compromised.

If the second largest generator (GT plus associated HRSG) was also out of service, the remaining
cogeneration sets would maximize its operation. The lost power need to be purchased. The required
import power is 16.0 MW, above the existing maximum of 10 MW. Several options could help alleviate
this situation:

Power boost steam injection in GTs. It is estimated that approximately 0.1 MW of additional
power can be generated for each klb/h of injected steam. Therefore, 60 klb/h of steam would be
required. This may be feasible, but probably too tight on both GT injection and power import
limits.
Invest in additional power import capacity. Probably an expensive option.
Install condensing section in the new STGs. Under-utilized capex and lower efficiency during
normal operation as the condensing section need to be operated continuously at minimum flow.
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 28 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
Generate higher pressure steam in the HRSG to maximize the backpressure STG generation.
Additional 2.4 MW could be generated in the STG if the HRSG steam was at 900 psig and
840F. This is probably not enough potential to justify the added complexity (higher pressure
system, multiple, STG inlets, etc)

It is to note that this system would have a lot less flexibility to work under other scenarios like start-up or
190 KBPSD case.
7.2 Power Export Case
While oil refining is the core RCSA business, additional profit may be at hand by becoming a power
exporter. The scenario where the refinery operates in power export mode (as opposed to island mode),
selling the excess power is discussed in this section. Obviously, the economics will be heavily
dependant on the export price. The break-even power export price is calculated to be 63 COP/kWh
(todays price, scaled up for inflation).

It is understood the there are two possible power export modes:
Qualify as a power exporter (minimum requirement is 10 MW) and go through a daily bid
process to sell in the spot market. RCSA may find it difficult to compete as this market
mechanism seem to be best exploited by the low-cost hydroelectric plants, predominant in
Colombia.
Supply under a two-party contract to a dedicated customer. Ecopetrol-owned Propilco could be
a good candidate to exploit this option.

For the given prices, the PEE when power export is the marginal power is (5.26 x 3.41) / 63.1 =28%.
This means that if power can be generated on-site at a higher-than-PEE efficiency, it will be beneficial
to export.

A step-out case from the preliminary configuration is presented below. Normal operation at the highest
possible GT load within the steam balance constraints results in a potential form power export of 20.7
MW. There is still enough power reserve available to operate with the largest generator down while
keeping a similar export amount.

The economics summarized in the table below show that for given prices, the benefit would be
approximately 3.3 MMUSD/y. Importantly, this mode would add 4.7 MMSCFD to the total NG demand.



REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 29 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
As the power export comes from the higher load of already purchased equipment, the benefits would
come at no additional capital cost. If additional equipment needed to be installed to generate the export
power, the simple payback on large equipment TIC only is anticipated to be on the 10 years range.



7.3 Integration of Gas Turbine and Hydrogen Plant Case
To date, Technip and Air Liquide have installed at least six large SMRs integrated with cogeneration
units in Europe and the USA (The Large Hydrogen Plant Challenge, reprinted from Hydrocarbon
Engineering, J uly 2005), as illustrated in the below block flow diagram.

Given RCSAs hydrogen plant size, it is estimated that an exact match would be achieved through the
installation of a 33 MW Gas Turbine (~Frame 6). In addition, a 15 MW turbogenerator could expand
1500 psig steam to 600 psig. While the operating cost advantage is relatively small, one of the main
advantages would be the capital avoidance of the associated HRSG as the reformer furnace is used to
raise the steam from the hot GT exhaust gases.

The size of the exact match GT, significantly larger than the standard cogeneration sets discussed in
the previous sections, presents reliability problems (i.e. the largest generator would be larger now and
in turn, the power reserve would need to increase) on the power system. If the GT is sized
independently of the reformer (i.e. GT with similar size to the other cogeneration sets), this problem
would be alleviated but the benefits diluted.

REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 30 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
Integrated systems are typically supported by both a reliable power grid and a hydrogen network. None
of those is in place in RCSA, compromising the reliability of the system.



7.4 Propane as Margi nal Fuel Case
The NG supply line is close to maximum capacity for current import of 14 MMSCFD. This study
assumed that new infrastructure will be installed and sufficient NG will be available for both fuel usage
and hydrogen plant feed. In the event NG is not available for fuel usage, an alternative fuel has to be
burnt. The use of Propilcos propane as marginal fuel is analyzed in this section.

Propanes price is much higher than NG (18.0 vs. 5.26 USD/MMBTU). This will have a major impact on
the economics. For the given prices, the PEE when propane is the marginal fuel is (18.0 x 3.41) / 105.2
=58%. This means it is still beneficial to generate power on-site using high efficiency cycles (i.e. above
58% efficiency), but the incentive with respect to power import will be diminished. In essence, we go
from a situation where fuel is inexpensive relative to power to one in which fuel is expensive even
relative to fairly costly power.
In normal operation, the utility system uses 25.5 MMSCFD of NG as fuel, with two distinctive users:

Gas Turbines ~16.2 MMSCFD NG ~606 MMBTU/h ~4,000 BPSD propane
FG system makeup ~9.3 MMSCFD NG ~347 MMBTU/h ~2,300 BPSD propane

Reportedly, 2500 BPSD of propane are available from Propilco. These can be used for FG system
makeup, but there is no sufficient propane to be used in the GTs.

REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 31 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
The additional cost of using propane instead of NG exceeds 100 MMUSD per year, split as follows:

Gas Turbines ~65 MMUSD/y
FG system makeup ~37 MMUSD/y

The energy cost increases dramatically from 44 MMUSD/y to 146 MMUSD/y
7.5 165 KBPSD Case
From the estimated unit-by-unit power, fuel, steam and CW consumptions summarized below,
corresponding to the refinery processing 164 KBPSD, the main figures are:
Power consumption =75.4 MWe
NG import =48.6 MMSCFD
Net process units steam consumption =220 klb/h
CW circulation =107,000 GPM (24,292 m3/h)





REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 32 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
During normal operation, with all installed equipment available, the operation would be very similar to
the preliminary case, with the following key operating parameters:
Operation in island mode
Equipment operating:
o GTs = 4x11.3 MW (52% of max.)
o HRSGs =2x205 klb/h
o STGs =2x8.8 MW
o Boilers =0x0 klb/h
Make-up Boiler Feed Water (BFW) =430 klb/h
Total BFW =1,217 klb/h
Power reserve
o Required =11.3 MW
o Actual =31.3 MW
Cycle efficiency =79%
NG (fuel) =21.2 MMSCFD
Energy operating cost =36.9 MMUSD/y (excludes NG raw material)


REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 33 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A

The considerations for operation when the largest generator or the two largest generators are out of
service are analogous to the ones described in the preliminary case. The main equipment installed cost
would also remain unchanged.
7.6 190 KBPSD Case
The case where the old CDU2/VDU2 unit is operating is analyzed in this section. The estimated unit-by-
unit power, fuel, steam and CW consumptions can be found in the below table. The highlights are:
Power consumption =85.8 MWe
NG import =52.5 MMSCFD
Net process units steam consumption =254 klb/h
CW circulation =119,000 GPM (27,132 m3/h)

REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 34 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A


During normal operation (all installed equipment available), the key operating parameters are:
Operation in island mode
Equipment operating:
o GTs = 4x13.2 MW (61% of max.)
o HRSGs =2x232 klb/h
o STGs =2x10.1 MW
o Boilers =0x0 klb/h
Make-up Boiler Feed Water (BFW) =483 klb/h
Total BFW =1,366 klb/h
Power reserve
o Required =13.2 MW
o Actual =25.1 MW
Cycle efficiency =79%
NG (fuel) =23.4 MMSCFD
Energy operating cost =40.7 MMUSD/y (excludes NG raw material)
REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 35 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A



When the largest generator is out of service, the three remaining GTs can increase their load to 17.7
MW (82% of max). The power reserve (7.9 MW) is not enough to meet the reserve requirement (17.7
MW), making island operation unfeasible.

If the second largest generator is also down, the required power import would increase up to 9.8 MW,
close to the existing line maximum capacity of 10 MW.






REFINERA DE CARTAGENA MODERNIZATION PROJECT
KBC ADVANCED TECHNOLOGIES, INC. 36 RCSA CARTAGENA, COLOMBIA
MARCH 2008 CONFIDENTIAL REFERENCE NO 103020A
8.0 Concl usi ons
A preliminary utility system configuration has been suggested based on available information for
process units steam, power and fuel demands. Schedule A figures were available for some units
(hydrocracker, ULSD HTs, NHT, reformer, butamer) and typical figures from literature or from KBC
database have been used for the other process units. It is anticipated that the calculations should be
revisited and fined-tuned once more quality data is received from the licensors.

150 KBPSD 165 KBPSD 190 KBPSD
Power consumption 73.9 MWe 75.4 MWe 85.8 MWe
NG import 56.55 MMSCFD 48.6 MMSCFD 52.5 MMSCFD
Net steam consumption 195 klb/h 220 klb/h 254 klb/h
CW circulation 110,000 GPM 107,000 GPM 119,000 GPM

Four frame gas turbine (MS5001 parameters used, 26.8 MW ISO) and two duct fired HRSG are needed.
In addition, two 9.5 MW backpressure STGs would be installed. The estimated Capex (main equipment
installed cost only) is 240 MMUSD. The estimated Opex for given prices is 44 MMUSD/y.

The five existing STGs are scrapped, yielding an additional capital expenditure avoidance (2.0-2.5
MMUSD per unit is needed to upgrade the machines).

The system is highly reliable. During normal operation (all equipment available) and also when the
largest generator is out of service, it operates in island mode with enough steam and power reserve
capacity to respond with no external support.

If the two largest generators are down, it needs to be operate in import mode and synchronized to a
grid that acts as backup. In this scenario, a load shedding program or investment in additional power
import capacity infrastructure would be needed.

The utilities system design is likely to be a schedule-driven project, as the steam and power system
needs to be in place before the process units are. As a guideline, the estimated delivery time in
Colombia for a Gas Turbine (GT) is 18-20 months while for a package boilers (not needed in the
suggested design) is 24-30 months.

There are two main outstanding items:
Carbon footprint. There may be a possibility for RCSA to play a role in the carbon credits trading
through Clean Development Mechanism (CDM). As an example, en efficient steam and power
system in the current refinery saves approximately 100,000 t CO2/y. Assuming a CO2 cost of
10 USD/tCO2, this would be equivalent to 1.0 MMUSD/y
H2 plant design. Different designs can have a significant impact on the energy balances and, in
turn, on the utility system design.