Sie sind auf Seite 1von 1

Contract 922: Construction and Completion of Expo Station and Overrun tunnel for downtown line satge.

3
Manpower Schedule for Diaphragm wall construction and Bored Piling Works
Aug Sep Oct Nov Dec J an Feb Mar Apr May J un J ul Aug Sep Oct Nov Dec
Project manager 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Planning manager 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Site QS 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Draftsman 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Site Adminstration 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Safety manager 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Safety Coordinator 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1
Safety Supervisor 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Safety Worker 2 1 1 6 6 6 6 6 6 6 6 6 6 6 6 4 4 4
Construction manager 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Site Manager 2 1 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Site Engineer 2 1 2 4 4 4 4 4 4 4 4 4 4 4 4 3 3 3
Site Supervisor 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Plant supervisor 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Site Foreman 2 1 1 4 5 5 5 5 5 5 5 5 5 5 5 4 3 3
Site mechanic 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Site Electrician 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Welder 2 2 2 4 6 6 6 6 6 6 6 6 6 6 6 4 4 4
Lifting supervisor 2 2 2 8 10 10 10 12 12 12 12 12 12 12 12 8 8 8
Ganger(Signal/rigger man) 2 6 6 16 20 20 20 20 20 20 20 20 20 20 20 12 12 12
Banksman 2 1 1 2 3 3 3 3 3 3 3 3 3 3 3 2 2 2
Plant-workers 2 3 3 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2
General worker 2 6 24 26 26 40 40 40 40 40 40 40 40 28 28 28
29 32 72 100 102 102 118 118 118 118 118 118 118 118 84 83 83 Total