TEST OPIS

Cold Test
Uzorak 1
IEC Publication 60068-2-1
Temperature: 25C 3C, Duration: 16 hours
initial measurement of insulation resistance
equipment not operating during conditioning and testing except for functional
test
functional test during the last hour at the test temperature
insulation resistance measurement and the functional test after recovery
Heat Test
Uzorak 1
IEC Publication 60068-2-2
Temperature: 70C 2C, <50% Humidity, Duration: 16 hours
equipment operating during conditioning and testing
functional test during the last hour at the test temperature
Cold Test
Uzorak 2
IEC Publication 60068-2-1
Temperature: 25C 3C, Duration: 16 hours
initial measurement of insulation resistance
equipment not operating during conditioning and testing except for functional
test
functional test during the last hour at the test temperature
insulation resistance measurement and the functional test after recovery
Heat Test
Uzorak 2
IEC Publication 60068-2-2
Temperature: 70C 2C, <50% Humidity, Duration: 16 hours
equipment operating during conditioning and testing
functional test during the last hour at the test temperature
Dump Heat Test
Uzorak 1
IEC Publication 60068- 2-30 Test Db
Temperature: 55C 2C, Humidity: 97% +/-3%, Duration: 2 cycles (12 + 12
hours) -> Total 48hours
measurement of insulation resistance before test
equipment operating during the complete first cycle and switched off during
second cycle except for functional test
functional test during the first 2 hours of the first cycle at the test temperature
and during the last 2 hours of the second cycle at the test temperature
recovery at standard atmosphere conditions
insulation resistance measurements and performance test
Dump Heat Test
Uzorak 2
IEC Publication 60068- 2-30 Test Db
Temperature: 55C 2C, Humidity: 97% +/-3%, Duration: 2 cycles (12 + 12
hours) -> Total 48hours
measurement of insulation resistance before test
equipment operating during the complete first cycle and switched off during
second cycle except for functional test
functional test during the first 2 hours of the first cycle at the test temperature
and during the last 2 hours of the second cycle at the test temperature
recovery at standard atmosphere conditions
insulation resistance measurements and performance test
Insulation resistance
Test voltage (2 x Un for Un 65 V) = 60V
Minimum insulation resistance: Before 10 M, After 1 M
insulation resistance test is to be carried out before and after: damp heat test,
cold test
between all phases and earth, and where appropriate between the phases
Note: Certain components, e. g. for EMC protection, may be required to be
disconnected for this test
KORACI
1. Utorak do 16 sati: Insulation Test
2. Utorak u 16:00 startati Cold Test
3. Srijeda 7:00 - 8:00 (zadnji sat) funkcionalni test
4. Insulation test (na sobnoj temp.)
5. Funkcionalni test (na sobnoj temp.)
1. Srijeda u 16:00 startati Heat Test
2. etvrtak 7:00 - 8:00 (zadnji sat) napraviti funkcionalni test
1. Do 16 sati: Insulation Test
2. etvrtak u 16:00 startati Cold Test
3. Petak 7:00 - 8:00 (zadnji sat) funkcionalni test
4. Insulation test (na sobnoj temp.)
5. Funkcionalni test (na sobnoj temp.)
1. Petak u 16:00 startati Heat Test
2. Subota 7:00 - 8:00 (zadnji sat) funkcionalni test
1. !! U petak napraviti Insulation test na uzorku 1 !!!
2. Subota 11:00 startati Dump Heat Test
3. 13:00 Funkcionalni test (na 55C, prva dva sata prvog ciklusa)
4. Ponedjeljak 7:00 Funkcionalni test (na 55C, prva dva sata prvog
ciklusa)
1. !! Insulation test na uzorku 2 !!!
2. Ponedjeljak 08:00 startati Dump Heat Test
3. 10:00 Funkcionalni test (na 55C, prva dva sata prvog ciklusa)
4. Utorak 18:00 Funkcionalni test (na 55C, prva dva sata prvog ciklusa)
5. Srijeda 08:00 Insulation Test
6. Functional test