Gulf Smelters Large Potlines supplied by large high efficiency
CCGT power plants Risks and Benefits of a Grid Connection Page No.1 Heading 1 Heading 2 Heading 3 2 lines Heading 4 Heading 5
CCGT Using Large F Class GT Units - Benefits
Low Capex / kW Installed typically US$650 US$700 per kW in the Gulf. High Efficiency - typically 55% (LHV basis) above ~90% load and reduced fuel cost. Well proven technology. Low Emissions NOx ~ 15 - 25 ppmv (30 - 50 mg/M 3 ) CO ~ 25 ppmv. Short Construction Schedule, typically 30 -36 months for 4 GT Unit CCGT Plant. Page No.2 Heading 1 Heading 2 Heading 3 2 lines Heading 4 Heading 5
Gulf Aluminium Smelter Potline Size Growth
Page No.3 2005 - ALBA Potline 5 1x 336 pots 505 MW 2009 - Sohar Aluminium 1 x 360 pots 560 MW 2011 - Qatalum 2 x 352 pots 2 x 500 MW 2011 - Emal 1 2 x 378 pots 2 x 600 MW 2015 Sohar Aluminium 1 x 460 pots > 800 MW MW values shown are for the potline power only Heading 1 Heading 2 Heading 3 2 lines Heading 4 Heading 5
Matching the Power Plant to the Smelter
Page No.4 F Class 50 Hz GTs have ISO ratings (15 Deg C &1013 mbara) between 250 - 280 MW with typical Gulf Summer ratings (45 Deg C & 1000 mbara) between 210 - 235 MW. In CCGT operation each GT will produce an additional 50% output from HRSG that supplies a steam turbine (ST). F Class GTs therefore effectively produce 315 350 MW in CCGT operation in a Gulf Summer. To allow for maintenance, a minimum of N+1 GT Units must be installed, where N is the number of GT Units operating to meet the Smelter power demand. To minimise capital cost, no more than N+1 GT Units should be installed. To achieve high efficiency the GTs should operate at ! 90% power output. Therefore, for an assumed Smelter power demand of 900 MW, a minimum of four (4) F Class GTs must be installed. Heading 1 Heading 2 Heading 3 2 lines Heading 4 Heading 5 E Class F Class No of GT Units Installed 6 / 7 4 No of GT Units Running to Supply Smelter 5 / 6 3 LHV Efficiency 48% 55% Annual Fuel Consumption MMBtu 54.4 million 47.5 million Annual Fuel Cost @ US$ 1.5 /MMBtu $81.6 million $71.2 million Annual NOx Emissions - tonnes 3700 - 4100 2800 Capital Cost - US$ millions $835/$920m $850/$940m
Comparison of CCGT Plant Using F and E Class GT Units to supply an assumed 900 MW Smelter Load
Reliability & Security of Smelter Power Supply In House Power Generation Page No.6 Aluminium Smelters need a very secure and reliable power supply. In house power generation alone cannot meet this requirement unless adequate standby generation is installed. A single standby GT is not sufficient see table below. ____________________________________________________________ Assumed GT Availability 93%, Unavailability 7% No of GTs Installed 7 6 5 4 No of GTs operating to meet 6 5 4 3 Smelter Power Demand Reliability of Power Supply 91.9% 93.9% 95.8% 97.3% _____________________________________________________________
Reliability & Security of Smelter Power Supply Grid Connection
Page No.7 Connection to the local HV Electrical Grid provides standby generation capacity and improves the reliability and security of the smelter power supply. Capacity of Grid Inter-connector should at least match the output of 1 GT and its associated ST this achieves a 99.8% reliable power supply with the a 3 out of 4 GT operating scenario. Two (2) Grid inter-connectors increase the reliability of the power supply to 99.99% (< 1 hour unavailability of full power supply per year) Capital cost of a Grid Connection is much lower than the cost of installing additional GT Unit(s)
Page No.8 Provides start-up power for the Smelter & its power plant. Provides power during maintenance and forced outages of gas turbines (GT) or steam turbines (ST). Provides spinning reserve generation that instantaneously (within 5 secs) allows power import in the event of a trip of a Smelter GT or ST Unit. Allows the Smelter GT Units to operate at > 90% output and hence at high efficiency. Helps maintain the Smelter electrical system frequency and voltage.
Page No.9 Provides a large steady load throughout the year that helps stabilise Grid voltage and frequency, particularly during the low load Gulf Winter period. Provides spare generating capacity that can be made available to the Grid during the peak load Gulf Summer period. Provides short term (1 minute to 1 hour) frequency support to the Grid by de-loading the potline. Smelter is a large customer and a potential source of significant revenue to the Grid.
Page No.10 Trips of Grid generating units will affect Smelter electrical system frequency and may reduce power to the potline. Electrical faults on the Grid network may affect Smelter electrical system voltage and power supply to the potline. Grid has a primary responsibility to maintain the security and integrity of its own system, not to support the Smelter. Grid may therefore disconnect if it considers the Smelter power system is having a significant negative impact on the Grid. Disconnection from Grid may result in instability of the Smelter power system resulting in a power black-out.
Page No.11
Smelter Electrical System Instability following Disconnection from Grid Heading 1 Heading 2 Heading 3 2 lines Heading 4 Heading 5
Risks to Grid of Connection to Smelter
Page No.12 Potline trip causing a sudden very large power flow into the Grid resulting in a rapid increase in grid frequency and the trip of Grid generating units. Trip of a large Smelter generating unit causing a significant fall in Grid frequency and resultant load shedding. Electrical faults on the Smelter electrical network that affect Grid system voltage and stability.
Risk Mitigation by Smelter to Protect the Grid (1) Page No.13 Ensure a potline trip causes a matching rapid reduction in Smelter generation Smelter power reduction must occur within ~ <250 ms to avoid rapid increase in Grid frequency. GT governor/load control is not fast enough hard wired trip of GT and ST HV circuit breakers from potline trip system is required. Pre-selection of which GTs and STs to disconnect is required. Pre-selection scheme becomes more complex as more generating units and potlines are included.
Risk Mitigation by Smelter to Protect the Grid (2) Page No.14 Automatic disconnection from the Grid if a potline trip occurs AND high frequency is detected at the Grid Connection point. High grid frequency allied with a potline trip indicates the primary protection method described on the previous slide has failed to operate correctly. If a large Smelter generating unit trips, deload the potline using the high speed tap-changers of the rectiformers until Grid frequency recovers. Pre-selection of which potline to deload may be required in a multi potline Smelter.
Heading 1 Heading 2 Heading 3 2 lines Heading 4 Heading 5 Risk Mitigation to Protect the Smelter Page No.15 A Minimum of two Grid inter-connectors each rated to at least match the output of 1 GT and its associated ST. Grid Connection Agreement should include A clear communication protocol between Grid Despatch and Smelter power plant Operations. A clear set of operating instructions that specify under what circumstances and with how much warning the Grid can disconnect the Smelter. Smelter must develop and maintain good relationships at all levels with Grid personnel.
Heading 1 Heading 2 Heading 3 2 lines Heading 4 Heading 5 Summary Page No.16 There are significant Financial and Operational Benefits to the Smelter of connecting to the Grid. There are Benefits to the Grid of a connection to the Smelter, but the associated Risks can be significant. Smelter must appreciate the obligations of the Grid to its other Customers and take mitigation measure to ensure the Risks posed by Smelter connection to the grid are minimised. Good working relationships and communication at all levels between the Smelter and the Grid is essential to ensure that, in the event of a serious power system disturbance, the security of the Smelter potline power supply is not jeopardised.