Beruflich Dokumente
Kultur Dokumente
Lab3
Lab6
Lab9
Lab12
Lab15
Lab18
Lab21
Lab24
Lab27
Ldescription
Asbestos_Foreman
Asbestos_Worker
Aspestos_Apprentice
Blast_Foreman
Brick_Layer
Brick_Layer_Foreman
Brick_Layer_Helper
Carpenter
Carpenter_Foreman
LtotalRate LbasicRate
46.531
29.45
45.741
28.95
36.577
23.15
35.155
22.25
41.633
26.35
44.793
28.35
32.232
20.4
40.922
25.9
44.082
27.9
Res.:
Carpenter
40.922
Formula based on ceated names of the
Range B1:D10 has been selected and
Direct formulas:
25.9 label names (limited to this sheet only) - wo
25.9 lookup
Input Data
Important Functions:
Vlookup
Match
Index
Offset
Array functions (Use shift, Ctrl, & Enter)
Countif
Sumif
Field:
LtotalRate
a based on ceated names of the table
B1:D10 has been selected and name created
Estimate:
Resource
L6
No.
3.00
Cost/hr
43.53
Total Cost/hr
130.59
Notes:
1. The database starts with field names in row 8. One blank row (7) is needed to separate the database.
2. For large tables, use the "Window-Split" and "Window-Freeze Panes" menu options at cell A9.
3. The "Data" menu provides simple tools for data-entry, sorting, and filtering the data, etc.
4. Shaded cells contain formulas that can be copied from one row to the other.
5. The formula in C9 is "=D9 * 1.58", as an average adjustment to the basic rate, for workers' compensation, overhead & profit, etc.
6. The "Data-Form" menu option is a useful data-entry tool that copies calculation cells automatically.
Code
L3
Description
Carpenter
L6
L9
Equip._Oper._Medium
Laborer
Rate/hr
41.79
BasicRate
26.45
43.53
32.63
27.55
20.65
Avail
Description
Equip._Oper._Medium
Total Rate/hr($)
Code
L6
Total
43.53
Description
Dozer_224_Kw
Elev. Scraper, 8.4 m3
Gas_Eng._Power_Tool
Rate/hr
154.99
91.74
9.22
BasicRate
140.90
83.40
8.38
Avail
Notes:
Code
Description
CRA-01 Crew CRA-01
CRB-33F Crew CRB-33F
CRC-01 Crew CRC-01
Rate/d NoR1
334.76
1.00
1609.698 1.00
1264
3.00
Res1
L9
L6
L3
NoR2
1.00
0.50
1.00
L6
E3
CRC-01
Description
Selection:
L6
E3
$Res1
32.63
43.53
125.37
$Res2
9.22
16.31
32.63
$Res3
0.00
10.88
0.00
$Res4
0.00
91.74
0.00
$Res5
0.00
38.75
0.00
Avail
Notes: 1. The "Avail" field can be used to link this table to other inventory sheets.
2. Notes 1, 2, 3, 4, and 6 in the "Labour" sheet apply to this sheet.
3. An average 10% is added to the Basic$/Unit for overhead and profit.
4. Material costs include delivery to the site. No sales tax included or allowance for wasted material.
Code
M3
M6
M9
Description
Plywood, 1use in wall forms
Plywood, 2uses in wall forms
Tiles
Cost/Unit
28.05
15.51
32.40
Basic$/Unit
25.50
14.10
29.45
Unit
m2
m2
Pack
Avail
Code
S3
S6
S9
Description
Brickwork-Simco Ltd.
Concrete Masters Inc.
Excavation-Earth Movers Inc.
Cost/Unit
33.00
165.00
3.85
SubCost
30
150
3.5
Unit
m2
m3
m3
Selection:
Notes: 1. Select a CREW (or a SUB) and a MATERIAL using the comboboxes, then copy their code
CRC-01
Crew
M3
M3
Material
S3
S3
Sub
CRC-01
Code
Description
Crew
Sub RegPr/d MatQ Material Hrs/d OTadj MatCost CrewCost SubCost WinProd SprProd FallProd
334.76
287.00
1.17 m3
CRA-01
287.00
1,609.70
528.00
3.05 m3
CRB-33F
2,092.61
646.80
3.24 m3
CRB-33F
2,695.00
700.00
CSI-031-158-0010 Form-Foot.-Wall-Ply-1use
2,241.26
34.84
3.85 m3
64.33 m2CA CRC-01
S9
8.00
8.00
0.00
334.76
0.00
0.80
1.00
0.90
528.00
8.00
8.00
0.00
1,609.70
0.00
0.70
1.00
0.90
528.00
10.00 10.40
0.00
2,092.61
0.00
0.70
1.00
0.90
0.00 2,695.00
0.70
1.00
0.90
0.50
1.00
0.90
700.00
34.84
34.84
M3
8.00
8.00
0.00
8.00
8.00
977.26
1,264.00
0.00
(a) Pivot Table Report For Bid Proposal (Data of Part A).
Bid Details
Task (WBS3)
Excavation
Item
Item_Description
Quantity
Unit
Unit Price
Item1
1250.00
m^3
0.93
1166.41
Data
Total
5.50
6875.00
Duration1
2.55
8041.41
Duration2
2.76
13672.25
Duration3
3.38
13672.25
Cost($)1
6875.00
Item1 Total
Item2
Concrete Basement
310.00
m^3
44.10
Item2 Total
Item4
1250.00
m^3
1.04
Total
1296.01
Cost($)2
5777.36
Item4 Total
1296.01
Cost($)3
5444.05
Grand Total
23009.68
Excavation
7000.00
WBS2
Area1
WBS3
(All)
OBS
(All)
Cost ($)
6500.00
WBS1
6000.00
5500.00
Sum of TotalCost
Item
Item_Description
Item_Q
Item_U
Item1
1250.00
m^3
8041.41
Item2
Concrete Basement
310.00
m^3
13672.25
Grand Total
Total
21713.66
5000.00
2.00
2.50 (days)
Time
Time-Cost Relationship
3.00
3.50
Notes:
Estimate Sheet
Location: Place1
Item
Desc.
WBS3
OBS
Excavation
Mark Sarena
1,250
m^3
Civil
Area1
1,250
m^3
Civil
310
m^3
Civil
1,250
m^3
Civil
Peter Rofai
Selection:
sk1 to Task5).
"Labour" sheet apply here.
Table-Reports.
Q1
Method2
Q2
Method3
Q3
Method
PlanMonth ContUC
5.50
Compac.-300mm 1,000
lifts, 3passes
0.93
Form-Foot.-Wall-Ply-1use
200
44.10
Compac.-300mm 1,000
lifts, 3passes
12
1.04
TotalCost
SelectedTask
6,875.00
1,166.41
13,672.25
1,296.01
Form-Foot.-Wall-Ply-1use
Compac.-300mm lifts, 3passes
UniqueTaskName
Units
1,250
m3
1,000
m3
200
1,000
m2CA CRC-01
m3
CRA-01
M3
Note:
UnitC
700.00
8.00
0.00
6,875.00
0.00
1.79
0.70
2.55
6,875
5.50
287.00
8.00
1,166.41
0.00
0.00
3.48
1.00
3.48
1,166
1.17
34.84
8.00
8,062.25
0.00 5,610.00
5.74
0.90
6.38
13,672
68.36
287.00
8.00
1,296.01
0.00
3.48
0.90
3.87
1,296
1.30
0.00
Task (WBS3)
Cost1
Dur1
Cost2
Dur2
Cost3
Dur3
Excavation
6,875.00
2.55
5,777.36
2.76
5,444.05
3.38
Compaction
1,166.41
3.48
0.00
0.00
0.00
0.00
Wall Forms
13,672.25
6.38
0.00
0.00
0.00
0.00
Compaction
1,296.01
3.87
0.00
0.00
0.00
0.00
UniqueTaskName
L3
L6
L9
E3
0.00
0.00
0.00
0.00
0.00
0.00
1.00
0.00
3.00
0.00
1.00
0.00
0.00
0.00
1.00
0.00
E6
E9
SelectedTask
PlanCost
PlanDuration
PlanUC
0.00
0.00
6,875.00
2.55
5.50
0.00
1.00
1,166.41
3.48
1.17
0.00
0.00
Form-Foot.-Wall-Ply-1use
13,672.25
6.38
68.36
0.00
1.00
1,296.01
3.87
1.30
ntract items.
PlanPr/d
ActualC
ActualDur
Pcond
Mcond
ActualUC
ActualPr/d
490.00
5500.00
3.00
Good
Good
4.40
416.67
287.00
2000.00
5.00
Fair
Fair
2.00
200.00
31.36
8000.00
8.00
Fair
Fair
40.00
25.00
258.30
2000.00
5.00
Fair
Fair
2.00
200.00
Contract Items
Contract_Item_Desc
PlanUC
ActualUC
5.50
4.40
0.93
1.60
44.10
25.81
1.04
1.60
Concrete Basement
Excavation, New Building
Item
Item1
Item2
Grand Total
Item_Description
Quantity
Unit
Unit Price
Total
1250.00
m^3
0.93
1166.41
5.50
6875.00
8041.41
Concrete Basement
310.00
m^3
44.10
13672.25
13672.25
1250.00
m^3
1.04
1296.01
1296.01
23009.68
7000.00
Civil
Area1
6000.00
(All)
(All)
5500.00
f TotalCost
Item_Description
Item_Q
Item_U
1250.00
m^3
8041.41
Concrete Basement
310.00
m^3
13672.25
Total
5000.00
2.50 2.60 2.70
21713.66
Excavation
Data
Total
Duration1
2.55
Duration2
2.76
Duration3
3.38
Cost($)1
6875.00
Cost($)2
5777.36
Cost($)3
5444.05
Excavation
7000.00
6500.00
6000.00
5500.00
5000.00
2.50 2.60 2.70 2.80 2.90 3.00 3.10 3.20 3.30 3.40 3.50
Time-Cost Relationship
Sum of Values
Row
Compac.-300mm lifts, 3passes
Form-Foot.-Wall-Ply-1use
Excav.(a) Bulk, Sand&Gravel
Excav.(b) Bulk, Sand&Gravel
Excav.(c) Bulk, Sand&Gravel
Column
Cost /d
334.76
2241.26
1609.70
2092.61
2695.00
Sum of Value
Contract Item
Page1
Estimate1
Excav.(c) Bulk, Sand&Gravel
Estimate2
Estimate1
Compac.-300mm lifts, 3passes
Estimate2
Estimate1
Form-Foot.-Wall-Ply-1use
Estimate2
TotPr /d
287.00
34.84
528.00
646.80
700.00
Column
ActualUC
4.40
4.40
4.00
4.00
40.00
40.00
PlanUC
5.50
5.50
2.46
2.46
68.36
68.36
(All)
Average of Value
Row
Compac.-300mm lifts, 3passes
Excav.(c) Bulk, Sand&Gravel
Form-Foot.-Wall-Ply-1use
Column
ActualC
2000.00
5500.00
8000.00
ActualDur
5.00
3.00
8.00
ActualPr/d
200.00
416.67
25.00
PlanCost
1231.21
6875.00
13672.25
PlanDuration
3.68
2.55
6.38
PlanPr/d
272.65
490.00
31.36
ActualDur
5.00
5.00
5.00
3.00
3.00
3.00
8.00
8.00
8.00
ActualPr/d
200.00
200.00
200.00
416.67
416.67
416.67
25.00
25.00
25.00
PlanCost
1231.21
1231.21
1231.21
6875.00
6875.00
6875.00
13672.25
13672.25
13672.25
PlanDuration
3.68
3.68
3.68
2.55
2.55
2.55
6.38
6.38
6.38
Dur2
0.00
0.00
2.76
Cost3
0.00
0.00
5444.05
Dur3
0.00
0.00
3.38
Page1
Estimate1
Estimate2
Estimate1
Estimate2
Estimate1
Estimate2
Form-Foot.-Wall-Ply-1use Average
Column
ActualC
2000.00
2000.00
2000.00
5500.00
5500.00
5500.00
8000.00
8000.00
8000.00
(e) Tasks' Average Time-Cost Relationships Across Projects (Data of Part C).
Page1
Estimate1
Average of Value
Row
Compaction
Wall Forms
Excavation
Column
Cost1
1231.21
13672.25
6875.00
Dur1
3.68
6.38
2.55
Cost2
0.00
0.00
5777.36
PlanPr/d
272.65
272.65
272.65
490.00
490.00
490.00
31.36
31.36
31.36