11On the Design, Supervision and Construction of selected Chalala roads
1
Contents
1.0 Project Summary ....................................................................................................................... 2 2.0 Introduction ............................................................................................................................... 3 3.0 Progress of Works ..................................................................................................................... 4 3.1 General State of Progress ...................................................................................................... 4 3.2 Drainage ................................................................................................................................ 6 3.3 Problems Encountered .......................................................................................................... 6 3.4 Program of Works ................................................................................................................. 7 3.5 Quality Assurance ................................................................................................................. 7 4.0 Project Resources ...................................................................................................................... 8 4.1 Labour Returns...................................................................................................................... 8 4.2 Plant Returns ......................................................................................................................... 9 5.0 Project Financial Assessment ............................................................................................... 100 6.0 Conclusion ............................................................................................................................ 111 7.0 Photographic Report ......................................................................................................... 112
Progress Report No.11On the Design, Supervision and Construction of selected Chalala roads
2
1.0 Project Summary
Implementing Agency Road Development Agency Contract No. TB/ORD/011/08 Client The Government of the Republic of Zambia Paying Agency National Road Fund Agency Beneficiary The Government of the Republic of Zambia Contract location East of the Chilenje South suburb in the City of Lusaka Name of the Project Consulting services for the Design, Supervision, and Construction/Upgrading of selected Chalala Roads, Musi-O-Tunya Road extension, Part of Shantumbu Road and South of Chilenje South newly constructed road parallel to ZESCO pylons Length 15 .3 Km Main Contractor BCHOD ICU Supervising Engineers BCHOD and Partners Negotiated Contract value ZMK 36,896,223,626.00 Total variations Approved ZMK 12,649,733,154.97 New Contract Sum ZMK 49,545,956,781.25 Total Amount Claimed To Date ZMK 39,816,716,981.52 Date of award of the Contract 29 September 2008 Contract Start Date 9 October 2008 Project Delay due to Financial Constraints 24 months Payment Currency ZMK Construction Period 8 Months Contract Completion Date 15 th July 2011 Reporting Period November 2011
Progress Report No.11On the Design, Supervision and Construction of selected Chalala roads
3
2.0 Introduction
The Government of the Republic of Zambia through the Road Development Agency (RDA) intended to carry out the Design, Supervision and Construction/Upgrading of the selected Chalala Roads (6.8 km), Musi-O-Tunya Road extension (2.7 km), part of Shantumbu Road (3 km), and the newly constructed road parallel to Zesco pylons (2.7 km) south of Chilenje South, in Lusaka District to Bituminous Standard Class 1 based on Integrated Construction Unit (ICU) method of works, using funds approved in the Annual Work Plan (AWP) for 2008. Some of these funds would have to be carried over into the subsequent years.
In January 2011 the ICU was given confirmation that funds were now available for the project and that works should resume immediately. Work was initially slow to restart due to the time of year (rainy season) and availability of Contractors equipment.
This report is the eleventh of scheduled progress reports produced by BCHOD Consulting Engineers being the Supervision Engineers on this project, and covered the period August to October 2011.
Progress Report No.11On the Design, Supervision and Construction of selected Chalala roads
4
3.0 Progress of Works
3.1 General State of Progress
Up to the reporting period all layer works had been completed. Additionally there had been 9.1km of road surfaced, this partly consisted of approximately 1.9km of the extension of Mosi-O-Tunya (entire length U1), the road running parallel to the ZESCO pylons (U5) had been surfaced for approximately 1.0km, and part of Shantumbu road from Pemba road (U4), approximately 900m. The table below outlines the major asphalt surfacing work that had been carried out.
Table 1: Lengths of surfacing work carried out Road Length of surfacing required (km) Length surfacing done (km) Per centum done U1 1.94 1.94 100% U2 0.35 0.35 100% U3 0.11 0.11 100% U4 3.21 0.90 28.0% U5 1.80 0.95 52.8% U6 2.35 2.35 100% U7 2.03 0.80 39.4% U8 0.90 0.31 34.4% U9 0.24 0.24 100% U10 2.15 1.13 52.6%
The above tabulated work translated to an overall per centum length of 60% surfacing for the Project. Prime coat had also been applied on some of the remaining worked bases as follows: On U4, 400m by half width U5, 800m by full width U7, 900m by half width Progress Report No.11On the Design, Supervision and Construction of selected Chalala roads
5
The Revised Program of Works, Fig 1, shows the per centum achieved progress in relation to the planned program for some major activities of the Project.
Progress Report No.11On the Design, Supervision and Construction of selected Chalala roads
6
3.2 Drainage
There had not been much progress made on the drainage works as at reporting time. The Contractor had mainly focused on keeping the existing drains clear of obstructions and debris, and continuing with the lining of the drains along Mosi-O-Tunya (U1). The workmanship along this drain had not been of the required standard and the Contractor was instructed to repair sections and rework them, as shown in the photographic report. 3.3 Problems Encountered
The issue of constant traffic on the roads during construction was ongoing. The traffic was urged to use the deviations adjacent to the roads when available in order to try and stay out of the way of any construction vehicles. When roads needed to be crossed certain crossing points were established for vehicles to get from one side of the road to the other.
The Contractor used sign and flagmen to divert traffic from construction zones. The location of the current work areas however, did not allow for deviations due to land restraints, this also slowed the rate of construction down a great deal as the roads had to be worked in half widths so as to accommodate traffic.
Another issue that came up in the months leading up to the reporting period was the lack of a reliable supply of cement and bitumen from suppliers. Cement is required for the stabilisation of road base while bitumen functions as the adhesive between wearing course and base layer and also as the binding medium in the surfacing. This unfortunately caused the Contractor to fall behind schedule as the processing of base and application of asphalt wearing course could not be carried out.
Progress Report No.11On the Design, Supervision and Construction of selected Chalala roads
7
3.4 Program of Works
The hitherto administered Program of Works was as submitted at the end of January 2011 when the instruction to recommence was issued. However there were stoppages experienced in project activities due to unreliability of supply and uncertainties in availability of cement, diesel and bitumen. Variation to the Work had also been proposed in form of additional bellmouths. Hence the current Revised Program of Works, Fig 1. As at report time a total of 9.1 kilometres of roads had been surfaced out of a total of 15.3km, this representing approximately 60% of total project road length. The remainder of the Project roads had been constructed with pavement layers in readiness for priming and eventual surfacing. Project completion was set for December 2011. 3.5 Quality Assurance
All works are carried out under the supervision of the contractors Site Agent on site. The Engineer from BCHOD takes regular visits to site to ensure the contractor is working to the standards specified. The construction materials and road layer densities are being carried out by the contractors own laboratory. Every now and again tests are carried out by an independent laboratory in order to confirm the results submitted by the contractors laboratory as an additional form of quality assurance.
The Contractor has submitted compaction results that he has carried out on the Sub-base, and the stabilised base on some surfaced sections of project roads. In addition he has submitted the asphalt mix design used for the surfacing. Progress Report No.11On the Design, Supervision and Construction of selected Chalala roads
8
4.0 Project Resources
4.1 Labour Returns
The Contractor mobilised a single earthworks team to site in late January 2011. This team started working on the roads preparing the roads for various pavement layers. A drainage team joined them on site during the middle of March 2011. And the surfacing team arrived in June 2011. The Contractor had the following staff on site for the reporting period.
Table 2: Labour Item Description Number of 1 Site Agent 1 2 Foreman 1 3 Site Clerk 1 4 Operators 4 5 Drivers (These are hired so vary from day to day) 3 6 Bricklayers 6 7 General Workers 7 8 Guards 4
Progress Report No.11On the Design, Supervision and Construction of selected Chalala roads
9
4.2 Plant Returns
The Contractors plant that was mobilized to site is summarised in the table below.
Table 3: Plant On Site Item Description Make/Model Number of 1 Grader CAT 140G 1 2 Grader Komatsu 1 3 Pneumatic Roller Sakai 1 4 15,000 litre Water Bowser Benz 1 5 10,000 litre Water Bowser Leyland 1 6 Tractor Ford 1 7 2 ton truck Toyota 1 8 Water Pump - 2 9 Mechanical Broom - 1 10 Bitumen Distributor - 1
Progress Report No.11On the Design, Supervision and Construction of selected Chalala roads
10
5.0 Project Financial Assessment
The current Financial Status of the Project has changed from the previous report. There have been additional claims by the ICU team or payments made by the Client. The total claim for the works comes to ZMK 39,816,716,981.52 out of the total project sum of ZmK 49,545,956,781.25.
Chart showing expected expenditure versus actual.
The Table shows the amounts claimed to date on this project. Due to the erratic funding available for this project and consequent reduced project activity there were insignicant claims between April 2009 and January 2011. Subsequent Interim Payment Certificates were substantial as they included major surfacing works and all the earthworks that were done eventually.
0 10 20 30 40 50 60 1 2 3 4 5 6 7 8 24 25 26 27 28 29 30 31 32 Zmk Billions Month expected actual Progress Report No.11On the Design, Supervision and Construction of selected Chalala roads
11
6.0 Conclusion
The Contractor re-mobilised to site during the months of January and February 2011. All earthworks and layer works were completed as per specification.
In total 9.1km of road were surfaced out of the sanctioned 15.3km this representing approximately 60% of the project. The Project deadline of 15 th July 2011 had not been met due to factors outlined herein. The ICU Team was however endeavouring to seek and utilize all available possibilities of completing the Project at the earliest time and to the desired quality. The Contractor expected to complete the remaining works by December 2011, as per Revised Program Works, assuming a consistent supply of the key road construction materials: bitumen and cement.
All work carried out up to the reporting period had been done according to specification.
Progress Report No.11On the Design, Supervision and Construction of selected Chalala roads
12
7.0 Photographic Report
Material processing for base stabilisation Testing of stabilised road base
Road base with applied prime coat Application of asphaltic concrete surface
Asphalt being controlled by workmen and rolled into thickness
Progress Report No.11On the Design, Supervision and Construction of selected Chalala roads
13
A mechanical broom removing Primed half width on U7 deleterious material on U7 road base
Asphalt being rolled to thickness A surfaced half width
A section on U1 with completed A spot on U8 with electric poles requiring surfacing but poorly done drainage barriers