Description of Item Comments and Assumptions Estimate *

BASELINE CONFIGURATION

Wheelchair Accessibilty:
3-Stop Vertical Lift, Installed Cost 3-Stop vertical lift installed cost including building
modifications.
$ 54,000
Building Entrances, Doorways:
Powered Main Entrance Door Upgrade existing doors for electric powered
operation. Doors just meet minimum "clear
width" per building code.
$ 2,700
New Upper Level, Interior, Front and Rear Install fire rated doors per code requirements (30
minutes min).
$ 3,500
New Windows on Playground Side Four windows. Approx 32" wide x 48" tall.
Maintain same width to reduce installation cost.
$ 2,500
Heating, Ventilation and Air Conditioning:
2 Mini-Split Heat Pumps (Upper Level) 2 x 18,000 BTU for primary heating and A/C.
Installed cost.
Includes associated electrical work. Use existing
oil furnaces for backup on cold days. Do we
need to keep both furnaces?
$ 7,800
Fresh Air Ventilation System (Upper Level) Use existing ductwork (both levels) if possible to
save $$$.
$ 4,000
Washrooms, Construction and Plumbing Primary at foyer level, wheelchair accessible per
code. Smaller one on second floor.
$ 9,000
Electrical System, Wiring and Lighting Upgrades Per AVRL requirements. $ 3,000
Security System / Fire Alarm Details TBD. $ 2,500
New Furniture and Shelving Per AVRL requirements. Donated furniture could
lower costs.
$ 33,000
Exterior Signage Relocate existing sign on school grounds. $ 1,000
Exterior Renovations:
Siding - Removal and Disposal Asbestos material abatement. $ 5,500
New Siding TBD. Cost depends on type. Possible donation
of materials?
$ 18,000
Professional Services Architectural and Engineering consulting. $ 14,000


SUBTOTAL (Baseline Configuration): $160,500


OPTIONAL ITEMS
The "Nice to Have" Items


Heating, Ventilation and Air Conditioning:
2 Mini Split Heat Pumps (Lower Level) 2 x 12,000 BTU for primary heating and A/C.
Installed cost.
Includes associated electrical work and service
upgrades.
$ 6,400
Upgrade Electical Service and Panel to 200 A This may be a required item. TBD. $ 2,500
Enhanced Fire Rating:
Drywall on Walls Over existing wood pannelling. $ 5,000
Drywall on Ceiling Over existing ceiling tiles. $ 5,000
Additional New Signage TBD $ 2,000
Contingency Other Materials, Fees and Services, Etc. $ 10,000
Exterior Renovations:
Painting of Trimwork Material costs only. Assume free labour? $ 2,000
Landscaping Material costs only. Assume free labour? $ 2,500
Access via Playground For those who park at HMCC lot. $ 2,500


SUBTOTAL (Optional Items): $ 37,900
* Note: Materials and Labour, No HST


Save the Hantsport Public Library
(Scope of Work and Cost Estimates)