Beruflich Dokumente
Kultur Dokumente
=
=
) (
Pr
max
max
CT C OEE T
COtime
me oductionTi Daily TimePerDay Disposable
COtime
Day ngeoverPer TimeForCha Disposable
COtime
RT
theory
[7]
The maximum replacement time (RT
max
) is the time it takes the supplier to replace the
stock at maximum consumption and with the premise that disposable time is used for
change over. Also, it is the maximum time to replace a certain box taken from the
supermarket. Furthermore, it is the time a product is produced again at the latest with
the premise that every part is produced on per interval ( EPEI = Every Part Every
Interval)
Dimensioning the red, green and yellow sectors
Red sector
Equation 8: Number of pieces in red sector
Number of pieces S RT C + =
min max
[8]
=
min
RT Minimal replacement time (time)
Calculation of minimum replacement time
Equation 9: Minimum replacement time
transport Box startCO oKanban
T T COtime T T RT + + + + =
1 inf min
[9]
Green sector
Equation 10: Number of pieces in green sector
Number of pieces Box BS 1
min
= [10]
=
min
BS Minimum batch size of supplier of the supermarket (pieces)
Yellow sector
Equation 11: Number of pieces in yellow sector
Number pieces = total number pieces pieces red sector pieces green sector [11]
Note: With a very long RT
min
and/or large BS
min
the red and the green sector can adjoin
each other.
(ZF Ansa Lemfrder, 2007)
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
62
3.3.5 LPS workshop: 5S Sift, Set, Sweep, Standardize and Sustain
Figure 57: 5S workshop
5S is a process for workplace organization and visual controls. According to the LPS
philosophy, cleanliness and organization are the basis for accurate work, and it supports
the LPS pillar of the zero defect principle, see Figure 57 above.
The 5S is a system to develop a safe, clean and neat arrangement of the workplace
which provides specific location for all things and supports the employee. The system
encourages visual management; the use of visual controls such as letters, shapes,
symbols, pictures and sounds which make it readily apparent to any employee that
normal or abnormal condition exists. These techniques expose waste so that it can be
prevented and eliminated.
Running an LPS workshop with 5S as the theme will:
Engage operators in the changes
Encourage standardized work
Eliminate Waste
Improve safety, quality and productivity
Improve area cleanliness
Allows for visual management
Encourage continuous improvement
J
J
I
I
T
T
motivated employees and teams
continuous improvement
standardized and flexible products and
strong suppliers
highest quality shortest throughput time
Customer satisfaction
by eliminating waste
Takt
principle
low costs
Zero
failure
principle
Flow
principle
Pull
principle
SMED OEE
Dust seal
5S
Target:
100% good quality achieved by stable
design and standardized processes
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
63
The expected results from a 5S workshop are:
Quantitative results:
Reduction of time for searching
Minimizing of inventory of tools and utilities
Error prevention
Reduction of space consumption
Qualitative results:
Improvement of safety
Increasing transparency of processes
Increasing capabilities
To be able to eliminate waste, we need a common definition of what it is and a way to
measure it. Also it is needed to make sure it is not only done reactively, but as a
continuous improvement which will be standardized. As a reminder, the seven types of
waste are listed below:
Overproduction More than customer demand or faster than needed
Inventory Parts in excess of just in time
Distance Unnecessary distances
Transport Excessive transporting of material
Waiting Idle time, waiting on: machines, parts, people, information
Defects Repair, scrap, inspection
Space Inappropriate layout
The procedure for eliminating the waste contains 5 steps and in the original language of
the LPS philosophy, Japanese, the name of each step begins with an S, thereof the
expression 5S. Conveniently, there are similar words in English beginning with S, but
the translation differs depending on the source. Following are the five original words
together with translations.
1. Seiri = Sift or clear
2. Seiton = Set in order or organize
3. Seiso = Sweep or shine or clean
4. Seiketsu = Standardize
5. Shitsuke = Sustain
The main aims of each step are listed in Figure 58 below.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
64
Figure 58: Aims of 5S
Following are further explanations of the necessary steps in each of the 5 Ss during a
workshop.
1. Seiri = Sift
Define the purpose of the work area
Identify what is needed and not needed at the workplace
Analyze items using a priority check sheet, see Figure 59 below:
o Local storage at workstation
o Distant storage - 1 year rule
o Disposal - Items that do not contribute to the purpose of the work area
Move or dispose of items
Clean the area where items once were located
1.
Sift
2.
Set in order
3.
Shine
4.
Standardize
5.
Sustain
Eliminating
unnecessary
items from the
workplace
Equipment in
proper state and
within reach
Cleanliness of
workplace incl.
equipment
Cleanliness and
accuracy starts at
own workplace
Regular cleaning
and stick to
agreements
- unnecessary
tools +
machines
- defective parts
- tool racks
- marked
footprints
- visualised work
instruction
- tools and
machines
always cleaned
- clean shop floor
+ buildings
- Leaders must
set a good
example
- information for
all employees
- personal
responsibility for
the workplace
- accomplish
audits
5S-Checklist
Shadow board
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
65
Figure 59: 5S priority check sheet
2. Seiton = Set in order, organize
Organize what was kept and provide a place for everything needed for value
added work
Label parts/material/assembly locations. Write;
o Part name
o Part Number
o Min/Max quantities
Visibility
o Color code with floor tape or paint
o Floor locations marked
o Shelves, containers, racks painted
o Shadow boards, see Figure 58
Easy to put back
o Open storage for tools and fixtures
3. Seiso = Sweep
Define clean, How clean is clean?
Determine cleaning methods
o Make needed tools and materials available, organize them and clarify
safe use
Clean Everything
o spring cleaning
Inspect to determine sources of dirt, debris and fluid leaks
Eliminate source with irreversible corrective actions where possible
Priority Frequency of use Storage
Low
Less than once a year
Every couple of months
Throw away or store
away from the
department/area
Average
At least once a month
At least once a week
Once a shift
Store in the department,
but away from the work
stations
High
At least twice a shift
At least once an hour
Carry or keep at
individual work station
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
66
4. Seiketsu = Standardize
The standardization helps in maintaining the first 3 S's.
Map area into zones; assign responsibilities; develop schedule and display it
Create procedures, guidelines, steps, standards
Workplace organization audits
Establish visual controls:
o Maintains organization
o Serve as reminders
o Are quickly and easily recognized
o Colors, symbols, pictures, letters, sounds
o Makes it easy to see if things are running the way they are supposed to
be
o Helps to identify when assistance is needed
5. Shitsuke = Sustain
Eliminate the source of waste
Following 5S becomes the standard way to work
Continued training (share knowledge, ideas)
Establish 5S communication item within area information center
o before and after photos
o recent audit results
(ZF Ansa Lemfrder, 2007)
3.3.6 LPS workshop: Self Control
Another LPS workshop theme is self-control. It supports the pillar of the flow principle,
see Figure 24 in chapter 3.1.6 and it focus primarily on eliminating the waste of
movements and waiting.
Many manufacturing processes at ZF Ansa Lemfrder require a quality check after
changeovers or change of lot number. This quality control is usually performed by the
personnel from the quality department, so the operator needs to go look for the right
person to control the product before continuing the production. Sometimes the quality
control person is busy so the operator either has to wait or go look for someone else.
This is a time consuming procedure which interrupt the flow of production, since while
going around the plant looking for someone production time is lost.
This procedure can be avoided by implementing self-control, meaning that the operator
himself or herself controls the products. This requires that the operators receive the
appropriate training as well as an investment in control stations with the proper
equipment. (Guerrero, 2007)
The procedure for implementing self-control at ZF Ansa Lemfrder is not further
explained in this report since there still do not exist examples or instructions of how to
implement it.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
67
3.3.7 Other LPS workshops
It is possible to execute workshops in other areas than on the production floor, which is
rarely done at ZF Ansa Lemfrder but it has been done. For instance they did one
workshop at one of their suppliers with the theme of making a value stream analysis in
order to see where in their process they could work make improvements. Also, at other
Lemfrder group companies they have held workshops for the product development
processes. (Guerrero, 2007)
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
68
4 PRE-STUDY - LPS practice workshop: SMED
and 5S in BTB machine 928
As a part of the pre-study the student participated in a SMED workshop. The aim was to
learn the LPS workshop procedures.
4.1 Theme and objective
The theme of this LPS workshop was time reduction and simplification of changeover
as well as improvement of the state of the order and cleanliness. The objective was to
reduce the changeover time by 50%, decrease the walk distances by 70% and improve
the order and cleanliness at the workplace.
4.2 Method and schedule
The workshop was carried out during seven days in accordance to the eight phases of a
typical LPS workshop, see Figure 17 in chapter 0. What was completed during each
phase is explained further on, together with a part called important points. The
important points are matters which the student should keep in mind when organizing
and implementing an LPS workshop, and they are based on interviews with the LPS
coordinator (Guerrero, 2007)
All LPS workshops are held in the LPS room at ZF Ansa Lemfrder and so was this
workshop. The schedule was planned in advance by the LPS workshop coordinator, but
some activities were rescheduled to fit with the schedule of production changeovers, see
schedule Figure 60.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
69
Figure 60: Practice workshop schedule
In the end of each day a meeting with the steering committee was held, and the
coordinator presented the work of the day using a computer and projector together with
a PowerPoint slideshow, photos or documents. In the end of each meeting, the
committee asked questions or came with advice. The intermediate meeting and the final
meeting were longer and more formal, and at those meetings the whole group
participated in the oral presentation aided by a PowerPoint slideshow.
Rescheduled activities
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
70
4.3 The BTB production cell
The BTB production cell machines ball joint housings of eight references, namely X91,
B58, A7 and C307, whereof each one is produced in a right hand version (R) and in a
left hand version (L). The BTB production cell consists of two identical machines, 928
and 916, that perform the same type machining, see layout in Figure 61. The LPS
workshop focused on machine 928 with the intention to change the second machine
after the first one was completely changed and the process stabilized.
Figure 61: Layout of BTB production cell
4.3.1 Initial state of machine 928
A few days before the workshop started, the workshop coordinator collected data about
machine 928 from SCADA. A total of 56 changeovers were performed during the
period 01/05/2007 19/10/2007 and the average changeover duration was 4.65 hours,
see Figure 62 which illustrates the changeover times ordered by duration. The parts to
the extreme left and to the right of the graph were considered uncharacteristic and were
not taken into account as typical changeovers and thereby not used as references in
comparisons. The two parts marked in red circles in the middle of the graph were
assumed to be standard changeover times, whereas the middle left represents
changeover between references and the middle right represents changeover between left
and right hand of the same reference.
928
916
BTB
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
71
Figure 62: Changeover times of machine 928 ordered by duration
Additionally, the coordinator also learned from the production planning department that
they plan approximately one changeover every 1.7 days in machine 928, see Table 6.
Table 6: Changeover data of machine 928
Planned changeover
frequency
Registered
average
changeover time
(SCADA)
Estimated duration
between references
Estimated duration
between Left and
Right
1 time every 1.7
days
4.65 hrs 3 hrs 4 hrs
There exist several possible ways to changeover machine 928, and the approximate
duration of each changeover before the LPS workshop is illustrated in Figure 63 below.
0,00
2,00
4,00
6,00
8,00
10,00
12,00
14,00
16,00
18,00
20,00
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52
Uncharacteristic
Uncharacteristic
Between
references
Between Left
and Right
Hrs
Number of changeovers
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
72
Figure 63: Changeover times according to references
It is necessary to point out that the time for a changeover between left and right hand of
the same reference is shorter than the changeover between two references. Furthermore,
the changeover time between hands of X91 is a little bit longer than for the other three
references. The reason for the longer changeover time between the hands of X91 is due
to the need of changing a vibration feeder. This is not necessary with the other three
references.
4.4 Before the workshop
Before any LPS workshop starts, the workshop coordinator needs to prepare a workshop
definition sheet containing information about the initial situation, objectives, scope,
general conditions, qualitative and quantitative targets, team members and dates and
times. The definition sheet is given to all team members and to the involved department
managers. Furthermore, the coordinator use a template checklist to make sure that all
practical tasks will be prepared in time for the start, for example booking of room,
invitation of participants, etc.
4.5 Execution of the workshop
4.5.1 Phase 1 and 2: Education and objectives
In the morning of the first day of the LPS workshop the coordinator held a short
presentation about SMED, why it can benefit the production and the objectives of the
workshop. Usually the education should be held before the start of the workshop, but
this was not possible due to the schedules of the participants. The coordinator also
presented the initial state of the machine which is the same as mentioned in the previous
chapter in Table 6.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
73
The objective was to reduce the time of the changeover of the machine by 50%,
decrease the walk distances by 70% and improve the order at the workplace. See Table
7 below.
Table 7: Workshop objectives
Key references for
measuring results
Initial state Objective Difference
Time of changeover
(minutes)
280 min 140 min (-50%)
Walk distance during
changeover (meters)
446 m 140 m (-70%)
5S evaluation (max 25
points)
6 points 25 points (+19)
Important points phase 1 and 2:
The LPS organizer started the workshop by clearly declaring and writing down the rules
to be followed.
Do not look for the guilty one, instead look for solutions
Talk in facts
Punctuality
The first rule is important to communicate in order to avoid conflicts and letting the
team focus on the solutions. The second rule, talk in facts, helps the team to base all
decisions on facts instead of hunches and gut feelings. The third rule, punctuality, is
important since the workshop is executed during a relatively short period of time, so the
members cannot afford to waste time on waiting for late team members.
The organizer had in advance prepared a PowerPoint presentation with information
about SMED together with examples of successful SMED workshops. This helped the
team to understand the possible benefits of the workshop. Furthermore, data from the
machine to be studied was presented to give the members a clear picture of the current
state. The conclusion of this is that the workshop coordinator needs to thoroughly plan
the workshop, and collect necessary data before it starts. This will give the team more
time to focus on other issues.
The training is important since it might help avoiding discussions that are based on not
understanding the LPS theory. Example: batch size - better if small, but it is easy to
believe that it is better if it is big since it reduces the frequency of changeovers.
4.5.2 Phase 3: Analysis
The analysis took place the first day of the workshop and it consisted of observation of
a changeover between two references, from X91 to B58 in the BTB production cell, see
Figure 63 in previous chapter. The team went to the production cell, and four members
collected the following information during the changeover:
1. Noting duration of each step of the changeover process
2. Spaghetti diagram, showing the movements of the operator during the changeover
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
74
3. Photos of visible wastes
4. Writing down possible improvements that the team members thought of during the
observation
After the observation, the team went back to the LPS room and summarized all
observations and wrote down all improvement suggestions on an A1 sized paper which
was hung up on the wall in the LPS room.
1. Duration of each step
The duration of each step in the changeover process was written down and further on
transferred to an Excel sheet and transformed into a waterfall diagram, see Figure 64.
The two main activities during the changeover were controls and mechanical
changeover.
Figure 64: Observation and analysis of changeover
The times in Figure 65 below are approximate and based on the observation done on
October 22
nd
2007. Note that the times observed and estimated here are shorter than the
times in the statistics from SCADA, as in Table 6 in chapter 4.3.1.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
75
Figure 65: Changeover times according to references, after observation
The times of mechanical changeover and adjustments have been separated in the table
above. The mechanical changeover time is often easier to decrease than the adjustment
time since the mechanical changeover consists of static elements of action. Whereas the
adjustment time of the machine depends on many factors, and those factors are often
difficult to anticipate.
2. Spaghetti diagram
During the observation a spaghetti diagram illustrating the operators movements during
the changeover was created. The drawn lines illustrate the path and the bars symbolize
the number of times the operator walked along each path. See Figure 66. The most
frequent paths are those leading to the tow tool tables. The total distance during the
observation was 446 meters.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
76
Figure 66: Spaghetti diagram from first observation
3. Photos of wastes
Some photos of wastes were taken during the observation; see the examples in Figure
67 below. The first is inappropriate layout in the factory (space), since the operator
needs to move objects in order to pass with the forklift when going to fetch the feeder.
The second picture shows excess inventory next to the machine. The third picture shows
disorder in the toolbox used during the changeover. Note that the toolbox contained
many tools not needed during the changeover or during regular work tasks.
Figure 67: Photos of waste
4. Possible improvements
The team wrote down possible improvements during the observation and there were
many ideas. All the ideas were attempted to be implemented and it is described in
chapter 4.5.3.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
77
Important points phase 3:
Following is a citation from the LPS workshop coordinator regarding the importance of
the analysis phase; The analysis phase is maybe the most important phase, since during
a workshop we can only improve what we see, and what we dont see doesnt exist.
That is why its so important that we make the analysis the right way from the
beginning, making it possible to find the improvements and implement them.
The importance of a good analysis is crucial for the successive steps of the workshop,
and this is where the coordinator needs to be aware of what is happening and to make
sure that things are moving in the right direction. The coordinator needs to be aware of
what could go wrong and to be able to see if something is missing. That is why the
coordinator always needs to prepare for the workshop, making a checklist of all
necessary actions and data.
4.5.3 Phase 4: Ideas and solutions
After the data collection in the analysis phase, the team sat down in the LPS room and
discussed possible improvements. Both the improvements thought of before in the
analysis phase and new ideas were discussed. Each improvement idea which the team
agreed upon was transferred into an action for implementation. Each action was noted
on an A1 task paper together with deadline, responsible person and a Deming wheel
representing the state of completeness. See Figure 68. Note; the picture to the right is
the excel format of the same type of task list. It is mainly used after the workshop to
keep track of unfinished tasks.
Figure 68: Workshop tasks
New improvement ideas were thought of during the whole workshop and not only
during the analysis and solution phase. The number of task papers on the walls
increased constantly and in the end of the workshop approximately 20 tasks had been
created and most of the executed. Following are some examples of tasks:
Design a cart for transporting the feeders in order to avoid searching for a forklift.
Give design proposal to purchase department for approval.
Buy an air impact wrench to make the mechanical changeover faster
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
78
Design a cart for tooling that can be placed next to the machine during changeover,
to avoid movements when operator walks to the tool table. Give the design proposal
to the purchase department for approval.
Design a tool-board for tools needed during changeover, with magnets so that it can
be attached when needed and detached after use, to avoid movements. Give design
proposal to purchase department.
Mark a line on the floor between the machine and the inventory area, in order to
leave enough space for the forklift
Etc.
Important points phase 4:
The role of the coordinators involvement in the generation of ideas and solution
strongly depends on the group. Sometimes the coordinator needs to push the group in
the right direction, but other times the group can easily find solutions. Julio Guerrero,
the coordinator of this workshop said that he sometimes collaborates too actively, so the
group thinks that he is the leader and they wait for his opinion. The group believes that
they are instruments for someone else ideas. But as soon as they understand that they
are the ones who are supposed to generate ideas and that they will be heard, they
become surprised. Once they have comprehended that they are the sources of the ideas,
the work usually becomes easier. One way to push the group in the right direction is to
make them think that the ideas were theirs, by giving them the right information at the
right time.
4.5.4 Phase 5: Solution implementation
The responsibility of each solution to be implemented was given to one or more
persons. Depending on the knowledge of the person, the tasks differed. Most tasks were
quite simple and were implemented right away. Some tasks took longer time, and even
after the workshop end they were still not finished. Even tough a task is not finished, it
will not be forgotten. The coordinator keeps track of all tasks in the kaizen book and
tries to successively finish them.
In this phase, the 5Ss were implemented;
1. Seri = Sift or clear
2. Seiton = Set in order or organize
3. Seiso = Sweep or shine or clean
4. Seiketsu = Standardize
5. Shitsuke = Sustain or self control
Before the 5S activities started, a 5S self evaluation sheet was filled out in order to
evaluate the initial state of the workplace. After, the group started to clear out all tools
and other equipment that was not needed at the workplace. The needed tools were
organized and given a place to be stored, see Figure 69. Thereafter the workplace was
thoroughly cleaned. Afterwards, standards were created in order to sustain the order and
cleanliness at the workplace. One example of a standard is signs and etiquettes showing
where each tool belongs. Another example is pictures with clear illustrations of how the
workplace is supposed to look like in the end of the shift, see Figure 70. In the end of
the 5S implementation another self evaluation sheet was filled in order to measure the
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
79
5S score, see Figure 71. The result was a 10 point difference (initial score = 7 points,
final score 17 points).
Figure 69: Separation and organization of tools
Figure 70: Instruction of workplace order after each shift
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
80
Figure 71: 5S self evaluation sheet after the 5S activities
Important points phase 5:
The workshop can feel quite urgent and the team works quite intensively during the
workshop. The implementation of the solutions is always much easier to do during the
workshop, thats why the coordinator tries to push the team to implement as much as
possible before the workshop ends. Any solution that is not finalized during the
workshop is usually much more difficult to implement, because: 1; The team is
separated and 2; The bosses of different departments need to understand and approve of
the changes. During the workshop it is easier to convince them of the necessity, while
after the workshop the sense of urgency has disappeared.
4.5.5 Phase 6: Evaluation of results
At the time of the evaluation many of the improvements had been implemented. The
two ways of measuring the results were;
1. Duration of each step of the changeover process
2. Spaghetti diagram, showing the movements of the operator during the
changeover
The evaluation gave the following results:
Key references for
measuring results
Initial state Objective After
Time of changeover
(minutes)
280 min 140 min (-50%) 148 (-47%)
Walk distance during
changeover (meters)
446 m 133 m (-70%) 140 (-68%)
5S evaluation (max 25
points)
6 points 25 points (+19) 16 (+10)
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
81
Important points phase 6:
It is important that the key-figures chosen in the beginning of the workshop are clear to
measure and can be understood by everyone. There should be only one way to measure
one thing and the value should be meaningful and easy to understand for the people
using it. If not, there is a risk of misunderstandings and that the measurements will not
be made. For instance, during the evaluation, the spaghetti diagram was made by
another person than who made the previous one. The diagrams looked very different
and the comparison became unnecessarily difficult.
4.5.6 Phase 7: Standardization
Some standardization of the changes have already been mentioned in the part describing
the 5S, there many visual aids helps to standardize the work. Another type of
standardisation is written instructions, in addition to educating all operators of the new
procedures of work. All operators must receive education about the new procedures, and
the coordinator has to prepare the education and further on inform the shift leader. To
keep track of which operators received education, a list of the operators names can be
placed by the work place and the names will be checked after the education.
Important points phase 7:
The coordinators responsibility after the workshop is to check and register the changes
every month. The standardisation helps to establish key-values to measure and the
visual aids makes any abnormalities immediately obvious.
4.5.7 Phase 8: Communication of results
After the workshop, the coordinator prepared a report for the steering committee and
presented the results. The report is brief and it is written on an A4 sized sheet containing
target, changes and results. He also made a report and presentation for the shift
responsible and leaders, which train the operators. Furthermore, he prepared a standard
form for the operators to register the changeover times.
The coordinator also makes an information board to be placed by the machine,
explaining that an LPS workshop was performed there. The info-board also contains
things like; workshop target, agenda, participants, initial and final state and results. The
board is updated every month until the process is considered stable. The same
information is available on the company intranet, so other plants within the Lemfrder
group can learn from the experience.
Important points phase 8:
It is important that all operators receive the education, to ensure that all changes are
actually being employed.
4.6 Lessons learned
In the end of all LPS workshops a part called lessons learned is carried out. Then the
group discuss the things that went wrong as well as things that wasnt thought of during
the workshop but would be done if they could do the workshop over again. These points
are important because they work as reminders for the next workshop, and hopefully the
lessons will make the next one run smoother. Following are the lessons learned during
the LPS workshop - SMED and 5S in BTB machine 928:
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
82
The manager did not inform to the responsible of production planning about the
workshop plans to observe a changeover, so they were very surprised when the
workshop members asked to watch a specific changeover. So, dont expect that
everyone will do his job, it is always best to double check for critical activities
Always let the same person measure the same thing, in order to assure that it is
done that same way before and after.
The improvements that have an influence on organizational matters need to be
agreed upon during the workshop to assure that it will be implemented. The
workshop team must discuss the issues and agree upon them with responsible
people before the workshop ends.
No changes were made about the quality control procedures of the changeover;
maybe it would have been possible if the quality department team member had
been available during the whole workshop. (he had vacation during the first half of
the workshop)
Documentation
Many documents were produced during the workshop, both electronic and handwritten
on paper. Three main formats of information was produced on; A1 paper sheets, A4
paper sheets or as computer files (photos, excel files or word documents). The
coordinator was in charge of organising all information and all electronic information
was put into the LPS folder on the company computer network.
4.7 Results - follow up
On March 25
th
2008, roughly 5 months after the workshop, the results of the changeover
times of machine 928 were followed up, see Figure 72. The average changeover times
during the five months before the workshop (May-September) shows an average of 2.6
hours, while the average changeover time for the five months after (November-March)
shows an average of 2.4 hours. The decreasing trend is very slow and it is not certain of
the cause. It could be due to many machine breakdowns as well as a new feeding system
that was implemented in the beginning of year 2008. Therefore the LPS coordinator,
Julio Guerrero, will revise the workshop and investigate what measures can be taken.
(Guerrero, March 2008)
Figure 72: Development of changeover times in machine 928
Development of registered changeover times, machine 928
1.00
2.00
3.00
4.00
5.00
M
a
y
-
0
7
J
u
n
-
0
7
J
u
l
-
0
7
A
u
g
-
0
7
S
e
p
-
0
7
O
c
t
-
0
7
N
o
v
-
0
7
D
e
c
-
0
7
J
a
n
-
0
8
F
e
b
-
0
8
M
a
r
-
0
8
Period
H
o
u
r
s
Time
Month avg. time
SMED workshop
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
83
5 ANALYSIS - Mapping of the 8 principal volume
products
The analysis phase of the final degree project was performed with the intention to list
the main problems in the production. The area of investigation was limited to the 8
references representing 61% of the total planned sales volume as mentioned in the scope
of the pre-study of this report, chapter 1.1.6.
As mentioned earlier in chapter 2.4, all references contain the components housing and
ball pin, but in the analysis for only 2 references both housing and ball pin were
analyzed. For the other 6 references, responsible of the production department chose
which component was more important to focus on based on his knowledge of the
situation of the production. (Herremans, 2007)
Following references were analyzed in a value stream analysis and a material flow
diagram.
PQ35 SBJ Ball pin and housing
PQ24/PQ25 SBJ Ball pin
PUNTO SBJ Housing
A7 OBJ Housing
PQ35 IBJ Ball pin
C307 OBJ Ball pin and housing
B58 OBJ Ball pin
B58 IBJ Ball pin
The analysis made it possible for the student to make a list of problems of the current
state and solution suggestions for each one by workshops. The list was given to the LPS
coordinator who selected those he found most relevant. His selected list together with
the value stream maps were presented at the yearly LPS planning meeting. The LPS
group was asked to rank the workshop suggestions in order of workshops they believed
would have the most positive impact. Their ranking was needed to enable the LPS
coordinator making the LPS workshop planning for year 2008. The analysis phase
procedure is illustrated in Figure 73 below.
Figure 73: Analysis phase procedure
5.1 Mapping - Value Stream Maps & Material flow diagrams
Value Stream Mapping (VSM)
To make the VSMs two methods of data gathering were used; collecting the data at the
machine or at the place where inventory was kept or taking the data from the company
SAP system or SCADA. The data is divided into two groups according to the method of
taking the information.
Mapping &
Analysis
LPS Meeting
(LPS group)
Ranking
Final Selection of Workshops
for 2008 (Steering Committee)
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
84
At machine & inventory
CT Cycle Time (seconds)
TPT Through Put Time (seconds)
I Inventory by machine or intermediate inventory (pieces)
SAP & SCADA
OP/sh Operators per shift (1 operator per shift / 3 shifts per day 1/3)
Qty Quantity produced (pieces / operator / shift)
BS Batch Size (pieces)
# ref Number of distinct references treated in the process
C/O Changeover frequency (number of changeovers / week)
C/O t Changeover time (hours)
Scrap (%)
GE Global Efficiency (%)
I
Inventory in warehouse or at supplier (pieces)
The VSMs were made according to the schedule, but some datas were not possible to
attain due to problems such as no production activities on the day of the mapping or
insufficient data about individual machines in SCADA. Before the presentation of the
analysis as much data as possible was obtained. In the cases when the data was not
available it was noted on the value stream maps and those maps not completed after the
presentation were left uncompleted since after the presentation and decision of
workshops for 2008, the maps would not be used again.
Material Flow Diagrams
The material flow diagrams were based on the VSMs and a layout map of the plant.
Machine numbers were noted on both the VSMs and the plant layout; therefore the
distance the material flows in the plant could be estimated. The distances were
calculated by using a scale layout of the plant and measuring the distance with a ruler.
The VSMs and material flow diagrams can be found in Appendix II and Appendix III.
5.2 Analysis Problems, solution proposals & LPS group
meeting
The VSMs were utilized to create improvement proposals. All data in the VSMs was
examined together with a list of critical machines which can be retrieved from SCADA.
In this case the list of critical machines was obtained by the LPS coordinator. The data
were discussed with the supervisor and thereafter a list of LPS workshop suggestions
was created. Approximately half of the suggestions were created together with the
supervisor and the rest were created by the student alone.
Three major types of workshops were suggested; OEE, SMED and PULL (See chapter
3.3 on page 38 for definitions). For the two former types of workshops following
criteria were used; low value on Global Efficiency, existence on critical machine list
and high values on changeover time & frequency. For the latter, a workshop was
proposed for all investigated references because no reliable criteria existed since it was
not possible to estimate a realistic stock size.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
85
All machines with a GE under 90 % were proposed as candidates for an OEE workshop.
Most candidates for SMED workshops have a changeover time above 2 hours and a
frequency of roughly 1.5 times per week. Some of the candidates that have lower values
are either based on discussion with the supervisor or chosen because the value was the
highest in the value stream of that reference.
The final list contained 41 workshop suggestions, and once the list was done it was
given to the supervisor who selected the 20 proposals he found most relevant. His
selected list together with the VSM analyses was presented at the yearly LPS meeting.
At the meeting the LPS group members discussed the proposals and agreed about the
suggestions they found most important. They deleted some proposals and added some
additional suggestions to the list, see Table 8 below. In the end of the meeting, a list
consisting of 18 suggestions and thereby shorter than in the original, was agreed upon.
The group members were asked to rank the workshop suggestions to enable the LPS
coordinator to make the LPS workshop planning for year 2008.
Two suggestions were missed during the presentation, number 19 and 20 in the list
below, so they were added to the list afterwards, thus in the end the list consisted of 20
workshop proposals. The list was e-mailed to the LPS group members for the purpose
of ranking it. The criteria for ranking was in order of which workshop they thought
would have the greatest impact in terms of money. The ranking was highly subjective,
and depending on the work responsibilities of each group member, the ranking looked
different. There are two reasons for asking the LPS group for advice when planning the
improvements: 1) the members come from different departments so the votes will not be
favorable for one specific department, 2) there exist no precise or scientific manner for
ranking workshop suggestions, and if it did exist the LPS groups opinion would not be
needed.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
86
Table 8: Workshop suggestions lis
# Workshop Type of workshop Area
1 I. PULL Assembly, Ball Pins, PQ35 SBJ
2 II. OEE Pre-assembly and Assembly, PQ35 SBJ
3 III. OEE Machining, Housings, machine 752, PQ35 SBJ
4 IV. PULL Assembly, Housings, PQ35 SBJ
5 V. SMED Machining, Housings, machines 787-777
6 VI. PULL Assembly, Ball Pins, PQ24/25
7 VII. PULL Assembly, Housings, PUNTO SBJ, G124
8 VIII. OEE Machining, Housings, machine 648
9 IX. OEE Assembly, PUNTO SBJ, G124
10 X. PULL Assembly, Housings, Delta line
11 XI. SMED Pre-assembly, Delta line
12 XII. SMED Assembly, Delta line
13 XIII. OEE Pre-assembly, Delta line
14 XIV. OEE Assembly, Delta line
15 XV. PULL Ball Pins, Delta line
16 XVI. PULL IBJs
17 XVII. OEE Machining, Ball Pins, IBJ, machines 614/615
18 XVIII. SMED Machining, Ball Pins, B58-X91-M1, Beta line
19 XIX. Optimization of
processes to control
external processes
and deliveries
Not defined
20 XX. Self control Place or reference not defined
5.2.1 Savings estimations
Savings estimations were made for some workshop suggestions on the list, but it was
not possible to estimate the savings for all proposals.
OEE
The ultimate goal of an OEE workshop is to reach the theoretical GE or OEE of 100%.
To find out the theoretical productivity Equation 3 was employed, and after the
difference between the theoretical and the real productivity was used in Equation 4. The
savings were finally calculated with Equation 5, see chapter 3.3.1.
SMED
During the final degree project it was not possible to calculate the actual possible
savings of a SMED workshop at ZF Ansa Lemfrder. It was only possible to calculate
the productivity increase due to the time freed by the decrease of changeover time,
assuming that all time freed is devoted to production only. The same equation as above,
Equation 5, is used to calculate the possible saving.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
87
The other way of calculating the benefits of SMED is the decrease of inventory and
thereby decreases of inventory costs. This was not possible at the time, because no
defined inventory levels existed.
PULL
Just like in a SMED workshop, the benefits of a PULL workshop will most likely be a
decrease of inventory as well as a decrease of throughput time. As mentioned before,
the economical benefits cannot be calculated. This is the reason why it was not possible
to estimate the savings of the PULL workshops.
5.3 Ranking of the workshop suggestion list
5.3.1 Subjective ranking by LPS group & savings estimation
Five out of nine LPS group members ranked the list of workshop suggestions. The
results of the ranking are shown in Table 9 below.
Table 9: Workshop suggestion ranking
Rank Workshop Type of
workshop
1 2 3 4 5 6 6 () Avg.
score
1 VIII. OEE 18 20 14 9 12 20 131,482 15.5
2 XI. SMED 17 18 20 8 20 8 53,383 15.2
3 X. PULL 15 15 11 19 15 - 15.0
4 XII. SMED 16 19 19 5 19 2 14,243 13.4
5 II. OEE 20 12 9 20 10 6 39,018 12.8
6 XV. PULL 6 11 15 14 16 - 12.4
7 VI. PULL 19 6 3 18 14 - 12.0
8 XIV. OEE 7 17 16 2 17 13 85,689 11.8
9 XIII. OEE 8 16 17 3 18 5 35,169 11.2
10 I. PULL 12 11 7 16 9 - 11.0
11 V. SMED 11 14 13 12 13 2 13,989 10.9
12 IV. PULL 14 10 5 13 8 - 10.0
13 VII. PULL 10 16 6 15 3 - 10.0
14 III. OEE 13 13 12 1 11 5 36,132 9.2
15 IX. OEE 9 4 4 17 7 7 47,740 8.0
16 XVII. OEE 1 8 18 6 5 5 32,793 7.2
17 XVI. PULL 2 7 8 10 6 - 6.6
18 XVIII. SMED 5 9 2 11 11 - 5.8
19 XIX.
Optimization
3 3 10 4 4 - 4.8
20 XX.
Self control
4 5 1 7 1 - 3.6
The five LPS group members ranked the suggestions by giving them a score between 1
and 20, where 1 signifies the smallest impact and 20 the largest impact. The ranking
was integrated together with the savings estimations made for the workshops, and the
list was ordered by the average score of each suggestion. See also Appendix IV.
Since not all workshops savings could be estimated, the assumption was made that the
maximum value of those evaluated was the maximum value of all suggestions on the
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
88
list. Thereby the scores could be set by using the equation below, making it possible to
rank also the 10 proposals that had savings estimations: (Guerrero, 2007)
Equation 12: Ranking of workshop proposals with savings estimations
Rank
MaxEuro
xEuro
=
20
[12]
Example of score calculation based on cost estimation using Equation 12 (workshop
suggestion XVII, OEE)
5 9 , 4
131482
20 32793
=
5 points
The ranked proposals were placed in a diagram visualizing the impact, effort and
probability of success, see Figure 74 and Figure 75 below. In the diagram the order of
implementation of each workshop was numbered by the LPS coordinator. Note that the
order differs from the ranked list. This is due to the probability of success factor; the
workshop with the highest probability of success was chosen to be carried out first.
Another difference from the ranked list is that number 6, 7 and 10 from the list have
been placed to be carried out in the same PULL workshop because they treat the same
topic and the same type of components.
Figure 74: Diagram showing the order of workshop implementation
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
89
Figure 75: Explanation of figures in the diagram
The higher the effort the more the workshop would cost to carry out. The higher the
impact the bigger economical savings might be. The ultimate workshop would be
marked with a green circle, placed in the top left corner. That workshop would imply
that the economic savings would be fairly high, the cost of carrying out the workshop
would be low, and the probability of success high. The opposite of those results would
be produced by a workshop placed in the bottom right corner. The diagram above was
based on following factors (Guerrero, 2007):
Impact (scale 1-20)
Based on subjective rankings and calculated savings estimations
Effort ()
Based on cost estimations made by the LPS coordinator; Number of days, Number of
participants per day, Investments, Hours of external help (all except workshop
members), Extra hours to maintain changes afterwards
Probability of success (3=high, 2=medium, 1=low)
Subjective estimation made by LPS coordinator,
Below in Table 10 is the final list of workshops, in order of which was planned to be
carried out first.
Table 10: Final workshop list of 2008
# Type Area
1. SMED Pre-assembly, Delta line
2. OEE Machining, Housings, machine 648
3. PULL Assembly, Housings, Delta line
4. SMED Assembly, Delta line
5. OEE Pre-assembly and Assembly, PQ35 SBJ
6. PULL Ball Pins, Delta line + PQ24-25 + PQ35
7. OEE Assembly, Delta line
8. SMED Machining, Housings, machines 787-777
9. OEE Pre-assembly, Delta line
10. PULL Assembly, Housings, PQ35 SBJ
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
90
5.3.2 Final selection/approval of LPS topics year 2008 - Steering
committee
The LPS coordinator gave the workshop plan to the technical director of the company,
who approved it in December 2007. Thereafter a schedule for the first 6 months of LPS
activities was set by the LPS coordinator. The steering committee approved the plan in
the beginning of 2008. Their decision was not very urgent, because at the time there was
no top-manager at the company because the previous retired in December 2007, and the
new top-manager did not arrive until February 2008.
5.4 Analysis of supermarket, safety stock and batch sizes
As a part of the analysis of the final degree project, the student was asked to estimate
the maximum and minimum inventory levels needed in each mapped process (i.e. 10
processes). The student attempted to calculate the appropriate inventory levels since
those calculations could be used for estimating cost savings for the ranking of the
workshop suggestions. After a few days of research about supermarket sizes, it was
concluded that it is very difficult to calculate the levels due to lack of some crucial data.
Also, the necessary data might change until the supermarket is implemented, so it would
be better if the calculation is done at the time of implementation of the inventory levels.
Therefore the student and the supervisor agreed that it is better to let the estimation of
inventory levels be done at the moment needed. And even though it was agreed not to
calculate the inventory levels, the manner of doing it is explained in this chapter for
possible future use at ZF Ansa Lemfrder.
The premises for installing supermarkets were explained in the LPS PULL workshop
chapter 3.3.4. And as mentioned before, each premise needs to be fulfilled; otherwise
the supermarket inventory levels might become higher than the levels in a regular
inventory system. The premises are as follows:
1. Assure stable supplies before implementation
Stable, 100% reliable material supply
2. Do only implement on reliable and well-tried processes
Stable processes
3. Study demand history and sales forecasts in to assure that the demand is stable
Levelled production (small variations in demand)
4. Decide frequency of component deliveries
Short preferably standardized transport cycles (takted supply)
5. Decide frequency of Kanban pickup
Information flow fast as possible (takted)
6. Implement batch sizes for all internal processes
Short changeover times small batch sizes
7. Investigate need for changes in packaging or quantities for internal processes
Optimized packaging for next process / customer
8. All concerned employees must receive sufficient training before implementation
Knowledge of employees (information, training)
+ Estimate (or calculate) the necessary safety level of inventory for all
components
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
91
The premises written in bold above were not fulfilled at the time of the final degree
project, therefore it was not possible to make a reasonable estimation of the inventory
levels. Following are suggestions of actions which ZF Ansa Lemfrder could do to
fulfil the premises. The actions were discussed with the technical director of the
company in December 2007.
5.4.1 Decide frequency
The frequencies of component deliveries and order or kanban pickups must be decided.
The logistics, production and planning departments must agree on the frequency of
deliveries and who is to deliver the goods.
5.4.2 Batch size
A batch is a quantity produced at one operation. It can also be called lot. It is a definite
quantity of some product manufactured under conditions of production that are
considered uniform. (Oxford English Dictionary, 2008)
At the time of the final degree project there existed no defined standard batch size for
the raw material and the machined material at ZF Ansa Lemfrder. Instead, the batches
depended on the amount of pieces the supplier provides, and usually the suppliers
batches are a random amount of components for each delivery. But for the assembled
pieces there is always a batch size according to the customer request. Figure 76 below
illustrates where the batch sizes are not defined.
Figure 76: Batch sizes at ZF Ansa Lemfrder
The minimum batch size depends on factors such as changeover time, costs for storage,
ramp-up problems after changeover, experience, etc. One guideline for deciding a
Process:
Machining
Process:
Assembly
SUPPLIER
Inventory
size ?
Inventory
size ?
CUSTOMER
Inventory
size ?
Raw Material Machined Material Finished Product
Random
Batch Size
Batch Size Based on
Customer Request
Explanation of Batch Size Arrows
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
92
lean batch size is to calculate the economic lot size, following information is needed
for that:
Setup cost Labour and material for changeover
Storage cost Carrying cost per unit, average cost for storing an average production
unit for average time
Example: Economic lot size (ELS) for BTB 928, housing machining
Below is an example illustrating the Economic lot size of A7, See also Figure 77.
Following data and calculations were used. (Syamil, 2008)
Average changeover time 3 hrs
Operator salary 27.27 /hr
Demand a a = 1500 pieces/day
Lot size b b pieces
Lots per day c a / b = c lots / day
Average storage time x x = 1 / 2c days b / 2a days
Set up cost = (Labour cost/hour * Avg. Changeover time) / batch size pieces = x / piece
Storage cost = cost per piece per day * average storage time = x / piece
Total cost = changeover cost + storage cost
ELS 18 000 pieces
Note: If lower ELS are a shorter set up time will be necessary. A set up time of 1 hour would give an ELS
of 12 000 pieces.
Figure 77: Example of Economic Lot Size calculation for BTB 928, A7
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
93
The graph above in Figure 77 shows that the economic lot size is 18 000 pieces at the
point of the curve where the total cost is minimum. But since the curve of the total cost
is quite flat it is better to choose a lower quantity of the batch size, since it will increase
flexibility and makes the inventory levels lower which will release space. The lot size
could be set to 12 000 pieces or even 9000 pieces if the production responsible believes
that the benefits of having a more flexible system are greater compared to the costs of
changeovers. The economic lot size can be rounded up to an appropriate unit, such as
production of 1 day or 1 shift.
The current average batch size of machine BTB 928 is about 8000 pieces in average,
based on that there were 120 changeovers and 960.000 pieces produced in 2007. This is
lower than the ELS calculated in the example above, which was between 12 000 and
9000 pieces. But in fact the batch size of the machine is not always 8000, it usually
differs for each batch and can be smaller or larger than 8000. The size of the batch (or
order for changeover) often depends on the availability of raw material as well as
customer demand.
It is important to point out that the Economic lot size is only a guideline because of two
reasons; 1) Other factors affect the needs of the production, such as delayed deliveries
causing the need of urgent changeovers; hence the quantity needs to be chosen with
care, 2) The economic benefits of having smaller batch sizes is not easy to calculate, but
there are benefits such as; shorter lead time, increased quality, smaller stocks and
increased flexibility.
Hence caution should be taken when picking a batch size, the decision should not only
be based on the economic batch size, but also other benefits such as those mentioned
above needs to be considered. It is important that experienced personnel are involved in
the decision of the size of the batch for each reference. Most likely, planning,
production, logistics and maybe purchase departments will need to give their opinion
about the batch size.
5.4.3 Safety stock
As explained in the report, the safety stock levels can be set based on experience. This is
probably the easiest way, since there are many experienced employees at the company.
If it turns out that it is too big or too small, it is easy to change the size of the safety
stock, assumed that there is a follow up after the implementation. (Steffen, 2007)
Just like in the other two cases, it is important that experienced personnel from involved
departments are a part of the decision of the size of the safety stock. Involved in the
decision should be the planning and production departments, maybe together with
operators and shift leaders who know the production very well.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
94
6 IMPLEMENTATION - LPS workshop SMED & 5S
6.1 Choice of topic
After discussions it was agreed that the workshop topic would be SMED and 5S since
that was also the topic of the practice workshop in which the student participated in as a
pre-study. But in year 2008 a new way of defining a workshop was implemented at ZF
Ansa Lemfrder, making it necessary to separate the main topics of the workshops.
Therefore, two separate consecutively workshops on the same machine, SMED and 5S,
were chosen as the topic for the final degree project.
The reason to the change was that the global LPS group had seen a summary of the
workshops of the past year, 2007, and had pointed out that ZF Ansa Lemfrder had a
very low number of workshops compared to other plants in the group. The cause for
that was that in each workshop run at Ansa, 5S was included. While at the other plants,
5S was always done as a separate workshop. Therefore the LPS coordinator decided it
was better to separate all workshop topics in order to follow the Lemfrder group
standards.
The proposed area in the plant was the Delta line pre-assembly machine 935, based on
the list of planned workshops for 2008. See Table 10 in chapter 5.3.2. But when
discussing the topic with Emiliano de los Mozos of the engineering department who has
a lot of experience from the Delta line, he said that the changeovers for that particular
machine usually do not take more than an hour. He suggested that another machine,
assembly machine 936 in the same production line should be investigated instead. Both
machine 935 and 936 were on the list of planned workshops for 2008, but the LPS
coordinator found it important to start the year with the workshop on the machine with
the longest changeover time. It was decided that two preliminary observations of
changeovers, one of each machine, were to be done before taking a decision of which
machine to focus on. (de los Mozos, 2008)
6.1.1 First preliminary observation Delta line machine 935
On December 18
th
2007 the preliminary observation of the changeover in pre-assembly
machine 935 was made. All the actions the operator made during the changeover were
written down together with the duration and classification of operations. The data was
thereafter transferred into an excel template do create a waterfall diagram, see Figure
78.
The total time of the changeover was 98.5 minutes (1.64 hrs), and the main parts of the
changeover time were; Mechanical changeover (47%), Waiting (18%) and Movements
(16%).
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
95
Figure 78: Waterfall diagram of classified activities, preliminary observation of machine 935
Also the registered times of the machine from SCADA were collected for comparison
purposes between the two machines. The graph below in Figure 79 illustrates all the
changeovers registered during the period 01/06/2007 30/11/2007 which equals 98
work days at ZF Ansa Lemfrder. During this period the average changeover time
registered in SCADA were 2,1 hours at a frequency of more than one changeover per
day (1.3 per day).
Figure 79: Registered changeovers during period 01/06/2007 30/11/2007
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
96
6.1.2 Second preliminary observation Delta line assembly machine 936
On December 21
st
2007 the preliminary observation of the changeover in assembly
machine 936 was made, see Figure 80. The observation followed the same procedure as
for the previous observation of machine 935. The total time of the changeover was 62.5
minutes (1.04 hrs), and the main part of the changeover time was; Mechanical
changeover (76%).
Figure 80: Waterfall diagram of classified activities, preliminary observation of machine 936
During the period 01/06/2007 30/11/2007 the average changeover time registered in
SCADA were 2,05 hours at a frequency of almost one (0,92) changeover per day. The
changeover duration average is 0.05 hrs shorter than for machine 935 also the
changeover frequency is lower. See Figure 81.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
97
Figure 81: Registered changeovers during period 01/06/2007 30/11/2007
6.1.3 Final topic SMED and 5S on Pre-assembly machine 935
The observations and data from SCADA of the two machines showed that the pre-
assembly machine 935 needed longer time for changeover and undergoes changeovers
more frequently. See Table 11. Hence it was decided that the workshop should focus on
machine 935.
Table 11: Comparison of changeover observations
Pre-assembly 935 Assembly 936
Average changeover time 2,1 hrs 2,05 hrs
Changeover frequency 1,3 times/day 0,92 times/day
Duration of observed
changeover
98,5 min (1.64hrs) 62,5 min (1.04hrs)
Many factors affect the duration of a changeover, such as operator experience, material
supply and unexpected problems. Also the way of registering the time might differ from
case to case depending on the operator or if it is in the end or beginning of a shift.
Despite the knowledge of that those factors might have affected the measured and
registered times, it was decided that it was better to chose the machine with the longer
duration. Either way, the second machine was planned to be a part of a SMED and 5S
workshop later the same year.
6.2 Planning and preparations
The preparations of the workshop consisted of making a schedule and worksheet with
objectives and initial data, inviting the team members, informing and inviting the LPS
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
98
group and steering committee to the workshop presentations, reserve the LPS room and
equipment etc.
The checklist in Appendix V was followed in order to prepare for the workshop
contents. It includes the main steps of the workshop, together with necessary
preparations and the responsibilities of the coordinator during each step of the
workshop.
6.3 The workshops - SMED and 5S
6.3.1 Schedule
In Appendix V is the schedule which was handed out to all workshop members three
days before the workshop started. The scheduled was followed without any changes.
The members also received a copy of the workshop definition sheet which contains
objectives, times and team members names etc. See Appendix V.
Two timetables existed for the workshops; one full time of eight hours per day and one
reduced of three hours per day. The latter one was needed since some departments were
not able to spare one person for eight hours per day, but they agreed on the compromise
of participation three hours per day.
6.3.2 Workshop teams
The workshop teams consisted of following members:
SMED team members
From the left:
Sarah Johnsson (LPS & coordinator)
Benedicto Aparicio (Engineering)
Luis Maria Prez (Maintenance)
Ricardo Garca (Engineering)
Jos Moreno Murillo (Machine 935)
Julio Guerrero (LPS)
Csar Blanco (Quality)
Emiliano de los Mozos (Engineering)*
5S team members
From the left:
Benedicto Aparicio (Engineering)
Sarah Johnsson (LPS & coordinator)
ngeles Ruiz Gonzlez (Machine 935)
Ricardo Garca (Engineering)
Julio Guerrero (LPS)
Jos Javier Villanueva (Sales)
Emiliano de los Mozos (Engineering)*
*Not in picture
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
99
As mentioned in chapter 3.3.2 the SMED workshop team should consist of the
following members, but in this case no setter exist at machine 935 and the design
department did not participate in the workshop.
LPS-Trainer
Setter
Operator
Maintenance
Responsible for the area (production cell manager, team leader, )
Production engineering
Quality
Design
The operators at ZF Ansa Lemfrder work shifts. There exist three shifts per day, and
every week they alter shift. The workshops were held during 7 days, i.e. 5 days the first
week and 2 days the second week. Therefore, the participating operator of machine 935
differed for the two workshops. In the SMED workshop members from maintenance
and quality participated, while during the 5S workshop they could not participate.
Furthermore, in the 5S workshop, a sales engineer from the sales department was able
to participate on a reduced schedule. This was the first time a person from the sales
department participated in a LPS workshop.
6.3.3 Method
The workshop was carried out during seven days in accordance to the eight phases of a
typical LPS workshop; see Figure 17. What was completed during each phase is
explained further on. Just like the practice workshop, the workshop was held in the LPS
room at ZF Ansa Lemfrder. But this time only three presentations were held, the
intermediate SMED presentation and the final presentations of SMED and 5S
respectively. During the workshop, the important points from the pre-study workshop
were followed, see chapter 4.5.
Figure 17: LPS phases
Phase 1
Education
Before 1 - 2 weeks
Phase 2
Objectives
& tasks
Phase 3
Analysis
Phase 4
Ideas and
solutions
Phase 5
Implement
solutions
Phase 6
Evaluate
results
Phase 7
Standardi-
sation
Phase 8
Comun-
icate
results
Organizer:
Methods &
insights
Workshop team:
Generate,
implement and
verify improvements
plan
do check
act
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
100
6.4 The SMED workshop
6.4.1 Phase 1 & 2 - Education and objectives
The SMED workshop was held during 5 days, starting on Monday February 3
rd
2008.
The first hour of the first day a one hour presentation about SMED was held for the
whole team, and in accordance to the important points of the pre-study workshop, the
rules during the workshop were explained. Also, the area to be studied was presented as
well as the objectives.
The studied machine was a pre-assembly machine (935) in a line called the delta-line.
The delta-line consists of two pre-assembly machines and three assembly machines.
The pre-assembly machine 935 is connected with two assembly machines, 936 and 937.
Pre-assembly machine 935 assemble four references, A7, X91, B58 and ALFA 939,
whereof the three first goes to assembly machine 936 and the two last goes to assembly
machine 937. See Figure 82 below.
Figure 82: Layout Delta line
The target machine, pre-assembly machine 935, see Figure 83, preassembles ball joints
by assembling four components. Thereafter the pre-assembled ball joints are transported
on a conveyor belt through an oven for heat treatment, and are thereafter transported on
a belt to the destination assembly machine. One operator per shift works 100% at the
pre-assembly machine.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
101
Figure 83: Pre-assembly machine 935
Objectives and initial state
As mentioned in chapter 6.1, the historical changeover time of machine 935 was and
average of 120 minutes during the period October 1
st
2007 January 14
th
2008, with a
frequency of roughly 1 changeover per day (the frequency changes from month to
month). This was set as the key value, and the objective of the workshop was a 50%
decrease of the key value of the changeover time. Another objective was to decrease the
movements and transportations during the changeover by 50%, see workshop definition
sheet in appendix V. The initial value of the movements was not known in the
beginning of the workshop, but was to be measured during the observation of the
changeover. The third and last objective was to simplify the changeover, and since this
is a highly subjective objective no key value or means for measurement was set. The
above objectives are standard LPS objectives when running a SMED workshop.
Statistics of machine 935 showed that the main reason for machine stops was
changeovers. The changeovers were responsible for 54 hours of stops, i.e. 32% of the
total amount of stops during the same period mentioned above. (All data from SCADA)
See Figure 84 below.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
102
Figure 84: Pareto diagram of causes for machine stops (pre-assembly machine 935)
6.4.2 Phase 3 - Changeover observation and analysis
A changeover was performed by Jose Moreno Murillo, one of the workshop team
members and also operator at machine 935. He was asked to make the changeover in the
same manner as usual, and the rest of the team observed the work and documented it as
planned through video, photos and drawing the movements. Thereafter, the collected
data was analysed by listing all the changeover operations, classifying all activities and
next making the following graphs (Figure 85, Figure 86 and Figure 87)
Figure 85: Classified activities first changeover observation of machine 935
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
103
Figure 86: Internal and external activities of first changeover observation of machine 935
Figure 87: ECRS analysis of first changeover observation of machine 935
The diagram with the classification of the operations shows that the two operations with
the longest duration are mechanical changeover and adjustments. The analysis of
whether or not the operations had the potential to be internal or external showed that the
majority of the activities need to be internal, only 4 minutes (i.e. about 8%) could be
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
104
converted into external activities. The ECRS analysis shows that the team estimated that
several operations could be simplified and a few be eliminated or combined. The
spaghetti diagram from the observation showed that the operator had moved 391 meters
during the changeover. See appendix V.
6.4.3 Phase 4 & 5 - Problems, tasks and solutions
Looking at the analysis the team started to discuss the main problems causing the long
durations of the mechanical changeover and the adjustments. The team was enthusiastic
and came up with many ideas without the need of guidance from the coordinator.
The analysis showed that there was not one main operation, rather several shorter
activities. Therefore, several tasks were created with the hope that the total amount of
time savings created by the implementations would be enough to create a decrease.
Following are the 16 problems thought of during the workshop, together with tasks and
implementations.
Problem It is difficult to fasten the guides of the ball pins and seats, very time
consuming to screw down the screws since they are long.
Task Look for alternative systems to tighten the guides for ball pins and
seats.
Final solution Rapid changeover washers were added so that the operator does not
need to screw down the screws as far down as before. Also, the
washers were fastened in the machine by chains to eliminate the risk of
loosing the washer during changeover.
Problem While exchanging some tooling inside the machine the operator starts
to take out the eight old ones and thereafter place the eight new ones.
The separation of operations (that could be combined) is a waste.
Task Investigate possibility of combine the exchange of tooling
Final solution An additional space for putting tooling was created, enabling the
operations to be combined.
Problem The emptying of the feeder drums for seats and end caps is time
consuming and sometimes ergonomically incorrect.
Task Investigate possibility to empty the feeders of seats and end caps
automatically
Final solution The feeder drum for the seats already had an automatic function for
emptying that was not known to the operators; this function was put
into the new procedure of the changeover, also a stand was made for
placing the box where the seats will exit during emptying. The feeder
drum for the end caps also had the same function, but the drum is
covered with a sound reducing shell which disables the function of
automatically emptying the end cap feeder. But to facilitate the
emptying of the feeder a stick with a magnet attached on the end was
placed next to the feeder. This makes the work a bit easier.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
105
Problem The operator transported components, to and from the same storage
area, but separate times for each component. The number of transports
could be decreased.
Task Find a way to transport components at the same time and make it a part
of the new changeover procedure.
Final solution The task was rejected. The operator did not like the idea of transporting
the components at the same time since it is more convenient to have
the components on their individual carts next to respective feeder. If
the cart would be shared between the components it would either
increase the movements when filling the feeder during the regular work
or would require lifting and moving the boxes of components to put
them next to the feeder.
Problem Loading the feeders was difficult since the operators only tool to fill
them were boxes designated for storing ball pins; the only other option
was to use their hands.
Task Find a way to simplify filling end caps and seats into the feeders.
Final solution Small shovels were purchased and hung by each feeder.
Problem The end cap guide did not have visual marks for different references.
This made the adjustments of the guide difficult and the operator
depended on trial and error, including walking in and out of the
machine, to get the adjustment right
Task Make it easier to adjust the end cap guide
Final solution One guide for each reference was produced. The new guides are easy
to take out and exchange, so the total duration of exchanging the new
guides is shorter than the duration of adjustments
Problem At the conveyor belt there is a protection shield to prevent accidents.
There were two shields for the four references, and depending on the
references the shield was exchanged. The exchange of shields was
unnecessarily time consuming
Task Simplify the mounting of the conveyor belt protection or investigate
the possibility of unifying the protection shields
Final solution The protection shield was unified so that all different references can
use the same shield, eliminating the need of exchanging it
Problem When the flanging station tool was exchanged, the operator had to go
out of the machine to fetch a tool and thereafter return into the
machine.
Task Place tool by flanging station
Final solution the necessary tool was placed by the flanging station inside the
machine
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
106
Problem During production, the operator checks if the thread of the housing is
cantered, by putting the housing in a special control tool. In each
changeover the operator exchanges the control tool. But the team
thought it was strange that the thread had to be checked in pre-
assembly because the thread is also checked in the process before
Task Eliminate thread centre check at machine 935
Final solution The quality department agreed to eliminate the quality check for three
out of four references, eliminating the need to change the control tool
Problem Dust from the flanging operation makes it dirty in the machine
Task Find a way to improve machine cleanliness
Final solution The team placed a source for compressed air in the machine and
defined in the new changeover procedure to vacuum clean the fixtures
of the tooling during each changeover. (to avoid machine breakdowns
or poor quality due to the dirt)
Problem The changeover times for different operators differs. The workshop
team thought that one reason is that the changeover standard procedure
is not clear enough
Task Define new standard procedure for changeover and teach it to all
operators of machine 935
Final solution New standard procedure was created during the workshop
Tasks not finished during the workshop (29/02/08)
Problem There is a tool for marking the; logotype, reference and week of
production. To change the reference or week the machine needs to be
stopped, i.e. an internal operation. But if there would be a duplicate of
the tool the operation could be done externally.
Task Duplicate the marking tool to make the operation external
Final solution Not finished during final degree project
Problem Usually the operator does not know ahead when the next changeover
will take place. If the order of a changeover comes right after the
operator has filled all the feeders of the machine, it will make the
changeover duration longer since emptying the feeders is time
consuming
Task Find a production planning solution to ensure that the operator is
informed of the changeover at least one hour earlier, so that the
operator can avoid filling the feeders.
Final solution Not finished during final degree project
Problem It is time consuming to adjust the ball pin rail
Task Find a way to simplify the adjustment
Final solution Holes were made in the rail, which makes it possible to find the right
position without any adjustments. Finished in end of February 2008
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
107
Problem Changing the feeder plate is time consuming
Task Investigate possibility to unify the feeder plate for all references
Final solution A CAD model of the new feeder plate was made, but the physical plate
was not produced during final degree project
The tasks not finished during the workshop were noted in the kaizen book. The
important point of phase 5 (see pre-study, chapter 4.5.4) was that all tasks should be
carried out during the workshop, and this was nearly achieved except for four tasks
which were carried out later by the persons responsible for respective task.
6.4.4 Phase 6 - Result evaluation
Right after most of the tasks had been implemented, the changeover was observed a
second time. The team documented the changeover in the same manner as before, and
the results are illustrated in the following waterfall diagram, Figure 88.
Figure 88: Comparison of first and second changeover observation, machine 935
The total time of the second changeover was 44,9 minutes (44 minutes and 55 seconds)
see Table 12. Compared to the first changeover observation, which had the duration 55
minutes, i.e. the total time was decreased by 18%. But if looking closer on the duration
of the classified activities we can see that the decrease was affected by three factors:
mechanical changeover activities, adjustment activities and machine breakdown
activities. The mechanical changeover activities duration were reduced by 9,4 minutes,
i.e. 27,5% decrease compared to the first changeover, and the adjustments by 9,1
minutes, i.e. 64%. But during the second changeover observation some machine
breakdowns occurred which did not happen during the first changeover. The
breakdowns had a duration of 10,4 minutes.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
108
The movements of the operator during the second changeover observation were actually
30% greater than in the initial observation. It can be explained by the breakdowns
during the second observation. During the breakdown, the operator had to walk back
and forth from the control board and various parts of the machine in order to find out
what was wrong with the machine.
Note that in the second observation the duration of the movements was zero, but that
was in fact not true. During the classification of the activities the movements were
forgotten, but one can assume that the duration increased due to the breakdowns.
Table 12: Duration of changeover activities and Movements during changeover
Duration
Classification Initial duration Duration after
improvements
Difference
Movements 00:01:15 00:00:00 - 100%
Documentation 00:01:50 00:02:35 + 41%
Adjustment 00:14:39 00:05:15 - 64%
Control 00:00:37 00:00:50 + 35%
Mechanical
changeover
00:33:14 00:24:06 - 27,5%
Cleaning 00:00:00 00:00:00 ----------
Breakdowns 00:00:00 00:10:24 +
Transports 00:03:25 00:01:45 - 49%
Waiting 00:00:00 00:00:00 ----------
TOTAL duration 00:55:00 00:44:55 - 18%
Movements
Initial After improvements Difference
391 m 507,5 m + 30%
One can suppose that the time decrease of the mechanical changeover steps as well as
the adjustments will be maintained, since those activities look the same for any
changeover and are unlikely to be affected by outer circumstances. The total decrease of
the two activities mentioned above was 18,45 minutes, i.e. 39%.
If we would assume that the breakdowns had not occurred, i.e. giving a total duration of
34,5 minutes, the decrease of the total changeover time would have been 37%. But since
machine breakdowns do occur and may be hard to control, it is not reasonable to make
the assumption that the future average changeover time would be decreasing due to the
improvements. However, the improvements did decrease the duration for mechanical
changeover activities as well as adjustment activities during the second observation.
Just as mentioned in the important points of the pre-study workshop, it is important to
keep in mind that the key value in the objective if the workshop, which was a 50%
decrease of the average registered changeover times. Thus both observed changeovers
during the workshop reached the goal value.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
109
6.4.5 Phase 7 - Standardization
The objective of the workshop was to decrease the average changeover time from 120
minutes to 60 minutes. The observed changeovers lasted less than 60 minutes, so the
team agreed that the procedure was a best practice, and that it could be used as an
example for making a new changeover procedure. Normally the changeover procedure
consists of a written document which does not contain any pictures, and it is placed on
the machine. In order to make the procedure more obvious the new procedure was
visualized with photos. It was placed on the machine in two versions; one document of
6 pages with all steps of the procedure written and illustrated by pictures, see Figure 89,
and the second version were made on cards with text and pictures, which were placed at
the location in the machine which it was referring to, see Figure 90.
Figure 89: New changeover procedure, collected 6 page document
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
110
Figure 90: New changeover procedure, instruction card placed on machine
The factors that affect a changeover duration are many. The operator might be working
faster than usual since she is being observed, also the operator experience level will
affect the outcome. Other factors which the operators cannot influence, such as delayed
material deliveries or machine breakdowns, will also show in the duration.
When observing only two changeovers it is impossible to detect all possible problems
that might occur during the changeover. Therefore the attitude during workshop was;
the problems we see now are what exists and is what we will solve. As mentioned in
the important points of the pre-study workshop, the standardization of the changeover
helps to measure the effect of the SMED workshop, and a few months after the
workshop it should be possible to see the effects of the workshop in the data registered
by the operators.
6.4.6 Phase 8 - Communicate results
In the final presentation of the SMED workshop the analysis, implementations, results
and future work were summed up. The audience did not have any particular remarks of
questions so there were no discussions regarding the workshop topics.
A report summarizing the workshop in the size of an A4 sheet of paper was made and
sent to the global LPS group. This is a standard report which is done after any LPS
workshop at all Lemfrder plants. See Appendix V, LPS workshop report.
One month after the workshop ended the operators had still not received education
about the new changeover procedure.
6.5 The 5S workshop
6.5.1 Education and objectives
The 5S workshop was held during 2 days starting on Monday February 11
th
2008. The
first thing of the 5S workshop was the education, which was held during the one hour.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
111
After the education the area of study and objective of the workshop were
communicated. The area of study was the same as before, namely machine 935, and the
objective was 25 points out of 25 on the subjective 5S evaluation. The workshop
followed the procedure of the 5S methodology, namely; Sift, Set, Shine, Standardize
and Sustain. The initial value of the 5S evaluation sheet was 10 points.
6.5.2 Sift and Set in order
The operator was helped by the team to put away all the objects not needed at the
workstation. The objects that were needed at the workstation were left at their original
place, and the other objects were placed in one out of three possible boxes; one for
throwing away, one for using in other part of the plant and one for storage near the
workstation, see Figure 91. Thereafter, all objects still at the workstation were put in
order by situating them in the place where needed most. The place for each thing was
visualized by tape on the floor, signs, etc. See Figure 92.
Figure 91: Tool box at pre-assembly machine 935 before and after "sift"
Figure 92: Clear signals of where things belong
6.5.3 Shine and Standardize
The whole workstation was thoroughly cleaned and cleaning supplies were placed at the
workstation to facilitate the cleaning in the future. A standard for cleaning the machine
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
112
at the end of each shift already existed, but according to one of the operators the way
each operator performed the cleaning differed and sometimes some operators even
forgot to clean. A standard procedure of cleaning was agreed upon with the operator,
and two documents were created and put on the machine in a place visible for everyone.
The first document contains pictures of how it is supposed to look like in the end of
each shift. The second document tells exactly what cleaning activities needs to be done
in the end of the shift and also instructs what cleaning is to be done during changeover
of the machine. See Figure 93 below. The reason to the specific cleaning during
changeover is that some cleaning can only be done when the machine is stopped or
when tooling is being replaced.
Figure 93: New cleaning standards
6.5.4 Sustain
The operators of machine 935 were to be educated in the new cleaning procedure at the
same occasion as the education for the changeover procedure. The standards created
during the workshop were hoped to be followed, but there is no guarantee that it will
happen because at the moment there are no auditory activities of the 5S workshops at
ZF Ansa Lemfrder. The reason is that they do not have enough resources for those
activities; also there exist no standard auditory procedure. A second 5S self evaluation
was made after the implementations and it had a score of 17 points, i.e. an increase of
10 points.
6.5.5 Communicate results
The 5S work was summarized and presented for the steering committee and the LPS
group. No questions were asked after the presentation.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
113
6.6 Lessons learned during the SMED & 5S workshops
After the SMED and the 5S workshops the team discussed what should be done
different in the next workshop. Following points were brought up:
Personnel from quality department need to participate during the whole workshop,
try to involve them next time.
Try to involve all operators of the machine in the workshop if possible, as well as
the shift leader or group leader. One solution might be to start the workshop on a
Thursday and finish on a Wednesday, which would allow at least two different
operators to participate.
It was positive to film the changeover, it made the work easier. Continue with it.
It is important that the objectives are clear from the first day since it will make the
team members focused on their tasks in order to reach the goal.
The LPS room where the workshop education, activities and presentations are
carried out becomes very hot. The LPS coordinator has contacted the relevant
department for fixing it.
Search a way to inform about new changes and the reasons to the changes to the
operators not participating in the workshop, in order to avoid surprises.
It would be better to have the two final presentations (SMED and 5S) at the same
occasion with the aim of keeping the audiences attention.
6.7 Results and follow up
After any workshop at ZF Ansa Lemfrder the tasks that were not finished during the
workshop are registered in a kaizen book. The kaizen book is not a book as it might
sound like, it is rather an excel document containing all unfinished tasks, responsible
person and estimated date of termination. The document is updated by the LPS
coordinator on regular basis until all tasks are done. All but one of the tasks of the
kaizen book were finished during the final degree project. The task not finished was the
feeder-plate modification.
According to the LPS workshop procedures, four weeks after the workshop the group
should meet again to see if the improvements are sustained. However, for the LPS
workshop of this degree project, the last meeting was not held because the student was
no longer present at ZF Ansa Lemfrder at that time.
At the time of the end of this final degree project it was still too early to see clear
changes in the changeover time statistics. But after the project on March 25
th
2008,
more than one month after the workshop, the registered changeover times were
followed up by the LPS coordinator Julio Guerrero. The trend shows average
changeover duration of 55 minutes in March which is below the objective of 60
minutes, Figure 94 and Appendix V. The decrease occurred even though the operators
were not educated during this period. The LPS coordinator and shift leaders believed
that the education was not necessary since the new changeover procedure was clearly
posted on the machine and easy to comprehend. Therefore they consider that the
education abundant if the procedure is easily understood. (Guerrero, March 2008) But it
still remains to see whether or not the durations will be stable in the future.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
114
Development of registered changeover times, machine 935
0.0
0.5
1.0
1.5
2.0
2.5
3.0
Oct-07 Nov-07 Dec-07 Jan-08 Feb-08 Mar-08
Period
H
o
u
r
s
Time
Month avg. time
SMED workshop
Figure 94: Development of changeover times, machine 935
6.8 Workshop benefits
The workshops will hopefully have a positive impact on inventory levels and the
throughput time of the product, or on the productivity of the machine. A productivity
increase can easily be translated into an economic benefit, while a decrease of inventory
level and throughput time are harder to estimate.
The workshop gave more employees at the company the opportunity to learn more
about LPS. The LPS needs to be taught to all employees before the end of 2009, so this
workshop was yet another step towards that goal. Also, the experience gained by the
employees is a valuable resource for further LPS work.
After the improvement implementations on the machine, the operators found several
changeover steps easier. Also some ergonomic improvements ease their work, such as
the magnet for picking up end caps and shovels for filling the feeders. Also, the shorter
adjustment times of some operations eliminates some work with bent back.
Furthermore, the operators spontaneously started to give many improvement ideas after
the workshop, which imply that their involvement in the workshop made them
understand that their involvement contributes to their workplace.
6.8.1 Economic benefits
Calculating the economic benefits of a SMED workshop is a difficult task, since there
exist no standard way to do it in the Lemfrder group. The following is only a
simplified way meant to illustrate and facilitate comparison between workshops of the
same theme. The economic result of a single SMED workshop is not a concern in LPS,
but it is all the implemented improvements functioning together which can give the
biggest economic benefits.
A SMED workshop eliminates non-value adding time, and the decrease of changeover
time opens up for two possibilities, a higher flexibility or a higher productivity. In the
LPS theory the aim of a SMED workshop is to increase the flexibility (by decreasing
the changeover time the frequency of changeovers can increase making the system more
flexible) all in order to help achieve a JIT production. The benefit of a decreased
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
115
changeover time is a faster reaction time between production order and production start
making it easier to fulfill the customer service level. Additionally, the benefits of
increased flexibility are lower inventory levels. But ZF Ansa Lemfrder does not
consider those factors as key values when it comes to evaluating benefits of
implementations, in addition those factors are difficult to measure since no records exist
facilitating these types of estimations.
If the changeover time decrease is not substituted by more frequent changeovers the
productivity of the machine will theoretically increase, supposing that the time freed up
by the SMED workshop is dedicated to production. This is the method of workshop
economic comparison currently used at ZF Ansa Lemfrder, as well as in this report.
The method is used for a rough theoretical estimation of savings, but also as a tool to
compare workshops of the same theme.
Furthermore, the method is appropriate at the moment, since no plan exists for
increasing the changeover frequency in machine 935, at least not in the near future.
Also, the estimation of stock level decrease due to the workshop is impossible to
calculate since there still are no defined stock levels at ZF Ansa Lemfrder.
Since the final degree project finished about two weeks after the workshop ended it was
not possible to retrieve enough statistical results of machine 935. In the following
calculations it is assumed that the objective of 50% decrease will be reached.
Explanation Value
Initial changeover time 120 minutes
Expected changeover time 60 minutes = 1hr
Changeover frequency (average) 1 time per day
Number of workdays between workshop
end and end of year 2008
175 days
Number of workdays in one full year 211 days
Eliminated non-value added time 149 hrs/year
Operator salary 27 /hr
If we assume that the time saved by the SMED workshop is utilized for production, also
assuming that the changeover frequency will be constant, the increase of production
time will be 175 hours during year 2008 or 211 hours during one full year. Instead of
letting the operator use those 175 hours for non-value adding operations, i.e. changeover
activity, the time is dedicated to value adding work, i.e. production. That would
eliminate the waste on non-value adding operations and would thereby be an indirect
saving of 4725 during the remaining of year 2008 and during a whole year the saving
would be 5697 . See Equation 5.
Productivity increase = hrs 175 175 1 1 =
Workshop saving rest of 2008 = 4725 27 175 =
Productivity increase = hrs 211 211 1 1 = (during one whole year)
Workshop saving one year = 5697 27 211 =
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
116
6.8.2 Expenses
The expenses of the workshop only consider the SMED workshop, i.e. only 5 days. The
reason is that the 5S workshop does not have any quantitative key values which can be
used for comparisons. All the salaries are average salaries (Enriquez, 2007) for each
category of work, based on average salaries from year 2007. Note: the member for the
quality department only participated 2 days.
Table 13: Salaries
Number of
participants
Salary
/hr
Participation
hrs/day
Total
participation
hrs
Cost
Operator 1 27.3 3 15 409.5
Engineer 3 34.5 8 40 4140
Maintenance 1 29.6 3 15 444
Quality 1 34.5 3 6 207
LPS 2 0 8 40 0
TOTAL 5200.5
The total cost of salaries during the workshop was 5200.5 , see Table 13. The LPS
participants salaries are not considered, since it is a part of the regular LPS budget and
always dedicated to all LPS activities.
Table 14: Purchases
Product Cost
Small boxes for keeping small tools 162,72
Tool box 24,39
Yellow marking tape 14,81
TOTAL: 201,92
The total expense for purchases during the workshop was 201.9 . The only expenses
registered on the LPS account were those shown in Table 14.
Other expenses
The expenses for the technical implementations and office material were not possible to
estimate, since material that was used already existed at the company. Furthermore
expenses such as electricity as well as usage of the LPS room were not considered since
those two costs would not have changed no matter if a workshop was held or not.
Total workshop cost
Workshop cost = 5200.5 + 201,92 = 5402.42 5400
6.8.3 Comparison
Workshop amortization = Workshop cost / Workshop saving per year = 5400 / 27 = 200
days = 0.95 years
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
117
The time for amortization of the workshop will approximately be one year (200 days).
That is a relatively long time, but it is important to remind and point out that the actual
savings gained from the workshop are very difficult to estimate correctly. A SMED
workshop might not show any immediate economical benefits, but the actual winning
lies in the possibility of making the whole production chain lean through continuous
improvements.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
118
7 CONCLUSIONS AND RECOMMENDATIONS
7.1 Conclusions of the final degree projects
Goal
The goal of this final degree project was to:
1. Find the main problems of the production of the eight highest volume products
2. Select LPS tools/solutions which can solve those problems
3. Successfully implement the most relevant solution through a LPS workshop.
The two first goals were reached during the final degree project. At the end of the
degree project it was still too early to say whether or not the third goal was reached,
since a long period of time is needed to determine the real results of a LPS workshop.
Desired conclusion
The desired conclusion was that one of at the time biggest production problems would
be found and successfully eliminated by using the LPS philosophy and tools. The
biggest problems of the production were found through a value stream analysis and a
subjective ranking made by the LPS group of the company. The problem area perceived
as the most important was focused on in the LPS workshop. As mentioned earlier, it
was too early to state if the workshop was a success or not.
Expected result and usage
The expected results of the degree project were:
If internal deliveries of heavy components is the biggest problem
Result: reduced stock and lead time, leading to released capital
If another problem is bigger, the expected result will be stated in the implementation
phase of the final degree project.
The internal deliveries of heavy components were not found to be the most important
problem at the time, based on the subjective ranking of the LPS group, see chapter
5.3.1. The area that was focused on was the changeover time of a pre-assembly
machine, and the objective was a 50% decrease.
The planned uses of the final results were:
Ideas for future LPS activities
Knowledge and know-how for future LPS activities
During the analysis phase of the degree project many ideas for LPS workshops were
created. The results and procedures are documented in this report which was handed in
to the company.
Tasks
In the pre-study chapter tasks, chapter 1.1.3, the tasks were not clearly stated, instead
following questions were asked and the tasks were stated in the schedule of the final
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
119
degree project, see Appendix I. The answer to the questions can be found in the chapters
denoted in brackets in the end of each question.
Questions to be answered:
What does the current system look like for the 8 most sold products? (Appendix II
and III)
What are the main problems? (5.3.1)
Is the internal delivery system the main problem? (no)
If answer is no:
Which LPS tools can be used to solve the problem? (5.3.1)
Which LPS tools should be used in the workshop executed by the
student? (6.1.3)
If answer is yes:
What is the main problem?
Which LPS tools can be used to solve the problem?
Which LPS tools should be used in the workshop executed by the
student?
What will be the targets and objectives of the workshop? (6.4.1)
How much would it cost to make the changes? (not answered)
How much money can be saved if changes are made? (5.3.1)
How can the changes be standardized in order to maintain the result? (6.4.5)
The question How much would it cost to make the changes was not investigated prior
to the execution of the workshop since it was not possible to predict the specific
solutions that would be created. Instead an economic study was made after the
workshop, estimating the cost of the workshop, see chapter 6.8.
Note - incorrectly asked questions:
Three months into the final degree project, it was realized that the questions to be
answered were not correctly expressed. The question Is the internal delivery system
the main problem was too specific, since the aim was to get a more general idea of the
problems. The question was asked after discussions about the project topic with the
company supervisor, who had suggested that the internal delivery system would be an
interesting area to focus on. Believing that the analysis might lead to the conclusion that
the internal delivery system was the main problem, the question was written in the pre-
study.
But it is important to say that the internal delivery system is one big part which the LPS
focus on, and the system can be broken down into several sub problems. For instance,
the rates of the internal deliveries are affected by factors such as changeover times,
demand, deliveries, etc. Thereby one could say that all LPS related work are somehow
connected to the internal deliveries, but also that it is the entire chain of processes and
systems working together which affects the production output.
7.2 Conclusions and recommendations of the Analysis
The value stream maps created in the beginning of the project were used as a base for
creating the list of workshop proposals. The list was ranked through a combination of
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
120
mainly subjective votes and some possible economic benefits, and the outcome of the
list was the planning of the improvement work of year 2008.
The method of ranking the list by using mainly subjective votes was a necessity. As
mentioned earlier there exists no standard manner of comparing the possible impact of a
workshop in the LPS, since it is impossible to make a correct estimation what the result
will be, but also because the impact of two distinct workshops can have very distinct
outcomes.
The choice of area to focus the LPS activities on can be based on the production data
collected from the processes, such as changeover times, productivity or inventory sizes.
But the data from SCADA or SAP does not reveal problems in the production process.
A value stream analysis helped to make the problems more visible, but since the value
stream map is a snapshot of the production it does not reveal all problems. In the case of
this final degree project, the student made the value stream analysis and at that time she
did not have much knowledge about the processes, thereby there was an increased risk
of missing important problems during the mapping. But since the LPS group
participated in the decision of which LPS activities to do and where to do them, as well
as gave proposals of workshop topics, the likelihood of choosing the areas which would
have the greatest impact increased.
During the final degree project the student was asked to estimate appropriate levels of
regulated inventories needed in the processes of the 8 investigated references. This was
not possible due to lack of necessary data which were batch sizes, delivery frequency,
order pickup frequency and safety stock size, see chapter 3.3.4. It is recommended that
the mentioned premises are established before implementing regulated inventories,
which can be done using the methods for implementing supermarkets including
Equation 6 to Equation 11 explained in chapter 3.3.4 starting on page 56. Supermarkets
are necessary for implementing pull, and since there may be a need of organisational
changes to implement supermarkets; it might be a good idea to set the maximum and
minimum levels of stocks in connection to the execution of a PULL workshop.
7.3 Results and recommendations of the Workshop
Results
The objective of the SMED workshop was a 50% decrease of the changeover time, from
an average of 120 minutes to 60 minutes in the registered times in SCADA.
During the workshop two changeovers were observed, one initial and one after
improvements had been implemented. The difference between the two observations was
an 18% decrease of the total time. See Table 15.
Within the total time the activities adjustments and mechanical changeover took up
the largest part in both changeover observations, and they had the total initial duration
of 47,88 minutes and after the improvements their total duration was 29,35 minutes.
Thus a decrease of 18,53 minutes (-39%). But in the second observation, there was a
10,4 minutes duration caused by breakdowns while in the first observation no
breakdowns occurred. The movements of the operator during the first observation were
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
121
roughly 400 meters, and during the second 500 meters. The movements increased by
30% after the improvements, due to the breakdowns.
Table 15: Workshop results
Duration (workshop data)
Classification Initial
duration (hrs)
Duration after
improvements
(hrs)
Difference Objective
Movements 00:01:15 (1,25) 00:00:00 (0) - 100%
Documentation 00:01:50 (1,83) 00:02:35 (2,58) + 41%
Adjustment 00:14:39
(14,65)
00:05:15 (5,25) - 64%
Control 00:00:37 (0,61) 00:00:50 (0,83) + 35%
Mechanical
changeover
00:33:14
(33,23)
00:24:06 (24,1) - 27,5%
Cleaning 00:00:00 (0) 00:00:00 (0) ----------
Breakdowns 00:00:00 (0) 00:10:24 (10,4) +
Transports 00:03:25 (3,42) 00:01:45 (1,75) - 49%
Waiting 00:00:00 (0) 00:00:00 (0) ----------
TOTAL
duration
00:55:00 (55) 00:44:55
(44,91)
- 18% - 50%
Movements
Initial After
improvements
Difference Objective
391 m 507,5 m + 30% - 50%
5S evaluation
Initial After
improvements
Difference Objective
7 points 17 points + 10 points 25 points (+18)
Both changeover durations were below the key value of the objective of the workshop
(60 minutes). Hence, the procedure observed during the second observation was used as
a best practice when making the new changeover procedure. The new procedure was
clearly posted on the machine. Before the new procedure had been taught to the
operators of the machine, they learned the new procedure solely through looking at the
procedure pictures posted. Therefore, about one month after the workshop, the LPS
coordinator and the shift leaders decided that education would be abundant, since all the
operators were already aware of the new procedures.
The long term workshop result was yet too early to estimate during this final degree
project, but the following Figure 95 shows the changeover times registered in SCADA
by the operators during one month after the SMED workshop. The trend shows an
average changeover time of 55 minutes in March, which is below the objective 60
minutes, even though the operators were not educated during this period. It remains to
see if the lower durations will sustain during the coming months.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
122
Development of registered changeover times, machine 935
0.0
0.5
1.0
1.5
2.0
2.5
3.0
Oct-07 Nov-07 Dec-07 Jan-08 Feb-08 Mar-08
Period
H
o
u
r
s
Time
Month avg. time
SMED workshop
Figure 95: Development of changeover times, machine 935
The cost of the workshop was 5400 . If the final result of the SMED workshop will be
a 50% decrease of the changeover time, either the changeover frequency can be doubled
(which is recommended since it increase the process flexibility) OR the amount of time
that can be dedicated to value adding work will be 211 hours during one year, which
would indicate a saving of 5697. If comparing the cost of the workshop and the
possible savings during one year, it would take approximately one year to cover the
costs of the workshop.
Another result of the workshop was a higher operator involvement. After the workshop,
the operators spontaneously started to come with improvement proposals for the work
place. This can be seen as a step in the right direction of implementing LPS, since the
philosophy encourages employee involvement.
Recommendations
It is recommended to let the operators register the changeover times by hand due to the
problem of validity of the data registered in SCADA, see chapter 1.2.2. Make a list
with; date, operator name, duration and notes for problems and reasons for long
duration. This way the main reasons for long changeovers will be easier to find when
the results of the workshop will be evaluated.
It is also recommended to keep track of the changeover times of the machine for several
months after the workshop until the changeover times are stable. If the changeover
times do not reach the goal value of 60 minutes, follow up will be necessary. An
investigation of why it failed should be made, and another SMED workshop might be
necessary if it is a critical machine.
The 5S workshop results are difficult to evaluate, but one way for evaluation would be
to create a way for making 5S audits. The audit should be equal for all Lemfrder plants
in order to allow comparison.
The lessons learned that are produced in the end of each LPS workshop at ZF Ansa
Lemfrder should be collected in one place, and presented in the beginning of each new
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
123
workshop. This could help the workshop team to avoid making mistakes. Also, if
possible, a lessons learned data base for the whole Lemfrder group could be created.
7.4 Integrating LPS
Letting only the LPS coordinator be responsible for all LPS activities sends out the
message that the activities are only a concern of the LPS department, while it is actually
a concern of the whole company. It is important that the LPS methodology is spread
throughout the company and that the knowledge deepens and gradually integrates the
company culture, otherwise there might be a risk that the LPS will just become a quick
fix and all efforts will be wasted.
In the field of LPS workshops it would be recommendable to let more people be
involved in order to make the LPS implementation faster and to spread deeper
knowledge to more people. One reason for promoting a fast implementation is that if the
implementation is too slow, the results will not be as obvious and employees might start
to think that the LPS does not work as promised.
One way to implement LPS faster is to let the engineers of the engineering department
plan and arrange one LPS workshop each per year in an area of their speciality. This
would deepen their understanding of the LPS work. It would also make the LPS
education of the operators spread more rapidly, assuming that the workshops held
would be extra workshops, and not a part of the 10 yearly workshops of the LPS
coordinator.
The engineers already do work with improvements, and they have a busy schedule and
are often needed in many places on the production floor throughout the day. But it is
advisable that also they learn how to work with improvements through the methods of
LPS. To make it possible for them to both carry out their normal work as well as LPS
activities, they could devote maybe 3 or 4 hours per day during one week to a LPS
workshop or a project, and time could also be set off for improvements based on the
LPS methodology. This does not only have to be limited to the production department
but could be spread to the other departments as well.
A recommendation for next years planning of LPS activities, for year 2009, is to let
employees already involved with production problems make value stream maps, and
thereafter let them make workshop suggestions. This would give a wider range of
information input and make it more likely that no important problem is forgotten.
Another advantage of involving more people in such LPS activities is that the LPS
knowledge would be further spread out in the company.
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
124
8 REFERENCES
Oxford English Dictionary online, Validity, Oxford Univesity Press, Second edition
(1989), Printed 2008-03-14, 14:03
http://dictionary.oed.com.focus.lib.kth.se/cgi/entry/50274591?single=1&query_type=w
ord&queryword=validity&first=1&max_to_show=10, Appendix VI
Oxford English Dictionary online, Reliability, Oxford Univesity Press, Second edition
(1989), Printed 2008-03-14, 14:19
http://dictionary.oed.com.focus.lib.kth.se/cgi/entry/50202002?single=1&query_type=w
ord&queryword=reliability&first=1&max_to_show=10, Appendix VI
Oxford English Dictionary online, Batch, Oxford Univesity Press, Second edition
(1989), Printed 2008-03-14, 16:55
http://dictionary.oed.com.focus.lib.kth.se/cgi/entry/50018304?query_type=word&query
word=batch&first=1&max_to_show=10&sort_type=alpha&result_place=3&search_id=
W7RW-twsuYn-6991&hilite=50018304, Appendix VI
Wikipedia, Author unknown, SCADA, page last modified 2008-03-11, 17:17, Printed
2008-03-13, 14:47, http://en.wikipedia.org/wiki/SCADA, Appendix VI
Wikipedia, Author unknown, SAP, page last modified 2008-03-12, 10:18, Printed 2008-
03-13, 14:43, http://en.wikipedia.org/wiki/SAP_AG, Appendix VI
Wikipedia, Author unknown, Lean Manufacturing, page last modified 2008-03-12,
05:13, Printed 2008-03-14, 14:27, http://en.wikipedia.org/wiki/Lean_manufacturing,
Appendix VI
Wikipedia, Author unknown, SMED, page last modified 2008-02-15, 18:29, Printed
2008-03-14, 15:55, http://en.wikipedia.org/wiki/Single_Minute_Exchange_of_Die,
Appendix VI
ZF webpage, Company: ZF group overview, Responsible VVK, Last Update 2008-03-
04, Printed 2008-03-13, 14:54,
http://www.zf.com/content/en/import/zf_konzern/startseite/unternehmen/Unternehmen.
html, Appendix VI
Arkansas State University webpage, Syamil A., Supply chain design, Last update xxxx,
Printed 2008-03-18, 13:44, http://www.clt.astate.edu/asyamil/chase11/ppt/,
www.clt.astate.edu/asyamil/chase11/ppt/Handout_TPS%20&%20Lean.ppt, Appendix
VI
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
125
Written material from ZF Ansa Lemfrder regarding LPS
Note: The material is copyrighted and not available to the public. To receive copies of any document
please contact Mr. Julio Guerrero, LPS coordinator at ZF Ansa Lemfrder, e-mail:
julio.guerrero@zf.com, telephone: +34 947 47 90 00
ZF Ansa Lemfrder, (2007), Lemfrder Production System - Compact-Training
(Company information about LPS), F-VL, lm000370, PowerPoint slideshow
EN_Compact_Training.ppt
ZF Ansa Lemfrder, (2007), Value stream analysis training (Company information
about LPS), F-VL, lm007798, PowerPoint slideshow EN_WSA-Training.ppt
ZF Ansa Lemfrder, (2007), Lemfrder Production System - Guideline changeover
time reduction, (Company information about LPS), F-VL, lm002734, PowerPoint
slideshow EN_Changeover_reduction.ppt
ZF Ansa Lemfrder, (2007), Lemfrder Production System - OEE, (Company
information about LPS), F-VL, lm002734, PowerPoint slideshow EN_OEE.ppt
ZF Ansa Lemfrder, (2007), Lemfrder Production System - Guideline for Supermarket
Dimensioning, (Company information about LPS), F-VL, lm002734, PowerPoint
slideshow EN_Supermarkt.ppt
ZF Ansa Lemfrder, (2007), Lemfrder Production System - 5S A Process for
Workplace Organization and Visual Controls, F-VL, PowerPoint slideshow EN_5S-
Training.ppt
ZF Ansa Lemfrder (2007), Final presentation of the LPS vision phase,
070604_PRES_5_Presentacin final de la fase de vision.ppt, J:\LPS\FASE DE
VISION\Presentaciones
Enriquez Baranda M.A., (2007), Aplicacin de tcnicas LPS a maquinas de
rebordedado y montaje de rtulas de suspensin, Universidad de Burgos,
(Final degree project report - implementation of LPS in Suspension Ball Joint assembly)
Interviews & information
Guerrero J., Engineer and LPS coordinator, ZF Ansa Lemfrder, Burgos, Spain,
interview, several times between October 2007 and February 2008
de Prado J.M., Engineer, ZF Ansa Lemfrder, Burgos, Spain, interview, January 2008
de los Mozos E., Engineer, ZF Ansa Lemfrder, Burgos, Spain, interview, January 2008
Herremans P., Production responsible, ZF Ansa Lemfrder, Burgos, Spain, interview,
October 2008
Steffen E., Engineer, ZF Lemfrder GmbH, Dielingen, Germany, telephone interview,
November 2007
Melgar Plaza J.J, Engineer, ZF Ansa Lemfrder, Burgos, Spain, October 2007
Final degree project, Sarah Ayumi Johnsson
Lean production: Value stream analysis & application of SMED on pre-assembly machine
126
Literature
Bergman, B., Klefsj, B., (2003), Quality - From customer need to customer
satisfaction, 2
nd
edition, Lund, Student Litteratur, ISBN 91-44-04166-7
Liker, J., (2003), The Toyota Way, Blacklick, OH, USA, McGraw-Hill Professional
Publishing, ISBN 97-0-07-139231-0
Liker, J., (2005), Toyota Way Fieldbook: A Practical Guide for Implementing Toyota's
4Ps, Blacklick, OH, USA, McGraw-Hill Companies, ISBN 97-0-07-144893-2
George, M. L., (2002), Lean Six Sigma : Combining Six Sigma Quality with Lean
Production Speed, Blacklick, OH, USA, McGraw-Hill Companies, ISBN 0-07-138521-
5
Burton, T. T., (2003), Lean Extended Enterprise : Moving Beyond the Four Walls to
Value Stream Excellence, Boca Raton, FL, USA, J. Ross Publishing Incorporated, ISBN
1-932159-12-6
Borris, S., (2005), Total Productive Maintenance, Blacklick, OH, USA: McGraw-Hill
Professional Publishing, ISBN 97-0-07-146733-9
Hobbs, D. P., (2003), Lean Manufacturing Implementation : A Complete Execution
Manual for Any Size Manufacturer, Boca Raton, FL, USA: J. Ross Publishing,
Incorporated, ISBN 1-932159-14-2
Viale, J.D., Carrigan, C., (1996), Inventory Management: From warehouse to
distribution center, Course Technology Crisp, Menlo Park, CA, U.S.A., ISBN 1-56052-
361-1,
Goldsby, T.J., Martichenko, R., (2005), Lean Six Sigma Logistics, Boca Raton, FL,
USA , J. Ross Publishing Incorporated, ISBN 1-932159-36-3
Simchi-Levi, D., (2003) Managing the Supply Chain, Blacklick, OH, USA: McGraw-
Hill Professional, ISBN 0-07-143587-5
Gross, J. M., (2003), Kanban Made Simple : Demystifying and Applying Toyota's
Legendary Manufacturing Process, New York, NY, USA, AMACOM, ISBN 0-8144-
0763-3
Referred to but contents not used for conclusions etc.
Geng, H., 2004, Manufacturing engineering handbook, New York, NY, USA: McGraw-
Hill, ISBN 97-0-07-139825-1
Larraeta, J, (1995), Mtodos modernos de gestin de la produccin, Madrid, Alianza
Editorial S.A., ISBN 84-206-8122-9
127
APPENDIX I: Schedule final degree project
128
APPENDIX II: Value stream maps
Value Stream Map 1: PQ35, SBJ, Ball Pin 1(2).
To calculate the total lead time and the time in process, Equation 1 and Equation 2 on page 34 were used.
129
Value Stream Map 1: PQ35, SBJ, Ball Pin 2(2)
130
Value Stream Map 2: PQ35, SBJ, Housing 1(2)
131
Value Stream Map 2: PQ35, SBJ, Housing 2(2)
132
Value Stream Map 3: PQ24-25, SBJ, Ball Pin 1(1)
133
Value Stream Map 4: PUNTO, SBJ, Housing 1(1)
134
Value Stream Map 5: A7, OBJ, Housing 1(1)
135
Value Stream Map 6: PQ35, IBJ, Ball Pin 1(1)
136
Value Stream Map 7: C307, OBJ, Ball Pin 1(1)
137
Value Stream Map 8: C307, OBJ, Housing 1(1)
138
Value Stream Map 9: B58, OBJ, Ball Pin 1(1)
139
Value Stream Map 10: B58, IBJ, Ball Pin 1(1)
140
APPENDIX III: Material flow diagrams
Material Flow Diagram 1: PQ35, SBJ, Ball Pin
141
Material Flow Diagram 2: PQ35, SBJ, Housing
142
Material Flow Diagram 3: PQ24-25, SBJ, Ball Pin
143
Material Flow Diagram 4: PUNTO, SBJ, Housing
144
Material Flow Diagram 5: A7, OBJ, Housing
145
Material Flow Diagram 6: PQ35, IBJ, Ball Pin
146
Material Flow Diagram 7: C307, OBJ, Ball Pin
147
Material Flow Diagram 8: C307, OBJ, Housing
148
Material Flow Diagram 9: B58, OBJ, Ball Pin
149
Material Flow Diagram 10: B58, IBJ, Ball Pin
150
APPENDIX IV: Analysis
Equations used for calculations: Estimated saving of OEE workshop: Equation 3, 4 and 5. Estimated saving
of SMED workshop: Equation 5. (Note: N.A. = not available)
Ranked list of workshop proposals for 2008
(Only the 20 proposals discussed during LPS group meeting)
Ranking
within
workshop
group Ref.
Type
of ball
joint Process
Line / Group /
machine Key value
Current
status Goal
Estimated
Savings
(/year)
Stock
reduction
(pieces)
OEE workshop (/year) (pieces)
1
PUNTO
SBJ Housings 648 GE 55% 100% 131 482
2
A7
OBJ Assembly Delta - 920 GE 50% 100% 85 689
3
B58
OBJ Assembly
Delta - 936 &
937 GE 35% 100% 66 182
4
PUNTO
SBJ Pre-assembly G124 GE 55% 100% 47 740
5
PQ35
SBJ Pre-assembly
+ assembly
Alfa - G134 GE
82% 100% 39 018
6
C307
OBJ Assembly Delta - 920 GE 50% 100% 38 878
7
PQ35
SBJ Housings 752 GE 85% 100% 36 132
8
B58
OBJ Pre-assembly Delta - 935 GE 50% 100% 35 169
9
B58
IBJ Ball Pins 614/615 GE 60% 100% 32 793
10
C307
OBJ Pre-assembly Delta - 919 GE 58% 100% 31 660
SMED workshop Goal (/year) (pieces)
1
B58
OBJ Pre-assembly Delta - 935 C/O time 2,3 50% 53 383
C/O freq. 4,4 N.A.
2
B58
OBJ Ball Pins Beta - 878 C/O time 3,9 50% 32 916
C/O freq. 1,6 N.A.
3
A7
OBJ Pre-assembly Delta - 935 C/O time 2,3 50% 26 692
C/O freq. 4,4 N.A.
4
Delta line
(A7, C307,
B58)
OBJ Assembly Delta -936 C/O time 2 50% 14 243
C/O freq. 2,7 N.A.
5
PQ35
SBJ Housing 777-787 C/O time 4,42 50% 13 989
C/O freq. 1,2 N.A.
PULL workshop Goal (/year) (pieces)
- SBJ
Assembly -
Housing G133/G134
Total
Inventory 167 769 N.A. N.A. N.A.
-
PQ35
SBJ
Assembly -
Ball Pins G133/G134
Total
Inventory 238 000 N.A. N.A. N.A.
-
A7
OBJ
Machining &
assembly Delta
Total
Inventory 70032 N.A. N.A. N.A.
-
C307
OBJ
Machining &
assembly Delta
Total
Inventory 282598 N.A. N.A. N.A.
-
B58
OBJ
Machining &
assembly Delta
Total
Inventory 47340 N.A. N.A. N.A.
Other workshop
All
All Self-control All N.A. N.A.
151
APPENDIX V: SMED and 5S workshop
documents
Schedule LPS
Workshops 08 03 and 08 04, SMED and 5S on machine
935
152
Workshop definition sheet SMED
SMED workshop 08 03
153
Workshop definition sheet 5S
5S workshop 08 04
154
Workshop planning checklist
Workshop step Necessities / Preparations Responsibility of coordinator
Before workshop: Preliminary
analysis of changeover
Stop watch Observe one or more
changeovers to know what to
look for in the real observation
Introduction Prepare presentation, practice Present in the morning
SMED education Slideshow about SMED, notes
about what to say, practice
Present SMED theory
Objectives and assignment Workshop definition sheet
(Hoja de definicin )
Present the objectives etc.
1st Changeover observation Camera (film), Stopwatch,
Templates for listing activities,
Templates with layout, Measure
tape, Pens
Assign activities, Observe
changeover
Analysis of collected data Excel template for analysing
data
Transfer all collected data to
Excel file, Present results
Solutions generation A1 sheets for writing/drawing
(solutions, sketches, task list
with Deming wheels), Pens,
Enquiry paper for purchases
Document solution tasks, Assign
tasks, Set deadlines
Intermediate presentation
SMED
Excel and PowerPoint templates
for making the presentation, All
data from the observation,
Photos or film
Make the presentation, assign
who is to say what
Solutions implementation In the end of each meeting check
which tasks are fulfilled and
check on list (Deming wheel)
2nd Changeover observation:
(after modifications)
Assign activities
Evaluate result and generate
improvements
Excel template for analysing
data, A1 sheets
Transfer all collected data to
Excel file, present results,
discuss possible improvements
Standardization SMED Discuss appropriate standards,
assign tasks
Final presentation SMED
Excel and PowerPoint templates
for making the presentation, All
data from the observation,
photos
Make presentation, assign who is
to say what
5S education
Slideshow about 5S, Notes about
what to say, practice
Present the 5S theory
5S application Evaluation sheet, Camera,
Cleaning supplies, material for
making etiquettes for visual aid,
etc.
Assign activities
Standardization 5S Discuss appropriate standards,
assign tasks
Final presentation 5S
Excel and PowerPoint templates
for making the presentation,
photos
Make presentation, assign who is
to say what
Follow up End eventual unfinished tasks if
possible, place some kind of
registration board at the machine
for operators to fill out make
graph of changeover time
Education (operators) Discuss with supervisor about
how and when
155
Spaghetti diagram 1st observation
156
Spaghetti diagram 2nd observation
157
LPS workshop report
158
Changeover times registered in SCADA, machine 935
Period: 02/10/2007 - 25/03/2008. Note: only values in green are used for the average values
Start Finish
Duration
(hrs)
Month
average Start Finish
Duration
(hrs)
Month
average
02/10/2007 11:14 02/10/2007 13:02 1.80 1.77 02/01/2008 11:55 02/01/2008 14:27 2.53 1.45
02/10/2007 22:41 03/10/2007 01:18 2.62 02/01/2008 14:32 02/01/2008 14:50 0.30
03/10/2007 11:04 03/10/2007 12:36 1.53 03/01/2008 22:55 04/01/2008 02:37 3.70
04/10/2007 22:11 05/10/2007 00:10 1.98 04/01/2008 14:33 04/01/2008 16:07 1.57
05/10/2007 19:40 05/10/2007 21:43 2.05 08/01/2008 12:51 08/01/2008 14:46 1.92
06/10/2007 05:15 06/10/2007 06:18 1.05 09/01/2008 12:33 09/01/2008 20:40 8.12
09/10/2007 12:37 09/10/2007 15:09 2.53 10/01/2008 20:17 10/01/2008 21:34 1.28
10/10/2007 06:27 10/10/2007 07:22 0.92 15/01/2008 05:09 15/01/2008 07:22 2.22
11/10/2007 06:37 11/10/2007 08:26 1.82 16/01/2008 02:14 16/01/2008 02:26 0.20
15/10/2007 15:10 15/10/2007 20:37 5.45 17/01/2008 01:41 17/01/2008 04:03 2.37
17/10/2007 06:26 17/10/2007 08:17 1.85 21/01/2008 14:37 21/01/2008 14:44 0.12
18/10/2007 21:30 18/10/2007 22:35 1.08 21/01/2008 16:17 21/01/2008 17:51 1.57
20/10/2007 03:43 20/10/2007 05:42 1.98 22/01/2008 01:21 22/01/2008 02:59 1.63
22/10/2007 17:56 22/10/2007 20:16 2.33 23/01/2008 14:34 23/01/2008 16:14 1.67
23/10/2007 05:01 23/10/2007 07:13 2.20 23/01/2008 16:16 23/01/2008 16:29 0.22
23/10/2007 17:54 23/10/2007 20:19 2.42 26/01/2008 04:38 26/01/2008 05:50 1.20
24/10/2007 18:19 24/10/2007 20:28 2.15 28/01/2008 06:24 28/01/2008 06:57 0.55
29/10/2007 01:20 29/10/2007 04:06 2.77 30/01/2008 11:01 30/01/2008 12:44 1.72
29/10/2007 14:30 29/10/2007 16:33 2.05 30/01/2008 13:43 30/01/2008 14:38 0.92
30/10/2007 08:23 30/10/2007 09:27 1.07 01/02/2008 17:57 01/02/2008 18:47 0.83 1.18
05/11/2007 17:34 05/11/2007 20:15 2.68 1.64 04/02/2008 10:41 04/02/2008 11:35 0.90
06/11/2007 01:06 06/11/2007 03:20 2.23 05/02/2008 08:40 05/02/2008 09:29 0.82
06/11/2007 22:46 07/11/2007 00:36 1.83 06/02/2008 10:24 06/02/2008 11:29 1.08
07/11/2007 11:51 07/11/2007 13:31 1.67 07/02/2008 11:45 07/02/2008 12:28 0.72
07/11/2007 22:46 08/11/2007 00:44 1.97 08/02/2008 16:40 08/02/2008 18:52 2.20
08/11/2007 04:55 08/11/2007 06:14 1.32 13/02/2008 16:37 13/02/2008 18:36 1.98
09/11/2007 21:13 09/11/2007 22:32 1.32 14/02/2008 11:08 14/02/2008 12:17 1.15
13/11/2007 13:31 13/11/2007 14:38 1.12 18/02/2008 06:25 18/02/2008 06:31 0.10
13/11/2007 23:08 14/11/2007 00:33 1.42 19/02/2008 07:03 19/02/2008 08:04 1.02
14/11/2007 04:49 14/11/2007 07:02 2.22 19/02/2008 08:19 19/02/2008 08:45 0.43
15/11/2007 08:21 15/11/2007 10:48 2.45 20/02/2008 04:58 20/02/2008 06:14 1.27
21/11/2007 16:02 21/11/2007 18:50 2.80 21/02/2008 12:12 21/02/2008 14:00 1.80
22/11/2007 14:31 22/11/2007 15:04 0.55 22/02/2008 23:13 23/02/2008 01:51 2.63
22/11/2007 16:34 22/11/2007 18:25 1.85 28/02/2008 18:31 28/02/2008 20:25 1.90
26/11/2007 20:38 26/11/2007 22:11 1.55 28/02/2008 23:03 28/02/2008 23:28 0.42
27/11/2007 06:35 27/11/2007 08:10 1.58 04/03/2008 07:35 04/03/2008 11:00 3.42 0.89
27/11/2007 19:03 27/11/2007 20:42 1.65 05/03/2008 00:06 05/03/2008 00:49 0.72
28/11/2007 04:50 28/11/2007 06:16 1.43 06/03/2008 13:24 06/03/2008 15:01 1.62
28/11/2007 06:24 28/11/2007 06:31 0.12 10/03/2008 16:13 10/03/2008 16:51 0.63
28/11/2007 07:19 28/11/2007 07:31 0.20 11/03/2008 10:37 11/03/2008 11:14 0.62
30/11/2007 07:27 30/11/2007 09:14 1.78 11/03/2008 11:38 11/03/2008 11:50 0.20
03/12/2007 08:26 03/12/2007 10:52 2.43 1.93 12/03/2008 01:34 12/03/2008 03:25 1.85
10/12/2007 16:13 10/12/2007 18:16 2.05 13/03/2008 17:46 13/03/2008 18:32 0.77
12/12/2007 02:18 12/12/2007 04:35 2.28 15/03/2008 03:42 15/03/2008 04:42 1.00
14/12/2007 09:27 14/12/2007 11:46 2.32 17/03/2008 08:35 17/03/2008 09:17 0.70
17/12/2007 21:36 18/12/2007 06:23 8.78 18/03/2008 11:37 18/03/2008 12:01 0.40
18/12/2007 06:24 18/12/2007 07:10 0.77 19/03/2008 08:03 19/03/2008 08:40 0.62
18/12/2007 10:44 18/12/2007 12:26 1.70
159
APPENDIX VI: Web reference printouts
Validity
2. The quality of being well-founded on fact, or established on sound principles, and
thoroughly applicable to the case or circumstances; soundness and strength (of
argument, proof, authority, etc.). a. In the phrase of...validity.
http://dictionary.oed.com.focus.lib.kth.se/cgi/entry/50274591?single=1&query_type=word&queryword=v
alidity&first=1&max_to_show=10
Reliability
2. Statistics. The extent to which a measurement made repeatedly in identical
circumstances will yield concordant results.
http://dictionary.oed.com.focus.lib.kth.se/cgi/entry/50202002?single=1&query_type=word&queryword=r
eliability&first=1&max_to_show=10
Batch
5. transf. A quantity produced at one operation, e.g. a brewing; a lot. arch.
http://dictionary.oed.com.focus.lib.kth.se/cgi/entry/50018304?query_type=word&queryword=batch&first
=1&max_to_show=10&sort_type=alpha&result_place=3&search_id=W7RW-twsuYn-
6991&hilite=50018304
SCADA
SCADA is the acronym for Supervisory Control And Data Acquisition. In Europe,
SCADA refers to a large-scale, distributed measurement and control system, while in
the rest of the world SCADA may describe systems of any size or geographical
distribution. SCADA systems are typically used to perform data collection and control
at the supervisory level. Some systems are called SCADA despite only performing data
acquisition and not control.
The supervisory control system is a system that is placed on top of a real-time control
system to control a process that is external to the SCADA system (i.e. a computer, by
itself, is not a SCADA system even though it controls its own power consumption and
cooling). This implies that the system is not critical to control the process in real time,
as there is a separate or integrated real-time automated control system that can respond
quickly enough to compensate for process changes within the time constants of the
process. The process can be industrial, infrastructure or facility based as described
below:
Industrial processes include those of manufacturing, production, power
generation, fabrication, and refining, and may run in continuous, batch,
repetitive, or discrete modes.
Infrastructure processes may be public or private, and include water treatment
and distribution, wastewater collection and treatment, oil and gas pipelines,
electrical power transmission and distribution, and large communication
systems.
Facility processes occur both in public facilities and private ones, including
buildings, airports, ships, and space stations. They monitor and control HVAC,
access, and energy consumption.
http://en.wikipedia.org/wiki/SCADA
160
SAP
SAP was founded in 1972 as Systemanalyse und Programmentwicklung[2] by five
former IBM engineers in Mannheim, Baden-Wrttemberg (Dietmar Hopp, Hans-
Werner Hector, Hasso Plattner, Klaus Tschira, and Claus Wellenreuther).[3] The
acronym was later changed to stand for Systeme, Anwendungen und Produkte in der
Datenverarbeitung ("Systems, Applications and Products in Data Processing").
SAP ERP is one of five major enterprise applications in SAP's Business Suite. The
other four applications are:
customer relationship management (CRM) - helps companies acquire and retain
customers, gain deep marketing and customer insight, and align organization on
customer-focused strategies
product lifecycle management (PLM) - helps manufacturers with a single source
of all product-related information necessary for collaborating with business
partners and supporting product lines
supply chain management (SCM) - helps companies enhance operational
flexibility across global enterprises and provide real-time visibility for customers
and suppliers
supplier relationship management (SRM) - customers can collaborate closely
with suppliers and integrate sourcing processes with applications throughout the
enterprise to enhance transparency and lower costs
http://en.wikipedia.org/wiki/SAP_AG
Lean Manufacturing
Lean manufacturing is the production of goods using less of everything compared to
traditional mass production: less waste, human effort, manufacturing space, investment
in tools, inventory, and engineering time to develop a new product. Lean manufacturing
is a generic process management philosophy derived mostly from the War Manpower
Commission which led to the Toyota Production System (TPS)[1] and also from other
sources. It is renowned for its focus on reduction of the original Toyota 'seven wastes' in
order to improve overall customer value but has some key new perspectives on how to
do this. Lean is often linked with Six Sigma because of that methodology's emphasis on
reduction of process variation (or its converse smoothness) and Toyota's combined
usage (with the TPS). Toyota's steady growth from a small player to the most valuable
and the biggest car company in the world has focused attention upon how it has
achieved this.
http://en.wikipedia.org/wiki/Lean_manufacturing
SMED
Single Minute Exchange of Die (SMED) is one of the many lean production methods
for reducing waste in a manufacturing process. It provides a rapid and efficient way of
converting a manufacturing process from running the current product to running the
next product. This rapid changeover is key to reducing production lot sizes and thereby
improving flow (Mura) which is a 'Lean' aim. It is also often referred to as Quick
Changeover (QCO). Performing faster change-overs is important in manufacturing, or
any process, because they make low cost flexible operations possible.
161
The phrase "single minute" does not mean that all changeovers and startups should take
only one minute, but that they should take less than 10 minutes (in other words, "single
digit minute").
http://en.wikipedia.org/wiki/Single_Minute_Exchange_of_Die
ZF web
ZF is a leading worldwide automotive supplier for Driveline and Chassis Technology.
The company operates 120 plants located in 25 countries and has nearly 58,000
employees including around 23,000 working at foreign locations. ZF estimated revenues
in 2007 totaled EUR 12.6 billion. ZF ranks among the 15 biggest automotive suppliers
worldwide.
ZF develops and produces products serving the mobility of human beings and goods.
Innovations in Driveline and Chassis Technol-ogy provide increased driving dynamics,
safety, comfort, and econ-omy as well as lower fuel consumption and emissions in the
vehi-cles of the customers: By land, by sea, and in the air.
ZFs main priority is to meet its customers needs by using leading technology, quality,
and service; this is the key to strengthening the international market position. In addition
to the benefits of com-ponent expertise, the customer profits from the Groups system
know-how.
ZF is a decentralized organization with divisions and business units. They are
responsible for worldwide products, markets, and results and are run as profit centers.
These operational entities are governed by strategic and financial objectives.
ZF plays an active role in society and is continuously engaged in a dialog with the
public and its employees. The company promotes employees based on qualification,
performance, work ethics, and mobility. The company assumes social and societal
responsibility. Environmental protection is a professed corporate objective.
http://www.zf.com/content/en/import/zf_konzern/startseite/unternehmen/Unternehmen.html
Arkansas State University webpage
Section 3: Supply Chain Design
Chapter 11 Handout: Toyota Production System (TPS) and Lean Manufacturing (3.2
MB)
162
Customer
orders 10
Lot size = 5
Lot 1 Lot 2
Lot size = 2
Lot 1 Lot 2 Lot 3 Lot 4 Lot 5
Reducing Lot Sizes Increases the
Number of Lots
Which Increases
Inventory Costs
Lot Size
Cost
Holding
Total
Setup
Optimal
Lot Size
Smaller
Lot Size
163
http://www.clt.astate.edu/asyamil/chase11/ppt/
www.clt.astate.edu/asyamil/chase11/ppt/Handout_TPS%20&%20Lean.ppt
Unless Setup Costs are Reduced
Lot Size
Cost
Holding
Total
Setup
Original
optimal
lot size
New
optimal lot
size