0 Bewertungen0% fanden dieses Dokument nützlich (0 Abstimmungen)
13 Ansichten11 Seiten
ALMA Project Design / Engineering at the OSF Technical Facilities For Construction Phase 3 Geotechnical Report Contract No. 72057 / MEP / 03 / 0568 / RFI Doc. No.: SITE-20.00.00.00-000-A-REP Version : A Status : For Review and Comments 30-Jan-2004.
ALMA Project Design / Engineering at the OSF Technical Facilities For Construction Phase 3 Geotechnical Report Contract No. 72057 / MEP / 03 / 0568 / RFI Doc. No.: SITE-20.00.00.00-000-A-REP Version : A Status : For Review and Comments 30-Jan-2004.
ALMA Project Design / Engineering at the OSF Technical Facilities For Construction Phase 3 Geotechnical Report Contract No. 72057 / MEP / 03 / 0568 / RFI Doc. No.: SITE-20.00.00.00-000-A-REP Version : A Status : For Review and Comments 30-Jan-2004.
Mass excavation, transport, fill and compaction for the Site
Preparation of the Technical Facilities at the Operation Support
Facility (OSF) Site of the Atacama Large Millimeter Array (ALMA) Observatory located near the villages of San Pedro de Atacama and Toconao, II. Region, Chile, South America.
For Construction Phase 3
Geotechnical Report
Doc. No.: SITE-20.00.00.00-000-A-REP
Version : A
Status : For Review and Comments
30-Jan-2004
Prepared By : Name(s) and Signature(s) Organization Date
Michael Wagner
29.Jan.2004
Approved By : Name(s) and Signature(s) Organization Date
Claus Dierksmeier
30.Jan.2004 Released By : Name(s) and Signature(s) Organization Date
Claus Dierksmeier
30.Jan.2004 ALMA Project
Design/Engineering at the OSF Technical Facilities For Construction Phase 3 Geotechnical Report Contract No. 72057/MEP/03/0568/RFI Doc. : SITE-20.00.00.00-000-A-REP Date : 30.Jan.2004 Version : A Status : For Review And Comment Page : 3 of 10
Change Record
Version Date Section/ Page Affected Reason/ Initiation Documents/ Remarks
ALMA Project
Design/Engineering at the OSF Technical Facilities For Construction Phase 3 Geotechnical Report Contract No. 72057/MEP/03/0568/RFI Doc. : SITE-20.00.00.00-000-A-REP Date : 30.Jan.2004 Version : A Status : For Review And Comment Page : 3 of 10
Table of Contents Page
1.1 Introduction 4 1.2 Available Antecedents 4 1.3 Available Information 4 1.4 Analysis of the Information Obtained 6 1.5 Bearing Capacity 6 1.5.1 Foundation on Rock (Ignimbrite) 6 1.5.2 Foundation on Structural Fill Material 7 1.6 Excavation of Slope 9 1.7 Excavation and Fillings 9 1.8 Treatment of the Embedment 9 1.9 Fill Material 9 1.10 Uniformity of the foundation Embedment 10 1.11 Reception of the Foundation Embedment 10
ALMA Project
Design/Engineering at the OSF Technical Facilities For Construction Phase 3 Geotechnical Report Contract No. 72057/MEP/03/0568/RFI Doc. : SITE-20.00.00.00-000-A-REP Date : 30.Jan.2004 Version : A Status : For Review And Comment Page : 3 of 10
1.1 Introduction
The ALMA project (Atacama Large Millimeter Array) in the II region is considering a Operation Support Facility (OSF) to be build at an elevation of approximately 2.900 m a.s.l.
In the framework of the design of technical facilities at the OSF a geotechnical investigation has been perfomed in order to determine the geotechnical parameters and the bearing capacity of the material where structures of the Operation Support Facility will be founded.
1.2 Available Antecedents
For this geotechnical report the following antecedents have been taken into account:
A Site visit to the OSF of the geotechnical engineering team The execution of 2 Rotation Drilling with 15 meters depth The excavation of 15 exploration pits covering the future OSF site The results of the field prospectings and the laboratory rock tests performed (Report of TECNOLAB LTDA., with the number 53.709)
1.3 Available Information
The two rotation drillings with 15 m depth each have been executed at the following topographical coordinates:
Prospection Coordinate UTM North Coordinate UTM East Drilling 1 7.488.356 604.633 Drilling 2 7.448.490 604.708
From the 15 exploration pits with variable depths, 12 have been placed in the construction area of the structures and 3 at places where it should be possible to gain structural fills and materials for concrete production.
The most probable stratigraphic description for the OSF site:
Horizon 1: 0.0 - 0.4 Gravel with sandy silt, brown color, medium compactness, low moisture, non plastic fine, angular and subangular grains.
Horizon 2: 0.4 - Ignimbrite rock. Light brown color. Medium to low hardness. Not sensitive to water contact.
ALMA Project
Design/Engineering at the OSF Technical Facilities For Construction Phase 3 Geotechnical Report Contract No. 72057/MEP/03/0568/RFI Doc. : SITE-20.00.00.00-000-A-REP Date : 30.Jan.2004 Version : A Status : For Review And Comment Page : 4 of 10
In the following some pictures of the drillings, the exploration pits and the rock samples are presented.
Photo 1: Drilling 1
Photo 2: Location of Drilling 2
ALMA Project
Design/Engineering at the OSF Technical Facilities For Construction Phase 3 Geotechnical Report Contract No. 72057/MEP/03/0568/RFI Doc. : SITE-20.00.00.00-000-A-REP Date : 30.Jan.2004 Version : A Status : For Review And Comment Page : 5 of 10
Photo 3: Drillings Cores
Photo 4: Exploration Pit 10
ALMA Project
Design/Engineering at the OSF Technical Facilities For Construction Phase 3 Geotechnical Report Contract No. 72057/MEP/03/0568/RFI Doc. : SITE-20.00.00.00-000-A-REP Date : 30.Jan.2004 Version : A Status : For Review And Comment Page : 6 of 10
1.4 Analysis of the information obtained
Out of the analysis of the information obtained the following conclusions can be drawn:
1. The material where the different structures of the project will be founded is rock that is starting from a maximum depth of 0,4 m.
2. The rock type is INGNIMBRITE of light brown color with medium to low hardness.
3. Where the foundation level lies higher than the actual landscape (filling areas), structural fills, based on sandy materials, will have to be made.
1.5 Bearing Capacity
The bearing capacity of the ground for the foundations of the structures has been determined for the following two cases:
- Foundation on rock and - Foundation on structural fill material
Both cases are shown as follows:
1.5.1 Foundation on Rock (ignimbrite)
A. Geotechnical Parameters
The following geotechnical parameters have been adopted for the ignimbrite.
Foundation Material Ignimbrite Color Light Brown Density [ton/m 3 ] 2,13 Uniaxial compressive strength [kg/cm 2 ] 157 Elasticity Module [kg/cm 2 ] 2000 Ratio of Poisson 0,15 Internal friction angle [] * 50 Cohesion [kg/cm 2 ] * 0,5 *: Only for calculation purposes. Does not have validity in another sense
ALMA Project
Design/Engineering at the OSF Technical Facilities For Construction Phase 3 Geotechnical Report Contract No. 72057/MEP/03/0568/RFI Doc. : SITE-20.00.00.00-000-A-REP Date : 30.Jan.2004 Version : A Status : For Review And Comment Page : 7 of 10
B Ignimbrite Bearing Capacity
Using the geotechnical parameters given above and considering the characteristics of the ignimbrite, the bearing capacity has been determined according to the Canadian Geotechnical Manual for bearing capacity in rocks:
q ul = K s * RCS * D
where -
q ul : Bearing Capacity [kg/cm 2 ] K s : Factor associated to discontinuities (0,3 for this case) RCS : Uni-axial compressive strength [kg/cm 2 ] D : Form Factor (1,4 for this case)
Considering the result of the uniaxial compressive strength test with RCS = 157 the bearing capacity is: q ul = 66 kg/cm 2
Considering a security factor of 3, the acceptable bearing capacity for the ignimbrite is:
q ad = 22 kg/cm 2
This value allows for the foundation of any normal structure on the ignimbrite.
The settlements associated to these bearings, are considered to be lower than 1 cm.
1.5.2 Foundation on Structural Fill Material
There have been made exploration pits in different locations. Some of these exploration pits were designated to the identification of adequate filling material. It was possible to detect some suitable sand fill material at a distance of 3 km to the OSF site.
A Geotechnical Parameters
The following are the geotechnical parameters that have been adopted for the compacted sand at this site.
ALMA Project
Design/Engineering at the OSF Technical Facilities For Construction Phase 3 Geotechnical Report Contract No. 72057/MEP/03/0568/RFI Doc. : SITE-20.00.00.00-000-A-REP Date : 30.Jan.2004 Version : A Status : For Review And Comment Page : 8 of 10
Foundation Material Compacted Sand Color Brown Dry unit weight [ton/m 3 ] 1,84 Water content [%] 4,0 Void Ratio 0,47 Elasticity Module [kg/cm 2 ] 800 Ratio of Poisson 0,15 Internal friction angel [] 35 Cohesion [kg/cm 2 ] 0,0 Active pressure coefficient 0,31
B Bearing Capacity of the Compacted Sand
Using the geotechnical parameters given above a Soil Mechanics calculation has been performed in order to determine Bearing Capacity in the filled areas.
For the foundation at the structures it has been considered that the filling material will have a minimum thickness of 0,5 m under the foundation. On the other hand the embedment of the foundation will be buried into the filling material with a minimum of 0,6 m.
Therefore the fill will have a minimum depth of 1,1 m.
The foundations will be made based on continuous footings with a width of 0,6 m, or square footings with a width of 0,5 m x 0,5 m.
The parameters used are the followings:
Depth of Embedment D = 0,6 m Width of Continuous Footing B cor = 0,6 m Width of square footing B cua = 0,5 m Load over soil q sol = 2,0 kg/cm 2
With the previous data and the parameters of the filling material, the bearing capacity has been calculated (see Annex). The results are the following:
For continuos footing:
Static Bearing Capacity q ult = 2,5 kg/cm 2
Seismic Bearing Capacity q ults = 3,7 kg/cm 2
Settlement < 1 cm
For square footing:
Static Bearing Capacity q ultcua = 2,2 kg/cm 2
Seismic Bearing Capacity q ultsa = 3,3 kg/cm 2
ALMA Project
Design/Engineering at the OSF Technical Facilities For Construction Phase 3 Geotechnical Report Contract No. 72057/MEP/03/0568/RFI Doc. : SITE-20.00.00.00-000-A-REP Date : 30.Jan.2004 Version : A Status : For Review And Comment Page : 9 of 10
Settlement < 1 cm
Those values are conservative and they indicate that the filling material has a suitable bearing capacity and will not produce excessive settlements.
The previous results indicate that if the filling material is being loaded with 2 kg/cm 2 , the settlement will be less than 1 cm, a value totally acceptable for this type of works.
1.6 Excavation of Slopes
The cuts and slopes of the project that will be made in rock (ignimbrite) allow almost vertical slopes (it is recommended to use a slope of 1:5, horizontal: vertical).
1.7 Excavations and Fillings
For the excavations conventional machinery according to the construction companys availability can be used. However there has to be applied manual excavation for the last 0,30 m over the level of the embedment in order to minimize the alteration of the natural structure of the support material.
Any over excavation, either in depth or in width, will have to be filled with concrete of 170 kg cement per cubic meter, being specifically forbidden any other filler type. However, over excavation over the embedment will be stuffed with the resulting material of the same excavation. This material that will be placed with light compaction, with 6 cycles of manual compactor in layers with a thickness of 0,25 m.
1.8 Treatment of the Embedment
Previously to the placement of the footings or fill, all loose and/or strange material that could have been deposited during the excavation will have to be removed from the foundation embedment.
1.9 Fill Material
As fill material a granular material, like sand, will be used. The maximum content of fine soil (under 200 USCS sieve) in the fill will be 12%. The maximum size of the material will be 2". The granular material will have to be placed in layers of 30 cm of thickness (in loose state), following compaction until reaching an equivalent density to 85% of the Relative Density. The fill will have a minimum total thickness of 1,1 m.
ALMA Project
Design/Engineering at the OSF Technical Facilities For Construction Phase 3 Geotechnical Report Contract No. 72057/MEP/03/0568/RFI Doc. : SITE-20.00.00.00-000-A-REP Date : 30.Jan.2004 Version : A Status : For Review And Comment Page : 10 of 10
In case there will be fill over soil material (silt with gravel) the superficial 10 cm of soil have to be removed. A compaction passing 4 times with a rolling compactor has to be performed before putting the fill material.
1.10 Uniformity of the Foundation Embedment
In order to avoid differential settlement in the structures it will be mandatory that all the structure will be founded in one single material type. That means that each structure will be founded either on rock or on the structural fill. A structure should never be founded in mixed form.
1.11 Reception of the Foundation Embedment
The foundation embedment must be approved by a Civil Engineer specialized in such works.