Sie sind auf Seite 1von 114

Engineering Manual

Integrated Support




E
n
g
i
n
e
e
r
i
n
g

M
a
n
u
a
l

AM 9995 PM
MAINTENANCE REQUIREMENTS
ANALYSIS MANUAL
Version 5.0
Issued July 2010
Owner: Manager, Engineering Services
Approved
by:
Mike Hogan
Engineering Services Manager
Authorised
by:
Ron Azzi
General Manager
Professional Services
Disclaimer
This document was prepared for use on the RailCorp Network only.
RailCorp makes no warranties, express or implied, that compliance with the contents of this document shall be
sufficient to ensure safe systems or work or operation. It is the document users sole responsibility to ensure that the
copy of the document it is viewing is the current version of the document as in use by RailCorp.
RailCorp accepts no liability whatsoever in relation to the use of this document by any party, and RailCorp excludes
any liability which arises in any manner by the use of this document.
Copyright
The information in this document is protected by Copyright and no part of this document may be reproduced,
altered, stored or transmitted by any person without the prior consent of RailCorp.
UNCONTROLLED WHEN PRINTED Page 1 of 114
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 2 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
Document control

Version Date Summary of change
1.0 N/A First Issue
2.0 October 2000 N/A
3.0 March 2003 Updated Section 3 to include Design FMECA
4.0 J une 2008
Rebadging to RailCorp, reformatting and combining Sections
into a single document. Note, as Section 3 was already
version 3, this combined document is now version 4
5.0 J une 2010 Three year review and application of TMA 400 format


RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 3 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
Contents

1 Executive Review....................................................................................................................7
1.1 Introduction................................................................................................................7
1.1.1 Maintenance Requirements Analysis (MRA) .............................................7
1.1.2 FMECA and RCM Analysis........................................................................8
1.1.2.1 New Capital Assets.....................................................................8
1.1.2.2 Existing Assets............................................................................8
1.1.3 Documentation.........................................................................................12
1.1.4 Quality management................................................................................12
1.1.5 Use of this Manual....................................................................................12
1.1.6 References...............................................................................................13
1.1.7 Suggested Readings & References.........................................................13
2 Background and theory........................................................................................................14
2.1 Definition of terms....................................................................................................14
2.1.1 Acronym Definitions .................................................................................14
2.2 Reliability and maintenance.....................................................................................18
2.2.1 Introduction...............................................................................................18
2.2.2 Reliability..................................................................................................18
2.2.3 Failure Characteristics..............................................................................19
2.2.4 Reliability Modelling..................................................................................20
2.2.5 Maintenance Task Applicability................................................................22
2.2.6 Maintenance Task Effectiveness .............................................................23
2.2.7 Suggested Readings & References.........................................................23
2.3 Maintenance, Risk and RCM...................................................................................23
2.3.1 Introduction...............................................................................................23
2.3.2 Maintenance.............................................................................................23
2.3.3 Risk...........................................................................................................24
2.3.3.1 Risk Assessment ......................................................................25
2.3.3.2 New Acquisitions Risk...............................................................25
2.3.4 RCM Process ...........................................................................................25
2.3.5 Other Users of RCM.................................................................................26
2.3.6 Benefits ....................................................................................................26
2.3.7 The RCM Model .......................................................................................27
2.3.8 Process Steps ..........................................................................................27
2.3.9 Analysis Team..........................................................................................27
2.3.10 Post Acquisition Analysis .........................................................................30
2.3.11 New Acquisitions......................................................................................31
2.3.12 Data Collection.........................................................................................31
2.3.13 Suggested Readings & References.........................................................32
3 System Breakdown ...............................................................................................................32
3.1 Introduction..............................................................................................................32
3.1.1 Establishing Boundaries...........................................................................33
3.1.2 Develop Functional Block Diagrams ........................................................35
3.1.3 Significant Items.......................................................................................36
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 4 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
3.1.3.1 Top down approach..................................................................39
3.1.4 Prioritisation..............................................................................................39
3.1.5 Numbering Systems.................................................................................40
3.1.6 Electronic Filing........................................................................................43
3.1.7 Suggested Readings & References.........................................................43
3.2 Failure Modes and Effects Analysis (FMEA)...........................................................43
3.2.1 Introduction...............................................................................................43
3.2.2 Process Overview....................................................................................44
3.2.3 Functions, Missions and Failures.............................................................44
3.2.4 Types of Functions...................................................................................45
3.2.5 Failure Modes...........................................................................................47
3.2.6 Types of Failures......................................................................................48
3.2.7 Failure Causes .........................................................................................49
3.2.8 Failure Effects ..........................................................................................50
3.2.8.1 Local Effect...............................................................................50
3.2.8.2 System Effect............................................................................51
3.2.8.3 Impact of operating mode of failure effect. ...............................51
3.2.9 Hidden Failures ........................................................................................51
3.2.9.1 Types of hidden failures............................................................52
3.2.10 Analysis Logic Statement.........................................................................52
3.2.11 Protective Systems...................................................................................53
3.2.12 Use of Risk Assessment..........................................................................54
3.2.13 Suggested Readings & References.........................................................54
3.3 Criticality Analysis....................................................................................................55
3.3.1 Introduction...............................................................................................55
3.3.2 Criticality During design............................................................................55
3.3.2.1 Operator detection....................................................................56
3.3.2.2 Compensating provision...........................................................57
3.3.2.3 Severity Class...........................................................................57
3.3.2.4 Criticality Analysis.....................................................................58
3.3.3 During Maintenance Analysis...................................................................60
3.3.4 RCM analysis ...........................................................................................62
3.3.4.1 Hidden.......................................................................................62
3.3.4.2 Safety/Environment...................................................................63
3.3.4.3 Economic..................................................................................63
3.3.5 Suggested Readings & References.........................................................64
4 RCM Analysis ........................................................................................................................64
4.1 Task Analysis...........................................................................................................64
4.1.1 Task Objectives........................................................................................65
4.1.2 Task Options ............................................................................................65
4.1.3 Task Applicability......................................................................................66
4.1.3.1 Service / Lubrication Task Application Using
MIMIR .......................................................................................68
4.1.4 Task Effectiveness ...................................................................................69
4.1.5 Non Programmed Tasks ..........................................................................70
4.1.6 Task Logic Charts ....................................................................................72
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 5 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
4.1.7 Default Actions and Tasks .......................................................................72
4.1.8 Default Decision Strategy.........................................................................72
4.1.9 Default Tasks ...........................................................................................77
4.1.10 Documentation of Task Decisions............................................................77
4.1.11 Summary..................................................................................................78
4.1.12 Suggested Readings & References.........................................................78
4.2 Frequency Determination........................................................................................80
4.2.1 Introduction...............................................................................................80
4.2.2 On Condition Examinations......................................................................80
4.2.3 Zonal Examinations..................................................................................82
4.2.4 Hard time Rework or Discard Tasks ........................................................83
4.2.5 Combinations of Tasks.............................................................................84
4.2.6 Failure Finding Tasks...............................................................................84
4.2.7 Suggested Readings & References.........................................................86
4.3 Task Packaging.......................................................................................................86
4.3.1 Introduction...............................................................................................86
4.3.2 Options.....................................................................................................86
4.3.3 Packaging Process...................................................................................88
4.3.4 Latitudes...................................................................................................89
4.3.5 Task Packaging Guidelines......................................................................90
4.3.6 Standard Terminology..............................................................................90
4.3.7 Suggested Readings & References.........................................................91
5 Audit and Evaluation ............................................................................................................92
5.1 Auditing....................................................................................................................92
5.1.1 Introduction...............................................................................................92
5.1.2 Timing of the Audit...................................................................................92
5.1.3 Auditor Selection......................................................................................92
5.1.4 Significant Item Selection.........................................................................93
5.1.5 Item Function, Failure and Effects ...........................................................93
5.1.6 Classification of Failure Consequences...................................................94
5.1.7 Evaluation of Applicability and Effectiveness Criteria..............................94
5.1.8 The Completed Program..........................................................................95
5.1.9 Suggested Readings & References.........................................................95
5.2 Test and Evaluation.................................................................................................95
5.2.1 Introduction...............................................................................................95
5.2.2 Initial Schedules - New Equipment..........................................................96
5.2.3 Initial Schedules - In Service Equipment..................................................96
5.2.4 Suggested Readings & References.........................................................96
5.2.5 Test and Evaluation Program Brief ..........................................................97
5.2.5.1 Introduction...............................................................................97
5.2.5.2 Objective...................................................................................97
5.2.5.3 Scope of Work..........................................................................97
5.2.5.4 Key Issues ................................................................................97
5.2.5.5 Typical Project Profile...............................................................98
5.3 Technical Maintenance Plans..................................................................................98
5.3.1 Introduction...............................................................................................98
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 6 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
5.3.2 Item Listing Criteria..................................................................................98
5.3.3 Plan Information.......................................................................................98
5.3.4 Responsibility...........................................................................................99
5.3.5 Suggested Readings & References.........................................................99
6 MRA Techniques and Policy ................................................................................................99
6.1 Age exploration........................................................................................................99
6.1.1 Introduction...............................................................................................99
6.1.2 Process ....................................................................................................99
6.1.3 Research Opportunities......................................................................... 100
6.1.4 Cost Effectiveness................................................................................. 100
6.1.5 Responsibilities ..................................................................................... 100
6.1.6 Summary............................................................................................... 100
6.1.7 Suggested Readings & References...................................................... 100
6.2 Task Frequency Algorithms.................................................................................. 101
6.2.1 Introduction............................................................................................ 101
6.2.2 Condition Monitoring Algorithm............................................................. 101
6.2.3 Double Failure Algorithm....................................................................... 102
6.2.4 Hard Time Algorithm............................................................................. 103
6.3 Level of Repair Analysis....................................................................................... 104
6.3.1 Introduction............................................................................................ 104
6.3.2 Repair Versus Replace Decisions......................................................... 105
6.3.3 Repair In Situ......................................................................................... 105
6.3.4 Repair at Local Workshop..................................................................... 105
6.3.5 Repair at Contractor Facility.................................................................. 105
6.3.6 Process Map for LORA......................................................................... 106
6.4 MRA Policy........................................................................................................... 107
6.4.1 Introduction............................................................................................ 107
6.4.2 Supplier Recommendations.................................................................. 107
6.4.3 New Systems ........................................................................................ 107
6.4.4 Individual Equipment Replacement....................................................... 108
6.4.5 Existing Equipment Modification........................................................... 108
6.4.6 Maintenance Reviews........................................................................... 109
6.4.7 Pro-active Reviews................................................................................ 109
6.4.8 Reactive Reviews.................................................................................. 109
7 Analysis of Safety Critical Items ...................................................................................... 110
7.1 Introduction........................................................................................................... 110
7.1.1 Quantitative Risk Assessment .............................................................. 110
7.1.2 Documentation...................................................................................... 111
7.1.3 Suggested Readings & References...................................................... 111
Appendix A Packing Guidelines............................................................................................. 112


RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 7 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0

1 Executive Review
1.1 Introduction
This document supports the RailCorp Asset Management Policy Manual with detailed
procedures for implementing a significant element of Logistic Support Analysis (LSA)
1
.
This element includes the determination of preventive maintenance requirements of both
in service and new assets. This process, along with the identification of all corrective
maintenance needs of a system, is termed Maintenance Planning in the LSA task list.
The document is not meant to stand alone and should be read in conjunction with the
reference documents at the end of each section. These references have been assessed
as "world best practice" and provide additional detail to staff tasked with undertaking
maintenance requirements analysis.
This document is primarily directed at engineers responsible for establishing and
implementing maintenance policies contained in Technical Maintenance Plans. Other
staff involved in the technical management and maintenance of capital assets would also
benefit from a conceptual knowledge of the process.
1.1.1 Maintenance Requirements Analysis (MRA)
A significant component in the LSA process is the determination of maintenance
requirements which consist of preventive and corrective maintenance procedures. These
procedures are related to both the physical and functional configurations of items
comprising a system and recognise that the operating context or environment of
equipment is a critical contributor to system maintenance needs.
A "world class" standardised Maintenance Requirements Analysis (MRA) process now
accepted by, and applied across, all engineering disciplines for the development of
system preventive maintenance requirements is Reliability-Centred Maintenance
2
(RCM)
analysis. The RCM process derives from the application of Failure Modes, Effects and
Criticality Analysis (FMECA) and recognises that preventive maintenance can only, at
best, enable assets to achieve their built-in level of inherent reliability.
RCM programs require the selection of preventive maintenance tasks on the basis of the:
reliability characteristics of the equipment
operating context of the equipment (ie its environment)
logical analysis of the failure consequences
The RCM process is supported by Level of Repair Analysis (LORA)
3
. LORA identifies
the most cost effective corrective maintenance strategy for failed items, that is to maintain
or to dispose of failed items and, if maintain, the organisational level at which that
maintenance strategy will be applied. FMECA, RCM and LORA combined provide a
comprehensive set of analysis tools to determine, either at the design stage or later in-
service, an equipment's complete set of preventive and corrective maintenance
requirements and the organisational level at which that maintenance will be done.



1
MIL-STD-1388-2A&B Logistic Support Analysis
2
Anthony Smith, Reliability Centred Maintenance, McGraw Hill, 1993, J ohn Moubray, RCM II Reliability-centred Maintenance,
Butterworth Heinemann, 1992 and US MIL-STD-2173AS, Reliability Centred Maintenance for Naval Aircraft Weapons and
Support Equipment.
3
US MIL-STD-1390C, Level of Repair Analysis.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




1.1.2 FMECA and RCM Analysis
Failure Mode Effects and Criticality Analysis
4
(FMECA) is a standard tool for identifying
and prioritising the failure potential of a design. It is usually conducted during the
developmental stage in order to prioritise design actions aimed at their (failure potential)
removal during that stage. Removal of high risk failure modes early in the design process
has significant economic advantages and will usually more than justify the additional
investment necessary to conduct a FMECA during the acquisition phase
5
.
1.1.2.1 New Capital Assets
Application of the FMECA process was originally established to support military
equipment procurement activity; however the process is now rapidly expanding to non-
military equipment6. Process FMECA 7 extends the original hardware design FMECA
concept into production and other process type activity to identify all possible failures,
hardware and human, and establish effective control mechanisms.
For newly acquired assets, the Failure Mode Effects Analysis (FMEA) element of the
FMECA is used as raw information for RCM analysis. This information combined with the
functional specifications required by the acquisition methodology to be defined in the RSA
Asset Management Policy Manual, provide the basic data for undertaking RCM analysis.
The RCM analysis for new assets should be the responsibility of the prime system
supplier and the subsequent documentation should be a contract deliverable.
The analysis sequence for new assets is shown at Figure 1.
ESTABLISH
FUNCTIONS
UNDERTAKE
FMECA
UNDERTAKE
RCM
UNDERTAKE
LORA
MAINTENANCE
REQUIREMENTS
ANALYSIS
COMPLETE

Figure 1 - Maintenance requirements analysis elements
1.1.2.2 Existing Assets
The application of RCM analysis to existing assets usually means that there is no pre-
established FMECA data to work with and hence considerable work must be done to
establish functional relationships and FMEA data. This process is staff resource
intensive. The establishment of functional relationships can take up to 40% of the total
time but usually provides considerable insights into the equipment and its functions.
Major reasons for implementing maintenance requirements analysis on existing assets is
to:
Improve the understanding of all engineering and maintenance staff as to what is the
equipment's function and how this supports the business.
Establish a baseline of functional failures and their compensating redesign, operational or
maintenance tasks



4

US MIL-STD-1629A A Procedure for a Failure Mode Effects and Criticality Analysis.
5
Blanchard, Logistics Engineering and Management
6
Smith, Reliability Centred Maintenance, McGraw-Hill, 1991
7
Reheja, Assurance Technologies, McGraw Hill, 1991 Pp 198-203
RailCorp Page 8 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 9 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
Establish an optimised preventive maintenance program that matches business needs
and the inherent reliability characteristics of the equipment
A basic seven step process for undertaking RCM analysis in accordance with the
principles contained in referenced standards and guidelines is shown at Figure 2.
Experience indicates that 12 to 18 months is required to complete a comprehensive
analysis and implement a significant RCM program on an existing asset. However, a
"fast track" analysis process which bypasses some of the more onerous quality
assurance aspects of a formal analysis program can be achieved in much shorter time
but at the sacrifice of some accuracy. The "fast track" is generally used to rapidly
establish a documented maintenance "baseline" for existing assets with established
maintenance programs to enable the implementation of an effective prioritised continual
improvement program.
The output from either the comprehensive or fast track process is a set of preventive
maintenance tasks which achieve necessary levels of safety and availability at minimum
life cycle cost commensurate with the inherent characteristics of the design.
The RCM analysis process is usually an initial "best guess" that will require review as
assumptions made during the analysis are verified or otherwise by service performance.
Additionally, changes to operational requirements, system configuration and operating
and maintenance environments will require reference back to original analysis and review
of the maintenance requirements.
The maintenance requirements analysis process that connects RCM analysis with FMEA
and the continual improvement process is shown at Figure 3.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 10 of 114
Issued J uly 2010 5.0 UNCONTROLLED WHEN PRINTED Version
RELIABILITY - CENTRED MAINTENANCE
(A seven step structured decision support process)
STEP 1 Breakdown the asset into manageable
systems and items of equipment.

STEP 2 Prioritise the assets for analysis according to
risk exposure from failure.

STEP 3 Collect system information and define each
failure problem to be addressed.

STEP 4 Establish possible preventive maintenance
strategies for dealing with each failure cause
based on its consequence.

STEP 5 Evaluate the validity of each particular
preventive maintenance policy (task and
frequency).

STEP 6 Determine what to do if there are no
applicable and effective maintenance policies.

STEP 7 Package the valid preventive maintenance
policies into cost effective schedules.
Figure 2 - The 7 Step RCM Analysis Method


ering Manual Integrated Support
quirements Analysis Manual AM 9995 PM




RailCorp Page 11 of 114
Issued J uly 2010 Version 5.0

Figure 3 - Maintenance Requirements Analysis process (MIL-STD-2173AS)
UNCONTROLLED WHEN PRINTED

RailCorp Engine
Maintenance Re
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
1.1.3 Documentation
The analysis documentation, whether electronic or paper, must provide the justification
for all the tasks defined in the preventive maintenance program and specified in a
Technical Maintenance Plan (TMP). The particular details of what data has been
collected against each Application will also provide the details needed to complete each
field in sufficient detail to allow systems engineers today or 20 years hence to understand
completely the reason for the existence of each and every task in the schedules without
conducting a reverse engineering exercise or redoing the analysis.
Any necessary caveats regarding the accuracy of information used, or assumptions
made, should be included with the analysis documentation associated with each asset
type.
The output of the maintenance requirements analysis process, whether hard copy or
electronic, should be maintained by a single authorised engineering manager. This
manager is responsible and accountable for the configuration control aspects of the data
as defined in an asset type's Configuration Management Plan (CMP).
Maintenance requirements analyses are controlled documents defined in the relevant
configuration management plans.
The quality of the documentation, which will be the basis of audits and quality
improvement programs, must be maintained at all times.
1.1.4 Quality management
Quality assurance of the analysis process should be achieved through an accreditation
framework for MRA analysts.
This Manual will be the prime documentation covering the maintenance requirements
analysis process and should be referred to by the quality manual framework covering the
organisation's activity.
Having produced a baseline via the RCM analysis process, every effort must be made to
continually refine the output in accordance with the principles of Total Quality
Management. This continual refinement process follows the principle of using staff at all
levels to continually refine the analysis results. Certain analysis decisions will however
require the application of statistical analysis and engineered solutions and hence require
specially trained and accredited staff.
To ensure that limited engineering resources achieve their best return, activities will be
prioritised on the basis of opportunities for monetary savings or performance
improvement. Analysis candidates are identifiable either by their high resource
consumption or by demonstrating considerably less performance than benchmarked
"world best". Prioritisation for improvement analysis will be based on a combination of
the two factors.
1.1.5 Use of this Manual
This Manual is not a definitive document providing all the detailed procedures and
technical knowledge necessary to undertake maintenance requirements analysis.
Rather, it should be read in conjunction with other more detailed texts included in the
suggested reading material from which the methods have been drawn. This includes the
user manual for any electronic database used to capture information and apply decision
algorithms to determine optimum task frequencies.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
This Manual provides:
A tailored beginners manual for applying RCM analysis to non safety critical
equipment (closure on safety critical failures shall require a further HAZOP or
equivalent safety analysis refer Section 7).
An RCM guide for those accredited in RCM analysis
Adequate explanation for those not involved in the process of maintenance
requirements analysis to understand the concept.
Necessary text for the training of staff that will provide specialist technical
knowledge during an RCM analysis project under guidance from a trained
facilitator.
1.1.6 References
There are a number of reference texts that either explain the RCM analysis process in
detail or in some way provide support to the total process of producing preventive
maintenance programs.
Available RCM procedural texts are all based on the same original work conducted during
the development of the Maintenance Steering Group procedures of the International Air
Transport Association. Detailed directions for RCM analysis are contained in the four
primary references as follows:
Nowlan and Heap, United Airlines, San Francisco, California, 1978
United States Military Standard MIL-STD-2173AS, Reliability Centred Maintenance
for Naval Aircraft Weapons and Support Equipment. 1992
Smith, Reliability Centred Maintenance, McGraw Hill, 1992
Moubray, RCMII Reliability-Centred Maintenance, 1991
The following documents are also recommended as further reading for those who intend
to extend their knowledge of the MRA process and associated reliability engineering
techniques applied as part of a systems engineering process integrating the LSA function
into design.
Maintenance Steering Group 3 Report. 1980
United States Military Standard MIL-STD-2169A, A procedure for a Failure Mode,
Effect and Criticality Analysis. 1977
Blanchard, Logistics Engineering and Management, Wiley Interscience 1986
Blanchard, Systems Engineering and Management, Wiley Interscience, 1991
US MIL-HDBK-388-1A, Electronic Reliability Design Handbook, 1988
United States Military Standard MIL-STD-1388-1A Logistic Support Analysis, 1991
AMCP (US Army Material Command), 706-132
1.1.7 Suggested Readings & References
The following are suggested additional readings for this section.
Standard or Reference Name Page Numbers
Asset Management Policy Manual 12-1 to 12-6
Nowlan & Heap, Reliability - centred Maintenance
Preface and executive
summary
United States Military Standard MIL-STD-2173AS Foreword Pp 1-33
Moubray, RCMII Pp 1-20
Smith, Reliability Centred Maintenance
Foreword and Preface
Pp 1-26
MSG 3 Report Preface
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
2 Background and theory
2.1 Definition of terms
The terms listed in this Manual have the following definitions.
2.1.1 Acronym Definitions
The following acronyms are commonly used within this Manual and are defined below:
FMEA Failure Mode Effects Analysis
FMECA Failure Mode Effects and Criticality Analysis
FTA Fault Tree Analysis
LSA Logistic Support Analysis
MIL-HDBK United States Military Handbook
MIL-STD United States Military Standard
RCM Reliability-Centred Maintenance
MTBF Mean Time Between Failures
MTTF Mean Time To Failure
MDT Mean Down Time
MRA Maintenance Requirements Analysis
MTTR Mean Time To Repair
COTS Commercial Off The Shelf
Actuarial Analysis Statistical analysis of failure data to determine the age-
reliability characteristics of an item.
Age Exploration The process of determining age-reliability relationships through
controlled testing and analysis of chance or unintentional events of safety critical items;
and from operating experience for non-safety items.
Application The set of assets defined by a single Technical Maintenance Plan and
hence given a single accountability for engineering management.
Check Task A scheduled task requiring measurement of some parameter and its
comparison to a required standard (accept/reject criteria).
Configuration Management Plan A document that provides key managerial
accountability and local procedures for the configuration management functions of
identification, change control, status accounting and audit. Additionally, the document
provides details of the numbering and information management practices necessary for
controlling the data set required by configuration management.
Conditional (also Potential) Failure The failure of an item to meet a desired quantifiable
performance criteria which may be either an output or condition parameter and which
indicates that conditional risk is unacceptable.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
Conditional Probability of Failure The probability that an item will fail during a particular
age interval, given that it survives to enter that age interval.
Consequence of Failure The results, to an operating organisation, of a given functional
failure at the equipment level and classified in RCM analysis as:
safety
operational
economic
safety hidden
non safety hidden
Corrective Maintenance The actions performed, as a result of failures (either functional
or conditional) to restore an item to a specified condition (MIL-STD-721B).
COTS The acronym used for Commercial Off The Shelf. Applies to equipment and
software which are part of the manufacturers / suppliers standard product.
Defect Any unacceptable departure of a characteristic of an entity (system, equipment,
assembly, part) requirements.
Default Decision In a decision tree where one of two decisions must be made, it is the
mandatory decision to be made in the absence of complete information. This may occur
in the analysis of both new and in service equipment.
Discard Task The scheduled removal and disposal of items or parts at a specified life or
condition of item or part (time or event) limit.
Double Failure A failure event consisting of the sequential occurrence of the failure of a
protective function and the failure of a function it is protecting. The double failure may
have consequences that would not be produced if either of the failures occurred
separately.
Effectiveness (Task) The criteria for determining whether a particular task is capable of
reducing the failure rate or probability of failure to a required or acceptable level. (i.e. that
the task is worth doing).
Engineering Failure Mode The specific engineering mechanism of failure which leads to
a particular functional or conditional failure.
Examination Task A scheduled task requiring visual examination for explicit evidence of
failure.
Failure The cessation of the ability of an item to perform a specified function.
Failure Effects The impact a particular failure mode has on the operation, function or
status of an item.
Failure Mode The engineering mechanism of failure which leads to a particular functional
or conditional failure. It includes the manner by which the failure is observed and is
generally described by the way in which the failure occurs and its impact, if any, on
equipment operation.
Failure Rate Ratio of the total number of failures within an item population, divided by the
total number of life units expended by that population during a particular measurement
interval under stated conditions.
Fail Safe A design property of a system or equipment which prevents its failure resulting
in catastrophic outcomes.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
Fault The inability of an entity to perform a required function.
Fault Tree Analysis (FTA) The analysis process where by the relationship and
combinations of faults/events are established that will lead to the occurrence of a defined
Fault, and are presented diagrammatically.
FMEA Acronym for Failure Modes Effects Analysis. A process that identifies how a
systems or equipment fail, and identifies the effect of the failure.
FMECA Acronym for Failure Modes Effects and Criticality Analysis which extends the
FMEA to assess the criticality of the failure on the system. (Ref MIL-STD-1629A)
Functional Failure The failure of an item to perform its normal or characteristic functions
within specified limits.
Functional Check A task requiring measurement of some defined parameter and its
comparison against a defined standard (synonymous with a check task).
Hidden Failure A failure not evident to the operator(s) during their performance of normal
duties.
Infant Mortality The relatively high conditional probability of failure during the period
immediately after an item enters or returns to service. Such failures are usually due to
defects in manufacturing not prevented or detected by the quality assurance process (if
any).
Inherent Reliability A measure of the reliability that includes only the effects of an item
design and its application and assumes an ideal operating and support environment.
Level Of Repair Analysis (LORA) The process for determining on an economic basis
whether equipment should be discarded or maintained, and if so whether the
maintenance is performed on or off site.
Logistics Support Analysis The process of determining the total support requirements
for equipment or systems. (MIL-STD-1388-2A&B Logistic Support Analysis).
Mean Down Time A measure of the period of time that an entity is unavailable for its
required function. (includes Mean Time To Repair (MTTR), logistics down time and
administrative downtime).
Maintenance Requirements Analysis (MRA) The process of identifying the appraisal,
preventive and corrective maintenance requirements of systems / equipment to allow the
system / equipment to fulfil its intended function.
Mean Time Between Failure (MTBF) A basic measure of reliability for large repairable
items which exhibit an exponential (random) failure characteristic.
Mean Time To Failure (MTTF) A basic measure of reliability for large non-repairable
items which exhibit an exponential (random) failure characteristic.
Mean Time To Repair (MTTR) A basic measure of the maintainability for repairable
items/systems. It is generally taken as the mean repair time once the staff are on site
with the requisite spares, tools and test equipment.
MIL-HDBK United States Military Handbook
MIL-STD United States Military Standard
MIMIR The Maintenance Requirements Analysis software produced by RailCorp and
named after the giant in Norse mythology who guards the Highest Well of Wisdom
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
On Condition Task Scheduled task to detect potential failures, or to meet calibration
requirements
Operator Person who uses or operates equipment as part of their allocated duties during
its normal usage.
Operational Checks Scheduled tasks to detect the operability of a particular function in
order to check for hidden failures.
Operational Maintenance (also called " organisational" and " field" maintenance)
Maintenance which is either preventive or corrective in nature and that is undertaken on
the system irrespective of whether it is operating or shut down.
Preventive Maintenance The actions performed in an attempt to retain an item in a
specified condition by providing systematic inspection, detection and prevention of
incipient failure (MIL-STD-721B).
Risk The product of conditional probability of failure and failure event consequence.
Redundancy The existence of more than one means for accomplishing a given function.
Each means of accomplishing the function need not necessarily be identical (MIL-STD-
721B).
Reliability Centred Maintenance (RCM) A process which aims to determine the
maintenance requirements of an asset in its operating environment.
Safe Life Limit A life limit imposed on an item that is subject to a critical failure
established as some fraction of the average age at which test data shows that failures will
occur.
Secondary Damage The immediate physical damage to other parts of items that result
from a specific failure mode.
Servicing The performing of any action needed to keep an item in operating condition,
(e.g. lubricating, oiling, fuelling.) but not including preventive maintenance of parts or
corrective maintenance tasks
Servicing Schedule A defined set of tasks to be undertaken on an asset or set of assets
in a defined place at a defined point in time; the result of the task aggregation process
following the RCM task analysis activity.
Significant Item An item whose failure either alone, (or if delivering a hidden function
then in conjunction with another failure), has safety, operational or major economic
consequences.
Technical Maintenance Plan A document which details:
which items are to be maintained,
what maintenance tasks are to be done, and
when and where the maintenance task is to be performed.
Total Quality Management A management approach that achieves continuous
incremental improvement in all processes, goods and services through the creative
involvement of all people.
Wear-out The process which results in an increase of the failure rate or conditional
probability of failure with the accumulation of life units
Workshop Maintenance Deepest level of maintenance undertaken on equipment or
their assemblies (also known as Depot level maintenance in the reference texts).
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED

2.2 Reliability and maintenance
2.2.1 Introduction
While the concept of reliability is not new, its proper definition and introduction as a
branch of engineering is relatively recent. Thus "reliability" is related to a recently
developed body of concepts and methods which date from the 1940s. Maintainability
engineering, as the branch associated with the proactive examination of the maintenance
task, is even younger.
A concise history of reliability, maintainability and safety engineering is available in
Villemeur
8

pages 3-14. It is strongly recommended as background reading.
2.2.2 Reliability
People in all walks of life regularly use the word reliability. We all want reliability from our
assets, be it rail vehicle, high voltage switchgear or dishwasher. Few understand that for
the professional engineer "reliability" is a specialist word with an entire engineering
discipline behind it. A maintenance or systems engineer without an understanding of
reliability is like a surgeon without a scalpel. The necessary incisive tools are just not
there.
Reliability is defined as:
"the probability that an item will perform its intended function for a specified interval
under stated conditions"
9.
The theoretical and mathematical foundations for the reliability engineering discipline are
comprehensively described in Chapter 5 of MIL-HDBK-388-1A
10,
Electronic Reliability
Design Handbook. Many other commercial texts are available on the subject. The
handbook, provides detailed but practical approaches to specifying, allocating and
predicting reliability for engineering systems and equipment.
An understanding of reliability requires more than a cursory look at the primary elements
of the definition. To assist the development of a basic understanding of these elements
and their implications, they are described in further detail as follows:
Probability is a quantitative expression that follows strict mathematical rules and
can be expressed as either a fraction, a percentage, or a decimal value that lies
between zero and 1. Failures are described in probabilistic terms because they
can be expected to occur at different points in time even for identical equipment
operating under identical conditions.
The items being compared must have the same configuration to ensure that
variation in effecting factors is kept to a minimum. Different configurations
represent different populations of items, hence the mathematics of statistics, which
requires statistically homogenous groups (populations), cannot be properly applied
without high probability of erroneous results.
Satisfactory performance requires that specific and measurable criteria have been
established to determine what is satisfactory. This set of quantitative and
qualitative criteria is usually (should be) contained within the system specification.



8 Villemeur, Alain, Reliability, availability, maintainability and safety assessment, J ohn Wiley & Sons, 1992, pages 3-14.
9 US MIL-HDBK-338-1A, Electronic Reliability Design Handbook, US Department of Defence, 1988
10 US MIL-HDBK-338-1A, Electronic Reliability Design Handbook, US Department of Defence, 1988.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




Specified operating conditions include environmental conditions, operational profile
or other such factors which drive the variability of stresses to which the item is
exposed.
Time is the measure against which performance is judged, and provides the
mathematical rigour for reliability through the formulae for varying reliability
characteristics.
From the definition it is evident that the reliability of an item is an inherent attribute
dependent on the item design and its operational requirement and environment. No
amount of maintenance can increase the reliability of an item beyond its design capacity.
Given an effective maintenance regime, only a change of configuration (modification) or a
change to operational requirements and environment can improve an item's inherent
reliability.
Reliability and probability are of particular interest when examining the subject of hidden
functions and double failures. Double failures are generally associated with redundancy
and hence there is a need to understand the impact of redundancy on reliability
calculations.
2.2.3 Failure Characteristics
The failure characteristic of an item refers to the hazard rate (i.e. increasing or decreasing
failure rate with time) profile of that item over time. Until the mid 1970s items were seen
as exhibiting a common failure profile (reliability characteristic) as shown in Figure 4
consisting of three separate characteristics combining into a single composite called a
"bathtub" curve named after its general shape. The three separate characteristics are:
An infant mortality period due to quality of product failures
A useful life period with only random stress related failures
A wear out period due to increasingly rapid conditional deterioration resulting from
use or environmental degradation.
Time
Hazard
Rate
Infant
Mortality
Useful Life Wear Out

Figure 4 - Hazard Rate as a function of age
However, with the advent of increasingly complex systems and equipment, reality proved
to be not as simple as the "bathtub". Actuarial studies of aircraft equipment failure data
conducted in the mid 1960s identified a more complex relationship between age and the
conditional probability of failure. Six different failure characteristics were identified, along
with their relative percentage representation in the aircraft failure population, as shown in
Figure 5.
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




4%
Wear-In to Random to Wear Out

2%
Random then Wear Out

5%
Steadily Increasing

7%
Increasing during Wear-in and then Random

14%
Random over measurable life

68%
Wear-in then Random

Figure 5 - Age (X axis) reliability (y axis) pattern
The six age-reliability failure patterns listed above are described in detail in Nolan and
Heap
11
at Pp 46 and referenced in Moubray "RCMII"
12
at Pp 203217 and Smith
13
at Pp
45. All analysts should be thoroughly familiar with the implications of each type of failure
characteristic. These characteristic failure patterns identify those maintenance tasks that
will be applicable and effective for each identified failure mode and its associated failure
pattern.
2.2.4 Reliability Modelling
The first reliability modelling tools were used on the German V1 rocket program during
World War II. Initial unreliability (100%) was explained by a "weak link concept"
14
which
said the system was only as strong as the weakest part. This was replaced after
consultation by Von Braun with Eric Peirushka, a mathematician, who advised that the
survival probability (reliability) of a set of identical elements with individual survival
probability of 1/x would be (1/x)n (where n =number of identified elements).
The series reliability formula derived from Peirushka's response is shown in Figure 6.



11
Nolan and Heap, United Airlines, San Francisco, California, 1978
12
Moubray, J ohn, Reliability-Centred Maintenance, Butterworth Heinemann, 1992, 203217.
13
Smith, Reliability Centre Maintenance, McGraw-Hill, 1991
14
F T Pierce, Tensile Strength for Cotton Yarns Part 5 The Weakest Link, Theorems on Strength and Composite Specimens,
Textile Institute J ournal, Transactions, 1926
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




R
n
R
1
...........
R
3
R
2

Rt =R
s
=R
1
x R
2
x R
3
x ..............x R
n
Where Rt =Rs =System reliability =Total reliability
R
1
...
n
=Elemental reliability
Figure 6 - Series reliability formula
The series reliability formula is complemented by the parallel reliability formula which
reflects the reliability of a system that has redundant elements capable of maintaining the
function should one of the redundant elements fail. The most common usage of these
phenomena is as a "one in two" redundancy, although other more complex arrangements
(e.g. three in five, two in six ...) are possible. The formula for the basic one in two
redundancy is shown in Figure 7.
Redundancy arrangements in systems enable the consequences of individual item
failures to be avoided by providing a standby item or equivalent function that will fulfil the
complete function of the primary item when it fails. This redundant capability reduces the
consequence of failure to a timely repair process only, and, if there are no other
consequences other than this repair function, the item can be cost effectively run to
failure without any other consequence reducing maintenance.
R
2
R
1

R
t
=R
1
+R
2
- (R
1
x R
2
)
Where R
t
=Total reliability
R
1
...
n
=Elemental reliability
Figure 7 - Parallel reliability formula
Examples of changes in total system reliability performance through application of
redundancy are shown at Figure 8.
In a series system (Figure 6) of equal unit reliability
Rt =R
n

Where R is the unit reliability of corresponding unit and n is the number of units
In a parallel system of equal unit reliability
Rt =1-(1-R)
n
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




Number of similar
units in Series
Number of similar
units in Parallel
System Reliability System Reliability
1 0.9 0 0.9
2 0.81 1 0.99
3 0.73 2 0.999
4 0.66 3 0.9999
Figure 8 - System reliability calculations
Reliability achieved through complex redundancy arrangements of parallel units, which
may only require say 3 of 5 parallel units are known as m out of n reliability. Figure 9
depicts a system whose successful operation requires the correct functionality of m or
more of its n components (parallel configuration).
R
2
R
1
R
3
R
4
R
n
m

Figure 9 - n Parallel reliability block diagram with a minimum of m blocks operable
In situations where the failure rate is constant, the reliability R at time t for m out of n
reliability is given by:
( )
( )

+
=
1
0
)! !
!
) 1 (
1
1
m
i
i n
n
t
i n i
n
t
R


2.2.5 Maintenance Task Applicability
Maintenance activity which supports a system should be designed to protect the reliability
of that system through an understanding of the failure characteristics of the individual
elements of the system and the reliability relationships of those elements. For a
maintenance action to be applicable to a particular piece of equipment, the action must
address individual failure mode(s). A detailed description is provided in Section 4.1.3,
see Task Applicability.
Applicability is a measure of the suitability of the task to the failure mode.
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
2.2.6 Maintenance Task Effectiveness
The effectiveness of a maintenance task is a measure of its ability to achieve its objective
which is usually the ability to reduce or eliminate the effects of the failure mode to an
acceptable level. However, if the objective is to avoid all functional failures then a task
that only reduces the failure rate is inadequate. A detailed description is provided at
Section 4.1.4, see Task Effectiveness.
Effectiveness is the ability of the task to achieve the maintenance objective.
2.2.7 Suggested Readings & References
The following are suggested additional readings for this section.
Standard or Reference Name Page Numbers
Nowlan & Heap Reliability - Centred Maintenance Pp 38-45
United States Military Standard
MIL-STD-2173AS
Nil
Moubray, RCMII Nil
Smith, Reliability Centred Maintenance Pp 43-57
MSG 3 Report Nil
2.3 Maintenance, Risk and RCM
2.3.1 Introduction
The MRA methods described in this manual are based on RCM analysis techniques
developed by the commercial aircraft industry since the early 1970s.
A "brief" history of the RCM process is provided in Chapter 12 of J ohn Moubray's text,
RCM II, Reliability-Centred Maintenance
15
and the preface to Smiths text Reliability-
Centred Maintenance
16
is strongly recommended as background reading. This history
should be read at this stage of the Manual by serious users.
Briefly, the term Reliability-Centred Maintenance was derived from a report by Nolan and
Heap of United Airlines commissioned by the United States Department of Defence in
1978. The process evolved in the private airline industry primarily through the activities of
a Maintenance Steering Group of the International Air Transport Association. The report
of the Maintenance Steering Group in 1972 titled MSG-2 (updated in 1980 with MSG-3),
provided the backbone of the logic processes contained in the referenced texts and RCM
analysis. The RCM process has now been applied to a variety of military and commercial
assets using a number of variations on the original theme.
2.3.2 Maintenance
Maintenance has been defined as
"all actions necessary to retain a system or product in, or restore it to, a
serviceable condition"
17
.



15
Moubray, J ohn, Reliability-Centred Maintenance, Butterworth Heinemann, 1992, .
16
Smith, Reliability Centred Maintenance, McGraw-Hill, 1991
17
AMCP (US Army Material Command), 706-132.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




The word "serviceable" in the definition is considered to mean "fit for function" which has
a significant impact on the decision processes associated with reliability assessment.
Additionally, function should be considered as business function or capability, there being
a need for all maintenance actions to provide a return on their investment through
assured business performance.
The statement, "fit for function", includes not just performance but the level of reliability
(or probability that the item will operate as required for a future period) required and
reinforces the fact that reliability is inherent in design and cannot be increased beyond
that provided by the designer. Maintenance tasks specified in TMPs are generally aimed
at achieving this inherent design reliability by maintenance action. Assets which are
fundamentally incapable of delivering required performance must either be modified or
have their performance criteria lowered.
Achieving an asset's inherent level of reliability requires the identification of what
maintenance is necessary to address the various ways in which the asset fails to deliver
its intended function. It should be noted that for some assets, overdesign or changed
operational circumstances may have reduced its required level of performance. Assets
whose performance requirements are reduced from original design level may have their
maintenance requirements reduced to achieve their reduced level of operational and
associated business performance. This is shown in Figure 10.
PERFORMANCE
PARAMETER
Designed in Capability
Maintenance requirements
reduced to match lower
performance requirements
Increased performance requirements
Reduced performance requirements
Maintenance cannot
increase performance
beyond design capability
Maintenance at best can
only achieve this design
level of performance

Figure 10 - Maintenance Performance
2.3.3 Risk
There has been a tendency in the past for organisations to believe that the equipment
failure process is deterministic and flows from inadequate maintenance; "if you engineers
maintained it properly then it wouldn't fail". This approach completely misunderstands the
probabilistic nature of engineering and in particular the failure process. The "risk" of
failure cannot be totally eliminated but its size can be reduced by an effective approach to
designing-in reliability and responding to the design with applicable and effective
preventive maintenance requirements.
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




2.3.3.1 Risk Assessment
In this regard, risk as it applies to maintained systems can be modelled as the product of
event probability, event consequence and control effectiveness. This model is shown at
Figure 11.
Without a logical and structured approach to determining maintenance requirements that
are based on the mathematics of reliability and risk, a maintenance program will result in
one of two possible outcomes:
The program will not address the inherent failure mechanisms and their
consequences resulting in inefficient reactive maintenance producing occasional
high consequence outcomes such as personal injury or death and secondary
damage to assets.
The program will be conservative in nature and over prescriptive resulting in
excessive maintenance costs and a reduced asset reliability due to inevitable
increases in the levels of infant mortality.
Failure
Mode
Mechanism
and
Cause
Risk Effects
Control
Risk
Event
Consequence
Control
Effectiveness Probability
Event

Figure 11 - Risk quantification with maintenance as control
2.3.3.2 New Acquisitions Risk
Without the RCM approach, the maintenance program for new equipment will usually
progress from an inadequate program to an overly prescriptive one as actual failures are
responded to on a piecemeal basis. Each reactive decision becomes locked in, as time
progresses and the reasons for including tasks is either not documented and forgotten or
if documented, become lost in the archives.
The RCM program manages the risks associated with asset support by ensuring that the
activities necessary to operate the equipment at defined levels of safety and service are
achieved at minimum lifecycle cost. Additionally, the structured and documented
approach ensures the program will remain viable in the long term through an ability to
respond readily and promptly to changes in the operating or maintenance environment.
2.3.4 RCM Process
The determination of maintenance requirements is based on three key analytical
techniques which are:
Failure Modes and Effects Analysis (FMEA)
Reliability-Centred Maintenance (RCM)
Level of Repair Analysis (LORA).
The 7 step RCM process at Unit 1 asks eight basic questions as follows:
which assets (significant items) are to be subject to the analysis process
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
what are the functions and associated performance criteria (accept/reject
boundaries) of each asset in its particular operating environment
how does it fail to fulfil its listed functions (failure modes) FMEA
what failure mechanism causes each loss of function (failure cause) FMEA
what is the outcome and impact (criticality) of each failure (failure effect) FMECA
what maintenance tasks can be applied to prevent each significant/critical failure
(preventive maintenance)
what action should be taken if effective maintenance tasks cannot be identified
(default action).
This process is detailed in Section 4 of this publication.
2.3.5 Other Users of RCM
RCM has been applied extensively to the commercial airline industry since the late 1960s
when the International Air Transportation Association, Maintenance Steering Group
report MSG-1 was developed for and applied to the Boeing 747 aircraft. This initial work
was followed by improvements embodied in the MSG-2 report in 1972 and the MSG-3
report of 1980.
The RAAF applied a variation of the MSG-2 process to its aircraft from 1975 under the
RAAF Analytical Maintenance Philosophy (RAMP) project. The US Navy applied the
MSG-2 logic to a number of aircraft commencing in 1978 with the P-3 Orion maritime
aircraft. Since then the logic has been applied to a number of high value and
operationally critical commercial sites such as oil platforms and nuclear power stations.
A listing of types of industries known to be using RCM analysis around mid 1992 are
listed in Moubray's book "RCMII"
18
page 268. In Australia, the RCM process is now used
in the following industries:
Rail
Power
Military
Mining
Water Supply
Manufacturing
2.3.6 Benefits
The benefits of applying RCM will vary between organisations and will depend on the
effectiveness of current maintenance practices. However, application of the process can
generally be expected to result in:
Increased safety and environmental integrity due to prioritisation in the logic chart,
reduction in double failure probabilities and reduced exposure to unnecessary
maintenance.
Improved system effectiveness where effectiveness is defined as the product of
availability, operating efficiency and quality of output or yield. This results from
reduced hard time maintenance tasks, improved repair times and improved
reliability flowing from removal of unnecessary items found redundant by the
analysis.



18
Moubray, J ohn, 1992, Op Cit, 268.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
Improved maintenance cost effectiveness resulting from increased levels of
planned maintenance, improved contract maintenance performance and reduced
need for expensive field service representation.
Extended asset lives by ensuring best balance between being over-maintained,
which wears and damages key interfaces such as connectors and fasteners, and
being under-maintained which allows significant degradation, each of which may
not be economically recoverable requiring premature replacement.
Improved engineering knowledge flowing from the application of the analysis
process and the availability of a maintenance database which clearly describes the
origin of maintenance requirements which can be used to support change. This
reduces an organisations susceptibility to loss of knowledge through personnel
movements.
2.3.7 The RCM Model
Maintenance requirements analysis described in this Manual has been drawn from
experience in the Australian aircraft, rail, power and water industries. These
organisations have used a variety of resources to undertake RCM analysis of equipment
which has generally been in operation for at least five or more years.
The general structure of the model to be applied in determining the maintenance policies
for equipment and systems (tasks and frequencies) is shown at Figure 12.
New assets will require analysis to be done in accordance with a single standard
generally applied through an interactive computer data base to improve development
efficiency and facilitate ease of access by responsible systems engineers. The
requirement for RCM analysis data should be a deliverable in future significant asset
acquisition projects.
2.3.8 Process Steps
Whether conducted by hand or done on a spreadsheet or interactive database, RCM
analysis follows the process flow chart in Figure 13 and Figure 14.
Three standard RCM task analysis logic diagrams were examined to create the logic
process defined in this publication. These logic charts were drawn from:
MSG-3 Report (Used for new commercial aircraft)
US MIL-STD-2173(AS) (Used for new and in service military aircraft)
RAAF Analytical Maintenance Philosophy (Used for new and in service military and
transport aircraft).
2.3.9 Analysis Team
RCM analysis has been performed both during the design of an asset and after its
acquisition. As stated, analysis during design is the most effective method, however, for
a variety of reasons the analysis of existing systems often becomes necessary.
Irrespective of whether the analysis is pre or post acquisition, a team effort will be
necessary to get the best results.
The selection of the analysis team depends on the alternatives being satisfied. However,
the important principle to be followed is that no one person has all the information
necessary to undertake an effective RCM analysis. Participation of staff at all levels in
the organisation is essential, not just for technical reasons but for the acceptance of the
output of the process.

RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM


Design characteristics
Functional Breakdown
Significant systems
FMEA
RCM Analysis Logic
and items
Re-Design
Maintenance
Program
Preventive
Package tasks
Determine task period

Figure 12 - RCM analysis process chart


RailCorp Page 28 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
ering Manual Integrated Support
quirements Analysis Manual AM 9995 PM




RailCorp Page 29 of 114
Issued J uly 2010 Version 5.0

Figure 13 - RCM analysis logic chart
UNCONTROLLED WHEN PRINTED


RailCorp Engine
Maintenance Re
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




Operator
Monitoring
Assess
Criticality
Redesign
Safety
Environment
Economic
Group Tasks
On-System
Group Tasks
Off-System
Assemble
TMP
Legend:
Task analysis
Logic diagrams see Section 8.8
Structured
Breakdown
Select
Candidates
Identify
Functions
New
Configuration
Collect
Data
Identify
Failure Modes,
Causes and Effects
YES NO
EVIDENT EVIDENT HIDDEN
Safety
Environment
HIDDEN
Economic

Figure 14 - Analysis process chart
2.3.10 Post Acquisition Analysis
When analysis is performed after an item has been acquired and been operating for
some time, the following team selection process is recommended:
The team must have an identified facilitator to provide encouragement, direction,
referee functions and allocation of follow-up tasks.
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
Team size should be between three and six staff, including the facilitator, to
provide a balance between knowledge needs and the complexity of communication
between participants (too many cooks!).
Team knowledge must cover from "hands on" through to specialised technical aspects.
Some participants may be invited specifically for one key task. Typical participants in a
team are:
Operator
Trade maintainers / Technical Officer
Engineering specialist
Supervisor
Scribe
Where computerised analysis is conducted, a technical scribe can often be highly cost
effective in reducing analysis time and assisting facilitators who may be part time internal
staff. Scribe duties encompass such activities as:
the rapid typing of large amounts of commentaries from participants into
spreadsheets or databases
managing the configuration management aspects of an often large and complex
database of analysis files
printing out and disseminating "post analysis" actions to be completed prior to the
next analysis meeting
preparing the room for the facilitator
Latest approaches to facilitation use computer overhead displays in an intense
information retrieval and decision making process. The advantages of this process are:
Preparation work is done by scribes who assemble configuration data regarding
the functions and physical data of the systems and their items of equipment.
Data is collected in structured manner with all relevant comments from participants
captured on a permanent record.
Decisions are quickly obtained and signed off in a visible manner
Delays to the analysis due to lack of information are prevented by documenting
hold ups and allocating accountability for post meeting action.
2.3.11 New Acquisitions
For new acquisitions, the conduct of the RCM analysis should be the responsibility of the
Prime Contractor and should be a deliverable under the contract. The procedures used
should satisfy the approach in this document and be delivered in a form which will
interleave smoothly with operating systems data. Project design reviews (e.g.
Preliminary Design Review, Critical Design Review) in accordance with the principles
contained in the Asset Management Policy Manual will require the assembly of an audit
team to examine progress in FMECA and RCM activity.
This subject is dealt with in greater detail at Section 4.
2.3.12 Data Collection
Maintenance requirements analysis cannot be undertaken in an information vacuum and
certain data will be necessary to start the process.
This process of collecting data represents the first step in the analysis flow chart at Figure
14. The data, which would include failure summaries and key diagrams such as
functional, physical and reliability block diagrams, not only supports the maintenance
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
analysis but may become invaluable in the future as a set of resource data managed
under configuration control.
Typically the collected data should, where possible, include the following:
System and equipment drawings
Electrical and hydraulic circuit diagrams
System plans
Operations and maintenance manuals
System and equipment failure data
System functional and physical block diagrams
2.3.13 Suggested Readings & References
The following are suggested additional readings for this Section.
Standard or Reference Name Page Numbers
Asset Management Policy Manual
Nowlan & Heap Reliability - centred Maintenance
United States Military Standard
MIL-STD-2173AS
Foreword Pp 1-33
Moubray, RCMII Pp 1-20
Smith, Reliability Centred Maintenance Foreword and
Preface Pp 1-26
MSG 3 Report Preface
3 System Breakdown
3.1 Introduction
System breakdown provides the most important first step of structuring the system into
logical blocks to enable the application of a structured approach to the analysis activity
and to provide the list of significant items for analysis. The process also establishes the
boundaries for the:
collection of data to support the continual improvement process and
allocation of certain management accountabilities.
Not all items that make up a system justify the detailed analysis required by the RCM
techniques described in the texts. Only those items whose failure results in potential
safety, environmental or economic consequences should be considered for analysis.
A detailed description of the formal process used in establishing a system breakdown
structure is contained in US MIL-STD-1629A (FMECA)
19
pages 101-1 to 101-4. Where
FMECA is undertaken as a requirement of the design process, the output of the FMECA
is a set of failure modes and effects with established criticalities.
Those failure modes not removed during the iterative design process will have a
remaining criticality assigned which may be expressed either quantitatively or
qualitatively. These remaining failure modes must have an assigned compensating
provision or management mechanism. Operator monitoring and preventive maintenance
are two such compensating provisions.
The primary elements of the system breakdown process are shown at Figure 15.



19 US MIL-STD-1629A A Procedure For a Failure Mode, Effects and Criticality Analysis, 101-1 to 101-4
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




BOUNDARIES
BREAKDOWN
COMPLETE
FUNCTION
DIAGRAM
SIGNIFICANT
ITEMS
PRIORITISE
DETERMINE DEVELOP
ESTABLISH

Figure 15 - System breakdown process
3.1.1 Establishing Boundaries
Each system identified in the system breakdown will have a number of interconnects
(interfaces) with adjacent interactive systems. These boundaries need to be defined in a
clear and unequivocal manner to ensure that there are no accountability gaps or
overlaps.
The objectives of establishing data collection arrangements and the allocation of
accountabilities should be carefully considered during the breakdown process. General
rules for establishing effective system boundaries are that the boundary should:
Contain a clearly defined function.
Commence at an identifiable point where system interface requirements are clear
and, where possible, physical separation is achievable.
Not cross areas of defined managerial accountability.
The drawings at Figure 16 and Figure 17 show an example of a boundary established
between a bulk oil supply and individual client units. Systems 1, 2 and 3 have different
management accountabilities therefore boundaries are established which clearly identify
the division between the common service function of bulk oil supply and the individual
clients of system 1 and system 2. The boundary is set at the input end of the shut off
valve as this valve protects the client systems and is functionally unlinked to any third
system.
System 1
System 2
System 3
Bulk Oil Supply
Turbine A
Turbine B

Figure 16 - Boundary block diagram
Figure 18 shows how the boundary is established at the detailed level allowing for
allocation of asset management accountabilities. Thus although the interface
specification or description defines the physical separation point, the accountabilities,
shown by a circle at Figure 17, absorb this connection arrangement into a total
accountability to ensure clear ownership of the interface. Most systemic problems occur
at interfaces due to unclear accountability; this allocation of total accountability reduces
that risk.
A difference in engineering discipline is not a valid reason for establishing a boundary.
For example, although a chimney may be a civil engineered concrete structure it should
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




be included as an integral part of the exhaust system much of which may include
scrubbers and other mechanical plant. This concept encourages the application of a
systems approach to the management of the defined assets rather than a constrained
discipline approach which may be insensitive to systems wide interactions.
System 1 System 2
Analyse and
maintain as
single entity

Figure 17 - Boundary detail
Examples of other boundaries similar to that described in Figure 17 above are:
Primary machine and supporting plinth
Primary item and cable connectors
A further example shown at Figure 18 develops the concept of separation of supply,
distribution and user where the supply function is distributed to a variety of users. The
idea of suppliers and customers is encouraged in that each asset manager is both a
customer of some and a supplier to other customers that is each asset manager should
ensure that they receive required services from suppliers and provide required services to
their customers.
Boiler
Storage
Tank
Steam
Pipes
SUPPLIER
DISTRIBUTER
USER

Figure 18 - Steam heating supply
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




Clear ownership boundaries for indication and control systems are often difficult to
establish. In most instances, sensors take inputs from the prime equipment (and are
often buried inside that equipment), convert this to a transmittable signal that is passed
along metal wire to a central control room. Control mechanisms can also be embedded
in the prime equipment and follow similar rules regarding asset ownership.
The following general rules are usually effective in allocating functional boundaries for
control and indicating equipment accountability:
Sensor and associated indicating equipment attached to the prime equipment
belongs to the control and indications system owner.
Remote indicating and control equipment (clustered in a control room for example)
and the associated cabling belongs to the control and indications system owner.
Sensors embedded in or removed with the prime equipment belong to the prime
equipment owner.
Sensors and controls that remain attached to their cabling when the prime
equipment is removed belong to the control and indications system owner.
3.1.2 Develop Functional Block Diagrams
Functional block diagrams describe the operation, interrelationships and
interdependencies of functional entities in a system. They are constructed in terms of
engineering data and schematics to enable failure modes and effects to be traced
through the various levels of a system.
These diagrams are essential to a clear understanding of the total system and its
interactions when preparing for the failure modes and effects analysis.
A system level diagram is also essential to the description of the Application in the
preface to the Technical Maintenance Plan. A typical electrical network assets
application block diagram is provided below for each asset class.
ER
Earthing
SU
Substation
General
TX
Transformers
OH
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
Overhead lines
UG
Underground Cables
SL
Street Lighting
SC
SCADA
CM
Communications
PR
Protection
AU
Auxiliary Equipment
AF
Audio Freq Load Ctrl
DC
DC Power System
VR
Voltage Regulation
SW
Switchgear

Figure 19 - Typical Electrical Application Block Diagram
The detailed procedure for developing and numbering a functional block diagram are
available in MIL-STD-2169A Pp101-3 to 4 and 9.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




3.1.3 Significant Items
Not every item in a system is significant and justifies the expense of a comprehensive
RCM analysis. The basic approach to be applied in establishing the significant item list is
shown in Figure 20. The system plans, drawings and diagrams are used to compile a list
of functional items in the system. This list is then processed to determine those items
whose failures have some significant impact on the business objectives of the
organisation.
The significant item analysis process undertakes a comprehensive review of the system
design features to limit the size of the analysis task by a quick, but conservative,
identification of the set of functionally significant, structurally significant and hidden
function items. The results of applying the process are shown in Figure 21 and Figure
23.
SYSTEM
OR EQUIPMENT
FUNCTIONAL
BREAKDOWN
MAJOR LOAD
CARRYING
ELEMENT
ADVERSE EFFECT
ON SAFETY, THE
ENVIRONMENT
OR SERVICE
IS FAILURE RATE
OR COST HIGH
STRUCTURALLY
SIGNIFICANT
ITEM
YES
NO
YES
YES
NO
DOES THE ITEM
HAVE EXISTING
SCHEDULED
MAINTENANCE
FUNCTIONALLY
SIGNIFICANT
ITEM (FSI)
NON SIGNIF-
CANT ITEM
YES
NO
NO
DOES ITEM PROVIDE
EMERGENCY FUNCTION
YES
NO

Figure 20 - Selecting significant items
Figure 21 displays the items in a system as a descending hierarchy. Not all these items
will be classified as "significant" as their failure may have little impact on the operation of
the system other than the cost of repair. As a guide, significant items are considered to
be those:
Whose failure modes threaten safety or breach known environmental standards.
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010


The spreadsheet at Figure 22 identifies the system equipment from the example shown in
Figure 16 that are candidates for assessment. Only those that are considered significant
in accordance with the logic chart will be subject to analysis. Spreadsheets provide a
convenient mechanism for storing information and automating some simple activities
when conducting item significance analysis.
UNCONTROLLED WHEN PRINTED
Whose failures modes have significant operational or economic consequences
Which contain a hidden function whose failure exposes the system to a significant
double failure consequence
Are part of an emergency system.
APPLICATION
Parts

Systems
Sub Systems
Assemblies
Figure 21 - All elements listed
ering Manual Integrated Support
quirements Analysis Manual AM 9995 PM




RailCorp Page 38 of 114
Issued J uly 2010 Version 5.0 UNCONTROLLED WHEN PRINTED
System Code TR-01-00-00

System Name Emergency Pumping System



Asset Code Equipment Name MLC Saf Env Serv HFR HRC Exist Emerg Sign
TR010100 Pump n n n y n n y n Y
TR010200 Level sensor n n n n n n n y Y
TR010300 Control Unit n n n y n n n y Y
TR010400 Auto Shut off valve n n n n y n n y Y
TR010500 Isolating Valve n n n n n n n n N
TR010600 Pipework n n n n n n y n Y

Abbreviated column headings for the criticality assessment are:
MLC main load carrying structure
Saf failure of the equipment has safety implications
Env failure of the equipment has environmental implications
Serv failure of the equipment has service implications
HFR high failure rate equipment
HRC high resource consumption
Exist there is an existing preventive task
Emerg the equipment is part of an emergency system
Sign the equipment is significant, yes (Y) or no (N). Only if all the above questions result in a no answer does the system qualify as not
significant.
Figure 22 - Significant items spreadsheet


RailCorp Engine
Maintenance Re
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




Figure 23 shows the non significant items removed from the tree leaving fewer individual
items to consume the resources allocated to analysis.
APPLICATION
Systems
Sub Systems
Assemblies
Parts

Figure 23 - Significant items remaining
3.1.3.1 Top down approach
The RCM analysis occurs from the top down and should be conducted at the highest
level possible in the system. Analysis at the assembly and parts level should only occur if
that part has an actual function. Performing the RCM analysis at too low a level in the
structure i.e. at parts as shown in Figure 23, unnecessarily complicates the analysis
process by focusing on detail, creating excessive paperwork and usually identifying no
additional tasks.
3.1.4 Prioritisation
RCM analysis is expensive and a return on the investment in the analysis should be
obtained as quickly as possible. This can be achieved by prioritising the equipment to be
analysed and implementing the outcome as soon as the supporting maintenance
management systems will allow.
Prioritising the conduct of the RCM analysis activity is usually only an issue for assets
already in service where the results of the analysis can be independently applied to the
asset under review. For new equipment yet to be placed in service or with equipment
where the analysis results must be developed during the procurement process, this is
usually not an issue.
An example of prioritisation of in service RCM analysis is a distributed electrical system
which may have the output of RCM analysis applied separately to specific parts of the
system. This is possible due to the ability to contain the application of RCM to finite
elements such as say the DC Circuit Breakers in an electrical supply substation.
The prioritisation process also enables evaluation or prototyping programs to be
conducted independently allowing high cost activities or equipment to be targeted for
early implementation.
RailCorp Page 39 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 40 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
The prioritisation process should reflect system and equipment criticality as determined
by the FMECA process or some other similar risk estimation method. The process must
direct the analysis at determining the preventive maintenance requirements of those
items of equipment which represent the greatest risk to organisational and/or business
objectives if proper maintenance is not undertaken.
3.1.5 Numbering Systems
There are three types of numbers that may be used to categorise data against a system.
These numbers are:
A functional system identifier that is often referred to as a technical maintenance
code (TMC) and is used to develop the maintenance requirements analysis.
A geographic identifier common to asset registers that enables the particular
functional element in a system to be found for maintenance or other purposes.
A unique item identifier that enables allocation of data against a particular item
fitted to the functional "hole" at a geographic point in the system. This data usually
contains three pieces of information, Item manufacturer, Item Part Number and
Item Serial Number.
Each number is part of the set of data controlled by a configuration management system
that:
Identifies the system configuration
Controls changes to that configuration
Accounts for status at any particular time
Audits the physical and functional configuration at key points in the system life
cycle
The system breakdown and its associated numbering should be structured to support the
"functional" thrust of the RCM analysis program. For this reason a hierarchical system
which reflects the configuration of the total system and the functional relationships
between its parts is recommended.
As a general rule, fleet type equipment and production plant will generally require a
system consisting of:
Application (Equipment type covered by the Maintenance Plan)
System
Sub-system
Assembly
Sub-assembly
Item
Distributed systems, where components are scattered and individual elements of
significantly different configuration are interchangeable, have a structure that responds to
reduced depth and greater equipment diversity:
Application (Maintenance plan coverage)
System
Item Category
Item Type
Distributed systems, often have multiple types of items capable of undertaking a
particular function in the system, particularly where procurement practices encourage a
multiplicity of models and makes.
Numbering systems should be kept simple. One system used extensively in the
Australian rail and air environment is shown at Figure 24.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




TR 01 00 00 00

where TR is the Application giving potentially 26 x 26 different maintenance plans
depending on the need to align letters with actual names.
01 is the system
00 are the remaining lower order elements or categories
Figure 24 - Numbering system structure
A possible implementation of a four level structure for typical electrical assets (shown in
Figure 19) is outlined in Figure 25 below:
RailCorp Page 41 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




NAME
1 2 3 4
SW 00 00 00
SWITCHGEAR
SW 01 00 00 BULK OIL, OUTDOOR
SW 02 00 00 MINIMUM OIL, OUTDOOR
SW 03 00 00 GAS, INDOOR
SW 04 00 00 VACUUM, OUTDOOR
SW 05 00 00 AIR, INDOOR
SW 06 00 00 BULK OIL, INDOOR
SW 07 00 00 MINIMUM OIL, INDOOR
SW 08 00 00 VACUUM, INDOOR
SW 10 00 00 LOW VOLTAGE
SW 15 00 00 RECLOSERS
SW 20 00 00 AIRBREAK SWITCH, MANUAL-not pol e s/s type
SW 21 00 00 AIRBREAK SWITCH, AIR OPERATED
SW 22 00 00 AIRBREAK SWITCH, ELEC. OPERATED
SW 23 00 00 BUSBAR, EXPOSED (WITH VT' S)
SW 24 00 00 BUSBAR, ENCLOSED (WITH VT' S)
SW 50 00 00 AIR BREAK SWITCH, DISTRIBUTION LOCATION
SW 60 00 00 Ri ng Mai n Swi tch (AIR) - metal encl osed
SW 61 00 00 Ri ng Mai n Swi tch (OIL) - metal encl osed i ncl udes bus bars
SW 62 00 00 Ri ng Mai n Swi tch (SF6) - metal encl osed i ncl udes bus bars
SW 65 00 00 Ri ng Mai n Swi tch (AIR) - Resi n encl osed
TX 00 00 00
TRANSFORMERS
TX 01 00 00 132/33/11kV
TX 02 00 00 132/11kV
TX 03 00 00 66/33 kV
TX 04 00 00 66/11kV
TX 05 00 00 33/11kV
TX 80 00 00 Auto Tap Changers - Rei nhausen
TX 82 00 00 Auto Tap Changers - Charl eri o
TX 83 00 00 Auto Tap Changers - Feranti
TX 84 00 00 Auto Tap Changers - ABB
TX 85 00 00 Auto Tap Changers - Other
OH 00 00 00
OVERHEAD LINES
UG 00 00 00
UNDERGROUND CABLES
PR 00 00 00
PROTECTION
PR 01 00 00 Current Transformers
PR 02 00 00 Vol tage Transformers
PR 10 00 00 Rel ays - Mechani cal
PR 11 00 00 Rel ays - El ectroni c
PR 20 00 00 Surge Di verters - 132kV
PR 21 00 00 Surge Di verters - 66kV
PR 22 00 00 Surge Di verters - 33kV
PR 23 00 00 Surge Di verters - 11kV
PR 24 00 00 Surge Di verters - other
DC 00 00 00
DC POWER SUPPLIES
ER 00 00 00
EARTHING
AU 00 00 00
AUXILLIARY EQUIPMENT
SU 00 00 00
SUBSTATIONS (General )
SC 00 00 00
SCADA
SL 00 00 00
STREET LIGHTING
CM 00 00 00
COMMUNICATION
AF 00 00 00
AUDIO FREQUENCY LOAD CONTROL
VR 00 00 00
VOLTAGE REGULATION
TMC code

Figure 25 - Typical 4 level TMC Outline Structure
RailCorp Page 42 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 43 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
3.1.6 Electronic Filing
Completed MIMIR

maintenance analysis databases will be kept under configuration
control to support continual improvement. Maintenance requirements analysis, even
when done cost effectively is a costly investment. Much of the return on investment
comes from the continual improvement program and hence the ongoing validity of the
analysis data should be maintained.
Analyses collected and maintained on databases such as MIMIR

will be transferred from
the analysis PC to the Client Library which will be maintained as a master. Each system
will correspond to an equipment class, and the systems and equipment will be added to
the library when the analysis, Service Schedules and TMP entries have been approved.
Local backups of the local MIMIR database will be generated using the programmes
Backup Current Database function. The Client Library should reside on a file server
which is backed up regularly, or else on a PC where backups are generated onto storage
media after each database transfer to the Client Library.
3.1.7 Suggested Readings & References
The following are suggested additional readings for this section.
Standard or Reference Name Page Numbers
Nowlan & Heap, Reliability - centred Maintenance Pp 80-86
United States Military Standard
MIL-STD-2173AS
Pp 20-21
Moubray, RCMII Reliability- centred maintenance Pp 243-244
Smith, Reliability Centred Maintenance Pp 38-41
MSG 3 Report Nil
3.2 Failure Modes and Effects Analysis (FMEA)
3.2.1 Introduction
If equipment never failed or needed preventive maintenance then there would be no need
for the provision of any maintenance support. Maintenance plans would not be needed
nor would maintenance staff, spares, tools and the other support costs associated with
the correction and prevention of failures.
All support needs flow from the fact that systems and equipment fail.
It is equipment failure modes and their subsequent effects that are the starting point for
the determination of system support requirements.
The Failure Modes and Effects Analysis process (FMEA) is a reliability procedure which
documents all potential failures in a system design through application of a set of
specified rules. The process may be top down, similar to fault tree analysis (FTA) or
bottom up commencing at the smallest indivisible element in the system.
FMEA as an element of the complete Failure Modes Effects and Criticality Analysis
(FMECA) process is described in MIL-HDBK-338-1A Sect 7-100
20
. The specialist text
which provides the standardised methodology for both FMEA and FMECA is MIL-STD-



20
US MIL-HDBK-338-1A, Electronic Reliability Design Handbook Sect 7100
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




1629A
21
. A more general approach can also be found in IEC 60812.
22
These texts are
not appropriate for use directly in the analysis of rail systems and accordingly they have
been tailored within this text by the experience gained during past RCM analysis
programs.
The failure data derived from the FMEA provides the raw data for all subsequent analysis
associated with the provision of support needs under the generic heading of a Logistic
Support Analysis process.
These support needs include:
Maintenance Planning
Technical data
Training
Personnel
Supply support
Support and test equipment
Facilities
Packaging, handling, storage, and transport
Computer Support.
3.2.2 Process Overview
The FMEA process applied to systems design, involves the identification of the system
functions, the identification of possible failure modes and the effect of the failure mode.
The process is an iterative design tool used to reduce future failure modes in the end
product and is shown in Figure 26.
Definition of the
system its function
and components
Determination of
failure mode
inventory
Examination of
failure mode
effects
Past Failures
Similiar equipment
failures
Reliability Tests
Allocation of
failure modes
to components
and functions

Figure 26 - Failure mode and effects analysis
3.2.3 Functions, Missions and Failures
As defined earlier, the purpose of maintenance is to ensure assets are able to fulfil their
intended business function. The identification of functional requirements provides the
starting point for the analysis of identified significant items.
Functions are established in a top down manner using functional block diagrams. The
function statements must provide clear traceability from the functional requirements of the



21
US MIL-STD-1629A A Procedure For a Failure Mode, Effects, and Criticality Analysis.
22
IEC 60812 Analysis techniques for system reliability Procedure for failure mode and effects analysis
RailCorp Page 44 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




business system through to the resulting assemblage of maintenance tasks defined in a
Technical Maintenance Plan.
The relationship between business requirements, functions and preventive maintenance
tasks is shown at Figure 27. Business needs create asset solutions with system
functions and derived equipment functions that lead to the determination of maintenance
requirements that include a risk managing preventive maintenance program.
Business
Requirement
Asset
Solutions
System
Functions
Maintenance
Requirements
Preventive
Maint tasks
Equipment
Functions
Functional
Descriptions

Figure 27 - Relationship between business needs and preventive maintenance
3.2.4 Types of Functions
At the equipment level there are four types of functions used in the FMEA process and
applied as the prelude to RCM analysis of existing equipment:
Principal functions which represents the business reason for an assets
existence.
Ancillary functions which provide additional useful functions either as enhanced
capability such as reverse thrust in aircraft engines, additional capability such as
steerage with differential braking or opportunistic such as attachment points and
load carrying of adjacent equipment.
Protective functions such as alarms and automatic shutdowns.
Obsolete functions that serve no identifiable useful purpose, but whose failure
may result in adverse effects such as by passed plumbing, circuitry or unused but
dynamic infrastructure (e.g. Track embankments, bridge abutment subject to
collapse).
All listed functions of an item that are to be protected by maintenance activity should
derive from, and support, a top level business objective.
Functions are best illustrated via the creation of a logic block diagram of the entire system
which defines the functional dependencies among the elements of the system. Figure 28
provides an example of a functional block diagram. This functional block diagram, if
complex, may be supported by a data dictionary such as the example shown in Figure
29, which provides a more exacting description of each function including required values
and allowed operating envelopes or performance standards e.g. 440V 20V.
These functional block diagrams and their supporting data dictionaries provide a checklist
of the key functions that maintenance must protect in terms of extending the life of the
item with necessary service activities and preventing the consequences of failures
through the cost effective application of condition monitoring, hard time changeout (for
overhaul or throwaway) and failure finding tasks.
RailCorp Page 45 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




AC Power from Rectifier XFMR
Cool Air
Shunt
SCADA Controls
Buchholz Relay
OCB Shunt
Auxiliary Supply
AC Protection Relay Power
AC Protection Relay Output
1500V +ve
DC Power to Rectifier OCCB
600V AC to Auxiliary XFMR
Hot Air (Heat added)
Earth Current
Buchholz Relay
DCCB Power
SCADA Indication
Visual Indications
OCB Controls
DCCB Controls
DCCB Status
AC Protection
Relay
POWER CUBICLE
CONTROL CUBICLE

Figure 28 - Functional block diagram
Functional block diagrams must be available before the commencement of the failure
modes and effects analysis. These block diagrams should be drawn from available
manuals and drawings and verified where ever possible by site examination. Properly
drawn, with the extraneous material usually present in design and production drawings
removed, they provide a clear and visible checklist of items comprising the systems and
their functional relationships.
It is also important that, where appropriate, the various system states are properly
inventoried and characterised to ensure that the maintenance actions reflect the actual
operating environment of the equipment. Some examples of these states are:
Operating Standby Backup
Storage Testing

Functions are usually identified in the form of a desired standard of performance with
functional failure deemed to have occurred when this level of performance is not
available. The process of defining functions is described in MIL-STD-1629A
23
Page 101-
104, in Moubray's RCMII
24
, pages 37-54 and in Smith
25
at pages 78-80. These more
detailed descriptions may be read in conjunction with this section for a more complete
understanding of the importance of and possible options for clear concise functional
descriptions.
Function name Function Parameters
AC Power from Rectifier
XFMG
2 x 3 600 Vac (1 , 1>)
AC Protection Relay Output Trip
Auxiliary Supply 120 Vdc , 220 Vac (Control cubicle lamp)
Buckholz Relay Status gas surge (G31), Oil Surge (G32)
DCCB Controls Close (3,9), Open (7)
DCCB Status In Service (C4), Closed Ind (5) open Ind (6) Reverse
Current (10), ">" (14)



23
US MIL-STD-1629A, A Procedure For a Failure Mode, Effects, and Criticality Analysis., 101104.
24
Moubray, J ohn, Reliability-Centred Maintenance, Butterworth Heinemann, 1992, 3754.
25
Smith, Reliability Centred Maintenance,
RailCorp Page 46 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 47 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
Function name Function Parameters
DC Power To Rectifier
DCCB
1 x 12 Pulse Output (1500Vdc, +ve &-ve)
Manual Controls OCB Close, OCB Open, DCCB Close, Lockout,
Reset, Indication lamps ON, Supervisory/Local
OCB Controls Trip (from 5250), Trip (52T), Remote Close Control
(305), Closing Contactor, Drive (84), Closed (68),
Open (50), Closed - DCCB Control (66)
SCADA Controls Open, Close
SCADA Indications Lockout, In Service
Shunt 2 Wire Circuit from -ve shunt
Visual Indications OCB Closed, OCB Open, DCCB Closed, DCCB
Open, Local/ Supervisory, Lockout, Buckholtz Gas,
Buckholtz Oil, Reverse Current, Output Current,
Output Voltage, Trip Supply, Sequence Timing,
Frame Leakage.
Buckholtz Power BP
DCCB Power BP, BP, BN3, BN1,
Figure 29 - Functional data dictionary - Rectifier
The following is an example of a functional statement with associated performance
standards suitable for RCM analysis:
To transmit a warning signal to the control room when the gas turbine exhaust
temperature exceeds 520C or a shut down signal if the temperature exceeds 550C.
Key aspects in identifying functional failures are that:
Equipment may have more than one function
Functions are not just binary (off or on) but may involve operating envelopes or
performance standards of one or more parameters.
FMEA examines failures in relation to reliability and hence is influenced by the
particular mission phase and associated environment that establishes the reliability
performance of the equipment. Reliability is directly affected by the operating
environment of the equipment as shown in the definition statement.
Performance standards set the operating boundaries of items of equipment and
often cover the perceived needs of a number of different stakeholders with differing
priorities in regard to operating requirements.
3.2.5 Failure Modes
Failure mode is defined as "The manner by which a failure is observed and generally
describes the way the failure occurs and its impact on equipment operation"
26.
By
defining the functions intended to be performed, we clearly define what a failure mode is.
Failure modes are "the effects by which failures are observed."
Maintenance is managed at the failure mode level because each failure mode is
assessed individually and tasks appropriate to the management of that failure mode can
be determined. Care must be taken to ensure that identified failure modes are properly
connected to the causative mechanism. Some lateral thinking may be required to
prevent stating the obvious and missing the underlying cause.



26
US MIL-STD-1629A, A Procedure For a Failure Mode, Effects, and Criticality Analysis.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 48 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0

For example functional failures in an air compressor may be listed as:
piston seized
bearings seized
crank failed.
This listing may lead, quite erroneously, to a proposal to check for bearing vibration or
undertake oil analysis for wear particles. Instead, the prime failure mechanism was lack
of oil from which the other failures flowed and hence the failure modes could be listed at
the top level (Air Compressor) as:
Air compressor seizes due to oil leakage from life expired seals
Air compressor seizes due to lack of oil from normal operational consumption
In MIMIR, this information would be recorded as follows:
Part Description: Air Compressor
Failure Description: Seizes
Failure Cause: Oil leakage from life expired seals.
Failure Cause: Lack of oil from normal operational consumption.
3.2.6 Types of Failures
There are two types of failure categories assigned to identified failure modes:
Functional failures where the function and its associated performance standard
can no longer be achieved
Conditional failures where the items conditional failure probability (ie probability
that the item will fail in a future time period), as assessed through some form of
condition monitoring, is no longer acceptable
The decision to undertake preventive maintenance is an expenditure that must provide a
return on investment. Clear traceability of each function to a business objective is an
essential element in reducing the likelihood of unproductive maintenance actions being
specified within a maintenance plan.
MIL-STD-1629A
27
(pages 101-105) provides the following minimum list of typical failure
conditions to assist in assuring that a complete analysis has been performed:
Premature operation
Failure to operate at a prescribed time
Intermittent operation
Failure to cease operation at a prescribed time
Loss of output or failure during operation
Degraded output or operational capability
Other unique failure conditions based on system characteristics and operational
requirements or constraints.
The provision of standard lists or inventories of failure modes which can be selected by
the analysts simplifies the decision process and saves significant time during the analysis
process. Some MIL-STD-1388-2B Logistic Support Analysis Record (LSAR) compliant
software products provide access to large databases of failure modes provided by the
Rome Air Defence Centre in the United States. A more detailed list of failure modes is



27
US MIL-STD-1629A, A Procedure For a Failure Mode, Effects, and Criticality Analysis., 101105.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 49 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
provided at Figure 31. More comprehensive lists are available, on certain asset classes,
in the MIMIR library function.
It should be noted that not every failure mode can be corrected or alleviated by a
maintenance action. Close examination may indicate that the cause of failure may flow
from a hardware (design) deficiency or from a personnel (training) deficiency. In these
cases the analysis should provide a consolidated report to the appropriate authority
indicating the deficiency and its future implications.
A database of identified failure modes drawn from the analysis of each application is
included in the attached appendices. This failure data comes from staff experience and
reported failures. Other sources of failure information are:
Manufacturers manuals
Other operators
MIL-HDBK-338-1A (Electro-mechanical)
28

MIL-HDBK-217E (Electronic parts reliability)


29
Care should be taken not to list every possible, or sometimes impossible, failure mode
that may exist. This may result in a great deal of unnecessary analysis activity and the
possible inclusion of low return tasks in the resulting maintenance program. Cost
effectiveness of the process depends on identifying the basic modes of failure.
3.2.7 Failure Causes
Failure causes are derived from the design. They are associated with the detailed design
approach taken, the materials used (including working fluids), the operating environment
including such information as physical loads and corrosive materials.
Knowledge of the failure cause is necessary to identify failure mechanisms and hence
derive an effective preventive maintenance task or default redesign where necessary.
It is not always easy to distinguish between failure modes and failure causes. Failures
may result from the failure of other components thus the cause is external to the item
being examined. It may be useful at times to list failure causes into separate lists as
shown in Figure 30.
Failure Modes Internal Causes External causes
Failure to start - Mechanical binding - Loss of electrical supply
- Human error (excessive
tightening of seal)
Pump flow rate
inadequate
- Mechanical failure
- Wear
- Vibration
- Loss of electrical supply
- Cavitation
- Significant pressure drop
upstream
Figure 30 - Failure causes
These external and internal causes are usually consolidated into a single list.
When the FMEA is being done to support the determination of maintenance requirements
after the design and construction phase, then causes are generally restricted to only
those necessary to support the preventive and corrective maintenance determination.



28
MIL-HDBK-338-1A, Electronic Reliability Design Handbook
29
MIL-HDBK-217E, Electronic parts reliability.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 50 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
Human factors information is also required at this stage to support the allocation of
warning notices in manuals or servicing schedules.
Delayed operation
Erratic operation
Erroneous indication
Erroneous input
Erroneous output
External leakage
Fails closed
Fails open
Fails to close
Fails to open
Fails to start
Fails to stop
Fails to switch
False actuation
Inadvertent operation
Intermittent operation
Internal leakage
Leakage (electrical)
Loss of input
Loss of output
Open circuit
Out of tolerance (high)
Out of tolerance (low)
Physical binding or jamming
Premature operation
Restricted flow
Short circuit
Structural failure
Vibration

Figure 31 - Generic failure modes
3.2.8 Failure Effects
Failure effects are defined as the consequence(s) of a particular failure mode of the
operation, function, or status of an item. In MIL-STD-1629A
30
these effects are classified
as either local-effect, mid-effect or end-effect. This MIL Standard is structured for use
during design and uses allocations of local, mid or end effect to assist in the evaluation of
compensating provisions as described at page 101-107 of the standard. These
compensating provisions cover either design provisions (such as redundancy, alarms or
fail safe operation) or operator actions (subject to human engineering confirmation).
In IEC 60812 these effects are classified as Local Effects and System Effects
31
For RCM analysis the descriptions of the failure effects must be adequately detailed to
allow classification into one of the four categories of consequence:
Hidden/safety/environment,
Evident/safety/environment,
Evident/economic, or
Hidden/economic.
Further details on the selection of criticality are contained in Section 3.3
For application in the rail environment, RailCorp uses the MIMIR software to record the
local effect and the system (end) effect. The definition of these effects for RailCorp is:
3.2.8.1 Local Effect
Local effects concentrate specifically on the impact a failure mode has on the operation
and function of the item in the level under consideration. The local effects are generally
those which can be expected to be seen every time the failure mode occurs.
The consequences of each failure affecting the item shall be described along with any
second-order effects which result. The purpose of definition of local effects is to provide a



30
US MIL-STD-1629A, A Procedure For a Failure Mode, Effects, and Criticality Analysis, p 101107.
31
IEC 60812 (2006) Analysis techniques for system reliability Procedure for failure mode and effects analysis, p33
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 51 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
basis for evaluating compensating provisions and for recommending corrective action. It
is possible for the local effect to be the failure mode itself.
3.2.8.2 System Effect
The system level effects concentrate on the impact an assumed failure has on the
operation and function of the items in the next higher level above the level under
consideration. This shall include the end effects that allow the analyst to evaluate and
define the total effect the failure mode has on the operation, function, or status of the
system.
The end effect described may be the result of a double failure. For example, failure of a
safety device may result in a catastrophic end effect only in the event that both the prime
function goes beyond limit for which the safety device is set and the safety device falls.
Those end effects resulting from a double failure shall be indicated.
3.2.8.3 Impact of operating mode of failure effect.
During the FMEA/ FMECA the analysis team must also consider the operating mode of
the system at the time of the failure, as the resulting failure effect, particularly the system
level can be significant.
Typical operating modes would include Normal, Emergency and Storage.
Example 1. Consider a system of tunnel exhaust fans in an underground rail system.
Under normal operation the fans are operated (generally in summer) to move air through
the tunnels and platform areas when air temperature or CO
2
levels exceed comfort
thresholds. However under emergency conditions such as a train fire in the tunnel, some
fans are required to move fresh air into the tunnel to allow evacuation, and an adjacent
set of fans in the underground rail system are used to exhaust the contaminated air
(smoke and fumes) away from the evacuees and emergency services.
These are two different operating aspects of the same function (to supply/exhaust air
from the tunnel and station). A failure mode can therefore impact upon the two operating
modes, and whilst the local effect may be the same, the system effect will be different in
each operating mode.
Example 2. A batch of high voltage transformers are purchased by an electrical
distributor, one of which will be placed into storage as part of an insurance (emergency)
spares pool. The transformer is filled with insulating oil, and has seals etc, which will
commence to degrade even if the unit is not in service, however the degradation rate will
be considerably slower. The FMECA and subsequent RCM analysis must recognise the
two modes of operation, normal and storage, and maintenance programmes for each
mode must be developed to ensure that the spare transformer is serviceable when
required.
3.2.9 Hidden Failures
Generally when items fail, the loss of function is usually evident to someone, somewhere.
Evidence of failure may by deliberately built into the system design such as sounds or
light indication to an operator or overload shutdown of the equipment. Other more subtle
effects such as vibration, smell, sound or physical manifestations such as the escape of
operating or lubricating fluids may be reliably detectable by the operator.
These types of failures are classified as evident failures as they are detectable by the
operator.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




However, there is another class of failures which may not become evident until combined
with a second functional failure of either the same or another functionally linked item.
These are classified as hidden failures, and are failures which are not evident to the
operator.
3.2.9.1 Types of hidden failures
Hidden failures may be either active or passive in nature.
Passive hidden failures are usually associated with design redundancy where no warning
mechanism has been provided to indicate failure of the passive redundant item. In this
generic type of failure, items are generally passive during the normal operation of the
system and only become active in response to another event which is usually a primary
system failure. This feature is shown in Figure 32.
Active hidden failures are associated with warning systems where failure indication has
been provided but the active warning system is not fail safe and may fail in a manner that
is hidden from the operator.
IN OUT
Primary
Standby
Primary
OUT IN
Switch
Primary Flow
Redundant Flow
Base Flow NO REDUNDANCY
REDUNDANCY
No indication of operation
No indication of failure

Figure 32 - Redundant/non-redundant system
Full functional failure will occur if the primary, having failed, is not restored to an operating
condition before the standby fails.
3.2.10 Analysis Logic Statement
A hidden functional failure is a failure that, when it occurs on its own, will not be evident to
the operator during the normal performance of their duty.
RailCorp Page 52 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




Is the failure occurence
evident to the operator(s)
while performing normal
duties
NO
YES
HIDDEN
FUNCTION
FAILURE
EVIDENT
FUNCTION
FAILURE

Figure 33 - Hidden functional failure selection logic
3.2.11 Protective Systems
The performance of protective equipment and systems has achieved prominence in some
significant industrial accidents. The Chernobyl Nuclear accident, Piper Alpha Platform
explosion and the Bhopal gas release can be traced to the failure of protective equipment
and systems. Protective systems generally provide key functions associated with system
safety (people and the environment) or the prevention of service loss and secondary
damage related to failed equipment.
Typical functions of protective systems are to:
Alert operators to abnormal conditions (functional or conditional failures).
Shut down equipment in the event of failures.
Automatically act to temporarily relieve abnormal conditions and prevent secondary
damage.
Take over completely from a function that has failed.
There are two types of protective systems, monitored and unmonitored. Diagrammatic
examples of the two systems are shown in Figure 34. The maintenance response to
possible failures of each of these systems types is quite different:
Monitored systems provide immediate notice of protective system failure and allow
two possible maintenance responses:
a) Shut down the protected system until the protective elements have been
repaired
b) Undertake a risk assessment to establish a maximum acceptable time for
the system to be non operational and the repair process completed.
Unmonitored systems do not provide notice of failure and require the application of
a failure finding task. Again, risk analysis may be used to determine the necessary
period between the failure finding tasks which achieve an acceptable level of risk
exposure.
RailCorp Page 53 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




PROCESS
PROCESS
Sensor
Sensor
Dolls-eye Indicator Normally Off
Dolls-eye Indicator Normally On
Unmonitored - Failed Sensor not evident
Monitored - Failed Sensor

Figure 34 - Examples of monitored and unmonitored protective systems
3.2.12 Use of Risk Assessment
Risk assessment involves the application of probability theory and reliability engineering
associated with event consequence calculations to determine quantitative values of risk.
The procedures for this are defined in IEC 60300Dependability Managementand AS/NZS
ISO 31000:2009 Risk Management.
In conclusion it must be remembered that in real life the vast majority of hidden functions
relate to protective devices which have random failure characteristics and are not fail
safe. Thus the application of some failure finding task at a frequency determined by risk
analysis is usually mandatory.
3.2.13 Suggested Readings & References
The following are suggested additional readings for this section.
Standard or Reference Name Page Numbers
United States Military Standard MIL-STD-1629A Pp 8-9
Nowlan & Heap, Reliability - centred Maintenance Pp 31-49, 80
United States Military Standard MIL-STD-2173AS Pp 17-21
Moubray, RCMII Reliability-centred Maintenance Pp 37-61
Smith, Reliability Centred Maintenance Pp 78-89, 117-118
RailCorp Page 54 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 55 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
Standard or Reference Name Page Numbers
IEC 60812 Analysis Techniques for System Reliability
Procedure for Failure Mode and Effects Analysis
(FMEA), ed. 2

MSG 3 Report Pp 5
3.3 Criticality Analysis
3.3.1 Introduction
The purpose of criticality analysis in FMECA and RCM is quite different. During design it
is used to assist the designers in identifying failure modes which should or must be
removed, where in RCM it is used to determine the logic process for the analysis.
3.3.2 Criticality During design
The criticality assessment procedures in MIL-STD-1629
32
Pp 102-1 to 102-7.are
designed to rank each potential failure mode identified in the Failure Modes and Effects
Analysis (FMEA) in accordance with its risk of the combined influence of failure severity
and probability of occurrence.
FMECA uses the criticality rating to prioritise potential failure modes in regard to their
criticality (probability of event multiplied by the consequence) and directs design
resources to removal of high criticality (risk) failure modes. The process is used during
initial design to prioritise effort to remove high risk failures by redesign.
During design, criticality analysis may be either qualitative or quantitative. The process is
directed at the early design stage where the risk associated with identified failure modes
are quantified, prioritised and assessed as to the effectiveness of compensating
provisions such as operator or maintenance action. High risk failure modes can then be
cost effectively removed in priority by design changes.
In undertaking the criticality analysis, the analyst shall identify how or even if the operator
is able to detect the failure, the compensating provisions applicable to mitigating the
effect of the failure, the severity of the failure, and the criticality ranking. These factors
are described in more detail below.
Two approaches to criticality ranking are possible, a qualitative approach that assigns
coded descriptors against severity and frequency to establish a criticality matrix (see
Figure 35) and a quantitative approach which calculates the risk associated with each
identified failure mode. The results of the quantitative approach can also be
superimposed on the criticality matrix, which allows the criticality analysis process to be
applied both qualitatively and quantitatively depending upon the level of data available on
each failure mode.



32
MIL-STD-1629, A Procedure For a Failure Mode, Effects, and Criticality Analysis
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




4 3 2 1
A
B
C
D
E
Probability
of
Occurrence
Level
Severity Classification
Increasing
Criticality
Increasing
Increasing

Figure 35 - Typical Criticality matrix
3.3.2.1 Operator detection
The method by which occurrence of the failure mode is detected by the operator shall be
recorded. The operator may be the train driver, train controller, signaller, electrical system
operator or maintainer (on or offsite) depending upon the system and the current
operating mode.
The failure detection means is to be identified. This shall include methods such as visual
or audible warning devices, automatic sensing devices, sensing instrumentation, other
unique indications, or none at all. Where the warning takes the form of a degradation of
condition that is managed by a maintenance intervention / examination type task, the type
of operator indication would be nil.
Other indications
Descriptions of indications which are evident to an operator that a system has
malfunctioned or failed, other than the identified warning devices, shall be recorded.
Proper correlation of a system malfunction or failure may require identification of normal
indications as well as abnormal indications. If the undetected failure allows the system to
remain in a safe state, a second failure situation should be explored to determine whether
or not an indication will be evident to the operator. Indications to the operator should be
described as follows:
Normal. An indication that is evident to an operator when the system or equipment is
operating normally.
Abnormal. An indication that is evident to an operator when the system has
malfunctioned or failed.
Incorrect. An erroneous indication to an operator due to the malfunction or failure of an
indicator (i.e., instruments, sensing devices, visual or audible warning
devices, etc.).
Isolation
Describe the most direct procedure that allows an operator to isolate the malfunction or
failure. An operator will know only the initial symptoms until further specific action is
taken such as a maintainer performing a more detailed built-in-test (BIT). The failure
being considered in the analysis may be of lesser importance or likelihood than another
failure that could produce the same symptoms and this must be considered.
RailCorp Page 56 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 57 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
Fault isolation procedures require a specific action or series of actions by an operator,
followed by a check or cross reference either to monitoring system VDUs, instruments,
control devices, circuit breakers, or combinations thereof. This procedure is followed until
a satisfactory course of action is determined.
3.3.2.2 Compensating provision
An important element of the FMECA is the identification of compensating provisions
which will nullify the effects of a malfunction or failure. Identification of these provisions
enable the true behaviour of an item in its operating context to be determined and could
include:
Design
Compensating provisions which are features of the design at any level that will nullify the
effects of a malfunction or failure, control, or deactivate system items to halt generation or
propagation of failure effects, or activate backup or standby items or systems shall be
described. Design compensating provisions include:
Redundant items that allow continued and safe operation.
Safety or relief devices such as monitoring or alarm provisions which permit
effective operation or limit damage.
Alternative modes of operation such as backup or standby items or systems.
Fail safe designs which may fail in a manner which interrupts service rather than in
a safety critical Manner (see 3.3.4)
Operator action
Compensating provisions which require operator action to circumvent or mitigate the
effect of the failure shall be described. The compensating provision that best satisfies the
indication(s) observed by an operator when the failure occurs shall be determined. This
may require the investigation of an interface system to determine the most correct
operator action(s). The consequences of any probable incorrect action(s) by the operator
in response to an abnormal indication should be considered and the effects recorded.
Maintenance
Compensating provisions which require maintenance action to manage the postulated
failure relate to those failure modes which can be successfully managed by maintenance
tasks such as lube/service, condition monitoring/assessment, scheduled restoration /
discard, or failure finding (ie operational check) type actions. If this compensating
provision is selected the task and associated task effectiveness and task interval shall be
supported with an RCM analysis.
Commissioning test
Compensating provisions which require commissioning tests as a compensating
provision are aligned to those failure modes, which once verified cannot change until
such time as the equipment is replaced / recommissioned. Tests of this nature are
typically polarity tests for power supplies and DC magnetically held high current high
speed circuit breakers.
3.3.2.3 Severity Class
A severity classification category shall be assigned to each failure mode according to the
failure effects. The effect on the functional condition of the item under analysis caused by
the loss or degradation of output shall be identified so the failure mode effect will be
properly categorised.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 58 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
Where effects on higher levels are unknown, a failures effect on the level under analysis
shall be described by the severity classification categories.
Severity classifications are assigned to provide a qualitative measure of the worst
potential con-sequences resulting from design error or item failure. A severity
classification shall be assigned to each identified failure mode in each item analysed in
accordance with the loss statements below.
Where it may not be possible to identify an item or failure mode according to the loss
statements in the four categories below, similar loss statements based upon loss of
system inputs or outputs shall be developed and included in the FMECA ground rules for
procuring activity approval.
Severity classification categories for application in the NSW rail environment are defined
as follows:
Category 1 - Catastrophic - A failure which may cause death and/or multiple
severe injury, or extensive interruption of train services.
Category 2 - Critical - A failure which may cause severe injury, major property
damage, major system damage or which will result in interruption to train services
greater than 15 minutes (i.e. SRA mission loss).
Category 3 - Marginal - A failure which may cause minor injury, minor property
damage, minor system damage or which will result in minor train delays (3-15
minutes) delay or loss of availability.
Category 4 - Minor - A failure not serious enough to cause injury, property
damage, system damage or train delays, but which will result in unscheduled
maintenance or repair.
The failure effect severity shall also be qualitatively classified against the four categories
of Evident (i.e. not Hidden mode failure), Safety, Environmental and Operational. See
Section 3.3.3
3.3.2.4 Criticality Analysis
The criticality analysis within the design FMECA process is intended to provide a
methodology whereby all failure modes are ranked with the aim of determining the
relativity of various failure modes, and subsequently identifying potential candidate failure
modes for redesign. The ranking is achieved by determining the relative probability of
each failure mode using either a qualitative or a quantitative basis.
The failure modes criticalities are calculated for each failure mode, and then summed to
provide a part criticality which is used for the final sorting. As a check that the failure
modes for each part identified in the FMEA have been considered by the analysis team,
each failure mode is allocated a relative weighting within the part. This weighting - the
failure mode Ratio (), is allocated by the analysis team to each failure mode and the
sum of these within each part should add up to 1.0. A check is automatically provided for
each part on the MIMIR data entry table, and the sum is highlighted yellow when it is not
equal to 1.0
Qualitative Criticality Analysis
Failure modes identified in the FMEA are assessed in terms of probability of occurrence
when specific parts configuration or failure rate data are not available. Individual failure
mode probabilities of occurrence should be grouped into distinct, logically defined levels,
which establish qualitative failure probability level for entry into the MIMIR Probability
field.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 59 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
Probability Of
Occurrence
Definition
A) Frequent A highly probability of occurrence during the item operating time
interval. High probability may be defined as a single failure mode
probability greater than 0.20 of the overall probability of failure
during the item operating time interval.
B) Reasonably
Probable
A moderate probability of occurrence during the item operating
time interval. Probable may be defined as a single failure mode
probability of occurrence which is more than 0.1 but less than
0.20 of the overall probability of failure during the item operating
time. In MIMIR a Reasonably Probable level is assigned a value
of 0.15 for ranking purposes.
C) Occasional An occasional probability occurrence during item operating time
interval. Occasional probability may be defined as a single failure
mode probability of occurrence which is more than 0.01 but less
than 0.10 of the overall probability of failure during the item
operating time. In MIMIR a Occasional level is assigned a value
of 0.05 for ranking purposes.
D) Remote An unlikely probability of occurrence during item operating time
interval. Remote probability may be defined as a single failure
mode probability of occurrence which is more than 0.001 but less
than 0.01 of the overall probability of failure during the item
operating time. In MIMIR a Remote level is assigned a value of
0.005 for ranking purposes.
E) Extremely
Unlikely
An extremely unlikely probability of occurrence during item
operating time interval. Extremely Unlikely probability may be
defined as a single failure mode probability of occurrence which
is more than 0.0005 but less than 0.001 of the overall probability
of failure during the item operating time. In MIMIR an Extremely
Unlikely level is assigned a value of 0.00075 for ranking
purposes.
F) Rare A failure whose probability of occurrence is essentially zero
during item operating time interval. Rare probability may be
defined as a single failure mode probability of occurrence which
is less than 0.0005 of the overall probability of failure during the
item operating time. In MIMIR an Extremely Remote level is
assigned a value of 0.0005 for ranking purposes.

Quantitative Criticality Analysis Calculation
The quantitative criticality analysis is formed by calculating the individual failure mode
criticality C
m
= t (See below for definitions). The failure criticality of the higher level
part is then calculated from the sum of its failure mode criticalities (C
m
).
A FMECA criticality report can then be produced, which reports the part criticalities in
descending order within each of the four criticality groups, evident, Safety, Environmental
and Operational. This report assists the design team in identifying parts with the
system/equipment which have unacceptable criticalities and which are logical candidate
items for redesign.
Failure Mode Ratio -
The fraction of the part failure rate (
p
) related to the particular failure mode under
consideration shall be evaluated by the analysis team and recorded. The failure mode
ratio is the probability expressed as a decimal fraction that the part or item will fail in the
identified mode. If all potential failure modes of a particular part or item are listed, the sum
of the values for that part or item will equal one. If detailed failure mode data is not
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 60 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
available, the values shall represent the analysts judgement based upon all analysis of
the items functions.
Part Failure rates -
The failure rates are included in the quantitative analysis method. The analysis team
identifies the Conditional Failure Rate and the Functional Failure Rate. The rates are
identified in terms of failures per year and are summed into a Design Failure Rate.
Where the data is available as gross failure rate value, the analysis team shall apportion
the rates between the conditional and functional failure rates. These apportioned rates
shall then form the basis against which the actual failure rate performance can be
monitored and compared when the system becomes operational.
Operating Time - t
This is the operating time in years over which the criticality ranking is to be performed.
Generally this would be over one year.
Failure effect probability -
The values are the conditional probability that the failures System Effect will result in
the criticality classification with the identified severity once the failure mode has occurred.
The values should reflect the analysis teams judgement where actual data is not
available, and be quantified according to the following:
Failure Effect value
Actual loss 1.00
Probable loss >0.1~to <1.00
Possible loss >0 to 0.10
No effect 0

Sample Failure Mode Criticality Calculation
Quantitative Method
Failure Mode 1 : =0.1, =0.25 ,
p
=.25 failures per year, t =1 year
C
m1
=0.00625
Failure Mode 2 : =0.9, =0.1 ,
p
=.25 failures per year, t =1 year
C
m2
=0.0225
C
part
=C
m1
+C
m2
=0.02875
Qualitative Method
This could also have been estimated qualitatively by selecting the Remote probability for
the first failure mode, and the Occasional probability for the second failure mode, which
would have resulting in a similar ranking of overall part criticality.
3.3.3 During Maintenance Analysis
RCM analysis uses criticality to determine the analysis logic through a broad division of
possible failure effects (adverse outcomes) into two by two matrix of combining failure
visibility (hidden and evident) and failure effect (safety/environment and economic).
Figure 36 describes the four resulting categories.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




HIDDEN EVIDENT
SAFETY/
ENVIRONMENT
ECONOMIC
1
2
3
4

HIDDEN / SAFETY/ENVIRONMENT
HIDDEN / ECONOMIC
(EVIDENT) SAFETY/ENVIRONMENT
(EVIDENT) ECONOMIC
Figure 36 - Four criticality groupings
Effects such as service or operations have been used to give priority to unquantifiable
economic loss flowing from in-service failures. This is generally not supported as it
avoids the issue of properly accounting for failure effects. The baseline comparison of all
non statutory (other than safety and environment) outcomes is encouraged to support a
business approach using economic cost as a comparison.
RCM analysis applies a logic flow using only broad divisions of criticality. These criticality
assessments then direct the analyst into a particular logic process as described in
Section 4.1. The logic process for selecting failure mode criticality is shown in Figure 37.
I s the functional
failure
evident to the
operator
NO
Y ES
Does the functional failure have an
adverse effect on customer
service or production or
Y ES
NO
Does the functional failure cause
loss of function that will
adversly effect safety or
breach environmental laws
Y ES
NO
ECONOMIC
SAFETY OR
ENVIRONMENT
HIDDEN
CRITICALITY
cause secondary damage
Does the functional failure and the
loss of its protected function
adversly effect safety or
breach environmental laws
loss of its protected function
adversely effect
customer service or production or
cause secondary damage
NON CRITICAL
NO
Y ES
Y ES
NO
Does the functional failure and the
h

Figure 37 - Criticality analysis logic diagram
RailCorp Page 61 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




3.3.4 RCM analysis
Criticality assessment in RCM analysis is conducted to determine which particular
analysis logic path is to be applied in the determination of applicable and effective
preventive maintenance tasks or default actions. The allocation of failures to a criticality
category is based on the effects or outcomes (local, mid, end) derived during the FMEA.
These outcomes are divided into the three basic groups described in Section 3.2 each of
which are subject to a defined task analysis logic.
3.3.4.1 Hidden
A hidden function is one whose failure will not become evident to the operating crew
under normal circumstances if it occurs on its own. An example of this is shown by a
failure of pump B in the redundant pump configuration in Figure 38. A failure of pump A
in the stand alone configuration is classed as evident as someone will find out about it if it
occurs on its own. However, a failure of the stand-by pump B in the redundant
configuration can go unnoticed under normal circumstances. This failure will have no
direct impact on its own. Thus, failure of pump B will not become evident to the operating
crew unless some other failure also occurs such as the failure of pump A, or someone
makes a point of checking periodically whether pump B is still in working order.
A
B
A
Configuration 1 - Stand Alone
Configuration 2 - Redundant Standby

Figure 38 - Operating configurations
Hidden failures can be separated from evident failures by asking "will the loss of function
caused by this failure mode become evident to the operating crew or staff under normal
circumstances?"
If the answer to this question is no, the failure mode is hidden, and if the answer is yes, it
is evident.
RailCorp Page 62 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 63 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
In general the vast majority of hidden functions are protective equipment that are not fail-
safe (See Section 3.2.9). The function of this equipment is to ensure that the
consequences of the failure of the protected function is significantly less than if there
were no protection. So any protective device is in fact part of a system with at least two
components:
the protective equipment
the protected function.
3.3.4.1.1 Fail-safe protective equipment
In this context fail-safe means that the failure of the device on its own will become evident
to the operating crew under normal circumstances. This is because fail-safe units usually
stop the system from operating if there is a failure. Railway signalling is an example of a
fail safe system where the system signals the driver with a red stop in the event of a
critical failure. Another is a HV circuit breaker trip circuit supervision system which raises
an alarm signal to the electrical system operator in the event of a critical failure of the
circuit breakers trip circuit.
Fail safe systems in power stations use parallel sensors whose output is constantly
monitored by a software comparator in the receiving circuit board which sends a warning
to the operator if there is a variation between the signals.
3.3.4.1.2 Protective equipment which are not fail-safe
In a system which contains a protective device which is not fail-safe, the fact that the
device is unable to fulfil its intended function will not be evident to the operator under
normal circumstances.
There are considered to be two categories of hidden functions which are not fail-safe:
The protective system is a standby to a primary function and gives no indication
that it is in a failed state (Passive hidden function).
The protective system is required to measure and assess (continually active)
whether a particular event has occurred and act in some manner to protect the
system but is in a failed state with no indication (Active hidden function).
3.3.4.2 Safety/Environment
Safety and environmental requirements are statutory (i.e. covered by Acts of Parliament
and associated government regulations). This category of failures is defined as that
where a failure mode has:
Safety consequences if it causes a loss of function or other damage which could
injure or kill someone.
Environmental consequences if it causes a loss of function or other damage which
could lead to the breach of any known environmental standard or regulation.
3.3.4.3 Economic
The consequences of an evident failure which has no direct adverse effect on safety or
the environment are classified as economic as all outcomes can be costed in some
manner.
Economic consequences comprise all failure consequences that incur a financial loss that
is probabilistic in nature. This loss may be direct cost against the balance sheet or
indirect in terms of image loss or customer perception that will require financial
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 64 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
expenditure to recover. Some possible economic consequences flowing from a possible
failure mode are listed at Figure 39.
Event Probability Consequence
Repair 1 Average cost of repairs
Secondary damage Variable Average cost of repairs
Service loss Variable Value of foregone revenue either
immediate due cancelled travel or
customer loss
Image loss Variable Cost of advertising necessary to repair
an established image
Fines Variable Direct penalties for statutory breaches
plus cost of defence plus possible loss of
image costs
Compensation Variable Direct penalties plus possible loss of
image costs
Insurance premiums Variable Increased cost of premiums associated
with insured element of loss
Figure 39 - Failure mode economic consequences
For failure modes with economic consequences:
a preventive task is worth doing (effective) if over a period of time, it costs less than the
cost of the consequences of the failures which it is meant to prevent.
Assessing the effectiveness of a task is achieved by summing the probabilistic economic
cost of failures and comparing the result to the cost of preventive maintenance.
If a repetitive preventive task is not worth doing, then in rare cases a modification may be
justified as a single one-off cost.
3.3.5 Suggested Readings & References
The following are suggested additional readings for this section.
Standard or Reference Name Page Numbers
United States Military Standard
MIL-STD-1629A
Pp 102-1 to 102-7
Nowlan & Heap Reliability - Centred Maintenance Pp 25-31
United States Military Standard
MIL-STD-2173AS
Pp 21-22
Moubray, RCMII, Reliability-Centred Maintenance Pp 66-105
Smith, Reliability Centred Maintenance Pp 89-93
IEC 60812 Analysis Techniques for System Reliability
Procedure for Failure Mode and Effects Analysis
(FMEA), ed. 2

MSG 3 Report Pp 8-9

4 RCM Analysis
4.1 Task Analysis
Every failure has an impact on an organisations ability to service its internal and external
customers. Some failures are directly related to product via their effect on output and
quality, others relate to externals such as adverse public safety and environmental
effects. Some failures have no immediate effect but lower system reliability established
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 65 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0

by the designer via the use of redundancy provisions or monitoring functions associated
with human intervention.
Preventive maintenance tasks are identified and established to reduce the adverse
impacts of failures which consume resources to correct failures which often result in loss
of revenue from reduced product or service supply and may result in significant losses
through personal injury and secondary damage. The effort organisations will apply to
prevent failures is usually a function of the consequence of failures; high impact failures
will generate considerable effort to prevent, while low consequence failures may result in
a purely reactive effort.
Having identified the failure modes relevant to the equipment in its operating
environment, the task analyst must identify two quite different sets of maintenance tasks
depending on the stage in the equipment's lifecycle. For new acquisition projects (i.e.
analysis undertaken during the design phase) the analyst must identify all maintenance
tasks identified as a consequence of failures. This will include both corrective and
preventive tasks, a list of which provides the technical manuals writer with the raw
material for the engineering publications which support the equipment.
4.1.1 Task Objectives
Failure prevention is not so much about preventing the failures themselves but avoiding
or reducing the consequences i.e. risk reduction where:
Risk =Probability of Failure x Consequence of Failure
"Failure prevention has much more to do with avoiding or reducing the
consequences of failure than it has to do with preventing the failures
themselves."
33
Thus preventive action must be directed at reducing both the probability of the failure and
the consequence of the failure.
"A preventive task is worth doing if it deals successfully with the consequences of
the failure which it is meant to prevent"
34
4.1.2 Task Options
The task types applied through RCM fall into four outcome categories:
Life extending tasks where the item is serviced or lubricated to achieve it's inherent
design life
Failure preventing tasks where the item is either repaired in situ or removed from
service prior to functional failure to prevent the consequences of such a failure.
Failure finding tasks which identify hidden failures to reduce the risk of double failure to
acceptable levels.
Default tasks that determine necessary action if the consequences of failures cannot be
managed by maintenance alone.



33
Moubray, J ohn, Reliability-centred Maintenance, Butterworth Heinemann, 1992
34
Moubray, 1992, Op Cit.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 66 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
Thus life extending tasks ensure that the inherent design life of the equipment is achieved
by ensuring design requirements, commensurate with the operating environment, are
complied with. Life extending tasks do not however manage the consequences of failure
and must be associated with a failure management task to reduce the failure risk.
Failure preventing and finding tasks manage the risk of failure by reducing the failure
probability to an acceptable level commensurate with the inherent design characteristics
of the equipment.
Default tasks such as redesign manage the problem of no effective maintenance to
manage the failure mode.
The preventive maintenance task options available to the analyst are:
Lubrication/Service task that includes lubrication (generally a design requirement) or
consumables replenishment as with fuel and oil.
Condition monitoring task which detects conditional (potential) failures before they lead
to functional failure and allow the equipment to be either repaired in situ or replaced and
a restoration process conducted at a separate facility. Note that calibration tasks are
considered to be condition monitoring tasks.
Scheduled restoration or rework which at some hard time conducts a standard
schedule of maintenance tasks on an item of equipment.
Scheduled discard which at some hard time removes an item from the system and
discards either the item or some element of it such as an electrolytic capacitor.
Combination task which may combine a number of the above task types which
individually may not be effective against the identified failure mode.
Failure finding task which is only applicable to hidden functional failures where a
confidence check that the system is still operational is required at some interval to reduce
the probability of double failures.
Default Task which provides for situations where an effective preventive maintenance
task cannot be identified.
An additional maintenance activity which is not specifically determined by the RCM
analysis logic is the zonal examination. This examination consists of a general look at
an area without necessarily a specific examine task and is a confidence building task
undertaken on items which:
Are subject to very slow inherent rates of degradation that may lead to significant
consequences if left unattended indefinitely.
May go lengthy periods without a site visit and which are exposed to random
external activity such as vandalism or environmental damage.
4.1.3 Task Applicability
The RCM analysis logic diagrams shown at Figure 41 to Figure 46 (with an overview
shown in Figure 48) steps the analyst through the process of selecting tasks which are
applicable (technically feasible) and effective (worth doing). This means that the task
must address the failure mode by reducing its probability of occurrence and must reduce
that probability to an acceptable level commensurate with the cost of the task.
The process of selecting tasks which are applicable firstly identifies a listing of possible
tasks. These tasks represent various maintenance strategies as follows:
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 67 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
Service/Lubrication. Service tasks replenish material consumed during the normal
operation of the equipment; examples of this include grease in trackside lubricators,
greasing linkages, oil change/replacement, and water and detergent in windscreen
washers. In addition, lubrication tasks which renew degraded or removed lubricant
material are usually the mandatory requirement of a design and must be included in the
program. Refer to Section 4.1.3.1.
On Condition. These tasks prevent potential failures before they can cause a functional
failure. The tasks include examinations for indications of conditional degradation
commensurate with an unacceptable increase in failure probability. There are four
criteria for on condition task applicability:
a) It must be possible to detect the reduced resistance to failure for a particular
engineering failure mode.
b) It must be possible to define a potential failure condition that can be detected by
an explicit task.
c) There must be a reasonably consistent time interval between the potential to
identify the (conditional) failure and the functional failure.
d) Near original reliability performance is restored.
Hard Time Rework or Discard. These are tasks which schedule either a rework
(overhaul) task or a throw away (discard) task at a fixed period or number of events
because their function is considered so critical that no failures can be acceptable. An
example of a hard time throw away task is the discard of the front fan of a High Ratio By-
pass gas Turbine Engine which has a known fatigue life with a high consequence
outcome.
The applicability criteria are:
a) The item must be capable of achieving an acceptable level of restored failure
resistance through a rework task.
b) The item must exhibit wear-out characteristics which are identified by a rapid
increase in the conditional probability of failure such that a wear out age for
reworks or a safe life limit for discard can be established.
c) A large percentage of the items must survive to the wear out age or life limit.
Failure Finding. The task must be applicable to the hidden failure and would usually
follow the form of an operational or functional check (see definitions) task to determine
the current status of the equipment.
A list of these task options, their task outcome category, the selection sequencing and
relationships is shown at Figure 41. Depending on the RCM criticality assigned to the
failure mode, a selection of possible tasks in order of cost is presented for assessment as
to their applicability and effectiveness.
Tasks to be selected must be both applicable to the failure cause and effective in
managing the failure risk. Should there be no effective failure management mechanism
then the default task shall apply.
Once an applicable and effective task has been identified then the analyst stops as any
further task will increase costs dramatically for little additional reduction in failure risk.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 68 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0

4.1.3.1 Service / Lubrication Task Application Using MIMIR
In MIMIR, service/lubrication tasks are determined as part of the task selection process
directed at specific failure modes.
Nowlan and Heap
35
proposes that:
lubrication for example, really constitutes scheduled discard of a single celled item
(the old lubrication film). This task is applicable because the film does deteriorate
with operating age and shows wearout characteristics.
and
the servicing tasks (e.g. Checking fluid levels in oil or hydraulic systems) are on-
condition tasks. In this case, potential failures are represented by pressure or fluid
levels below the replenishment level, and this condition is corrected in each unit as
necessary.
Using this concept, lubrication and servicing tasks are identified as Consequence
Preventing (Refer to Figure 41) when applying the task selection processes shown in
Section 4.1.8.
Thus the selection of an applicable and effective lubrication task in MIMIR constitutes the
scheduled discard of the old lubrication film.
Similarly the selection of an applicable and effective servicing task in MIMIR constitutes
the examination for indications of conditional degradation of the oil (e.g. Condition
monitoring of the oil level / level of contamination).



35
Nowlan and Heap, Reliability Centered Maintenance, US Department of Commerce, National Technical Information Service,
December 1978, p 72, sec. 3.6.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 69 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0

System under analysis: ACCB System under analysis: Air Compressor
Subsystem (Part of ACCB)
Part Description #1 Air Compressor Part Description #1 Oil
Failure Description
#A
Seizes Failure Description #A Degrades
Failure Cause #1 Oil degradation Failure Cause #1 Operational use
Proposed task Replace oil
every 2 years.
Proposed task Replace oil every 2
years.
Failure Description #B Leaks
Failure Cause #2 Oil leakage from
life expired
seals
Failure Cause #1 Oil seals life expired
Proposed task Examine seals
and check oil
level
Proposed task Examine seals and
check oil level
Failure Description #C Depleted
Failure Cause #3 Normal oil
operational
consumption
Failure Cause #1 Normal oil
operational
consumption
Proposed task Check oil level Proposed task Check oil level
Failure Cause #4 Oil
contaminated
from operational
use
Failure Cause #2 System leaks
Proposed task Replace oil after
1000 operations
Proposed task Examine for leaks
and check oil level
Failure Description #D Contaminated
Failure Cause #1 Normal operational
use
Proposed task Replace oil after
1000 operations
Figure 40 - Examples
Figure 40 shows the same equipment, the Air Compressor, being analysed in two ways.
Under the System: ACCB analysis, the air compressor is analysed as a part, which if it
fails, would impact on the function of the system and have some failure consequences.
The compressor would be a configuration item for the ACCB. At this level, the oil is not
considered as a configuration item.
Under the System: Air Compressor System analysis, the air compressor is analysed as
a system and the oil is analysed as a part. The oil is considered as a configuration
item for the compressor as it forms an integral part of the design of the system.
The oil, if it fails, would impact on the function of the system and have some failure
consequences.
In both cases, the identification and structure of the failure mode (identifying the root
cause) provided a task for each specific failure mode.
4.1.4 Task Effectiveness
The task effectiveness criteria is applied on the basis of the required outcomes of the task
which flow directly from the failure consequences. These effectiveness criteria relate
directly to consequence and are as follows:
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 70 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
Hidden Function. Preventive maintenance tasks are worth doing if they reduce the risk
of double failures to an acceptable level.
Safety and Environment. Preventive tasks are worth doing if they reduce the risk of
failure to an acceptable level.
Economics. Preventive tasks are worth doing if the cost of doing the tasks is less than
the cost of not doing the tasks, i.e the cost of operational failures and/or the cost of
repairing the items after failure.
4.1.5 Non Programmed Tasks
Assets that are exposed to the public in generally insecure situations can suffer from
various degrees of damage due to either vandalism or accidents. Those actions that
result in the immediate loss of a function that is operator monitored have no effective
preventive maintenance tasks and would not be included in the maintenance program.
However, some forms of damage can either inflict hidden function failure or significantly
reduce resistance to failure.
Exposures to random failure from reduced failure resistance through vandalism or
accident must be managed by inclusion in the appropriate condition monitoring or failure
finding program even though not strictly an RCM logic task. These tasks are often
included within the zonal examination programs as they are random in nature and
cannot usually be clearly defined by a specific task in the servicing schedule.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




Task Options
Is a lubrication or
service task applic-
able and effective
Is a condition
monitoring task
applicable and
effective
Is a scheduled
restoration task
applicable and
effective
Is a scheduled
discard task
applicable and
effective
Yes
Include Task
Include Task
Yes
No
No
Redesign is
mandatory
No
Yes
Yes
Include Task
Include Task
Is a failure
finding task
applicable and
effective
No
Yes
Include Task
No
Is a combination
of the above tasks
applicable and
effective
Yes
Include Tasks
No
Life Extending
Consequence Preventing
Failure Finding
Default
Hard Time Tasks

Figure 41 - Task Options
RailCorp Page 71 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 72 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
4.1.6 Task Logic Charts
The basic logic diagram for conducting maintenance requirements analysis is provided at
Figure 14. The task analysis logic diagrams appropriate for each of the four criticality
categories, as represented by the shaded area in Figure 14, step the analyst through a
question and answer process to determine which of a set of possible maintenance
activities are applicable and effective for the equipment and its associated failure
mechanism.
For each identified consequence criticality there is a separate logic process for selecting
the appropriate preventive maintenance tasks. These lower order logic processes
following on from the selection of RCM criticality are shown in Figure 43 to Figure 46.
Analysts should note that the general practice is that once an effective task is found the
analysis process is discontinued. This is logical as to pursue the remaining few percent
of remaining unreliability with increasingly expensive maintenance processes would not
possibly be cost effective.
4.1.7 Default Actions and Tasks
Default strategies are necessary both during and at the end of the analysis logic. In new
systems where information is scarce decisions are required under conditions of
uncertainty. A decision default strategy allows decisions to be made under such
conditions.
4.1.8 Default Decision Strategy
The default decision strategy is listed at Figure 42.
Default decision Default
answer
Possible adverse
outcomes
Outcome eliminated
with age exploration
Is item clearly non-
significant?
No Unnecessary analysis No
Is the failure operator
monitored?
No Unnecessary
maintenance task
Yes
Does failure have
safety impacts
Yes Unnecessary redesign
or maintenance
No (redesign)
Yes (maintenance)
Will condition
monitoring task
detect potential
failures?
Yes Maintenance not cost
effective
Yes
Is condition
monitoring task
effective?
Yes Maintenance not cost
effective
Yes
Is hardtime task
applicable?
No Delayed opportunity to
save costs
Yes
Is hardtime task
effective?
No Delayed opportunity to
save costs
Yes
Figure 42 - Default decision strategy checklist
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM





Figure 43 - Hidden function task analysis
RailCorp Page 73 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM





Figure 44 - Safety and environmental task analysis
RailCorp Page 74 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM





Figure 45 - Hidden economic task analysis
RailCorp Page 75 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM





Figure 46 - Economic task analysis
RailCorp Page 76 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




4.1.9 Default Tasks
As previously stated, depending on the consequences of failure, if a suitable (applicable
and effective) preventive maintenance task cannot be found then some default action
must be applied. The default tasks that have been defined for the four logic processes
associated with each assessed system or item criticality type, are shown in Figure 43 to
Figure 46.
The application of default tasks usually means some form of redesign. This could take a
variety of forms from modifying the equipment to provide increased redundancy to
providing additional alert devices for the operators. These options are detailed in
Smith
36
, pages 147 to 154.
Yes
ECONOMIC
SAFETY AND
ENVIRONMENT
HIDDEN
FUNCTION
Maintenance actions
reduce the probability of a
multiple failure to an
acceptable level
Maintenance actions cost
frombetter operations
No
Redesign may
be DESIRABLE
Could the double failure
adversely effect Safety
or the Environment?
No
Maintenance actions
reduce the probability of a
double failure to an
acceptable level
Redesign is
MANDATORY
Yes
No scheduled
maintenance
Redesign may
be DESIRABLE
No
more than the savings
&/or reduced repairs
Redesign is
MANDATORY

Figure 47 - Default logic chart
4.1.10 Documentation of Task Decisions
The collective decision process which is undertaken in developing task lists may involve
keen discussion on the part of the analysts. Care should be taken to document the
results of these discussions in a manner that will enable later audits, reviewers or just
seekers of information to clearly see why the decision shown on the analysis form was
reached.
For future staff attempting to improve the maintenance process, nothing could be worse
than cryptic, unsupported decisions regarding task selection or frequency. They will
probably need to start the analysis process again losing the value of many hours of hard
work by the original analysis team in data collection and argument.



36
Smith, Relability Centred Maintenance, McGraw-Hill, 1991
RailCorp Page 77 of 114
Issued J uly 2010 UNCONTROLLED WHEN PRINTED Version 5.0
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual AM 9995 PM




RailCorp Page 78 of 114
Issued J uly 2010 5.0 UNCONTROLLED WHEN PRINTED Version
4.1.11 Summary
Figure 48 provides a summary of the relationship between:
Failure consequences (RCM Criticality)
Task types
Effectiveness criteria
Applicability criteria
The diagram is meant to provide a single reference document to assist analysts in the
determination of applicability and effectiveness rules for tasks.
4.1.12 Suggested Readings & References
The following are suggested additional readings for this section.
Standard or Reference Name Page Numbers
Nowlan & Heap Reliability-Centred Maintenance Pp 50-99
United States Military Standard MIL-STD-2173AS Pp 21-33
Moubray, RCMII Reliability-Centred Maintenance Pp 157-169
Smith, Reliability-Centred Maintenance Pp 89-104 and 147-154
MSG 3 Report Pp 10-19

ering Manual Integrated Support
quirements Analysis Manual AM 9995 PM




RailCorp Page 79 of 114
Issued J uly 2010 Version 5.0 UNCONTROLLED WHEN PRINTED
On Condition
FAILURE
CONSEQUENCE
SAFETY ECONOMICS
NON SAFETY
HIDDEN FAILURE
SAFETY HIDDEN
FAILURE
EFFECTIVENESS CRITERIA
APPLICABILITY CRITERIA
Servicing -
Lubrication
The replenishment of consumables or lubricants must be due to normal operations
1. Must be possible to detect reduced failure resistance
2. Must have a definable, detectable potential failure condition
3. Must have a consistent age from potential failure to functional failure
Hardtime Must have an age
below which no
failures occur
Must be possible
to restore to
acceptable level
of reliability
ALL TASKS
Reduces risk of
Failure to
Acceptable level
Must reduce risk of
multiple failure to
acceptable level
Cost of maintenance should be less than
cost of operating loss and or repair

Must have age
below which no
failure occur
Must be possible
to restore to
acceptable level
of reliability
No other task is applicable and effective
Figure 48 - Task applicability and effectiveness summary (Based on US MIL-STD-2173AS)
Must have age where conditional probability
of failure shows rapid increase
A large percentage of items must survive to
this age
Rework must be able to restore to an
acceptable level of failure resistance
Failure Finding

RailCorp Engine
Maintenance Re
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




4.2 Frequency Determination
4.2.1 Introduction
The selection of task frequency has a significant impact on the both the cost and
effectiveness of the defined preventive maintenance program. If tasks are too infrequent
then system reliability will suffer; if tasks are too frequent then the program cost will
become prohibitive.
Additionally, tasks which are too infrequent also drive up the cost of maintenance by
increasing the level of often high cost unplanned corrective maintenance. Conversely,
tasks which are too frequent can reduce reliability by increasing the level of infant
mortality associated with hard time activity.
It should be noted that for new equipment little data is generally available and
conservative estimates backed by an aggressive age exploration program are usually
necessary. Task frequencies can be established from similar operating equipment using
analysts experience regarding the impact of design and operating variations.
The rationale and procedures for estimating the frequency for each task category are
defined in the following paragraphs.
4.2.2 On Condition Examinations
Determining the interval for on-condition examinations is based on establishing a high
event probability P
e
(P
e
> 0.995) of identifying the potential failure condition. The
individual event success probability in a checklist examination varies between a
probability of 0.9 to 0.95. Thus, selection of a time period to achieve a required
probability of fault detection will generally be based on a minimum of two independent
examinations whose combined probability value lie between 0.99 (individual event
probability of 0.9) and 0.9975 (individual event probability of 0.95). This is shown in
Figure 49.
TO FAILURE
RESISTANCE
VISIBLE EVIDENCE of FAILURE
CONDITIONAL
FAILURE
FUNCTIONAL
FAILURE T
OPERATING AGE
T T
0%
100%
Where T = Time between Conditional
and actual Functional Failure
T = Time between successive examinations
CF Interval

Figure 49 - Task period selection
The key to effective condition monitoring lies with the accuracy and consistency of the CF
interval as estimated by the analyst. Increasingly accurate CF interval data generally
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
becomes available as the condition monitoring program collects field data and assesses
the validity of the original CF value.
The task description in the analysis must identify the condition monitoring technique (for a
list of possible techniques see Moubray, RCMII
37
Appendix 1 pages 274-301) and the
specific limits or values to be applied. The origins of the rejection criteria must be
identified and should be supported by quantitative data from either the same or similar
equipment.
Note that the conditional (or potential) failure criteria should be established to provide
sufficient time for a planned corrective task to be implemented. If the conditional failure
parameter results in immediate (i.e. a functional failure usually identified by the
exceedance of a required performance standard) in an operating environment then the on
condition task is by itself not applicable.
Consideration must be given to the task success probability when selecting task
frequencies for condition monitoring. That is, given the form of the task, what is the
expected probability that the human operator/maintainer will successfully complete the
task. Statistics on success probabilities for interpretative tasks are used from two
sources:
MIL-STD-2173AS 38
Villemeur, Reliability, Availability, Maintainability and Safety Assessment, J ohn
Wiley and Sons 1992.39
MIL-STD-2173AS describes the assessment of on-condition intervals at page 55 para 5c.
In brief, the CF interval (time between conditional and functional failures) divisor values
will result in the following number of condition monitor tasks in the CF interval:
FAILURE CRITICALITY No OF TASKS TASK FREQUENCY
Safety/Environment critical 3 Divide CF by 3
Hidden Safety Environ- critical 3 Divide CF by 3
Service critical 2 Divide CF by 2
Economic critical 1 Divide CF by 1
Hidden -Economic critical 1 Divide CF by 1
Figure 50 - Condition monitoring task frequency selection
In the assessment of frequencies for task types, consideration should be given to the type
of task and its success probability. Villemeur
40
gives probabilities for operators detecting
abnormal conditions depending on whether the task is general or check listed. The
probabilities for these two types of tasks are:
TASK TYPE RELIABILITY
General or Zonal task 0.5 (estimated)
Specific or Checklist task 0.9 to 0.95
Figure 51 - Task reliability
Thus, where an equipment condition examination has a low probability of success then
multiple applications of the task will be necessary to achieve an acceptable level of



37
Moubray, J ohn, Reliability-Centred Maintenance, Butterworth Heinemann, 1992, Appendix 1 p 274-301.
38
MIL-STD-2173AS, p 55, para 5c
39
Villemeur, Reliability, Availability, Maintainability and Safety Assessment, J ohn Wiley and Sons 1992.
40
Villemeur, Reliability, Availability, Maintainability and Safety Assessment, J ohn Wiley and Sons 1992, p430
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
detection probability. The probability equations for determining failure detection reliability
(Pt) for multiple attempts of the same probability of detection:
Pt = P1 + P2 - (P1 x P2) for two tests
=2P-P2 if (P =P1 =P2)
Pt =3(P-P2) +P3 for three tests
where P is the individual attempt success probability
and Pt is probability for the number of attempts made
Figure 52 - Determination of multiple task success probability
Thus:
Attempt Reliability 1 Attempt 2 Attempts 3 Attempts
0.5 0.5 0.75 0.875
0.9 0.9 0.99 0.999
0.95 0.95 0.9975 0.999875
Figure 53 - Multiple task success probability
The failure finding probabilities at Figure 53 support the concept of applying a low cost
general zonal examination of relatively low success probability that can be used to cover
long term degradation type failure modes, which have a high but variable CF value. This
strategy can be cost effective when combined with a specific maintenance task of any
type in the zone to be examined.
The cost effectiveness of specific task examinations versus a general look for faults is
clearly evident from the probability set at Figure 53. A specific examination regime of
tasks with high reliability requiring two attempts for a particular CF interval may replace a
general examination regime of low attempt reliability where many more attempts may be
required to achieve the same outcome.
US MIL-STD-2173AS provides an algorithm to calculate the optimum number of
examinations to be conducted across the CF interval. The details are contained at
Section 6.2.
4.2.3 Zonal Examinations
Zonal examinations are required by the RCM based analysis logic. Zonal examinations
are not directed at any particular failure mechanism but recognise that general
deterioration, accidental damage and vandalism can occur at any time. Such failures are
not related to the natural failure mechanism of the item but occur randomly at lengthy
intervals.
The Zonal examination directs attention to specific zones or areas of the system, and
includes checks of areas not normally examined such as inside cabinets, conducting
checks of equipment for security, obvious signs of accidental damage or leaks and
general wear and tear.
The following procedures can be used to develop a zonal inspection program:
a) Divide the Application into zones.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
b) Prepare a task listing work sheet for each zone including the location, a
description, access notes, etc.
c) During actual analyses of systems, equipment and structures, list any general
visual task which could be conducted as a zonal external/internal surveillance
on the task listing work sheet for each zone involved.
d) Include the interval from the original analyses on the zone work sheet.
e) As the analysis covering the items in a zone iscompleted, the zone should be
reviewed to consolidate examination requirements and assign task frequencies.
The frequencies of examinations in each zone are established from experience and
generally a function of:
The visibility of operating equipment in the zone
The criticality of contained operating equipment in terms of consequences of failure
Load rating in terms of stresses to which the equipment and associated structures
are subjected
General exposure to accidental or vandal damage
It should be noted that track walking by infrastructure, transmission/distribution line patrol
by maintenance staff, signal relay box examination by signalling staff, driver walkarounds
and substation outdoor area inspections are, to a large extent, zonal examinations.
4.2.4 Hard time Rework or Discard Tasks
Hard time rework (overhaul) tasks must be technically feasible in terms of removing
deteriorated equipment from service prior to failure, thus failures must show a wear out
tendency and be concentrated about an average age. If failures are concentrated,
scheduled restoration prior to this age can reduce the incidence of functional failures.
This may be cost-effective for failures with major economic consequences, or if the cost
of doing the scheduled restoration task is significantly lower than the cost of repairing the
functional failure.
The frequency of hard time reworks are generally estimated at acquisition on the basis of
equivalent equipment and confirmed by an aggressive age exploration program drawing
on the initial items in a batch procurement. It should be noted that this strategy may be
difficult to follow where individual items of infrastructure equipment are procured in small
numbers with limited manufacturer information or support.
Where significant numbers of equipment are available then Weibull analysis techniques
can determine the failure characteristics of the equipment and whether hard time rework
is applicable and if so what is the most cost effective overhaul period. Further details on
establishing hard time rework frequencies are listed at Unit 9.
It should be noted the disadvantages of scheduled restoration are that:
Items must removed from the facility and hence require additional cost of rotable
pool spares.
Many items do not achieve their optimum life as they are removed early.
The greater level of invasive maintenance means more opportunity for human error
and quality problems.
However, scheduled restoration is generally more cost effective than scheduled discard
because it involves recycling items instead of throwing them away. Additionally, the
discard task is usually mandated by fatigue and safety reasons and hence the time period
is often conducted at about one third of the value at which an increase in failure rate
occurs to guarantee no failures.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED

Hard time discard is usually the least cost-effective of the three preventive tasks, but
where it is technically feasible it does have certain desirable features. Safe-life limit can
reduce the frequency of functional failures which have major economic consequences.
Safe-life limits are rarely used in the rail industry and if required would flow from a test
program conducted by the manufacturer. The task frequency would of necessity be a
manufacturers requirement verified during acquisition and confirmed during operation.
4.2.5 Combinations of Tasks
For some failure modes which have safety or environmental consequences, a single task
cannot be found which reduces the risk of the failure to an acceptable level. In these
cases, it may be possible to find a combination of tasks which reduces the risk of the
failure to an acceptable level. Each task should be carried out at the frequency
determined for that task. Note that situations in which this is necessary are very rare, and
the process should not be used as a "just in case" exercise.
4.2.6 Failure Finding Tasks
Failure finding tasks are associated with hidden functional failures and hence deal with
the risk associated with double failures. The theory associated with this analysis is drawn
from US MIL-HDBK-338-1A
41
.
Suffice to say that the problem of double failures is one of conditional probability i.e. given
the hidden failure (failure of the stand-by unit, Item A), what is the failure probability of
item B which will then result in total function failure. The probability of a double failure is
therefore a function of probability of failure of items A and B and the percentage
downtime or unavailability of item B. Unavailability of hidden failures is related to the time
between failure finding tasks which is set by either the reliability achievable by the hidden
failure item, assuming an insignificantly short fix time, or by the availability of the item
flowing from lengthy down times due to the repair process.
This relationship is shown in Figure 54.



41
US MIL-HDBK-338-1A
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




Item A
Item B
Failure
Occurs
Functional
UpTime
DownTime
Legend
UpTime
DownTime
Failure
Repair
A functional failure occurs when an item B
failure occurs during the down time of item A
Downtime is the period between failure and repair
and includes failure finding and repair time
Primary
Standby
Double failure area

Figure 54 - Probability of double failure
The probability of having a double failure is calculated by the following equation:
Probability of
Item A being
failed
Probability
of Item B
failing

OR
Probability
of Item B
being failed
Double failure/Year and
Failure rate
of item A
per year
PRIMARY SYSTEM
PROTECTIVE SYSTEM
COMBINED SYSTEM
= A x B

Figure 55 - Calculation of a double failure
Thus if in a 12 month period item B's downtime is one month then the probability of item
B being failed at any particular time during the year is 1/12 or an unavailability of 0.083. If
the probability of item A failing in a given year is 1/10 (unreliability of 0.1) then the
probability of full functional failure, that is A and B failed simultaneously, is 1/12 multiplied
by 1/10 which equals 1/120 (0.0083).
The failure finding frequency can be calculated on the basis of economic return on the
investment associated with doing the failure finding examination ie.
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




The annual cost
of doing the failure
finding tasks
The annual loss
exposure of not
doing the tasks
OR

Figure 56 - Calculation of failure finding frequency
In this regard loss exposure is considered to cover loss to the community at large and
could factor in the death, injury and environmental damage costs as appropriate. Often
the data to support this analysis may not be available and the assessment of failure
finding frequencies is conducted by establishing an acceptable event probability and
determining the failure finding task frequency required to achieve this probability.
Further details on the determination of failure finding frequencies are shown at Unit 9.
4.2.7 Suggested Readings & References
The following are suggested additional readings for this section.
Standard or Reference Name Page Numbers
United States Military Standard
MIL-STD-1629A
Nil
Nowlan & Heap Reliability - Centred Maintenance Pp 324-325, 224-225,
62-63
United States Military Standard
MIL-STD-2173AS
Pp 57-66,81,154-156
Moubray, RCMII Pp 136-140, 109-120
Smith, Reliability-Centred Maintenance Pp 58, 186-188
MSG 3 Report Nil
4.3 Task Packaging
4.3.1 Introduction
The maintenance analysis process creates, as its primary output, a list of tasks and
associated frequencies. These tasks, depending on the level of knowledge available to
the analysts, will be spread across a spectrum of time and event based frequencies.
Packaging refers to the activity of bringing together into packages, the individual
preventive maintenance tasks identified during the maintenance requirements analysis
activity. The objective of packaging is to provide manageable groups of activities for the
maintenance planning and control process to resource.
The process provides a mechanism for placing under a single identifying code all
maintenance to be done to an asset or set of assets at a particular geographic position at
a particular point in time. These aggregations of tasks are termed servicing schedules in
that they are a schedule of servicing tasks to be completed together.
4.3.2 Options
There are a number of packaging options available to the analyst. A set of guidelines
should be drawn up at the beginning of the analysis activity to guide the analysts in the
production of the packages. The guide should identify the constraints and the objectives
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




of the packaging process. As an example the guidelines produced for the packaging of
rail vehicle (and infrastructure equipment) servicing schedules are detailed at the end of
this Section.
Packaging options available to the analyst are:
Hierarchical Set where the packages get progressively larger as the shorter frequency
activities, as multiples of the longer frequency activities, are added together. The
duration to complete the aggregated group of tasks will steadily increase unless more
resources are allocated. This is shown diagrammatically in Figure 57.

Figure 57 - Hierarchical servicing set
Equalised or Balanced Sets are directed at creating servicing sets of equal duration.
The process is generally applied to achieve servicing task times that match available
maintenance windows of opportunity. The period may vary from up to 4 hours for Rolling
stock between the peak service requirements to as low as 15 minutes for scheduled
services on the infrastructure. The process is shown in Figure 58.
3 Month
6 Month
12 Month 3 Mth 6 Mth 9 Mth 12 Mth
Legend
Time
Half the 6 Month Tasks
Quarter the 12 Month Tasks
Tasks
Tasks
Tasks

Figure 58 - Balanced servicing set
Phased Servicing takes the balanced set one step further by breaking the servicing
down into smaller packages which can be completed in a short period of time. Such
packaging may be of advantage where regular access to the equipment is available and
time constraints are critical. Packages can be tailored by splitting up the activities into
more numerous but equal sized packages to fit into "maintenance windows" of
opportunity. Thus, by halving the task groups at Figure 58, the new smaller task groups
in Figure 59 are required twice as often but take half the time.
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




3 Month
6 Month
12 Month
Legend
Time
Tasks
Tasks
Tasks
Task
Task Group done every 1.5 Months
Available Maintenance Window

Figure 59 - Phased servicing set
Special Servicings are occasionally required where activities just don't fit into the
packaged set because the servicing is related to random events such as a flood or storm,
or some non time based measure such as a number of fault openings for a bulk oil circuit
breaker which cannot be accommodated within the prime set.
4.3.3 Packaging Process
Having established the packaging guidelines the following steps are taken to establish
the servicing set:
Timebase the Tasks. All task frequencies are brought to a common baseline, usually
against time as shown in Figure 60. Those tasks which are event based may be either
left at the event count and included as a special servicing or can be converted to a
timeline by determining the event rate and statistical distribution. Care should be taken to
adequately identify those tasks which are converted from an event to time base to ensure
that when operational conditions are changed the task frequencies are updated. Tasks
should be given some form of individual identification at this stage even if only temporary.
Timeline Tasks. The average time for each task is essential to the remaining steps in
the process. As the tasks are usually stable in content with few variables, a reasonably
accurate task time should be identifiable. Care should be taken with underestimating the
task time and a test and evaluation program for any significant departures from normal
practice will be necessary.
Physically Represent Tasks. The tasks can then be physically represented by a piece
of cardboard cut to a scale to represent task time. This will enable various combinations
of task programming (number and certification of staff, access arrangements and
relationships between tasks) to be relatively easily tested using the constraints provided
in the packaging guidelines.
Group Tasks Into Schedules. The related sets of tasks can then be assembled into a
servicing schedule set which is applied to a particular group of assets at a particular
period.
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual





Figure 60 - Task aggregation - timing
4.3.4 Latitudes
Each task or schedule identified in the maintenance plan will require the allocation of a
latitude of particular value to allow for effective maintenance planning and control The
latitude sets the maximum and minimum time span for the maintenance activity.
Latitudes are not arrangements which enable the reduction of maintenance effort by
setting the activity at the maximum frequency but a pragmatic mechanism for balancing
risk against management capability.
The determination of economic latitudes may be established with the assistance of the
task cost curve graph in MIMIR. The validity of the latitude will be influenced by the
accuracy of the CF interval determination and the business costs.
The approaches to be followed are shown at Figure 61.
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




R4
New
R1 R2 R3 R4
Note: The R4 resets the counter if the servicing set is heirarchial
R4
New
R1 R2 R3 R4
Note: The R4 does not reset the counter in a balanced sevicing set
BALANCED SERVICING SET
HEIRARCHIAL SERVICING SET

Figure 61 - Usage of latitudes
4.3.5 Task Packaging Guidelines
Prior to the packaging activity commencing, a clear and concise set of guidelines must be
provided to the analysis team. The guidelines will depend on the structure of the system
being analysed and it could be expected that distributed linear systems such as a
transmission line would have entirely different requirements than mobile items such as
rolling stock, assets such as a hole borer/crane or fixed assets such as a circuit breaker.
For further details refer to Error! Reference source not found..
As a general rule packaging guidelines will take account of the following:
Available or desired maintenance windows
Staff available at any particular time
Staff skill mix
Facility constraints regarding capacity and access
Level of local decision making autonomy
4.3.6 Standard Terminology
The format for servicing schedules will vary between disciplines, however the words used
to define trades staff actions must be standardised to ensure consistency of approach
and to assist the transfer of information across application boundaries. Consistency of
task description enables the provision of one training course for trades staff across the
organisation and a common interpretation of instructions and task directives by all
support staff.
Each task statement should have the standard structure shown at Figure 62.
VERB NOUN CONDITIONAL STATEMENT
Examine attachment blocks security for

Figure 62 - Standard task statement structure
The verbs are the key words which define the task action and have a standardised
description. The remainder of the statement will depend on the particular item and failure
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
mode and hence use conventional English meanings. These key verbs are listed in
Figure 63:
Verb Detailed requirement
Examine
Carry out a visual survey of the condition of an item without
dismantling (unless directed to do so by the maintenance
instruction).
Lubricate
Apply a specified lubricant (e.g. oil type XYZ, grease type ABC) to a
specified area of equipment (often specified in a separate
lubrication chart).
Check
Make a comparison of a measurement of some quantity (e.g. time,
pressure, temperature, resistance, dimension) to a known value
(accept/reject criteria) for that measurement and if required rectify
and/or replenish if necessary.
Check
Operation or
Operate
Ensure that an item of equipment or system functions correctly as
far as possible without the use of test equipment or reference to a
measurement.
Clean
Remove contaminating materials (e.g. dust, dirt, moisture,
excessive lubricant) from an item of equipment.
Adjust
To alter as necessary to make an item compatible with system
requirements.
Test
Determine by using appropriate test equipment that a component of
equipment functions correctly.
Replenish
Refill a container to a predetermined level, pressure or quantity and
undertake associated access and closure tasks.
Fit Correctly attach an item to another.
Refit Fit an item that has been previously been removed.
Calibrate
Make a comparison of a measurement of time, pressure,
temperature, resistance, dimension or other quantity to a known
standard (usually a NATA laboratory function).
Disconnect Uncouple or detach cables, pipelines or controls.
Reconnect Reverse of disconnect.
Safetyseal
Securing of equipment which requires the breaking of a seal to
manually operate (usually associated with emergency equipment).
Remove Correctly detach one item from another.
Secure To make firm or fast.
Figure 63 - Task verbs - standard terminology
4.3.7 Suggested Readings & References
The following are suggested additional readings for this section.
Standard or Reference Name Page Numbers
Nowlan & Heap Reliability - Centred Maintenance Pp 284-291
United States Military Standard
MIL-STD-2173AS
Pp 175-201
Moubray, RCMII Pp 172-176
Smith, Reliability - Centred Maintenance Nil
MSG 3 Report Nil
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
5 Audit and Evaluation
5.1 Auditing
5.1.1 Introduction
Although the RCM analysis is conducted by the best technical and engineering staff
available and facilitated by experienced analysts, bias may be introduced during the
analysis.
The auditing of the analysis process and the resulting decisions is essential to counter
either the familiarity possessed by internal staff or the lack of visibility of the process in an
external provider.
An independent review of the analysis decisions ensures that the logic has been
properly applied and reduces the probability of errors of judgement.
Additionally, as the analysis process involves the establishment of significant policy
decisions, senior management are not absolved from accountability for the outcomes.
Accordingly the audit process provides a mechanism through which management can
assure itself that defined procedures have been followed and sustainable outcomes
achieved. The audit may be done by senior management staff themselves or by
delegation, provided the auditor is properly qualified and experienced to undertake the
audit function.
Auditing is best conducted independently of, and if possible externally to, the group
performing the analysis. The audit process should include the following areas:
Significant item selection.
Determination of item functions, failure modes, cause and effects.
Classification of failure consequences.
Evaluation of applicability and effectiveness criteria.
Task packaging guidelines.
5.1.2 Timing of the Audit
Audits should be carried out progressively
Audits should be carried out progressively as each system review is completed for the
following reasons:
Analysis group members may change from system to system and the audit should
be conducted while team members are still available
Early audits will make for easier recall of the basis for decisions if documentation is
unclear
The audit process will provide valuable feedback to analysis team members and
improve performance on the remaining task
Early approval of analysis results may allow their issue as policy and hence gain
the benefits of the decision.
5.1.3 Auditor Selection
A chief pre-requisite for auditors is a clear understanding of the RCM principles.
Knowledge only of the equipment or technologies being analysed will not be adequate
and will threaten the achievement of an objective review. Auditors must primarily be
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
completely familiar with the RCM process and be able to detect errors in logic and
documentation.
Additionally, they must have a working knowledge of the technical aspects of the system
to be able to properly audit the key functional description statement. When analysis is
conducted as a part of asset acquisition program, the requirement for audit by the
procuring organisation, where both procedural and technical knowledge exist, should be
included in the procurement contract.
5.1.4 Significant Item Selection
The sharing of common definitions of significant items and operational consequences by
analysts and auditors is essential. In this regard:
Identification of significant items is based on their failure consequences not on the
item cost or its complexity. Failure consequences refer to the direct impact that the
loss of a particular function has on the safety and service capability of the
equipment not on the number of failure modes or their effect on the item itself.
The circumstances that establish service consequences and their costs must be
clearly defined. This information is essential to the determination of economic
consequences and should be supported by a simple readily understood economic
analysis.
5.1.5 Item Function, Failure and Effects
The recorded data should provide for clear traceability of task outcome via the provision
of adequate and clearly presented information at each step of the analysis process.
Auditors should be satisfied that each task is completely traceable.
Traceability should be available in both directions. Beginning at a function, traceability
through to the task(s) assigned to protect that function or beginning with a task to
backtrack through to the reasoning that led to its selection.
Auditors should pay particular attention to the detection of the following:
Improper definitions of the function of an item
Is there a clear functional diagram of the system or equipment?
Is the selected level correct?
Are all the hidden functions identified?
Have all secondary functions been listed?
Confusion between functional failures and engineering failure modes
Does the failure mode describe the lost function rather than the manner in which
the failure occurs?
Are failure modes that have never actually occurred been listed?
Are the failure modes reasonable given experience with similar equipment?
Have any important failure modes been overlooked?
Does the description of the failure relate to the cause of the failure rather than its
immediate results?
Description of failure effects to include all information necessary to support the
consequence evaluation
Is a description of the physical evidence used by the operator(s) to identify the
failure included?
Are the effects of secondary damage clearly stated?
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
Does the description identify the ultimate effects of the failure given no preventive
maintenance?
Are the effects of protected functional failures associated with hidden or
protective functional failures stated?
5.1.6 Classification of Failure Consequences
The first four questions in the decision logic (see Figure 43) identify the consequences of
each type of failure and direct the analyst to the particular branch of the analysis process
to be applied. These answers to these questions are particularly significant and hence
warrant special attention during auditing.
Again the basis of each answer should be clearly traceable in the documentation and
auditors should pay particular attention to:
The identification of hidden function failures
Has the evident failure question been asked of the functions not the item?
Has operator instrumentation been overlooked as an indication system?
Have redundancies without indication of failure been adequately considered?
Have the hidden function of emergency items been overlooked?
Have built in test functions been properly assessed in regard to failure visibility to
the operator?
The identification of safety and safety hidden failures
Has the failure been identified as critical on the basis of double failure
consequences rather than the consequences of a single failure?
Has it been identified as critical because it requires immediate corrective action?
i.e. it is service critical.
Has the analyst taken into account redundancy or fail safe design features that
prevent the functional failure from being critical?
5.1.7 Evaluation of Applicability and Effectiveness Criteria
When auditing the selected tasks for applicability criteria, the auditors should assure
themselves that the analyst understands the resolving power of the types of tasks
available and the conditions under which each type of task is applicable. Of importance is
the fact that if the task is directed at the mere examination of an item of equipment for
condition rather than a specific failure mode, then it is not an on-condition task.
An on condition task must be directed at a failure mode that has a definable potential
failure stage with an adequate and fairly predictable interval for examination.
The audit checklist for the application of these criteria to the possible maintenance task
types is:
Are on condition monitoring tasks feasible and practical?
Have the age characteristics been established for hard time tasks?
Will rework restore original reliability (particularly if the item under study has no
empirical evidence to justify the assumption)?
Is the task interval applied to hard time tasks cost effective?
Have manufacturers recommendations been followed and if not is justification
clearly presented?
Are the failure finding tasks linked to hidden functional failures only?
Have the appropriate items been assigned to an age exploration program?
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
Effectiveness criteria depend completely on the objective of the particular task and the
consequences it is intended to prevent. The same task type will vary in its effectiveness
depending on the application. The audit checklist for effectiveness criteria are as follows:
Do the tasks and periods selected have an acceptable probability of preventing all
critical failures?
What is the basis for accepting residual risk levels?
Do hard time tasks (if specified) adequately prevent critical failures or just control
them?
What mechanisms are available for the application of default strategies?
Is the mechanism for determining cost effectiveness clearly visible?
Is the cost of service interruptions realistic and based on approved criteria?
Are there adequate mechanisms to quantify risk in relation to safety and service
related events?
Do failure finding tasks duplicate the operator activities?
5.1.8 The Completed Program
After analysis of individual sections is complete and their results audited separately, the
program as a whole following task aggregation may need auditing. This activity ensures
that:
Aggregation activities have considered all options.
Any variations to task frequencies go through the audit process.
5.1.9 Suggested Readings & References
The following are suggested additional readings for this section.
Standard or Reference Name Page Numbers
Nowlan & Heap, Reliability - Centred Maintenance Pp 350-369
United States Military Standard
MIL-STD-2173AS
Pp 210-224
Moubray, RCMII Pp 239-240
Smith, Reliability - Centered Maintenance Nil
MSG 3 Report Nil
5.2 Test and Evaluation
5.2.1 Introduction
The introduction of new preventive maintenance schedules brings with it an element of
risk which must be managed by the responsible and accountable authority for the subject
equipment.
A significant element in the risk management of new maintenance schedules is the
conduct of a test and evaluation program which confirms the theoretical and experiential
decisions made during the analysis and protects against unanticipated risks.
The risks associated with a new or modified schedule set are considered to be:
Safety risks associated with task sequencing and task conduct.
Service risks associated with task description and duration, inventory and support
equipment needs.
Economic risk associated with task description and duration.
Human resource risks associated with any change.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
The requirement for a formal test and evaluation of either initial or modified preventive
maintenance programs will generally be subject to engineering judgement within a set of
defined guidelines. These guidelines are contained in the following paragraphs which are
divided into two different origins for analysis activity.
5.2.2 Initial Schedules - New Equipment
The purchase of new equipment, not currently in service, will inevitably require the
specification of new maintenance policies and their associated servicing schedules.
These policies and their supporting schedules should be delivered before the arrival of
such equipment in accordance with the requirements imposed by functional/performance
specifications regarding system support.
The system/equipment specification, if formatted in US MIL-STD-490
42
or equivalent
format, will require the maintenance plan, servicing schedule and maintenance task data
including associated analysis as deliverables which clearly show, in accordance with the
procedures outlined in this Manual, how the maintenance policies and associated task
descriptions were derived.
The test and evaluation program for the schedules will also be included in the
deliverables list and will usually be a milestone in the procurement program as a
demonstration that maintainability targets such as MTTR and MDT have been achieved.
The evaluation should also include checks on the suitability of the assigned facilities, the
available support equipment and their expected interaction with the proposed
maintenance schedule.
5.2.3 Initial Schedules - In Service Equipment
Despite the best intentions of organisations to procure properly documented systems,
there will be a need from time to time to undertake the maintenance analysis of new
equipment which, for a variety of reasons, may have arrived without a well documented
set of maintenance requirements. Individual pieces of equipment procured on a one - off
replacement basis without coverage of a period contract requiring standardisation may
not have an RCM based maintenance program.
New schedules developed in accordance with this program should be tested in the same
manner as for new equipment during its test and evaluation phase. A typical brief for the
test and evaluation of a significant maintenance schedule change is shown at
Section 5.2.5.
5.2.4 Suggested Readings & References
The following are suggested additional readings for this section.
Standard or Reference Name Page Numbers
Nowlan & Heap Reliability - Centred Maintenance Nil
United States Military Standard
MIL-STD-2173AS
Nil
Moubray, RCMII Nil
Smith, Reliability - Centered Maintenance Nil
MSG 3 Report Nil



42
US MIL-STD-490, Specification Practice
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
5.2.5 Test and Evaluation Program Brief
5.2.5.1 Introduction
A comprehensive Reliability-Centred Maintenance (RCM) analysis program is being
undertaken to develop Technical Maintenance Plans and their associated servicing
schedules. The program will produce a set of maintenance schedules which must be
verified before approval can be given to their application in the field.
5.2.5.2 Objective
The objective of this brief is to define the services required to implement and document a
test and verification program for the servicing schedules developed by a new decision
process (RCM analysis).
5.2.5.3 Scope of Work
The program will include the following activities:
Identify the content of a test and evaluation program that will:
i) Provide the accountable Engineering Manager with clear and concise
evidence necessary for sign off on the safety aspects of the schedule
ii) Confirm the ability of the schedule to achieve its required maintenance
window criteria.
iii) Confirm the task sequencing and task relationships specified in the
schedules.
iv) Confirm or enhance the logistic support (test equipment, tools and spares)
requirements established during the analysis.
Develop an implementation project plan for the identified test and evaluation
program.
Develop a risk management program that, as a minimum covers safety, industrial
relations and technical risk exposures.
Undertake, or as necessary arrange, the familiarisation and training of staff
requisite for the success of the program.
Collect technical and administrative data necessary to complete an effectiveness
evaluation of the process.
On completion of the test and evaluation program:
i) Produce a report on the effectiveness of the total process (RCM analysis
and subsequent schedule development) in agreed quantitative measures.
ii) Identify the necessary changes to the original analysis documentation
following completion of the evaluation.
5.2.5.4 Key Issues
Verification is a high risk aspect of a project designed to produce both a significant
change to the technical content of work in a conservative environment as well as
establish the groundwork of a major realignment of a well entrenched and established
culture.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
5.2.5.5 Typical Project Profile
The following steps and their duration would be expected in a typical test and evaluation
program:
Task List Duration
Prepare Project Plan and Conduct Initial Briefings
Prepare Test Schedule
Complete Preparatory Procedures
Training
Support Equipment & Special Tools
Spares and consumables
Conduct Initial Test of Each Schedule (4 weekends due to limited asset
availability)
Complete analysis of results and identify changes for second review
Second Review facilitated by Engineering Services
3 Days
3 Days
2 Days
1 Days
2 Days
8 Days
3 Days

Total Days 22 Days
5.3 Technical Maintenance Plans
5.3.1 Introduction
The results of the maintenance requirements analysis on a particular Application are
usually promulgated as a set of maintenance policies in a Technical Maintenance Plan
(TMP). The plan provides a comprehensive listing of Application systems and their
associated configuration items along with the maintenance policies that apply to each
configuration item.
The plan is usually structured as a paper document which is an output from a word
processor / spreadsheet or increasingly a data base. Computerised maintenance
management systems contain the plan as the directive set of requirements for scheduling
preventive maintenance.
5.3.2 Item Listing Criteria
The TMP lists items when:
They are repairable.
They have a defined maintenance policy (ie. the item has scheduled maintenance
activity at a defined interval).
They require some special maintenance management input and thus will need
certain information to be recorded.
5.3.3 Plan Information
The TMP provides maintenance policy information and includes as a minimum:
Which items are maintained
What maintenance is carried out
When maintenance is carried out
Who performs the maintenance
Where maintenance is carried out
How maintenance is carried out (cross reference to quality document)
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
5.3.4 Responsibility
The content of the TMP is the responsibility of an authorised engineering manager
normally defined in a Configuration Management Plan. Procedures for management of
the data contained in a TMP are defined in this publication and the specific Appendix for
the particular Application.
Specific maintenance requirements are continually under review, therefore the contents
of each TMP are regularly revised as necessary. Applicable configuration management
practices must be applied in the development and issue of technical maintenance plans
to ensure currency and auditability.
5.3.5 Suggested Readings & References
The following are suggested additional readings for this section.
Standard or Reference Name Page Numbers
Nowlan & Heap Reliability - Centred Maintenance Nil
United States Military Standard
MIL-STD-2173AS
Nil
Moubray, RCMII Nil
Smith, Reliability Centered Maintenance Nil
MSG 3 Report Nil
6 MRA Techniques and Policy
6.1 Age exploration
6.1.1 Introduction
Age exploration is a process associated with the application of RCM analysis techniques
in accordance with the procedures outlined by the IATA Maintenance Steering Group 2/3
and MIL-STD-2173AS and described in detail in Nowlan and Heap.
The process is primarily established to iteratively refine initial maintenance tasks and
associated frequencies resulting from RCM analysis conducted during the design stage
of new equipment. Initial estimates of failure modes, equipment failure characteristics,
MTBF and MTTF which determine tasks and their associated frequencies must be
verified and if necessary varied to suit actual equipment performance.
6.1.2 Process
Age exploration has three main elements:
Failure data collected during normal operation of the equipment is analysed to
determine the accuracy of original estimates of MTBF or, in the absence of a
mathematical approach, the use of maintainer experience.
During routine repair of failed items, additional tasks may be inserted in the repair
process to examine the condition of components prone to wear or fatigue. The
results of this analysis are then used to either establish an overhaul period if not
yet set or to verify an already defined frequency.
Investigative maintenance activities are conducted to ascertain the failure
degradation rates of significant equipment or components. Significance is allocated
on the basis of complexity, cost or criticality. The process may vary from the
relatively low cost determination of consumable (lubricants, motor brushes) rates of
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
loss or deterioration, to the more costly full strip, examination and report on larger
equipment such as electric motors, pumps, air conditioners or compressors.
6.1.3 Research Opportunities
The age exploration process will often include the need for research briefs to be
established to improve the entire maintenance process. Such briefs may involve
improving the knowledge of failure mechanisms and identifying opportunities for
advanced technology to enable the implementation of condition monitoring tasks.
The application of a wide range of condition monitoring techniques are available to the
professional maintainer and often simple and unsophisticated techniques such as
temperature sensitive tapes may provide invaluable data on operational overheating.
6.1.4 Cost Effectiveness
At all times the cost effectiveness of the Age Exploration process should be considered in
the light of its expected cost and its expected outcomes. An Age Exploration Plan and its
associated procedures should be established for each Application and included within the
Engineering Management Plan for the responsible engineering authority. The program
must be costed to ensure return on investment and have clearly allocated responsibilities
and accountabilities to ensure useful outcomes are achieved.
6.1.5 Responsibilities
The Age Exploration (Agex) Program is an integral element of the quality management
approach as it applies to the continual improvement of the content of the Technical
Maintenance Plans. The quality management principles behind this program require the
allocation of management priorities to candidate systems and equipment on the basis of
cost of ownership. That is, candidates for age exploration are selected using the Pareto
principle on the basis that the largest savings can most probably be achieved from
optimising the largest expenditures.
Ownership of the age exploration process resides with the engineering function and
should have a well defined owner who has accountability and responsibility for the
proactive process of continual improvement.
6.1.6 Summary
An Agex program can be a valuable tool in refining initial maintenance program estimates
into more cost effective tasks and their frequencies. Care should be taken that the
program is well defined (formal and visible) in terms of process, prioritisation and
ownership. Some form of plan will usually be necessary to ensure that objectives and
their supporting activities are properly selected and applied in a structured and cost
effective manner.
6.1.7 Suggested Readings & References
The following are suggested additional readings for this section.
Standard or Reference Name Page Numbers
Nowlan & Heap Reliability - Centred Maintenance Pp 106-108,114-
115,121-137
United States Military Standard
MIL-STD-2173AS
Pp 25 and Pp 86-90
Moubray, RCMII Pp 247
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




Standard or Reference Name Page Numbers
Smith, Reliability - Centred Maintenance Pp 186-189
MSG 3 Report Pp 28
6.2 Task Frequency Algorithms
6.2.1 Introduction
The determination of task frequencies can be enhanced in terms of both accuracy and
speed of decision making by the application of quantitative decision analysis techniques.
The use of algorithms enables the rapid assessment of possible task options and the
sensitivity of the outcome to estimation errors in the various elements.
The three task types most amenable to the use of algorithms are:
Condition monitoring
Hard time (Overhaul or restoration)
Failure finding
Three decision algorithms which support the RCM decision are listed in the following
paragraphs.
6.2.2 Condition Monitoring Algorithm
This algorithm is derived from US MIL-STD-2173AS and described at pages 58-59. A
diagram of the algorithm and the formula are shown at Figure 64.
TO FAILURE
RESISTANCE
VISIBLE EVIDENCE of FAILURE
CONDITIONAL
FAILURE
FUNCTIONAL
FAILURE T
OPERATING AGE
T T
0%
100%
Where T = Time between Conditional
and actual Functional Failure
T = Time between successive examinations
CF Interval
Repair $
Service Loss $
External Impact $
Maintenance Cost $
MTBF
Repair $
Failure Detection
Probability

Figure 64 - Condition Monitoring Algorithm
The algorithm for determining the optimum number of examinations n across the CF
interval is:
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual





Where n = Optimum number of condition examinations in the
time interval between conditional (potential) failure
and functional failure
T = Time interval between conditional (Potential)
failure and functional failure
T = Time interval between examinations
MTBF = Mean Time Between Failures or the average life
expectancy of the equipment if allowed to run to
failure
Ce = Cost of each examination
Cpf = Cost of correcting each conditional failure
Cnpm = Cost of not doing preventive maintenance (ie cost
of unplanned failure)
= Probability of detecting the failure in a single
examination
The algorithm requires the following assumptions:
MTBF >>T
Possible to detect reduced failure resistance for a given failure mode
Possible to define a potential failure condition (parameter and value) that can be
detected by an explicit task
Must be a reasonably consistent age interval between the time of conditional
failure and functional failure
The probability of detecting the failure in one examination is constant
6.2.3 Double Failure Algorithm
This algorithm considers the implications of a failed protective system and a failed
primary system and calculates the optimum maintenance period for a failure finding task
based on minimum total cost of maintenance plus risk exposure.
The model shown at Figure 65 describes the basic fault - event tree or cause -
consequence diagram that may be used to determine the optimum failure finding task
time T. In the Figure 65 maintenance cost is a function of condition monitoring task cost
and task frequency while cost of failures is a function of:
Primary item failure rate (fixed)
Protective item/system failure rate (variable depending on failure finding task time
T)
Probability and cost of possible outcomes following double failure to establish a
cost value per event.
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




FAILURE FINDING TASK
Is a failure
finding task
applicable and
effective
Primary Item
Protective Item
Adverse
Event
LOC
Possible
Outcomes
Optimum Task Time
Maintenance
Cost
$
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
Cost of
Failures
Total Cost of Task Freq
Model
Cost Profile

Figure 65 - Failure finding task frequency
A formula is not available from standards and texts. The time interval T (optimum task
frequency) for the task period can be calculated by determining a value for T that will
provide equal values for maintenance cost and cost of failures. This assumes that the
failure rate of the protective maintenance system is negative exponentially distributed
(random).
As depicted in the $/Time curves in Figure 65 the combined outcome ($ maintenance +$
failure cost) for a given task time, is very flat around the optimum task time. the process
is thus quite robust and not particularly sensitive to minor errors when estimating cost.
6.2.4 Hard Time Algorithm
Decision algorithms are available commercially for determining hard time tasks such as
overhaul. Weibull Probability paper can be used to establish the optimum interval for an
age based preventive replacement policy (hard time restoration). The procedure is
described in J ardine, Maintenance Replacement and Reliability and can be readily
conducted using commercial off the shelf software.
For hard time tasks it should be remembered that from the United Airlines actuarial study,
only 6% of items supported application of a hard time maintenance activity. Additionally,
the algorithms require quality mean time between failure data which is usually lacking in
most organisations.
However, certain items will exhibit a dominant failure mechanism and may be usefully
managed with a hard time restoration (overhaul) or discard process.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




Is a hard time
restoration task
applicable and
effective
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
Is a hard time
applicable and
effective
discard task
Item Wear Out
Restoration Period
For populations of items only
Optimum Task Time
Maintenance
Cost
$
Cost of
Failures
Total Cost of Task Freq
Model
Cost Profile
SCHEDULED (HARD TIME) RESTORATION
AND DISCARD TASK
Failure
Rate
Time

Figure 66 - Hard time task frequency
In regard to hard time total cost of task curve, note that the cost of failures curve is not
straight (ie random failure pattern), but represents a wear out failure pattern with an
increasing failure rate with time. Hence the optimum time is earlier than the
maintenance/failure cost cross over point and the curve has greater sensitivity to
variations in task time T.
6.3 Level of Repair Analysis
6.3.1 Introduction
Level of repair analysis (LORA) is a process for determining whether equipment should
be maintained at all and, if so, whether equipment should be maintained on or off the
prime Application or its operating systems.
The LORA process requires an explicit statement of whether the rail maintenance system
supports a two or three level maintenance organisation (Operational, Workshop and
Contractor). This should be defined in the maintenance concept for the Application and
documented in the appropriate Engineering Management Plan. However, while each
maintenance decision must stand alone in regard to cost effectiveness, care should be
taken that facilities are not used just because they are there and that the total implications
of continuing with a local facility is considered.
Key information essential to effective LORA at the design stage is a detailed operational
requirement and maintenance concept. With systems already in service this information
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
as well as actual cost data should be readily available. Using the checklists available
simple spreadsheets should be adequate for any necessary analysis.
6.3.2 Repair Versus Replace Decisions
Considerable theoretical mathematical work has been done on repair versus replace
decision algorithms. United States MIL-STD-1390 Level of Repair Analysis contains a
large number of optional algorithms to be applied to repair versus replace decision
making. However, the algorithms require considerable amounts of hard data regarding
reliability, maintainability and logistics costs which are rarely available in most
organisations undertaking maintenance requirements analysis for the first time.
Considerable theoretical work has also been done by Professor A K J ardine in the
application of Weibull analysis to determine optimum repair and replace strategies for
equipment which have a primary wear out failure mechanism. A large number of possible
algorithms are defined in J ardine, Maintenance Replacement and Reliability, Pitman
Publishing.
Having decided that "repair" and not "replace" is the most economic activity, the following
paragraphs provide some options to be considered regarding where to do the
maintenance. It should be recognised that such decisions also affect the cost of repair
and that there is an iterative loop in the repair versus replace decision process.
6.3.3 Repair In Situ
The need to repair in situ is usually driven by the technical or physical inability to remove
the component and replace it with a spare. For many large items of plant or infrastructure
equipment whose structure is virtually built into the plant, removal is not an option.
Examples of such items are structural repairs and repairs to linear assets such as wiring,
piping, track, transmission or distribution lines, underground cables etc.
6.3.4 Repair at Local Workshop
The repair process is conducted locally at a workshop because some key cost elements
such as:
Distance from alternate repair facility
No alternate technical capability
Limited allowed down time (no replacement item) and high cost of rotable spare
Low cost and technology repair process
Limited need for specialised test equipment
Cost is always the primary driver of decisions between alternatives and an
economic analysis conducted where decisions are not obvious (see Figure 67).
6.3.5 Repair at Contractor Facility
The use of external contractor facilities can be a contentious issue. Again economic
rational approaches to decision making are necessary to ensure that repair decisions
follow a consistent approach.
External contractors are normally used in circumstances where:
The function is contestable
High cost specialist support equipment is not necessary
Critical mass of activity necessary to maintain internal skills is not available
The item is common to many other users and supported by efficient specialist
maintenance facilities
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




6.3.6 Process Map for LORA
System design
information
Determine
candidates
Practical screening
Safety
Policy
Technical
Economic screening
Frequency
Cost
Risk
Clear
Marginal
Detailed analysis
Relaibility
Maintenance
Spares
Transport
Consistency check
Operational needs
Maintenance concept
Logistic support
Enunciate policy
Provide logistic support
Clear
Marginal
Pass
Fail

Figure 67 - LORA process map (Blanchard )
A more detailed description of the LORA process described in the process map at Figure
67 is contained in Blanchard, Systems Engineering Management Pages 329-335.
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
6.4 MRA Policy
6.4.1 Introduction
RailCorp has progressively applied customised RCM analysis techniques to determine
the optimum preventive maintenance requirements of the infrastructure and fleet assets
of the NSW statutory rail authorities and corporations. This activity represents a
considerable investment in the future management of their capital assets and should not
be diluted by the addition of equipment without similar justification and documentation of
preventive and corrective maintenance requirements.
Maintaining the validity of the maintenance requirements analysis data requires ensuring
that future assets are not procured without the necessary maintenance planning action.
Additionally, the procurement of new assets should not require the application of valuable
engineering resources to determine or justify their preventive maintenance programs.
Procurement action should wherever possible include the justification of any maintenance
actions provided by the system supplier.
The detailed procedures used by each discipline in determining their preventive
maintenance requirements are attached in the appropriate appendixes. The data
structures of the maintenance requirements analysis described in the appendixes for
each discipline should drive the minimum requirements of supporting maintenance data
from suppliers.
6.4.2 Supplier Recommendations
Some observations on maintenance recommendations from individual equipment or
component suppliers would seem appropriate at this time.
Contractual requirements for suppliers to provide recommendations for the maintenance
of their equipment provide little assurance that either appropriate or optimum
maintenance will be forthcoming.
Equipment and component suppliers for commercial of the shelf (COTS) systems and
equipments provide for a mass general purpose market. Rarely, do they know either the
operating environment or the functional criticality of the application of their equipment.
Any maintenance recommendations they may make relate therefore to the protection of
their warranties in an unknown environment. Their recommendations therefore, of
necessity, manage risk exposure through the specification of a lowest common
denominator maintenance program.
System providers, who understand the system operating environment and criticality, have
the knowledge to integrate equipment suppliers into an effective maintenance system and
should through contractual arrangements own the risk associated with the specification of
maintenance requirements. The proper determination and documentation of those
maintenance requirements should be progressively verified through the design review
process contained in AS ISO 10007-2003 : Quality management systems - Guidelines for
configuration management.
6.4.3 New Systems
Maintenance planning is an element of logistic support and provides the complete list of
preventive and corrective maintenance actions required to support a new capital asset.
The procurement of major new capital assets provides an opportunity for maintenance
planning and life cycle cost data to be provided directly from the supplier of the new
assets. Suppliers have access to design data that assist in the ready definition of
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
maintenance requirements and asset procurers must ensure that such data is made
available for the future management of the asset through the necessary logistic support
requirements of the contract.
For major new procurements, a Maintenance Requirements Analysis program should
consist of the following elements:
A maintenance concept for new equipment that is used in the conceptual phase of
the program when establishing the procurement specification for new capital
assets.
Development of corrective maintenance requirements using FMECA and
Maintenance Task analysis techniques.
Development of the preventive maintenance program using RCM analysis
techniques according to the principles contained in this book and its associated
reference documents.
The continuing review and update of the preventive program requirements using
the techniques of age exploration to refine the estimates and assumptions used to
establish the initial program.
This program is to be tailored to new procurements and subject to the necessary design
reviews that will cost effectively ensure that the necessary maintenance programs are in
place.
6.4.4 Individual Equipment Replacement
As stated previously, FMECA and RCM analysis data is rarely available for COTS
equipment.
When individual purchase of COTS replacement or minor enhancing equipment is
necessary, good sense should prevail and the requirements for cost effectiveness of the
replacement asset followed. Government requirements for value in contracting provide
for proper assessment of new inventory items in regard to life cycle cost. This includes
the provision of justifiable maintenance plans.
Purchase of new inventories provides an opportunity to both improve the reliability and
availability of the systems and ensure that these improvements are not dissipated
through inappropriate or at worst non existent maintenance policies. Accordingly
individual equipment with critical performance requirements should be replaced only with
items that have a verifiable set of performance characteristics including cost of
maintenance.
New equipment should therefore be procured with the necessary justification of
maintenance requirements specified to be provided by the manufacturer for the defined
operating environment.
6.4.5 Existing Equipment Modification
The modification of in service equipment by either partial change or replacement requires
management in accordance with defined configuration management practices. Such
changes should be subject to Engineering Change Request (ECR) action as defined in
the Configuration Management Policy Manual. The requirement for maintenance
analysis is a defined change impact assessed during the development of the ECR.
Any necessary MRA action should be undertaken by the party accountable for designing
and validating the modification to ensure cost effectiveness and accountability.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
6.4.6 Maintenance Reviews
Reviews of maintenance requirements may be either:
pro-active, that are initiated by management as a result of performance monitoring
of data provided from sources such as a computerised maintenance management
system, or
reactive, that respond to initiating events such as high consequence failures,
changes to level of use or need, changes to maintenance task techniques and
costs, or changes to system configuration through introduction of new equipment.
6.4.7 Pro-active Reviews
Pro-active reviews apply top down quality management practices of monitoring and,
where possible, benchmarking performance indices such as:
Cost of ownership
Ratios of conditional failures versus functional failures
Ratios of preventive versus corrective maintenance
System availability derived from equipment reliability and maintainability data.
Other maintenance related performance data
These reviews assess the suitability of the current maintenance program by assessing
the assumptions and data used to establish the present maintenance requirements. The
assessment establishes whether system performance can be improved through
maintenance action or whether a change in equipment configuration by either
modification or replacement is necessary and cost effective.
Reviews of maintenance requirements should focus on the completeness and accuracy
of the assumptions as the primary driver of task criticality, task frequency and task
packaging criteria. The reviews should be conducted on a regular basis and be part of a
defined continual improvement program.
6.4.8 Reactive Reviews
Reactive reviews flow from significant changes in the drivers of maintenance
requirements. These include:
Business requirements such as level of service.
Operational requirements such as rate of effort and required utilisation.
Technical performance such as critical one off system or equipment failures.
Maintenance performance such as rapidly increasing failure rates for particular
equipment types.
Reactive reviews follow the standard MRA practices but in a more narrowly focused
manner to determine just the particular maintenance policy changes necessary to
manage the defined problem.
Failure reporting and corrective action systems (FRACAS) provide a standardised
method for applying reviews of maintenance policy as the first step in the development of
solutions to a particular maintenance problem.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED

7 Analysis of Safety Critical Items
7.1 Introduction
This section supports the RailCorp Asset Management Policy Manual with an outline of a
possible process available for addressing Safety Critical Items. This section is not
intended to be a definitive reference on how to perform analysis of safety critical items,
but to provide an overview of possible process.
A safety critical failure is defined as A loss of a function or secondary damage resulting
from a given failure mode which produces a direct adverse effect on safety.
43

7.1.1 Quantitative Risk Assessment
In establishing a quantitative risk model for the safety critical fault being analysed the
following steps need to be completed to establish a basic cause / consequence diagram.
a) Establish fault tree structure for safety critical fault event. This should include
both equipment and human elements/events, and the logical relationships
(AND, OR etc) between the events for progression to the next higher level
event. All assumptions should be clearly stated and documented.
b) Collect output data from RCM analysis, or other data sources, to establish the
equipment related failure probabilities in the fault tree.
c) Collect human event failure data for human related exposure / failure
probabilities in the fault tree.
d) Establish safety critical event probability.
e) Establish realistic scope of consequences flowing on from safety critical event.
f) Establish relative probabilities of each consequence.
g) Establish exposure rates of each consequence.
h) Compare exposures to available risk standards.
i) If the results present an unacceptable risk, identify which elements of the cause
/ consequence tree can be managed to reduce the probability of occurrence of
the event represented by the element. Repeat process until acceptance control
measures have been identified.
j) Obtain independent audit of the solution.
k) Implement and then monitor failure rates and success of control measures.
l) Audit control measures and processes.
m) Regularly revisit model as new data becomes available.



43
MIL-STD-2173(AS), p5
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
7.1.2 Documentation
The analysis documentation, whether electronic or paper, must provide the justification
and traceability for all data and decisions. The particular details of what data has been
collected against each item in the fault tree will also provide the details needed to
complete each field in sufficient detail to allow systems engineers today or 20 years
hence to understand completely the reason for the existence of each and every element
without conducting a reverse engineering exercise or redoing the analysis.
Any necessary caveats regarding the accuracy of information used, or assumptions
made, should be included with the analysis documentation associated with each element.
7.1.3 Suggested Readings & References
The following are suggested additional readings for this section.
Standard or Reference Name Page Numbers
AS 4360 Risk Management All
IEC 61025 Ed. 1.0 b Fault tree analysis (FTA), ed. 2 All
MIL-STD-2173(AS) 5

RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
Appendix A Packing Guidelines
PACKING GUIDELINES
INFRASTRUCTURE SERVICING SCHEDULE DEVELOPMENT
General Packaging Guidelines
Packaging of an Infrastructure Based System of servicing schedules(such as signalling,
electrical and civil in the rail industry) is normally a two step process involving the
packaging of tasks at a single frequency against a particular piece of equipment and then
the assembling of those packages into standard work packages to be applied to a
particular geographic area.
These two steps are shown at Figure 68 and Figure 69.
Examples of the guidelines used for rolling stock and infrastructure maintenance analysis
follows:
ROLLINGSTOCK SERVICING SCHEDULE DEVELOPMENT
PACKAGING GUIDELINES
Introduction
The application of RCM analysis to a rail vehicle will provide a comprehensive list of
preventive maintenance tasks that must be assembled into work packages. This task
requires that constraints are identified and advised to those responsible for the packaging
process
Constraints
The following constraints are to be used in assembling the rail vehicle servicing schedule
packages:
Maintenance windows are to be no less than the present allocated target for the GI
servicing (4 hours)
Schedules are to be equalised (ie equal time) except where extensions to short
time servicing activities will jeopardise vehicle availability.
Current staff structures and work responsibilities are to be retained
Tasks to be sequenced on the basis of separate schedules being applied to a four
car set for Type 1 vehicle and a two car set for Type 2 vehicles.
No significant corrective maintenance is to be undertaken by the allocated
servicing team.
All depots will use the same schedule structure to ensure task consistency in the
case of vehicle transfers between depots.
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




STEP 1
Tasks 1 3 6 12
xxxxxxxxxx
xxxxxxxxxx
xxxxxxxxxx
xxxxxxxxxx
xxxxxxxxxx
xxxxxxxxxx
xxxxxxxxxx
xxxxxxxxxx
x
x
x
x
x
x
x
x
Basic Task
Yearly
Schedule
Three Yearly
Schedule
xxxxxxxxxx
xxxxxxxxxx
xxxxxxxxxx
xxxxxxxxxx
xxxxxxxxxx
xxxxxxxxxx
xxxxxxxxxx
xxxxxxxxxx
xxxxxxxxxx
Years

Figure 68 - Creation of aggregated tasks into schedules
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED
RailCorp Engineering Manual Integrated Support
Maintenance Requirements Analysis Manual




STEP 2
*******************
*******************
*******************
*******************
*******************
Technical
Plan
A
B
C
A Items A to D
Legend:
List of servicing
D
Amalgamated program of work to include the
servicing schedules of identified items in a
geographic work area.

Figure 69 - Creation of item specific servicing schedules
RailCorp
Issued J uly 2010 UNCONTROLLED WHEN PRINTED

Das könnte Ihnen auch gefallen