Beruflich Dokumente
Kultur Dokumente
, ,
- Dealing with the PV plant response requires modelling of
, ,
- Because associated responsibilities, involved specifications (P*, thermal
response, etc.) must be agreed with PV manufactures.
- Current specification practises:
- Guaranteed: P*, degradation rate in %/year
- Standard information: NOCT, Thermal coefficients
- Additional information: I-V graphics
, ,
modelling alternatives
1- Considering just the MPP
+ .
+ .
standard data sheet information (IEC 61215 and IEC 61646)
(a, b,c ) a=1, b=0, c=0
200
/
1000
(IEC 61215 and IEC 61646)
granting generality to published values
(1)
Commissioning tests
2- Considering the full I-V curve
Adjusting 5 parameters (ISC, VOC, RS, RP and m) to a given I-V curve is not straightforward
Module to module parameters variation is typically larger than MPP variation
3 Specific energy rating attempts
Kings model from Sandia Lab
Power matrix as defined at IEC 618532
(1) R. Kenny et al, Prog. Photovolt: Rs.Appl. (DOI: 10,1002/pip.2365 (2013)
Available literature warns about scarce benefits from complexity
Surprisingly, there doesnt seem to be a need for overly complicated modelling to
achieve this accuracy for most technologies
PERFORMANCE final brochure (EPIA, 2009)
A simplified version of the Kings model, using a single expression for the maximum,
power point and requiring just 6 empirical coefficients performs as well as the original
(Huld, T. 2011)
The authors feeling is that the complexity of the standard [ IEC 618532] is actually not
beneficial for an accurate energy prediction, as it requires data which is actually
normally not know and the generation of this.. seems to affect the overall agreement
more than it would be without this complicated step
(Jyotirmoy Roy, 2008)
Experimental comparison of different practical possibilities
- 6 PV arrays of different technologies (1.9 < P*(kW)<2.4) are connected to the grid
from 2011, at Navarra ( G
y
1900 kWh/m2; 2,6 < G
d
(kWh/m2)
< 7,6)
- P
DC
, G and T
C
(from Si-c reference PV modules ) are measured at 1 second rate and
recorded as 10 minutes averages.
- Considered models:
DATA SHEET ADDITIONAL EXPERIMENTS
Full I-V curve Full I-V curve
MPP, only MPP, and ref(1)
MPP, and
200
/
1000
MPP, and measurements
Weekly energy errors [(Modelled Experimental)/Experimental ], for the c-Si
PV array, weighted by the daily irradiation and expressed in %.
DATA SHEET ADDITIONAL EXPERIMENTS
Full I-V MPP
MPP
,
200
Full I-V
MPP
, ref (1)
MPP
, meas.
W1 0.4 1.85 2.67 -0.08 2.15 1.41
W2 -1.69 0.84 1.81 -0.79 1.12 0.28
W3 -1.78 0.97 2.03 -0.8 1.26 0.32
W4 3.95 1.89 3.79 -0.64 2.93 1.17
Year 2.11 1.50 2.64 -0,83 1.86 0.85
1.42 1.27 1.29 1.07 0.9 0.97
- P
REAL
* 1% larger than P
NOMINAL
*
- Selected weeks are centred on the equinox (W1 and W3), on the summer solstice
(W2) and on the winter solstice (W4)
An MPP model considering just the power temperature coefficient given at
the data sheet explains up to 97% of the observed variability.
Considering also the efficiency variation with irradiance reduces uncertainty
by about 1%
Yearly energy errors at 12 different commercial Spanish PV plants
- G and TC given by reference PV modules, MPP model with and
200
/
1000
- P* and
INVERTER
values obtained at Commissioning tests
Nominal power
(MW)
Real yearly Yield
(kWh/kW)
Modelled yearly
yield (kWh/kW)
Error (%)
2 2038 2067 1.4
2.16 2056 2095 1.9
2.95 2050 2096 2.2
2 2194 2163 -1.4
1.5 2074 2032 -2.1
1.4 1561 1597 2.3
2.03 2142 2140 -0.1
11.2 2016 2038 1.1
2.1 2204 2198 -0.3
1.9 2320 2279 -1.8
9.7 2108 2111 0.1
25.3 1594 1616 1.4
Daily energy errors at 45.6 kW Amaraleja PV plant
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8
-5
0
5
10
15
20
K
Td
T
h
e
o
r
e
t
i
c
a
l
-
M
e
a
s
u
r
e
d
(
%
)
-6 -4.5 -3 -1.5 0 1.5 3 4.5 6 7.5 9
0
5
10
15
20
25
30
Theoretical-Measured (%)
F
r
e
q
u
e
n
c
y
(
%
)
Mean: 1.3 %
STD: 1.9 %
- G and TC given by 9 reference PV modules, MPP model with
- P* and
INVERTER
values first obtained at Commissioning tests and
periodically reviewed
Commissioning testing: Current state of art - 1
- The simplest possibility rely on the Performance Ratio concept
- Acceptation
,
.PR
GUARANTEED
. (or PR PR
GUARANTEED
)
Given by the energy meter Specified at the contract (80%)
Nominal power Given by the in-plane solar radiation meter
- PR calculation requires only G records
- Because it includes time-dependent unavoidable losses, the mere PR is generally
not adequate for sub-year periods (days, weeks, months ).
Weekly PR evolution along the year
0,850
0,900
0,950
1,000
1,050
1,100
1,150
0 10 20 30 40 50 60
PR
DC
PR
The weekly PR varies up to 10% along the year, and up to 5 % along a
same month.
c-Si PV array, Navarra (Spain), 2011
Commissioning testing: Current state of art - 2
- Time-dependent unavoidable energy loses are removed at the Performance Ratio at
Standard Test Conditions concept:
(1
- E means energy loses and I extends to all unavoidable phenomena:
- Thermal (due to T
C
T
C
* )
- Efficiency variation with irradiance
- Anomalies: Shading, inverter saturation, PV plant disconnections, etc.
- PR
STC
calculation requires (additional to G ) T
C
records .and modelling.
- PV reference modules are recommended to minimize uncertainty
- Acceptation PR
STC
along T PR
STC, GUARANTEED
Weekly PR and PR
STC
evolution along the year - 1
0,850
0,900
0,950
1,000
1,050
1,100
1,150
0 10 20 30 40 50 60
PR
PRSTC
PR
PR
STC
Commissioning testing: Advances procedures
- Not only energy production but also PV plant characterization is addressed
G
TC
PDC PAC
P
REAL
* = P
NOMINAL
* . (1-F
G
);
INV, REAL
=
INV, NOMINAL
.(1-F
INV
- Highly desirable for further careful operation surveillance
- PV plant in-field characterization requires G, T
C
, P
DC
and P
AC
recordsand modelling
- PV reference modules and accurate wattmeters are recommended to minimize
uncertainty
PV reference modules and accurate wattmeters
In-field testing: AC power response
21
P
AC,EXP
P
DC,EXP
G, T
C
0
20
40
60
80
100
120
140
0 200 400 600 800 1.000 1.200
G
ef
(W/m
2
)
P
D
C
[
G
e
f
,
2
5
C
]
(
k
W
)
P
DC
= 0,1087 G
ef
R
2
= 1
In-field testing: STC power of the PV generator
| |
( ) | |
*
C C
DC
ef
DC
1
C 25 ,
T T
P
G P
+
=
P
AC,EXP
P
DC,EXP
G, T
C
,EXP
Mean
I
SC
*
[A] 1240.0 6.4
V
OC
*
[V] 862.3 5.1
I
M
*
[A] 1114.6 4.2
V
M
*
[V] 703.4 10.6
P
M, IEC-60891
*
[W] 784044 11067
FF
*
0.733 0.003
P
M,
*
[W] 742728 4894
In-field testing: efficiency of inverters
0
10
20
30
40
50
60
70
80
90
100
0,0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8 0,9 1,0
p
ac
(
%
)
Inversor A
Inversor B
Inversor C
Modelo
Fabricante
q
P
P
AC,EXP
P
DC,EXP
G, T
C
Dealing with hot-spots - 1
Hot-spots threaten PV module lifetime and reduce operation voltage
T
HS
5
o
C
V
OP
= 29.5 V
T
HS
17.4
o
C
V
OP
= 26.3 V
T
HS
14.3
o
C; T
HS
11.8
o
C
V
OP
= 22.6 V
Dealing with hot-spots - 2
Proposal for contracts:
- T
HS
20
o
C PV module rejection
- 10
o
C T
HS
< 20
o
C and V > 20%
CONCLUSIONS
- c-SI PV array response is properly described by a simple model considering
just the maximum power point and the power temperature coefficient
- The power temperature coefficient must be included at the guarantees
provided by the PV module manufacturers
- In-field commissioning testing must preferably deal with PR
STC
(over the
mere PR). That requires measuring G and T
C
and modelling unavoidable
loses
- Commissioning testing can also include the characterization of the
effective behaviour of the PV plant. That requires measuring G, T
C
, P
DC
and
P
AC.
- Reference PV modules are preferred for measuring, both, G and T
C
- Proposed rejection criteria for PV module with hot-spots:
- Temperature differences larger than 20
o
C
- Temperature differences between 10
o
C and 20
o
C, and voltage
operation loses larger than 20%