Design Phase:-
Detailed design engineering including proposed P&ID for approval.
Sequence of operation & control philosophy document for approval.
Agreement with client on critical design parameter and document revisions on approval.
Preliminaries:-
Preparation of site for installation works.
Offloading of new chillers (assumed site fork truck will be made available).
Skate chillers, PHE, pumps and materials into plantroom area.
Offload all room heaters into production area and installation onto hangers at high level.
Mechanical Works:-
Installation of new hot water distribution pipework from plantroom to the Production Area terminal units.
Each room heater fitted with isolation and regulating valves c/w binder test points.
Room heaters separated into 3 zones and modulating 2-port control valves fitted to each zone controlled from 3-off zone temperature sensors.
Installation of chilled water circuit pipework valves and fittings between chillers & PHE.
Installation of heating circuit CS pipework between chillers and primary circuit pumps.
Installation of heating circuit CS pipework between secondary variable flow distribution pumps.
Installation of well water SS pipework between local header and PHE.
Pressure testing of all circuits.
All new chilled and hot water pipework will be insulated on completion.
Electrical Works:-
Installation of new starter and control panel.
Installation of field power wiring to pumps and zone control valves.
Installation of field control wiring to chillers, pumps, control valves and zone sensors.
Provision of system PLC and system operating software and testing .
Commissioning:-
Set up chilled water and well water flow rates to chiller.
Set up heating water distribution and chiller flow rates.
Commission Secondary heating distribution pump speed controls.
Hand over heat pump units to manufacturers engineer for function testing and full commissioning.
Test & configure the overall heating control system.
Print Date: 15/09/2009 Page 2 of 3
Misc:-
Provision of comprehensive Construction Phase Health & Safety Plan in accordance with CDM regulations.
Provision of detailed project plan prior to commencement of works.
Production of detailed CAD drawings of proposed new piping systems.
Project Manager allocated to provide day to day running of the project through to completion.
Full-time site supervisor for the duration of installation works.
Operation & Maintenance manuals for the complete works complete with ‘as-built’ drawings, documentation and test certificates.
Training for site operators.
Qualifications:-
Design specifications to be Skyline standard.
The site works can be carried out with continuous access and during normal working hours.
The production area is clear from obstructions to allow use of mobile access platforms as required for overhead works, etc.
Room heaters can be suspended from existing steelwork using drop-rods.
Mains power supplies to chillers and panel by others (We can include once source location is advised).
Well water flow is constant and available at all times heating is required.
Skyline standard conditions of sale to apply.
Payment terms to 30 days from date of invoice. Milestone payments to be mutually agreed prior to commencement of works.
Payback Analysis:-
Based upon an estimated annual heating load of 2000 MW.hrs. (Assumes heat recovery from Air Compressor Air Blast Cooler can be utilised).
Annual electricity consumption for 1 no. heat pump = 250 MW.hrs. (28.25 Tonnes CO2)
Annual gas equivalent cost for heating @ £0.02/kW.hr cost = £40,000 p.a. (106 Tonnes CO2)
Annual electricity cost for heating @ £0.05/kW.hr cost = £12,500 p.a.
Net running cost saving per annum for heating = £27,500 p.a (68.75%), (77.8 Tonnes CO2).
Capital cost for equivalent gas-fired LPHW heating system would be in the order of £160,000.
Additional capital cost for heat-pump system with Air Compressor Heat Recovery is say £35,000.
Simple payback for heat pump system over gas-fired system would be £35,000/£27,500 = 15 MONTHS.
Further - Consider beneficial cooling effect on well water (Carbonation line chilling load reduction/benefit) this would apply as follows:-
‘Free-cooling’ effect on well water would amount to 750 MW.hrs.
Carbonation line is 10% of total flow rate, therefore take 75 MW.hrs.
Chiller running cost for provision of this cooling to carbonation line would be approx £1,250 p.a.
Therefore this would offset the total running cost of the heat pump giving an annual energy saving of £28,750 p.a.
Simple payback time for heat pump system over gas-fired system would then be £35,000/£28,750 = 14.6 MONTHS.