Sie sind auf Seite 1von 102

Governing document Classification: Internal

Field instrumentation















Project development (PD)
Technical and professional requirement, TR3032, Final Ver. 3, valid from 2011-08-15
Owner: Leader Maintenance Automation
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore


Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 2 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore






1 Objecti ve, target group and provision ............................................................................................................... 4
1.1 Objective.................................................................................................................................................... 4
1.2 Target group .............................................................................................................................................. 5
1.3 Provision .................................................................................................................................................... 5
2 General requirements .......................................................................................................................................... 6
2.1 Standardisation.......................................................................................................................................... 6
2.2 Engineering units ....................................................................................................................................... 6
2.3 Utilities........................................................................................................................................................ 6
3 Design requirements............................................................................................................................................ 9
3.1 General ...................................................................................................................................................... 9
3.2 Wireless field devices .............................................................................................................................. 10
3.3 Environment ............................................................................................................................................. 10
3.4 Heat tracing.............................................................................................................................................. 10
3.5 Purging Systems...................................................................................................................................... 12
3.6 Weather protection .................................................................................................................................. 12
3.7 Local Control Panel (LCP)....................................................................................................................... 13
3.8 Electromagnetic compability.................................................................................................................... 14
3.9 Ex protection............................................................................................................................................ 14
3.10 Degrees of protection .............................................................................................................................. 15
3.11 Material .................................................................................................................................................... 15
3.12 Signal types ............................................................................................................................................. 18
3.13 Provision for future modifications ............................................................................................................ 19
3.14 Instrument tubing and fittings .................................................................................................................. 19
3.15 Measurement uncertainty........................................................................................................................ 21
4 Installation design requirements ...................................................................................................................... 23
4.1 Equipment location .................................................................................................................................. 23
4.2 Field architecture and segregation.......................................................................................................... 24
4.3 Installation of wireless instrumentation.................................................................................................... 24
4.4 Tubing installation.................................................................................................................................... 24
4.5 Thermal Insulation ................................................................................................................................... 26
4.6 Winterisation ............................................................................................................................................ 26
4.7 Temperature instruments ........................................................................................................................ 27
4.8 Level instruments..................................................................................................................................... 27
4.9 Flow instruments...................................................................................................................................... 28
4.10 Fire & Gas equipment.............................................................................................................................. 29
5 Field instruments................................................................................................................................................ 32
5.1 General .................................................................................................................................................... 32
5.2 Temperature measurement ..................................................................................................................... 33
5.3 Flow measurement .................................................................................................................................. 34
5.4 Pressure measurement ........................................................................................................................... 40
5.5 Level measurement ................................................................................................................................. 40
5.6 Fire and gas detection ............................................................................................................................. 43
5.7 Manual callpoint ....................................................................................................................................... 44
5.8 Online analyser system........................................................................................................................... 44
6 Final control elements ....................................................................................................................................... 49
6.1 On/off valves............................................................................................................................................ 49
6.2 Control valves .......................................................................................................................................... 49
6.3 Instrumentation ........................................................................................................................................ 49
6.4 Actuator requirements ............................................................................................................................. 50
7 Additional information ....................................................................................................................................... 53
7.1 Definitions and abbreviations .................................................................................................................. 53
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 3 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





7.2 Changes from previous version............................................................................................................... 54
7.3 References............................................................................................................................................... 55
App A Installation typicals ............................................................................................................................................ 58
A.1 Capillary and diaphragm seal arrangement ............................................................................................ 61
A.2 Differential pressure transmitter with capillary and diaphragm seal ....................................................... 62
A.3 DP level transmitter, capillary type.......................................................................................................... 63
A.4 Pressure transmitter with capillary and diaphragm seal ......................................................................... 64
A.5 Pressure transmitter gas service............................................................................................................. 65
A.6 Pressure transmitter gas service............................................................................................................. 66
A.7 Pressure transmitter gas service heat traced.......................................................................................... 67
A.8 Pressure transmitter liquid/gas cryogenic ............................................................................................... 68
A.9 Pressure transmitter liquid service .......................................................................................................... 69
A.10 Differential pressure transmitter liquid service..................................................................................... 70
A.11 Differential pressure transmitter liquid service..................................................................................... 71
A.12 Differential pressure transmitter liquid service heat traced.................................................................. 72
A.13 Differential pressure transmitter steam service.................................................................................... 73
A.14 Differential pressure transmitter gas service........................................................................................ 74
A.15 Differential pressure transmitter gas service........................................................................................ 75
A.16 DP pressure transmitter capillary type .................................................................................................... 76
A.17 Pressure gauge........................................................................................................................................ 77
A.18 Pressure gauge- gas service................................................................................................................... 78
A.19 Pressure gauge Gas heat traced ......................................................................................................... 79
A.20 Remote pressure gauge liquid/gas cryogenic......................................................................................... 80
A.21 Pressure gauge steam service............................................................................................................. 81
A.22 Air distribution of manifold w/consumer................................................................................................... 82
A.23 Hydraulic distribution w/consumer........................................................................................................... 83
A.24 Hydraulic distribution w/consumer........................................................................................................... 85
A.25 Instrument support housed instrument................................................................................................. 87
A.26 Instrument support platform mounted .................................................................................................. 88
A.27 Instrument support system local analyser system............................................................................... 89
A.28 Instrument support gas detector........................................................................................................... 90
A.29 Instrument support gas detector........................................................................................................... 91
A.30 Instrument support gas detector........................................................................................................... 92
A.31 Instrument support flame detector........................................................................................................ 93
A.32 Instrument support flame detector........................................................................................................ 94
A.33 Instrument stand...................................................................................................................................... 95
A.34 Wall mounted instrument stand with plate .............................................................................................. 97
A.35 Wall mounted instrument stand............................................................................................................... 99
A.36 Instrument enclosure ............................................................................................................................. 101


Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 4 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





1 Objective, target group and provision
1.1 Objective
This document states functional and technical requirements related to field instrumentation components and
systems part of automation technology competence area.

TR3031 defines the automation technology competence area and states general requirements.

Technical requirements for junction boxes, glands, cables, cable trays, cable ladders and earthing are stated in
TR3023 and TR3024.

Technical requirements for Remote I/O cabinets and field termination cabinets are stated in TR3034.

Technical requirements for pressure relief valves, pilot operated relief valves and bursting discs are stated in
TR3014.

Technical requirements for HVAC actuators are stated in TR1562.

Technical requirements for vibration systems on rotating machinery are stated in TR3132.

Actuator control panel typicals for on/off valves are given in TR0038.

Life Cycle Information (LCI) such as document formats and document types are stated in TR2381.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 5 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore






GL3032 (Hold) is the field instrument guideline for selection between the various measurements principles. This
information is extensive and shall be further discussed with Company and equipment Suppliers before a
decision on the most appropriate measurement technology is made.
1.2 Target group
The target group for this TR is:
System and discipline responsible personnel within HSE, automation, operation and maintenance,
process control, IT, security and safety systems, project management, drilling and well technology
All personnel involved with design, operation, maintenance or modifications of plant technical
systems.
Suppliers and Vendors
1.3 Provision
This document is provided for in Automation, Technical Requirements and Standards (TR3030).
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 6 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





2 General requirements
2.1 Standardisation
Field instrumentation components shall be standardised throughout the installation to a limited number of types,
and preferably one manufacture for each component type unless otherwise accepted by the Company.
Standardization requirements shall not eliminate the possibilities of utilizing new technology where appropriate.

Technical design solutions shall be uniformed and a limited number of variants shall be used.

Field instruments installed outside of hazardous areas should be of the same type as those installed inside
hazardous area for the purpose of standardisation, unless their quantity may justifies different stock.

Only one make of instrument tubing compression fitting and sealing compounds shall be used throughout the
installation.
2.2 Engineering units

The following engineering units shall be used, unless alternate units are stated by project specific documents:

Table 1 - Engineering units
Physical property Unit
Pressure bar, mbar, barg, bara where
Bara = Absolute pressure is zero referenced
against a perfect vacuum, so it is equal to gauge
pressure plus atmospheric pressure.
Barg = Gauge pressure is zero referenced against
ambient air pressure, so it is equal to absolute
pressure minus atmospheric pressure.
Bar or mbar = Differential pressure is the
difference in pressure between two points.
Level mm, % for indication
Volume flow m
3
/h (flowing condition), Sm
3
/h (standard condition
according to ISO 1000)
Mass flow kg/h
Temperature C
Other According to ISO 1000

2.3 Utilities
2.3.1 Instrument air supply
Instrument air for field instruments including accessories and pneumatic control devices shall be segregated
from other consumers (e.g. plant air), and have priority in the air distribution network.

Nominal air distribution pressure shall be 7 barg. Maximum pressure 12 barg and minimum pressure 5,5 barg,
measured at consumer location.
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 7 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore






The compressed air system shall include receiver and distribution system. The system shall have enough
capacity to serve consumers without fluctuations in supply pressure and provide for a minimum of 20% future
users.

Each consumer shall be supplied with a separate filter regulator and isolation valve. Air manifolds shall be
provided with a drain isolation valve at lowest point.

The dew point of the gas supplied shall be at least 10 C below the lowest ambient temperature present at the
plant. The dew point shall be based on maximum operating pressure.

The supply shall be basically free from contaminations in form of hydrocarbons and solids. Quantity of solid
particles should be less than 0.1 g/m
3
and no particle shall be greater in diameter than 3 m.

For additional guidelines refer to ANSI/ISA 7.0.01, Quality Standard for Instrument Air.
2.3.2 Hydraulic supply
The plant shall supply hydraulic fluid for hydraulic control devices. The system shall contain supply and return
distribution to each consumer.

The hydraulic system including distribution shall have enough capacity to serve consumers without fluctuations
in supply pressure, and shall be equipped with central accumulator capacity to activate all connected
consumers minimum once without use of any hydraulic power source. The hydraulic reservoir shall be sized
such that, when all actuators are driven, the tank shall not be less than 25% full. When the actuators are
returned, the reservoir level shall not be greater than 75%. Provision for expansion of central accumulator
capacity shall be included. Measures for avoiding humidity in the system shall be included. The hydraulic
system distribution should be designed to allow for flushing of tubing to end devices, not including valve control
panel and actuator.

The nominal hydraulic distribution pressure shall be 200 barg. The maximum pressure shall be 210 barg and
the minimum pressure 160 barg, measured at consumer location.

Hydraulic supply requirements for special applications, e.g. reservoir downhole valves, shall be derived from
case by case studies, per the project requirements.

The supply system for hydraulic control panels for valves shall be independent and segregated from other
hydraulic supply systems such as for doors, hatches and winches to avoid cross contamination of the control
panels.

The hydraulic fluid shall have cleanliness as ISO4406 code of --/15/12 or better.
2.3.3 Electrical supply
2.3.3.1 General
Requirements stated below apply for facilities according to TR3021 and TR3022, as applicable. For other
locations local regulations shall apply. Standard line voltages may differ (e.g. for Canada and GoM, line AC
voltage is 120VAC, 60Hz).

Table 2 -Electrical supply for field equipment
Components Supply
Instrument panels in LER 230 V AC 50 Hz (standard) or 24 VDC
Field instruments 24 V DC (standard) or 230 VAC 50 Hz
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 8 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





Components Supply
Instrument field panels 24 V DC (standard) or 230 VAC 50 Hz


A minimum of two independent and redundant power supplies shall be used to power instrument systems.
Non-critical field instruments with external power may be powered from a single supply 230 VAC 50 Hz.

24 VDC shall be derived from the 230 VAC supply.

Critical systems/safety related systems shall be supplied with dual power (2 X UPS), including dual DC power
supplies within user equipment cabinets. TR3124 is refered to for UPS requirements.

DC power supplies should be of hot-swap design.

Segregation, redundancy, and individual isolation shall be ensured throughout the 230 VAC / 24 VDC
distributions.

Special attention shall be paid to inrush current of power supplies.
2.3.3.2 24 V DC Distribution System
24 VDC supply shall be floating and adjustable within the range of 24 - 28 VDC.

If earthing of a pole of 24 VDC voltages is required, the Instrument Earthing (IE) system shall be used.

Earth fault and power fault monitoring shall be implemented in the 24 VDC distribution systems.

All power supplies shall be equipped with a common alarm contact (open contact in case of trip).
2.3.3.3 Spare Capacity
All power supplies shall have at least 30% spare capacity with the system fully equipped and at worst working
condition.

All 24 V DC distributions shall contain MCBs with necessary numbers of circuits (10% spare to be included).

Input / Output cards and individual field instruments shall generally use fused power feeds.
2.3.3.4 Other electrical sources
Use of other electrical sources, e.g. batteries for wireless instruments, shall be qualified for the application.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 9 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





3 Design requirements
3.1 General
Instruments that can not be justified to cover a defined need or use shall be avoided.

Local gauges shall be provided facilitate local start-up and monitoring and to assess basic process status in the
event of control system failure and possible local venting actions.

Field transmitter output signal loop shall be floating.

Field instruments should be loop powered directly from I/O card. Active or passive input should be defined in
the project hardware typicals.

Any arrangement of instruments shall allow for the removal of a sensor/detector head while maintaining the
integrity of the other sensors, e.g. in addressable systems like fieldbus systems, wireless systems, smoke
detectors.

Galvanic isolation barriers shall be used for IS signals. These barriers should have full smart signal transmission
capability.

Electrical/electronic equipment in panels shall be protected against hydraulic leakage (e.g. leakage point such
as fittings on hydraulic lines should not be placed so that the electronic equipment can be exposed to the fluid
leak).

Instrument impulse lines that can be clogged due to high viscosity fluids, hydrates or other factors, shall have
the instrument close-coupled to the process pipeline/equipment. Alternatively, the instrument shall be protected
with a remote seal, provided that accuracy and response time are acceptable.
Remote seals shall also be used to protect the instrument when the heat required to keep the process fluid in a
free flowing state is greater than the design temperature limitation of the instrument.
Care shall be taken to ensure that the seal fluid will operate within the required temperature range and that it is
compatible with the process. The seal fluid shall be nonflammable, have low vapour pressure and low thermal
expansion characteristics. Should a diaphragm rupture occur, be compatible with and non-contaminating to the
process and the operating environment.
Diaphragm seals may present accuracy problems at pressures less than 2 barg and shall not be used if the
required accuracy can not be attained.
2/5 way valve manifold functionality shall be available when remote seal is used.

Each pressure instrument with process connection shall be fitted with instrument block /bleed manifold.
Pressure instruments shall be fitted with a 2-way valve manifold. DP pressure instruments shall be fitted with a
5-way valve manifold.

Locking devices for latching in open position should be considered for for instrument block valves when field
instrument is part of a safety function (ESD/PSD).

Full functional independence between control and safety devices shall be assured, including vessel/pipeline
connections. Common pressure taps for control and safety devices shall not be used.
Common sources may be considered for gamma ray based control and safety function level measurements,
with prior Company approval.

Isolation valves for instrument air supply or for instrument hydraulic supply/return shall be clearly marked to
identify the consumer served by each valve.

Governing document: Field instrumentation Classification: Internal




Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 10 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





Field located enclosures and panels shall be equipped with drain nipples. Drain nipple should be placed at the
lowest point.

Field located enclosures and panels weighing more than 25 kg shall be equipped with lifting eyes.

For requirement regarding position securing system (interlock), reference is made to TR2315.
3.2 Wireless field devices
Wireless field devices are only qualified for monitoring applications. Use of wireless instrumentation for
applications other than monitoring shall require prior Company approval

The following requirements shall apply for wireless field devices:
Maximum latency (time from originator to gateway) should be of up to 40% of the update rate or up to
maximum of 3 seconds
Battery lifetime should be a minimum of 5 years with the specified update rate
Alarm for reduced battery life time/health should be transferred to SAS
Radio transmission range should be a minimum of 50 meters

The wireless networks shall have redundant gateways. Each pair of redundant wireless gateways shall be
connected to one logic solver.

Existing Wireless HART gateways should handle a minimum of 25- 30 messages per second.
The recommended number of devices connected to one gateway should be limited to 50 sensors. (Consult also
Manufacturer recommendations.)
3.3 Environment
Field devices and commodity items shall be designed for operation in the actual ambient and process
environment given in the project design basis.
3.4 Heat tracing
3.4.1 General
External heat tracing of instrument impulse lines, level bridles and wetted parts where required, should be
electrical. (ref. TR3021 and TR3022.).

The selection of other types of heat tracing method will be subject to the availability of a suitable heating
medium and the particular application.

Heat tracing shall be designed and installed so as not to interfere negatively to measurement results. (E.g.
temperature and volume measurements of fluids or gas)

Use of pre-insulated heat trace tubing shall be preferred.

Heat tracing that shall be provided for instruments and instrument piping in services have the following
characteristics:

1. The contained or conveyed fluid has a freezing point above the project design low ambient temperature;
2. The relevant properties of the fluid would interfere with the instrument response at or near the project
design low ambient temperature;
3. Water vapour or hydrate formation within the fluid could condense, solidify, promote corrosion, or
otherwise result in faulty instrument response or premature instrument failure; or,
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 11 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





4. Instrument calibration or operation is temperature sensitive.

3.4.2 Glycol Tracing
Glycol tracing of instruments and lead lines shall use tubing and fittings with project specified dimensions and
material. Where stainless steel tubing is in contact with insulation, chloride-free insulation shall be specified to
prevent stress corrosion cracking of the tubing.

A separate glycol supply shutoff valve shall be installed in the tracer supply line for each instrument. It is
recommended that glycol feed and return tubing be run to each instrument in systems of tube bundles from
takeoff points on the headers. Each takeoff point should be valved and tagged with the instrument number
served by that takeoff.

When the temperature of the tracing glycol exceeds the design temperature of the instrument or connecting
lines, then the process liquid may vaporize in the connecting line, or the corrosion rates may increase greatly.
One of the following should be done to prevent this:

1. The tracing tubing should be separated from the instrument and/or connecting lines by insulating blocks
or pipe insulation.
2. Glycol should be used at a lower temperature.
3. Smaller size tracer tubing should be used..

Where maximum heating effects are desired, the glycol tracing shall be in direct contact with the impulse lines
or instrument (heavy tracing). However, the maximum recommended temperature limits of the Manufacturer
shall not be exceeded.
3.4.3 Steam Tracing
Unless otherwise specified, low pressure saturated steam shall be provided for use in instrumentation steam
tracing as follows:

Table 3 - Instrumentation steam tracing
Process Design Mechanical Design
Temperature (C) 150 175
Pressure (Barg) 2,5 5,0


Steam tracing of instruments and lead lines shall use tubing and fittings with project specified dimensions and
material. Where stainless steel tubing is in contact with insulation, chloride-free insulation shall be specified to
prevent stress corrosion cracking of the tubing.

A separate steam supply shutoff valve and condensate trap shall be installed in the tracer supply line for each
instrument. It is recommended that steam and condensate tubing be run to each instrument in systems of tube
bundles from takeoff points on the headers. Each takeoff point should be valved and tagged with the instrument
number served by that takeoff.

Steam traps shall be of the inverted-bucket type.

When the temperature of the tracing steam exceeds the design temperature of the instrument or connecting
lines, then the process liquid may vaporize in the connecting line, or the corrosion rates may increase greatly.
One of the following should be done to prevent this:

1. The tracing tubing should be separated from the instrument and/or connecting lines by insulating blocks
or pipe insulation.
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 12 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





2. Steam should be used at a lower pressure and temperature.
3. Smaller size tracer tubing should be used.

Where maximum heating effects are desired, the steam tracing shall be in direct contact with the impulse lines
or instrument (heavy tracing). However, the maximum recommended temperature limits of the Manufacturer
shall not be exceeded.
3.4.4 Heat Using Process Flow
Radiant heat from the process flow line may be used for protection of instruments where there is continuous
flow and the line temperature ranges between 15C and 65C.

The process line shall be bared around the location of the instrument and a weatherproof, insulated housing
shall be mounted to totally enclose the bare line and instrument.
3.5 Purging Systems
Purges shall be used when the process fluid would migrate through the seal fluid to the instrument or when
neither heat tracing nor diaphragm seals provide satisfactory results.

The purge fluid shall be a liquid when the process fluid is a liquid, and shall be a gas when the process fluid is a
gas. The purge fluid shall be clean, free of solids, and compatible with and non-contaminating to the process.
The temperature of the purge fluid shall not cause a change of state (i.e. flashing, condensation or solidification)
of the process or purge fluid.

The purge fluid pressure shall be sufficient to force a smooth, continuous flow through the process impulse lines
and into the main process stream. A purge rotameter (purge regulator) shall be installed and adjusted for a
continuous uniform purge flow.

The point of entry for the purge into the instrument lines shall be as close to the measurement connection as
practical.

If the instrument is a differential pressure type, then a purge rotameter shall be installed in each process
impulse line and adjusted so that the rotameters show equal flow. The transmitter zeroing valve in the
instrument manifold shall be open for this adjustment.

Purge systems do not always eliminate the need for heat tracing. Certain viscous streams require heat tracing;
not only for the instrument and its connections, but also for the line supplying the purge fluid.

It should also be noted that purge systems may also be used in high ambient temperature conditions. For
example, downhole well pressure in thermal heavy oil recovery schemes can often be achieved via the use of
gas purge systems (commonly referred to as bubble tubes).
3.6 Weather protection
3.6.1 General
If ambient conditions such as deluge, sun, wind, snow and sand can adversely affect the field instrumentation or
its functionality, then the instrument shall be sheltered by use of weather protection/protective shades, hoods or
enclosures.
3.6.2 Instrument enclosure design

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 13 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





Enclosures with electronic equipment, e.g. instrument transmitters, located such that changes in ambient
temperatures can cause internal problems such as condensation or freezing, shall be equipped with internal
heating elements or dehumidifiers, in order to prevent deterioration and failure of electronic components.

For electric tracing, an electric heater should be installed inside the enclosure. A self regulating temperature
controller or a thermostat shall be used. The heater and controller shall be installed in a manner that does not
hinder the removal of the instrument for calibration or maintenance. The heating system shall not promote
signal interference with the electronic instruments. .

Where glycol or steam tracing is used, heating shall be achieved by means of a tubing coil supplied and fitted
inside the enclosure by the housing Supplier. Such coils shall be installed in a manner that does not hinder the
removal of the instrument for calibration or maintenance.

Instrument enclosures for transmitters shall be large enough to accommodate the valve manifold.

Bulkhead unions for process gas service impulse tubing should be placed on the bottom of the enclosure.
Bulkhead unions for process impulse tubing for liquid service should be placed on the side of the enclosure.
Drain/vent from the instrument valve manifold should be through bulk head unions at the bottom of the
enclosure.

When transmitters with indication are mounted in enclosures, then the enclosures shall have window for easy
reading. Process tubing connections for calibration and maintenance shall be fitted outside the enclosure.
3.7 Local Control Panel (LCP)
3.7.1 General
See TR3131 for more information about requirements and control philosophy for equipment packages.

The preferred choice should be push-button based LCP with status lights / local indicators.

Signalling to and from a push-button based LCP shall be connected to the instrumented system and not directly
to or from field equipment.

Interactive touch screen panels may be used based on prior approval from the Company. Environmental and
operational aspects need to be addressed.

The LCP shall contain all necessary status information in order to achieve a safe and predictable operation, and
means to transfer the control mode to/from the central control room (local control / remote control switch).

The LCP should be fitted with adequate internal lighting. This lighting shall be suitable for the area classification
pertaining to the panel location. Activation of the internal panel lighting may be either manual of automatic,
linked to the door operation.

LCPs, except server cabinets, should be designed to avoid the need for cooling fans. Special considerations,
such as perforation of cabinet/doors and enforced cooling, shall be taken for server cabinets.

On floating facilities, doors shall self lock in the fully opened position.

Swing frames or logic solvers mounted in the door should be avoided. If used however, special consideration
should be made to robustness of cable connections and resistance to vibration and physical contact when
opening swing frame/doors.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 14 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





3.8 Electromagnetic compability
Electrical powered devices shall comply with IEC61000 with respect to both electromagnetic emission and
immunity.
3.9 Ex protection

Reference: IEC60079

For ex-requirements to fibre optic cables refer to IEC 60079-28.

All equipment shall comply with the requirements of the specific hazardous area where they are installed.

Field Instruments installed in non-hazardous naturally ventilated areas shall comply with a level of explosion
protection according to hazardous area division 2 or zone 2 requirements as a minimum.

Preferred EX protection methods shall to maximum extent possible be:
Ex i for field instruments
Ex m for solenoid valves

Ex d may be used for field equipment and shall be provided with an Ex e indirect entry.

Ex p should be avoided where possible and shall be provided with an Ex e indirect entry when used.

Ex n equipment may be used in zone 2 areas and in safe areas outside. A Statement of compliance shall be
delivered by a Notified Body.


Equipment, which shall remain electrical energised after an APS/ESD situation, shall follow requirements
specified in TR1055 or TR2237, as applicable.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 15 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





3.10 Degrees of protection
Minimum degree of protection provided by local control panels, enclosures, instrument housing (i.e. transmitter
housing) and junction boxes shall be as follows, in accordance with IEC60529 (international) or NEMA for
facilities in North America.

Table 4 - Enclosure protection
Location IEC60529 NEMA 250
Outdoor areas, naturally
ventilated areas and wash
down areas
IP 56 4X
Dry indoor areas IP 20 12
Other areas IP 44 (IP 54 for indoor areas with
water mist)
13/3S
3.11 Material
3.11.1 General
All equipment and materials shall as a minimum be flame retardant and with preferably no halogen content (e.g.
no fluoride, chloride, bromide, iodide)

Equipment enclosures located outdoor, in naturally ventilated areas and wash down areas, shall be made of
proven sea water resistant material, or be protected by a coating system according to TR0042.

Precautions against galvanic corrosion shall be made.
3.11.2 In-line instruments and instrument wetted parts
The following specific material requirement applies:

For in-line field instruments and instrument wetted parts, material shall be selected in accordance with
TR2000, but shall as minimum be AISI 316 SS.
Thermowell in carbon steel pipe work shall be as a minimum AISI 316 SS
AISI 316 SS shall not be used for thermowells above 60C.
For sour service, all wetted parts shall be in accordance with ISO 15156 or NACE MR0175.
All internal wetted parts shall be made from bar, forging, plate or pipe and shall have equivalent or better
corrosion resistance as materials used for body and bonnet. Castings according to TR2000 is also
acceptable for internals
Material for control valves shall be in accordance with TR2212.
Material for on/off actuators shall be in accordance with TR0038
Material requirements for valve commodity items shall be as follows:
Material quality for mounting assembly e.g. brackets, nuts and bolts diameter 10 mm and less
shall be AISI 316 SS.
Pneumatic and electric components such as indicators, solenoids and limit switches shall be
AISI 316 SS as standard.
Air reservoir shall be AISI 316 SS.
Air filter regulators shall be AISI 316 SS
Rupture discs shall be AISI 316 SS
Small relief valves shall be AISI 316 SS
Framework for control circuits shall be AISI 316L SS
Cabinets for control circuits shall be AISI 316L SS
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 16 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





Boosters shall be in AISI 316 SS
3.11.3 Off-line instruments and instrument tubing
For sour service offline instruments shall be in accordance with ISO15156 or NACE MR0175.

Off-line instrument elements and body shall be AISI 316 SS.

Material requirements for tubing, fittings and instrument valves shall be stated in pipe class sheets in TR2000,
but shall as minimum comply with requirements in table 5. Every project shall have specific pipe/tubing class
sheets.

Table 5 - Material requirements for instrument tubing, fittings, instrument wetted parts and instrument
val ves
Atmosphere/
field
environment
Service
(Note 1)
Material for
instrument
tubing
(Note 3)
Material for
other
components i.e.
instrument
wetted
parts/fittings/
instrument
valves
Maximum
temperature to
minimise risk of
external crevice
corrosion or stress
corrosion cracking.
Maximum
temperatur
e to
minimise
risk of
internal
crevice
corrosion
(Note 3)
Hydrocarbon
and hydraulic
SS Type AISI
316 SS
SS Type AISI
316 SS
Max 60 C
(Note 2)
N/A
Instrument air SS Type AISI
316 SS
SS Type AISI
316 SS
Max 60 C
(Note 2)
N/A
Sea water Titanium grade
2
Titanium grade
2 or grade 5
Hastelloy C-
276
N/A

N/A
85 C

30 C
Indoor and dry
atmosphere or
external non-
saliferous
atmosphere
Fresh water SS Type AISI
316 SS
SS Type AISI
316 SS
Max 60 C
(Note 2)
N/A
Hydrocarbon
and hydraulic
SS Type 6Mo

25 Cr Duplex


SS Type 6Mo



SS Type AISI
316 SS

Hastelloy C-
276
Max 120 C for
SS Type 6Mo
Max 110 C for
25 Cr Duplex
Max 60 C for
SS Type AISI 316 SS
N/A
N/A

N/A

N/A

N/A
Instrument air SS Type 6Mo

25 Cr Duplex


SS Type 6Mo



SS Type AISI
316 SS

Hastelloy C-
276
Max 120 C for
SS Type 6Mo
Max 110 C for
25 Cr Duplex
Max 60 C for
SS Type AISI 316 SS
N/A

N/A

N/A
External and
saliferous
atmosphere
Sea water Titanium grade
2
Titanium grade
2 or grade 5
Hastelloy C-
N/A

N/A
85 C

30 C
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 17 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





Atmosphere/
field
environment
Service
(Note 1)
Material for
instrument
tubing
(Note 3)
Material for
other
components i.e.
instrument
wetted
parts/fittings/
instrument
valves
Maximum
temperature to
minimise risk of
external crevice
corrosion or stress
corrosion cracking.
Maximum
temperatur
e to
minimise
risk of
internal
crevice
corrosion
(Note 3)
276
Fresh water SS Type 6Mo

25 Cr Duplex


SS Type 6Mo



SS Type AISI
316 SS

Hastelloy C-
276
Max 120 C for
SS Type 6Mo
Max 110 C for
25 Cr Duplex
Max 60 C for
SS Type AISI 316 SS
N/A

N/A

N/A

Notes
1. See TR2023 for sour (H2S/SSC) service restrictions.
2. A maximum temperature for risk of initiation of crevice corrosion will apply. Maximum 30 C in chlorinated seawater is
recommended.
3. Piping class material to be taken into consideration.
4. When using SS316 fittings with 6Mo tubing, maximum hardness of both materials must be taken into
account. It shall be ensured that the compression tube fitting material is hardest and that combining SS316
and 6Mo is in accordance with supplier recommendations.

Material for instrument clamps, where there is risk of vibration, shall be fire retardant polymer. Either AISI 316
SS or fire retardant polymer may be used for instrument clamps where there is noo risk of vibration.
3.11.4 Qualifications
Manufacturers of high alloyed materials such as 25 Cr duplex, 6 Mo, Titanium shall require qualification and
acceptance by the Company, and shall be listed in TR2000.
3.11.5 Welding and NDE

All welding shall be continuous. Full penetration welding shall be used for stressed components.

Welding repairs or fabrication welding including weld overlays shall be in accordance with the appropriate valve
standard. Where the valve standard does not quote any requirements then the following shall apply:

Qualification of welding procedures for weld overlay shall be in accordance with ASME IX. Acceptance criteria
shall be the same as for the base material and the testing shall satisfy the standard and the MDS requirements.

Certification of NDE operators shall be in accordance with EN 473 or equivalent. For GoM certification of NDE
operators shall be in accordance with ASNT-TC-1A or equivalent

Specific procedures shall be established for all non-destructive examination.
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 18 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





3.11.6 Other items
Table 6 - Material requirements for instrument housing, enclosures and fire&gas detectors
Atmosphere/ field
environment
Instrument
housing

Fire&Gas
detectors
Protective
shades
Local Control
Panels
Enclosures
Indoor and dry
atmosphere or external
non-saliferous
atmosphere
GRP with
polyester resin
or SS Type
AISI 316 SS


Fire retardant
plastic or
SS Type AISI
316 SS

NA Non-
corrosive
materials like
SS Type AISI
316 SS or
GRP

GRP with
polyester
resin

External and saliferous
atmosphere
AISI 316 SS AISI 316 SS GRP with
polyester
resin.

AISI 316 SS AISI 316 SS
or GRP with
polyester
resin



For instrument housing and fire&gas detectors in external and slaiferous atmosphere, use of other materials
than 316SS shall require company approval.

Manual call points shall be of non-corrosive materials. Manual call points for external and saliferous atmosphere
shall be glass fibre reinforced plastic or stainless steel 316L.

Hinges and locking arrangements shall be of SS Type AISI 316 SS.

3.12 Signal types
3.12.1 Electrical hardwired field devices
The following signal types shall be the preferred choice for electrical hardwired field devices:

Table 7 - Electrical signal types for field instrumentation
Signal Type
Analogue input

4 20 mA with HART protocol
Analogue output

4 20 mA with HART protocol
Digital input Potential free contact
Proximity switches with line monitoring (e.g. NAMUR
interface )
Digital output

24 VDC normal power, minimum 0,5 mA

Industrial network for signal transfer based on fieldbus protocols may be used. This shall be in accordance with
IEC 61158. The preferred choices are Profibus PA and Foundation Fieldbus.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 19 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





Field transmitters and final control elements using Foundation Fieldbus or Profibus PA shall have documented
interoperability, e.g. tick-marked.
3.12.2 Electrical wireless field devices
Wireless network for field devices may be used, provided these have a documented quality and functionality
equal or better than the project requirements. Communication protocol shall be WirelessHART or ISA100.11a
3.12.3 Pneumatic field devices
The following signals types shall be used for pneumatic field devices

Table 8 - Pneumatic signal types for field instrumentation
Signal Type
Analogue input 0,2 1,0 barg
Analogue output 0,2 1,0 barg

All pneumatic signals shall be powered from the plant instrument air distribution system.
3.13 Provision for future modifications
The following spare capacity that shall be provided at the time of plant start-up.

Table 9 - Spare capacity requirements
Item Spare capacity
Multi-core cables 20 % increase in number of I/O
Air distribution manifold 20 % installed spare branches, each fitted with
a valve and plug
3.14 Instrument tubing and fittings
Use of combined manifolds for piping and instruments valves shall be evaluated. Combined manifolds may be
used when instruments are direct mounted on or in the immediate vicinity of the pipe/vessel.

Package Suppliers shall terminate hydraulic and pneumatic tubing at skid edge with bulkhead male connectors
or unions.

Instrument ball valves shall only be used for on/off operation.

Where several consumers are located close by, an instrument distribution manifold with needle or ball valves for
each consumer shall be used.

There shall be a needle valve or ball valve for shut off of air supply located close (approximately 3 meter) to
each consumer.

Air and hydraulic distribution manifolds shall be of compact type with full bore.
The manifold source shall have an isolation valve installed.
Each secondary branch smaller shall be supplied with a block valve located at the take-off point from the
manifold. Instrument valves shall be of ball, needle or plug type. There shall be a separate drain valve included
in the manifold. Special considerations shall be taken to prevent unintended operation.

Tubing shall be seamless and shall be in metric sizes as standard unless otherwise agreed by the project.
(e.g. sizes shall be in inches in the GoM)
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 20 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore






Table 10 - Instrument tubing sizes
Application Size
Max 387 barg 10 mm x 1,5 mm Signal air, impulse tubing, instrument air supply
and hydraulic supply to instruments
Max 535 barg 10 mm x 2,0 mm
Instrument air supply Max 12 barg 25 mm x 1,5 mm
Max 250 barg 25 mm x 2,5 mm Instrument hydraulic supply
Max 389 barg 25 mm x 3,0 mm

All tubing shall meet or exceed the maximum design pressure for each specific service. Maximum allowable
pressure ratings shall be in accordance with the tubing and tubing fitting manufacturer published design data.

Standard compression tubing sizes shall be used wherever possible. Other sizes may be used to satisfy special
process requirements and application shall be subject to Company approval.

Tube fitting and instrument small valves for hydraulic service shall have parallel pipe thread connections (e.g.
BSPP). Packing ring /dowty ring shall be in 316SS or duplex material.

Fittings for N
2
service in hydraulic applications shall have parallel pipe threads (e.g. BSPP).

Tube fittings for other services than hydraulic and N
2
services shall be NPT threads.

Soft seals for instrument needle valves shall be used wherever relevant.

Pre-insulated heat traced tubing shall be the preferred method for all tube installations where heat tracing is
required.

Fire resistant, braided flexible hose connections between the tube and the actuator final fitting may be
considered when there is risk of high vibration.


Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 21 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





3.15 Measurement uncertainty
Uncertainty limits in table 11 with a confidence level of 95% shall apply.


Table 11 - Uncertainty limits
Instrument Instrument uncertainty at
installation point
Instrument uncertainty
Flow measurement - liquid
petroleum
+/- 2,0 % of measured
value
+/- 0,5 % of measured value
Flow measurement Natural
Gas
+/- 3,0 % of measured
value
+/- 1,0 % of measured value
Flow measurements - liquid
water
+/- 2,0 % of measured
value
+/- 0,5 % of measured value
Flow measurements - steam +/- 2,0% of measured value +/- 1 % of measured value
Flow measurements - air +/- 3,0 % of measured
value
+/- 1 % of measured value
Flow measurements
chemicals
+/- 2,0 % of measured
value
+/- 0,5% of measured value
Temperature inline +/- 0,5 % of measured
value
+/- 0,3 % of measured value
Temperature clamp-on +/- 1,0 % of measured
value
+/- 0,5% of measured value
Pressure +/- 0,5% of measured value +/- 0,2 % of measured value
Pressure DP +/- 0,5% of measured value +/- 0,2 % of measured value
Pressure gauge +/- 2% of full scale +/- 1% of full scale
Level separators +/- 20 mm +/- 5 mm
Level - scrubbers +/- 20 mm +/- 5 mm
Level degassing units +/- 20 mm +/- 5 mm
Analysers Oil-in-water +/- 4 ppm in the range from
0 40 ppm
+/- 10 ppm in the range
from 40 100 ppm
+/- 10% in the range from
100 1000 ppm
+/-10% of measured value
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 22 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





Analysers O
2
+/- 5 % of full scale +/- 0,1% of full scale
Analysers - Cl +/- 10% of full scale +/- 5% of full scale
Analysers Salinity/NaCl +/- 5 % of full scale +/- 2 % of full scale
Analysers - pH +/- 0,5 pH units +/- 0,2 pH units
Analysers H
2
S +/- 5% of full scale +/- 2% of full scale
Analysers - Viscometers +/- 5% of full scale +/- 2% of full scale
Analysers sand detector +/- 5% of measured value +/- 5% of measured value

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 23 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





4 Installation design requirements
4.1 Equipment location
General requirements to electrical, instrumentation and telecom installation design are specified in TR3023 and
TR3024.

Installation typicals recommendations for field instruments are given in appendix A.

Equipment shall be located/installed:
in accordance to Vendor requirements
protected against ingress and mechanical damage (especially for panels)
protected against vibration (vibration-free remote support)
protected against weather and water jets
so that it is easy to operate and maintain
so that display instruments and flashing lights are legible and visible from main access areas or
walkways (e.g. loop powered idicators may be beneficial alternative)
so that it does not interfere with escape routings, walkways, other equipment, pipes etc.
to facilitate the removal of other equipment for maintenance, for example coolers, motors etc.
according to layout drawings (XYZ co-ordinates)

Field equipments shall not be supported on pipe work (including tubing), handrails, access ladders or cable
ladders. Instruments which are not classified as in-line shall be either pedestal or bracket mounted. Pedestal
shall not be mounted on grating.

Instruments shall not use impulse piping and tubing as support. Instrument supports shall not be mounted on process
equipments

Field equipments shall not be mounted on blast walls/explosion relieves.

A lifting area shall be considered for heavy instruments.

Equipment located in areas, which do not allow for required maintenance accessibility shall be installed such
that the equipment can be rotated, raised or lowered into areas where maintenance can take place without the
need for scaffolding.

Sensing elements such as orifice assemblies, thermocouples, etc., together with their respective process
connections and isolating valves shall be accessible from normal working locations without use of scaffolding

If applicable the installations shall be arranged so that they can be heat traced and thermally insulated.

All instruments with indication as main function shall be clearly visible from the equipment they serve. Location
of the display element shall be between 1,1-1,8 m above ground level and be fully readable.

Instruments which have been mounted inside enclosures or panels shall be identified by tag number plates on
the outside and inside.

Sensing elements such as orifice assemblies, thermocouples, etc., together with their respective process
connections and isolating valves shall be installed within 0,5m horizontally, and 2m vertically from floor,
platforms or walkways. In order to achieve this, platforms shall be extended, or extra platforms shall be provided
whenever necessary.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 24 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





4.2 Field architecture and segregation
The field architecture shall reflect project split-location fabrication and ease final assembly by minimizing hook-
up items.

Field instrument and valve signals shall be hardwired directly to Remote Input/Output (RIO) units located locally
in different areas. Junction boxes should be avoided, but can be justified if a field device has several signals
that connect the same automation system, e.g. PCS, PSD.

Field transmitter signals may be hard wired directly to safe area located Field Termination Cabinet (FTC) if
suitable.
4.3 Installation of wireless instrumentation
When installing new wireless instrumentation network, other networks (WLAN) shall be identified and
coexistence of the networks shall be verified. Where conflicts exists between networks an evaluation shall be
done to have the WLAN operate in the 5 GHz band instead of the 2.4 GHz band, i.e. using the 5 GHz portion of
IEEE 802.11n, optionally IEEE 802.11a instead of IEEE 802.11b/g

Factors that may affect the transmission range such as machinery, pipes, walls, vessels and electromagnetic
noise shall be identified. The maximum distance between network transmission devices should be 25 meters
(82 ft). Consult Manufacturer for additional compatibility and performance factors.
4.4 Tubing installation
4.4.1 General

Instrument tubing shall be installed according to the recommendations of the Manufacturer.

Instrument tubing shall not support connected components.

Instrument tubing sizes less than 16 mm outside diameter shall be supported to field trays or cable ladders.

Trays are not required for internal tubing on components if tubing is sufficiently protected.

Tubing with size equal to or below 25 mm outer diameter, to be fastened to tubing clamps with span max every
60 x tubing diameter, multitube approximately every 2,5 m for vertical runs and 1,5 m for horizontal runs.

Tubing sizes above 25 mm outside diameter shall as a minimum have support every 1,5 m.

Galvanic corrosion between tubing and tubing support system shall be avoided. The tubing clamp shall, when
installed, not allow for water/sea water to be accumulated between tubing and tubing clamp on wall. Tubing
clamps should be of a self draining type.

Parallel runs of tubing on the same support shall be arranged such that it is possible to have access to every
connection point. Fittings should be maximum 0,25 m from support to instrument tubing on hydraulic lines.

Installation into or through panels shall be by use of bulkhead unions or multi cable transits (MCT).

Instrument tubing and cables may be installed on the same field tray for shorter distances (appr. 5 m).
Instrument tubing and cables may be routed through the same cable/tubing penetration provided the transit is
approved for such use.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 25 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





All tubing and/or tube fittings which are not connected shall be sealed by use of end-plug / cap of same material
as the tubing, fittings.

Test connections, vent, drain and manifold valves shall be available external to applied thermal insulation.

Capillaries of filled systems shall be continuously supported by field trays. Capillaries shall be coiled inside a
cable tray or have similar mechanical protection.

Sealing compounds for process services and instrument air services shall require approval from the Company.

Impulse tubing shall be as short as possible and be installed so that gas/liquid pockets are avoided.

Impulse tubing shall have minimum 1:12 slope.

The slope shall be as follows:
Liquid - down from the tapping point
Steam and Condensate - down from the tapping point
Gases - up from the tapping point
Cryogenic - up from the tapping point


Contractor shall ensure that vents are placed at the highest point of the installation and drains at the lowest.

Special considerations shall be made where movement of connected equipment can occur.

Multi tube bundles shall have sufficient straight length before end connection.

Field instrument process connections shall be 1/2" NPT minimum.
Field instrument pneumatic connection shall be 1/4" NPT.
Field instrument hydraulic connections shall be 1/2" parallel pipe threaded end fittings (typically BSPP) without
adapters to ISO 228-1, sealing surface to DIN 3852, form A, utilising a bonded seal packing in Duplex
SS/PTFE.

The orientation of the process tapping point shall be in conjuction with the slope. Slope down to process means
tapping up, slope up to process means tapping down but at +/-45 with reference to six oclock
For interface to process hook-up see also TR2325 .

4.4.2 Cleaning

All tubing shall be cut by proper tubing cutting tools and de-burred. Tubing shall be blown through with clean,
dry air before final installation.

All tubing in hydraulic systems shall be hot oil flushed and cleaned in accordance to TR2323 ch.8, cleanliness
level, ISO 4406 17/15/12.
4.4.3 Tubing and distribution manifold labelling
Distribution manifolds shall be tagged.

Tubing for pneumatic supply and hydraulic supply and return shall be marked with the consumer tag number,
either at the distribution manifold or at the point of connection to the main line.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 26 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





Tubing passing through bulkheads/MCT shall be marked with consumer tag number on both sides of the
penetration point.
4.5 Thermal Insulation
Capillaries shall be thermally insulated if ambient temperatures can cause significant change in capillary
volumes and mismeasurement. Capillaries shall not be heat traced.

Level transmitters in hydrocarbon service shall follow the insulation requirement given
in the vessel trim number. However as a minimum the level transmitters shall be thermally insulated.

Level gauges in hydrocarbon service shall be thermally insulated and heat traced without
exceptions. Insulation shall include drain and vent valves on the level gauge.
If the vessel is fire insulated, fire insulation of the level gauges itself is not required, however the nozzles to the
vessel shall be fire insulated and heat traced.
4.6 Winterisation
Winterisation shall be accomplished by first considering indoor installation, then outdoor installation with suitable
instruments and heated enclosure.

Where instrument process tubing is located outside and is prone to freezing or process fluids which may
become viscous, prefabricated, traced and insulated tube bundle shall be used.

Instrument process tubing for differential pressure instruments shall have common heating and insulation to
assure equal temperature in both lines. Heat traced tube bundles are preferred.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 27 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





4.7 Temperature instruments
When thermowell is used the temperature transmitter should be mounted directly on top of the thermowell.

Where the access to the measurement point is difficult, the possibility for installing the temperature transmitter
inside a RIO-cabinet shall be evaluated. Cable length and influence from electromagnetic noise should be
evaluated.

Thermowells shall be mounted in such a manner that the element can be installed and removed from the
thermowell for maintenance, without disconnecting the cable.

Thermowells shall be located downstream of flow meter so as not to disturb the flow pattern in the line upstream
of the flow meter.
4.8 Level instruments
4.8.1 General
Level transmitters shall be accessible, removable, and capable of isolation in place from the tank exterior, for
calibration and maintenance purposes.

Instrument nozzles shall be located at the top and/or side of the vessel, such that negative impacts on the
measurement are minimized.

Cage side/side mounted interface for liquid/liquid application shall be designed with three process connections
and be jig set from the factory to avoid any installation alignment issues.

All instruments and gauges shall have dedicated nozzles.

Relief/drainage tubing or pipe shall be routed to a safe location according to area requirements.

Definitions for 0% and 100% level shall be equal for all level instruments and glasses.
0% shall be the lowest measurable level and 100% shall be the highest measurable level.

Definitions for 0 mm in horizontal tanks shall be the inside bottom. For vertical tanks, the tangent line shall be
0mm. For side mounted nozzles, 0% and 100% level is measured from the center of the respective nozzles.

Reference point for 0% shall be marked on the vessel.

Level glasses shall as a minimum cover the total range of transmitters for both safety and control.

Vessels containing liquids with different specific gravities shall be fitted with two overlapping level glasses, not a
single large one. This is to prevent a liquid seal forming and to allow the various layers to be seen. Visible
sections shall overlap by at least 50 mm.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 28 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore







Figure 1: Example of 0 100% level






Example for horizontal tank
LST
LIT
4mA=0%
20mA=100%
4mA=20%
20mA=80%

Welded bottomlinemark =0mm-ref
0%/ 200mm
100%/ 3000mm
75%/ 2300mm
50%/ 1600mm
25%/ 900mm
LST
TANK
Tan-linje = 0mm-ref
Example for verti cal tank
LIT
4mA=0%
20mA=100%
4mA=20%
20mA=80%
Welded bottom line mark
200mm
3000mm
0mm
0%/ 200mm
100%/ 3000mm
75%/ 2300mm
50%/ 1600mm
25%/ 900mm

4.9 Flow instruments
Flow meters shall be installed according to recognized standards or according to the recommendations of the
Manufacturer. Standards referred to in chapter 5.3 contain additional installation requirements, which should be
followed.

Flow meters shall be placed upstream of control valves and other pressure reduction items
Irrespective of design, the flow meter shall not cause flashing or cavitation at any position in the line. Pressure
drop shall generally be kept to a minimum and shall not cause an unacceptable restriction to flow unless it is a
dedicated flow restriction.

The design shall take into consideration the need for space above/below the flow element for isolation valves,
tubing and transmitters.

Ultrasonic meters should not be installed with the transducers positioned at the top or bottom of the meter, in
order to avoid adverse effects from gas or solid deposits.
Installation of ultrasonic meters in wet gas (e.g. from 1
st
stage separators) processes must be carefully
evaluated. Both placements of transducers as well as mounting of the meter shall be considered.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 29 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





Noise from valves or process equipment up or down stream the ultrasonic meter shall be evaluated.

When installing orifice plates correct postion of the drain hole shall be evaluated.

The following upstream and downstream straight pipe lengths should be used for design of flow meter
installations:

Table 12 Upstream/downstream pipe length
Measurement principle Upstream pipe length Downstream pipe length
Orifice Minimum straight lengths (ISO 5167: part 2, Table 3 column B or
Manufacturer recommendation) shall satisfy the measurement accuracy
requirements for the application.

Venturi tubes Minimum straight lengths (ISO 5167: part 4, Table 1 column B or
Manufacturer recommendation) shall satisfy the measurement accuracy
requirements for the application.

V-cone 3D 1D
Annubar 20D 5D
Ultrasonic 20D 5D
Vortex 20D 5D
Variable Area Meter No requirements No requirements
Electromagnetic Flow Meters 5D 2D
Turbine Meters 20D 5D
Coriolis Meters No requirements No requirements

The use of flow straightners or flow conditioners shall be considered, where long upstream pipe lengths such as
20D or greater are required.

The use of a strainer shall be considered upstream of turbine meters to avoid damage to the turbine blades or
rotor.
4.10 Fire & Gas equipment
Fire and Gas equipment shall be installed according to Supplier requirement.

Sensor range, cone of vision, sensor direction and angle shall be considered.

The detection system shall be designed and installed in such a way that it can be functionally tested without
interrupting the normal plant activities.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 30 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





For gas detection in ventilation inlets the detector shall be located as close as possible to the inlet to ensure fast
detection.

Arrangement shall be made for testing of F&G equipment in order to avoid use of temporary arangement
(scaffolding etc).

Flame detectors shall be installed in a way that facilitates cleaning of the optics.

Sensors exposed to weather, should be oriented in a downward facing position, and if possible, not be pointing
directly into the sun. Each detector should be protected by drip or splash guards.

All detectors shall be provided with a pig tail in such way that the equipment can be moved 2 meters in any
direction without disconnecting the cable.

Early warning detectors shall be mounted minimum 0.5 metre away from light sources.

Gas line of sight detectors and flame detectors should be mounted directly on the structure to avoid vibration. If
a separate stand is used, then it must be stiffened to avoid vibrations.

The minimum distance from line of sight receiver to any light sources shall be as per Supplier
recommendations.

Based on a typical flame detector characteristic, the distance between flame detectors and targets monitored
should not exceed 26 m or the Supplier recommended distance.

For flame detectors sensitivity to external impact such as arc welding, burner boom and flare etc. shall be
considered in order to avoid activation of sensors in a non fire situation. Special means shall be applied to avoid
false triggering from steady state radiation sources

Heat detectors shall have a maximum coverage in naturally ventilated area of approximate 24 m2, maximum
distance between sensors 7 m and maximum distance from wall 4,5 m and minimum 0,5 meters away from
outside wall or dividing partition.
Heat detectors shall have a maximum coverage in mechanically ventilated area approximate 37 m2. the
maximum distance between sensors shall be 9 m and the maximum distance from the wall 4,5 m.

Smoke detectors shall be mounted 100 300 mm below the roof, straight below steel beams.
If the detector is mounted on a ceiling or a completely flat roof, then the Suppliers guideline shall be followed.

Smoke detectors shall have maximum distance between sensors of 11 meters, maximum distance from sensor
to bulkhead of 5,5 meters and shall be a minimum of 0,5 meters away from outside wall or dividing partition.

Smoke detectors mounted in areas such as suspended ceilings and raised floors shall have their location
indicated by visible tag-plate.

Catalytic and Electrical chemical gas detectors shall be mounted with the head pointing downward.

For gas line of sight detectors, there shall be enough space around the receiver and transmitter to install the
alignment equipment.

Gas point detectors not accessible from normal access level shall be equipped with a test tube down to
1500mm above access level for easy access and regular testing of detectors.

A working method for optimization of installation of duct mounted gas line detectors shall be established during
detailed engineering. This is in order to avoid condensation on mirrors. Duct penetrations shall be according to
the Suppliers recommendations.
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 31 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





Point gas detectors in air inlets shall be protected against water ingress. Maintenance access for such detectors
shall be addressed.

Manual call points shall be mounted 1.5 meters above ground level.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 32 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





5 Field instruments
5.1 General
This section states requirements for the most frequently used measuring principles. Other types may be used
on special applications. For field instruments not described within this document, the design shall be based on
recognised international standards or Supplier recommendations.

Instrument performance/accuracy shall be sufficient to fulfil process/unit performance requirements and shall be
selected to minimize calibration frequency and maintenance.

The Supplier shall provide data for long-term stability and confidence level for the field device performance.

Field instruments for safety functions shall be documented to be suitable for their intended purpose, in
compliance with IEC 61508/61511 or ANSI/ISA S84.01 and the corporate requirements in TR1055 and TR2237,
as applicable.

Instrumentation used for hydrocarbon services shall be constructed in such a way that any fault in the primary
process barrier will not leak into the main compartment or junction box. If a leakage occurs, it shall not be
possible to build up any pressure inside the instruments.

Mechanical switches shall be avoided in favor of analog instruments.

Field instruments and controllers of pneumatic type should generally be avoided.

Transmitters shall have integrated local indicators. Separate local indicators shall be used if physical placement
of transmitter complicates accessibility and readability or for operational purposes, (e.g. local control panels or
where a local control point is located away from the point of measurement).

Field instrument cable entry shall have ISO threads - size depending on cable size.

Flange connection for inline instruments shall follow piping class, see TR2000.

All in-line flow elements (when part of the process line) shall be flanged for removal from the process line.

Field transmitters and final control elements shall have possibilities for online self-reporting.

All instruments given a tag number shall be delivered with a 316SS tag plate, minimum size 50 x 20mm, with
etched or embossed characters of minimum 5 mm high. This tag plate shall contain the tag number only. The
plate shall be wired to the instrument with a stainless steel wire.

Nameplate of the field instrument shall as a minimum contain:
Instrument serial no.
Instrument model no.
Protection category and Eex/ATEX certificate no. (if applicable).

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 33 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





5.2 Temperature measurement
5.2.1 General

Technical requirements stated in API 670 shall apply for temperature sensors used in machinery protection
systems. Temperature measurements in rotating machinery such as metal temperature in bearings, windings or
drain temperature shall be recorded and presented on the SAS system. See TR3132 for further information
about instrumentation for machinery systems.

Non-intrusive temperature measurements not requiring a conventional or weld-on type thermowell should be
used if the accuracy and response time requirements are met. Non-intrusive elements should always be
considered for high vibration or high flow velocity applications.

Non-intrusive temperature transmitters shall be constructed to meet the anticipated vibration levels. They should
be easy to mount and have sufficient support strength to mount instruments with dual PT100 RTD elements,
wired via a connecting a tube to a common transmitter housing mounted on the clamp.

Non-intrusive temperature transmitters should only be used for line sizes 3 in or larger.

Thermowells should be used for temperature measurements that are not of the clamp-on type.

In addition, thermowells shall be used if any of the following apply:
operation temperature exceeds 160 degrees centigrade
pipe wall thickness exceeds 25 mm (for duplex or materials with similar heat conductivity)
the pipe is manufactured in a material with significantly lower heat conductivity than stainless steel
sufficient thermal isolation cannot be achieved
the pipeline is heat traced
there is not a straight pipe of sufficient length where the temperature is to be measured
significant heat radiation from the flare or other sources will disturb the measurements

Thermowells shall be used for fiscal measurements, heating medium systems, on heat traced pipelines, HVAC
liquid systems, process vessels and safety systems.

Temperature elements not accessible during operation shall for selected critical equipment be installed with
dual elements (backup element) and terminated in the field for easy access.

Temperature measurements should be performed by PT 100 RTDs in accordance with IEC 60751.

For temperature measurements above 600 C thermocouple material Chromel Alumel (type K), in accordance
with IEC 60584-1, IEC 60584-2 and IEC 60584-2-am1, should be used.

Temperature sensors shall be enclosed in a 6mm diameter AISI 316 SS sheath, preferably spring loaded to
ensure contact with the thermowell.

Where a thermowell has been specified, it should be delivered together with its associated temperature sensor.

Temperature transmitters that accept dual elements and have the possibility to swap elements upon failure (hot
back-up) shall be considered.
5.2.2 Thermowells
Thermowell flange arrangement shall be in accordance with TR2325 .

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 34 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





Thermowells shall be of the flanged type, size 1,5 in, normally. For tanks and vessels, and for pressure class 2
600 lb and above, the size shall be 2 in.
For non-critical utility service, thermowells of threaded type (NPT) can be accepted.

The thermowells inner diameter shall be suitable for temperature elements with stem diameters of 6 mm OD.

Thermowell lengths shall be standardised. See Piping Detail Standard TR2325 for technical solution of
thermowell.
Also API 551 should be consulted to determine thermowell insertion depth.

Welded thermowell shall be constructed in accordance with Norsok M-601 and all welds shall be liquid
penetrant tested.

Thermowell strength calculations (e.g. wake frequency calculations) shall be performed for process
hydrocarbon systems according to ANSI/ASME PTC 19.3 TW-2010.

Thermowells for insulated vessels should have extension necks.
5.2.3 Temperature gauges
Bi-metallic or gas filled temperature gauges with 100 mm nominal head diameter shall be used for local
indication with 360 degree orientation. Stem diameters shall be 6 mm OD.

Normal temperature shall be at approximately 60% of full range

Temperature gauges with capillary tubing should not be used.

Manufacturers standard ranges shall be used and dials shall have large, black and easy to read, digits on white
background.
5.3 Flow measurement
5.3.1 General
See TR0814 for flow measurements for fiscal applications.

Robustness with regard to variations in operating conditions and fluid properties need to be given due
consideration, when selecting a flow meter. Selection of the measurement principle and design of the piping
arrangement are critical for performance and measurement quality.

Flow meters shall not be used in applications with higher gas or water content than the Manufacturer accepts
for a guaranteed meter performance.

Flow elements shall not be used where possible loss of mechanical components upon failure can endanger
downstream equipment (e.g. insertion turbine meters in a compressor inlet).

Evaluation criteria shall as minimum include the following:

process conditions (pressure, temperature, phase, etc.)
fluid properties (clean/dirty, dielectric properties, etc.)
turn down requirements
uncertainty requirements
traceability requirements
available pressure drop
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 35 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





installation requirements
acoustique noise / ultrasonique noise from other valves etc.
relevant piping specification requirements for the flow meter
operational experience
maintenance requirements
verification of meter performance in operation
.
For test and / or inlet separator metering, the design shall be based on an evaluation of the following:
whether or not the separator is to be used as reference for calibration of multiphase meters.
the presence of liquid carry-over in gas stream
avoiding flashing conditions in a liquid flow meter
bypass arrangements on liquid meters (turbine meters)

Flow elements shall be marked with flow direction, pressure rating and appropriate hazardous area
classification.

The flange and piping arrangement shall be in accordance with TR2325 .
5.3.2 Preferred measurement principles
5.3.2.1 Petroleum liquid process flow measurements

Metering principles which shall be considered for petroleum liquid flow measurements are:

turbine
ultrasonic
coriolis
orifice plate
v-cone

Other measurement principles may be considered in special cases such as for very high turndown
requirements, liquids with high viscosity or measurements on very high or very low flow rates.
5.3.2.2 Gas process flow measurements

Metering principles which shall be considered for gas flow measurements are:

ultrasonic
orifice plate
v-cone
venturi

In special cases (typically low flow rates) coriolis meters may also be considered.

For applications such as flue gas, where C0
2
-concentration are high in combination with low pressure and high
turndown requirements, finding a good metering principle may be challenging and the metering principle shall
be advised by the Company.
5.3.2.3 Water liquid process flow measurements

Metering principles which shall be considered for water flow measurements are:
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 36 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





turbine
ultrasonic (clamp-on may be considered)
coriolis
electromagnetic
orifice
v-cone

Other principles may be considered for special applications such as low flow or very dirty liquids.
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 37 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





5.3.2.4 Chemical liquid flow measurements

Metering principles which shall be considered for chemical injection liquid flow measurements are:

coriolis
positive displacement
turbine meters

Other measurement principles may be considered in special cases.
5.3.2.5 HVAC/Air Flow measurements

A DP flow measurement principle should be used.

The metering principle shall be chosen in conjunction with the HVAC system Supplier.
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 38 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





5.3.2.6 Steam Flow measurements

Metering principles which shall be considered for steam flow measurements are:
Vortex
Orifice plate
Ultrasonic
Variable area
Annubar
Coriolis
5.3.3 Orifice plate
The orifice-plate shall be calculated, manufactured and installed according to ISO 5167 or meet the
recommendations of the manufacturer.

The minimum pipe size for orifice plate metering should be 2". If process piping is smaller than 2", then the pipe
size shall be increased to 2" for the meter run. Should this not be possible then an integral orifice meter or a
precalibrated meter run shall be used.

Orifice plates shall be provided with a handle of sufficient length to extend beyond the pipe flanges. This is to
enable the information stamped on the upstream side of the handle to be read.
Information to be stamped on the handle is to include the orifice bore (d), the nominal pipe size (D) the material
used and the instrument tag number.

Dual chamber orifice fittings may be used to cover services with wide flow rate ranges.

A third-party verification shall be performed of design and calculation model of multihole restriction orifices used
for blowdown applications. Hole tolerances should be verified.
5.3.4 Venturi tubes
Venturi tubes shall be calculated, manufactured and installed according to ISO 5167 or meet the
recommendations of the Manufacturer.
5.3.5 V-cone flow meters
The v-cone shall be calculated, manufactured and installed according to Manufacturer recommendations.
5.3.6 Annubar Flow Meter
This type of meter shall only be used on clean gas, steam, clean liquids and air applications.

Annubar flow meters shall not be used for low flow applications where the Reynolds number is less than 10000.
The Reynolds number should be above 30000.

Annubar meters should be designed to allow their extraction during operation.
5.3.7 Ultrasonic flow meter
Selection and installation design of ultrasonic meters should be according to AGA 9 for gas applications and to
API MPMS, Chap. 5.8 for liquid applications.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 39 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





The measuring principle shall be the transit time differential method.

Clamp-on ultrasonic meters shall only be used for non-critical measurements.

Before a clamp-on meter is chosen, an evaluation of position, process fluid, flow conditions and piping material
including isolation and lining material shall be conducted.
5.3.8 Vortex flow meters
Meter can be used on both liquid and gas applications

The meter shall not be used for low flow where Reynolds number ReD <10000 and on low pressure application.
Reynolds number should be above 30000.
5.3.9 Variable area flow meters
Variable area flow meters shall only be considered for simple duties, such as purge or seal fluid monitoring etc.

Variable area meters should have metal tubes with flange connections and actual flow indicating scales.

Glass tubes shall only be used on fluids such as clean water, air or nitrogen etc. which in the event of a
breakage will not be hazardous to personnel or plant. Screw connection can be applied for these applications.
5.3.10 Electromagnetic flow meters
Electomagnetic flow meters can be used for water applications with a continuous conductivity according to
Manufacturers recommendations.
5.3.11 Turbine flow meters
The selection and installation design for turbine meters should be according to API MPMS Ch.5.1 and 5.3 for
liquid applications and to ISO 9951 for gas applications.

For facilities in North America, AGA 7 should be used for natural gas applications.

Signal amplifiers shall be mounted on or adjacent to the meter.
5.3.12 Coriolis flow meters
Selection and installation design should be according to AGA 11 or API/MPMS Ch.5.1 and 5.6 section 6 and 7
or ISO 10790.
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 40 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





5.4 Pressure measurement
5.4.1 General
Minimum one pressure transmitters installed on piping or equipment protected by a pressure relief device, shall
have a measuring range covering the set pressure of the relief device

Pulsation dampers shall be used if pulsations are likely to occur.
Needle valves shall not be used as pulsation dampers.

All pressure instruments shall withstand an overpressure of minimum 130 % of upper range value without the
need for recalibration.

Differential pressure instruments shall be able to withstand full static (line) pressure on either of the inputs, with
the other input at zero (atmospheric pressure) without damage to the sensor and without the need for
recalibration.

Differential pressure instruments equipped with capillaries and remote seals shall have 3 inch flanges and
flushing ring equipped with two 1/2 NPT FEMALE plugged connections. Smaller diaphragms shall be
considered for high pressure measurements. When used capillary leads shall be kept as short as possible

Diaphragm seals may present accuracy problems at pressures less than 2 barg (30 psig) and shall be used only
if the required accuracy is attainable.

Diaphragm seals shall be fitted to pressure instruments in corrosive, viscous or services containing solids,
provided that the desired accuracy can be achieved.

Ranges below 50 mbar shall be avoided.

Use of permanent pressure gauges shall be minimized.

Pressure switches shall be avoided.
5.4.2 Pressure gauges
Pressure gauges shall be of the heavy duty liquid filled type with safety glass and rear safety blow out disc.

Gauges with ranges from 0,6 barg, shall have bourdon type element and shall have liquid filled house/case. The
measuring element shall generally be a Bourdon tube type unless process considerations dictate the use of a
diaphragm seal type to prevent corrosion, plugging etc.

Normal pressure shall be at approximately 60% of full range.

The nominal housing/case diameter for process applications shall as a minimum be 100 mm.

Dual element gauges or differential pressure gauges for measurement of differential pressure should not be
used.
5.5 Level measurement
5.5.1 General
Direct vessel mounted instruments with non-moving parts should be used.
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 41 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore






The level application shall have compensating measures if variations in process conditions (e.g. temperature,
pressure, density) will affect the measurement accuracy.

External bridles shall typically be of 2 to 4 nominal diameter, with 2 side/side flanged process connections
and shall be equipped with flanged vent and drain connections.

An arrangement for in-line calibration and flushing of the instrument shall be included.

Level sensing instruments that can be clogged due to high viscosity, hydrates, foam, scaling, build up, or
affected by other factors shall be equipped with flushing possibilities. Flushing possibilities may be manual or
automatic( e.g. flushing port for DP).

Measuring principles shall be selected according to application. Evaluation criteria should as minimum include
the following:
non moving parts
density
pressure
accuracy
temperature
vessel geometry
nozzle locations
clogging
scale build-up
foaming, emulsion or turbulence problems
vibration / level fluttering
fluid level interface phases
process inlet and outlet
installation induced movements (floater, ship etc.)
top mounted, side mounted or mounted in a cage.
Maintenance and calibration

The flange arrangement shall be in accordance with TR2325 .
5.5.2 Preferred measurement principles
Gamma and differential pressure shall be the standard level measurement principles for process control and
safety applications for two-phase and three phase applications.

Guided wave radar measurement may be considered for two-phase and three-phase applications.

Vibration level switches may be used for high level safety functions. Switch should not be used for low level.

Level instruments such as ultrasonic, capacitance, displacer or conductive type may be used for special
applications e.g. homogeneous applications such as lube oil systems.
5.5.3 Local level indicators (gauges)
Level indicators shall cover maximum and minimum operational levels including high/low trip points.

The scale on the level glass or magnetic level gauges shall indicate both [mm] and [%].

Calibration of level instrument and level glass shall be identical, for the same level measurement.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 42 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





Selection of level gauge type readability shall be evaluated based on the actual fluid process medium. Integral
back light for transparent level gauges shall be considered.

Gauges with magnetic indicators should only be used in clean liquid applications, i.e. there should be no risk of
the magnetic displacer unit getting stuck or contaminated due to the process fluid.

Magnetic type level gauges may be used for ranges above 1200 mm, eliminating the need for multiple level
gauges.

Shrouded covers shall be used to protect glass edges from sandblasting.

Gauge glass type shall allow for cleaning during operation.

Reflex type gauge glass shall only be used on clear mediums. For interfaces (oil/water), the transparent type
gauge shall be used. Transparent type gauges shall be equipped with back lights.

Reflex and transparent gauges shall be equipped with glass breakage automatic shut off valves.

Level gauge glasses shall have flanged process connections, and be fitted with gauge valves for maintenance
purposes. The gauge valves shall be located so that complete drainage of the gauge is possible.

Simpler solutions may be used on small and non critical vessels.
5.5.4 Differential pressure
Pressure instruments shall be installed with permanent connections for calibration. DP level instruments shall
be mounted on dedicated nozzles.

Differential pressure measurement instruments for pressurized vessels shall be of the capillary type, with
remote seals. Electronic seals without the use of capillaries may be used on vessels with a low static pressure

Remote seal process connections shall have 3 inch flanges.

Remote seals shall be equipped with a means of flushing, venting and draining of the diaphragm process side.
A minimum of two off female NPT connections shall be provided for this purpose.
5.5.5 Capacitance
If there is risk of contamination from wax or scale, then the capacitance meter shall have an automatic cleaning
system.

Probes shall not be used for applications where there is a risk of variations in electrical conductivity of the
process media.
5.5.6 Guided wave radar
All units shall be capable of level determination for products with a dielectric constant as low as r =1,4. As well
for interface applications, the units shall be able to handle upper products with a dielectric constant as low as
1,4 when the dielectric constant of the lower product is at least higher than that of the upper product by 10 (i.e.
upper dielectric constant = 1,4/ lower dielectric constant = 14.

In applications suffering from chalk like sediment, build up, scaling, hydrates, crystallization or condensation the
probe shall be suitable for its intended use. Single, rigid or single wire or enlarged co-axial with flushing
connection type of probe shall be used if build up is expected.
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 43 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





5.6 Fire and gas detection
5.6.1 General
TR1055 and TR2237, performance standards 3 and 7 state functional requirements related to fire and gas
detection.

Fire and gas detectors may be of the smart addressable, e.g. field bus type.
5.6.2 Fire detection
5.6.2.1 General
Detector characteristics and calibration (pre-set sensitivity) shall ensure detection of a fire condition at an early
stage. The detector shall be capable of operating under the conditions at the time that fire detection is needed.

Fire detectors should be self-monitoring.

Maximum response time of the fire detection function shall be evaluated and defined according to safety
criticality. Response time for fire detection should not exceed 10 seconds.
5.6.2.2 Flame detectors
Where flame is predominating and according to flame wave radiation characteristic, flame detectors shall be of
the multispectrum IR, or combination UV/IR, type.

The optical lens may have a built-in adjustable heater.

The sensitivity setting of the flame detector shall be determined according to distance from detector to fire
object. Low sensitivity setting shall not be used.
5.6.2.3 Heat detectors
Heat detectors should be a combination of rate of rise, and fixed temperature.

Heat detectors should have local alarm indicators to visually indicate when detectors are in alarm mode
5.6.2.4 Smoke detectors
Optical smoke detectors should be used for detection of smouldering fire.

Ionic type, smoke detectors may be used where there is risk of energy intensive smoke generating fires, e.g.,
fire in high voltage switchgear caused by a short circuit.

Smoke detectors shall not be sensitive to water vapour.

Smoke detectors should have local alarm indicators to visually indicate when the detectors are in alarm mode.

Early warning sensors shall have higher sensitivity (0.4 % to 0.8 % light obscuring per metre) than the normal
recommendation.
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 44 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





5.6.3 Gas detectors
IR gas detectors (HC) shall be the preferred technology whenever suited for the gas to be detected.

Gas detectors should be self-monitoring.

Catalytic detectors shall only be used if proper detection performance by other types is not achieved (e.g. on
hydrogen gas).

H
2
S detectors shall be used in areas with a risk of harmful H
2
S concentrations, e.g. drilling mud/shale shaker
area.

Ultrasonic gas leak detectors may be used. This type of detector may be beneficial in areas where the
background noise level is constant.

Gas detector characteristics and sensitivity shall ensure that the presence of gas is not underestimated, e.g.
gas concentration (point detectors), gas amount (optical beam detectors) or leakage rate (acoustic detectors).

The maximum response time of gas detection functions shall be evaluated and defined according to safety
criticality, in order to ensure that total reaction time for each safety function can be fulfilled.

Typical response times that should be complied with unless faster responses are specified elsewhere, are as
follows:
IR detector response time (T90) should be less than 5 seconds for general area applications.
Catalytic detector response time from low alarm (%LEL) to high alarm (%LEL) should be less than 10
seconds (considering test gas 50% LEL and T50(10s) and(T90 (30s))
Acoustic detector response time including delays employed to improve false alarm immunity should not
exceed 30 seconds.
Upon gas exposure, the time from detector alarm limit is exceeded until alarm is presented/tagged on
operator station should be less than 2 seconds.

Detectors shall give a fault alarm if the lens is contaminated or measurement path blocked.
5.7 Manual callpoint
Manual activation buttons shall be protected against inadvertent activation, e.g. by use of protective covers.

Manual callpoints shall have loop monitoring for open circuits/short circuits.

Push buttons shall be manually reset.

Each post shall be clearly marked, and a consistent colour coding shall be applied for the activation buttons.
5.8 Online analyser system
5.8.1 General
See TR0814 for use of online analysers for fiscal applications.

See API RP std 555 for recommended measurement principles.

Selection of analysers and design of analyser systems shall be carried out in close cooperation with the
Company. Technology and components shall be field proven for the intended application and shall have
documented performance under similar operating conditions.
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 45 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore






Unless an inline analyser is being used, a sample probe should be used to take process samples.

Provisions shall be made for testing and calibrating each analyser. All necessary calibration/test equipment
shall be supplied with the analyser. Where possible, the change over from process sample to test sample shall
be controlled remotely from the LCR/CCR, by switching inline solenoid valves.

When designing an analyser system, the following requirements shall be evaluated:

Analysis shall be performed on a representative sample (sampling in a turbulent flow regime);
Results shall be within the required accuracy, response time and stability.
Availability of system shall not be impaired by excessive maintenance and calibration
requirements.
The system shall be designed so that maintenance and calibration can be performed by one person.
The analyser shall be provided with self-diagnostic facilities to give an alarm when it is not working properly
or an error has occurred (fault alarm).

Analysers exposed to dirty processes (e.g. produced water) where sensors, measurement chamber, or sample
system risk contamination shall have an automatic cleaning system.

Inline analysers shall be safely retractable during operation.

Manual sample points for laboratory analyses shall be provided at the online analyser sample point.

Where high availability of the analyser is important and there is a risk for deposits e.g. scaling or wax in
operation, a duty-standby solution shall be evaluated. (e.g. for oil-in-water, O
2
for water injection).
Full duplication of analyser probes, sample lines, pressure reduction and gas conditioning systems shall be
considered for critical applications.

Sample cylinders used in sour-gas service shall be either polytetrafluoroethylene (PTFE) coated or epoxy
coated.

5.8.1.1 Sand detectors and erosion probes

As a minimum the acoustic sand detectors shall have possibilities for filtering of acoustic noise from other
sources than the sand production. This will as a minimum require that the background noise is flat when the well
or flow line is shut down.

Provision shall be made for online calibration of sand detectors via sand injection upstream of detectors.

Increasing erosion readings shall not be caused by mechanical failures or impacts.
5.8.2 Analyser House
Analyzer houses shall have interior gas detection.

The Analyser house should be large enough to allow sufficient headroom and free access to three sides of wall-
mounted equipment.

A drain and vent system shall be provided for sample disposal unless the sample is returned to the process.

The back-pressure effect on analyzers connected directly to the system drain or vent shall be evaluated.
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 46 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore






The location of sample supply and return connections shall be evaluated.

Adequate lighting shall be provided around the analyzers and other equipment.

Need for forced ventilation shall be considered.

The design shall be compliant to Statoil requirements in TR1055 and TR2237.
5.8.3 Sampling System
5.8.3.1 General
In order to monitor the true concentrations for complex or contaminated process waters, one must be able to
control or minimise any phase separation during sampling and measuring stages.
To ensure that the sample under analysis is representative for the property to be measured and at conditions
suited for the correct operation of the analyser, a careful study of the overall sampling system shall be carried
out. The study shall include recommendations as specified by the analyser Supplier.
5.8.3.2 Sample Tapping
Samples that are taken from the process stream shall have the same composition as the average composition
of the process over the whole cross section of the pipeline, at the location and time of sampling.
Sampling/measuring in a true turbulent flow will give a representative analysis.

Placement of sample tapping points for hydrocarbon gas applications should follow the recommendations in
ISO10715 Natural gas.

Placement of sample tapping points for liquid applications should follow the recommendations in ISO 3171 ch.
5.

For projects in North-America the requirements for sample tapping shall follow the recommendations in API
MPMS Ch 14.1 for Natural Gas and API MPMS Ch 8.2 for liquid applications.

Inline analyzers shall be installed/positioned according to the same requirements as sample probes.

An ASTM type nozzle shall be used for obtaining steam samples and may be used for liquids. Steam samples
shall be done via a cooler.

The typical gas sample probe, also referred to as a straight tube sample probe, can be used for gases.
Flow impact probes should be considered where considered adequate.

Gas lines with streams free of entrained liquids and at flow conditions well above their dewpoint temperatures
may be sampled with any probe design.

Lines that are operating at or near the gas stream dewpoint shall have a special probe designed to overcome
the problems of condensation and liquid.

Where required, sample take-off & return probes shall be included. Typical installations use 2 flanged
connections.

Each sample probe shall be fitted with a set of double block & bleed isolation valves.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 47 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





The design of the probe shall take into account the possibility of resonant vibration being induced in the probe
by high flow velocities in the pipeline.

Sampling devices shall not be installed in horizontal pipelines where contaminants are likely to be in
suspension.

Mixing equipment shall be considered for installation upstream of the sampling probe, whenever required in
order to achieve a representative sample.
5.8.3.3 Manual sample point for laboratory
Provision for manual sampling shall be accommodated, where required for back-up and calibration of online
analysers. This manual sample point shall be located as close as possible to the sample point for the online
analyser.

All sample points should be installed together with a probe as specified in this document.
All sample connections shall be fitted with a ball valve and a needle valve for tapping.
Sample point shall be located for easy access.
The sample excess shall be returned to the process, drain, vent or to the fuel system/flare.
5.8.3.4 Sample Transport Line
Representativity shall persist throughout the period of transfer of the batch. The sample shall be maintained in
the same condition as at the point of extraction without loss of liquid, solids or gases and without contamination.

Sampling lines shall be as short as possible.
Sample volumes shall be kept to a minimum.
Time lag calculations shall be prepared and documented for each installation / stream. The transport time
through the sample handling system shall be less than 2 minutes (i.e. to assure that a fresh sample is always
analysed, to avoid "memory" effects).
The sample transport system shall be designed to convey the fluid to the analyser from the sample tap with the
minimum of time lag (isokinetic flow).
Tubing and fittings used in the system shall not absorb components from the gas and thereby affecting the
analysis result. Chemical leakproofing compounds (e.g. Loctite) which may emit components to the gas shall
not be used. Tubing and fittings used in systems for measurement of H
2
S shall be chemically treated (e.g.
silicated) in order to avoid absorbsion or emission of H
2
S. Tubing and fittings used for carrier gas shall also be
chemically treated (e.g. silicated) in order to avoid affecting the measurement.
Fast loops systems are preferred due to small line lags and to a minimum of product waste.

Double piping from the probe to the analyser shall be considered for cleaning purposes when the sample is
expected to be contaminated. If the sample contains slurries, then a cleaning facility downstream shall be
considered. The connections and change over valves shall be primarily mounted on ground level or be
accessible from accessible platforms.

Transmitters for flow, pressure and temperature and check-valves shall be used as necessary, to ensure that
sample flow is adequate (isokinetic) and in the proper direction.
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 48 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





5.8.3.5 Sample Conditioning
It is imperative that the sample being analysed is suitable for the analyser. For example samples normally
require some form of conditioning such as filtering, pressure control, flow control, temperature control, phase
control or phase change prior to passing through the analyser.

As a general rule, all sampling systems shall contain suitable filters. Self-cleaning bypass type filters shall be
used.

Conditioning may be required for the removal of dirt particles, liquid/gas entrainment, corrosive agents, etc.
Special consideration shall be given to vapour samples containing a large proportion of steam or other
components which needs to be condensed and removed before analysis.

When Analyser Houses are employed the sample conditioning equipment shall whenever possible be located
on the outside walls of the analyser house and shall be adequately protected.
5.8.4 Online analyser used for authority reporting
Non-fiscal online analysers may be used for authority reporting. In such cases the analysers shall be subject to
a technology qualification.

Analysers used for reporting of oil-in-water discharge to sea shall in each case be qualified according to
Company requirements.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 49 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





6 Final control elements
6.1 On/off valves

For technical requirements regarding actuators for on/off valves and accessories reference is made to TR0038 .

For requirements to montoring of safety critical valves reference is made to TR3138.

The pneumatic/hydraulic/mechanical arrangement of the ESV shall be designed and built so that the ESD
action is never prevented, i.e. to bring the ESV to the safe state.
The PSD related arrangement of the ESV shall be designed and built such as to never prevent the ESD action,
which is to bring the ESV to the safe state.

All on/off valves shall generally have CCR and local end position indication. All ESVs used for the
sectionalisation purpose shall have local reset.

ESVs used in the blowdown system shall not have a local manual reset.
6.2 Control valves
6.2.1 General
TR2212 states the technical requirements for control valve and choke valves.

Globe valves should normally be used. However, other types (e.g. angle valves, ball valves, or disc/butterfly
valves) may be used, subject to service conditions and application

Control valves shall be specified with leakage class III, class IV and class V. For applications with high
differential pressure, shut off leakage class V shall be used.

Self-acting control valves shall be used only when a sufficient differential pressure exists.
6.3 Instrumentation
6.3.1 Air filter regulator
Air filter regulators shall be provided with an integral relief valve and micron filter. If regulator supply pressure is
lost, downstream air pressure shall be relieved.
6.3.2 Positioner
In general, all control valves shall be equipped with a positioner, preferably an intelligent type.

The positioner shall preferably be installed as direct acting.

Valve positioners shall be provided with gauges to indicate supply pressure, control air signal, and positioner
output pressure.

Electro-pneumatic valve positioners and pneumatic valve positioners with integral electro-pneumatic
transducers shall not be used in a vibrating service conditions. The I/P transducer shall then be mounted
separately from the valve and actuator assembly.
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 50 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore






The total maximum inaccuracy of the signal conversion in I/Ps, or electro-pneumatic valve positioners, due to
any limitation (e.g., repeatability, dead band, resolution, hysteresis, etc.), shall be less than 2.0%.

For intelligent positioners with 4-20 mA input and HART or Fieldbus communication and diagnostic possibilities,
a documented baseline footprint/valve signature from the FAT shall be delivered electronically in a readable file
format.
6.3.3 Limit switches
With the exception of North American facilities, limit switches shall be of inductive type complying with EN
60947-5-6 (NAMUR).

When limit switches are specified, a suitable junction box shall be mounted to the actuator or valve body for
termination of flying leads.
Flying leads from limit switch to junction box shall be physically protected by design. If no other options are
possible then AISI 316 SS tubing shall be used. When tubing is used, it shall be delivered with open ends for
drainage.

Limit switches shall be activated by the movement of the valve shaft or stem and shall switch at less than 5% of
the movement of the respective limit.

The limit switches shall normally be fitted inside a combined switch house/junction box, complete with terminals
or be installed on rigid AISI 316 SS steel fixing plates or brackets and shall be easily adjustable.

Limit switches should preferably have integral LED indication.
6.3.4 Position Indicator
Both control valve and on/off valves shall have a local position indicator.
Position indicators on thermally insulated valves shall have possibilities for extension.
6.3.5 Solenoid valves and lock up devices
When used for control valves, the solenoid valve shall be installed in the pneumatic signal line between valve
positioner and actuator.

Air lock-up devices shall be provided for all services requiring the control valve to remain in the position it had at
loss of air. The lock-up device shall be mounted between positioner output and actuator.

When lock-up devices are used on control valves with solenoid valves, the solenoid valve shall be installed
between lock-up valve and actuator.
6.4 Actuator requirements
6.4.1 Control valve actuator requirements
TR2212 states the technical requirements for control valve actuators.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 51 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





6.4.2 On/Off valve actuator requirements
6.4.2.1 General
All actuators shall be designed and dimensioned to operate the valves under the worst case process conditions.

Actuator performance design shall be carried out with consideration of the overall valve response requirement.

The specified closing/opening time shall be independent of the process condition.

The safety margin stated for the valve application shall apply at any position of the valve stroke, and shall
include the end position of the spring stroke for fail safe operations.

Actuators for safety valves shall generally be either electrical, pneumatic or hydraulic single acting with spring
return. Where valve/actuator service exceeds the spring return design, hydraulic double acting actuator with
accumulator shall be utilized.

The main selection criteria between these alternatives shall be LCC (Life Cycle Cost) including capital cost and
normal maintenance costs, plus local availability of the type of energy supply. Operational wear, weight and
dimensions shall also be considered, and shall be decisive for the selection where such factors are paramount.
Access and serviceability shall also be considered for final selection between equally good alternatives.

Electric actuators shall be preferred for on-off valves without fail safe action, (PCS designation), if such
actuation can be provided with the required speed of operation, and in accordance with safety restrictions.
The nominal supply voltage shall be used for calculating torque/thrust on electrical actuators.

Double acting pneumatic actuators shall be avoided.

Pneumatic/hydraulic actuators shall be fitted with flushing/bleeding facilities.
6.4.2.2 Additional electrical actuator requirements

Electrical actuators used on safety valves shall either be well proven industrial types electrical actuators with
spring return or electro-hydraulic double-acting.

UPS power supply should be standard for electrical actuated valves with safety action.

A three phase motor system should be selected to get a wider torque range and a more flexible and standard
power configuration.

Diagnostic information from the actuator should be available on a serial communication link either wired or
wireless. The condition monitoring system should be set up to handle the data from the actuator.

Operation of electrical actuated valves and the effects of transients and changes in power supplies during
special operations like start-up of large equipment shall be evaluated.
6.4.2.3 Actuator Control Circuits
Type of circuit design shall be decided by the Purchaser. See TR0038.

The control circuits shall be designed for easy maintenance at location.

All accessories required for control of the actuator movement, such as hydraulic inlet
filter, solenoid valves, manual valves, pressure gauges etc. shall be mounted on a control panel.
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 52 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore






Valve control panels for on/off valves should be of the compact type, avoiding internal tubing and fittings.

Control panels for the different circuit types shall be standardised in size, layout and mounting arrangement.
Valve control panels for on/off valves shall preferably be mounted on separate stands and not directly on
actuator.

Devices for control of the speed in both directions shall be installed on the control unit. It shall not be possible to
fully close the restrictors. The restrictors shall be easy to adjust during operation and shall have a fool proof
locking device.

Pressure gauges shall indicate the internal pressures in the control unit.

Constant internal leakage shall not be designed into a control system, especially solenoid- and
hydraulic/pneumatic valves.

Filter units to be used shall have a differential pressure indication.

The accumulators and their protection devices shall be assembled as a part of the control circuit panel, to form
a composite unit, but they may also be required as independent units, depending on the space available in the
plant. The vent outlets from bursting discs must be guided to a safe location.

Direct access for calibration and maintenance of all instruments shall be provided. It shall be possible to remove
individual components without having to remove inter-connected components.

Hydraulic oil inlet and outlet ports shall be clearly marked "Oil Inlet" and "Oil Outlet", both on control panel and
actuator.

Isolation valves for supply and return lines shall be installed as close to the instrument as possible.

Final layout arrangements proposed shall be confirmed and agreed by Purchaser upon fabrication.

Oil-mist lubrication systems shall not be used unless required for special applications (gear motors etc.).

A check valve shall be included on hydraulic circuit supply lines and pneumatic supply line.

For hydraulic operated valves with a check valve in the circuit supply line there will be a trapped-in liquid volume
in the actuator/control circuit. In case there will be a temperature rise in this liquid volume (due to external heat
input) the pressure may exceed allowable limits. To avoid this, a comined check/pressure relief valve should be
included. A small volume nitrogen accumulator (nitrogen cushion separated from the oil by a diaphragm) can be
used.

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 53 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





7 Additional information
7.1 Definitions and abbreviations
7.1.1 Definitions
Field instrumentation Components installed in the field for detection, monitoring and control

Field instruments Part of a system measuring physical conditions and transfer these into e.g.
electrical signals that can be interpreted and used in SAS for safety, control
and monitoring purposes, or local visualisation. E.g. instruments for pressure,
temperature, level, and flow, fire and gas detectors.

Final control elements Part of an instrumented system which implements the physical action
necessary to achieve a predefined state. E.g. control valves, on/off valves,
pumps and compressors (the latter two is part of mechanical competence area)

Commodity items Components needed for transmitting field signals to/from instrumented
systems, normally not tagged supplies. E.g. instrument tubing.

Gateway Provides the connection to the host network. A WirelessHART gateway and the
main host (PCDA) are interfaced using e.g. Modbus or Profibus, either over
serial communication ports or over Ethernet. Configuration and administrative
monitoring access is normally provided by http over Ethernet. The Gateway
integrates both the Network and Security Manager into the same hardware.

Winterisation Winterisation is the protection of instruments and instrument tubing against the
effects of low ambient temperature; including hydration formation,
condensation, viscosity changes and freezing.

Local Control Panel(LCP) Local control panel to perform and monitor local actions on equipment like
turbines or pumps

Instrument housing Typically housing of a transmitter or an indicator

Instrument enclosure A housing/cabinet to protect the field instrument from the ambient conditions.


7.1.2 Abbreviations
AC Alternating Current
APS Abandon Platform Shutdown
ATEX ATmosphere EXplosive
BSP BSPP Parallel & BSPT Tapered
CER Central Equipment Room
CCR Central Control Room
CPU Central Processing Unit
DBB Double Block and Bleed
DC Direct Current
DP Differential Pressure
ESD Emergency ShutDown
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 54 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





ESV Emergency Safety Valve
FAT Factory Acceptance Test
F&G Fire & Gas
FTC Field Termination Cabinet
GoM Gulf of Mexico
GRP Glassfibre Reinforced Plastic
HART Highway Addressable Remote Transducer
IP Ingress Protection
IR Infra Red
IS Intrinsically Safe
LCI Life Cycle Information
LCP Local Control Panel
LCR Local Control Room
LED Light Emitting Diode
LER Local Equipment Room
MCB Miniature Circuit Breaker
MDS Material Data Sheet
N/A Not Applicable
NAS National Aerospace Standard
NPT National Pipe Taper threads
PCS Process Control System
PSD Process ShutDown
RIO Remote Input Output
RTD Resistance Temperature Detectors
SAS Safety and Automation System
SIL Safety Integrity Level
SS Stainless Steel
7.2 Changes from previous version
1) General: Improved gramatics
2) Sect. 2.3.1 Clarified requirement for capacity of air supply
3) Sect. 2.3.2 Added requirement for flushing.
4) Sect. 3.1 Requirements for cable entry removed since this is covered by TR3023 and TR3024.
5) Sect. 3.2 Added requirements for alarm for reduced battery lifetime
6) Sect. 3.6.2 Added requirement for window in enclosures and process tubing connections for calibration
and maintenance. Moved from ch.4
7) Sect. 3.9 Added reference for ex-requirement to fibre optic cables
8) Sect. 3.11.3 Added note to table 5 to clarify hardness of materials when using 316SS fittings with 6Mo
tubing
9) Sect. 3.11.6 Requirements for junction boxes removed since this is covered by TR3023 and TR3024.
10) Sect. 3.13 Table 9; spare requirements for hydraulic distribution manifolds and electrical distribution
removed
11) Sect. 3.14, Reference to TR2000 removed.
12) Sect. 3.14 Added requirements for packing ring when using parallel pipe thread connections
13) Sect. 3.15 Uncertainty requirements updated
14) Sect. 4.1 Added requirement for valve control panel to be mounted on separate stand
15) Sect. 4.1 Changed requirement for height of display elements.
16) Sect. 4.3 reference standard modified
17) Sect.4.4 Clarifying requirement to tubing clamps added
18) Sect. 4.4.2 New section, added requirements for cleaning of tubing
19) Sect 4.7 Added requirement for position of thermowell
20) Sect. 4.8 Added figure as an example 0 100% level
21) Sect 4.8 Added requirement for 0% reference point
22) Sect 4.9 added requirement for orifice plates
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 55 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





23) Sect. 4.9 Requirements in table 12 changed from shall to should
24) Sect. 4.10 Added requirement for pig tail in early warning detectors
25) Sect. 4.10 Added requirement for line of sight detectors
26) Sect 4.11 New section covering tagging and marking of field instruments
27) Sect. 5.2.1 Clamp-on replaced by non-intrusive
28) Sect 5.2.2 New version of standard ANSI/ASME PTC 19.3 added (wake frequency calculations)
29) Sect. 5.3.3 Added reference and additional requirement for restriction orifices.
30) Sect 5.3.4 Added reference
31) Sect. 5.5.2 Added requirement to clarify use of vibration level switch
32) Sect. 5.5.3 Removed requirement for forged steel and toughened steel in gauge glasses
33) Sect. 5.8.1.1 Added requirements to sand detectors and erosion probes
34) Sect. 6.1 Removed requirement for state monitoring and leak detection. New reference to TR3138.
35) Appendix A Installation typicals added to document
7.3 References
Company requirements
Surface preparation and protective coating (TR0042)
LCI Requirements (TR2381)
Valve Actuators (TR0038)
Metering systems for fiscal, allocation or custody transfer applications (TR0814)
Performance Standards for Safety Systems and Barriers Offshore (TR1055)
HVAC Design and fabrication requirements (TR1562)
Piping and Valve spec. (L-SP-200) (TR2000)
Control & Choke Valves (TR2212)
Safety design for Onshore Plants (TR2237)
Valve Locking, Interlocking ans other Position Securing Systems (TR2315)
Piping, Fabrication, Installation and Testing Specification (TR2323)
Piping Detail Standard (TR2325)
Process Safety (TR3001)
Electrical system design, offshore units (TR3021)
Electrical system design, onshore plants (TR3022)
Electrical installation, offshore units (TR3023)
Electrical installation, onshore plants (TR3024)
Automation, Technical Requirements and Standards (TR3030)
Automation technology (TR3031)
Safety and Automation System (TR3034)
Automation technology for equipment packages (TR3131)
Testing and inspection of safety instrumented systems including safety related valves (TR3138)
Vibration Protection and Diagnostic System (TR3132)
Welding and Inspection of piping (Norsok M-601)
Qualification of Manufacturers of special materials (Norsok M-650)

Company guidelines

Field instruments (GL3032 - hold)


International standards

AGA Report no. 03, Orifice Metering of Natural Gas and Other Related Hydrocarbon Fluids
AGA Report no. 07, Measurement of Natural Gas by Turbine Meters
AGA Report no. 09, Measurement of Gas by Multipath Ultrasonic Meters
AGA Report no. 11, Measurement of Natural Gas by Coriolis Meter
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 56 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





ANSI/ISA 7.0.01, Quality Standard for Instrument Air
ANSI/ASME PTC 19.3 TW-2010
API/MPMS Ch 5.1, General Consideration for Measurement by Meter is missing from the
references.
API MPMS Ch 5.2, Measurement of Liquid Hydrocarbons by Displacement Meters
API MPMS Ch 5.3, Measurement of Liquid Hydrocarbons by Turbine Meters
API MPMS Ch 5.6, Measurement of Liquid Hydrocarbons by Coriolis Meters
API/MPMS Ch 5.8, Measurement of Liquid Hydrocarbons by Ultrasonic Flow Meters Using Transit
Time Technology
API MPMS Ch 14.1, Collecting and Handling of Natural Gas Samples for Custody Transfer
API MPMS Ch 8.2, Standard Practice for Automatic Sampling of Liquid Petroleum and Petroleum
Products
API RP STD 555, Process Analyzers
ASME B31.3 Process Piping
ASME MFC-3M Measurement of Fluid Flow in Pipes Using Orifice, Nozzle, and Venturi
ASTM A269 Specification for Seamless and Welded Austenitic Stainless Steel Tubing for General
Service
ASTM E230 Standard Specification and Tempertaure-Electromotive Force (EMF) Tables for
Standardized Thermocouples
ASTM E1137 Standard Specification for Industrial Platinum Reistance Thermometers
EN 60947-5-6, Low-voltage switchgear and controlgear part 5-6: Control circuit devices and switching
elements DC interface for proximity sensors and switching amplifiers (NAMUR)
IEC 60079, Electrical apparatus for explosive gas atmospheres
IEC 60529, Degrees of protection provided by enclosures (IP code)
EN 60751, Industrial Platinum Resistance Thermometer sensors
IEC 61000, Electromagnetic compatibility (EMC)
IEC 61158, Industrial communication networks - Fieldbus specifications
IEC 61508, Functional safety of electrical/electronic/programmable electronic safety-related
systems
IEC 61511, Functional safety - Safety instrumented systems for the process industry sector
EN 60534, Industrial process control valves
IEC 60584, Thermocouples
IEEE 802.11a 54 Mbit/s, 5 GHz standard
IEEE 802.11b Enhancements to 802.11 to support 5.5 and 11 Mbit/s
IEEE 802.11g 54 Mbit/s, 2.4 GHz standard (backwards compatible with b)
IEEE 802.11n Higher throughput improvements using MIMO (multiple input, multiple output
antennas)
ISA MC96.1 Temperature Measurement Thermocouples
ISA S84.01, Application of Safety Instrumented Systems for the Process Industry
ISO 228-1, Pipe threads where pressure tight joints are not made on the threads
ISO 1000, SI units and recommendations for the use of their multiples and certain other units
ISO 3171, Petroleum liquids - Automatic pipeline sampling
ISO 4406, Hydraulic fluid power -- Fluids -- Method for coding the level of contamination by solid
particles
ISO 5167, Measurement of fluid flow by means of pressure differential devices inserted in
cuircular cross-section conduits running full
ISO 9951, Measurement of gas flow in closed conduits - Turbine meters
ISO 10715, Natural Gas - Sampling Guidelines
ISO 10790
ISO15156/ NACE MR0175, Materials for use in H
2
S-containing environments in oil and gas
production
NAS 1638 Cleanliness Requirements fo Parts Used in Hydraulic Systems
NEMA Ratings and IP Equivalency Chart
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 57 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





NEMA 250 Ratings and IP Equivalency ChartEnclosures for Electrical Equipment (1000 Volts
Maximum)
WirelessHART
ISA100.11a
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 58 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





App A Installation typicals
Typical installation drawings below are for design guidance only. Principles shall however apply. Detailed hook-
up drawings shall be issued for each project. Requirements for installation drawings are stated in TR2381.

1 Objecti ve, target group and provision ............................................................................................................... 4
1.1 Objective.................................................................................................................................................... 4
1.2 Target group .............................................................................................................................................. 5
1.3 Provision .................................................................................................................................................... 5
2 General requirements .......................................................................................................................................... 6
2.1 Standardisation.......................................................................................................................................... 6
2.2 Engineering units ....................................................................................................................................... 6
2.3 Utilities........................................................................................................................................................ 6
3 Design requirements............................................................................................................................................ 9
3.1 General ...................................................................................................................................................... 9
3.2 Wireless field devices .............................................................................................................................. 10
3.3 Environment ............................................................................................................................................. 10
3.4 Heat tracing.............................................................................................................................................. 10
3.5 Purging Systems...................................................................................................................................... 12
3.6 Weather protection .................................................................................................................................. 12
3.7 Local Control Panel (LCP)....................................................................................................................... 13
3.8 Electromagnetic compability.................................................................................................................... 14
3.9 Ex protection............................................................................................................................................ 14
3.10 Degrees of protection .............................................................................................................................. 15
3.11 Material .................................................................................................................................................... 15
3.12 Signal types ............................................................................................................................................. 18
3.13 Provision for future modifications ............................................................................................................ 19
3.14 Instrument tubing and fittings .................................................................................................................. 19
3.15 Measurement uncertainty........................................................................................................................ 21
4 Installation design requirements ...................................................................................................................... 23
4.1 Equipment location .................................................................................................................................. 23
4.2 Field architecture and segregation.......................................................................................................... 24
4.3 Installation of wireless instrumentation.................................................................................................... 24
4.4 Tubing installation.................................................................................................................................... 24
4.5 Thermal Insulation ................................................................................................................................... 26
4.6 Winterisation ............................................................................................................................................ 26
4.7 Temperature instruments ........................................................................................................................ 27
4.8 Level instruments..................................................................................................................................... 27
4.9 Flow instruments...................................................................................................................................... 28
4.10 Fire & Gas equipment.............................................................................................................................. 29
5 Field instruments................................................................................................................................................ 32
5.1 General .................................................................................................................................................... 32
5.2 Temperature measurement ..................................................................................................................... 33
5.3 Flow measurement .................................................................................................................................. 34
5.4 Pressure measurement ........................................................................................................................... 40
5.5 Level measurement ................................................................................................................................. 40
5.6 Fire and gas detection ............................................................................................................................. 43
5.7 Manual callpoint ....................................................................................................................................... 44
5.8 Online analyser system........................................................................................................................... 44
6 Final control elements ....................................................................................................................................... 49
6.1 On/off valves............................................................................................................................................ 49
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 59 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





6.2 Control valves .......................................................................................................................................... 49
6.3 Instrumentation ........................................................................................................................................ 49
6.4 Actuator requirements ............................................................................................................................. 50
7 Additional information ....................................................................................................................................... 53
7.1 Definitions and abbreviations .................................................................................................................. 53
7.2 Changes from previous version............................................................................................................... 54
7.3 References............................................................................................................................................... 55
App A Installation typicals ............................................................................................................................................ 58
A.1 Capillary and diaphragm seal arrangement ............................................................................................ 61
A.2 Differential pressure transmitter with capillary and diaphragm seal ....................................................... 62
A.3 DP level transmitter, capillary type.......................................................................................................... 63
A.4 Pressure transmitter with capillary and diaphragm seal ......................................................................... 64
A.5 Pressure transmitter gas service............................................................................................................. 65
A.6 Pressure transmitter gas service............................................................................................................. 66
A.7 Pressure transmitter gas service heat traced.......................................................................................... 67
A.8 Pressure transmitter liquid/gas cryogenic ............................................................................................... 68
A.9 Pressure transmitter liquid service .......................................................................................................... 69
A.10 Differential pressure transmitter liquid service..................................................................................... 70
A.11 Differential pressure transmitter liquid service..................................................................................... 71
A.12 Differential pressure transmitter liquid service heat traced.................................................................. 72
A.13 Differential pressure transmitter steam service.................................................................................... 73
A.14 Differential pressure transmitter gas service........................................................................................ 74
A.15 Differential pressure transmitter gas service........................................................................................ 75
A.16 DP pressure transmitter capillary type .................................................................................................... 76
A.17 Pressure gauge........................................................................................................................................ 77
A.18 Pressure gauge- gas service................................................................................................................... 78
A.19 Pressure gauge Gas heat traced ......................................................................................................... 79
A.20 Remote pressure gauge liquid/gas cryogenic......................................................................................... 80
A.21 Pressure gauge steam service............................................................................................................. 81
A.22 Air distribution of manifold w/consumer................................................................................................... 82
A.23 Hydraulic distribution w/consumer........................................................................................................... 83
A.24 Hydraulic distribution w/consumer........................................................................................................... 85
A.25 Instrument support housed instrument................................................................................................. 87
A.26 Instrument support platform mounted .................................................................................................. 88
A.27 Instrument support system local analyser system............................................................................... 89
A.28 Instrument support gas detector........................................................................................................... 90
A.29 Instrument support gas detector........................................................................................................... 91
A.30 Instrument support gas detector........................................................................................................... 92
A.31 Instrument support flame detector........................................................................................................ 93
A.32 Instrument support flame detector........................................................................................................ 94
A.33 Instrument stand...................................................................................................................................... 95
A.34 Wall mounted instrument stand with plate .............................................................................................. 97
A.35 Wall mounted instrument stand............................................................................................................... 99
A.36 Instrument enclosure ............................................................................................................................. 101










Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 60 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore






Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 61 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.1 Capillary and diaphragm seal arrangement



Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 62 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.2 Differential pressure transmitter with capillary and diaphragm seal

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 63 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.3 DP level transmitter, capillary type

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 64 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.4 Pressure transmitter with capillary and diaphragm seal

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 65 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.5 Pressure transmitter gas service

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 66 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.6 Pressure transmitter gas service

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 67 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.7 Pressure transmitter gas service heat traced

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 68 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.8 Pressure transmitter liquid/gas cryogenic

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 69 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.9 Pressure transmitter liquid service

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 70 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.10 Differential pressure transmitter liquid service

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 71 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.11 Differential pressure transmitter liquid service

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 72 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.12 Differential pressure transmitter liquid service heat traced

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 73 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.13 Differential pressure transmitter steam service

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 74 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.14 Differential pressure transmitter gas service

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 75 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.15 Differential pressure transmitter gas service

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 76 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.16 DP pressure transmitter capillary type

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 77 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.17 Pressure gauge

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 78 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.18 Pressure gauge- gas service

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 79 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.19 Pressure gauge Gas heat traced

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 80 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.20 Remote pressure gauge liquid/gas cryogenic


Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 81 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.21 Pressure gauge steam service

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 82 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.22 Air distribution of manifold w/consumer

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 83 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.23 Hydraulic distribution w/consumer

HY DRAULI C SUPPL Y
CONT ROL CA BI NET
H Y DRA ULIC O IL R ETU RN LINE
H YDR AU LIC O IL SU P P LY LIN E ( 2 00 B ARG)
B
Y

P
I
P
I
N
G

B
Y

I
N
S
T
R
U
M
E
N
T

B
Y

V
A
L
V
E

S
U
P
P
L
I
E
R

J B000555
J B000564
J B000558
J B000553
J B000044
J B000557
J B000552
J B000377
J B000557
B
Y

I
N
S
T
.

B
Y

V
A
L
V
E

S
U
P
P
L
I
E
R

J B000563
J B000561
J B000561
J B000561
J B000562
J B000562
J B000562
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 84 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore








Item Description Qty
JB000552 TUBE UNION, 20mm OD, . G20S71X 1.0
JB000562 25mm FUNCTION NUT FM25S71 5.0
JB000561 20mm FUNCTION NUT FM20S71 5.0
JB000553 TUBE UNION, 25mm OD, G25S71X 1.0
JB000555 MALE CONN. 25mm OD X 3/4" BSPP , GE25SR3/4EDOMD71 1.0
JB000377 INSTRUMENT TUBE, IT-20 OD X 2.0MM 316SS. 12.0M
JB000557 MALE CONN. 20mm OD X 3/4" BSP , GE20SREDOMD71 3.0
JB000563 BALL VALVE 3/4" BSPP FEM. PISTER RKH4425 G 2.0
JB000564 BALL VALVE 1 BSPP , 316SS PISTER RKH4425 1 G 1.0
JB000044 INSTRUMENT TUBE, IT-25.OD X 2.0 MM 316SS. 12.0M
JB000558 MALE CONN. 25mm OD X 1" BSPP GE25SREDOMD71
2.0




















Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 85 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.24 Hydraulic distribution w/consumer

H Y D R A U L I C SUP P L Y
C O NT R OL C A BI NET
H Y DR A U L IC O I L R ETU R N L I N E
H Y DR A U L IC O I L S U P P LY L I N E ( 2 0 0 B AR G )
B
Y

P
I
P
I
N
G

B
Y

I
N
S
T
R
U
M
E
N
T

B
Y

V
A
L
V
E

S
U
P
P
L
I
E
R

J B 000557
J B 000563
J B 000557
J B 000552
J B 000337 J B 000554
J B 000032
J B 000559
B
Y

I
N
S
T
.

J B 000565
O P E N C L O SE
J B 000559
J B 000560
J B 000568
J B 000560
J B 000560
J B 000561
J B 000561
J B 000561
S
U
P
P
L
I
E
R

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 86 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore








Item Description Qty
JB000032 INSTRUMENT TUBE, IT-10.0 X 2.0MM 316SS. 10.0mm OD X 2.0mm WT. 12.0M
JB000561 20mm FUNCTION NUT FM20S71 5.0
JB000560 10mm FUNCTION NUT FM10S71 5.0
JB000568 THREAD REDUCER/EXPANDER M x F RI3/4EDX1/271 1.0
JB000554 TUBE UNION, 10mm OD, G10S71X 1.0
JB000552 TUBE UNION, 20mm OD, G20S71X 1.0
JB000559 MALE CONN. 10mm OD X 1/2" BSPP GE20SREDOMD71 3.0
JB000565 BALL VALVE BSPP 7723F8Y/BSPP 1.0
JB000377 INSTRUMENT TUBE, IT-20mm OD X 2.0mm WT 316SS. 12.0M
JB000557 MALE CONN. 20mm OD X 3/4" BSPP GE20SRED71X 3.0
JB000563 BALL VALVE 3/4" BSPP RKH4425 G 1.0

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 87 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.25 Instrument support housed instrument

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 88 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.26 Instrument support platform mounted

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 89 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.27 Instrument support system local analyser system

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 90 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.28 Instrument support gas detector

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 91 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.29 Instrument support gas detector

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 92 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.30 Instrument support gas detector

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 93 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.31 Instrument support flame detector

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 94 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.32 Instrument support flame detector

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 95 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.33 Instrument stand


Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 96 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore







Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 97 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.34 Wall mounted instrument stand with plate

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 98 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore









Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 99 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.35 Wall mounted instrument stand


General Notes:
Alternative support solution may be used
Length to be adjusted and protected against vibration at site
All material to be stainless steel AISI 316L
Notes
2 pipe, wall thickness 2 mm
Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 100 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





6 mm PLATE
250 x 250 x 10 mm PLATE


Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 101 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore





A.36 Instrument enclosure

Governing document: Field instrumentation Classification: Internal


Project development (PD), Technical and professional requirement, TR3032, Final Ver. 3, valid from
2011-08-15
Page 102 of 102
Validity area: Corporate techn. and prof. req./All locations/All value chains/On- and offshore








ITEM DESCRIPTION
1 GRP ENCLOSURE, MODEL 315, FIRE RETARDANT TO BS476, PART 7, CLASS 2. ANTI-STATIC TO EN50014. (COLOUR BLACK)
2 HINGE - ST. STEEL - 2 OFF
3 PROPSTAY - ST. STEEL
4 GASKET - NEOPRENE
5 TOGGLE FASTENER - ST. STEEL - 2 OFF
6 MOUNTING PLATE & CLAMP, TO SUIT 2" NB PIPE STAND - ST. STEEL
7 TAG LABEL - TRAFOLYTE W/B/W
8 VIEWING WINDOW - TOUGHENED GLASS
9 CABLE GLAND - M25 - 3 OFF
10 MANIFOLD MTG BRACKET, TO SUIT BASE INSTRUMENT MANIFOLD (ITEM 12). - ST. STEEL
11 INSTRUMENT
12 INSTRUMENT MANIFOLD - 316 ST. STEEL - 1 OFF
13 COMPRESSION FITTINGS - 316 ST. STEEL
14 6mm OD x 1.0mm WT TUBE - 316 ST. STEEL
15 TRACEPAK END SEAL - TPKES-4.
16 INST. HEATER. ST. STEEL SPRING LOADED BRACKET
17 JUNCTION BOX - 2 x M25 & 1 x M20 CABLE GLAND AND HEAT TRACE CABLE TERMINATION KIT
18 DRAIN PLUG
19 J.BOX TAG LABEL BRACKET - ST.STEEL

Das könnte Ihnen auch gefallen