Sie sind auf Seite 1von 4

Sl.No Specification NO L B H QTY.

Appx.qua
ntity Unit Rates in figures Amount in Rs.
1 DEMOLITION WORK
Demolition of old floor using necessary tools and
machinery, clearing site etc. completed.
old floor 1 50.62 42.32 2142.238
2142.2384 M
2
215.2 461009.70
2 EARTH WORK EXCAVATION
EARTH WORK EXCAVATION in all types of
soil including breaking clods,watering,ramming
,sectioning of spoil bank and backfilling the
excavated earth/supplied earth ramming,
compacting etc. as per the levels shown in
drawings and directions of site engineer, for wall
foundation
Up to a depth of 1.50m
Foundation 1 140.56 0.3 0.3 12.6504
12.6504 M
3
400 5060.16
3 BED CONCRETE
DATE
Kakkanadu
18/6/2014
PROJECT NAME
ARCHITECT
DETAILED ESTIMATE
Nirmal infopark
BIJU P. B B Tech M T Arch, STHAPATHY,KALOOR
CONTRACTOR
SITE LOCATION
P.C.C 1:3:6, 50 mm thick using 20mm size(or any
required size as per structural drgs.)hard broken
granite stone for flooring bed or wherever required
including cost of boxing, laying to line and level,
covering in case of adverse weather/rain conditions
, including cost of cement, curing for the required
period as per the Architects/Structural
Engineers/Site Engineers advice etc. for
Foundation, FLOOR
Floor 1 50.62 42.32 2142.238
2142.2384 M
2
0 0.00
4 BED CONCRETE
P.C.C 1:4:8 using 40mm size(or any required size
as per structural drgs.)hard broken granite stone for
foundation and flooring bed or wherever required
including cost of boxing, laying to line and level,
covering in case of adverse weather/rain conditions
, including cost of cement, curing for the required
period as per the Architects/Structural
Engineers/Site Engineers advice etc. for
Foundation, FLOOR
Foundation 1 140.56 0.4 0.15 8.4336
Floor 1 50.62 42.35 0.15 321.5636
329.99715 M
3
4250 1402487.89
5 R.C.C FOR BELT
Vibrated R.C.C for mix as per structural drgs.
Using 20mm nominal size hard broken granite
stones including cost of all formwork,labour
charges, all materials ,constructing to line level and
plumb, covering in case of adverse weather/rain
conditions,watering,curing for the required period
as per the Architect/Structural Engineers/Site
Engineers advice etc,complete for RCC BELT
1 140.56 0.15 0.22 4.63848
4.64 M
3
18000 83492.64
6 AEROCON WALL PARTITION.
Aerocon cement panel of approved quality and
make for a height of 4.5M using proper MS
channels and accessories.
GROUND FLOOR
wall 1 140.56 4.5 632.52
632.52 M
2
1775.4 1122976.01
7 GRID CEILING
Grid ceiling using 60x60 cm E board ,6 mm thick
including all accessories and fixtures. ``
1 50.62 42.35 2143.757
2143.76 M
2
699.4 1499343.65
8 Painting
Applying two coat of primer with approved quality
cement primer.
2 140.56 4.5 1265.04
1265.04 M
2
107.6 136118.30
9 Vitrified tiles
Supplying and fixing 60x60cm vitrified tiles of
approved make and quality with 3 mm spacer in
floor.
1 50.62 42.35 2143.757
2143.76 M
2
1054.48 2260548.88
10 Wall tile
Provide and fix approved 90x45 cm glazed wall
tiles as per design and drawing upto a height of
2.1m.The rate includes complete labour and
materialexpences(cutting,leveng,finishing, mseal
etc)associated to fixing and finishind of wall tile.
1 91.6 2.4 219.84
11 Sanitary fittings 219.84 M
2
1097.52 241278.80
Provide and fix sanitary ware of approved make
and Quality
Wall hung closet 13 13.00 nos 15000 195000.00
Wash basin 10 10.00 nos 12000 120000.00
urinal 5 5.00 nos 9500 47500.00
Consealed cistern 13 13.00 nos 80000 1040000.00
12 Plumbing LS 500000 500000.00
13 Electrification LS 300000 300000.00
9414816.03
Say 9831000.00
Rupees Ninety Eight lakhs Thirty one thousand only.
Design and Supervision charges @ 2% 196620.00